This programme is co-financed by the European Union and the Republic of Turkey 1 EU-TURKEY CHAMBER FORUM II EU-TURKEY CHAMBER FORUM II GRANT SCHEME GRANT SCHEME PROJECT FINANCIAL REPORTING PROJECT FINANCIAL REPORTING 2 July 2013 2 July 2013 Burcu Atılgan-Grant Expert Burcu Atılgan-Grant Expert TOBB EU Department TOBB EU Department
32
Embed
EU-TURKEY CHAMBER FORUM II GRANT SCHEME PROJECT FINANCIAL REPORTING 2 July 2013
EU-TURKEY CHAMBER FORUM II GRANT SCHEME PROJECT FINANCIAL REPORTING 2 July 2013 Burcu Atılgan-Grant Expert TOBB EU Department. Project Documentation and Accountancy Reporting Requirements Monitoring and Support Activities. Content. PROJECT DOCUMENTATION AND ACCOUNTANCY. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
This programme is co-financed by the European Union and the Republic of Turkey
1
EU-TURKEY CHAMBER FORUM II EU-TURKEY CHAMBER FORUM II GRANT SCHEME GRANT SCHEME
Burcu Atılgan-Grant ExpertBurcu Atılgan-Grant ExpertTOBB EU DepartmentTOBB EU Department
This programme is co-financed by the European Union and the Republic of Turkey
2
Content
• Project Documentation and Accountancy
• Reporting Requirements
• Monitoring and Support Activities
This programme is co-financed by the European Union and the Republic of Turkey
3
PROJECT PROJECT DOCUMENTATION AND DOCUMENTATION AND
ACCOUNTANCYACCOUNTANCY
This programme is co-financed by the European Union and the Republic of Turkey
4
DOCUMENTATION AND ACCOUNTANCYFinancial documentation
Expenditure Documents
All expenditure
Proof of purchase such as invoices and receipts
Proof of payment such as bank statements, debit notices, proof of settlement by the contractor
Proof of delivery of services such as approved reports, proof of attending seminars, conferences and training courses (including relevant documentation and material obtained, list of attendees, certificates), etc
The Beneficiary Accounting records (computerised or manual) such as general ledger, sub ledgers and payroll accounts, fixed assets registers and other relevant accounting information
This programme is co-financed by the European Union and the Republic of Turkey
5
DOCUMENTATION AND ACCOUNTANCYFinancial documentation
Human Resources
CVs of all experts,Contracts, Staff and payroll records, Salary statements,Monthly time-sheets (prepared in detail, signed by the experts and the representative of the Grant Beneficiary) of all project staff, Bank statements/receipts for payments,Per diem ledgers.Board Decision if the staff of the Beneficiary and/or Partners assigned to the Action
This programme is co-financed by the European Union and the Republic of Turkey
6
Travel
Public transport: Transport tickets (including boarding passes in case of travel by air)
Rented transport: Invoice from supplier and summary list of distance covered
Car: For fuel and oil expenses, a summary list of the distance covered, the average fuel consumption of the vehicles used, fuel costs.
DOCUMENTATION AND ACCOUNTANCYFinancial documentation
This programme is co-financed by the European Union and the Republic of Turkey
7
DOCUMENTATION AND ACCOUNTANCYFinancial documentation
Expenditure Documents
Subcontracted supplies or services
Proof of procurement procedures such as tendering documents, bids from tenderers and evaluation reports, Proof of commitments such as contracts and order forms, Proof of receipt of goods such as delivery slips from suppliers, Certificate of origin, Pictures and/or video records of the events, Attendance sheets, etc.
This programme is co-financed by the European Union and the Republic of Turkey
8
Technical documentation
• Examples of project documents for some of the project activities.Surveys /studies • ReportsPublications • Copies of publicationsSeminars, conferences, working meetings • Programme • List of presentations / conference reports• Handouts• List of participants• List of speakers• Minutes (if applicable)• Press clippings• Feed-back questionnaires (if applicable)
This programme is co-financed by the European Union and the Republic of Turkey
9
• Technical documentationTraining • A detailed description of the training – training modules, training
hours per subject, methods, etc.• Training schedule• List of participants /Attendance sheets• List of trainers / lecturers• Feed-back questionnaires• Training evaluation reportExperts• Timesheets• Copies of the outputs • Activities reports
This programme is co-financed by the European Union and the Republic of Turkey
10
Accounting requirements Aappropriate accounting and double-entry book-
keeping system Accounts and expenditure should be • easily identifiable and verifiable separate
accounts for the action • a simple accounts ledger together with other
useful templates.
This programme is co-financed by the European Union and the Republic of Turkey
11
DOCUMENTATION AND ACCOUNTANCY
Accounting requirements
The Financial Report should be properly and easily reconciled to the Grant Beneficiaries accounting and bookkeeping system.
This programme is co-financed by the European Union and the Republic of Turkey
12
REPORTING REQUIREMENTS
This programme is co-financed by the European Union and the Republic of Turkey
13
REPORTS
•Final narrative and financial report •Expenditure verification report
This programme is co-financed by the European Union and the Republic of Turkey
14
FINAL NARRATIVE REPORT • Narrative section: Project activities/management,
participation of partners, relations with key stakeholders, visibility, progress on performance indicators, assessment of the project and notifications about minor contract changes and addenda
• Templates for the final narrative report is provided in
www.etcf.org.tr
This programme is co-financed by the European Union and the Republic of Turkey
15
FINAL NARRATIVE REPORT
• You should prepare the final report in 4 hard copies an 4 CD:
- 2 copies to SU
- 1 copy to EUD
- 1 copy for their records
• SU will send one copy of the reports to the CFCU
with a cover letter and the checklist
This programme is co-financed by the European Union and the Republic of Turkey
16
Within 1 month following the completion of the project the GB should send it to the SU for checks.
• Within 3 months following the completion of the project the report should reach the CFCU.
This programme is co-financed by the European Union and the Republic of Turkey
17
• Minor /major change requests and CFCU’s approval letters• Copy of the printed materials• Contracts (supply/service), invitation letters, tender offers
(applications), letters to unsuccessful tenderers, evaluation reports• Visibility material samples • “Performance Indicators Documents”• Training/conference/visit programmes, reports, participants list
(Annex3)• For the external experts -Training/conference reports, presentations,
surveys• Copy of the “transfer of title of equipments”( Ekipman Mülkiyet Devri
Belgesinin kopyası)(Before the approval of the notariate) (Annex 4)
This programme is co-financed by the European Union and the Republic of Turkey
18
FINAL FINANCIAL REPORT
•The bank letter indicating that no interest rate has been applied to the project account and account summary that indicates that the account covers only the project implementation period.
•“Project Expenditure Summary” and “Account Ledger”
This programme is co-financed by the European Union and the Republic of Turkey
19
Human Resources Expenditure List For every project expert: • CVs of all experts, • Contracts, • Staff and payroll records, • Salary statements, • Monthly time-sheets (prepared in detail, signed by the experts and the
representative of the Grant Beneficiary) of all project staff, • Bank statements/receipts for payments, • Per diem ledgers. • Board Decision if the staff of the Beneficiary and/or Partners assigned to the Action
This programme is co-financed by the European Union and the Republic of Turkey
20
Travel and perdiems Expenditure List • Transport tickets (including boarding passes in case of
travel by air)• Related with per diems: Hotel invoices or the copy of
the documents that indicates the round trip dates• The copy of the document indicating that the per diems
payments are made
This programme is co-financed by the European Union and the Republic of Turkey
21
Equipment Expenditures List
For every equipment in a separate dossier:
Invoice or the document that indicates the payment is
made to buy the equipment.
Certificate of the Origin, Contract, market survey document
This programme is co-financed by the European Union and the Republic of Turkey
22
Local Office Expenditure List
Copies of the invoices of vehicle costs, office rent, consumables - office supplies, other services (tel/fax, electricity/heating, maintenance), contract or payment document
This programme is co-financed by the European Union and the Republic of Turkey
23
Other costs, services expenditure list:
Expenditures documents (invoices and an explanation letter indicating the aim of the contract) for :
This programme is co-financed by the European Union and the Republic of Turkey
24
Expenditure Verification Report by
External Auditor
This programme is co-financed by the European Union and the Republic of Turkey
25
EXPENDITURE VERIFICATION REPORT
Consist of:
• TOR for an Expenditure Verification of a EC financed Grant Contract for External Actions- should be completed by the (Grant) Beneficiary and be agreed with the Auditor
Annex 1: Information about the Subject of the Expenditure Verification
Annex 2: Scope of Work – Procedures to be performed• 2. Report of Factual Findings for an Expenditure Verification of an
EC financed Grant Contract for External Actions-should be provided by the Auditor
The template can be found at www.etcf.org.tr
This programme is co-financed by the European Union and the Republic of Turkey
26
PAYMENT PROCEDURES
• Pre-financing: %80 of the sum is paid within 45 days of receipt of the Request for Payment (by CFCU)
• Final payment: CFCU’s 45 day approval procedure of the final narrative and financial reports, Expenditure Verification Report and the Request for Payment
This programme is co-financed by the European Union and the Republic of Turkey
27
MONITORING MONITORING AND SUPPORT AND SUPPORT
ACTIVITIESACTIVITIES
This programme is co-financed by the European Union and the Republic of Turkey
28
MONITORING FRAMEWORKMONITORING FRAMEWORK
In Procedures,• Compliance with procurement rules• Eligibility of costs• Compliance with publicity and visibility rules• Documentation and Archiving• Bookkeeping and Accountancy• Reporting obligations• Contract Modifications• Non-Compliances and IrregularitiesIn Progress,• Financial and Technical progress • Performance indicatorsand Problems And Needs of the beneficiaries
This programme is co-financed by the European Union and the Republic of Turkey
29
MONITORING FRAMEWORKMONITORING FRAMEWORK
Monitoring tools: Monitoring visits, declaration reports and final report.
Monitoring visits will be conducted by SU using checklists, monitoring reports etc.
SU experts will review and give advice on draft notification letters, addendum requests and final report.
Monitoring and/or Spot visits by CFCU
This programme is co-financed by the European Union and the Republic of Turkey
30
MONITORING RESPONSIBILITIES OF GBsMONITORING RESPONSIBILITIES OF GBs
To make key staff of project be present.To provide up-to-date informationTo define performance indicatorsTo define needsTo clarify major dates in procurementTo inform SU in case of unavailabilityTo archive all documents for 7 years
This programme is co-financed by the European Union and the Republic of Turkey
31
MONITORINGMONITORINGThe following information will be monitored by SU
• Project Management
• Adequacy of Documentation
• Progress of Activities
• Risks and Problems
• Project Indicators
• Procurement Matters and Records
• Visibility of the Project