Edward Farquharson James Ballingall March 2011 The Procurement Process
Mar 27, 2015
Edward Farquharson
James Ballingall
March 2011
The Procurement Process
2
Agenda
Procurement Process
• Principles
• Steps
• Best use of competition
• Evaluation
• Approvals
• Lessons
3
Principles
• Select a bid
• Maximize the benefits of competitive tension between bidders
• Deliver the best bid from the most competent bidder
• Minimize time and cost
• Stand up to scrutiny
=> balance these different objectives
4UNCLASSIFIED
Request for Final Proposals
Selection of Final / Preferred bidder
Financial Close
Number of Bidders
Depth ofInformation
flow
Project Launch
Negotiation/dialogue
Pre-qualification
5
Competitive Dialogue Procedure
“a procedure in which any economic operator may request to participate and whereby the contracting authority conducts a dialogue with the candidates admitted to that procedure, with the aim of developing one or more suitable alternatives capable of meeting its requirements and on the basis of which candidates are invited to tender”
Public Contracts Regulations 2006 (SI 2006 No 5)
6
Progressing through the process
• OJEU notice– Specify that competitive dialogue process will be used
– Intention to reduce the number of bidders at certain stages
– Needs and requirements (can also be included in a descriptive document)
– Pre qualification questionnaire issued (PQQ)
• Invitation to Participate in the Dialogue– 37 day clear days between despatch of OJEU to return date for expressions of
interest
– Minimum of three bidders that meet the PQQ selection period
– IPD: mature document which bidders can price. Need to have stakeholder support for its content
7
Evaluation criteria example: PQQ Level 1
Weighting Minimum Pass Score
Legal/Eligibility n/a(Pass/Fail Only)
Pass/Fail
Technical Ability 75% 50%
Economic & Financial Standing
25% 50%
8
Evaluation criteria example: PQQ Level 2Level 1 Criteria: TECHNICAL ABILITY 75 100Level 2 Criteria
Technical Capacity, Ability & Experience 60
Assessed through questions:C1, C2, C3, C4, C5, A11, A12, C6, C7, C8, C9, C10, C11
Level 2 Criteria
Experience of Working on Similar Projects 12
Assessed through questions:D1, D2
Level 2 Criteria
Method of Working 12
Assessed through questions:E1, E2, E3, E4
Level 2 Criteria
Quality Management, Environmental Management and Sustainability 6.5
Assessed through questions:G1, G2, G3, G4, G5
Level 2 Criteria
Health & Safety 6.5
Assessed through questions:H1, H2, H3, H4, H5, H6, H7, H8, H9, H10, H11
Level 2 Criteria
Equal Opportunities 3
Assessed through questions:I1, I2, I3, I4, I5, I6, I7
9
Dialogue Phase
• Aim is to “identify and define the best means suited to satisfying [the contracting authority’s] needs
• Phase should continue until the contracting authority is satisfied that it has identified and defined its requirements with sufficient precision to enable Final Tenders to be submitted
• May be conducted in “successive stages” – no limit to the number of stages provided that at the end of the dialogue there are sufficient bidders to allow for a genuine competition (usually a minimum of two)
• Dialogue continues until the contracting authority identifies the solution or solutions to meet their needs
10
Progressing through the process
• Call for final tenders
– Bidders to submit their tenders based on solutions identified in dialogue phase (comparable to submission of final ITN responses where no BaFO stage or a request for BaFO submission if this stage included)
– Suggest that request is submitted in writing. If the specification has been updated or revised then this should be issued
11
Submission and evaluation of Final Tenders
• Must contain “all the elements required and necessary for the performance of the project”
• Final tenders can be “clarified, specified and fine tuned” provided that this “does not involve changes to the basic features of the tender or call for tender, variations which are likely to distort competition or have a discriminatory effect”
– e.g. pricing changes
• Issues should be resolved before Preferred Bidder stage
12
Evaluation criteria example: Second StageCriterion Name at PQQ
Say 6 - 8
ISOS Weighting
say 3-4
ISDS Weighting
say 2
ISFT Weighting
1A Legal / Contractual 5.0% 10.0% 15.0%
A1 Legality 1.0% 2.0% 3.0%
A1.1 Legality 1.0% 2.0% 3.0%
A2 Contractual, Commercial Acceptability and Risk Transfer
3.0% 6.0% 9.0%
Etc
B Financial 15.0% 50.0% 50.0%
B1 Cost 5.0% 40.0% 40.0%
B1.1 Price 1.0% 30.0% 30.0%
B1.2 Payment Profile 1.0% 2.0% 2.0%
B1.3 Sensitivity Testing under Different Assumptions 3.0% 8.0% 8.0%
etc Financial Quality Criteria……. 10.0% 10.0% 10.0%
13
Evaluation criteria example: Second Stage cont…
Criterion Name at PQQ
6 - 8
ISOS Weighting
3 - 4
ISDS Weighting
2
ISFT Weighting
1C Technical 62.0% 33.0% 28.0%C1 Technical Solution 32.0% 16.5% 14.5%C1.2 Performance against Targets 6.2% 3.2% 2.8%EtcC2 Operation and Contract Management
Systems etc etc5.0% 3.0% 2.5%
D Environment & Sustainability 15.0% 5.0% 5.0%D1 Environment 15.0% 5.0% 5.0%D1.3 Mitigation of Environmental Issues 5.75% 1.9% 1.9%
etc….E Bid Integrity 3.0% 2.0% 2.0%E1.1 Consistency of Technical, Financial, Legal
and Sustainability Proposals etc…..1.5% 1.0% 1.0%
100.0% 100.0% 100.0%
14
Progressing through the process
• Appointment of Preferred Bidder
– Bidder offering economically most advantageous tender
– Criteria: Technical, Financial, Legal, other e.g. deliverability
• Key issues
– Methodology
– Informing Bidders
– Flexibility
15
Approvals
• Staged Approach
– OJEU
– IPD
– PB
• Matters to consider
– Requirement (time, cost, performance)
– Affordability
– VfM
16
Opportunity to Influence Project Outcome
Time
100%
Wh
ole
Lif
e E
xpen
dit
ure
Confirm StrategyConfirm
JustificationCompetitive Procurement
In-ServiceConfirm Benefits
Strategic Assessment
Contract Award
0%
Gate 0
Gate 1
Gate 2
Gate 3
Gate 4
Gate 5
ProcurementStrategy
InvestmentDecision
ReadinessFor Service
BenefitsEvaluation
BusinessJustification
17
OGC GatewayReview 1
OGC GatewayReview 2
OGC Gateway Review 3
OGC GatewayReview 4
OGC GatewayReview 5
Lessons: Gateway Review ProcessLessons learned
Define Programme
ExecuteProgramme
CloseProgramme
Develop Business
Case
Develop Procurement
Strategy
CompetitiveProcurement
Award andImplement
contract
Manage contract
Closure
Business justification
Procurement strategy
Investment decision
Readiness for service
OGC Gateway Review 0Strategic
assessment
Repeat asnecessary
Contributes
Procurement projects
OGC Gateway Review 0
OGC Gateway Review 0
*
*
Benefits realisation
Policy ReviewPolicy MaintenancePolicy ImplementationPolicy Design
18
Procurement Lessons: Gateway Reviews
• Effective stakeholder communication (approvals)
• Sound financial controls (affordability)
• Good Market knowledge and procurement advice
• Adequate skills and resources
• Clearly defined roles and responsibilities
• Robust business case
• Benefits realisation process
• Pre-agreed Critical Success Factors
• Ongoing risk management process
19
Lessons Learnt: The Project Manager’s View• Plan ahead but be flexible – things inevitably change
• Set a prudent budget – investing at this stage can yield long term savings
• Advisers – name key personnel
• Advisers – fixed price for clearly defined work packages
• Things will change – look at potential for variations when assessing advisers fees and resources.
• Project Governance and approvals – communicate and manage expectations – shocks don’t go down well.
• Link back to the core business – good communication links
• Transition plan – knowledge transfer to contract management team
• Financial Close – it is not the end – it has only just begun!
20
Lessons Learnt: The Advisers’ View
• An experienced project manager and a clear remit give confidence
• Too many advisers and advisers managing advisers leads to confusion on roles, increases costs, leads to delays
• Clients who are willing to listen often achieve best results
• Unrealistic timescales affect quality of service
• Suitable resources are not always readily available
• Best projects have experienced client fronting all bidder meetings
• Financials – advisers are there to make money
• Partnership ethos – advisers will often go the extra mile
• Reputation issues – future work
21
Lessons Learnt: The Bidders’ View
• What does the client really want?• Who are the key decision makers and influencers?• Does the project have a deliverable solution?• Is there a level playing field in terms of competitors?• Can I offer a USP that differentiates my consortium?• What are the external stakeholder issues (planning)?• Level of approval to date (affordability, vires, etc)• Extent of risk transfer• Are the timescales realistic?• Forecast Bid Costs• Supply chain, local resource and inflationary pressures• New v mature market with standard procedures• Other projects in the market – which has best chance of success?
22
Questions and Discussion