Page 1: ET1622 Define KPI Waste Project Presentation Template.

ET1622

DefineKPI

WasteProject Presentation Template

Page 2: ET1622 Define KPI Waste Project Presentation Template.

ObjectivesAfter completing this section, participants should be able to:

Construct a process map, identifying key process steps, inputs, and outputs;

Understand when it is necessary to narrow the project focus;

Construct a top-down flowchart;

Construct a deployment flowchart;

Explain when each of these methods is most useful;

Understand how to use flowcharts to identify opportunities for improvement;

Have an appreciation for the value of process maps and flowcharts in the DMAIC structure.

Page 3: ET1622 Define KPI Waste Project Presentation Template.

Understanding the ProcessA team’s work in the DMAIC process typically begins with

clearly defining the process.

By creating a detailed description of how the process works we clarify the process activities that will be targeted, identify inputs and outputs, identify non-value added activities, and uncover many opportunities for improvement.

In this section, we will discuss four tools for defining a process:

Process maps, top-down flowcharts, and deployment flowcharts.

Page 4: ET1622 Define KPI Waste Project Presentation Template.

Understanding the ProcessAs you get started, be sure to keep the following in mind:

Are the process boundaries clearly defined?

Is the purpose of the process understood by all members?

What level of detail is needed?

Process boundaries are established to define the beginning and end of a process, and to help the team understand which activities to include as part of the ‘process’.

The purpose of the process is defined to make sure that we understand the process from the perspective of the customer.

What are the customer’s requirements? What is the customer’s definition of ‘quality’?

Page 5: ET1622 Define KPI Waste Project Presentation Template.

Understanding the ProcessUnderstanding what the customer requires helps the team evaluate

which tasks add value to the process, and helps to ensure that the process is understood by all members.

The level of detail required in defining the process is based on both the opportunities for improvement and the complexities of the process.

There should not be so much detail that the ‘big picture’ is lost, particularly early on.

On the other hand, there should not be so few details that major opportunities for improvement are missed.

Page 6: ET1622 Define KPI Waste Project Presentation Template.

Understanding the ProcessFinally, it is necessary for all team members to have an

overall understanding of the process.

Some members will be more familiar with the process than others, and even the most knowledgeable members may not be as ‘educated’ about the process as they would like to believe.

The following activities are helpful:

Observe the process in action.

Interview associates and others involved in the process.

Interview internal suppliers and customers.

Review operating procedures or manuals.

Page 7: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process MapWhat is a process map?

A process map is a graphical representation of the process. It is a high level flowchart that represents how things are really being done (versus how we think they should be done).

In developing a process map, the process is identified, and then the following steps are taken (not necessarily in this order):

1. Identify key steps in the process.

2. List inputs at each process step.

3. List critical outputs from each process step and the final output(s).

4. Identify the most critical inputs.

5. Add operating specifications and targets.

Page 8: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process Map1. Identify key process steps

A simple flowchart can be used to display the major process steps.

Here’s a simple method to construct a basic flowchart:

1. Establish the first and last steps.

2. Describe each major activity using a verb followed by a noun (if possible).

3. Write each step on a Post-ItTM note so it can be moved.

4. Once the correct order is determined, connect the steps with arrows to show the sequence of activities.

Note: Don’t get lost in the details of the process at this point.

Page 9: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process Map

G et a p iece ofbread

Put bread intoaster

Settem perature

setting

Activatetoaster

Rem ovebread from

toasterS topS tart

In this section, we will use the process of ‘making a piece of toast’ to illustrate the mechanics of making a process map.

Although the process may seem overly simple, it provides a useful illustration.

Below, we see the process map after the key process steps have been identified and after the correct order of activities has been determined.

Page 10: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process Map2. Identify process inputs for each process step

Inputs are referred to as our ‘X’s.

They can fall into one of the following categories: Materials, methods, machines, manpower, measures, and environment.

G et a p iece ofbread

Put bread intoaster

Settem perature

setting

Activatetoaster

Rem ovebread from

toaster

B read typeB read tem pB read th icknessA ge o f b readO pera torE nvironm ent

S lo t positionToaster tem p# o f s lo tsO pera torTem p se lection

Toaster tem pB read typeO pera torS etting

C urrent to toasterA ctiva tion m ethodO pera tor

R em ova l tim eS lice am ountsO pera tor

S topS tart

Page 11: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process Map3. Identify process outputs and CTQ’s (our ‘Y’s’)

Intermediary process outputs should be identified, as well as final quality characteristics.

Characteristics or measurements that are ‘critical to quality’ from the perspective of the customer are referred to as ‘CTQ’s’.

G et a p iece ofbread

Put bread intoaster

Settem perature

setting

Activatetoaster

Rem ovebread from

toaster

B read typeB read tem pB read th icknessA ge o f b readO pera torE nvironm ent

S lo t positionToaster tem p# o f s lo tsO pera torTem p se lection

Toaster tem pB read typeO pera torS etting

C urrent to toasterA ctiva tion m ethodO pera tor

R em ova l tim eS lice am ountsO pera tor

Piece of bread Bread in toaster Tem perature set B read cooking Toast, S lightlyBrowned

S topS tart

Page 12: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process Map4. Identify critical process inputs

Identify inputs that your team feels have the most significant impact on the outputs.

These are inputs that your team will investigate as you move into the Measure and Analyze Phases.

Get a piece ofbread

Put bread intoaster

Settemperature

setting

Activatetoaster

Removebread from

toaster

Bread typeBread tempBread thicknessAge of breadOperatorEnvironment

Slot positionToaster temp# of slotsOperatorTemp selection

Toaster tempBread typeOperatorSetting

Current to toasterActivation methodOperator

Removal timeSlice amountsOperator

Piece of bread Bread in toaster Temperature set Bread cooking Toast, SlightlyBrowned

StopStart

Page 13: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process Map5. Add operating specifications and process targets

Identify both internal and customer targets and specifications.

Critical Inputs

TargetUpper Spec

Lower Spec

Age of Bread5 days prior to expiration

10 days 0 days

Removal Time 15 seconds25

seconds5

seconds

Setting Level 4 Level 5 Level 3

Page 14: ET1622 Define KPI Waste Project Presentation Template.

Critical Inputs

TargetUpper Spec

Lower Spec

Age of Bread5 days prior to expiration

10 days 0 days

Removal Time 15 seconds25

seconds5

seconds

Setting Level 4 Level 5 Level 3

Process Map: Making a Piece of Toast

Get a piece ofbread

Put bread intoaster

Settemperature

setting

Activatetoaster

Removebread from

toaster

Bread typeBread tempBread thicknessAge of breadOperatorEnvironment

Slot positionToaster temp# of slotsOperatorTemp selection

Toaster tempBread typeOperatorSetting

Current to toasterActivation methodOperator

Removal timeSlice amountsOperator

Piece of bread Bread in toaster Temperature set Bread cooking Toast, SlightlyBrowned

StopStart

Page 15: ET1622 Define KPI Waste Project Presentation Template.

Developing a Process MapIf mapping the process seems frustrating or

overwhelming, the process boundaries may be too wide.

The team may need to narrow the focus of the process to a specific process step or group of steps.

Ask the following questions to help narrow the focus:

Is a particular part of the process known to be most troublesome?

Where do most of the errors occur?

Will improvements to the initial steps of the process reduce the number of problems downstream?

Page 16: ET1622 Define KPI Waste Project Presentation Template.

Detailed FlowchartsThe methods introduced in this section apply to both

manufacturing and non-manufacturing processes.

For example, we can easily develop a Process Map for the following processes:

Order fulfillment for a particular part,

Purchasing particular raw materials, or

Accounts Receivable for a specific customer.

For these and other business processes, the steps demonstrated in the previous example can be followed to develop a process map and to identify initial opportunities for improvement.

Page 17: ET1622 Define KPI Waste Project Presentation Template.

Detailed FlowchartsHowever, since business processes are often poorly defined, and can

involve numerous decision points and parallel activities, more detailed flowcharts may be required.

Two useful types of flowcharts for describing the steps in a process are top-down flowcharts and deployment flowcharts.

Top-down flowcharts show the few major steps of a process and list each of the sub-steps for each step.

These charts are particularly useful when there are multiple sub-steps involved.

Deployment flowcharts list the individuals, groups or areas involved in the process, show the flow of a process, and identify those involved at each step.

Page 18: ET1622 Define KPI Waste Project Presentation Template.

Detailed FlowchartsBelow is a top-down flowchart for a finished product

inspection operation.

The operation consists of three primary steps, and a number of sub-steps:

Inspect and Sort Measure Package

Read Work Order

Review Customer Specs

Inspect Parts According toCustomer Specs

Obtain Supervisor Signoff

Send Nonconforming Productto Rework or Material Review

Complete and Sign Paperwork

Move to Measure

Read Work Order

Set Up Measure Machine

Program Measure PC

Feed Test Parts

Make Adjustments if Needed

Feed Parts and Stack

Print Paperwork and Sign

Read Customer Instructions

Obtain Pallet and PackingMaterials

Set Up Packing Machine

Pack

Stretch Wrap

Weigh

Print Customer Labels andAdhere

Move to Shipping Dock or FGIRacks

Page 19: ET1622 Define KPI Waste Project Presentation Template.

Detailed FlowchartsDeployment flowcharts are effective with processes

where materials and/or information pass through many different functional areas.

Deployment flowcharts use a variety of symbols to describe the steps in a process. These symbols indicate the type of activity.

The most commonly used symbols are given below:

Process Decision ConnectTerminator

Process Step Decision Point

Link To orFrom

AnotherFlowchart

Start or Stop

Document

CompletePaperwork

Page 20: ET1622 Define KPI Waste Project Presentation Template.

Partial deployment flowchart of the food service process in a restaurant.

The deployment flowchart on the following slide clearly identifies the areas of responsibility in a New Product Request process.

Hostess Wait Staff Kitchen

Take Drink Order

Seat Guest(s)

Make Drink(s)

Serve Drink(s)

Take Food Order

Make Order

Deployment Flowchart ofRestaurant Food Service Process

Serve Order

Yes

Ingredients inStock?

No

Page 21: ET1622 Define KPI Waste Project Presentation Template.

Opportunities for ImprovementDefining a process provides an ideal opportunity to identify

inefficiencies and sources of error.

As you investigate the process, be on the lookout for the following inefficiencies:

Duplication - are identical activities being performed at different places in the process?

Unnecessary tasks, such as paperwork or approvals.

Illogical or inefficient sequencing of tasks, which causes delays and extra work.

Unclear lines of responsibility, which can result in delayed decisions .

Opportunities for errors - there are often many of these.

Page 22: ET1622 Define KPI Waste Project Presentation Template.

Opportunities for ImprovementInefficiencies (continued):

Inconsistencies - are different methods or procedures being used?

Non-value added activity - is work being done that does not add value?

Customer requirements - are they clearly defined and communicated?

Standards no longer used - do standard methods previously agreed upon still apply?

Page 23: ET1622 Define KPI Waste Project Presentation Template.

SummaryThe methods introduced in this section are effective in focusing our

attention on the process.

In the Define Phase, they are useful for many reasons, such as:

Defining how the work is done, and providing the team with an in-depth understanding of the process,

Helping to bound the scope of improvement projects,

Showing customer supplier relationships,

Identifying inefficiencies, gaps, bottlenecks and inconsistencies,,

Identifying critical process inputs , and

Providing information that can be used with other problem solving tools.

Page 24: ET1622 Define KPI Waste Project Presentation Template.

Defining the Process ExerciseIn this exercise, we will work in teams to develop a Process

Map, a Top-Down Flowchart or a Deployment Flowchart for the process you will be studying in your project.

Select the method that best suits your process.

Note: For this exercise, use flip charts and post-it notes.

Alternative: If your project needs to be re-defined, or if you are not familiar enough with your process to proceed, use the following process:

‘Barbecuing a hamburger on a charcoal grill’.

You will have approximately 20 minutes. Be prepared to give a brief presentation of your results.

Page 25: ET1622 Define KPI Waste Project Presentation Template.

Six Sigma Improvement Process Project KPIs and Goals

• The Project Charter• Project KPIs• Plotting the KPI• Scaling KPIs• Goal Statements • Project Scope and Boundaries• Refining Your Project Charter• Closing Comments

Page 26: ET1622 Define KPI Waste Project Presentation Template.

Objectives• After completing this section, participants

should be able to:– Complete a project charter for their projects;– List characteristics of an effective Project KPI

(Key Process Indicator);– Define an appropriate project-level KPI for their

project;– Determine the time period that will be used in

time-ordered plots of the Project KPI; – Determine whether their Project KPI should be

scaled for time-ordered plots.

Page 27: ET1622 Define KPI Waste Project Presentation Template.

Introduction

Measure

Define

AnalyzeImprove

Control

Page 28: ET1622 Define KPI Waste Project Presentation Template.

Prior to initiating a Lean6sigma project, there is the recognition that an opportunity exists.

The goals and objectives of the project are defined and a team is formed.

The project charter is a document that defines the project, its structure, and the team’s goals and timeline.

In a sense, the project charter is a contract detailing what is expected of the team relative to the given project.

During the define phase of a Lean6sigma project, the project charter and project goal are reviewed and clarified, the process is defined, and key process inputs and outputs are identified.

Introduction

Page 29: ET1622 Define KPI Waste Project Presentation Template.

A Lean6sigma project charter consists of:– The business case: Why the project was selected.– The opportunity statement: The potential opportunity.– The goal statement and KPI: The specific objectives of the team

and baseline measurement.– The project scope: The boundaries of the project.– The team selected: The project team, the sponsor, the Expert

assigned, and other resources.– A project plan: Key milestones.

The Project Charter

Page 30: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs• The Project Charter requires that the team defines a KPI and a goal in

the Goal and KPI section.• The Goal and KPI statement consists of three, and only three,

components:– The project-level KPI, – The current and desired level of performance, stated in terms of the

KPI, and– A date by which the desired performance will be achieved.

• In this section, we:– Describe characteristics of a good Project KPI,– Present examples of KPIs,– Explore KPI issues.

Page 31: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs• The main characteristics of a desirable Project KPI are:

– The KPI should be directly tied to the process and the characteristic that the team wants to improve;

– It must be measurable;

– It should be as fundamental (“low level”) a measure as possible;

– There is usually, but not always, a single Project KPI – sometimes teams need to optimize more than one criterion.

• The goal statement is a statement of the current level of the KPI and the desired level (or “goal”) for the KPI, along with a time period over which the improvement will occur.

Page 32: ET1622 Define KPI Waste Project Presentation Template.

Goal and KPI Reduce the mean number of days to process

Industrial NPRs, measured weekly, from 77 days to 14 days by December 31, 2002.

The Project Charter

Page 33: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs• The Project KPI is critical, as it drives the project!• The KPI should be closely tied to the process being studied and

improved.• It is useful, in determining the KPI, to define the process which it is

measuring.• Process maps, flow charts, and value stream maps are methods for

describing the process of interest. • Teams sometimes find it useful to revisit their KPI after developing

maps of the process.• The KPI must also be consistent with the project scope.

Page 34: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs• The Project KPI, process of interest, and

scope of the project, must be in alignment.

Project KPI

Process Scope

Page 35: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs

• Example: Scrap Reduction• A team is trying to reduce the amount of waste produced by a certain

finishing operation.• Parts are run through the operation. Parts that are not properly

finished can often be reworked (sent through the operation a second time). These are called defective parts.

• A scrapped part is one that can not be reworked.• The process is run over three shifts.• The total number of parts run through the process can vary

dramatically from day to day and shift to shift.• What is an appropriate Project KPI?

Page 36: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs

• Some possible KPIs:– Total cost of scrap – Number of parts that are scrapped– Percent of parts that are scrapped– Percent of parts scrapped by shift– Number of parts that are defective after the first

pass– Percent of parts that are defective after the first

pass

Page 37: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs• Example: Meeting Specifications• A team is charged with reducing variation in OD (outside diameter) for

a specific part. The team is to ensure that the OD meets its target value and specification limits.

• The number of parts produced varies by day.• What is an appropriate Project KPI?

– Percent of parts out of specification

– Percent of parts off target

– The OD measurement itself, from daily samples

– A Cpk index before and after improvement

– Other?

Page 38: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs

• Example: Engineering Design• A team is trying to improve the timeliness of an engineering design

process.• The team is planning to focus on the process of delivering a

design.• This process begins with the customer request and ends with

delivery of the design to the customer.• The team does not see reducing labor costs as within its

scope.• What is an appropriate Project KPI?• Remember that the Project KPI, the process of interest, and

the scope of the project need to be in alignment!

Page 39: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs• Some teams may find that data is not currently being collected on

their KPI.• This is not unusual, and points to a situation where the sheer

act of measuring the problem is of value.• Do not be daunted if data does not currently exist on your team’s

Project KPI. • If this is the case, the team should:

– Define the process of interest using a process map, flow chart or value stream map (these will be discussed later).

– Use the map of the process to design a data collection plan.– Then, begin collecting data as soon as possible.

Page 40: ET1622 Define KPI Waste Project Presentation Template.

Project KPIs• Here are some examples of typical project KPIs:

– Amount or percent scrap– Critical dimensional measurements– Cycle time (the time required to process a part)

– Elapsed time (the number of days between a scheduled and an actual start date)

– Time spent in a given activity (machine time, time spent setting up a machine, time spent on non-value added work)

– Proportion of false positives (or negatives) in an inspection process

– Quantity of raw materials consumed

Page 41: ET1622 Define KPI Waste Project Presentation Template.

Plotting the KPI

• A Lean6sigma project always focuses on improving a process.

• The KPI is always tied to that process.• Since a process is dynamic – it changes over time – the

KPI must be monitored on a periodic basis. • Some KPIs are summarized and plotted daily, others

weekly.• KPIs can be plotted on run charts or control charts.• A team hopes to see improvement reflected when plotting

the KPI in this fashion.

Page 42: ET1622 Define KPI Waste Project Presentation Template.

Plotting the KPI

• Example: Suppose that a project team is interested in reducing the proportion of defective parts produced by a process.

• The goal might be to reduce this from an average of 12% per day to an average of 5% per day.

• The team should track the daily proportion of defective parts, and plot the results on a control chart.

• On the next slide, we see control charts of the daily proportion defective, covering the periods before and after implementation of the team’s solution.

Page 43: ET1622 Define KPI Waste Project Presentation Template.

Plotting the KPI

Solution

Shows process level and daily variation prior to solution

Page 44: ET1622 Define KPI Waste Project Presentation Template.

• A Project Goal is a statement of how much improvement is to be expected and by when.

• The goal is defined in terms of the KPI.• Clear, understood, and agreed-upon team goals are important for the

following reasons (among others):– They provide a focus for the team’s activities,

– Goals help channel the team’s activities by pointing everyone in the same direction,

– They provide a target, and

– They provide a means to evaluate whether the team has been successful.

Goal Statements

Page 45: ET1622 Define KPI Waste Project Presentation Template.

• Recall that goals should include information on what will be affected (the KPI), how will progress be measured, and when will the goal be achieved.

• The following goal statement format is recommended:• To improve (e.g. increase, decrease or eliminate) the

(description of the KPI) from (current level of performance) to (desired level of performance) by (date).

• For example:• To increase the on-time delivery rate from 82% to 95% by

September 2002.

Goal Statements

Page 46: ET1622 Define KPI Waste Project Presentation Template.

Goal Statements

• Comment: A goal statement should absolutely not suggest, propose, or even hint at a solution.

• Yet, consider the following, which are typical of goal statements that teams present:– Increase inventory turns by identifying sources that contribute to

excess finished inventory and implement solutions to prevent future occurrences.

– Reduce late deliveries by eliminating a machining step.– Reduce inventory by defining part numbers and location of

misallocated inventory.

Page 47: ET1622 Define KPI Waste Project Presentation Template.

Goal Statements

• Goal statements should also not include:• Elements of the project plan:• “We plan to define a process to….”, or• “We plan to analyze data from…”• A list of three or more KPIs:

– There should be one or at most two measures that will reflect the overall success of the project – these are the Project KPIs;

– If the team wants to track more than one or two measures, this should be indicated under the Project Plan.

Page 48: ET1622 Define KPI Waste Project Presentation Template.

Goal Statements• Remember that a goal statement consists of only three elements:

– The KPI, – The current and desired level of the KPI, and– The date by which the desired level of performance will be achieved.

• This first component of the statement should include verbiage that indicates how the KPI will be plotted as a baseline.

• This would include the time period over which measurements will be summarized in order to plot a point on a run or control chart, as well as a clear description of how the plotted value is calculated.

Page 49: ET1622 Define KPI Waste Project Presentation Template.

Project Scope The key question is whether everyone on the team has the same

picture of what the team is there for. We can never assume that everyone shares the same

picture. Understanding and agreeing upon the scope and boundaries of the

project early on are critical to the success of the team. Although the project charter will define the project scope, the

team will have additional ideas and concerns, and will need some clarification from the sponsor.

Defining the project scope also allows us to determine if our project goals are reasonable, or if they need to be further refined.

Page 50: ET1622 Define KPI Waste Project Presentation Template.

Closing Thoughts

During initial meetings, Six Sigma teams review the project charter to make sure that all members understand the purpose and function of the team.

In general, members should be able to answer the following questions:– What is the opportunity or problem the team will be addressing?

– What is the project goal?

– Are there any potential issues or obstacles?

– What are the project deadlines and key milestones?

– How will the workload of the team be shared?

– What additional resources are available to the team?

Page 51: ET1622 Define KPI Waste Project Presentation Template.

Closing Thoughts

Your team may need to refine or change its goal as more data is obtained and as the team develops a better understanding of the opportunity or problem.

You may also recognize the need to add additional members to the team, and should identify other resources and temporary members that your team will need.

The scope of the project may be narrowed or broadened as the team begins to study the process.

Close communication with the sponsor at each stage of your project is critical.

Your sponsor is ultimately responsible for the success of the project.

Page 52: ET1622 Define KPI Waste Project Presentation Template.

Minimize Waste• Overproduction

• Excess Inventory

• Transportation

• Unnecessary Processing

• Defective parts (rejects/rework)

• Waiting

• Unnecessary Motion

Page 53: ET1622 Define KPI Waste Project Presentation Template.

Overproduction

• Two possible reasons– Theory of Constraints

• Bottleneck• Entire process is paced by the slowest process step.

– Producing more than needed because of known quality rejection rate

• No visible idle time, everyone appears to be working hard

• Large amount of inventory. Typically, before and after each process step.

• Leads to plans for overtime/investing in more equipment to work down the inventory.

Page 54: ET1622 Define KPI Waste Project Presentation Template.

Excess Inventory

• Purchasing – Purchasing an excess amount of material to obtain

discounts • minimum order quantities

– Ensuring factory does not run out of certain stock it ran out of last year

• Manufacturing– Material that is extra raw material, WIP, FG not

shipped• Engineering

– Obsolete parts due to change in design (usually handled through Engineering Change Orders and effective dates)

Page 55: ET1622 Define KPI Waste Project Presentation Template.

Transport

• Symptom of factory layout• Movement of product from one place to another

Page 56: ET1622 Define KPI Waste Project Presentation Template.

Process

• Examples:– Locating a wire harness tie on a chassis– Drilling an extra hole on a part so that the part

can be located properly on an assembly– Grinding and polishing after cutting a part– Requiring extra signatures on a contract– Moving locator pins on a welding die for a

welded assembly

Page 57: ET1622 Define KPI Waste Project Presentation Template.

Rejects and ReworkVendor

Purchasedmaterial

Internal Manufacturing Processes

Assembly Processes

Shipping

Customer

Y1% rejects

Y2% rejects/Y1% rework

Y3% rejects/Y2% rework

Y4% rejects/Y3% rework

Y5% rejects/Y4% rework

#Rejects=ΣYii=1

5

Page 58: ET1622 Define KPI Waste Project Presentation Template.

Waiting

• Waiting for materials

• Waiting for inspection

• Waiting for prints or instruction

• Waiting for process to complete

• Waiting for people, machines, materials, information

Page 59: ET1622 Define KPI Waste Project Presentation Template.

Unnecessary Motion

Work Area 3

Work Area 1

Wor

k A

rea

2

Work Area 4Filing

CopyMachine

Filing

Printer

Work Area 3

Work Area 1

Wor

k A

rea

2

Work Area 4

Filing

Before After

CopyMachine

Printer

Work-flow Diagrams are used to diagram movements of people, parts, paperwork or other information within a process.

Page 60: ET1622 Define KPI Waste Project Presentation Template.

Creating a Value Stream Map

Home Center

11,400/ Mo. Flat

3,500/Mo. Phil.

745 / day

20 box/pallet

Daily

SHIPPING

Staging

Assembly

1

Mark

11

Sub Assy 2

1

Sub Assy 1Press

1.5 sec CT

90 min c/o

80% U/T

2 shifts

40 sec CT

5 min c/o

100% U/T

2 shifts

71 sec CT

5 min c/o

100% U/T

2 shifts

54 sec CT

10 min c/o

90% U/T

2 shifts

59 sec CT

5 min c/o

100% U/T

2 shifts

II

4,400 flat800 phillips

MaterialStores Area

Coils10 daysHandles6 days

10,000 flat8,000 phillips

3,200 flat1,100 phillips

2,200 flat1,000 phillips

1,200 flat4,000 phillips

II II

Betty’s

2X W

eekly

Pete’s

Weekly

1500 lbcoils

500 lbBox

Weekly Schedule

Daily Ship Schedule

6 wk Fcast

Weekly FAX

3 mo. Forecast

Daily OrdersMRP

Production Control

10 days

1.5 sec 40 sec 71 sec 54 sec 59 sec

24.1 days 5.8 days 4.3 days 7 days 7 days

Production Lead Time

58.2 days

Value Added Time

225.5 sec.

(10,000 + 8,000)/745 = 24.1 days

Page 61: ET1622 Define KPI Waste Project Presentation Template.

Homework

• Look through your workspace or home/room.• Find some opportunities that will eliminate any of

the seven types of waste.• Describe the opportunity and how it will eliminate

waste.• If possible gather some data to quantify the

amount of waste that is eliminated.• Submit a report by next meeting class 9/14.

Page 62: ET1622 Define KPI Waste Project Presentation Template.

Lean6Sigma Project Title

~ Define & Measure Phase ~

Name LastName-Project LeadMonth, Day, Year

Page 63: ET1622 Define KPI Waste Project Presentation Template.

Business Case

Opportunity Statement

Page 64: ET1622 Define KPI Waste Project Presentation Template.

Goal Statement / KPIs•

Project Sponsor

• Sponsor:

Page 65: ET1622 Define KPI Waste Project Presentation Template.

Process Map (or Process Flow Diagram or Value

Stream Map)

Page 66: ET1622 Define KPI Waste Project Presentation Template.

Pareto (distribution or measurement of problem)

Page 67: ET1622 Define KPI Waste Project Presentation Template.

Control Chart (for KPI measurements)

Page 68: ET1622 Define KPI Waste Project Presentation Template.

Cause and Effect Diagram

Page 69: ET1622 Define KPI Waste Project Presentation Template.

Data Collection Plan

FactorOperational Definition

Data TypeCollection

Method/SourceAvailable?

1

2

3

4

5

6

7

8

9

Data Collection Plan

Page 70: ET1622 Define KPI Waste Project Presentation Template.

Project TitleProject Title Phase:

Accomplishments: Goals for mmyy:

Project Plan and Milestones:

Milestone or Major Activity Due Date Status

Open Issues/Concerns & Resolutions:

Big-Y:

Indicate status as follows:

Green: On Track

Yellow: In Danger

Red: Late

If you want to color the cell:

1) Right click cell and select “Borders and Fill…”

2) Select the Fill color under the Fill tab

Indicate status as follows:

Green: On Track

Yellow: In Danger

Red: Late

If you want to color the cell:

1) Right click cell and select “Borders and Fill…”

2) Select the Fill color under the Fill tab