Experiment of 11.7GHz PE at AWA DL 3/3/2014
Mar 23, 2016
Experiment of 11.7GHz PE at AWA DL
3/3/2014
Execution before the next meeting in around a week
1. 19MeV beam simulation---John/Dan
2. Structure assembling---Jing
3. Cleaning the rf load --- Sergey
4. Installation layout--- Scott (cross, pumping, ict location…)
5. Pump and leak check of diagnostic beamline--- Eric
Slide in Meeting on 2/27/2014
When:
Task* Description Res. Due Note
1 KL1/2 readiness Liu 4/30
2 LLRF readiness Jing 4/30
3 Structure readiness Jing 3/10 Re-cleaning and assembling, load
4 Installation readiness Scott 4/15 HW for installation
5 Safety readiness Manoel 3/30 Approval for 19MeV DL
6 Vacuum readiness Eric 4/30
7 Beamline readiness Liu 4/30 PS, magnets, actuators, remote control
8 Diagnostics readiness John 4/30 Cameras, cables, scope
9 Laser readiness John 4/30 16/32 bunch train
10 High charge (??) Eric 4/15 New cathode (upon the need)
11 simulation John 3/15 19MeV to DUT
Proposed starting date of experiment: 5/1
The goal of this meeting is to decide the installation configuration so that we can start ordering the necessary parts.
11.7GHz Proposed Config. 02-28-2014
11.7GHz Proposed Config. 02-28-2014
11.7GHz Proposed Config. 02-28-2014
11.7GHz Proposed Config. 02-28-2014
11.7GHz Proposed Config. 02-28-2014
Execution before the next meeting
• Final configuration drawing based on the 3 points mentioned in the meeting and Order all needed vacuum parts.
• Waveguide plumbing: loads (test L1&L2 with K1/K2 asap).
• Laser beam flap and re-alignment• Finish beam simulation