Stanford Cath Labs 7, 9, & 10 Numeric results of CAD vs. BIM to 2” vs. full BIM Jason Holbrook David Denysenko Eric Peabody
Nov 21, 2014
Stanford Cath Labs 7, 9, & 10 Numeric results of CAD vs. BIM to 2” vs. full BIM
Jason Holbrook
David Denysenko
Eric Peabody
7
9
10
Experimental Controls
BIM Use Area* Start** ArchitectCath Lab 7
CAD 720 SF 2006
Cath Lab 9
2” Standard
1,173 SF 2009
Cath Lab 10
Everything
1,060 SF 2010
Experimental Variables
*Results expressed per SF to normalize this variable**Cost values escalated to 2010 relative value to normalize this variable
What’s supposedly in it for me?Save up to 23% on project costsComplete project 35% fasterDrop change order rate to <0.1%44% fewer RFIs
The Design Partnership LLP Architects + Planners
What’s supposedly in it for me?23% less $Complete project 35% fasterDrop change order rate to <0.1%44% fewer RFIs
The Design Partnership LLP Architects + Planners
What’s supposedly in it for me?Save up to 23% on project costs
35% fasterDrop change order rate to <0.1%44% fewer RFIs
The Design Partnership LLP Architects + Planners
What’s supposedly in it for me?Save up to 23% on project costsComplete project 35% faster
Changes to <0.1%
44% fewer RFIs
The Design Partnership LLP Architects + Planners
What’s supposedly in it for me?Save up to 23% on project costsComplete project 35% fasterDrop change order rate to <0.1%
44% fewer RFIs
The Design Partnership LLP Architects + Planners
Cath Lab 7CAD Only
The Design Partnership LLP Architects + Planners
7
Cath Lab 7: Siemens Biplane Cath LabProject Area: 720 Gross Square Feet Construction Start: 2006
Procedure Room: 600 Net Square Feet BIM Use: None
The Design Partnership LLP Architects + Planners
(E) CAD V.I.F. (N) CAD Construction
The Design Partnership LLP Architects + Planners
(E) CAD V.I.F. (N) CAD Construction
The Design Partnership LLP Architects + Planners
(E) CAD V.I.F. (N) CAD Construction
The Design Partnership LLP Architects + Planners
(E) CAD V.I.F. (N) CAD Construction
The delay was caused…by the over-head structural and M/E/P/FP not being coordinated. The majority of the overhead had to be re-designed.
The Design Partnership LLP Architects + Planners
“ ”DPR Construction
Cath Lab 9BIM to 2”
The Design Partnership LLP Architects + Planners
9
Cath Lab 9: Siemens Biplane Hybrid ORProject Area: 1,173 Gross Square Feet Construction Start: 2009
Procedure Room: 821 Net Square Feet BIM Use: Model to 2”
3D Scan (E) Model (N) Model
Construction
The Design Partnership LLP Architects + Planners
3D Scan (E) Model (N) Model
Construction
The Design Partnership LLP Architects + Planners
The Design Partnership LLP Architects + Planners
3D Scan (E) Model (N) Model
Construction
The Design Partnership LLP Architects + Planners
3D Scan (E) Model (N) Model
Construction
Cath Lab 10BIM Everything
The Design Partnership LLP Architects + Planners
10
Cath Lab 10: Siemens Biplane Pediatric Cath LabProject Area: 1060 Gross Square Feet Construction Start: 2010
Procedure Room: 717 Net Square Feet BIM Use: Model Everything
3D Scan (E) Model (N) Model
Construction
The Design Partnership LLP Architects + Planners
3D Scan (E) Model (N) Model
Construction
The Design Partnership LLP Architects + Planners
The Design Partnership LLP Architects + Planners
3D Scan (E) Model (N) Model
Construction
The Design Partnership LLP Architects + Planners
3D Scan (E) Model (N) Model
Construction
Results
The Design Partnership LLP Architects + Planners
BIM Use % from CAD
Cath Lab 7
CAD
Cath Lab 9
2” Standard
-15.0%
Cath Lab 10
Everything
-4.1%
Construction Cost
Change Order Cost
*All figures in 2010 Relative Value
BIM Use % of TotalCath Lab 7
CAD 12.4%
Cath Lab 9
2” Standard
8.1%
Cath Lab 10
Everything
<0.1%The Design Partnership LLP Architects + Planners
*All figures in 2010 Relative Value
BIM Use Construction Days/SF % from CAD
Cath Lab 7
CAD 8.40 mo 0.23 D/SF
Cath Lab 9
2” Standard
8.50 mo 0.15 D/SF -34.8%
Cath Lab 10
Everything
8.45 mo 0.16 D/SF -30.4%
Construction Schedule
The Design Partnership LLP Architects + Planners
All Costs
*All design professional fees, including non-BIM fees**Cath lab contribution margin of ~$8,000 per day
Survey All Services*
Construction $
Margin** Total
Cath Lab 7 18.5% 18.5%Cath Lab 9 1.6% 27.3% (15.0%) (22.0%) (23.3%)Cath Lab 10
1.6% 18.5% (4.1%) (18.6%) (17.9%)
ConclusionsSave up to 23% on project costsComplete project 35% fasterDrop change order rate to <0.1%44% fewer RFIs