Top Banner
EPA Conference on Enterprise Servers and EPA Conference on Enterprise Servers and Data Centers: Opportunities for Energy Data Centers: Opportunities for Energy Savings Savings January 31 January 31 - - February 1, 2006 February 1, 2006 Case Study: Expanding Existing Data Center Case Study: Expanding Existing Data Center Mukesh K. Khattar, Ph.D., PE Mukesh K. Khattar, Ph.D., PE Energy Director Energy Director
25

Expanding Existing Data Center

Feb 11, 2017

Download

Documents

buinguyet
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Expanding Existing Data Center

EPA Conference on Enterprise Servers andEPA Conference on Enterprise Servers and Data Centers: Opportunities for EnergyData Centers: Opportunities for Energy

SavingsSavingsJanuary 31January 31--February 1, 2006February 1, 2006

Case Study: Expanding Existing Data CenterCase Study: Expanding Existing Data CenterMukesh K. Khattar, Ph.D., PEMukesh K. Khattar, Ph.D., PE

Energy DirectorEnergy Director

Page 2: Expanding Existing Data Center

Energy Efficiency Options for…

Expanding Existing Data CenterExpanding Existing Data Center••Tier 4; ~45,000 ftTier 4; ~45,000 ft22 raised floor; Add ~27,000 ftraised floor; Add ~27,000 ft22

••~Average 125 W/ft~Average 125 W/ft22; Add up to ~400 W/ft; Add up to ~400 W/ft22

••~4 kW/rack; up to ~25 kW/rack~4 kW/rack; up to ~25 kW/rack

Page 3: Expanding Existing Data Center

Existing Data Center Expansion

Primary Focus: Cooling SystemPrimary Focus: Cooling System99Electrical hardware procured earlierElectrical hardware procured earlier99Air distribution criticalAir distribution critical

……especially for high density racksespecially for high density racks99Free cooling opportunitiesFree cooling opportunities

••Air side economizerAir side economizer••Water side economizerWater side economizer

99VFD for new chillers?VFD for new chillers?

Page 4: Expanding Existing Data Center

HVAC SystemHVAC System

••30 tons CRAC units, under floor air30 tons CRAC units, under floor air distribution (~1800 tons); Add ~1200 tonsdistribution (~1800 tons); Add ~1200 tons

••4x600 tons chillers, capacity modulation4x600 tons chillers, capacity modulation

••2x600 tons additional chiller2x600 tons additional chiller

••Primary/Secondary pumpingPrimary/Secondary pumping

••5 Cells cooling tower5 Cells cooling tower

Page 5: Expanding Existing Data Center

Heat Rejection Chain Several heat transfer loopsSeveral heat transfer loops

……independent, but interactingindependent, but interacting••Server fans, from server chips to room airServer fans, from server chips to room air

••CRAC, from room air to cooling coil waterCRAC, from room air to cooling coil water

••Secondary pumps, from cooling coil water toSecondary pumps, from cooling coil water to primary loopprimary loop

••Primary pump, from loop to chillerPrimary pump, from loop to chiller

••Condenser water, from chiller to cooling towerCondenser water, from chiller to cooling tower

••CT fans, from condenser water to airCT fans, from condenser water to air

Page 6: Expanding Existing Data Center

Air Flow

Air flow determined from heat carryingAir flow determined from heat carrying capacity:capacity:

Q = M*CQ = M*Cp*p*(T(Too -- TTii))

==kk*CFM* (T*CFM* (Too -- TTii))

TTii = Server inlet temp, ~55F= Server inlet temp, ~55F

TT00 = Server outlet temp, ~100 F= Server outlet temp, ~100 F (acceptable, chip core temp <190 F)(acceptable, chip core temp <190 F)

Page 7: Expanding Existing Data Center

Required airflow…

Minimum server flow: 67,600 CFMMinimum server flow: 67,600 CFM

……for removing 1000 kW server loadfor removing 1000 kW server load

……based on 53 F server inlet and 100 Fbased on 53 F server inlet and 100 F discharge tempdischarge temp

CRAC Units Airflow: 171,100 CFMCRAC Units Airflow: 171,100 CFM

……300 tons CRAC units300 tons CRAC units

……based on 72 F return and 53 F supplybased on 72 F return and 53 F supply

Page 8: Expanding Existing Data Center

Airflow, min. required vs. actual

……for 1000 kW server loadfor 1000 kW server load……cost based on $.055/kWhcost based on $.055/kWh

Minimum Required CFM

Bypass/ or

CFM

$18,493

$28,232 Over supply

Page 9: Expanding Existing Data Center

Cost Impact of 10% AirflowReduction

$14,979

$19,083

$12,662Minimum Required

CFM

Bypass/OverSupplyCFM

Potential 10% CFM Reduction

……for 1000 kW server loadfor 1000 kW server load

Page 10: Expanding Existing Data Center

Cost Impact of 20% AirflowReduction

Minimum Required

CFM

Bypass/OverSupply

CFM

Potential 20% CFM Reduction

$8,628

$8,812

$29,285

……for 1000 kW server loadfor 1000 kW server load

Page 11: Expanding Existing Data Center

Measured Fan Power Vs. Speed

0% 100% 75% 50%

Fan Speed, %

Fan

Pow

er, %

Measured ^3 Correlation ^2 Correlation

20%

40%

60%

80%

100%

Page 12: Expanding Existing Data Center

Reducing flow/ using VFD

AgainstAgainst

••Data center load isData center load is constant and doesconstant and does not varynot vary

••It is not used in dataIt is not used in data centerscenters

••Not cost effective?Not cost effective?

••How would youHow would you control VFD?control VFD?

ForFor

••Data center isData center is designed with ~15designed with ~15­-20% redundant CRAC20% redundant CRAC and airflow capacityand airflow capacity

••Data center loadData center load does vary, not hour todoes vary, not hour to hour, but from day tohour, but from day to day as number ofday as number of servers changeservers change

Page 13: Expanding Existing Data Center

What won approval for VFD?

However, for a 1000 kW server area, useHowever, for a 1000 kW server area, use of VFD would save 50 kW power at 80%of VFD would save 50 kW power at 80% fan speed.fan speed.

Would IT rather have 50 kW powerWould IT rather have 50 kW power to put 10 additional 5 kW serverto put 10 additional 5 kW server racks?racks?

……Energy savings???Energy savings???

Page 14: Expanding Existing Data Center

VFD Economics Estimated payback ~16 monthsEstimated payback ~16 months

(assuming avg. 15% speed reduction,(assuming avg. 15% speed reduction, ~50% power reduction)~50% power reduction)

Actual payback ~8 monthsActual payback ~8 months

(time required to load servers/racks;(time required to load servers/racks; VFD operated at ~50% speed, >80%VFD operated at ~50% speed, >80% power savings)power savings)

Recommendations: Oversupply of air;Recommendations: Oversupply of air; Reduce Airflow; VFD Cost effectiveReduce Airflow; VFD Cost effective

Page 15: Expanding Existing Data Center

Comparison of CRAC fanenergy vs. chiller/central plant y A 40 ton CRAC has ~15 hp fan, ~11 kW y Typical 20% redundant/extra capacity, fan

power ~13kW y Fan power load constant 365x24 y Chiller central plant power ~.70 kW/ton y A 40 ton CRAC will use ~28 kW y Central plant energy use will change with

ambient, average ~20kW for 365x24 y Fan energy ~30-45% of total HVAC energy

Page 16: Expanding Existing Data Center

Free cooling

y Air side economizer – Can be used when ambient air below ~55 F

y Water side economizer – Run cooling tower when ambient outdoor is cold

to chill condenser water to ~42 F – Use cooling tower water to cool chilled water to

45 F – Can be used when ambient outdoor wet bulb

temperature is below ~35 F

Page 17: Expanding Existing Data Center

Free cooling potential

Austin Weather Data

0

200

400

600

800

1000

1200

1400

77.5

102.5

Ambient Temperature

Num

ber o

f Hou

rs

WATER AIR

17.5

22.5

27.5

32.5

37.5

42.5

47.5

52.5

57.5

62.5

67.5

72.5

82.5

87.5

92.5

97.5

Page 18: Expanding Existing Data Center

Free Cooling Potential

Austin Weather

0 1000 2000 3000 4000 5000 6000 7000 8000 9000

10000

Cum

ulat

ive

Hou

rs

WATER

AIR

17.5

22.5

27.5

32.5

37.5

42.5

47.5

52.5

57.5

62.5

67.5

72.5

77.5

82.5

87.5

92.5

97.5

Ambient temperature

Page 19: Expanding Existing Data Center

Air side economizer

y Large amounts of outdoor air needed y ~1,710,000 CFM needed at 53 F y ~3400 ft2 opening/ filter area needed (at 500

FPM) y No convenient way to bring outside air to CRAC

on raised data floor with down flow design y Humidity control problems; other contaminants y Did not find it practical

Page 20: Expanding Existing Data Center

Water side economizer y Preferred to air side: Avoids contaminants, humidity

problems, large OA opening, delivering OA to CRACon raised data floor

y However, fewer potential hours <600 annually y Question about cooling tower operation and

performance at freezing ambient conditions; notenough information, data available

y Controls issues with switching between condensermode to economizer chiller mode

y New VFD chillers very efficient at low ambient y Heat exchanger requirement between condenser and

chilled water; retrofit impractical with existing system

Page 21: Expanding Existing Data Center

Additional Chillers

y Existing chillers constant speed, vane capacity modulation

y Newer technology (primarily refrigerant) available y Will chiller VFD…

– parallel?

y Selected VFD for new chillers – More efficient new chillers are lead chillers – Still optimizing operational and control sequences

Provide any energy benefits? How will it be sequenced with existing chillers operating in

Page 22: Expanding Existing Data Center

Lights out data center

y Installed motion sensors on fluorescent lights between isles

y Cost effective questions as people would be working most of the time?

y Certainly cost effective to install now than to retrofit later

y Security issue; emergency 7x24 lights sufficient for new security cameras

y Reduced light power load can be spared for use by IT equipment

Page 23: Expanding Existing Data Center

Q U E S T I O N S A N S W E R S

Page 24: Expanding Existing Data Center
Page 25: Expanding Existing Data Center

World-Class Austin Data Center

y 1 Acre of computer room space

y Middle of the US y Dual power feeds y

backup generators y Three 600 ton chillers y Dual redundant OC12

Ring to RMDC Oracle’s Austin Data Center

Five 2-MegaWatt diesel