TUROGE 2014 - Ankara, 10 April 2014 Exploration & Production onshore and offshore: technical challenges and their solutions Safety of Onshore and Offshore Oil & Gas Operations Giovanni Uguccioni – D’Appolonia SpA - Italy
Jul 15, 2015
TUROGE 2014 - Ankara, 10 April 2014
Exploration & Production onshore and
offshore: technical challenges and their
solutions
Safety of Onshore and Offshore Oil & Gas Operations
Giovanni Uguccioni – D’Appolonia SpA - Italy
Introduction
Giovanni Uguccioni, O&G Sector Development Manager in
D’Appolonia SpA, former Head of the HSE Division in
D’Appolonia.
D’Appolonia SpA is an Italian Company with 700+ technical staff
and offices in Italy and worldwide (including Turkey) belonging
to the RINA Group, providing services to Clients in the O&G,
Transportation and Infrastructures markets from concept to
decommissioning, through consultancy, design, management and
operation & maintenance engineering.
For the O&G sector, in addition to PMC, Basic and Detail design,
Gesoscience, Asset Integrity Management, O&M services,
D’Appolonia has a long term experience in Safety and
Environmental consultancy to major O&G Operators and EPC
Contractors Worldwide.
Risk: Nature
The Oil and Gas (O&G) industry supplies the world
market with substantial amounts of raw products,
fuel and refined products produced and transported
for a number of industrial activities.
Therefore the O&G industry is by its very nature a
high risk industry, handling large quantities of
flammable, hazardous and sometimes toxic (H2S)
substances frequently with high pressure and
temperature scenarios.
Risk: Nature
Despite sophisticated Health, Safety and Environment
(HSE) Management Systems and highly developed
safety cultures, major accidents in the Oil & Gas
industry are reoccurring events, putting at stake the
lives of personnel working at the site, the life and
health of populations in neighboring communities, the
viability of the ecosystem, the reputation and the
same economic survival of the Company involved.
During the ’70s some major accidents
occurred in Europe :
1974 Flixborough (United Kingdom)
[28 fatalities, damages to the environment]
1975 Beek (Netherland)
[14 fatalities, 106 injured ]
1976 Seveso (Italy)
[chronic damage to population and environment]
After this last event, in 1982 Council Directive 82/501/EEC on the major-accident hazards of certain industrial activities, so-called Seveso Directive,was adopted.The Directive was then revised in 1996 (96/82/EC) and in 2003(2003/105/EC), after the industrial accidents of Toulouse (F), Baia Mare(RO) and Enschede (NL)
Legislation on Industrial safety in Europe
• prevention of major accidents involving dangerous
substances
• limitation of the consequences of accidents on
man and the environment
high level of protection
for man and the environment (throughout
the European Union), through…..
Aim of the “Seveso” Legislation
Demonstrate Safety within the Safety Report
SafeManagement
SafeTechnology
Emergency
Planning
Land-Use
Planning
Info
rma
tio
n to
th
e P
ub
lic
I N S P E C T I O N S
Accident Reporting and Lessons Learnt
“Seveso” Legislation General Philosophy
• SEVESO approach is based on the concept of controlling the risk
• SEVESO relates to 'presence of dangerous substances‘
– actual
– anticipated
– generated during loss of control of an industrial chemical process
• Dangerous substances are listed in the Annex I
– a list of Named Substances (i.e. LPG, Chlorine, methanol, MIC,
gasoline, gasoil, dioxins, etc.)
– a list of Generic Categories of Substances and Preparations
(i.e. toxics, flammables, explosives, dangerous for the aquatic
environment, etc.)
“Seveso” Legislation Hazardous Plants
The level of the hazard is based on the presence of specific quantities of
dangerous substances. The higher the Hazard, the more stringent the
safety measures shall be.
The SEVESO Directive sets two levels of controls depending on quantities
(so called lower tier and upper tier)
– Example:
• gasoline and light liquid hydrocarbons: Lower tier is set to 2,500 tons, Upper
tier is set to 25,000 tons
• Substances “Toxic for Aquatic environment”: Lower tier is set to 200 tons,
Upper tier is set to 500 tons
• Upper tier industries (Type B) are more hazardous than lower tier
industries (Type A)
• Upper tier requirements are more severe than lower tier requirements
“Seveso” Legislation Tiered approach
10
Maximum amounts on siteSeveso Directive
Upper tier Lower tier
Classificatio
nO
bligatio
ns
Notification to the authorities
Major Accident Prevention Policy
Safety Management System
Safety report
Information to the public on safety
measures
Emergency planning
Shows Level of risk of the plant and demonstrate reliability of safety measures
Environmental risk reduction policy
Threat assessment(risk analysis)
“Seveso” Legislation Tiered approach
Enforced for the
first time
August 2010
Regulation on Control of Major Industrial Accidents
Revised regulation
December 2013
Regulation on Prevention of Major Industrial Accidents and Reduction
of Their Impacts
Prepared in line with SEVESO Directive
Involves the same principles with SEVESO
What about Turkey?
12
Maximum amounts on siteTurkish Regulation
Upper tier Lower tier
Classificatio
nO
bligatio
ns
Notification to the authorities
Major Accident Prevention Policy
Safety report
Public Notification
Emergency Planning(Internal and External Plans)
Turkish Regulation
Quantitative Risk Assessment
Enforcement dates
31.12.2013
01.01.2016
“Seveso” Directive Competency Building
“Seveso” Directive is not yet fully operative in Turkey, however its
full application is under way.
An “Europaid” Project is on-going, co-financed by the European Union
and the Republic of Turkey, to provide Technical Assistance to the
competent Ministries in Turkey on Increasing the Implementation
Capacity of the Seveso II Directive.
The Project, carried out by a Consortium of six companies including
D’Appolonia, is aimed to provide training to Central and Local
Authorities personnel, as well as developing a Pilot Safety Report
study on a Turkish O&G installation to test the application of the
Seveso Directive principles and criteria in a real Turkish situation.
A Safety Report demonstrate the Safety of an operation, by:
1. demonstrating that a particular scenario no longer presents a
major-accident hazard due to the measures in place;
2. demonstrating that the extent of the effects of a particular
scenario have been limited or the probability of the scenario is
sufficiently low;
3. demonstrating the efficiency and the effectiveness of mitigation
measures put in place;
4. establishing whether further mitigating measures are necessary;
5. providing information for competent authority obligations (e.g.,
emergency plans, land-use planning).
In summary, by establishing whether the activity is “tolerable”.
Risk Analysis and Safety Report
• The main elements in any risk analysis process are :
• Hazard identification (checklists, hazard indices and historical
data, HAZOP, FMEA, event trees accident scenario selection)
• Scenarios’ ‘likelihood’ (historical data, fault/event trees,
expert judgment), considering the reliability and availability of safety systems (measures to prevent/limit consequences)
• Scenarios’ consequence assessment (population and opertors, environment, property)
• Risk ranking (on the basis of frequency and severity, e.g. by individual risk and social risk measures)
Risk Analysis Process
Minor injuries
Serious Injuries
Lethality threshold
Fatality
Risk Analysis Results
R s = < f .C >S = Scenario
f = Expected frequency of an adverse event
C = Consequent reference damage
Risk Assessment
“Risk” is defined as “the probability of suffering a given damage”,
and is a function of Frequency and Damage level. In general terms:
Starting from the general definition, Risk Indicators can be quantitative,
semi-quantitative or qualitative. The choice of either a qualitative or
quantitative approach is strongly influenced by the specific safety culture
philosophy within each individual State.
How are the Risk Analysis results used for?
To assess the Risk…..
Individual riskannual frequency of occurrence of the reference
damage (e.g., the death), in any point of the
geographical area, for a person present in the area,
taking into account the probability of the presence
of the person.
Residential area
10-4 10-5 10-6 10-7
Risk source
Sea
Risk Assessment –Quantitative Indicators
Societal Risk
An F-N curve describes the cumulative
frequency (F) of accidents from all risk sources
leading to the reference damage (e.g. death)
for a number of people equal to or greater
than N. This figure characterises the societal
dimension of possible accidents.
10-4
10-5
10-6
10-7
10-8
1 5 10 50 100 Number of
deaths N
Annual
frequency F
Land-Use Tolerability Each combination of the likelihood and the severity
classes is associated to a specific land use that is
tolerable. Examples are tolerable land uses (Italian
Law 9/5/2001)
Risk Assessment –Semiquantitative Indicators
Accidentfrequency
Damage Effect Categories
Fatalities LethalityThreshold
Seriousinjuries
Minor Injuries
< 10-6 DEF CDEF BCDEF ABCDEF
10-4 – 10-6 EF DEF CDEF BCDEF
10-3 – 10-4 F EF DEF CDEF
> 10-3 F F EF DEF
Use of the Safety Report in Authorisation Process
New or
modified ?
Preliminary
Safety Report
Approved ?
new
noStop
Authorisation
to build the
plant
yes
Upper tier?
Detailed
Safety
Report
Document
non increase
of risk
Approved ?
Authorisation
to Operate
no yes
Approved ?
Authorisation
to build and
operate
Revise
Project
no
Increase of Risk
(DM 9.8.00) ?
modification
yes
no
yes
yes
Notifyno
Updat
edev
ery
5 y
ears
Offshore ?
On June 2013 the European Parliament has approved Directive
2013/30/EU on “safety of offshore oil and gas operations”, that
will fully enter into force in 2016 for new and in 2018 for existing
installations.
The Directive adopts the same philosophy and principles described
for the “Seveso” Directive (onshore), in particular:
• The operator shall issue a Safety Report identifying Major
Hazards to safety and environment;
• The Operator shall submit an Emergency Response Plan (ERP);
• An Independent Verification Scheme on Safety and Environmental
critical elements shall be enforced by Operators;
• A competent Authority will be appointed to manage regulatory
functions.
Conclusions
• Risk of Major Accidents affects any O&G installation
• Public concern causes “NIMBY” reactions… project schedule
jeopardized
• Risk Analysis techniques triggered by “Seveso” improve safety
of installations
• Scope can be extended: from onshore to offshore
• Coverage also expanding: several non-EU Countries are applying
“Seveso-like” concepts
• Next step: TURKEY!
Thank you for your attention