1 Estonia - Latvia Programme 2007-2013 Cross-Border Co-operation Programme under the European Territorial Co-operation Objective CCI No 2007 CB 163 PO 050 ANNUAL IMPLEMENTATION REPORT 2012 May 2013
1
Estonia - Latvia Programme 2007-2013
Cross-Border Co-operation Programme under the European Territorial Co-operation Objective
CCI No 2007 CB 163 PO 050
ANNUAL IMPLEMENTATION REPORT
2012
May 2013
2
Table of Contents 1 IDENTIFICATION ............................................................................................................................... 3
2 OVERVIEW OF THE IMPLEMENTATION OF THE OPERATONAL PROGRAMME ................................ 5
2.1 Achievement and analysis of the progress .............................................................................. 5
2.1.1 Information on the physical progress of the Operational Programme ........................... 5
2.1.2 Financial information as of 1 January 2007 – 31 December 2012 .................................. 8
2.1.3 Information about the breakdown of the use of the funds ........................................... 10
2.1.4 Assistance by target groups .......................................................................................... 10
2.1.5 Assistance repaid or re-used .......................................................................................... 11
2.1.6 Qualitative analysis ....................................................................................................... 13
2.2 Information about compliance with Community Law........................................................... 22
2.3 Significant problems encountered and measures taken to overcome them ........................ 22
2.4 Changes in the context of the operational programme implementation ............................. 24
2.5 Substantial modification pursuant to Article 57 of Regulation (EC) No 1083/2006 ............. 24
2.6 Complementarity with other instruments ............................................................................ 24
2.7 Monitoring and evaluation .................................................................................................... 25
2.8 EU Strategu for the Baltic Sea Region ................................................................................... 26
3 IMPLEMENTATION BY PRIORITY .................................................................................................... 28
3.1 Priority 1 Increased cohesion of the Programme area ......................................................... 28
3.1.1 Achievement of targets and analysis of the progress ................................................... 28
3.1.2 Significant problems encountered and measures taken to overcome them ................. 30
3.2 Priority 2 Higher competitiveness of the Programme area .................................................. 30
3.2.1 Achievement of targets and analysis of the progress ................................................... 30
3.2.2 Significant problems encountered and measures taken to overcome them ................. 32
3.3 Priority 3 Active, sustainable and integrated communities .................................................. 32
3.3.1 Achievement of targets and analysis of the progress ................................................... 32
3.3.2 Significant problems encountered and measures taken to overcome them ................. 34
4 MAJOR PROJECTS .......................................................................................................................... 34
5 TECHNICAL ASSISTANCE ................................................................................................................ 34
6 INFORMATION AND PUBLICITY ..................................................................................................... 41
6.1 Information and publicity activities ....................................................................................... 41
6.2 Media Monitoring ................................................................................................................. 44
7 CHALLENGES FOR 2013 ................................................................................................................. 45
3
1 IDENTIFICATION
OPERATIONAL
PROGRAMME
Objective concerned European Territorial
Cooperation
Eligible area concerned Estonia (Lõuna-Eesti, Lääne-
Eesti) and Latvia (Kurzeme,
Pierīga, Rīga, Vidzeme)
Programming period 2007-2013
Programme number (CCI No) 2007 CB 163 PO 050
Programme title Estonia – Latvia Programme
2007-2013
ANNUAL
IMPLEMENTATION
REPORT
Reporting year 2012
Date of approval of the
annual report by the
Monitoring Committee
The Annual Implementation Report of the Estonia – Latvia Programme 2007-2013 has been
prepared in accordance with Article 67 of the Council Regulation (EC) No 1083/2006 of 11
July 2006 laying down general provisions of the European Regional Development Fund, the
European Social Fund and the Cohesion Fund as well as the model provided in Annex VI of
the Commission Regulation (EC) No 846/2009 of 1 September 2009 amending Regulation
(EC) No 1828/2006 setting out rules for the implementation of Council Regulation (EC) No
1083/2006. The Commission Regulation (EC) 1828/2006 was further amended by
Commission Regulation (EC) 832/2010 of 17 September 2010. Annex I of this Regulation
replaces point 2.1.2 Financial information of Annex XVIII of the Commission Regulation (EC)
No 1828/2006. The Programme implementation is also based on the relevant provisions of
the Regulation (EC) No 1080/2006 of the European Parliament and of the Council on the
European Regional Development Fund.
The Estonia – Latvia Programme 2007-2013 (hereinafter also referred to as the
“Programme”) is a cross-border cooperation programme including the NUTS III regions from
Estonia (Lõuna-Eesti, Lääne-Eesti) and Latvia (Kurzeme, Pierīga, Rīga, Vidzeme).
4
The Operational Programme (hereinafter also referred to as the “OP”) for the Estonia –
Latvia Programme 2007-2013 was approved by the European Commission on 21 December
2007.
The Agreement between the Estonian Ministry of the Interior, the Republic of Estonia and
the Republic of Latvia on the management and administration of the Estonia – Latvia
Programme 2007-2013 came into effect in March 2009. The agreement stipulates the
structure, as well as the rights and obligations of the Programme institutions and the main
principles of the Programme implementation and management. In Estonia, the Ministry of
the Interior hosts the Managing Authority (hereinafter also the MA), the Certifying Authority
(hereinafter also the CA) and the Audit Authority (hereinafter also the AA) of the
Programme.
In Latvia, the Ministry of the Environmental Protection and Regional Development is the
responsible institution for the Programme as of 1 January 2011.
The main contact point for the applicants and beneficiaries is the Joint Technical Secretariat
(hereinafter also as the JTS), which is located in Estonia, in Tartu. The JTS is established as a
separate legal entity within Enterprise Estonia (hereinafter also as the EAS). During the
previous years, the JTS had the Info-point in Riga. However, as there was no practical need
for the info-point anymore because all the funds had been committed by the end of 2012,
the decision was taken by the MC to close down the Riga info-point as of 1 January 2013.
The relations between the Programme authorities and the JTS as well as the JTS’ activities
and obligations are regulated by the Administration Contract between the Estonian Ministry
of the Interior and the EAS.
The overall objective of the Programme is to promote sustainable development and
economic competitiveness of the Programme area through achieving an integrated and
cross-border approach to economic, social and environmental development in ways, which
involve and benefit local people and communities.
The report includes the following annexes:
1) Information about the breakdown of use of the funds
2) List of the projects approved in 2012
3) List of supported projects during the implementation period
4) List of the projects contributing to the EU Strategy for the Baltic Sea Region
5
2 OVERVIEW OF THE IMPLEMENTATION OF THE OPERATONAL
PROGRAMME
2.1 Achievement and analysis of the progress
2.1.1 Information on the physical progress of the Operational Programme
The Estonia – Latvia Programme 2007-2013 has four priority axes: priority 1: Increased
cohesion of the Programme area” with two directions of support, priority 2: “Higher
competitiveness of the Programme area with three directions of support, priority3: “Active,
sustainable and integrated communities” with two directions of support. Priority 4 is
Technical Assistance (hereinafter also the TA). The total ERDF allocation to the priorities 1 –
3 is 35 934 836 EUR. By the end of 2012 all Programme funds had been committed. As
described in the Annual Implementation Report 2011, in May 2011 in Jurmala, the MC
decided to allocate the funding available under the 1st and 2nd priority to the projects
strategically important for both countries. This decision was taken to better focus the
Programme aims and to manage the de-commitment risk. Finally six such project
applications were approved by the MC at the meeting in Tartu in May 2012 or via written
procedure. The projects are described in the section 6.1.2 “Qualitative analysis”.
By the end of 2012, sixty three projects had received financing from the Programme and
during the year nine subsidy contracts were signed including the contracts for two strategic
projects. All in all 30 amendments were formalised to the previously signed subsidy
contracts. As of the end of 2012, twenty five projects had been completed with the final
payments made.
With so many projects finished and several being close to submitting their final reports it is
fair to make some conclusions about the overall implementation of the programme, which
concerns implementation of projects. All in all, the projects have done a good job with
fulfilling their promises stated in the application forms and none of the projects have been
stopped or closed down before its planned end. In the Programme Document the target set
for an indicator “percentage of all projects approved for funding implemented successfully”
was 95%, but so far the Programme has the success rate of 100% and it should be realistic to
keep it this way till the end of the Programme.
Partly it is a result of a thorough assessment procedure before approval of projects - the
weaker projects have been put aside already during assessment. But also a good and
intensive cooperation between the projects and authorities of the Programme has
supported achievement of this aim, and professional work of project teams, both on a lead
partner and partner level. Naturally, the capacity of project teams has varied with some
projects needing only comments and clarifications from the first-level control bodies and the
JTS during the whole project cycle, while there have also been projects, who need sufficient
assistance in compiling the reports or request for changes. Usually finishing the project is the
most challenging part for partners, as processing the last reports might extend to a year or
more after all the other project activities are completed. It means that people have already
6
other tasks, possibly some involved persons have left for other jobs etc, which makes this
step of the project in some cases problematic and time-consuming. But again, for projects
with cooperative and professional teams, who might have also earlier international
cooperation experience and are led by strong managers, the finalisation of the projects does
not pose a problem. Often such teams are led by outsourced project managers.
However, as said above, all the projects have been successfully implemented so far, i.e. their
objectives have been achieved, and only in a few cases have the projects lost partners during
project implementation. Most common reason for stepping out of partnership has been
limited financial resources, i.e. the partners have not had sufficient funds to credit their
activities and wait for reimbursement. In such cases other partners have always taken over
the tasks of stepped out partners and negative effects on achieving the projects’ objectives
have been avoided.
In 2012 the Amendment to the Operational Programme of the Estonia - Latvia Programme
2007-2013 was approved by the European Commission Decision C(2012) 7497. The
Monitoring Committee had approved the Amendment on 28 February 2012 and before the
final approval, the unofficial consultations were held with the Commission. The proposal for
amendments to the Operational Programme of the “Estonia - Latvia Programme 2007-2013”
arose from different necessities – from the results of the Programme evaluation, highlighting
the socio-economic changes, as well as from more technical issues related to the
implementation of the Programme.
Amendments to the Operational Programme were the following:
Chapter 7.6.4. Amendment to specify requirements for signing the declaration of
confidentiality and impartiality – exclusion of the principle of signing a declaration of
confidentiality and impartiality when being nominated by each member of the
Monitoring Committee. Only the principle of signing the declaration of confidentiality
and impartiality at each meeting of the Monitoring Committee was preserved in the text
of the OP.
Chapter 8.1 (d) Amendment to specify de minimis rule applicable to the Programme –
the principles of granting de minimis aid to agricultural production in accordance with
the Commission Regulation (EC) No 1535/2007 and to the fisheries sector in accordance
with the Commission Regulation (EC) No 875/2007 were included to the text of the OP.
Amendment in the ERDF co-financing rates of Priority Axes 1 and 2 – community funding
allocated for private partners under priorities 1 and 2 was decreased to 600 000 EUR in
Priority Axis 1 and 500 000 EUR in Priority Axis 2; and the share of community funding
allocated to public partners was increased accordingly to ensure more efficient use of
ERDF funds.
Amendment in the ERDF co-financing rate to Priority Axis 4 – Technical Assistance. The
amount of ERDF co-financing for Priority Axis 4 remained at the same level, as in the
7
original Operational Programme, but the ERDF co-financing rate was raised to 49% from
35,76%.
Chapter 10.1. ERDF co-financing rate to revenue generating projects was previously up to
50% of eligible expenditure of revenue generating projects. According to the amendment
the principle of co-financing all types of legal entities participating in revenue generating
projects with the co-financing rate 50 per cent was excluded from the text of the OP.
In 2012, the Member States started to design the Estonia – Latvia programme 2014-2020.
Several activities in this context were implemented including formation of the Joint
Programming Committee (hereinafter also “JPC”), identifying the possible cooperation areas,
recruiting Programme preparation expert etc. Different activities related to the
programming of the next period are described in a more detail in the chapter 2.1.6
Qualitative analysis.
8
2.1.2 Financial information as of 1 January 2007 – 31 December 2012
Table 1
Total funding of the operational programme (Union and national)**
Basis for calculating Union contribution (Total cost)
Total amount of certified expenditure paid by beneficiaries
Corresponding public contribution
Implementation rate in %
a b c d e=c/a
Priority Axis 1 Increased cohesion of the Programme Area 26 035 355,00 Total costs 10 473 003,41 10 165 411,12 40,23%
Priority Axis 2 Higher competitiveness of the Programme area 12 579 750,00 Total costs 8 110 584,67 7 818 223,04 64,47%
Priority Axis 3 Active, sustainable and integrated communities 4 227 628,00 Public costs 2 643 534,57 2 643 534,57 62,53%
Priority Axis 4 Technical Assistance 4 681 047,00 Public costs 1 703 577,75 1 703 577,75 36,39%
Grand Total 47 523 780,00 22 930 700,40 22 330 746,48 48,25%
*Certified and send to the European Commission as of 17.10.2012. ** Based on Commission decision 24.10.2012
The Certifying Authority carried out its activities according to the work-plan for 2012. The CA sent to the European Commission an annual statement for the year 2011 on
withdrawal and recovered amounts, pending recoveries and irrecoverable amounts on
14.03.2012. In annual statement for the year 2011 on withdrawal and recovered amounts,
pending recoveries and irrecoverable amounts the CA stated that 704,14 euros of ineligible
costs were deducted from Technical Assistance Priority1 and that the programme had 2,26
1 The CA deducted these recovered ineligible TA costs 704,14 euros from the statement of expenditure No 6 that
was sent to the European Commission on 17.01.2011.
9
euros of pending recoveries in the under the priority 1 and 1143,64 euros pending
recoveries in priority 22.
The CA submitted 2012-2013 ERDF payment forecast to the European Commission on
09.04.2012. The indicative ERDF forecast for Estonia-Latvia Programme 2007-2013 for the
year 2012 was 7 935 000 EUR and for the year 2013 it was 6 123 610.
In 2012 the CA received from the European Commission interim payments in total 8 759
577,88 EUR (the CA fulfilled 110,39% of the payment forecast). All together the CA drew up
and submitted to the European Commission the certificate, statement of expenditure and
application for payment three times on the following dates: 29.02.2012; 18.05.2012 and
17.10.2012. By 30 September 2012 the CA had cumulatively certified 22 930 700,40 EUR of
total eligible costs to the European Commission.
The CA applied for and received bridge financing 13 130 000 EUR from the Ministry of
Finance of the Republic of Estonia in 2012, the repayment deadline is 2.12.2012. Most of the
bridge financing was paid back to the Ministry of Finance by end of 2012; however
571 511,12 euros bridge financing has not been paid back to the Ministry of Finance. This
amount will be paid back after next interim payment will be made by the European
Commission. The European Commission did not make any additional prepayments to the
Estonia - Latvia Programme account during the year 2012.
The CA certified 10 429 190,41 EUR (incl. eligible ERDF support 8 408 982,09 EUR) total
eligible costs at project level during the period January 1, 2012 - December 31, 2012. The CA
had sufficient resources for making all required ERDF payments to the project beneficiaries
in 2012.
In 2012 the CA was fully staffed, there was some turnover of staff in the CA. The new CA
senior accountant joined the CA in 9 March 2012. There were 4 officials working for Estonia
– Latvia Programme in the CA: Head of the Finance Department, Deputy Head of the Finance
Department, chief specialist (part-time) and senior accountant (part- time).
The assessment of the CA is that the progress of the implementation of the Estonia - Latvia
Programme 2007-2013 in the year 2012 was good. In order to speed up the implementation
of the Estonia – Latvia Programme, CA made 726 812 euros pre-payments to the projects in
2012.
2 As of 31.12.2011 there were 2 pending recoveries: project EU30063 „Back to Nature“ (total ineligible sum
2,26 euros) and project EU29867 „IAVV“ (total ineligible sum 1143,64 euros). These ineligible costs the CA
deducted from the next statement of expenditure No 9 that was submitted to the European Commission on
25.01.2012 .
10
2.1.3 Information about the breakdown of the use of the funds
The information about the breakdown of the use of the funds has been completed as
foreseen in Part C of Annex 2 of the Commission Regulation (EC) No 1828/2006 of 8
December 2006 and transmitted to the European Commission via SFC system.
2.1.4 Assistance by target groups
By their legal status, the project applicants in 2012 represented only public sector, as only
strategic projects were supported by the Programme in 2012. The six supported projects,
which were pre-selected by the Member states, are all carried out by different publicly
financed bodies, as can be seen from the table below . Altogether they involve 43 partners –
38 from Latvian and 15 from Estonia.
In total, the division of ERDF commitments between target groups is as follows (in EUR):
Table 2: Assistance by target groups
TOTAL 2012 2011 2010 2009 2008
Local public authorities 8 258 274 23% 1 483 118 19% 452 721 7% 49 943 1% 2 323 425 19% 3 949 067 71%
Regional public authorities 1 786 523 5% 879 388 11% 113 844 2% 0 0% 793 291 7% 0 0%
Environmental bodies 1 576 620 4% 0 0% 228 779 5% 164 617 4% 1 140 751 9% 42 473 1%
Universities and research institutions 1 441 046 4% 183 426 2% 274 776 4% 0 0% 982 844 8% 0 0%
State agencies 5 634 371 15% 349 995 4% 901 739 14% 2 971 112 70% 380 482 3% 1 031 043 19%
Other public bodies 13 327 684 36% 5 483 802 65% 2 861 862 45% 0 0% 4 982 020 41% 0 0%
NGOs 3 882 241 11% 0 0% 1 281 583 20% 1 066 805 25% 1 206 911 10% 326 942 6%
Private partners 687 838 2% 0 0% 200 219 3% 0 0% 307 592 3% 180 027 3%
Total 36 594 597 100% 8 379 729 100% 6 315 523 100% 4 252 477 100% 12 117 316 100% 5 529 552 100%
Examples of the projects implemented in the framework of the Programme
Project FoodArt organized a number of specialized trainings for farmers and food growers,
teaching them different methods that would help them sell their locally grown products to
gourmet restaurants in nearby cities and finding new markets. Põlva region farmer Ly Kaasik
from Põhjala farm in Southern Estonia participated in Food Art hands-on training about
baking, herbs and spices. Already by Christmas time the product that she designed during
the training sessions – tea „The Christmas Warmth” („Jõulusoojus” in Estonian became a
seasonal bestseller. The farm managed to produce around 1500 packages for the holidays,
all sold out in markets in Tallinn and Võru. The project promises to bring many other success
stories in the area of food in the future.
11
ICT DCNet project focused on establishing better connections between the IT and business
sectors in Estonia and Latvia. The most visible and also most successful creation of this
project were three Demo Centres – hubs for information and communication technology
service developers – in Riga, Tartu and Ventspils. Each of the centres specializes in providing
a slightly different service, for instance, Riga Demo centre focuses on robotics testing, Tartu
Demo Centre’s focus is mobile and location based services, and Ventspils is more specializing
for showcasing high technology products. All three centres are now up and running and
available for business clients that want to test their product prototypes or software
applications as well as other audiences, seeking to learn more about locally designed
technologies.
Local Artists for Regional Development project, which aimed to educate and motivate
artists in the regions to become more active in selling their art, has not only been recognized
by its immediate target audiences but also beyond. In December 2012 this project,
implemented jointly by Cesis and Tartu received an international „Cultural Award 2012 ”
from the Union of Baltic Cities. This annual award is given to a Baltic sea region city for active
and innovative work in culture and was awarded to Tartu and Cesis for for joint cultural
cooperation and involving of local artists living in the regions into the cultural life of the
society. The justification of the award also notes the contribution of cultural activities
towards other areas, for instance, economy, social sphere and city environment.
Connecting Stende and Võhma project concluded in 2012 with opening of an open air stage
in Stende on the European Cooperation Day 2012. Similar stage earlier has been constructed
also in Võhma. Both towns have a long-lasting cooperation, which started in 2001 and in
2012 was even more active thanks to the project, during which a number of exchange visits
between various groups of people - dance groups, choirs, youth choirs and craftspeople –
were organised. The main events – Latvian Days in Võhma and Estonian Days in Stende –
already took place for the second year in a row and are bound to become a tradition in the
future, thus uniting these two rural communities long beyond the official project duration.
The project also helped both towns with marketing – new logos were established for
attracting visitors, as well as a special table game was developed, thus creating an interest
about cooperation across borders among younger Stende and Võhma inhabitants.
2.1.5 Assistance repaid or re-used The CA made one reclamation decision for project EU29902 “Protolab” on 23 January 2012.
Total ineligible costs were 4788,58 EUR, including ineligible ERDF support 4070,29 EUR and
ineligible co-financing 718,29 EUR. Tartu Science Park Foundation paid back ineligible ERDF
support 4070,29 EUR on 24 January 2012.
The contracting authority Tartu Science Park Foundation did not respect the following
provisions of the Estonian Public Procurement Act: § 39 section 1; § 38 section 2 in
conjunction with section 1 and § 47 section 1 and section 2. Legal basis for the recovery
12
decision was decree of the Government of Estonia No 278 “Conditions and procedure of
recovery and reimbursement of assistance and submission of information concerning
irregularities in granting and using assistance” §11¹ section 4.
Tartu Science Park Foundation also did not perform correctly the requirement arising from
the Subsidy Contract for the implementation of the project of the Estonia – Latvia
Programme 2007-2013 § 3 point 2 to implement the project with the requisite care,
efficiency, transparency and diligence, in line with best practice in the field concerned and in
compliance with the contract: this is related to the ineligible alcohol costs.
Table 3: Detailed breakdown of ineligible costs based on 23.01.2012 “Protolab” reclamation decision
Ineligible costs Sum (in euros) Incl. ineligible ERDF support for public sector
Incl. ineligible co-financing for public sector
5% from Termoskale UAB (procurement No 111513) contract for furnace 5 333,37 € (without VAT)
266,67 226, 67 (85%) 40 (15%)
5% from all other contracts (27882,02 €) of procurement No. 111513
1 394,10 1 184,98(85%) 209,12(15%)
5% from contract with Fastems UAB No. 09/07/03-1 on 03/07/2009 for universal turning lathe NEF 400 in sum 59600 € (without VAT) (procurement No. 114451)
2 980 2 533(85%) 447(15%)
50 % of the costs of alcohol beverages (Wild Grupp OÜ invoice No. 90 on 06/10/2009 and OÜ Püssirohukelder invoice No. 1458 on 13/01/2009. Total sum 295, 61 (VAT included))
147,81 125,64 (85%) 22,17 (15%)
Total 4 788,58 (100%) 4 070,29 (85%) 718,29 (15%)
13
2.1.6 Qualitative analysis
The implementation of the Programme continued actively in 2012. There were two MC
meetings held in 2012, both in Estonia - in Tartu in May and in Pühajärve, in December. The
MC made altogether six funding decisions in 2012.
Three funding decisions in the total amount of 5 029 999 EUR were made at the MC meeting
in May when the following three strategic projects were approved:
1) Project “Improvement of traffic conditions on Ape-Mõniste connection road between
Riga-Pskov and Võru-Valga-Valmiera transport corridors (Reconstruction of road
Ape–Mõniste)”;
2) Project “Coastal and maritime spatial planning in Pärnu Bay area in Estonia and
coastal municipalities of Latvia (Coastal and maritime spatial planning)”;
3) “Renovation of Valga-Valka railway station (WRS)”.
Three funding decisions in the total amount of 3 349 730 EUR were made by the MC via
written procedure:
4) Project “Development of Estonian – Latvian and Latvian – Estonian dictionary
(DICTIONARY)” (Priority 1);
5) Project “Building Cross-border Capacity to Perform Joint Activities in Tough
Environment (JATE)” (Priority 1);
6) Project “Development of water tourism as nature and active tourism component in
Latvia and Estonia (Riverways)“ (Priority 2).
In total, the ERDF commitment to the six projects was 8 379 729 EUR.
The first MC meeting was held in Tartu, Estonia on 11 May, where additionally to the
approval of the applications of the strategic projects, the main decisions were related to the
changes in the Programme Manual specifying some implementation and reporting
requirements:
1. Setting a threshold for costs of alcohol beverages allowed to be
reported by project partners. The formulation added to the Programme Manual
is: “Alcoholic beverage are eligible only together with a meal and in
moderation, forming up to ¼ of the respective invoice” (Chapter 5.3.4. Travel
and Events);
2. Defining the situations when the MA has the right to decrease a project
budget (Chapter 8.9 De-commitment Rule). The following was decided:
Budgets of the projects which have spent less than 60 % of their planned
funding by the end of the 1st project year will be reduced by the unused
amount of the 1st year, unless a sound justification for non-reduction is
provided by the LP. The JTS follows the spending rate and in case of such
significant under-spending, the projects will be individually contacted;
14
3. Amending and simplifying the reporting procedure in case partners have
no costs to report (so called zero costs report) (Chapter 9.1. Submission
of Progress Reports);
4. Changing the procedure for declaring costs by allowing the reporting of
the costs from the previous milestone and specifying that the division of
project budget into work packages is indicative (Chapter 9.1. Submission
of Progress Reports);
5. Setting forth the rules for applying the flat rate in reporting
administration costs according to the decision of the MC made in
October 2011, approved by the European Commission in April 2012
(adding a new chapter 9.2. Use of flat rate for reporting administration
costs).
- These decisions were taken to better manage the Programme implementation as well
as to facilitate the reporting procedure in order accelerate carrying out the project
activities and the use of funds.
The MC approved the guidelines for preparation of reclamation decisions in the
Estonia – Latvia Programme 2007-2013.
The second MC meeting in 2012 was held in Pühajärve, Valga County, Estonia on 4
December where the main decisions were the following:
1. In relation to the Programme’s commitments and expenditure, the MC asked the
JTS to contact the project “Seto-Suiti Renaissance”, which was the first project in
the reserve list of the 3rd priority by the decision made by the MC at the meeting
on 13-14 December 2011 and inquire whether the project partners are still able
to carry out the project.
To date, the partners have confirmed the readiness to implement the project.
Also they have fulfilled the conditions set by the MC and the project application
was approved by the MC at the meeting on 13-14 May 2013.
2. Taking into account the amendments to the Operational Programme, the MC
made the following decisions:
To approve the principle of continuation of the use of pro-rata based
shares to national contribution of Priority Axis 4 (Technical Assistance), as
agreed in the Agreement between the Estonian Ministry of the lnterior, the
Republic of Estonia and the Republic of Latvia on the management and
15
administration of the Estonia - Latvia Programme 2OO7-2013 CCI No.2OO7 CB
163 PO 050.
New co-financing levels are as follows:
- Estonian national contribution will be 20.62% of the total TA budget,
which is 40.43% of the total member states’ contribution to national co-
financing budget to Priority Axis 4 (Technical Assistance).
- Latvian national contribution will be 30.38% of the total TA budget, which
is 59.57% of the total member states’ contribution to national co-financing
budget to Priority Axis 4 (Technical Assistance).
3. Concerning the Riga Information Point, the MC decided:
3.1. Close the office of the Information Point of the Estonia – Latvia
Programme 2007-2013 at the State Regional Development Agency of the
Republic of Latvia (hereinafter also SRDA) as of 1 January 2013.
3.2. Stop covering costs related to the office space of the Information Point
from the technical assistance budget of the Estonia – Latvia Programme as of
1 January 2013, which have been approximately 2500 EUR/year.
3.3. Stop covering costs of the support staff of the Information Point at SRDA,
which have been approximately 5800 EUR/year.
3.4. Close the Information Point of the Estonia – Latvia Programme 2007-2013
according to the host agreement by Enterprise Estonia and State Regional
Development Agency, i.e. on 31 December 2013.
Preparation of the Estonia – Latvia Programme 2014-2020
In 2012, the programming of the Estonia – Latvia Programme 2014-2020 started. The
Member States decided to form the Joint Programming Committee for the preparation of
the Estonia – Latvia Programme 2014-2020 and it was established in March 2012. The JPC
consists of the representatives of the ministries and regional public authorities, five persons
from both countries. The JPC discusses all the issues related to the programming and is the
decision-making body for the preparation of the Estonia – Latvia Programme 2014-2020.
In 2012, two JPC meetings took place: in March in Riga, Latvia and in October in Tallinn,
Estonia. The main issues of discussion included the working procedures of the JPC, and
mainly steps to be taken for the preparation of the new programme. It was decided to have
stakeholders’ seminars on prior agreed topics (see below in this chapter), start elaborating
of the content of the thematic objectives and decide on the investment priorities.
The activities of the JPC were included as a separate section into the work-plan of the
Programme and EUR 150 000 was allocated from the TA budget to the new programme’s
preparation activities during the 2012, 2013 and 2014 if necessary. The work-plan and the
TA budget were approved by the MC on February 6, 2012.
16
The JTS of the current Programme supports and provides services to the JPC, including
organisation of the meetings, conducting written communication, preparing documents etc.
In 2012, two JPC meetings were held.
The Member States also decided to recruit a programme preparation expert – a person who
is responsible for writing the Programme document as well as for the coordination and
supervision of all activities related to the preparation of the new Programme. The vacancy
of the programme preparation expert was announced in May and following the interviews,
the programme preparation expert started to work at the JTS office in Tartu on 13 August
2012.
The preparation of the new Programme also implies carrying out the ex-ante assessment
involving the Strategic Environmental Assessment. The JTS launched the first tender on 17
July with a deadline of 15 August. However, the first tender was not successful and the
second one was launched on 9 November with the deadline of 3 December 2012. Three
offers were received and consequently a contract was awarded to the consortium of
companies CPD (Estonia) and Safege Baltija (Latvia).
Stakeholders’ involvement
One of the most challenging tasks of the programming process is to design the content of
the new programme. As the first step, the Member States had to agree on the cooperation
areas based on the 11 thematic objectives as presented in Article 9 in the proposal of the
Regulation by the European Parliament and the Council laying down common provisions for
the European Social Fund, for the European Regional Development Fund, the Cohesion Fund,
the European Agricultural Fund for Rural development and Fisheries Fund covered by
Common Strategic Framework. The areas were identified via consultations with the regions
and the Member states decided to research the following fields further:
1) Education (including higher education, vocational education, hobby schools, adult
education (based on the TO 10)
2) Transport networks and accessibility including physical transportation and ICT
(based on the TO 9)
3) Environment and green economy renewable energy, energy saving, energy
independency (based on the TO 6)
4) Business development and competitiveness (based on TO 3)
5) Employment and labour market needs combined with the lifelong learning (based on
TO 8)
Four of these five seminars were organised in 2012.
The early involvement has ensured transparency and pro-activeness, as the information
about the Programme preparation is proactively accessible. In general, the constant
communication with the stakeholders helps indicating priorities, specifying information and
17
needs within each priority topic, and compiling situation analyses upon which the content of
the programme will be designed.
The overall objectives of the seminars were to identify on a bottom-up basis the main
problem areas and sub-themes in the specific fields, and the possible solutions, actions and
measures that could be supported from the next Estonia-Latvia programme. The seminars
were organised as moderated discussions and group work, using a brainstorming
methodology. During the seminars 2-3 brainstorming sessions were organised which were
focusing on the following issues: identifying the main problems, suggesting possible actions
for the next programme period and coming up with concrete ideas for possible projects,
which could be submitted during the next programme. Finally, the participants were asked
to vote for the ideas they considered most important.
The first seminar was held with the stakeholders and experts in the field of education, and
took place on 27 June 2012 in Salacgriva, Latvia with 42 participants. During the seminar 3
brainstorming sessions - individual and in group - were organised.
In the first session the participants identified a large number of existing problems, which
were grouped by the moderators into 5 areas:
1. Quality and Content of Education. The problems identified under this sub-topic
reflected the general idea that the quality of the education needs to be improved
on all levels, starting with primary and secondary education and finishing with
higher education.
2. Better Links between Education and Labour Market. The topic highlighted mostly
the challenges how to better adapt the focus and content of education with the
real needs of companies.
3. Building joint vision and strategy for Estonia-Latvia cooperation. The topic
highlighted lack of coordination and planning between Estonian and Latvian
policy makers in the area of education. Many problems in both countries could be
better addressed if it would be done jointly and with shared resources.
4. Life-long learning and continuing education. The main problems identified were
related to the shortage and accessibility of life-long learning possibilities. Another
major problem area was linked to the fact that e-learning possibilities are not
effectively used and properly promoted.
5. Role of education for regional development. This topic highlighted mostly the
problems related to the role educational institutions in local and regional
development.
The actions that were voted as the most important for cooperation were: strengthening
cooperation of vocational education centres (ranked 1st); support increased qualification of
teachers and adaption of teaching curricula to industry/business needs (ranked 2nd);
integrating real business elements into education (ranked 3rd).
18
Concrete project ideas identified as most important were: elaboration of Estonian-Latvian
language teaching materials (ranked 1st); vocational schools networking (teachers trainings
and exchanges) (ranked 2nd and 3rd); joint training of specialists for cross-border (business)
projects (railway, wind parks etc.); future strategic projects between Estonia and Latvia
(ranked 2nd and 3rd).
The second seminar was held with the stakeholders and experts in the field of
transportation and accessibility, which took place on 18 October 2012 in Valga, Estonia. The
discussion seminar was held in a group of 24 experts and specialists from relevant ministries,
regions, local authorities and road administrations. The seminar also took into account the
outcomes of the Latvia - Estonia Intergovernmental Commission meeting that was held a
week earlier on 9-10 October in Pärnu, Estonia.
The discussion was structured under three topics; the problems and the ideas were
mapped relevantly. With each topic, the discussion followed three aspects:
- Strategic plans in the state level (members of ministries)
- Plans and needs on the local level with cross-border impact (members of
municipalities)
- Concrete ideas, objects and their estimated approximate cost.
• Railways. To apply for railway projects was not considered to be reasonable as the
states have more resources from other funds (Cohesion fund, TEN-T) to finance bigger
railway projects. Programme resources should come to the local level.
• Waterways. Very much related to the tourism (e.g. yachting as tourism segment,
connect all small harbours – agree on standards for harbours, improve the infrastructure
(similar standards – access to water, electricity), marketing campaign. As for the ferry
lines: the programme should not support daily operating activities, but investments and
infrastructure.
• Roads. It was discussed to be reasonable to support roads that connect bigger towns
rather than small roads with low density of traffic; key word is connectivity. The
bottlenecks on existing roads, dangerous places in the border area should be identified
and improved. To see the bigger complex picture: e.g. link to education when the
number of schoolhouses is decreasing: access to schoolhouses, cycle roads to connect
villages and small towns etc.
Taking into consideration that the financial capacity of the Estonia – Latvia programme is
relatively small for large investments, it might be reasonable to concentrate on either 1-2
bigger strategic investment objects or several smaller scale service improvement
activities in the area of transport and accessibility. The rating of the listed objects and
ideas emphasised the cooperation interest in sea area (passengers and ferry lines - 8
points; yacht and tourism development at ports - 7 points), which are also strongly
related to the tourism development.
19
The third seminar was held with the stakeholders and experts in the field of
environment and green economy, which took place on 6 November 2012 in Valmiera,
Latvia. Altogether 30 persons participated representing the range of specialists from the
relevant ministries, local authorities, and environmental organisations. The discussions
were held under 5 following sub-topics that were identified after grouping all indicated
problems from the first individual brainstorming:
- Energy
- Urban planning, waste management
- Nature protection
- Water and coastal issues
- Awareness and education
Most important measures and actions mentioned were the following: using renewable
energy sources, renewable energy planning; saving energy in buildings; green infrastructure;
water, parks, recreational area (riverbanks etc.) - to make it attractive for people; eco traffic
system in urban and rural areas; bicycle paths (urban and rural); re-designing brown areas
(industrial and military fields); waste management; development of joint methodology for
ecosystem service (assessment and evaluation); work out joint set of management rules for
cross-border protected areas and joint visitors’ infrastructure (nature centres); pilot projects
and good practices for managing cultural heritage sites (both privately and publicly owned);
generate local nature products and services for tourists, support for product development,
branding, marketing; best practice in management of Natura 2000 sites; the Baltic Sea coast
protection.
The seminar showed the high importance of the issue of energy and resource saving, yet the
investments are too big and cross-border effect needs to be specified. Awareness and
education on green economy is needed and this could be implemented as a supportive
activity in parallel with any other action. Urban planning and waste management is
important, but organising this in cross-border cooperation is a challenge as the country-
specific regulations could be an obstacle. Nature protection was the most common
cooperation area.
The forth seminar was held with the stakeholders and experts in the field of business
support, and took place on 28 November 2012 in Kopra Farm, Viljandi County, Estonia. The
focus of the discussion was on supporting the SMEs, therefore it targeted the
representatives of organisations and authorities in the programme area that were involved
with supporting the SMEs on a daily bases.
The seminar focused on the following subtopics: public sector’s support to businesses;
business to business activities; capacity of SMEs: product development, R&D, innovation; life
in rural areas. The most important actions and measures to overcome the problems
mentioned in the seminar were the following:
20
- Creating a meeting point (15 points). Physical and virtual meeting place for SMEs, start-
ups, unions, local government, investors, etc. Purpose: to consult, coach, network,
exchange, finance.
- Separate small project fund for border areas (12 points). To consider both land and sea
border.
- Clustering (9 points). Joint marketing / tender etc.
- Market research projects (5 points). Virtual networks. Business meetings.
- Creating risk capital (5 points). Fund for export, start-up’s, fast growing businesses.
- Regional marketing (5 points). Cross border marketing.
- Developing rural infrastructure (incl. business infrastructure) (4 points).
It was emphasised at the seminar that support for the SMEs is most effective when
comprising a strong practical output and impact for small businesses daily action.
Therefore practical benchmarking trips lead by competent coordinators, social events for
trust building, and individual contacts can be the most beneficial methods for long term
impact, and are highly valued among SMEs.
The results of the seminars will be further discussed by the JPC members in order to
finalise the selection of topics and to meet the needs of the area in the best possible
way.
Impact of the projects on the Programme environment
As the programme period nears its end and many projects have already been completed, the
Programme authorities continue to hear positive stories about the impact of the
implemented projects. Most project implementers and beneficiaries agree that the projects
have left an impact on their communities and helped develop connections and products that
otherwise would have not been possible. According to several impact interviews that were
conducted in 2012 with the partners of the finished project and also written feedback that
has been received, projects not only achieved their intended goals but lied ground for other
future cooperation activities between Estonians and Latvians either in other territorial
cooperation programmes, in business contacts or just in the area of cultural and social
exchange.
Protolab network partners in Tartu, Ventspils and Ogre noted that the project helped them
establish a cross-border network of prototyping laboratories, thus sharing individual
experiences and specializing in various areas of prototyping. Now partners can easily direct
potential clients to the best possible service provider. Also, the establishment of the network
is helping these specialized laboratories to cooperate with clients from the business and
research sectors not only in their home markets but also internationally.
Representatives of the project admitted said the project implementation period coincided
with the economic recession, and the project funds and challenges helped their
21
organizations to survive through the toughest times, when the funding from other sources
was minimal or non-existent. The laboratories were able to develop also during those slower
times and now, when the economies have recovered, are ready to provide services to
innovative companies. The greatest benefit from the project, as all three sides noted, are the
contacts with partners in the neighbouring country, which have already been used in putting
together and implementing other joint projects as well as development of business relations.
Estonian partners from Tartu are finding ways to the Latvian clients through partners in Ogre
and Ventspils, while Latvian partners find new markets for prototyping services in Estonia
and even Scandinavian countries through their Tartu counterparts.
Representatives from Cultural Cooperation for Intermediates project similarly value most
the contacts established across the borders. They point out that some of the cultural
traditions, started during the project, are now continued on a voluntary basis. Now it has
become easy to pick up the phone and call their counterparts across the border and invite
them to perform at a local cultural event. The infrastructure that has been renovated in the
framework of the project helps attract more people to the social and cultural activities in the
community, claims the director of one of the renovated culture houses. In some cases the
number of people participating in local cultural groups have doubled. Simple investments
into infrastructure, such as renovation of bathrooms or instalment of lighting equipment in
small rural culture house are still talked about and appreciated by the beneficiaries.
Alūksne – Haanja Uplands project representatives told that besides improved contacts with
the neighbours, the project helped to upgrade the qualifications of many skiing and biathlon
trainers and judges. They are now able to find work opportunities and although it was one
small part of the project, it changed the lives of many individuals in the situation of
economic recession and unemployment in the region. They are able to find jobs for training
or judging. Some of the traditions of visiting competitions across the border were created
with the help of the project.
Est-Lat-Pharma project representatives have told us that the project has helped them
establish new working contacts between pharmaceuticals industry and research bodies in
Estonia and Latvia. Now the cooperation in this fast growing and developing industry is much
smoother than before, which also helps to develop new products and attract new customers
from new markets, including in Western Europe.
In general the effect created by the projects is usually greater than the project partners
expected during the preparation process, as cross-border cooperation and new contacts
have widened their horizon and created new opportunities. In many cases the intensity of
cooperation is high also after the end of the project with project partners clearly benefiting
from it. While most of the benefits often stay within partner organisations or within a limited
group of experts, there are also projects with wider and more visible impact. The most
22
intensively used public sites improved with the help of the Programme are probably the
reconstructed cross-border roads in south-western Estonia and Northern Latvia, and large
recreational area in the centre of Valga/Valka on the border of Estonia and Latvia. But also
small-scale cooperation projects, which have altogether attracted tens of thousands of
spectators and participants in the fields of singing, dancing, art, handicraft, various sports
and youth cooperation have increased visibility of the Programme in the border area and
enlivened the idea of cooperation in the region.
Last, but not least, the Programme has also managed to support entrepreneurship in the
region, which initially did not go so smoothly. The projects like Good Fruit, ProtoLab
Networks, BaltOrgPotato, Food Art, Buy Local, SIB Net and Est-Lat Pharma have all
contributed to development of entrepreneurship and supported especially small companies
to define and fulfil their plans.
2.2 Information about compliance with Community Law
The Programme has been set up and is implemented according to the relevant Community
legislation: Regulation (EC) no 1080/2006 of 5 July 2006 on the European Parliament and of
the Council on the European Regional Development Fund; Council Regulation (EC) no
1083/2006 of 11 July 2006; Commission regulation (EC) No 1828/2006 of 8 December 2006
setting out rules for the implementation of Council Regulation (EC) No 1083/2006;
Commission Regulation (EC) No 846/2009 of 1 September 2009 amending Regulation (EC)
No 1083/2006; Commission Regulation (EU) No 832/2010 of 17 September amending
Regulation (EC) No 1828/2006.
The applicable legislative acts are available on the Programme web-site and appropriate
provisions have been included into the Programme Manual. In addition, the subsidy contract
signed between the Managing Authority and the lead partner lists all relevant Community
legislation as well as refers to the Estonian and Latvian national legislation to be followed in
the implementation of the projects.
The changes in the Community and national legislations are followed on a regular basis and
if necessary, the approved legislative changes will be incorporated in the Programme
documents. So far there have been no problems with the implementation of the operational
programme regarding Community Law.
2.3 Significant problems encountered and measures taken to overcome
them
In 2012, some significant problems were identified by the second-level audit. These concern
two projects: “Baltic small harbours network” (“Baylink”) and “Raising the attractiveness
and competitiveness of North Kurzeme in Latvia and Saaremaa Island in Estonia by
improving tourism environment and its offer using the natural advantages of coastal
municipalities” (One vacation – Two Countries”).
23
Regarding the project “Baylink”, the contracting authority, Mersrags Port Authority has not
followed the certain provisions of the Latvian national legislation and of the Subsidy Contract
signed for the implementation of the project. The infringements concerned the following:
Incorrect amendments of the employment contracts of some employees of the
Mersrags Port Authority. These amendments stipulated overtime work for the
project, whereas overtime work according to the Regulation No 89 adopted on 27
January 2009 of the Cabinet of Latvia is ineligible.
The requirements set for the project manager in the project application and in the
tender documents were not followed thus the selection of the best possible
candidate was not ensured.
Regarding the project “One vacation – Two countries”, the case concerned the Estonian
partner, Kuressaare Municipality. One sub-objective of the project was to get the Blue Flag
for the beaches of Kuressaare municipality and for Ventspils city (LV). However, by the time
of the application for the Blue Flag by Kuressaare municipality, the Estonian organisation
“Keep the Estonian Sea Tidy”, which coordinated the Blue Flag application procedure, had
withdrawn its membership from the international organisation granting the Blue Flag
certificate. Unfortunately the Kuressaare Municipality was not aware of this situation. In this
case the amendment to the Subsidy Contract should have been formalised in order to
change the sub-objective, however this was not done. Yet Kuressaare Municipality had
implemented all activities and made all investments related to this sub-objective, which
considerably improved the conditions of the beach therefore making it more attractive for
the tourists as well as for the local people. However, it is only in the competence of the
Foundation of the Environmental Education to tell whether the activities were sufficient for
the obtaining the Blue Flag.
As a result of these infringements the error rate of the of the audited operations was 6,32%.
The Programme authorities have seriously considered these findings and taken measures to
improve the management system. The procedures of the first level control are re-checked
and special attention is paid to the verification of procurements. The procurement checklists
have been reviewed to ensure that all procurement types are covered. Also the need for the
procurement expert in the Programme is assessed.
The JTS reinforces its monitoring system – in addition to the Programme consultant and the
project partner, the site visit reports will be reviewed and signed also by the Head of the
Secretariat. The Programme Manual will be further complemented by the cases requiring
the amendments of the Subsidy Contract.
However, it could be mentioned that measures taken in 2011 to decrease the risk of de-
commitment (e.g. introduction of flat rate for administration costs, pre-payment system),
24
which were described in the Annual Report 2011, have helped to achieve the target level of
expenditure to avoid de-commitment till the end of the Programme. Nevertheless, the JTS
will continue close monitoring of the spending rate of projects and will ask also quarterly
updates from the project partners on their expenditure plans to be able to react quickly in
case the risk of de-commitment rises again.
2.4 Changes in the context of the operational programme implementation
In order to monitor changes in the context of the operational programme implementation,
10 context indicators have been listed in the programme document. Mostly the trends of
context indicators reflect macro-level developments in Estonia and Latvia, and more
specifically also in the programme area.
In 2012 both Estonia and Latvia showed clear evidence of coming out of economic recession.
The first signs of passing recession were visible already in 2010 and 2011 and in 2012 these
trends continued. Compared to 2011 unemployment rate decreased from 10,80 % to 10,24
% in the programme area in Estonia and from 13,88 % to 13,65 % in the programme area in
Latvia, the growth of GDP per capita was 5,6 % year on year in Estonia and 9,9 % year on
year in Latvia; and increasing number of enterprises and NGOs in the programme area both
in Latvia and Estonia.
Also more specific context indicators show positive trends, including growing number of
households with internet access in the programme area, by 69,61 % in Estonia and 68,70 %
in Latvia in 2012 compared to 2011 and steady raise in number of tourists, both domestic
and foreign by 7,9 % in Estonia and 17,2 % in Latvia in 2012 compared to 2011.
2.5 Substantial modification pursuant to Article 57 of Regulation (EC) No
1083/2006
There have been no cases of investments in infrastructure or productive investments,
undergoing substantial modifications, caused by a change in the nature of ownership or
cessation of productive activities, affecting the nature or the implementation conditions of
the operation or which gave to a firm or a public body an undue advantage in 2011 – as
stipulated in paragraph 1 under Article 57 of the Council Regulation (EC) No 1083/2006 of 11
July 2006, amended by Regulation (EU) No 539/2010 of the European Parliament and of the
Council of 16 June 2010.
2.6 Complementarity with other instruments
As in 2012 only strategic projects were supported by the Programme and these strategic
projects were pre-selected by the member states, initially the member states checked that
the projects, were not financed from any other sources.
25
During the assessment procedure, in order to avoid double financing, the JTS checks the
projects stored in Enterprise Estonia database, which have a link with the project
applications submitted under Estonia – Latvia Programme and may have received financing
from the ERDF or ESF. In addition similar checking is performed in SFOS system, which is an
operative system of Structural Funds in Estonia, managed by the Ministry of Finance and
includes information on the projects financed under ERDF, ESF and CF.
On the Latvian side, similar procedures are carried out by Latvian National Responsible
Authority. More precisely, Latvian National Responsible Authority carries out cross-checking
with the relevant ministries to find out, whether similar activities have already been financed
by other financing sources.
Also the lead partners confirm by signing the application form, that the project, either in
whole or in part, has not received or will not receive any complementary EU funding during
the whole duration of the project. In addition the applicants are asked to describe any links
to on-going and/or finalised related programmes, projects and activities, and explain the
added value to be created through a particular project.
None of the strategic projects received financing in the field of agriculture in 2012 therefore
there was no need to do cross-checking with the Estonian Agricultural Registers and
Information Board, which was done during the previous years.
2.7 Monitoring and evaluation
The general basis for all the actions related to the proceedings of the project applications
and reports are the Programme Manual and rules of procedure of the Monitoring
Committee.
The technical tool for the proceedings regarding project application and monitoring of the
projects is Navision (internal electronic database of the Enterprise Estonia for project related
information, adjusted for the needs of Estonia – Latvia Programme). All documents related
to different project processing steps are uploaded in Navision, which enables to follow the
progress of a particular project.
On a project level, the JTS is carrying out regular site visits to each running project. On
average each project is visited ca 2 times by the JTS during its implementation. The
Programme consultants also try to participate in project meetings (especially kick-off
meetings), events or openings of investment objects. These visits significantly help the JTS
staff to get a real overview of the project activities and partners, and establish stronger
working relationship with the project staff. During the site visit, the “Site visit form” is
completed, where the results of the visit are described. In 2012 the JTS carried out 30 site
visits to projects.
The site visits are also carried out by Estonian and Latvian first-level control bodies. They,
inter alia, check the accuracy of the accounting system and the correct filing of
documentation including public procurement documents, verify themselves on the existence
26
of the goods and services procured or delivered during the Programme. In 2012, total 38 site
visits were carried out by Estonian and Latvian first-level controllers.
The first-level controllers check the partner reports and ultimately issue a confirmation on
the acceptance of the report to the lead partner of the project. Relevant information is also
sent to the project partner. On the basis of the approved partner reports the lead partner
compiles a progress report, which is sent to the JTS for approval and for further submission
for a payment.
Each progress report, when submitted for a payment to the CA, is accompanied by a letter
signed by the Head of the JTS confirming that the project has been so far duly implemented,
is in accordance with all set requirements and the applied amount comprises of eligible
expenditure only.
On the Programme level, the Managing Authority follows, through information received
from the JTS, FLC or from Navision, the implementation of the projects. The Managing
Authority submits a confirmation letter to the Certifying Authority on due implementation of
the Programme bi-annually. The letter is accompanied by a site visit table, which summarises
the information of the visits carried out by JTS and FLC as well as by the table on the
implemented audits. In case some shortcomings are identified, a deadline is provided for
their elimination in the site visit, and in the audit table.
2.8 EU Strategy for the Baltic Sea Region
Estonia - Latvia Programme 2007-2013 includes South, and West Estonia NUTS III regions
and North, West and part of the Central Latvia NUTS III regions. Thus the Programme area is
quite limited. Also most of the projects are of rather local character and impact, focusing on
the cooperation of local municipalities, foundations, NGOs in the border regions of the two
countries. The EU Strategy for the Baltic Sea Region is targeted at a macro-region and should
have a trans-national or at least inter-regional impact. Because of its local focus, the
Programme does not contribute directly to the implementation of the EUSBSR, as the small
projects do not have a wider trans-national impact.
However, as both countries are situated in the Baltic Sea region and the Estonia - Latvia
Programme is called forth to improve the situation in the border areas of Estonia and Latvia,
it has been decided to take EUSBSR on board to the extent it is considered appropriate and
feasible for the Programme. The projects which results have a wider impact and can be used
in the whole Programme territory or beyond it or which could create new development
potentials in the area the project is implemented have been identified as contributing to the
EUSBSR. The projects’ objectives and activities should also directly comply with the priority
areas of the Action Plan concerning the European Union Strategy for the Baltic Sea Region.
The labelling is done in cooperation between National Responsible Authorities, Joint
Technical Secretariat and Managing Authority.
27
Altogether 11 projects have been considered to have a link to the EU Strategy for the Baltic
Sea Region, and these links have been noted on the Programme website (at each project
description). In 2012, one new project was identified as contributing to the EUSBSR: „Costal
and Maritime Spatial Planning”. The table including the projects contributing to the EUSBSR
is added as Annex 4 to the report.
In 2012 the Programme Information Manager participated in two EU Strategy for the Baltic
Sea Region and at one of them presented Estonia – Latvia Programme storytelling example –
a documentary segment about the Reconstruction of Karksi-Nuia – Seda River cross-border
road, thus sharing the Programme experience in communicating its contributions to the
EUSBSR.
28
3 IMPLEMENTATION BY PRIORITY
Chart 1: Financial overview at the end of 2012
3.1 Priority 1 Increased cohesion of the Programme area
3.1.1 Achievement of targets and analysis of the progress
Table 4: Overview on the fulfilment of indicators under the 1st priority
Indicator Objective Baseline 2007
Achievement – 2012 (based on
project application
forms)
Programme target -
2015
Fulfil-ment % - 2012
Priority 1
1.Number of projects
creating new or
improving the existing
cross-border transport
connection links
Improved physical
connectivity of the
Programme area 0 5 10 50%
2.Number of projects
improving access to ICT
networks or services
Improved physical
connectivity of the
Programme area 0 3 10 30%
29
3.Number of projects
developing joint use of
infrastructure
Enhanced joint
management of public
services and resources
in the Programme area
0 9 5 180%
4.Number of projects
developing
collaboration in the
field of public services
Enhanced joint
management of public
services and resources
in the Programme area
0 10 5 200%
5.Number of projects
finding joint solutions
to similar
environmental
problems
Enhanced joint
management of public
services and resources
in the Programme area 0 9 10 90%
6.Number of people
participating in joint
education or training
activities
Increased knowledge
and capacity of the
target group 0 2134 300 711%
Table 5: Priority 1 by direction of support
Direction of support ERDF
allocation
ERDF committed
2012
ERDF committed
total
% of committed
ERDF ERDF paid
1.1 Reducing isolation through improved internal and external connectivity of the Programme area
21 914 737
4 949 994 12 091 680 54% 4 296 675
1.2 Enhancing joint management of public services and resources
1 629 735 10 151 476 46% 4 963 124
Total 6 579 729 22 243 156 100% 9 259 799
In total, twenty one projects have been supported under priority 1 – seven projects under
direction of support 1.1 and fourteen under direction of support 1.2. In 2012 five projects of
strategic importance to Estonia and Latvia were approved under priority 1, three under 1.1
and two under 1.2. At the end of 2012, the amount over-committed under this priority was
328 419 EUR. Although, the over-committed amount is steadily decreasing, as all the
finished projects report certain under spent sums, priority 1 might face a small shortage of
funds in the end of the Programme, which can be up to 67 000 EUR based on the newest
forecasts. However, on the Programme level no shortage of funds should appear in the end
of the period, thus re-allocation of funds between priorities should be sufficient for covering
a possible shortage under priority 1 in 2015.
As it was predicted in the annual report of 2011, major improvements took place concerning
the payment rate of priority 1 in 2012. While by the end of 2011 only 2.88 MEUR were paid
30
out to the beneficiaries, by the end of 2012 more than 9.25 MEUR are paid out, which
constitutes over 42% of the ERDF allocation for the priority. It means that the payment
amount was more than two times higher in 2012 than during all the previous years of the
Programme. Mostly it was caused by large payment requests of road construction projects.
Also the status with fulfilment of indicators has improved under priority 1, as five out of six
strategic projects approved in 2012 belong under priority 1. Especially the increased
fulfilment rate of two indicators with the lowest rates („Number of projects creating new or
improving the existing cross-border transport connection links“ and „Number of projects
improving access to ICT networks or services“) must be appreciated. Nevertheless, these two
indicators remain with the lowest fulfilment rates with the reasoning provided in the annual
reports for 2010 and 2011.
3.1.2 Significant problems encountered and measures taken to overcome them
There were no significant problems encountered related to priority 1.
3.2 Priority 2 Higher competitiveness of the Programme area
3.2.1 Achievement of targets and analysis of the progress
Table 6: Overview on the fulfilment of indicators under the 2nd priority
Indicator Objective Baseline
2007
Achievement – 2012 (based on
project application
forms)
Programme target -
2015
Fulfil-ment % - 2012
Priority 2
1.Number of projects
promoting
entrepreneurial spirit
and skills
Increased overall
economic
competitiveness of the
Programme area
0 11 15 73%
2.Number of projects
supporting the
development of
economic activities
with higher value
added
Increased overall
economic
competitiveness of the
Programme area 0 12 20 60%
3.Number of projects
encouraging the
development of cross-
border trade
Increased overall
economic
competitiveness of the
Programme area
0 7 10 70%
31
4.Number of co-
operation projects
between enterprises
and research or
education institutions
Increased overall
economic
competitiveness of the
Programme area
0 9 10 90%
5.Number of new or
improved joint tourism
products or services
Increased
attractiveness of the
Programme area for
visitors
0 20 20 100%
6.Number of projects
developing joint use of
infrastructure
Increased
attractiveness of the
Programme area for
visitors
0 6 10 60%
7.Number of
entrepreneurs
benefiting from the
projects aimed at
improving the business
environment
Increased capacity of
business operators in
the Programme area 0 942 300 314%
8.Number of people
participating in joint
education or training
activities
Increased knowledge
and capacity of the
target group 0 2475 1400 177%
Table 7: Priority 2 by direction of support
Direction of support ERDF
allocation ERDF committed
2012 ERDF
committed total
% of committed
ERDF ERDF paid
2.1. Facilitating business start-up and development
10 426 615
0 3 581 215 33% 2 748 276
2.2. Increasing the attractiveness of the Programme area
1 800 000 6 716 603 62% 3 889 869
2.3. Enhancing employable skills and human resources
0 475 600 5% 250 829
Total 1 800 000 10 773 419 100% 6 888 974
Altogether sixteen projects have been financed under priority 2, nine under direction of
support 2.1, six under direction of support 2.2 and one under direction of support 2.3. One
strategic project was approved in 2012, which belongs under direction of support 2.2. At
the end of 2012, the amount over-committed under this priority was 346 804 EUR. However,
the over-committed amount is steadily decreasing, as all the finished projects report certain
under spent sums. Based on current forecasts up to 110 000 EUR could remain unspent
under priority 2 by the end of the Programme, unless these funds are allocated for
additional activities of the already running projects, as there is no reserve list of projects
32
under priority 2, or re-allocated to priority 1, which might face a small shortage of funds in
the end of the period.
The payment rate under priority 2 continues to be good with 2/3 of the total ERDF allocation
of the priority being paid out by the end of 2012.
The status with fulfilment of indicators has not changed much compared to 2011, still the
only project approved under direction of support 2.2. has made a significant shift in
fulfilment rate of the indicator “Number of new or improved joint tourism products or
services” from 25% last year to 100% this year. For the rest of the indicators more
explanations have been provided in annual reports for 2010 and 2011.
3.2.2 Significant problems encountered and measures taken to overcome them
There were no significant problems related to priority 2.
3.3 Priority 3 Active, sustainable and integrated communities
3.3.1 Achievement of targets and analysis of the progress
Table 8: Overview on the fulfilment of the indicators under the third priority
Indicator Objective Baseline 2007
Achievement – 2012 (based on
project application
forms)
Programme target -
2015
Fulfil-ment % - 2012
Priority 3
1.Number of projects
improving services for
the communities
Improved availability of
services in the
Programme area 0 17 10 170%
2.Number of projects
increasing the activity
of local communities
Increased activity of
the local communities 0 26 10 260%
3.Number of rural
municipalities involved
in project
implementation
Increased activity of
local communities in
the Programme area 0 41 80 51%
4.Number of non-
governmental
organisations involved
in project
implementation
Increased activity of
local communities in
the Programme area 0 45 40 113%
33
5.Number of
participants benefiting
from joint social and
cultural activities
Increased social and
cultural integration of
the people in the
Programme area
0 51984 40000 130%
6.Number of people
participating in joint
education or training
activities
Increased knowledge
and capacity of the
target group 0 8625 300 2875%
Table 9: Priority 3 by direction of support
Direction of support ERDF
allocation
ERDF committed
2012
ERDF committed
total
% of committed
ERDF ERDF paid
3.1 Improving the environment for active and sustainable communities
3 593 484
0 1 433 857 40% 959 582
3.2. Promoting grass-root level actions
0 2 144 166 60% 1 416 059
Total 0 3 578 022 100% 2 375 641
Altogether twenty six projects have been financed under this priority, seven projects under
direction of support 3.1 and nineteen projects under the direction of support 3.2. In 2012,
no projects were approved under priority 3. Although it was predicted in the Annual Report
of 2011 that at least one of the priority 3 projects from the reserve list can be approved in
2012 it did not happen as there was not enough funding released from under spending of
finished projects yet. Compared to last year’s financial status of priority 3 with over-
commitment of 87 774 EUR the situation is more promising at the moment with 15 462 EUR
ready to be committed, but this is not sufficient for the first project in the reserve list, which
requests 107 310 EUR ERDF support. Based on the spending forecasts submitted by the lead
partners of the running projects such sum should be available by the time all the running
projects are finished, but hopefully the project could be contracted already earlier, i.e.
within 2013, to allow full implementation of the project before the closure of the
Programme. Thus, the JTS continues close monitoring of the spending rates and forecasts of
running projects under priority 3 and as soon as sufficient funds are available the first
project in the reserve list will be contracted.
The payment rate under priority 3 continues to be good with 2/3 of the total ERDF allocation
of the priority being paid out by the end of 2012.
As no projects were financed under priority 3 in 2012, the situation with fulfilment of
indicators has not changed and relevant chapter of previous annual report covers the topic.
34
3.3.2 Significant problems encountered and measures taken to overcome them
There were no significant problems related to priority 3.
Chart 2: Share of each direction of support to the total funding
4 MAJOR PROJECTS
Financing of major projects is not applicable in the framework of the Estonia – Latvia
Programme 2007-2013
5 TECHNICAL ASSISTANCE
The overall allocation of Technical Assistance in the Programme is 6 413 396 EUR with the
Community funding being 2 293 713 and national co-financing 4 119 683 EUR. The
Community share made up 35,76% of the total allocation but as mentioned before in the
report, with the Amendment of the Operational Programme the ERDF allocation was raised
up to 49%.
The total approved TA budget for 2012 was 626 732 EUR. In total, the eligible expenditure of
the TA was 452 940 EUR in 2012. For the period 2007-2012 the total eligible expenditure of
the TA amounts to 2 170 209 EUR. These figures reflect the sums confirmed by the First
Level Control bodies. The certified amounts are provided in the chapter 2.1.2 above, in table
1.
35
TA budget and work plan for 2012 were approved by the Monitoring Committee on 6
February 2012. TA budget was amended once in 2012, the following amendments were
approved at the MC meeting on 4 December 2012:
Amendments to the budget of the Joint Technical Secretariat
1. Budget line “Labour costs”:
The annual planned sum for the budget line “Labour costs” was decreased from
249 600 EUR to 232 600 EUR, as the staff costs of Tartu office were not used in
planned extent due to leaving of one programme consultant in June 2012, whose
position was not filled during the second half of 2012, and parental leave of the head
of the JTS during the second half of 2012.
Costs of the programme preparation expert for Estonia - Latvia Programme 2014-
2020 were added, as since August 2012 an expert has been employed at the JTS.
2. The annual planned sum for the budget line „Office expenses“ was increased from
29 400 EUR to 30 400 EUR , because the costs for announcing the vacancy of the
programming expert’s position at the JTS had not been planned in the JTS budget.
3. Annual planned sum for budget line „Publicity and marketing“ was increased from
57 100 EUR to 73 100 EUR, as the costs for celebrating the European Cooperation Day
and producing a documentary movie about the Estonia - Latvia Programme was more
expensive than planned.
4. Room rent and catering at other meetings organised by the JTS was added under the
budget line “Programme Meetings’ costs”, because JTS organised a meeting in Tartu in
July 2012 for information managers of CBC programmes active in Estonia and Latvia in
order to coordinate European Cooperation Day celebration activities.
5. Budget line “External expertise, analysis”:
Monitoring implementation of approved projects was added, as in the end of June
2012 one of the programme consultants left the JTS and her employment contract
was terminated. However, the consultant has helped the JTS to conclude processing
of several projects – DemoFarm, FireSafe, ICT DCNet, Skills Centre and SIB-Net – in
the frames of a service contract.
Assistance to the acting head of the JTS and programme preparation expert was
added, because the head of the JTS is working for the JTS in the frames of a service
contract during his parental leave from June 2012 till May 2013.
Explanation of the JTS budget
The labour costs included:
1) Staff costs of an information manager, assistant, 4 programme consultants,
programme preparation expert and the head of the JTS, all full time positions;
2) 1 full time information point manager and part-time support staff of the State
Regional Development Agency;
3) Staff costs of the position of 1 controller of the Latvian FLC;
36
4) Staff training costs.
Office expenses included:
1) Office costs of the JTS office in Tartu (rent, utilities, stationary), office equipment,
communication costs, costs for publishing job offers;
2) Office costs of the Information Point in Riga (rent, utilities, stationary), office
equipment and communication;
3) Office costs of 1 Latvian FLC controller's position.
Travel and accommodation costs included:
1) Travel and accommodation costs of the JTS staff;
2) Travel and accommodation costs of the FLC staff for participating in 4 trainings;
3) Travel and accommodation costs of 1 Latvian FLC controller's position;
4) Travel and accommodation costs of the Monitoring Committee (MC) members,
related to participation in the MC meetings;
5) Rent, fuel and maintenance of a car of the JTS.
Programme Meetings’ costs included:
1) Room rent and catering at 2 MC meetings in Estonia;
2) Room rent and catering at 1 meeting between Estonian and Latvian FLCs and the JTS;
3) Room rent and catering at a few other working meetings organised by the JTS in
connection with implementation of the Estonia – Latvia Programme.
Database costs included:
1) Development of the database of Enterprise Estonia according to the needs of the
Estonia - Latvia Programme.
External expertise, analysis costs included:
1) Translation and interpreting costs;
2) Assessment of construction documentation attached to project applications by
construction expert;
3) Workshops on communication and seminars in Estonia and Latvia on procurement
issues – altogether 6 trainers;
4) Monitoring implementation of approved projects;
5) Assistance to the acting head of the JTS and programme preparation expert.
Publicity and marketing costs included:
1) Annual conference of the Estonia – Latvia Programme 2007-2013;
2) Promotion of the ETC day;
3) Partner day to for partners of the running projects;
37
4) Events for partners of the running projects – seminars on reporting and publicity
requirements and on communications and procurement issues;
5) Website developments;
6) Newsletter design and translation;
7) Production of promotional materials (pens, reflectors, bags, stickers, flags).
Total sum for publicity and marketing costs for 2012 was a bit higher than that of 2011, as
for the first time the European Cooperation Day was celebrated in Europe and for the
Estonia – Latvia Programme it meant subcontracting production of several documentary
clips on the results of the projects and organising an annual conference in Võru, Estonia
focusing on the cross-border cooperation, its benefits and challenges.
Explanation of the MA, CA, AA budget
Labour costs included:
1) Labour costs of 2 full time employees in the MA, 2 part-time employees in the CA
with work load up to 60%, 1 full time employee in the AA;
2) Staff costs of the position of 1 controller of the Estonian FLC;
3) Ca 5 per cent for fringe benefit.
Wages of the employees of the MA, AA and CA for 2012 remained on the same level as in
2011, following the principles of the personnel policy of Estonian Ministry of the Interior.
However, as the workloads of the employees have increased and one full time position was
added to the First Level Control from the beginning of 2012, the total amount of labour costs
has increased.
Taking into account the phase of implementation of the Programme and the need to
manage de-commitment risk, the work load of the two employees of the CA increased due
to the increase of payment and pre-payment volume to the project partners as well as
keeping an account of amounts recoverable and withdrawn. Both employees of the CA spent
up to 60% of their time for the Estonia - Latvia Programme, in total this makes up 1.2 work
load for two persons.
Office expenses included:
1) Costs of translation;
2) Communication costs (landline and mobile phone costs);
3) Transportation costs;
4) Overhead costs – room rent etc;
5) Purchase of bureau equipment – 1 table and 1 dictophone to the CA, 1 laptop
computer and 1 laptop battery for the MA, workplace for 1 FLC controller if
necessary;
38
6) Room rent and catering at the meetings related to the Programme implementation,
including meetings of the Recovery Committee by the Certifying Authority, with the
Group of Auditors by the Audit Authority etc;
7) Costs related to trainings of the MA, AA, CA and 1 Estonian FLC controller’s position,
including MS Project software training, training and CGAP exam for the employee of
the Audit Authority etc;
8) Expertise – the following costs have been planned to the TA budget:
MA has planned 2 000 EUR for legal advice etc;
AA has planned 500 EUR for expertise related to the auditing of operations.
Travel and accommodation costs include:
1) Travel and accommodation costs of the staff, including
Travel and accommodation costs of 1 Estonian FLC controller's position;
Travel and accommodation costs of the Programme Authorities to MC meetings;
Travel and accommodation costs of the Programme Authorities, related to
participation in trainings in Estonia and abroad, including Interact-type of
trainings;
Travel and accommodation costs of the MA include attending COCOF meetings,
MA network meetings etc;
The costs of the AA for attending the meetings of the Group of Auditors and
carrying out site visits of the operations;
The costs of the Programme Authorities regarding participation in the activities
related to the preparation of the Estonia – Latvia Programme 20014-2020 and in
the Joint Programming Committee meetings.
Budget for the preparation of the cross-border programme between Estonia and Latvia for
the period 2014-2020
In addition to the costs of the Programme Authorities the TA costs also included the
preparation of the next co-operation programme between Estonia and Latvia for the period
2014-2020. The MC decided to allocate 150 000 EUR to cover the programming activities in
the years 2012, 2013 and in case of need in 2014.
The total available amount for programming activities is entered into the TA budget of the
Estonia - Latvia Programme 2007-2013 separately under ‘Preparation of the cross-border
programme between Estonia and Latvia for the period 2014-2020’. The detailed budget of
the programming activities was compiled and approved by the JPC.
The budget of the programming activities includes, but is not limited to the following types
of costs:
Travel and accommodation costs:
1) Travel and accommodation costs of the members of the Programming Committee.
39
Programme Meetings’ costs:
1) Room rent and catering at the meetings of the Programming Committee;
2) Room rent and catering at the meetings with the stakeholders.
External expertise, analysis costs:
1) Elaboration of the Operational Programme for the next period;
2) Carrying out the ex ante evaluation.
40
Table 10: Technical Assistance in 2012
Total Tartu
office Riga IP Total
Tartu
office Riga IP
Program-
ming
2014-
2020
Total Tartu
office Riga IP
Program-
ming
2014-
2020
Total Tartu
office Riga IP
Program-
ming
2014-
2020
Staff costs 773 651 661 076 112 575 232 600 178 600 54 000 180 062 158 125 21 937 953 713 819 201 134 512 0
Office expenses 137 311 114 699 22 612 30 400 24 400 6 000 24 230 20 719 3 511 161 541 135 418 26 123 0
Travel and accommodation 78 685 64 288 14 397 39 872 20 380 10 000 9 492 22 000 17 947 3 914 140 100 685 82 235 18 311 140
Programme Meetings (MC) 24 031 24 031 0 33 960 10 800 23160 12 126 4 277 7849 36 157 28 308 0 7 849
Database 39 856 39 856 0 3 000 3 000 0 1 499 1 499 0 41 355 41 355 0 0
External expertise, analysis 152 056 152 056 0 32 050 32 050 0 13 612 13 612 0 165 668 165 668 0 0
Publicity and marketing 132 626 132 626 0 73 100 73 100 0 65 797 65 797 0 198 423 198 423 0 0
Reserve 0 0 0 11 383 0 0 11383 0 0 0 0 0 0 0
JTS TOTAL 1 338 217 1 188 632 149 585 456 365 342 330 70 000 44 035 319 328 281 977 29 361 7 989 1 657 544 1 470 609 178 946 7 989
Labour costs 302 765 0 0 113 224 0 0 106 882 0 0 409 647 0 0
Office costs 31 670 0 0 21 940 0 0 5 862 0 0 37 532 0 0
Travel and accommodation 44 617 0 0 35 203 0 0 20 868 0 0 65 485 0 0
MA/AA/CA TOTAL 379 052 0 0 170 367 0 0 133 612 0 0 512 664 0 0
TOTAL JTS + MA/AA/CA 1 717 269 1 188 632 149 585 626 732 342 330 70 000 44 035 452 940 281 977 29 361 7 989 2 170 209 1 470 609 178 946 7 989
Eligible expenditure 2007-
2011Planned budget 2012 Eligible expenditure 2012 Total eligible expenditure 2007-2012
Joint Technical Secretariat
Managing Authority, Audit Authority, Certifying Authority
41
Table 11: Overview on the fulfilment of indicators under the Technical Assistance
Priority 4. Technical assistance
Indicator Objective Baseline
2007 Achievement
– 2012 Programme target - 2015
Fulfilment % - 2012
1.Percentage of all projects approved for funding implemented successfully
Efficient assessment, selection and monitoring procedures of the Programme
0 100% 95% 100%
2.Number of events, seminars and trainings organised for the publicity, information and capacity building about the Programme
Increased knowledge and capacity of the target group about the Programme 0 83 32 259%
3.Number of participants to different Programme events (conferences, workshops, seminars, trainings)
Increased knowledge and capacity of the target group
0 2732,
including 1835 female
1 200 thereof at least 50%
female
228%
6 INFORMATION AND PUBLICITY
6.1 Information and publicity activities
The information and publicity activities have been carried out in 2012 in accordance with the
Communication Plan approved by the European Commission in January 2009. The focus of
2012 activities has been on showcasing the Programme results through featuring project
partners and their achievements to various target audiences.
The following information, publicity and communication events were carried out by the
Programme in 2012:
An annual event of the Programme: International Conference on Border Areas
“Joint Experiences – New Challenges” on September 18-19, 2012 in Võru, Estonia,
with about 200 participants;
Annual partner day 2012 – event for the partners of approved projects on June in
Sangaste, Estonia;
– Information seminars for the partners of the approved projects (2 in Riga, Latvia and
2 in Tallinn and Tartu, Estonia);
42
– Specialized trainings for partners of the approved projects on procurement and
communication issues (2 events in Riga and Inčukalns, Latvia, and 2 events in Viljandi
and Tartu, Estonia);
– Production and broadcast of “Better Neighbours” documentary on ETV1, ETV2 in
Estonia and LTV1 and Re:TV in Latvia to an audience of more than 80,000 viewers;
– European Cooperation Day 2012 events during which project partners demonstrated
their achievements to local communities, all together 16 events in Estonia and Latvia;
– Programme newsletter – 2 editions, each in English, Estonian and Latvian;
– Regular updates of the Programme website, about a 100 stories on Programme and
project activities;
– Regular posts on newly established Programme social media pages on Facebook and
YouTube;
– Media activities in relation to approved projects.
In 2012, the main focus of all communication activities was communicating successful
implementation of projects and results achieved. The goal was to address broader
audiences, beyond the usual people involved in the Programme and project implementation.
Three man target groups were addressed:
- Programme stakeholders – all Programme authorities and people involved in
implementing the projects;
- Local communities – people from the regions that are directly benefiting from the
activities implemented by the project partners;
- General public – people from all walks of life that are interested in the results of
territorial cooperation and that potentially might be interested in submitting projects
during the next period.
Events for Programme stakeholders include all seminars and the Partner Day, as well as the
Programme’s annual event, International Conference on Border Areas „Joint Experiences –
New Challenges” that was organized around the European Cooperation Day to discuss the
results and future challenges of territorial cooperation in the area, attended by about 200
participants from Estonia and Latvia. Stakeholders also received the newsletter and other
materials that were sent out through Programme internal communication channels,
reaching more than 2000 people each time.
Local communities in the areas where projects are implemented had an opportunity to
participate in European Cooperation Day 2012 local open doors events, during which
project partners presented their work to people in their communities. It included open
43
lectures, open houses, small markets and demonstrations of project achievements. Local
communities also received news about the projects from the media.
For the general public in Estonia and Latvia the Programme prepared a 45-minute
documentary “Better Neighbours” about 8 projects that was broadcast on Estonian and
Latvian public television channels and re-run on Estonian Public Television’s channel ETV2
and Latvian Regional Television. In addition to TV, the documentary could be seen at
Programme events, on social media and web channels.
The Programme website www.estlat.eu was constantly updated, with around 100 news
items on running project events and Programme activities. New sections for European
Cooperation Day 2012, Planning for 2014-2020, International Conference on Border Areas,
Documentary “Better Neighbours” have been added. Estonian- and Latvian-language
sections have been significantly updated, including videos in Estonian and Latvian. Social
media plug-ins were integrated into the website, allowing people to share our news easier
on Facebook, Twitter and Latvian site Draugiem.lv, and inviting them to follow the
Programme on Facebook. The website was also presented in European Commission
competition RegioStars 2012, where it was selected among the finalists for the award in the
area of communication. All together from January 1 until December 31, 2012 the website
was visited by 14,720 unique visitors, 47% of whom returned to the site several times. 41%
of all visitors were from Estonia, 33 % from Latvia, 20% from other countries, mostly in the
European Union. Most popular things viewed on the website were news about the newly
approved projects, Programme documentary “Better Neighbours” and Programme vacancy
announcements.
The Programme website also contains a special section on each project, listing the project
beneficiaries, contact persons, short project descriptions and project budget. These sections
are frequently updated with the newest available information that is received from the
beneficiaries, for instance, project newsletters and photographs are uploaded on these
sections. The most prominent news items also get highlighted on the Programme start page
in section „Project news”.
Programme social media channels were established on Facebook and YouTube. Facebook
page featured hundreds of posts, among them news, photos and videos from the
Programme events, project events and other Estonia – Latvia cooperation related activities.
By the end of its first year, the Programme Facebook page had 200 followers and potential
reach of about 50,000 people, mostly from Estonia and Latvia. The most popular post on
Facebook page was a photo gallery from filming of “Better Neighbours” – about 400 people
saw, liked and commented this gallery. Most followers are from Riga, Tartu and Tallinn;
majority of them in the age groups between 25-34 (30%), 35-44 (17%) and 18-24 (15%). The
Programme YouTube channel features all Programme filmed material – promo videos for
European Cooperation Day (that the Programme arranged to be dubbed in the Baltic
languages for our use), Programme documentary segments, conference presentations and
44
impact interviews with completed project partners. In 2012 the Programme uploaded 51
videos on YouTube that were shared later on other web and social media platforms. Total
number of views at the end of the year was 4,426.
The Programme newsletter was issued in February and October 2012, each time in the
English, Estonian and Latvian languages. Since 2012 the newsletter is electronic and web
based. The aim of the newsletter was to inform various target groups about the latest
developments in the Programme, including European Cooperation Day 2012 and the
planning of the new Estonia – Latvia Programme 2014-2020.
Programme has continued to actively organize various special activities for the target group
of the supported and running projects.
Two Communication Seminars took place in spring 2012 – one in Riga, Latvia and one in
Viljandi, Estonia, to provide partners of the running projects training in basic communication
activities, which are important for the visibility and overall success of the projects and
Programme. Project partners are very important source of information about the
Programme, and they are the ones who have the possibility to carry further the message
about the benefits and impact on the regional development supported by the Programme.
Joint Partner Day was organized in Sangaste, Estonia in June 2012, in order to provide the
partners of the supported and running projects with networking opportunities, as well as to
give them a chance to discuss various unclear and challenging project administration issues
together with the Joint Technical Secretariat and first-level control bodies.
Following the financing decisions, four seminars for partners of the approved projects were
held in Estonia and Latvia in spring and fall of 2012. These were mainly focused on the newly
supported projects, but also attended by interested partners of the previously supported
and running projects. Seminars involved the LV and EE first-level control institutions and
focused on the reporting requirements, eligibility rules and various other administrative
requirements, providing guidance and explaining in detail each partner’s obligations during
the project implementation. Separate seminars on procurement issues were held in Estonia
and Latvia for project partners.
6.2 Media Monitoring
In 2012, the Programme was covered by at least 12 media outlets and stations, but the
Programme-funded projects received much more extensive coverage, especially in local and
regional media outlets. The Programme does not use professional media monitoring
services, but monitors media, using its own resources, therefore not all media impressions
can be precisely counted.
45
Programme publicity mostly consisted of coverage about European Cooperation Day 2012
events, Programme website nomination for RegioStars Award and the International
Conference on Border Areas. The largest media exposure last year was demonstration of the
documentary about Programme projects in Estonia and Latvia. In Estonia, the documentary
was demonstrated on ETV1 and ETV2, and in Latvia by LTV 1 and Re:TV all together reaching
the total audience of more than 80,000 people.
The information about the Programme’s supported projects and their activities has
constantly been disseminated by the project partners and reflected in various printed,
audio-visual and internet media, on the web sites of partners and other relevant institutions.
Due to the Programme’s focus on regional development, the project activities mostly take
place outside the capitals and are often aimed at specific communities in the regions.
Therefore local and regional media are the main target group for project stories and most
interested in reflecting the project developments.
In 2012, there has been coverage of various events organized by the running projects in local
media, in some cases also in national media. For example, Cēsis regional newspaper Druva
wrote about Artists for Regional Development project on several occasions, Tartu Postimees
wrote about SIB Net and ICT DC Net projects, Elu24.ee wrote about the activities of Young
Active Creative and Ziemellatvija.lv covered Art School Walk project. Some projects have
received also the attention of National Media, for instance Baltorgpotato project has been
covered on Latvian Television and in Latvijas Avize, while several projects on the Estonian
side have been noticed by Estonian Public Broadcasting, Postimees and Õhtuleht (road
construction projects, Radio Classics, SIB Net). The partners of the project Eagles Cross
Borders have been active communicators and the project has received nationwide coverage
on several occasions both in Estonia and Latvia.
7 CHALLENGES FOR 2013
The key word for 2013 will be programming of the Estonia – Latvia Programme 2014-2020.
A series of important decisions have to be taken in 2013, including the focus of the next
Programme and its financial allocations, at the same time compilation of the programme
document, ex ante evaluation and strategic environmental assessment of the new
Programme will be underway. As the JTS and the MA are in charge of managing the
programme preparation process, it will without doubt be their main challenge in 2013.
In parallel to the preparation of the new Programme, also equal importance should be paid
to the closure of the current Programme. The closure group will be formed of the
representatives of the MA, CA, and AA specifying the responsibilities of each member. It will
be further ensured that all information necessary for performing the closure is orderly and
available, and that an adequate audit trail is kept.
46
Implementation of the strategic projects should be closely followed. The authorities of the
Programme must receive confirmation from the partners of the strategic projects that all of
them are ready and have the capacity to carry out the planned activities in a timely and
correct manner, as due to their special status among supported projects some partners
might be less prepared for the daily realities of project partners, including reporting and
following all the eligibility rules. By the beginning of 2013 all six strategic projects have
received an approval from the MC, a few have started their activities, but none of them has
submitted a report yet.
As the Programme will try out something new as an annual major information event, the JTS
has to be thorough, careful and flexible in carrying out related tenders in time with good
quality results, e.g. production of attractive animated infographics about the Programme
and its results.
47
Annex 2 to the Annual Implementation Report 2012
Categorization of Funds 2012
Objective
Priority
Theme
Form of
Finance Territory
Economic
Activity Location
Allocated
Community
Contribution
ETC 03 01 08 03 EU 966107
ETC 03 01 08 22 EU 1402543
ETC 05 01 08 22 EU 229979
ETC 08 01 08 06 EU 139900
ETC 09 01 08 03 EU 314699
ETC 09 01 08 22 EU 1141668
ETC 13 01 08 21 EU 693098
ETC 16 01 08 11 EU 399999
ETC 23 01 08 11 EU 9499026
ETC 30 01 08 11 EU 1305180
ETC 39 01 08 21 EU 1227920
ETC 43 01 08 12 EU 237468
ETC 51 01 08 21 EU 2204847
ETC 53 01 08 21 EU 430000
ETC 53 01 08 22 EU 279014
ETC 54 01 08 22 EU 3191670
ETC 55 01 08 22 EU 5045696
ETC 57 01 08 20 EU 389833
ETC 57 01 08 22 EU 1281074
ETC 59 01 08 20 EU 547005
ETC 59 01 08 22 EU 256670
ETC 60 01 08 20 EU 1406478
ETC 60 01 08 22 EU 444410
ETC 62 01 08 01 EU 548787
ETC 62 01 08 22 EU 399400
ETC 67 01 08 20 EU 184997
ETC 71 01 08 20 EU 158714
ETC 75 01 08 18 EU 122430
ETC 75 01 08 20 EU 528300
ETC 76 01 08 19 EU 1617687
ETC 85 01 08 00 EU 761680
ETC 86 01 08 00 EU 84560
48
Annex 2 to the Annual Implementation Report 2012
List of Projects approved in 2012 in the Estonia – Latvia Programme 2007-2013
Project title/ short name Direction
of support ERDF funding
MC meeting
LP country
LP name LP type LP county/
district
Partners
EE LV Total
VVRS 1.1 399 999, 41 Tartu* EE Valga Town Government
Local public authority
Valga 1 1 2
Reconstruction of Road Ape-Mõniste
1.1 4 200 000, 00 Tartu EE Estonian Road Administration
National public authority
Harju 1 1 2
Coastal and maritime spatial planning
1.2 430 000,00 Tartu EE Estonian Ministry
of the Interior National public
authority Harju 2 4 6
DICTIONARY 1.1 349 994,70 WP1** EE The Institute of the Estonian Language
National public authority
Harju 1 1 2
JATE 1.2 1 199 734,81 WP2 LV
State Fire and Rescue Service of
the Republic of Latvia
National public authority
Rīga 1 1 2
Riverways 2.2. 1 800 000,00 WP3 LV Kurzeme Planning
Region Regional public
authority Saldus 9 30 39
*MC meeting in Tartu was held on 11 May 2012 ** WP is an abbreviation for “Written procedure”
WP1 – decision was taken via written procedure on 13 July 2012 WP2 – decision was taken via written procedure on 19 October 2012 WP3 – decision was taken via written procedure on 20 December 2012
49
Annex 3 to the Annual Implementation Report 2012
List of supported projects in the Estonia – Latvia Programme 2007-2013
Project title/ short name direction
of support
ERDF funding
MC meeting
LP country
LP name LP type LP county/
district
Partners
EE LV Tota
l
1) Towards the Blue Flag on Baltic beaches / Beach Hopping
2.2. 1 626 891 Kuressaare,
2008 Latvia
Saulkrasti Municipality
Council
Local public authority
Saulkrasti 2 5 7
2) Increasing the attractiveness of Valga-Valka / IAVV
2.2. 1 970 465 Kuressaare,
2008 Estonia
Valga Town Government
Local public authority
Valga 1 1 2
3) Activating vital and healthy community by promoting winter sports in Aluksne-Haanja Uplands/Aluksne -Haanja Uplands (AHU)
3.1. 287 385 Kuressaare,
2008 Estonia
Haanja Rural Municipality
Local public authority
Võru 1 1 2
4)Towards cross-border sports communities / SPORTBORDER
3.1. 285 600 Kuressaare,
2008 Latvia Ape Area Council
Local public authority
Ape 2 1 3
5)Increasing competitiveness of Estonian and Latvian food industry based on new and improved local fruit and berry product development / GoodFruit
2.1. 720 500 Kuressaare,
2008 Estonia
Estonian University of Life
Sciences
Public equivalent
body Tartu 2 4 6
6) Continuous cultural cooperation on the Estonian-Latvian border-area / Cultural Cooperation for Intermediates/
3.2. 291 975 Kuressaare,
2008 Latvia
Alūksne Local Municipality
Local public authority
Alūksne 2 3 5
50
7) Increasing Competitiveness of Estonian and Latvian Mechatronics sector through creation of Integrated Network of Product Development, Training and Testing Centres / Protolab Network
2.1. 913 750 Haapsalu,
2008 Estonia
Tartu Science Park
Public equivalent
body Tartu 1 2 3
8) Rising the Attractiveness and Competitiveness of Northern Kurzeme in Latvia and Saaremaa Island in Estonia / One Vacation - Two Countries
2.2. 713 895 Liepāja,
2009 Latvia
Ventspils City Council
Local public authority
Ventspils 1 2 3
9) Promotion of Local Communities of Stende and Võhma / Connecting Stende and Võhma
3.1. 275 665 Haapsalu,
2008 Latvia
Talsi Municipality Council
Local public authority
Talsi 1 1 2
10) Elaborating joint tools for environmental education as efficient mean of management of protected areas / Back to Nature
1.2. 554 760 Liepāja,
2009 Estonia
Foundation Tartu Environmental
Education Centre
Public equivalent
body Tartu 3 2 5
11) Unknown cultural heritage values in common natural and cultural space / Cultural heritage
1.2. 805 371 Liepāja,
2009 Estonia
State Forest Management
Centre
Public equivalent
body Harju 1 2 3
12) Awareness Rising of Voluntary Firemen Work and Safety Issues / FireSafe
3.2. 251 762 Liepāja,
2009 Latvia
State Fire and Rescue Service of
Latvia
National public
authority Rīga 1 4 5
13) Eliminating the infrastructure barriers on all-round development of border areas / Reconstruction of Karksi-Nuia - Koni road
1.1. 5 175 779 Liepāja,
2009 Estonia
The Road Administration of
the Western Region of Estonia
National public
authority Pärnu 1 1 2
14) Supporting the Song and Dance Festival Tradition in Estonian-Latvian Border Areas / SDF -Song and Dance Festivals
3.2. 107 277 Liepāja,
2009 Estonia
Euregio Pskov-Livonia, section
Estonia
Public equivalent
body Valga 1 1 2
15)Development of Cross-Border Choir Singing Culture / Singing Neighbours
3.2. 280 585 Liepāja,
2009 Estonia
Võru Parish Government
Local public authority
Võru 2 3 5
16) Go cycling through Vidzeme and Southern Estonia / ViSoEst by bike
2.2. 1 447 668 Liepāja,
2009 Latvia
Vidzeme Tourism Association
Public equivalent
body Cēsis 2 10 12
51
17) Promotion of the ball sports tradition in the border region through formation of a close cooperation network between ball sports fans of Estonia and Latvia / Cross Border Ball
3.1. 291 975 Liepāja,
2009 Latvia
Alūksne Municipality
Local public authority
Alūksne 3 2 5
18) Increasing the attractiveness of Madona and Polva territories through cooperation in active tourism and developing tourism marketing and skiing infrastructure / Active tourism- attractive feature of Madona and Põlva
2.2. 404 592 Liepāja,
2009 Latvia
Madona Municipality
Local public authority
Madona 1 1 2
19) Sustainable use of local natural resources and cultural heritage for business development in Setomaa and Ape regions / BUY LOCAL
2.1. 408 708 Dikļi, 2009 Estonia The Union of
Setomaa Rural Municipalities
Public equivalent
body Põlva 1 1 2
20) Development of Latvian-Estonian network for demonstration of environmentally friendly farming practices/DEMO FARM
1.2. 755 271 Dikļi, 2009 Latvia Latvian Rural Advisory and
Training Centre
Public equivalent
body Rīga 1 2 3
21) Cross-border transmission of best special teaching, knowledge and social protection / Easy together
3.2. 42 441 Dikļi, 2009 Estonia Võru Järve
School
Public equivalent
body Võru 1 1 2
22) Small Innovative Business Promotion Network/SIB Net
2.1. 477 520 Rīga, 2009 Latvia Riga Planning
Region
Regional public
authority Rīga 2 4 6
23) Boosting Cross-border Entrepreneurship in Life Sciences & Medicine related to Biotechnology and Medical ICT between Estonia and Latvia / Boost BioBusiness
2.1. 279 081 Rīga, 2009 Estonia
Entrepreneurship Development
Centre for Biotechnology and Medicine
Non profit oriented
organisation Tartu 3 3 6
24) Baltic small harbours network / BayLink 1.1. 1 360 805 Rīga, 2009 Latvia Mērsrags Port
Authority
Public equivalent
body Mērsags 1 3 4
25) Mentally disabled child among us / TOLERANCE 3.2. 200 512 Rīga, 2009 Estonia NGO Anni
Playground
Non profit oriented
organisation Tartu 2 1 3
26) Promotion of the use of sustainable and low energy buildings and constructions in Latvia and Estonia / Active through Passive!
1.2. 289 524 Rīga, 2009 Estonia Valga Town
Government Local public
authority Valga 2 4 6
52
27) Development of Cross-Border Co-operation Among the Grassroots for Development of Sustainable Latvia - Estonia Borderland Communities / Still active
3.2. 184 997 Rīga, 2009 Latvia
Latvian Community
Initiative Foundation
Non profit oriented
organisation Rīga 4 5 9
28) Valga-Valka Joint Rescue Capacity / VV JRC 1.2. 1 991 935 Rīga, 2009 Estonia Estonian Rescue
Board
National public
authority Harju 1 1 2
29) Unified ICT Network for Innovations / ICT DCNet 1.1 537 481
Pärnu, 2010 Latvia
Riga Technical University
National public
authority Rīga 2 3 5
30) Gulf of Riga as a resource for Wind Energy / GORWIND
1.2 1 227 920 Pärnu, 2010 Estonia
Marine Systems Institute at
Tallinn University of Technology
Public equivalent
body Tallinn 4 3 7
31) Developing Estonian-Latvian Medical Area / DELMA
1.2 1 522 237 Pärnu, 2010 Estonia University of
Tartu
Public equivalent
body Tartu 4 2 6
32) Increasing Competitivenss of Estonian and Latvian Mechatronics Sector / Skills Centre
2.3 475 600 Pärnu, 2010 Latvia Ogre Business
and Innovation incubator
Non profit oriented
organisation Ogre 1 2 3
33) Improving Sustainability and Vitality of Local Communities by Developing Co-operation in Youth Amateur MotoCross / MOTO
3.2 135 151 Pärnu, 2010 Estonia Motorcycle Club
K&K NGO
Non profit oriented
organisation Valga 1 1 2
34) Festival "Friendship Through Football" / FFF 3.2 50 596 Pärnu, 2010 Estonia NPO FC Santos Non profit oriented
organisation Tartu 1 2 3
35) Media Literacy - 21st Century Approach to Education / MLEDU
3.2 49 943 Pärnu, 2010 Estonia Tartu
Municipality Local public
authority Tartu 1 1 2
36) Cooperation of Young Sailors and Coaches of Estonia and Latvia / Young sailors
3.2 129 626 Pärnu, 2010 Latvia Laser class association
Latvia
Non profit oriented
organisation Rīga 2 2 4
37) Improving Sustainability and Vitality of Orienteering on a Local Level / Est-O-Lat league
3.2 141 358 Pärnu, 2010 Estonia Estonian
Orienteering Federation
Non profit oriented
organisation Tallinn 1 1 2
53
38) Eliminating the infrastructure barriers in Estonian-Latvian border areas / Reconstruction of the road Kilingi-Nõmme - Mazsalaca
1.1 2 626 802 Jūrmala,
2011 Estonia
Western region of Estonian Road Administration
National public
authority Pärnu 1 1 2
39) Bringing Estonia and Latvia Together on Emergency Ambulatory Medical Services / BEST TEAMS
1.2 95 450 Jūrmala,
2011 Estonia
Estonian Health Board
National public
authority Tallinn 2 2 4
40) Eagles cross borders / Eagles 1.2 299 217 Jūrmala,
2011 Latvia
Latvian Fund for Nature
Non profit oriented
organisation Rīga 1 1 2
41) Towards joint management of the transboundary Gauja/Koiva river basin district / Gauja/Koiva
1.2 718 435 Jūrmala,
2011 Latvia
Latvian Institute of Aquatic
Ecology
Public equivalent
body Rīga 3 4 7
42) Tuned nature management in transboundary area of Estonia and Latvia / Green Corridor
1.2 274 776 Jūrmala,
2011 Latvia
Nature Conservation
Agency
National public
authority Salacgrīva 1 1 2
43) Smart Botanic Gardens / SmartGardens 1.2 399 487 Jūrmala,
2011 Latvia
National Botanic Garden of Latvia
National public
authority Salaspils 2 2 4
44) Baltic Organic Potato for the World Markets / BALTORGPOTATO
2.1 254 488 Jūrmala,
2011 Latvia
Ltd. "Aloja Starkelsen"
Private partner
Limbaži 2 5 7
45) INTEGRATED BUSINESS DEVELOPMENT IN SOUTH ESTONIA AND NORTH LATVIA/ DELBI
2.1 229 979 Jūrmala,
2011 Latvia
Estonian Business
Chamber in Latvia
Non profit oriented
organisation Rīga 2 3 5
46) Promotion of cross-border partnership between Estonia and Latvia for development of antiviral drugs / EstLat Pharma
2.1 139 900 Jūrmala,
2011 Estonia TBD-Biodiscovery
Private partner
Tartu 1 1 2
47) Developing rural food businesses competitivness by cross-border artisan food networking /FOODART
2.1 314 700 Jūrmala,
2011 Latvia
Sigulda Municipality
Local public authority
Sigulda 2 2 4
48) Local Artists for Regional Development/ Artists for Development
3.2 116 514 Jūrmala,
2011 Latvia
Municipal agency "Cesis Culture and Tourism
center"
Public equivalent
body Cēsis 1 2 3
49) Improving Estonian-Latvian citizen education and urban development / Est-Lat urban activists
3.2 48 493 Jūrmala,
2011 Estonia
Estonian Urban Lab
Non profit oriented
organisation Tallinn 1 1 2
54
50) Development of cooperation between Estonian-Latvian youth hobby modelists/Hobby slot car racing
3.2 28 875 Jūrmala,
2011 Estonia
Sindi Town Government
Local public authority
Pärnu 1 1 2
51) Support to West Estonian-Latvian youth initiatives and co-operation. / Youth initiatives and co-operation
3.2 149 996 Jūrmala,
2011 Latvia
NGO Ventspils Youth Council
Non profit oriented
organisation Ventspils 1 1 2
52) Development of Valka Art School as common cross-border cultural education centre / Art School "Walk"
3.1 122 430 Sigulda,
2011 Latvia
Valka Municipality
Council
Regional public
authority Valka 1 1 2
53) Promoting Sustainable Urban Drainage Systems in Estonia-Latvia cross-border area to improve the environment for active and sustainable communities / (D)rain for life
3.1 97 631 Sigulda,
2011 Latvia
Latvian Association of
Spatial Planners
Non profit oriented
organisation Rīga 1 2 3
54) House of Sounds - renovation of instrumental music traditions in Vidzeme and South Estonia / House of Sounds
3.1 113 824 Sigulda,
2011 Latvia
Pārdaugava Folk Music Society
Non profit oriented
organisation Rīga 1 1 2
55) Developing of cross border trade network / Idea on the border
3.2 73 041 Sigulda,
2011 Latvia
Apes municipality
Local public authority
Ape 1 1 2
56) Promotion of youth involvement in professional classical music performance / Radio Classics
3.2 94 415 Sigulda,
2011 Latvia Latvian Radio
Public equivalent
body Rīga 1 1 2
57) Vital Communities by Promotion of Youth Skills and Involvement / Young Active Creative
3.2 117 071 Sigulda,
2011 Estonia
Põlva Town Government
Local public authority
Põlva 2 3 5
58) Renovation of Valga-Valka railway station / WRS 1.1 399 999 Tartu, 2012
Estonia Valga Town
Government Local public
authority Valga 1 1 2
59) Improvement of traffic conditions on Ape-Mõniste connection road between Riga-Pskov and Võru-Valga-Valmiera transport corridors / Reconstruction of Road Ape-Mõniste
1.1 4 200 000 Tartu, 2012
Estonia Estonian Road Administration
National public
authority Harju 1 1 2
60) Coastal and maritime spatial planning in Pärnu Bay area in Estonia and coastal municipalities of Latvia / Coastal and maritime spatial planning
1.2 430 000 Tartu, 2012
Estonia Estonian Ministry
of the Interior
National public
authority Harju 2 4 6
61) Development of Estonian – Latvian and Latvian – Estonian dictionary / DICTIONARY
1.1 349 995 Via written procedure,
2012 Estonia
The Institute of the Estonian
Language
National public
authority Harju 1 1 2
62) Building Cross-border Capacity to Perform Joint Activities in Tough Environment/ JATE
1.2 1 199 735 Via written procedure,
Latvia State Fire and
Rescue Service of National
public Rīga 1 1 2
55
2012 the Republic of Latvia
authority
63) Development of water tourism as nature and active tourism component in Latvia and Estonia / Riverways
2.2. 1 800 000
000,00
Via written procedure,
2012 Latvia
Kurzeme Planning Region
Regional public
authority Saldus 9 30 39
TOTALS
EE lead partners 31 Partners
EE LV Total
LV lead partners 32 106 162 268
56
Annex 4 to the Annual Implementation Report 2012
Projects contributing to the EU Strategy for the Baltic Sea Region in the Estonia – Latvia Programme 2007-2013
No Project number and title
Relation to the Priority Area (PA)of the EU Strategy for the Baltic Sea Region
Description of the project Lead Partner (LP)/partners (P)
ERDF funding /EUR
National Co-financing /EUR
1. EU 30086 Eliminating the infrastructure barriers on development of the border areas /Reconstruction of road Karksi-Nuia – Seda river
PA 11: To improve internal and external transport links
Reconstruction of cross-border road from Karksi-Nuia (EE) to Rūjiena (LV). The reconstruction is aiming at re-establishing proper transport link between Central Estonia and Latvia to facilitate economic development and increase tourism potential.
LP: Estonian Road Administration P: Ministry of Transport of the Republic of Latvia
2 715 568,61 479 217,99
2. EU31404 Baltic Small Harbours Network / BayLink
PA 11: To improve internal and external transport links
Improvement of internal and external connectivity of the Programme area and reduction of hindrances of the existing maritime border. New maritime connections through development of small harbours infrastructure are created. It will open new cross-border business opportunities, employment facilities and international passenger flow.
LP: Mersrags Port Authority (LV); P: Kurland Ltd (LV), AS Saarte Liinid (EE), ADA Ltd (LV)
1 360 804,70 Public: 185 256,30 Private: 311 019
57
3. EU34711 Gulf of Riga as a resource for wind energy (GORWIND)
PA 10: To improve the access to, and the efficiency and security of the energy markets
Fostering more efficient use of the
wind energy by providing decision
makers and potential developers of
wind parks in the Gulf of Riga with
reliable marine wind information from
high resolution remote sensing data.
Research institutes of both countries
carrying out the project plan to
complement the technical data and
wind measurements with the
information on wintering and habitat
area for seals, migrating and breeding
birds.
LP: Marine Systems
Institute at Tallinn
University of
Technology (EE); P:
University of Tartu
(EE), Estonian
University of Life
Sciences (EE), Latvian
University, Latvian
Institute of Aquatic
Ecology.
1 227 919,99 216 691,76
4. EU29881 Increasing competitiveness of Estonian and Latvian food industry based on new and improved local fruit and berry product development/ GoodFruit
PA 8: Implementing the Small Business Act: to promote entrepreneurship, strengthen SMEs and increase the efficient use of resources.
Raising the general competitiveness of
the local fruit and berry businesses that
form an important agricultural industry
in both countries. The project will set up
and develop Estonian-Latvian Fruit and
Berry Product Development
Competence Centre to ensure the
producers’ accessibility to and raise the
competitiveness of their production in
the market. The project will introduce
novel storage methodologies and
provide upgraded infrastructure and
know-how for product development for
both Estonian and Latvian companies.
LP: The Estonian University of Life Sciences; P: Pūre Horticultural Research Center (LV), Association Partnership of Kandava, farm Piladzi, (LV) farm „Lāses", and Berry Farming LLC (EE)
720 500 EUR Public: 94 500 Private: 185 000
58
6. EU31398 Small Innovative Business Promotion Network /SIB Net
PA 8: Implementing the Small Business Act: to promote entrepreneurship, strengthen SMEs and increase the efficient use of resources.
Promotion of new innovative high
growth firms by encouraging
entrepreneurial creativity, providing
needed knowledge and evaluating the
needs for early stage finance to cover
“death valley” between academic and
educational world and business
incubators in the regions; to create
efficient matching mechanisms for
investors and idea holders in two
investor forums and team building
event
LP: Riga Planning Region (LV); P: Ventspils University College (LV); Ventspils High technology Park (LV); Stockholm School of Economics in Riga (LV), Tartu Science Park (EE); Institute of Baltic Studies (EE)
477 519,80 84 268,20
7. EU29852 Towards the blue flag on Baltic Beaches / Beach hopping
PA 12: To maintain and reinforce attractiveness of the Baltic Sea Region in particular through education, youth, tourism, culture and health
Improvement of the overall
attractiveness, environment and safety
of the beaches along the coast of the
Gulf of Rīga by (1) raising the standards
of the beaches in partner municipalities
using Blue Flag as a benchmark,
focusing on lifeguarding and beach
safety; (2) increasing the awareness of
visitors about the partner
municipalities as attractive tourism
destinations.
LP: Saulkrasti Regional Council (LV); P: Audru Municipality (EE), Carnikava Municipality (LV), Häädemeeste Municipality (EE), Jūrmala City Council (LV), Salacgrīva Regional Council (LV)
1 626 890,65 287 098,35
8. EU29904 Raising the attractiveness and competitiveness of Northern Kurzeme in Latvia and Saaremaa Island in Estonia by
PA 12: To maintain and reinforce attractiveness of the Baltic Sea Region in particular through education, youth, tourism, culture and health
Raising attractiveness and
competitiveness of North Kurzeme in
Latvia and Saaremaa Island in Estonia
by improving its tourism potential,
using the natural advantages of the
coastal municipalities. The aim is to
LP: Ventspils City Council (LV); P: Kuressaare City Government (EE), Talsi Region Tourism Information Centre (LV)
713 894,60 125 981,40
59
improving tourism environment and its offer using the natural advantages of coastal municipalities /One Vacation Two Countries
achieve Blue Flag certificates for the
beaches of Ventspils and Kuressaare
municipalities and to ensure joint
visibility of the North Kurzeme region
and Saaremaa Island as an attractive
tourism destination for a broader
target audience.
9. Eliminating the infrastructure barriers in Estonian-Latvian border areas/ Reconstruction of the road Kilingi-Nõmme - Mazsalaca
PA11: “To improve internal and external transport links”
To improve the road conditions
between Kilingi-Nõmme and Maszalaca
towns in order to satisfy the local
needs and turn the region more
attractive and accessible place for
transport and tourism
LP: Estonian Road Administration; P: Ministry of Transport of the Republic of Latvia
2 626 802,27 538 019,75
10. Towards joint management of the transboundary Gauja/Koiva river basin district / Gauja/Koiva
PA3: “To reduce the use and impact of hazardous substances”
To enhance the management of shared
surface and groundwater resources by
development of a joint river basin
management plan for the
transboundary Gauja/Koiva river basin
district. More specifically: to get unified
boundaries of transboundary water
bodies; to clarify and set common
water quality objectives for the basin
district; to harmonise the approaches
and methods for the key aspects of
river basin management plans; select
cost efficient measures for
improvement of water status; provide
LP: Latvian Institute of Aquatic Ecology; P: Ministry of the Environmental Protection and Regional Development of Latvia; University of Latvia, Institute of Biology; Baltic Environmental Forum Latvia; Baltic Environmental Forum Estonia, Tallinn University of Technology; Estonian University of Life Sciences
718 435,26 147 149,39
60
information and public involvement in
water management
11 Coastal and maritime spatial planning in Pärnu Bay area in Estonia and coastal municipalities of Latvia / Coastal and maritime spatial planning*
1) PA Agri - Reinforcing
sustainability of agriculture,
forestry and fisheries;
2) PA Bio – Preserving
natural zones and
biodiversity, including
fisheries
3) PA Energy – Improving the
access to, and the efficiency
and security of the energy
markets
4) PA Ship – Becoming a
model region for clean
shipping
5) PA SME – Promote
entrepreneurship and
strengthen the growth of
SMEs
6) PA Transport – Improving
internal and external
transport links
Preparation of a maritime spatial plan
and a strategic environmental
assessment in Pärnu Bay area in
Estonia;
Preparation of a maritime spatial
planning methodology;
Preparation of of the methodology on
functional linkage between marine and
coastal territories; Preparation of
guidelines for minimization of coastal
erosion impacts in Latvia;
Preparation of management plans for
the Natura 2000 areas – nature
reserves “Ovīši” and “Užava”; Pilots in
Pāvilosta, Roja and Engure
municipalities.
LP: Estonian Ministry of the Interior; P: Engure Minicipality Council (LV) Kurzeme planning region (LV) Pärnu County Government (EE) Pāvilosta Municipality Self-Government (LV)Roja Municipality Council (LV)
430 000 88 072,29
*The labelling was done pursuant to the European Union Strategy for the Baltic Sea Region ACTION PLAN, February 2013 version.