Top Banner

of 18

Exxonmobil Presentation Agdc May 7 2014

Jun 02, 2018

Download

Documents

aby_abraham5005
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    1/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Alaska LNG Project

    Project Overview with AGDC

    Anchorage, Alaska

    May 7, 2014

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    2/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Alaska LNG Project - Overview

    Alaska LNG Plant

    Conceptual Layout

    Results ofURS ArcGISLocation SuitabilityScreening Study

    - 1 -

    Lead LNG Plant Site Selection- Extensive Analysis of SouthCentral coast

    - 20+ options analyzed; 4-5 sites feasible

    - Geotechnical, construction, operation issues

    Lead LNG Plant SiteNikiski Industrial Area

    BP, ConocoPhillips, ExxonMobil, TransCanada and the State ofAlaska are working together to progress the Alaska LNG project:- 300+ people involved in project design work-

    Multiple third party contractors engaged many Alaskan- Leveraging Denali, APP, related material ($700M past work)- Preliminary capital estimate - $45-65 Billion (2012 dollars)

    Key project design accomplishments to date:- Integrated Basis of Design heat/material balance complete- Confirmed ability to integrate into existing operations- Completed project design, announced concept Feb13- Finalized lead LNG plant site decision, announced Oct13

    Completed 2013 Summer Field Season:- Cultural resource assessment (>6,500 acres)- Hydrology / Lakes / Fisheries studied (37 / 17 / 20)- Traditional knowledge, subsistence, ethnographic surveys- 150 people involved

    Key project issues to address:- Mega-project challenges (labor, resources, equipment, etc.)-

    Uncertainty related to permit timing / scope- Commercial/fiscal issues with all parties, including State

    The ARC of Success- Al ignment four primary resource owners, working together- Risk reduction identify / mitigate risk and uncertainty- Cost low cost wins, defines competiveness/viability

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    3/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress2

    Alaska LNG Concept Summary - Upstream

    PTU (62 miles east of PBU/GTP area)

    Initial Production System (IPS) project in progress - 2016 SU

    Preliminary AK LNG design basis for PTU: Leverage IPS facilities, add fourteen new wells

    Add new gas facilities to existing central pad / facilities

    New 30 gas line from PTU to GTP in Prudhoe Bay

    Peak workforce 500-1,500 people

    PBU Tie-in (adjacent to proposed GTP location)

    Installation / tie-in managed by Prudhoe Bay Operator

    Tie into existing CGF, deliver gas to new Gas Treatment Plant

    Gas project / deliveries tied to future PBU operations

    Preliminary plan is to inject CO2 using existing injection systems

    as appropriate

    PTU Field Layout

    Process

    Utilities

    PowerGeneration

    Point Thomson

    Central Pad

    Compression

    PBU Central Gas Facilit y Tie-in

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    4/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Alaska LNG

    Pipeline Elevation Design Example

    Potential

    Pipeline Routes

    Alaska LNG Concept Summary - Pipeline

    Gas Pipeline and Compression Stations

    800+ mile 42 x80 pipeline

    3-3.5 billion cubic feet gas per day

    Eight compressor stations (30kHP each) Pipeline contents will be treated gas, impurities removed at NS GTP

    Designed to manage continuous and discontinuous permafrost regions

    Expansion potential with additional compression if appropriate

    Refining route based on summer field information, continued design work

    Five off-take points for Alaska gas delivery

    Peak workforce 3,500 - 5,000 people

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    5/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress4

    Alaska LNG - Concept Summary GTP / LNG Plants

    NS Gas Treatment Plant

    Defined PBU integration for gas inlet, discharge

    Designed to remove gas impurities

    Four amine trains with compression, dehydration and chilling

    Prime power generation (5 units, 54kHP)

    All required utilities, infrastructure and camps

    Facility will be modularized, sealifted to location

    Peak workforce 500-2,000 people

    LNG Plant, Storage and Marine Facility

    Three 5.8 million tons per annum (MTA) LNG trains (17-18MTA)

    - Plant receives 2.2 - 2.5 billion cubic feet per day to liquefy

    - LNG production varies with ambient temp (4.9 - 6.3 MTA)

    - Small volume of stabilized condensate (~1,000 bbl/day)

    Integrated utility system with all utilities on site

    Three 160,000 cubic meter LNG storage tanks

    Conventional jetty with two berths (15-20 LNG Carriers)

    Peak workforce 3,500 5,000 people for LNG plant

    Peak workforce 1,000 1,500 people for marine facility

    Evaluating modularization to manage risks

    NS Gas Treatment Plant

    LNG Plant and Storage

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    6/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress- 5 -- 5 -

    Objectives:

    Identify 3-5 sites viable for series of LNG trains and associatedMarine Terminal in close proximity

    Site must be suitable as termination point for feed gas pipeline and for

    LNG carrier load-out

    Deliverable:

    One primary lead LNG plant site with suitable alternate sites

    Process:

    Acceptability determined by extensive review process from companyand contract experts evaluating 50+ distinctive criteria (12mo process)

    Parallel/independent ArcGIS analysis

    Quantitative Risk Analysis (QRA) used to integrate analysis

    A parallel path Site Selection process that uses independent approaches and provides checks & balances.

    Alaska LNG - Site Selection Process

    InitialList of

    21 Sites

    8 RecommendedSites Based on

    Analysis of GIS

    GISSuitabilityAreas

    1stSME FlawScreening(13 Sites)

    2nd SME FlawScreening(8 Sites)

    Reconciled List of 8Common Sites

    Location Shift ToMatch Terrain

    Lead SiteSelected

    Expert Input toSupport

    Evaluation

    SME Common Listof 8 Sites

    ConceptualEngineering for5 Validated

    Rep. Locations

    Continued ExpertInput to Support

    Evaluation

    VMT Co-locationConsidered

    QRA forRepresentative

    Sites

    SiteAcceptabi li ty

    Marine

    LNG Siting

    ERL

    Geotechnical

    StakeholderImpacts

    PipelineApproach

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    7/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress6

    Alaska LNG Lead Site Design Work

    NRC Ice Modeling of Cook Inlet Ice

    LNG Plant Site Selection

    Announced Nikiski area, on the Kenai Peninsula as lead site in Oct13

    Extensive data acquisition program in 2012 to evaluate multiple sites

    Focus on geotechnical, marine, civil, and pipeline approach issues- Particular focus on seismicity, faults/folds, volcanic, tsunami risks

    - Evaluate marine bathymetry, metocean, navigation, infrastructure issues

    Assess constructability and long term operations

    Preliminary emissions modeling complete

    Nikiski area development requires less civil /construction work than other sites

    Marine Viability Assessment

    Design focused on conventional LNG carriers (~160,000 mt3)

    Engaged local Alaskan pilots, evaluated marine operations

    Completed maneuverability study to demonstrate ability to safely moor, load

    Evaluating tug effectiveness, required support for terminal

    Extensive modeling with international agencies to confirm intrinsically safe design

    Completed site visits to existing operations with similar marine environments Gathering additional metocean data to validate design

    http://www.google.com/url?sa=i&rct=j&q=lng+ship+cook+inlet+ice&source=images&cd=&cad=rja&docid=pq33lFvM2FPTpM&tbnid=TQr39I2kfTZLbM:&ved=0CAUQjRw&url=http://www.arcticgas.gov/lng-cold-facts-about-hot-commodity&ei=tcyCUYGCBJD88QTwq4CwCQ&bvm=bv.45960087,d.dmQ&psig=AFQjCNHAIGY2iYxiu91Qq1NRj8OyBOXXLw&ust=1367612971357361
  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    8/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Recent Progress - Prudhoe Bay

    7

    Prudhoe Bay

    Continued data capture/analysis of PBU gas

    composition

    Evaluated field dehydration performance

    Continuing depletion planning

    Developing integrated injection system

    Evaluating integrated power grid

    Preliminary CO2Re-Injection Design

    Prudhoe Bay Unit Central Gas Facility

    Preliminary CO2Re-InjectionDesign

    69KV PBU Power Grid

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    9/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Recent Progress - Point Thomson

    8

    Point Thomson

    Comparing plot plan options for

    safety and operability

    Evaluated process design

    requirements

    Developing design basis for future

    engineering work

    Point Thomson Unit Central Pad

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    10/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Recent Progress Gas Treatment Plant

    9

    Gas Treatment Plant

    Confirmed viability of 3 train design, aligns

    gas treatment plan with LNG plant Finalized CO2design / handling basis

    Working to modularize plant design

    Evaluating sealift plans / orderNS Gas Treatment Plant Sealift Option Exampl e

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    11/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Recent Progress Pipeline

    Pipeline

    Refined route from PBU to Livengood, finalizing

    route from Livengood to Cook Inlet

    Working special design areas

    - Atigun Pass - Denali National Park Area

    - Yukon River - Cook Inlet

    - Progressing fundamental technical work on

    geohazard analysis, waterway crossings,

    hydraulics and design

    Denali Park Area

    10

    Pipeline Hydraulic Model Example Compressor Station Locations

    Proposed Pipeline Route

    DENALI NATIONAL PARK COOK INLET

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    12/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Recent Progress LNG Plant

    11

    LNG Plant and Marine

    Lead site selected

    Completed plans for metocean data gathering

    Ambient air monitoring stations / plan finalized

    Progressing work on LNG capacity and

    technology

    Results ofURS ArcGISLocation SuitabilityScreening Study

    Lead LNG Plant Site Selection- Extensive Analysis of SouthCentral coast

    - 20+ options analyzed; 4-5 sites feasible- Geotechnical, construction, operation issues

    Lead LNG Plant Site

    Nikiski Industrial Area

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    13/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Recent Progress Environmental, Regulatory and Land

    Cultural Resource

    Survey Areas

    Environmental, Regulatory and Land

    Safe summer field season 2013

    No incidents for >40,000 man-hours, 90,000 miles

    No reportable spills or public complaints

    Peak workforce of over 130 contractor staff

    completed survey work from PBU to Livengood

    Over 6,500 acres surveyed for cultural resources

    Over 75 hydrology, lakes and fisheries surveyed

    Traditional knowledge and ethnographic surveys

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    14/18

    Alaska LNG ProjectConcept Information

    Work Product In Progress

    Forward Plan - Environmental, Regulatory and Land

    Plans for a safe 2014 field season

    Civil and scientific surveys from Livengood to Nikiski

    Subsistence and health impact surveys

    Marine current and ice profiling

    Geotechnical and geophysical surveys

    Collaboration with state and federal agencies for

    permitting and approvals

    Local community engagement for field study scopes

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    15/18

    Att h t 1

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    16/18

    Southcentral Alaska LNG Integrated Team

    Producing FieldsLead: BP

    PipelinesLead: Alaska Pipeline Project

    LNG PlantLead: ConocoPhillips

    Integration TeamLead: ExxonMobil

    Commercial TeamLead: BP

    Concept TeamLead: ExxonMobil

    Management Committee

    Technical

    Committee

    Multimillion Dollar, Four-Company Effort 125+ Employees, 100+ Contractors

    Joint work commenced March 31, 2012 after completion of the Pt. Thomson Settlement / joint work agreements

    Cooperative effort among the leading North Slope producers and a leading North American pipeline company

    Identified potentially viable LNG project options to monetize ANS natural gas

    Used company strengths, shared information / expertise; built upon past efforts, sought out new ideas

    Attachment 1

    Att h t 2

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    17/18

    Alaska Southcentral LNG Project Concept Description

    Gas TreatingLocated at North Slope or Southcentral LNG siteRemove CO2and other gases and dispose / useFootprint: 150 - 250 acresPeak Workforce: 500 - 2,000 peopleRequired Steel: 250,000 - 300,000 tonsAmong largest in world

    Liquefaction Plant Capacity: 15 18 million tonnes per annum (MTA)

    3 trains (5-6 MTA / train) Potential areas: 22 sites assessed in Cook Inlet, Prince

    William Sound and other Southcentral sites Footprint: 400 - 500 acres Peak Workforce: 3,500 - 5,000 people Required Steel: 100,000-150,000 tons

    Storage / Loading LNG Storage Tanks, Terminal Dock; 1 - 2 Jetties Design based on 15 20 tankers Peak Workforce: 1,000-1,500 people

    Estimated Total Cost: $45 $65+ Bil lion Peak Construct ion Workforce: 9,000 15,000 jobs

    Operations Workforce: ~1000 jobs in Alaska

    Attachment 2

    Descriptions and cost s are preliminary in nature and subject to change. Cost range excludes inflation.

    PipelineLarge diameter: 42- 48 operating at >2,000 psiCapacity: 3 - 3.5 billion cubic feet per dayLength: ~800 miles (similar to TAPS)Peak Workforce: 3,500 - 5,000 peopleRequired Steel: 600,000 - 1,200,000 tons

    State off-take: ~5 points, 300-350 million cubicfeet per day, based on demand

    Producing Fields~35 TCF discovered North Slope resourceAdditional exploration potentialAnchored by Prudhoe Bay and Pt. Thomson with

    ~20 years supply availableUse of existing and new North Slope facilitiesConfirmed range of gas blends from PBU/PTU cangenerate marketable LNG product

    Peak Workforce: 500 1,500 people

    Attachment 3

  • 8/10/2019 Exxonmobil Presentation Agdc May 7 2014

    18/18

    GO

    LNGProject

    Oper

    ations

    Execute: Final engineering Financing Procurement Fabricate / Logistics / Construct Prepare for Operations

    Complete Govt / Reg. Issues: Secure remaining construction

    / operating permits Stakeholder engagement

    Implement businessstructure & agreements

    Commission / start-up

    Southcentral Alaska LNG Work Plans / Key Decision Points

    Evaluate:

    Range of technically viableoptions for major projectcomponents

    Business Structure In-state gas / export LNG demand

    Screen commercial viability

    Viable Technical Option(s) Identified Government Support Permits / Land Use Achievable

    Potential Commercial Viability

    Requirements to Take Next Step:

    Progress :

    Preliminary engineering torefine concept

    Business structure Financing plan

    Start individ ual gas / LNGsales / shipping efforts

    Assess commercial vi abi lit y

    Viable technical option Government Support Permits / Land Use Underway

    Potential Commercial Viability

    Activities

    Complete:

    Front-end engineering & design Major contract preparation Business structure Financing arrangements

    Solicit Interest of Others

    Advance Govt / Reg. Iss ues : Key permit / land use approvals Stakeholder engagement Secure DOE Export License

    Execute individ ual gas / LNGsales / shipping agreements

    Confirm comm ercial viability

    Secure Permits / Land Use / Financing /Key Commercial Agreements

    Confirm Commercial Viability

    Execute EPC contracts

    Attachment 3

    Peak Staffing: ~200 400 - 500 500 1,500 9,000 15,000

    Cost ($): Tens of Millions Hundreds of Millions Billions Tens of Billions

    Est. Engineering / Technical Duration*: 12 - 18 Months 2 - 3 Years 5 - 6 Years

    ConceptSelection

    Pre-FEED

    FEED(Front-End

    Engineering &Design)

    EPC(Engineering,

    Procurement &Construction)

    Decisionto Build the

    ProjectDecision Decision

    (Today)

    PTUSettlement,Joint Work

    Agreements

    * NOTE: Duration of various phases may be extended by protracted resolution of fiscal terms, permittin g and regulatory delays, legal challenges,changes in com modit y market outlook, time to secure long-term LNG contracts, labor sho rtages, material & equipm ent availability, weather, etc.

    GO GO GO

    Solicit Interest of Others

    Establish Government Support and Advance Regulatory Issues: Competitive oil tax environment; predictable / durable LNG project fiscal

    terms; AGIA Issues Assure ability to secure regulatory approvals / permits / land use Environmental activities / Technical data collection Stakeholder engagement File DOE Export License