Louise Avenue Capital Improvement Project

Danée McGee, P.E. Project Manager: Charlotte Storm Water Services

Robert Wilson, P.E.Principal: USInfrastructure of Carolina, Inc.

March 13, 2007

USInfrastructureOf Carolina, Inc.

Page 2: Existing Conditions Presentation

Project Team & Meeting Purpose

Charlotte Storm Water Services: Project Management

USInfrastructure: Design Consultant

Michael Baker Engineering:Sub-Consultant for Stream Enhancement

Meade-Gunnell Surveying:Sub-Consultant for Site Survey

Explanation of Storm Water Program: Why Are We Here?

Obtain Public Input:Your Part in the Process…

Provide Project Overview: What Are We Doing?

Explanation of Next Steps:What is Coming Next…

USInfrastructureOf Carolina, Inc.

Page 3: Existing Conditions Presentation

Charlotte’s Storm Water Program

Water Quality

Maintenance

Capital Improvements

USInfrastructureOf Carolina, Inc.

Page 4: Existing Conditions Presentation

During the project:

Public Input

– Mailers Every Four Months – Website Updates: http://Stormwater.Charmeck.Org

– Public Meetings

– Questionnaires and Property Owner Surveys

– Email and Phone Contact as Needed

USInfrastructureOf Carolina, Inc.

Page 5: Existing Conditions Presentation

Project Phases

1. Planning

2. Design

3. Permitting (401/404)

4. Easement Acquisition

5. Bid & Construction

– Public Involvement Throughout

USInfrastructureOf Carolina, Inc.

Page 6: Existing Conditions Presentation

Drainage Conditions in The Neighborhood

USInfrastructureOf Carolina, Inc.

Page 7: Existing Conditions Presentation

Louise Avenue CIP Area

USInfrastructureOf Carolina, Inc.

Page 8: Existing Conditions Presentation

Final Project Phases - How things Work:

Next Steps

– Additional Planning, Modeling and Field Surveys

– Design Phase

– 401/404 Permitting

– Easement Acquisition

– Bid and Construction

USInfrastructureOf Carolina, Inc.

Page 9: Existing Conditions Presentation

Questions &

Comments

USInfrastructureOf Carolina, Inc.

Page 10: Existing Conditions Presentation

Additional Projects in the Area

Seigle Avenue Streetscape: Keith Carpenter, Project Manager: E&PM

Belmont Gateways:Leslie Bing, Project Manager: E&PM

Seigle Point Apartments: Jeff Meadows, Project Manager: CHA

Future Greenway Trails:Mecklenburg County Park and Rec