Top Banner
EXECUTIVE SUMMARY DRAFT EIA Report of 1300 MW Natural Gas Based Combined Cycle Power Plant At Vaghel Village, Sami Taluka, Dist. Patan, Gujarat PROJECT PROPONENT M/s. DMICDC Vaghel Power Company Ltd. Room No. 341 B, 3 rd Floor, Hotel Ashok, Chanakyapuri, New Delhi – 110 021 Prepared by: Environmental Engineers & Consultants Detox Corporation Pvt. Ltd.
25

EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Apr 18, 2018

Download

Documents

lamnga
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

EXECUTIVE SUMMARY

DRAFT EIA Report

of

1300 MW Natural Gas Based Combined Cycle Power Plant At Vaghel Village, Sami Taluka, Dist. Patan, Gujarat

PROJECT PROPONENT M/s. DMICDC Vaghel Power Company Ltd.

Room No. 341 B, 3rd Floor, Hotel Ashok, Chanakyapuri, New Delhi – 110 021

Prepared by:

Environmental Engineers & Consultants Detox Corporation Pvt. Ltd.

Page 2: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 2

Table of contents 1 INTRODUCTION ..................................................................................... 3 2 NEED OF PROJECT ................................................................................. 4 3 COST OF PROJECT .................................................................................. 4 4 SALIENT FEATURES OF SITE .................................................................. 5 5 Project details ....................................................................................... 6

5.1 Power Plant Detail .............................................................................. 6 5.2 Raw Material for Power Plant ............................................................... 7 5.3 Water requirement ............................................................................. 7

6 LAND AREA BREAK UP ........................................................................... 7 7 ENVIRONMENTAL PARAMETERS ............................................................ 8

7.1 Meteorology Conditions ....................................................................... 9 7.2 AIR ENVIRONMENT ........................................................................... 11 7.3 WATER ENVIRONMENT ...................................................................... 14 7.4 Waste water Generated ..................................................................... 15 7.5 NOISE ENVIRONMENT ....................................................................... 17 7.6 FLORA AND FAUNA ............................................................................ 18 7.7 LAND ENVIRONMENT ......................................................................... 18

8 GREEN BELT DEVELOPMENT ................................................................ 20 9 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN ..................... 20

9.1 SAFETY MEASURE PLAN ..................................................................... 21 10 SOCIO ECONOMIC ENVIRONMENT ....................................................... 22 11 Corporate Social Responsibility and Community Development Programs

22 12 CLEANER PRODUCTION DETAILS ......................................................... 23 13 ENVIRONMENT MANAGEMENT SYSTEM ................................................ 23 14 ENVIRONMENT MONITORING PLAN ..................................................... 23 15 Conclusions ......................................................................................... 24 

List of tables

Table 1 : Salient Features of Project Site ........................................................... 5 Table 2 : Co-ordinates of Project Site Boundaries ............................................... 6 Table 3 : Project details .................................................................................. 6 Table 4 : Raw material details for Power Plant .................................................... 7 Table 5 : Source of water ................................................................................ 7 Table 6 : Facilities available in proposed plant .................................................... 8 Table 7 : Detail Land Areas Break Up ................................................................ 8 Table 8 : Details of Stack ............................................................................... 13 Table 9 : Resultant Concentrations Due To Incremental GLC ............................... 13 Table 10 : From Power plant Quantity of waste water generated .......................... 16 Table 11 : Quantity of Domestic waste water generated ..................................... 16 Table 12 : Details of the satellite imagery ......................................................... 18 Table 13 : Land use/cover Categories Area Statistics within study area ................. 19 Table 14 : Summary of Demographic structure.................................................. 22

List of figures

Figure 1 : Wind Rose Diagram Summer Season 2010. ....................................... 10 Figure 2 : Air Quality monitoring locations ........................................................ 11 Figure 3 : Bolero canal branch ........................................................................ 25 Figure 4 : Proposed project site ....................................................................... 25 

Page 3: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 3

1 INTRODUCTION

Government of India in association with Government of Japan is developing a

Multi Model High Axle Load Dedicated Freight Corridor (DFC) between Delhi and

Mumbai, covering an overall length of 1483 km, with end terminals at Tughlakabad

and Dadri in the National Capital Region of Delhi and Jawaharlal Nehru Port at

Mumbai. This Dedicated Freight Corridor offers high-speed connectivity for High Axle

Load Wagons (25 Tonne) of Double Stacked Container Trains supported by high

power locomotives. The envisaged alignment of freight corridor passes through six

states viz. Uttar Pradesh, NCR of Delhi, Haryana, Rajasthan, Gujarat and

Maharashtra. The Delhi- Mumbai leg of the Golden Quadrilateral National Highway

also runs almost parallel to the Freight Corridor.

M/s Delhi Mumbai Industrial Corridor Development Corporation Limited

(DMICDC), was incorporated on 7th January, 2008, as the Project Development

Agency for Delhi Mumbai Industrial Corridor (DMIC). The Government of India holds

49% equity in M/s DMICDC. DMICDC acts as a facilitator for the development of all

basic infrastructure in investment regions / industrial areas/ economic regions/

industrial nodes and townships in the region including roads, ports, freight corridor,

power and airports.

M/s DMICDC Ltd. had been suggested three potential sites by Energy

Department, Government of Gujarat and Gujarat Infrastructure Development Board

(GIDB) for establishment of the proposed gas based power project. Thereafter a

joint team with representatives from DMICDC Energy Department, GoG and GIDB

visited the potential sites and collected information for assessing the suitability of the

sites. Based on the above information and site selection criteria, the site near to

Vaghel village, in Sami taluka of Patan District, was found to be suitable for

development of the proposed gas based power project.

M/s DMICDC Vaghel Power Company Limited Ltd. A dedicated project SPV

has been incorporated by M/s DMICDC Ltd. to develop the proposed 1300 MW Gas

based power plant at Vaghel village, Sami Taluka in the Patan District of Gujarat

State.

M/s Detox Corporation Private Ltd., (Detox), a QCI/ NBRT (Quality Council of

India) accredited environmental consulting agency has been entrusted to undertake

this EIA study. Subsequently, Detox has carried out baseline environmental studies

Page 4: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 4

during the summer 2010 and developed this Environmental Impact Assessment

(EIA) report as per the guidelines and best practices suggested by Ministry of

Environment and Forests (MoEF).

The project was placed before the Expert Appraisal Committee of Ministry of

Environment & Forests (MoEF) for approval of ToR for the EIA study. The project

received the approval for carryout EIA study from MoEF and the copy of Terms of

Reference approval letter issued by MoEF is placed at annexure-1 of EIA report.

2 NEED OF PROJECT

The proposed high-speed connectivity between Delhi and Mumbai offers

immense opportunities for development of an Industrial corridor along the alignment

of the connecting infrastructure. A band of 150 km to 200km (Influence region) has

been chosen on both sides of the Dedicated Freight corridor to be developed as the

Delhi-Mumbai Industrial Corridor. This corridor will be equipped with an array of

infrastructure facilities such as power facilities, rail connectivity etc. Several

industrial estates and clusters, industrial hubs, with top-of-the-line infrastructure

would be developed along this corridor to attract more foreign investment.

In order to support these developments in the Delhi Mumbai Industrial Corridor

(DMIC) region and to attract investors (global and domestic); it is essential to supply

reliable and uninterrupted power. Given the current and projected peak load demand

and using the indexation of electricity ratio of electricity to industrial growth rate

anticipated in the plan, the peak power demand for the DMIC region is expected to

reach 27,200 MW by year 2013-14 and rise up to 71,000 MW by 2039. The proposed

power project would be able to meet partial power requirement of the upcoming

industries in the DMIC region.

3 COST OF PROJECT

Total capital investment for the proposed power plant project is approximately Rs.

3800 Crores.

Page 5: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 5

4 SALIENT FEATURES OF SITE

The proposed project site will be located in the available Government waste land with

a Survey # 39 of Vaghel village, Sami Taluka of Patan District in Gujarat state. The

Total land available for the project is 226 acres.

Table 1 : Salient Features of Project Site

Village Vaghel Tauka Sami District Patan State Gujarat

Survey # 39 Total available area 226 acres

Land Use Waste land Nearest Villages from the

Project site Vaghel Village app. 2.2 km from project site Aritha Village app. 2.75 km from project site

Nearest town Harij app. 8km from the project site Nearest railway station Harij

Nearest Airport Ahmedabad (90 km) Nearest Gas Grid M/s GSPL gas pipeline which will pass through

Sidhpur Taluka about 60 km from the project site Fresh water availability From Sardar Sarovar Narmada Canal, trough Bolera

Branch Canal located at 8 km from the project site Electricity sub station 66 KV substation is at Kansa Village which is at a

distance of about 8 kms from the project site A 400 KV substation of M/s PGCIL is located at Kansari village which is about 25 km from the project site.

Page 6: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 6

Table 2 : Co-ordinates of Project Site Boundaries

Sr. No. Latitude Longitude

1 23° 37' 46.48"N 71° 56' 15.58"E

2 23° 38' 1.61"N 71° 56' 27.87"E

3 23° 37' 46.82"N 71° 57' 0.39"E

4 23° 37' 28.13"N 71° 56' 40.90"E

5 PROJECT DETAILS

Table 3 : Project details

Project Proposed Capacity

Gas based combined cycle power plant with heat and steam recovery

1300 MW

5.1 Power Plant Detail

The proposed thermal power plant will be a natural gas based combined cycle

thermal power plant with a maximum output of 1300 MW capacity. Three number of

Page 7: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 7

power blocks comprising of individual gas turbine (GT) and steam turbine (ST) with

common facilities has been envisaged as part of the project. The rated output from

individual block will be in the order of 275 MW from GT and 145 MW from ST

respectively. The actual configuration of the individual blocks will be selected based

on the specifications provided by the successful supplier. However, for the purpose

of this environmental impact assessment study, a maximum power generation

capacity of 1300 MW has been considered in order to represent the worst case

scenario.

5.2 Raw Material for Power Plant

Table 4 : Raw material details for Power Plant

Input Quantity Source

Natural Gas 5 million metric standard cubic meter per day with a gross calorific value of 9880 Kcal/Sm3 and Density 0.7 kg/Sm³.

M/s GSPL Pipeline passing through Sidhpur Taluka at about 60 km from project site

5.3 Water requirement

The power plant requires about 28,234 m3/day, fresh water for regular

operations of the facility. The nearest source of water is the Bloero branch canal of

Sardar Sarovar Narmada canal with an intake point at a distance of 8 Km from the

project site.

Table 5 : Source of water

Quantity Source Transportation

28,234 m3/day From Sardar Sarovar Narmada

Canal, through Bolera Branch Canal

located at 8 km away

Pipeline

6 LAND AREA BREAK UP

All the facilities like main power block with 400 kV switchyard, Water

Reservoir, Water treatment plant, Gas Conditioning skid and HSD storage etc shall

be provided. Apart from the above mentioned facilities, non-Plant Buildings such as

Security Building, First Aid Centre, Fire station, Administrative Building etc have also

been considered. The total area available for the proposed project is 226 acres. The

proposed plant layout have been prepared in such a way that space is properly

Page 8: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 8

utilized, process flow is maintained and adequate access for operation and

maintenance is available. The following facilities have been planned to be located in

the plant:

Table 6 : Facilities available in proposed plant

1. Power Block

2. Switchyard

3. Water storage, and treatment block

4. Gas receiving and conditioning block

5. Emergency liquid fuel storage

6. Black Start & Emergency Power Facility

7. Compressed Air Facility

8. Effluent Treatment and disposal

9. Non plant building block like canteen, workshop, spare parts storage etc.

10. Administrative service area block

11. Residential colony including guest house, recreation centre and other facilities.

Table 7 : Detail Land Areas Break Up

Facility Approximate Area Allocated

Acres m2 % of total area

Area utilized for proposed power plant 111.36 450660 49.4

Township Area 12.67 51290 5.6

Green Belt Area 101.56 411000 45.0

Total Area 225.59 912950 100

7 ENVIRONMENTAL PARAMETERS

Existing environmental parameters were studied for three months in summer

season 2010 within the study area comprising of 10 km radius from the project

site.

Air quality monitoring station was selected based on predominant wind direction

and wind speed using the meteorological data obtained from online

meteorological station. other factor considered are for selection of monitoring

station are terrain of the study area, density of population within the region and

residential and sensitive areas

Page 9: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 9

7.1 Meteorology Conditions

In order to assess the background environmental conditions a weather

monitoring station was installed at a height of 3 m above the ground level in the

project vicinity for continuous recording of micro meteorological parameters like

wind speed, wind direction, cloud cover, rainfall, air temperature and relative

humidity.

The wind speed in the study area during summer season is observed between 0

m/s to 10.27 m/s. Predominant wind direction is SW to NE and the windrose

diagram is enclosed below.

Page 10: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 10

Figure 1 : Wind Rose Diagram Summer Season 2010.

Page 11: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 11

7.2 AIR ENVIRONMENT

Baseline data:

Total of 8 locations were considered for study of air quality including one at

project site and seven in and around 10 Km radius from the project site. Four sites in

upwind and two sites in down wind direction with respect to the project location were

monitored for air quality monitoring. One station was setup at Harij which is the

densely populated small town in the study area. The sampling station was placed at

a height of minimum 3 m above the ground level. The air monitoring locations are

depicted on the study area map as given below along with the windrose diagram of

study area.

.

Figure 2 : Air Quality monitoring locations

The detail of the monitoring location with average concentration of each pollutant at

these locations is given below:

A1

A2 A3

A4

A5 A6

A8

A7

Page 12: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 12

PM10

At all the monitoring locations, PM10 level varies between 34 µg/m3 to 86 µg/m3 with

the mean values in the range of 44.63 to 77.67 µg/m3 which is lower than that of the

NAAQ standard (100 µg/m3).

PM2.5

At all the monitoring locations, minimum and maximum value for PM2.5 was found to

be between 18 µg/m3 to 58 µg/m3, with the mean values in the range of 24.67 to

49.71 µg/m3 which is lower than that of the NAAQ standard (60 µg/m3).

NOx

The nitrogen oxide concentrations at all the monitoring locations within the study

area varies between 2.14 µg/m3 to 20.68 µg/m3, with the mean values in the range

of 5.50 to 17.74 µg/m3, which is much lower than that of the NAAQ standard (80

µg/m3).

SO2

Sulphur dioxide concentrations at all the monitoring locations within the study area

varies between 1.69 µg/m3 to 6.43 µg/m3, whereas average value varies are in

range of 2.30 to 5.50 µg/m3, which is much lower than that of the NAAQ standard

(80 µg/m3).

Mercury

Mercury concentration was not detected at any of the monitoring locations in the

study area. Thus it can be concluded that the environment in the study area was free

from mercury (Hg).

Ozone

The Ozone (O3) concentration at all the monitoring locations within the study area

varies between 11.22 µg/m3 to 12.20 µg/m3.

During operation phase the major air pollution creating source will be the stack

attached to the gas engine. The details of the stacks are as given in the table#8

below:

Page 13: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 13

Table 8 : Details of Stack

Parameter Value Considered Configuration of the set (GT+ST) 420 MW(275+145) Number of sets 3 Fuel Natural Gas Sulfur content Traces Flue gas quantity 22,05,000 Kg/hr

475 Nm3/sec Flue gas temperature 103OC (376OK) Stack diameter 6.5 m Stack height 60 m Flue gas exit velocity at stack tip 18 NOX emissions from each stack 50 ppm v/v at 15% O2

100 mg/Nm3 47.5 grams/sec

Number of stacks 3 Approximate Distance Between two stacks 75 m

Air quality (ISCST-3 model) modelling was done in order to evaluate NOx incremental

short-term concentrations due to proposed project. These results are based on the

considering the main stacks. The above data were used as input data for the

modelling purpose.

The incremental increase in the concentration of pollutants is given in the table

below with superimposing the same on the existing baseline data.

Table 9 : Resultant Concentrations Due To Incremental GLC

Pollutant Incremental

Concentration

g/m3

Baseline

Concentrati

on

g/m3 *

Resultant

Concentrati

on g/m3

Distance

w.r.t.

centre

km

Direction

w.r.t.

centre

NOx 5.629 20.02 25.64 2.78 NE

Mitigation measures

Adequate stack heights will be installed for proper dispersion of the pollutants.

Regular water sprinkling will be done for suppression of dust particles. Internal roads

will be concreted to prevent fugitive emission.

Page 14: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 14

7.3 WATER ENVIRONMENT

Baseline data

The existing water quality of surface and ground water in the study area was

evaluated. Samples were collected from the surface water (village ponds) in the

nearby region around 10 Km radius of the project site. Ground water samples from

the existing bore wells were collected. Total 6 nos. of sample for ground water and 9

nos. of sample for surface water were evaluated.

Ground water

To evaluate the ground water quality in the study area six bore wells were selected

from nearby villages of the project site. From the analytical results it was found out

that TDS level near the project locality is very high; except at one well location in

Vaghel village having TDS value of 240mg/L, which is due to its location in close

proximity to the large village pond and there is possible recharge from this well.

TDS level from other wells are varying from 1410 mg/L to 4188 mg/L. with the

highest at one well sampled in Aritha village, which is clearly indicating high saline

ground water in this region . The chloride level, and Conductivity are also supporting

the high saline ground water conditions in the study area, which were found to be

varies between 851 mg/L to 2269 mg/L and 3280µS/ to9740 µS respectively, but at

the well located at Vaghel village Chloride content and conductivity level was found

to be only 56.72 mg/L and 560 µS due to the recharge from the large village pond.

Fluoride content was found out at all the wells, sampled except one at Aritha village.

The fluoride level was varying from 0.72-1.07 mg/. Mercury level in all the sampled

wells was below the detectable limit.

Surface water

In order to evaluate the surface water quality of the study area, nine village ponds

were sampled. The surface water quality of these rain water fed ponds are of good

quality water with the TDS level varying from 86-680 mg/L, with maximum at one

pond in Harij village. The total alkalinity varies from 140 mg/l to 380 mg/l with

maximum at Harij village. Chloride level was varying from 16.07 – 284 mg/L with

maximum at Harij. Sulphate content was detected only in two ponds sampled.

Page 15: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 15

Nitrate content of the pond at harij was slightly higher with 33.82 mg/L. which may

be due to the agricultural runoff or other anthropogenic activities in/from the

surrounding areas of this pond. The analytical result indicates the availability of good

quality surface water in this region.

The detail water balance diagram for the project showing the water consumption in

various plant activities and waste water generation from the project is as given in

Figure below.

7.4 Waste water Generated

Effluents from the main plant drains, oily waste, etc. would be treated in the local

treatment facilities provided within the respective plants and recycled wherever

possible. Oily waste would be treated using oil separator/skimmer. Oil separator

would be designed for treating the run-off water in the oil facility area during

rainstorm. Clear water would be led to sump.

.

Page 16: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 16

Table 10 : From Power plant Quantity of waste water generated Water Demanding Center Wastewater Discharge

m3/day Recycling m3/day

Cooling Tower as make-up 7416 Equipment cooling - HVAC make up 0 Miscellaneous/Floor washing 120 Sanitation 80 Filtered water to RO plant DM plant Boiler make up

888 168 RO reject

8424 168

From Colony and domestic uses During project operation, the facility will employ about 250 workers. In order to cater

to the need for the residential needs of the direct & indirect employees, it has been

proposed to develop a colony for the plant workers. Colony will consist of about 250

houses.

Table 11 : Quantity of Domestic waste water generated

Water

requirement

Source Waste water

generated

Treatment

option

120 m3/Day Filtered water 80 m3 STP

Impact study with mitigation measures

It has been estimated that about 8424 m3/day of wastewater will be generated from

the proposed power plant and about 80 M3/ day STP treated water from colony and

plant premises. 80 m3/day STP treated waste water would be utilized for plantation

and green belt in the plant/ colony area. An attempt was being made to explore the

possibility of recycling and reuse of the excess wastewater generated by RO

treatment. In this way about 5054 m3/Day can be recycled back to the system. Only

about 3370 m3/day RO reject has to be reused in green belt and landscape

development. Blow down from Cooling tower System can also be used as makeup to

Plant service water and as well as makeup supply to Fire water storage tanks. Excess

CW blow down water shall be led to the Guard pond. Provision shall be made for

diverting complete Cooling tower blow down water to the Central Guard pond which

can be recycled or reused after RO treatment. Blow down drain from HRSG/Power

Page 17: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 17

Cycle, and other Condensate drains etc. which are relatively of pure quality shall be

collected in central guard pond and shall be reused or recycled on continuous basis.

Total land available for the project is about 226 Acres. About 101.56 Acre land

demarcated for greenbelt development and landscape within the plant premises.

Rainwater Harvesting

Geologically the area study area comprises of Alluvium soil. It comprises of

alternate beds of sand, clay and Kankar. It has been proposed to adopt Rainwater

Harvesting system in the proposed project by adopting storm water collection and

reuse program during monsoon period. Rainwater harvesting structure shall be

provided to recharge the groundwater resources in the region. During monsoon

period, the runoff water from the roof of the structure and paved areas shall be

collected through storm water drainage system and initially led to underground raw-

water storage and surplus water in the rain water harvesting structure. With an

average monthly rainfall of about 128.8 mm/month (~12.8 mm/day with 10 rainy

days) during peak monsoon period, it has been estimated that about 6000 to 10000

m3/day of runoff would be generated from the project. With a raw-water reservoir

capacity of 2, 39,568 m3, significant quantities of run-off from the plant site can be

stored and reused for plant cooling applications. Several recharge well will be located

at strategic locations within the plant and will be interconnected to the storm water

drain network system. This will ensure the recharging of the ground water table. The

ground water table at the project site is 5.3 m and as the site is closely located

Narmada Canal Command Area. As per the hydro-geological information available for

the project site, the ground water in and around the study area is mainly confined in

unconfined and semi confined conditions.

7.5 NOISE ENVIRONMENT

Baseline data

The noise generation at the site and in the surrounding areas was mainly due to

vehicular transportations and normal village activities. Due to crop cutting season in

nearby field and new road making activities the noise level was slightly higher in

some locations; however all these activities are of temporary in nature.

Page 18: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 18

Impact study

During the construction phase the major noise generation will be from the

mechanical equipment installed at site for the construction work and noise due to

vehicular movement.

During operation phase the major noise generation will be from the mechanical

equipments at the plant site mainly gas engine and compressors.

Mitigation measures

Noise generating equipment shall be place in enclosed area equipped with silencers.

The operators working in the high-noise areas shall be strictly instructed to use ear-

muffs/ear-plugs.

Green belt shall be developed to attenuate noise and the extent of green belt shall

be as per CPCB guidelines.

Training of personnel is recommended to create awareness about the damaging

effects of vibrations; if PPEs are not used as regular practice while on duty.

Regular noise monitoring on weekly basis will be carried out at the noise generating

sources and the entry - exit gates of the plant.

7.6 FLORA AND FAUNA

No threatened flora and fauna observed in the study area.

7.7 LAND ENVIRONMENT

Table 12 : Details of the satellite imagery

Satellite -Sensor Path/Row Date Band

IRS-P6 LISS III 092/055 15th March, 2010 2345

The land use of the study area surrounding 10 Km from the proposed project site is given in the figure & table below:

Page 19: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 19

Table 13 : Land use/cover Categories Area Statistics within study area

Sr. No.

Categories % of area in 10 Km radius

Area (sq.km.)

1 Agriculture 87.72 307.23

2 Habitation 2.58 30.03

3 Scrub 8.57 9.02

4 Water Body 0.52 1.81

5 Industrial Area 0.15 1.61

6 River 0.46 0.54

Page 20: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 20

8 GREEN BELT DEVELOPMENT

In order to reduce the pollutant dispersion in the atmosphere, to resist the noise

generated due to plant activity and to uptake the wastewater generated to some

extent, it is recommended to develop green belt around the periphery of the plant

road side area. The total green belt area proposed to be developed is about 101.56

acres which is about 45 % of the total plot area. It is proposed to develop green belt

of about 50 meter width, consisting of three tiers of trees species, around the project

boundary with a tree density not less than 2500 tress per hectare. It also entrusted

to maintain at least 75 % survival rate. In addition to development of green belt

within the premises the company is committed to carry out afforestation and

biodiversity improvement programme in the surrounding villages.

9 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

The risk associated with proposed plant is analyzed by PHA (preliminary hazard

analysis and MCA (maximum credible Accident) for each hazard identified. The

major risks are fire and explosion associated with leakage of the natural gas as well

as toxic release due to leakage of chlorine from the tunner.

JET FIRE SUMMARY: Scenario Damage Distances in meters

Stability class: D

4 Kw/m2 12.5 kw/m2 37.5 kw/m2

FULL BORE RUPTURE OF NATURAL GAS PIPELINE 236 131 65 Vapor Cloud Explosion summary:

Scenario Damage Distances in meters Stability class: D

1.0 PSI 3.5 PSI 8.0 PSI

FULL BORE RUPTURE OF NATURAL GAS PIPELINE 3300 2000 1900

Chlorine dispersion summary: Scenario Damage Distances in meters

Stability class: D

0.5 ppm 2 ppm 10 ppm

LIQUID CHLORINE LEAKAGE IN CASE OF VALVE FAILURE 7400 4500 2300

Page 21: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 21

9.1 SAFETY MEASURE PLAN

a. Natural and chlorine gas detector and Explosion control system. Means of

shutting off the fuel supply.

b. Starting sequence of turbine should include a purge cycle adequate to

ensure a nonflammable atmospheric in the turbine and exhaust system

prior to ignition. Corrosion resistant equipment / pipes shall be installed.

c. All emergency and safety related equipment must be frequently and

regularly checked and maintained to ensure that their condition is

satisfactory. Records should be kept all checks and maintenance carried

out on this equipment.

d. The necessary first-aid equipment shall include emergency showers and

eye wash facilities.

e. Automatic sprinklers shall be installed.

f. The fire fighting media shall be selected according to their mode of action

and their use in combating or preventing the spread of fire. Portable and

mobile fire extinguishers such as pressurized water type, CO2 type, foam

type etc. shall be placed at strategic location throughout the plant area.

g. Extinguishers should be fitted with means to provide visual indications that

the unit has partially or wholly been discharged.

A fire detection alarm and automatically fire extinguishing system

from control room, other un-manned electrical and electronic room

etc. shall be provided.

Hydrant system covering entire power station area shall be provided

(pressurized pipe).

Automatic HVW/MVW spray shall be provided for transformers, cable

galleries, cable vaults, turbine lube oil system etc.

Activation of the system shall be automatic.

h. OFF site and ON site Emergency plan shall be followed strictly.

i. All the potential occupational hazardous work places such as Chlorine

storage area areas will be monitored regularly. The health of employees

working in these areas will be monitored once in a year for early detection

of any ailment due to exposure to hazardous chemicals.

Page 22: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 22

10 SOCIO ECONOMIC ENVIRONMENT

Baseline data

Villages located in the study area comprising of 10 Km radius of the project site were

taken into consideration for the detailed study of socio economic structure.

The demographic details have been abstracted from Primary Census Abstract 2001

(CD) of Patan. The salient demographic features of the study area as follows:

Table 14 : Summary of Demographic structure

No. of district 1

No. of Taluka 4

No. of Villages 26

Total no. of house hold 12491

Total no. of population 64196

Main workers 21449

Marginal workers 7442

Non workers 35305

Sex ratio 909

11 CORPORATE SOCIAL RESPONSIBILITY AND COMMUNITY DEVELOPMENT PROGRAMS

The proposed power project will provide employment to about 250 persons

during its operation. The proposed project will improve the overall power quality and

will support the economic development in the region.

In line with the TOR approved by MoEF for the proposed project, the project

proponent is committed to implement social welfare measures as part of Corporate

Social Responsibility plan as the part of the proposed project. CSR Plan for the

proposed project has been prepared in consultation with stakeholders, Local

villagers, Block development officer, Sami Taluka, District Collector, Patan and is

being submitted as an Annexure 8 along with this report. Project Proponent has

proposed to implement various community development programs at a cost of Rs

15.5 Crores and prepared a Corporate Social Responsibility Plan for the project,

Page 23: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 23

which will help to enhance the economic and cultural environment in the nearby

villages.

12 CLEANER PRODUCTION DETAILS

The company will make use of natural gas which is one of the cleanest

sources of fuel available for power generation.

The waste water generated will be reused completely within the premises.

There won’t be any discharge of the effluent on surface or ground water.

As it is gas based power plant there won’t be generation of any solid waste.

Good housekeeping will be kept within the premises

The equipment will be maintained and service regular to work efficiently.

Air – fuel ratio is altered i.e. more air provided for complete combustion and

there will be reduction in the NOx formation and emission from the stack.

Use of solar energy will be made wherever possible. Food preparation will be

done in canteen using solar cookers. Electricity to light canteen, parking

zone, office area will be generated vide solar energy. Solar heater will be

installed at company guest house.

13 ENVIRONMENT MANAGEMENT SYSTEM

A full fledge environment management cell shall be created as the part of project

with the necessary support infrastructure to strengthen and implement the effective

Environment Management system for the project.

14 ENVIRONMENT MONITORING PLAN

The main attributes for which monitoring shall be carried out are as below:

1. Ambient air Quality

2. Stack Emission

3. Wastewater Quality

4. Noise Level

5. Hazardous Waste

Page 24: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 24

15 CONCLUSIONS

After carrying out the Environment Impact Assessment studies, it has been

concluded that by adopting a robust environmental management plan and risk

mitigation measures as presented in the EIA report, the proposed project would

exhibit very insignificant environmental impacts. However, the implementation of

proposed massive plantation, green belt area and community development programs

under CSR activities would bring significant positive impacts to the entire region.

Page 25: EXECUTIVE SUMMARY DRAFT EIA Report · Vaghel village, in Sami taluka of Patan District, ... All the facilities like main power block with 400 kV switchyard, Water Reservoir, Water

Detox

Executive summary for DMICDC Vaghel Power Company Limited 25

Figure 3 : Bolero canal branch

Figure 4 : Proposed project site