EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s ACEG-MATRACON (JV) (M/s Anhui Construction Engineering Group Co., Ltd. in Joint Venture with M/s Matracon Pakistan (Pvt.) Ltd.) 1 1. Any other additional/ supporting information,the procuring agency may like to share: *Award will be subject to final approval by theNHA Executive Board. Generr,' -o'"qger (P&'CA) offrciar Stamp: ., ..... Natt$,. i;fif:#.ltuthoritv **Standard Bidding Documents (SBD) I Name of Procuring Agency: National Hiehway Authority 2. Method of Procurement: Sinele StaseTwo Envelope Procedure 3. Title of Procuredrent: Dualization of Indus Highway (N-55), Package-Il: Karak to Kohat (Km 60+846 - Km 127+349) 4. Tender Inouirv No.: 2@90 -0D IGM(P&CA)A{HA/20 1 7/ 5. PPR.A. Ref.No. 0SE): TS315691E 6. Date-& Timeof Bid Closins: l7'nJulv 2017 at I 100 hours local time 7. Date & Time of Bid Opening: 17'n Julv 2017 at 1130 hours localtime 8. No. of Bids Received: Six (06) 9. Criteria for Bid Evaluation: Criteria of Bid Evaluation is attached at Annex-I. 10. Details of Bid(s) Evaluation: As below Sr. No. Name of firm Technical (if npplicable Financial (if rpplicable) Evaluated Cost (Rs.) Rule / Regulation / SBD** / Policy/ Basis for Rejection / Acceptance asper Rule 35 of PP Rules.2004. (i) M/s ACEG-MATRACON (JV) Qualified Price Bid opened 1r,945,666,748 * Itt Lowest (iD IWsESER-SMC (JV) Qualified Price Bid opened 13,152,628,355 2nd (iiD M/s Frontier Works Organization r Qualified Price Bid opened 13,250,980,101 rrd J (iv) M/s LIMAK-ZKB (JV) Qualified Price Bid opened El3'792,301,725 4th (v) M/s SMADB _ SACHAL - usMANr - sEC (JV) Dis- Qualified Price Bid not opened PPRA Rule 36 (b) (v) (vi) M/s National Logistics Cell (NLC) Dis- Qualified Price Bid not opened -do-
31

EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s

Aug 21, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s

EVALUATION REPORT(As per Rule 35 of PP Rules,2004)

Lowest Evaluated Bidder: M/s ACEG-MATRACON (JV)(M/s Anhui Construction Engineering Group Co., Ltd. in JointVenture with M/s Matracon Pakistan (Pvt.) Ltd.)

1 1. Any other additional / supporting information, the procuring agency may like to share:*Award will be subject to final approval by the NHA Executive Board.

Generr,' -o' "qger (P&'CA)

offrciar Stamp: .,.....Natt$,. i;fif:#.ltuthoritv

**Standard Bidding Documents (SBD)

I Name of Procuring Agency: National Hiehway Authority2. Method of Procurement: Sinele Stase Two Envelope Procedure3. Title of Procuredrent: Dualization of Indus Highway (N-55), Package-Il: Karak

to Kohat (Km 60+846 - Km 127+349)4. Tender Inouirv No.: 2@90 -0D IGM(P&CA)A{HA/20 1 7/5 . PPR.A. Ref. No. 0SE): TS315691E6. Date-& Time of Bid Closins: l7'n Julv 2017 at I 100 hours local time7. Date & Time of Bid Opening: 17'n Julv 2017 at 1130 hours local time8 . No. of Bids Received: Six (06)9. Criteria for Bid Evaluation: Criteria of Bid Evaluation is attached at Annex-I.10. Details of Bid(s) Evaluation: As below

Sr.No.

Name of firmTechnical

(ifnpplicable

Financial(if

rpplicable)

Evaluated Cost(Rs.)

Rule / Regulation/ SBD** / Policy /

Basis forRejection /

Acceptance as perRule 35 of PPRules.2004.

(i)M/s ACEG-MATRACON(JV) Qualified

Price Bidopened

1r,945,666,748 * Itt Lowest

(iD IWs ESER-SMC (JV) QualifiedPrice Bidopened

13,152,628,355 2nd

(iiD M/s Frontier WorksOrganization r

QualifiedPrice Bidopened

13,250,980,101 r r dJ

(iv) M/s LIMAK-ZKB (JV) QualifiedPrice Bidopened El3'792,301,725

4th

(v)M/s SMADB _ SACHAL- usMANr - sEC (JV)

Dis-Qualified

Price Bidnot opened

PPRA Rule36 (b) (v)

(vi)M/s National LogisticsCell (NLC)

Dis-Qualified

Price Bidnot opened

-do-

Page 2: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s

oAnnex-l

GOVERNMENT OF PAKISTANMINISTRY OF COMMUNICATIONS

NATIONAL HIGHWAY AUTHORITYProcurement & Gontract Administration Section

28-Mouve Area, G-9/1, lslamabad.Tel: 051 -9032727, Fax: 051 -9260419

teifxo,-r ri$r.a.Ars

Page 3: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 4: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 5: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 6: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 7: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 8: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 9: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 10: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 11: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 12: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 13: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 14: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 15: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 16: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 17: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 18: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 19: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 20: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 21: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 22: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 23: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 24: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 25: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 26: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 27: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 28: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 29: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 30: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s
Page 31: EVALUATION REPORT - National Highway Authoritynha.gov.pk/wp-content/uploads/2018/01/Evaluation... · EVALUATION REPORT (As per Rule 35 of PP Rules,2004) Lowest Evaluated Bidder: M/s