W E L C O M E Experiences of Decentralized Management of Rural Infras Dev in Nepal Bhim Upadhyaya Integrated Learning Institute (ILI), 15 th Feb 2015 Integrated Learning Institute
103

Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Jul 15, 2015

Download

Engineering

Bhim Upadhyaya
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

1

WE L C O M E

Experiences of Decentralized Management of Rural Infras

Dev in NepalBhim Upadhyaya

Integrated Learning Institute (ILI),15th Feb 2015

Integrated Learning Institute

Page 2: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Namaste is

both Outer

and Inner

Engineering

and

Technology

gayatry mantra

Page 3: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Engineer & Engineering

"The ideal engineer is a composite…

He is not a scientist, he is not a

mathematician, he is not a sociologist

or a writer, but he may use the

knowledge and techniques of any or

all of these disciplines in solving

engineering problems."

-N W Dougherty (1955)3Integrated Learning Institute

Page 4: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Rural Hou'ng

Irrig'n

RuralEle'city

Solid Waste

Drink.Water

SocialInfras

Rural Transport

LocalInfras

7 Sectors of Local Infrastructure in Nepal

:yfgLo k"jf{wf/ ljsf; gLlt )^!

!= :yfgLo oftfoft k|0ffnL@= kmf]x/ d}nf Joj:yfkg#= vfg]kfgL ;/;kmfO{ $= ;fgf l;+rfO{ tyf gbL lgoGq0f

%= n3' hnljB't, j}slNks phf{

^= cfjf; ejg tyf zx/L ljsf;

&= ;fdflhs k"jf{wf/

Page 5: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

5

Organisations for Rural Transport Infrastructure

Development in Nepal

• DoR

• DoI

• DoUD&BC

• DoF(Forestry)

• MoAC and DoA

• Nepal Electricity Authority NEA

• MoLD

• DoLIDAR

• DDCs-75

• Municipalities-58

• VDCs-3913

Page 6: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Local Infrastructure and Poverty Reduction

Local infrastructure

Rural Development

Poverty Reduction

6Integrated Learning Institute

Page 7: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Infrastructure Status in Nepal (Approx.)

1. Irrigation

Cultivated Land- 26.5 Lakh ha.( 20% of Total Area)

Irrigable-17.6 Lakh ha.(66% of Cultiv'd)

Irrigated- 11.2 Lakh ha. (62% of Irrigable)

Year Round Irrigated-4.5 Lakh ha.( 40% of Irrigated, 25% of Irrigable)

2. Water & Sanitation

• water-76%, Sanitation- 26% (Quality? Quantity?)

3. Railway- 59 km

4. Airport Paved 10 Nos

5. Roads• All Weather 11,000 km

( All type 28,000 km)

• Paved Road- 4,000 km

6. Electricity Hydro- 556 MW(0.67% of Potential)

Diesel- 55 MW

Coverage- 40%(quality?!)

Total- 618 MW

7. Fuel/Energy Fossil Fuel- 18 Lakh L/Day

(11,550 B/D)

LP Gas - 225 MT/Day

8.Telephone Lines- 5.3 M

9. Internet Users- 0.2 M7Integrated Learning Institute

Page 8: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Government Organizational Tiers

for Rural Road Development

Ministry of Local Dev

Dept of Local Infras Dev

& Agri Roads (DoLIDAR)

District Dev Com. Office 75

Municipality >200

District Technical Office 75

Vill. Dev. Com. Office <3600

Page 9: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Institutional Setup for Rural Infrastructure Development in Nepal

9Integrated Learning Institute

Page 10: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

10

Single & Unified

Approach

Suitable Engineering

Organization

Single door system

of Res Mobilization

DoLIDAR: Guiding Principle

Page 11: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

11

DoLIDAR: An Organization for

Achieving the Objectives

Labor Based

Local Res.Oriented

Env. Friendly

Decentralized

Participatory

Dev of Local Infras

Direction to

Donors

Policy

Awareness

Effective

M&E

Improved O&M

Process

Establishment

of Engg Orgn

Planned

HRD

Decentralized

Planning

Need basedBudget Allocation

Uniform Planning

Process

Standardized

Implementation

Page 12: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

DoLIDAR

WBank ADB

MOFALD

VDC

Muni

DFID

Finland

NGO DTO

DDC

Consultant

International

Consultant

National

SDC

Denmark

ILO

JICA

DoLIDAR’s

Stakeholders

Page 13: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

0.3

0.3

0.3

0.3

0.3

0.3

0.4

0.5

0.5

0.3

0.4 0.7 1.1 2.4 3.3 3.6

3.7 4.0 4.1 4.6

3.6 4.8 6

.5 7.5 8.5 1

1.2 13.0

24.0

36.0

42.0 4

6.0

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

45.0

50.0

038

/39

03

9/4

0040

/41

041

/42

042

/43

043

/44

044

/45

045

/46

046

/47

04

7/4

8048

/49

049

/50

050

/51

051

/52

052

/53

053

/54

054

/55

05

5/5

6056

/57

057

/58

058

/59

059

/60

060

/61

061

/62

062

/63

06

3/6

4064

/65

065

/66

066

/67

067

/68

068

/69

Budget Allocation in MLD In Billion Rs

069/70= Rs 46 Bn

070/71= Rs 46 Bn

071/72= Rs 55 Bn

Page 14: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

cjnDjg ul/Psf gLlt tyf sfo{gLltx? :yfgLo :jfoQ zf;g P]g tyf lgodfjnL

:yfgLo k"jf{wf/ ljsf; gLlt, @)^!

:yfgLo k"jf{wf/ ljsf; ;+alGw sfo{qmdx?sf] sfo{If]q/;Ldf ;+aGwdf :ki6tf

:yfgLo k"jf{wf/ ljsf; ;+alGw gLlt tyf sfo{gLltx?

:yfgLo k"jf{wf/ ljsf; /0fgLlts sfo{of]hgf, @)^$

;+:yfut ;'b[9Ls/0f sfo{ of]hgf (ISAP)

jftfj/0fLo tyf ;fdflhs Aoj:yfkg vfsf (ESMF)

u|fld0f ;8s dd{t ;+ef/ lgb]{lzsf, @)^$

s[lif tyf :yfgLo :t/sf ;8s sfof{Gjog lgb]{lzsf @)^#

emf]n'Ë] k'n /0fgLlt, @)^@

emf]n'Ë] k'n If]qut sfo{qmd sfof{Gjog lgb]{lzsf @)^^

Uf|fdL0f oftfoft k"jf{wf/ If]qut sfo{qmd sfof{Gjog lgb]{lzsf @)^^

Page 15: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

15

Present policies and practices

Encouragement of Labor-based , Environment Friendly Technology of construction.

Application of mitigation measures as Bio-engineering and Slope stabilization

More curative approach than preventive / mitigative approach.

Emphasis on road-side plantation and Bio-engineering

Development of applicable tools, techniques and guidelines for sustainable rural infrastructure development

Page 16: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Under DoLIDAR

Page 17: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

17

ljefu dftxt ;+rflnt sfo{s|dx?

!= u|fdL0f vf]kfgL tyf ;/;kmfO sfo{s|d(RWSSP) -g]kfn ;/sf/@= u|fdL0f hn>f]t Joj:yfkg kl/of]hgf (RVWRMP-II) -lkmgNof08#= klZrd g]kfn u|fdL0f vfg]kfgL tyf ;/;kmfO{ cfof]hgf (RWSSPWN-

II) -lkmgNof08

$=u|fdL0f k'glgdf{0f tyf k'g:yfkgf cfof]hgf ( RRRSDP) -P=l8=la,a]nfot

%= :yfgLo oftfoft k""jf{wf/ If]qut sfo{s|d ( RTI-SWAP) -g]kfn ;/sf/^= em]fnË]k'n If]qut sfo{s|d–TB SWAP -g]kfn ;/sf/

&= u|fdL0f kxF'r sfo{s|d (RAP) -a]nfot*= lhNnf ;8s ;xof]u sfo{s|d (DRSP) -l:j; ;/sf/(= u|fdL0f kx'Fr ;'wf/ tyf ljs]lGb|t kl/of]hgf (RAIDP) -ljZj a}Fs

Page 18: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

18

ljefu dftxt ;+rflnt sfo{s|dx?======

!)=ljs]lGb|t u|fdL0f k"jf{wf/ tyf lhljsf]kfh{g ;'wf/ sfo{s|d (DRILP) -P=l8=la!! =:yfgLo:t/sf ;8s k'n tyf ;fd'bflos kx'Fr ;'wf/ sfo{s|d (LRBP/CAIP) --g]kfn

/hfkfg

!@ ;fd'bflos l;+rfO{ cfof]hgf (CIP) -PlzofnL lasf; a}+s

!#=hLjg:t/ ;'wf/sf nflu :yfgLo k'jf{wf/ sfo{s|d (LILI) - l:j; ;/sf/!$= ;fgf l;+rfO{ glb lgoGq0f tyf cGo k'jf{wf/ ljsf; sfo{s|d -g]kfn ;/sf/_

!%= k'glgd{f0f tyf k'g{:yfkg sfo{qmd -zflGt tyf k'glgdf{0f dGqfno_

!^= zflGtsf nflu lasf; sfo{qmd -zflGt tyf k'glgdf{0f dGqfno_!&= :yfgLo ;8s dd{t ;+ef/ sfo{qmd -;8s af]8{ g]kfn_

!*= k|:tfljt /fli6|o u|fdL0f oftfoft ;'wf/ sfo{s|d -laZj a}+s / a]nfot_

Page 19: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

नेपालमा ग्राममण सडकअमिलेख एकझलक

2012

19

Page 20: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

DONORS, Intern'l Firms, INGOs in

Rural Infras. Sector

1.Donors World Bank,

Asian Development Bank,

UK's DFID,

JICA,

SDC,

Finland,

OPEC Fund,

IFAD,

UN WFP

ILO

2. International Consulting Firms

WSP (British),

ITECO (Swiss),

Finland Consulting Group,

3. INGOs Helvetas,

GTZ

4. Domestic Consultantsalmost all

20Integrated Learning Institute

Page 21: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

21

Project(Public Works) Defined

A Project has…

• Objective or Goal

• Time

• Cost

• Location or space

Integrated Learning Institute

Page 22: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Public Works Parties

Client or Employer

Engineers

or Consultants

Contractor

or Builder

or UC

Client+Contractor+Consultant

Contractor

or UC

Client

+ Engineer

NASC class on Aspects of Rural

Infras Project Managment 066.11.25 22

Standard 3 party Int'l Practice for large Works

2 Party Nepali(Local Body) Practice for small and medium sized Works

Page 23: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

23

Phases of Public Works

Works

Precons-

truction

Phase

Construction

Phase

Operation and

Maintenance

Phase

Integrated Learning Institute

Page 24: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

24

Procurement

Goods Services Works

Integrated Learning Institute

Page 25: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

25

Preconstruction

Phase

Preparation

or

Design

Procurement

or

Tendering

Contracting

or

Agreement

Integrated Learning Institute

Page 26: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

26

Construction

Phase

SupervisionCompletion

Verification

Closing &

Handing Over

Integrated Learning Institute

Page 27: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Construction

Supervison

Money(Finance,

Account)

Men(Labor,

Consultants)

Machine(Equipments,

Tools)

Materials(Site Store,

Quarry,Fuel)

Component

s

27

Page 28: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Supervison

of Works

Process

(Quality

System or

control)

Payment(Cost

Control: direct

indirect)

Time

(Progress)

Performance

(Output)

28

Aspects

Scheduling, Gantt, CPM, PERT

Drawing, Specification, Lab Tests, Qualified Supervisors

Page 29: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

29

Supervisory Hierarchy

Client

Project

Manager

Engineer

Field Supervisor

Labor

Project Manager

or Client's

Representative

Consultant

Contractor3 Parties Mutual

Check and Balance

Integrated Learning Institute

Page 30: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

30

PROJECT MGMT PROCUREMENT

MGMT

FINANCIAL

MGMT

CONSTRUCTION

MGMT

CONTRACT

MGMT

QLTY/LAB

MGMT

SITE MGMT

Public Works Management

Technical

Audit

QAP

WORK PLAN

payment

DISBURSEMENT

Reporting

mobilization

Insurance

Claim & Refund

Completion Closing O & MIntegrated Learning Institute

Page 31: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

31

Cost Control through Time, Cost Control

Page 32: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

32

Core Function of a Project

Page 33: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

NASC class on Aspects of Rural

Infras Project Managment 066.11.25 33

Scope, Time and Cost management for Success of Project

Page 34: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

34

Highways in Nepal

Integrated Learning Institute

Page 35: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

3535

National Rural Roads Network:

52,000 Km

Operational Rural Roads:

20,000 Km

Highways: 15 No

Feeder/Other Roads: 5 No

Strategic and Local Road Network of Nepal

TB: 5600 Nos.

SRN : 6000 Km

LRN: 5000 Km

Integrated Learning Institute

Page 36: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

36

Good Quality works in progress

Integrated Learning Institute

Page 37: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

37

Good Quality road in progress

Integrated Learning Institute

Page 38: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

38

Good Quality works in progress

Integrated Learning Institute

Page 39: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

39

Lab Mangmt

Integrated Learning Institute

Page 40: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

40

Road Construction Technologies

Integrated Learning Institute

Page 41: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

41Integrated Learning Institute

Page 42: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

42

Worst Quality works

Integrated Learning Institute

Page 43: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

43

Road ill-designed and in Disrepair

Poor-Maintenance and hardships

Integrated Learning Institute

Page 44: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

44Integrated Learning Institute

Page 45: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

45Integrated Learning Institute

Page 46: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

46Integrated Learning Institute

Page 47: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

47Integrated Learning Institute

Page 48: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

NASC class on Aspects of Rural

Infras Project Managment

066.11.25

4848

More than 5000

such TB Required

Page 49: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

49Integrated Learning Institute

Page 50: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Tuin

Gravity Ropeway

50Integrated Learning Institute

Page 51: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

NASC class on Aspects of Rural

Infras Project Managment

066.11.25

5151

Page 52: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

52Integrated Learning Institute

Page 53: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

53Integrated Learning Institute

Page 54: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

54Integrated Learning Institute

Page 55: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

55Integrated Learning Institute

Page 56: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

56Integrated Learning Institute

Page 57: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

57Integrated Learning Institute

Page 58: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

58Integrated Learning Institute

Page 59: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

59

Arsenic Removal in Nawalparasi

Page 60: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Leguwaghat Truss Steel Bridge 120 m longest in Nepal

Page 61: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

61

x'Dnf lhNnfdf lgdf{0f ul/Psf] !!& ld, ;d'Gb| ;txaf6 prfO{ ^$)) ;a} eGbf cUnf] :yfgdf lgld{t lxN;f emf] k'

Total Span : 117 m

Walkway Widtb : 1.2m

Hight : 6400 m

District : Humla

Page 62: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

62

tgxF' lhNnfdf lgdf{0f ul/Psf] #%% ld= ;a}eGbf nfdf] Single span

Suspension dfbL emf]=k'

Page 63: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

63

dgfË lhNnfdf ;d'Gb|\L ;txaf6 $@)) ld =sf] prfOdf /x]sf] r'lnn]8f/ emf]=k''

Page 64: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

64

prfO{ !!& ld

nDjfO{ #$$ ld

vf]nfsf] ;txaf6 ;a} eGbf cUnf] emf]]=k'=s':df / UFofbL hf]8\g]

Page 65: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

65

Affof] O{lGhlgol/Ë –DRSP

Page 66: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya
Page 67: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

;8s 5]p a[Iff/f]k0f df]/Ë –RRRSDP

Page 68: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

68

Rodfl;+x cdf8f]n gfnf ;8s emQmk'/–RRRSDP

Page 69: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

69

s/df vf]nf ;8s k'n ;'g;/L –RRRSDP

Page 70: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

a/af]6 sf]if eGhfË ;8s cf]vn9'Ëf –DRSP

Kflxn]

Page 71: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

71

klxn] clxn] cf]vn9'Ëf ?Dhf6f/ hf]8\g] ;8s

Page 72: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

a/af]6 sf]if eGhfË ;8s cf]vn9'Ëf –DRSP

clxn]

Page 73: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

73

Nffl6 vf]N;L le/ sfe|] –RRRSDP

klxn] clxn]

Page 74: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

74

Tffn vf]nf k'n, kf]v/f–sf:sL

Kflxnf clxn]

Page 75: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

75

Photographs – Lot 2

Batch 2 Lot 2 : Ramechhap District

Photo 38-2.1

6-1 Site

Sukajor Khola

Unveiling of

commemoration

plate jointly by

the Secretary,

MoFALD, GON

and H.E. The

Ambassador of

Japan to Nepal

Photo 38-2.2

6-1 Site

Sukajor Khola

Traffic Opening

Ceremony

Dignitaries

passing the

Bridge

Page 76: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

76

Photographs – Lot 3

Batch 1 Lot 3 : Kavrepalanchowk District

Photo 30-3.1

Site 11-3

Roshi Khola

View of Tower

Erection (Left)

Photo 30-3.2

Site 11-3

Roshi Khola

Fixing Process of

Anchor Plates

(Left)

Page 77: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

77

Page 78: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Khani Khola Bridge, DolakhaSpan:24.7m, C Amount:16078174, Completion date:2070.03.21

• Khani Khola Bridge along Busti Putalikath Laharemane(Thulopatal) Roar at Gaurumudi-9 L/S & Namdu-1 R/S, Dolakha District

• Span : 24.70 m

• Type : RCC T- Beam & Deck

• Foundation : Open Type

• Benefited VDC – Gaurimudi, Mirge, Thulopatal, Jhule, Hawa, Chyama (30000 peoples benefited)

Page 79: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Sisne Khola Bridge, ArghakhanchiSpan:21m, C Amount:15250000, Completed date:2070.07.21

Page 80: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Gudrung Khola Bridge, KapilvasthuSpan:3x22.5m, C Amount:25960000, Completed date:2070.09.30

Page 81: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Harpan Khola Bridge, KaskiSpan:24.7m, C Amount:22837000, Completed date:2070.08.30

Page 82: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Shali Nadi Bridge, KathmanduSpan:21m, C Amount:22837000, Completion date:2070.08.30

Page 83: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Khadara Khola Bridge, MorangSpan:21m, C Amount:12179000, Completion date:2070.09.30

DoR Bridge, Kapilvasthu

Page 84: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Bhartaula Khola Bridge, Darchula

• Bhartaula Khola Bridge along Bhartaula Joljibi Sera Road at Dattu VDC , Bhartaula, Darchula District

• Span : 21.0 m

• Type : RCC T- Beam & Deck

• Foundation : Open Type

• Total Cost : 1,03,00000.00

• (DDC Contribution : 45 %)

• Completion Date : 069/070

Page 85: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

85

sflnsf]6 lHfNnfdf lgld{t ;fgf l;rfO{sf nflu kf]v/L –LILI

Page 86: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

86

b}n]v lHfNnfdf lgld{t ;fgf l;rfO{sf nflu kf]v/L –LILI

Page 87: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

87

vf]6fª lHfNnfdf lgld{t ;fgf l;rfO{sf nflu kf]v/L –LILI

Page 88: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

88KnlDaË tflnd lnb} ;xeflu, kj{t–RRRSDP

Page 89: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

89

a]df};dL t/sf/L v]tL tflndsf ;xeflu lrtjg –RRRSDP

Page 90: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Gravity flow water supply

Page 91: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Community contribution to water supply

Page 92: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Multiple-use systems

Page 93: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Renewable energy :

Micro/pico hydro, Improved Water Mills, Improved Cooking Stoves, biogas and Solar

Page 94: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Conventional (hill) irrigation

Page 95: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Sanitation & hygiene

Page 96: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Non-conventional irrigation

Page 97: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Schools

Page 98: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Environmental improvements

Tree nursery in Bishalpur VDC, Baitadi

Soil conservation / river bank erosion control in Sadepani VDC, Kailali

Page 99: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Environmental improvements at home:smokeless improved cooking stoves, washing rack, waste pits, latrines, biogas with latrine, hygiene & water safety plans

Page 100: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

100

Lifting Water Supply Project (3 stage) : From RWSSP-WN

Dumaikhola DWS : Alamdevi,Syangja(Pop.:2010,HH:311, Cost:1.78

Cror),There are 53 electrical and solar lifting systems are there. Solar

19 and electrical 33.

Page 101: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

101

Page 102: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Poetry of Science: What is Science? Scientists singing Anthem of Science's beauty

Carl Sagan

Richard Dawkins

Michael Shermer

Neil deGrassTyson

Brian Greene

Jacob Brownoski

Jill Tarter

Lawrence Krauss

Stephen Hawking

Carolyn Porco

PZ Myers

Large Hadrons Collider LHC CERN

Poetry of reality, the Science Anthem video

102

Page 103: Experiences of decentralized management of rural infras dev in nepal by bhim upadhyaya

Thank You

Mb 9851104057

Any Question?

103Integrated Learning Institute