Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all contributors In particular: K.Fuchsberger, S.Fartoukh, V.Mertens, J.Uythoven, M.Barnes, E. Carlier, W.Bartmann, C.Hessler, L.Jensen, R.Jones, M.Lamont, R.Giachino, G.Mueller, S.Redaelli, W.Herr, F.Schmidt, OP crews on shift…
20

Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Dec 29, 2015

Download

Documents

Henry Caldwell
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

1

LHC Injection and transfer lines

Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger

On behalf of all contributorsIn particular: K.Fuchsberger, S.Fartoukh, V.Mertens, J.Uythoven, M.Barnes, E. Carlier, W.Bartmann, C.Hessler, L.Jensen, R.Jones, M.Lamont, R.Giachino, G.Mueller, S.Redaelli, W.Herr, F.Schmidt, OP crews on shift…

Page 2: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

2

Scope

1. LHC transfer lines – 2009 optics studies• Trajectory• Dispersion• Kick response• Aperture

2. Injection regions• Injection steering• MKI wave form• Injection protection• Injection aperture

3. List of subjects to follow-up

Page 3: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

3

1- LHC Transfer line

Transfer line BPMs:

- calibration performed and included in the measurements -Rhodri, Lars and team + essential data from kick response measurements (Kajetan)

- request for additional BPMs upstream of TT60 – hidden trajectory bump – available for 2011 start-up

- more robust dispersion measurements in TI 8 thanks to the dual plane reading and the additional BPMs in the LHC injection area in TI 2, same improvements will be available for the 2011 start-up – BI teams

Main outcomes from all transfer line beam time measurements – trajectory, kick response and dispersion measurements:

Page 4: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

4

Trajectory examples

TI 8 bare trajectory

TI 8 corrected trajectory -few correctors, <20 rad

Page 5: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

5

Transfer line magnetic model: • TT60 MBE CC switched to MBB – vertical bare trajectory as expected• MQIs DK/K = ~1.006

• MQI measurements by magnet group• MBI sext. component of ~ -4.5e-4 @ r=25mm (idea from S.Fartoukh)

• Confirmed by magnet group from 2D calculations• MBI quad. component of ~1.35e-4 @ r=25mm

• Feed-down from systematic horizontal offset in MBI

NominalIdem + Dk/k+b2+b3

Idem + initial cdts

Rematched optics with b2,b3 componentsanduse new MQI CC

Page 6: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

6

Kick response measurements – TI 8 - V plane – Before rematching~ 0.7% over-focussing in vertical plane apparent cf model

Kick response measurements – TI 8 - V plane – After rematching

Courtesy: Kajetan

Page 7: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

7

TI 8 1st and 2nd order dispersion

with rematched optics

Dx

D’x

Page 8: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

8

TI 2 and TI 8 aperture studies

- Momentum aperture: +/- 0.35 to 0.4%, as expected.

- Physical aperture explored in both lines in H and V, at different phases, 30 deg intervals, using on-line model and dedicated knobs

Page 9: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

9

0

5

10

15

20

25

0 60 120 180 240 300 360Measurement phase [deg]

50%

tran

smis

sion

[si

gma]

.

T I2 aperture V [s]

T I2 aperture H [s]

In both planes in both lines:

-No bottlenecks Note: aperture restriction between P8 MSI and Q5 solved after re-alignments

- Measured aperture ≥10 nominal

Few phases in TI 2 to complete

Page 10: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

10

2- Injection region

• Injection steering• Injection region aperture• Kick response – dispersion measurements• MKI waveform• TDI and TCLIA/B setting up around orbit, LHCb BeamCdtMonitor, setup of TDIs to

golden orbit – see Wolfgang’s talk• Checked losses on TDI & IR8 for MKI off/over-injecting – see Christos’ talk• Tests of injection and matching with xing/sep bumps on – see Werner’s talk• Injection kicker timing in• Injection of multiple bunches• …

Much injection checks and setting-up work performed through the LHC beam commissioning

Page 11: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

11

TI 2-TI 8 Steering

11

TI 2+S23 and TI 8+S78 selections of the steering display now by default:

o TL trajectory

o Ring First turn - Closed orbit = injection oscillation

Closed orbit is estimated from average of 50 first turns

>> ensures that TL steering always brings beam onto the CO

FT-COTrajectory

Page 12: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

12

Injection Autopilot

12

Feedback tools inside steering program to correct injection oscillations:

o Same tool used for SPS injection oscillations & SPS target steering.

o Manually activated.

o Algorithm can be configured (DB). Presently:

Fit a betatron oscillation to the ring FT-CO

(in H subtract dp/p error).

Interpolate fit to a virtual start point (pos + angle).

If pos/angle out of tolerance, correct

with 2 correctors at end of line.

>> tested & works well !

May need to tune algorithm because of TL collimation.

o Global MICADO (towards ref) better?

>> need more experience !

Page 13: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

13

Kick response measurements -1

Data in very good agreement with model. All measurements were done at deltap/p = - 0.5 permil. Figures show a comparison between measurements (blue) and model (red). Beam from left.

H plane

V plane

Courtesy Kajetan

Page 14: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

14

H+V response of horizontal kicker MCIAH.80204 for TI8 and LHC sector 78.

Kick response measurements -2

H+V response for vertical kicker MCIAV.80704 for TI8 and LHC sector 78. Vertical (blue background) couples to horizontal (red background)

Courtesy Kajetan

Page 15: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

15

Point 2 / 8 TDI and TCLIA/B setting up

• Transfer line protection devices: setting up partially done

• TDI / TCDI : done– See Wolfgang Bartmann presentation

Page 16: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

16

MKI 2 and 8 waveform measured

Looks OK except for 2% overshoot, both MKI2 and 8 – being corrected

Courtesy M.Barnes

MKI8%

-10

0

10

20

30

40

50

60

70

80

90

100

110

65000

66000

67000

68000

69000

70000

71000

72000

73000

74000

75000

76000

77000

78000

79000

80000

81000

82000

83000

84000

85000

Delay (ns)D

efle

ctio

n (

%) MKI8%

97.0

97.5

98.0

98.5

99.0

99.5

100.0

100.5

101.0

101.5

102.0

102.5

103.0

75000

76000

77000

78000

79000

80000

81000

82000

83000

84000

85000

Delay (ns)

Def

lect

ion

(%

)

Page 17: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

17

Injection kicker timing in

Beam1 Beam2

• Both beams timed in– Adjusted with OASIS signals

– Configured for abort gap keeper

– Checked beam injected OK with acceptable oscillations

– Need to check the fine timing to fit full SPS batch

Page 18: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

18

Multiple bunch injection (and fixes)

• 4 bunch injection sequences worked after timing in MKI and MKD

• Need to be aware that injecting near to abort gap needs consideration – bunch is always at the head of the injection kicker

pulse – always 11 s gap as result after last bunch– may need to reorder some injection sequences,

especially with ‘trailing pilot’ – may need to change order of injection for some

bunches.• Setting up of protection devices to (re)do for high

intensity

Page 19: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

19

• Transfer lines: Importance of:– Regular survey checks and re-alignment– Steering with minimum corrector number and strength– Accurate characterisation of the main magnets– Noise on QPS from TF pulsing? Worry about other EMC sources

around ring?

• Injection region:– FT-CO evaluation is presently based on FIFO acquisition:

• Works only when injecting into EMPTY ring.– To be able to work on ANY injection (also with circ. beam):

• FT-CO from capture data. Code written – needs testing.• Capture data must be automatically configured and enabled to trigger

on the buckets corresponding to the injected bunches (>> injection sequencer).

– ‘Interference’ with PC interlocks of TLs:• Corrector interlock margin presently +- 10 rad (from CNGS

experience).• Must find a compromise between protection (small tol.) and steering

flexibility (larger tol.). Note that shift crews have the right to change the corrector reference settings (not the tolerance).

3- List of subjects to follow-up

Page 20: Evian LHC BC workshop 19-20 January 2010 1 LHC Injection and transfer lines Malika Meddahi, Brennan Goddard, Verena Kain, Jörg Wenninger On behalf of all.

Evian LHC BC workshop 19-20 January 2010

20

• Injection region (cont’d):

– Still investigate how to over-inject without interlocking• Puzzle of losses in P8 on MQX – issue of BLM range

– Fine synchronisation of injection kicker pulse to bucket 1

– Setting up of TCDIs and TCLIA/Bs

– Losses on TCDQ/TCSG for B1 at injection– (more) checks to make

– BQM information for IQC – to be made operational

– Injection sequences to revisit with ‘trailing pilot’ • May need to change order of injection for some bunches.

• Need adequate (re)commissioning time