Facilities Modernization Program Funded by Measure B Project Report November 21, 2011
7

Facilities Modernization Program Funded by Measure B Project Report

Feb 22, 2016

Download

Documents

♥Moriah♥

Facilities Modernization Program Funded by Measure B Project Report. November 21, 2011. PROJECT PROGRESS REPORT Child Development Center. LAS POSITAS COLLEGE November 21, 2011. Project Team: Architect : Beverly Prior Architects Construction Manager : Parsons Brinckerhoff - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization ProgramFunded by Measure B

Project Report

November 21, 2011

Page 2: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTChild Development Center

Project Team: Architect: Beverly Prior ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction Associates

Project Update:• Project is complete.• Project is in Warranty Period.

Occupancy Spring 2011

LAS POSITAS COLLEGENovember 21, 2011

Page 3: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)

Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction

Project Update:• Project is complete.• We are in Warranty Period.• DSA Closeout is in progress.

Occupancy: 04/2011

LAS POSITAS COLLEGENovember 21, 2011

Page 4: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTScience Building, Phase II

Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc

Project Update:• Interior/Exterior framing on first and second floors are being completed.• Exterior insulation is being installed. • Plumbing installation is continuing on first and second floors.• Electrical and Data installation is continuing at first and second floors.• Roofing on High Roof is complete, Low roof is 85% complete.• Storefront installation will start week of Nov 28, 2011.

Occupancy: 09/2012

LAS POSITAS COLLEGENovember 21, 2011

Page 5: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTStudent Services & Central Administration

Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction

Project Update:• GFRC installation erection complete, plumbing and lining remain.• Mechanical, Electrical, Plumbing rough in continues.• Interior wall partitions underway, exterior framing 50% complete.

Occupancy: Spring 2013

LAS POSITAS COLLEGENovember 21, 2011

Page 6: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTCampus Boulevard Phase I-III

Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: TBD

Project Update:• 100% Design review completed, final design schedule for December 2011.

Design Re-Start: 04/2011DSA Permit Approval: 02/2012Construction Start: 03/2012Occupancy: TBD

LAS POSITAS COLLEGENovember 21, 2011

Page 7: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTPhotovoltaic System Phase II

Project Team: Design Build Contractor: Cupertino Electric Inc.Construction Manager: Parsons Brinckerhoff

Project Update:• Fencing Completed.• Racking System completed and ready for Array installation.• PV Arrays installation will start week of November 28, 2011.• Inverters and Transformer install Mid December 2011.

Occupancy: January 2012

LAS POSITAS COLLEGENovember 21, 2011