    Responsibilities of the OwnersRepresentative in a Construction

    Project

    Jonathan Franklin

    University of Washington School of LawJim Hambleton

    Texas Wesleyan University School of Law

  • 8/11/2019 F2-Owner's Rep Role in Construction

    2/28

    The Players

    Owner & owners representative

    Architect

    Interior design & furniture consultant

    Acoustical & lighting consultants

    Contractor

    Construction manager

    Project supervisor

  • 8/11/2019 F2-Owner's Rep Role in Construction

    3/28

    Owners Representative

    3.2

    The Owner shall designate arepresentative who shall have expressauthority to bind the Owner with respect

    to all matters requiring the Ownersapproval or authorization.

  • 8/11/2019 F2-Owner's Rep Role in Construction

    4/28

    The Design Pieces

    The program

    ABA Standards 701704

    Defining your program

    Pre-design

    Schematic design

    Design development

    Construction documents

  • 8/11/2019 F2-Owner's Rep Role in Construction

    5/28

    ABA Standards

    701: General requirements

    702: Law Library

    703: Research & study space

    704: Technological Capacities

  • 8/11/2019 F2-Owner's Rep Role in Construction

    6/28

    The Design Pieces

    The program

    ABA Standards 701704

    Defining your program

    Pre-design

    Schematic design

    Design development

    Construction documents

  • 8/11/2019 F2-Owner's Rep Role in Construction

    7/28

    The Construction Pieces

    RFI: request for information

    PCO: proposed change order

    PR: proposal request

  • 8/11/2019 F2-Owner's Rep Role in Construction

    8/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    9/28

    The Construction Pieces

    RFI: request for information

    PCO: proposed change order

    PR: proposal request

    Submittal

  • 8/11/2019 F2-Owner's Rep Role in Construction

    10/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    11/28

    The Construction Pieces

    RFI: request for information

    PCO: proposed change order

    PR: proposal request

    Submittal

    Punch list

  • 8/11/2019 F2-Owner's Rep Role in Construction

    12/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    13/28

    The Process: ConstructionWeekly OAC Meeting

    Attendees: players plus subcontractors

    Agenda:

    Construction schedule

    PCO log

    Old business

    New business

    RFI log

    Submittal log

  • 8/11/2019 F2-Owner's Rep Role in Construction

    14/28

    The Process: ConstructionWeekly OAC Meeting

    Attendees: players plus subcontractors

  • 8/11/2019 F2-Owner's Rep Role in Construction

    15/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    16/28

    The Process: ConstructionWeekly OAC Meeting

    Attendees: players plus subcontractors

    Agenda:

    Construction schedule

  • 8/11/2019 F2-Owner's Rep Role in Construction

    17/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    18/28

    The Process: ConstructionWeekly OAC Meeting

    Attendees: players plus subcontractors

    Agenda:

    Construction schedule

    PCO log

  • 8/11/2019 F2-Owner's Rep Role in Construction

    19/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    20/28

    The Process: ConstructionWeekly OAC Meeting

    Attendees: players plus subcontractors

    Agenda:

    Construction schedulePCO log

    Old business

    New business

    RFI log

    Submittal log

  • 8/11/2019 F2-Owner's Rep Role in Construction

    21/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    22/28

    The Process: ConstructionResponsibilities of the Owners Rep

    Be thoroughly familiar with the blueprints

    Construction plans

    Elec/tele/data plan

    Finish plan

    Reflected ceiling plan

    Millwork detail

    Furniture plan

    Door & finish schedules

  • 8/11/2019 F2-Owner's Rep Role in Construction

    23/28

    The Process: ConstructionResponsibilities of the Owners Rep

    Construction oversight consistent with theAIA contract

    Coordinating the owners vendors with thecontractors vendors

    h i

  • 8/11/2019 F2-Owner's Rep Role in Construction

    24/28

    The Process: ConstructionResponsibilities of the Owners Rep

    Construction oversight consistent with theAIA contract

    Coordinating the owners vendors with thecontractors vendors

    Walk the construction site on a regular basis

  • 8/11/2019 F2-Owner's Rep Role in Construction

    25/28

    Th P C i

  • 8/11/2019 F2-Owner's Rep Role in Construction

    26/28

    The Process: ConstructionResponsibilities of the Owners Rep

    Construction oversight consistent with theAIA contract

    Coordinating the owners vendors with thecontractors vendors

    Walk the construction site on a regular basis

    Punch list

  • 8/11/2019 F2-Owner's Rep Role in Construction

    27/28

  • 8/11/2019 F2-Owner's Rep Role in Construction

    28/28

    Summary

    Communicate with your constituencies

    Defer to the professionals

    Dont settle for something that is not right

    Make decisions and be ready to explainthose decisions to your supervisor

    Keep a sense of perspective and a senseof humor