Supplier Contract Quality Requirements Specification
Division
Title: Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58
Area of Applicability: E
Documentation Type: PC
Revision: 0
Total Pages: 58
Next Review Date: March 2015
Disclosure Classification: CONTROLLED DISCLOSURE
-
Supplier Contract Quality Requirements Specification
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Unique Identifier: QM-58 Revision: 0 Page: 2 of 58
CONTENTS Page
1. INTRODUCTION
......................................................................................................................................................
4 2. SUPPORTING CLAUSES
........................................................................................................................................
4
2.1 SCOPE
..............................................................................................................................................................
4 2.1.1 Purpose
.....................................................................................................................................................
4 2.1.2
Applicability................................................................................................................................................
4
2.2 NORMATIVE/INFORMATIVE REFERENCES
..................................................................................................
4 2.2.1 Normative
..................................................................................................................................................
4 2.2.2 Informative
.................................................................................................................................................
4
2.3 DEFINITIONS
....................................................................................................................................................
5 2.3.1 Eskom Definitions
......................................................................................................................................
5
2.4 ABBREVIATIONS
..............................................................................................................................................
7 2.5 ROLES AND RESPONSIBILITIES
....................................................................................................................
8
2.5.1 Division of Responsibilities
........................................................................................................................
8 2.5.2 Eskom
........................................................................................................................................................
8 2.5.3 Contractor
..................................................................................................................................................
9
3. ESKOM RIGHTS (NOT LIMITED TO THE FOLLOWING):
...................................................................................
10 3.1 GENERAL REQUIREMENTS
.........................................................................................................................
11
3.1.1 QUALITY MANAGEMENT POLICY
........................................................................................................
11 3.1.2 IMPLEMENTATION
................................................................................................................................
11 3.1.3 QUALITY MANAGEMENT IN ENGINEERING
.......................................................................................
12
3.1.3.1 Design Quality Plan
.........................................................................................................................
12 3.1.3.2 Design Planning and Control
..........................................................................................................
12 3.1.3.3 Design Quality Planning
..................................................................................................................
13 3.1.3.4 Criticality Assessment and Application
...........................................................................................
14 3.1.3.5 Design Inputs
..................................................................................................................................
15 3.1.3.6 Design
Outputs................................................................................................................................
15 3.1.3.7 Design Verification
..........................................................................................................................
15 3.1.3.8 Inter-discipline Check and Review (Squad Check)
.........................................................................
16 3.1.3.9 Design Validation (Including Software Validation)
..........................................................................
16 3.1.3.10 Design Changes
............................................................................................................................
16 3.1.3.11 System and Sub-System Lists
......................................................................................................
17 3.1.3.12 Design Element Identification, Traceability, and
Composition Verification ................................... 17
3.1.3.13 Design, Safety and Model Reviews.
.............................................................................................
18 3.1.3.14 Constructability Maintainability, Operability Reviews
....................................................................
18
3.1.4 QUALITY MANAGEMENT IN FABRICATION & CONSTRUCTION
....................................................... 18 3.1.4.1
General
............................................................................................................................................
18 3.1.4.2 Quality Audits and Related Quality Performance Reviews
............................................................. 20
3.1.4.3 Eskom Right of Access
...................................................................................................................
21
3.2 TENDER SUBMISSION PHASE
.....................................................................................................................
21 3.2.1 Contractor documents with the tender
....................................................................................................
21 3.2.2 The Contractor shall submit a draft Contract Quality Plan
(CQP) with the tender. ................................. 22
3.3 TENDER EVALUATION, ADJUDICATION AND NEGOTIATION PHASE
..................................................... 23 3.3.1
Subcontracting.........................................................................................................................................
23
3.4 CONTRACT AWARD PHASE
.........................................................................................................................
26 3.5 CONTRACT AWARD AND QUALITY CONTROL PHASE
.............................................................................
27
3.5.1 Pre-contract execution
............................................................................................................................
27 3.5.1.1 Supplier and subcontractor Quality Management Plan
..................................................................
27 3.5.1.2 Supplier and Subcontractor Inspection and Documentation
Requirements ................................... 28
3.5.2 Contract execution
..................................................................................................................................
31 3.5.3 Inspection Reports
..................................................................................................................................
31 3.5.4 Non-conformance Reports and Log
........................................................................................................
32
-
Supplier Contract Quality Requirements Specification
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Unique Identifier: QM-58 Revision: 0 Page: 3 of 58
3.5.5 Contractors inspection and testing
.........................................................................................................
33 3.5.6 Verification of purchased product
............................................................................................................
33 3.5.7 Third Party Inspection
.............................................................................................................................
36
3.5.7.1 AIA
...................................................................................................................................................
36 3.5.7.2 Eskom appointed AIA organization
.................................................................................................
36
3.5.8 MATERIALS MANAGEMENT PROGRAM
.............................................................................................
37 3.5.8.1 General
............................................................................................................................................
37
3.5.8.1.1 Traceability
..............................................................................................................................
37 3.5.8.1.2 Positive Material Identification
................................................................................................
38 3.5.8.1.4 Quantitative quality measurement tools
..................................................................................
38 3.5.8.1.5 Preservation
............................................................................................................................
38
3.5.9 Expediting during contract execution
......................................................................................................
41 3.5.10 Quality Control on Completion of the Contract
......................................................................................
42
3.5.10.1 Manufacturing Record Books.
.......................................................................................................
42 3.6 SUPPLIER QUALITY PERFORMANCE MONITORING PHASE
...................................................................
43 3.7 E-QUALITY TOOL (ACHIEVER PLUS)
..........................................................................................................
44 3.8 PAYMENT AND DELIVERY
............................................................................................................................
44
4. AUTHORIZATION
..................................................................................................................................................
45 5. REVISIONS
............................................................................................................................................................
45 6. DEVELOPMENT TEAM
.........................................................................................................................................
45 APPENDIX A : TENDER & CONTRACT QUALITY REQUIREMENTS
....................................................................
47 APPENDIX B : QUALITY REQUIREMENTS FOR ISO 9001 SERIES
.....................................................................
48 APPENDIX C : TEMPLATE FOR A TYPICAL CONTRACT QUALITY PLAN
......................................................... 49
APPENDIX D : DEFECT NOTIFICATION
.................................................................................................................
53 APPENDIX E : CAR
...................................................................................................................................................
54 APPENDIX F : CONCESSION
...................................................................................................................................
55 APPENDIX G : CONCESSION
..................................................................................................................................
56 APPENDIX H: REQUIREMENTS FOR A PRODUCT VERIFICATION PLAN
.......................................................... 57
APPENDIX I: QUALITY CONTROL PLAN/INSPECTION & TEST PLAN
................................................................
58
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 4 of 58
1. INTRODUCTION
This specification is to specify and describe the minimum
quality requirements for all existing and potential Eskom
Contractors and Suppliers, and to define the quality criteria for
the evaluation, selection and monitoring of same.
2. SUPPORTING CLAUSES
2.1 SCOPE
2.1.1 Purpose
The purpose of this specification is to specify the requirements
by which Contractors and Suppliers shall manage, implement,
maintain and continually improve a quality management system (QMS)
based on ISO 9001:2008 (or latest applicable revision). The
intention is that Contractors and Suppliers should continuously
adhere to Eskoms quality requirements in respect of the supply of
products and related services.
2.1.2 Applicability
This specification applies to all employees, entities, suppliers
and Contractors involved in Eskom new build and operating and
maintenance programme (plant refurbishment, engineering,
procurement, manufacturing, installation, and commission works).
When applied to a particular contract, the relevant clauses of ISO
9001:2008 (or latest applicable revision) and the business
processes requirements are indicated on the enquiry/contract/order
quality requirement forms (see Annexure A and B) This specification
will be applicable to any type of contract, where the wording as
well as applicable aspects shall be customised to the specific
contract, and reflected in the contract document to be signed by
Eskom and the supplier.
2.2 NORMATIVE/INFORMATIVE REFERENCES
Parties using this document shall apply the most recent edition
of the documents listed in the following paragraphs.
2.2.1 Normative
[1] ISO 9001:2008 Quality Management Systems Requirements [2]
ISO 9001:2005 Quality Management Systems Fundamentals and
Vocabulary [3] ISO 10005:2005 Guidelines for Quality Plans Standard
[4] ISO 10006:2003 Guidelines for Quality Management Systems in
Projects [5] ISO 90003, Software Engineering Guidelines for the
Application of ISO 9001
2.2.2 Informative
[6] ISO 9004:2009 Managing for the Sustained Success of an
Organization A Quality Management Approach
[7] NEC family of contract documents, as applicable to the
specific contract
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 5 of 58
[8] FIDIC form of contract, as applicable to the specific
contract
2.3 DEFINITIONS
2.3.1 Eskom Definitions
a. Supplier The word supplier refers to the Contractor
b. Customer The word customer refers to Eskom Holdings SOC
Limited (in the context hereof referred to as Eskom)
c. Contractor A group of people and facilities (corporation,
firm, enterprise, institution etc.) with an arrangement of
responsibilities, authorities and relationships. It also refers to
supplier, consultant and service provider
d. Subcontractors An organization or legal entity that provides
a product to the supplier and/or that enters into a
subcontract and assumes some of the obligations of the supplier
or prime Contractor e. Inspection Agency
An organization or person appointed by Eskom for the purpose of
performing quality assurance or quality control monitoring and or
inspection services
f. Approved Inspection Authority An organization or person
approved by the Chief Inspector, South African Department of
Labour, in terms of the Occupational Health and Safety Act 85 of
1993 and appointed by Eskom
g. Regulatory body A person or persons representing a statutory
body as required by law
h. Works All deliverables expected from the Contractors as per
the scope of works, requirements specified in the request for
tender
i. Major plant items Plant and Material items (e.g. components,
works that have an impact on safety of staff or equipment, the
environment, plant reliability and availability and are of a high
cost (Refer to Guideline GGG 1099 General Plant level
Classification). This also includes Transmission Primary and
secondary Plant items, and same for Distribution.
j. Refurbishment Restoration to a sustainable usable state or as
near as possible to new state (within agreed limits)
k. Quality Control Plan (QCP) A document specifying the
activities to be inspected throughout the execution of the project,
inclusive of test methods, procedures and acceptance criteria.
(This term is equivalent to QIP and ITP)
l. Contract Quality Plan A document compiled, as required by the
Contract Quality Requirements Specification, by a Contractor which
spells out the aspects of the quality management system to be
applied within a
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 6 of 58
specific Eskom project, and the methods to be utilized to ensure
quality assurance, control and improvement of the identified
activities that they will be carried out as stated in the Works
Information to ensure that the product/service meets Eskom
requirements (This document can be viewed as a combination of a PQP
and QCP)
m. Intervention points Intervention points are those control
points indicated by the various controlling bodies concerned with
the implementation of a specific QCP / ITP. These can be in the
form of tests, inspection, surveillances, witnessing, reviews,
failure and incident investigations)
n. Hold points An activity of an inspection and test plan which
must be notified by the Contractor to Eskom and beyond which work
shall not proceed without the attendance of Eskoms representative
or the written approval of Eskom to proceed.
o. Surveillance Point Random monitoring of work processes and
tests.
p. Witness point An activity on an inspection and test plan
where work may proceed providing Eskom or Authority/Agency has been
notified as required and the latter has indicated that they will
not execute the intervention point
q. Document review A review of the records developed by a
Contractor to ensure that the relevant activity has been performed
satisfactory and that contractual requirements have been met
r. Project Quality Representative The most senior person
responsible for the management and administration of the Quality
System at the project/site/department. This includes an external
Contractor appointed by Eskom to perform this function
s. Technical expert This term refers to a person responsible for
and fulfilling the role concerned with the technical aspects and
integrity of the project, service, or process in respect of the
specific contract (e.g Eskom Engineer , IT Specialist, Auditor)
t. Advisory expert This term refers to a person responsible for
and fulfilling the role of providing specialist advice, as may be
determined and required in connection with any relevant aspect of
the review (e.g. Legal Advisor, Financial Advisor etc). This person
is only called upon on a need basis
u. Contract Manager/Expert This term refers to a person
responsible for fulfilling the role concerned with the contractual
aspect of the Eskom Commercial relationship with the Contractors in
respect of the specific contract (e.g. Package Manager)
v. Quality Dossiers An indexed file containing all applicable
records, documentation, certificates, data package, and other data
applicable to the works. The Quality Dossier will be reviewed
during the turnover process)
w. Data Package
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 7 of 58
All documentation and certification required to be issued by the
Contractor in order that the takeover can be certified by Eskom (An
index of data packages must be established before commencement of
works)
x. Criticality Rating The risk ranking of structures, materials,
equipment, components and/or systems determined on the basis of
either FMECA/FMEA, HAZOP studies/reports or any applicable risk and
criticality bases.
y. FMECA Failure Mode Effects and Criticality Analysis (PGZ
45-25 - FMECA Studies).
z. HAZOP Hazard and Operability Study (PGZ 45-24 - HAZOP
Studies)
zz. Surveillance Point Random monitoring of work processes and
tests.
2.4 ABBREVIATIONS
Abbreviation Description AIA Approved Inspection Authority CV
Curriculum Vitae
CQP Contract Quality Plan ISO International Standards for
Organization QC Quality Control ITP Inspection and Test Plan
NEC New Engineering Contract OHSA Occupational Health and Safety
Act PED Pressure Equipment Directive PER Pressure Equipment
Regulation PQP Product / Project Quality Plan PVP Product
Verification Plan QCP Quality Control Plan DRC Document
Return/Review Code QIP Quality Inspection Plan QMS Quality
Management System inclusive of project requirements SABS South
African Bureau of Standards SANS South African National Standard
NEC New Engineering Contract RFQ Request for Quotation MOC
Management of Change CQP Contract Quality Plan, including Project
and any related Life Cycle Requirements CAP Contract Administration
Plan
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 8 of 58
Abbreviation Description AVL Approved Vendor List NDT Non
Destructive Testing NDE Non Destructive Examination O&M
Operating & Maintenance Manual
NOBO Notifying Body NCR Non Conformance Report PMI Positive
Material Identification PQR Procedure Qualification Record WQR
Welders Qualification Record WPS Welding Procedure Specification
HES Health, Environmental, Safety MRB Manufacturing Record Books
BOD Basis of Design FEED Front End Engineering Design
CFCCQMP Contractor Fabrication, Construction and Completions
Quality Management Plan NORFI Notification of Readiness of
Inspection CAP Contract Administration Plan I&TN Inspection and
Test Notification RCA Root Cause Analysis
2.5 ROLES AND RESPONSIBILITIES
2.5.1 Division of Responsibilities
The Division of Responsibilities section identifies the
interactions and responsibilities of Eskom and the Contractor
during the performance of work. This document together with the
Project Procedures describes administrative and procedural
requirements that the Contractor must satisfy in accomplishing the
work.
2.5.2 Eskom
2.5.1.1 Co-ordinate the work of the Contractor with activities
of Eskom and other Contractors and service providers directly hired
by Eskom. 2.5.1.2 From reports compiled by the Contractor, evaluate
the performance of the work of the Contractor, suppliers and
Subcontractors regarding schedule, quality, cost, safety and
requirements for compliance with the Contract and bring any
deficiencies of which Eskom is aware to the attention of the
Contractor such review shall not relieve Contractor of its
responsibilities. 2.5.1.3 Perform technical appraisal of the
Contractors work efforts. Appraisal will be by specialist personnel
and will be co-ordinated with the aforesaid parties. 2.5.1.4
Furnish or cause to be furnished the services of any service
Suppliers as Eskom may wish to employ in connection with the
Project.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 9 of 58
2.5.1.5 Obtain support and agreement from Eskom finance and
procurement organisations to establish and manage the Project
quality Budget.
2.5.3 Contractor
2.5.2.1 Provide Eskom with information as requested for
appraisal of the Contractors, Sub-Contractors and suppliers
performance of the Project, including but not limited to, copies of
calculations, Construction Documents in preparation, purchasing and
contracting documents, estimates, schedules, progress measurements,
cost reports, etc. 2.5.2.2 Evaluate and assume full responsibility
for all design work including that performed by the Sub suppliers,
material/equipment suppliers and Sub-contractors including shop
drawings and samples for quality, conformance to design, and
safety. The Contractor shall be responsible for construction means,
techniques, methods and procedures. 2.5.2.3 Maintain effective
liaison as required to co-ordinate and expedite transmission and
interpretation of Construction Documents, to implement necessary
design changes or modifications, and to resolve technical problems.
All formal communications with suppliers and Sub-contractors shall
be through the Contractor. 2.5.2.4 Conduct regularly scheduled
meetings with Eskom to discuss status of various stages of the
Project, methods for resolving difficulties encountered or foreseen
and other topics pertinent to the Project. Record and issue minutes
promptly after each meeting. Conduct regularly scheduled meetings
with Eskom to provide constructability input and other information
regarding economy of design. 2.5.2.5 Process changes in accordance
with the agreed Project change management procedure. 2.5.2.6 Issue
monthly and quarterly progress reports to Eskom in accordance with
agreed Project requirements. 2.5.2.7 Maintain a comprehensive
filing system in a format and location to be agreed with Eskom, to
provide a current basis for all documents, decisions, disposition
of directives and inquiries, and information exchanged among the
parties including agreements and modifications thereto. 2.5.2.8
Formulate and implement procedures to protect Eskoms proprietary
information during the performance of the Project. 2.5.2.9
Administer work performed by the suppliers and Subcontractors and
monitor for quality, cost, schedule, progress, and safety. 2.5.2.10
Provide data, as required, to permit prompt resolution of technical
problems and implementation of any necessary changes and
modifications. 2.5.2.11Submit to Eskom those items requiring
advance approval, including but not limited to the following:
schedules, overtime requirements, submittals, travel plans for its
personnel and its supplier and Subcontractors personnel assigned to
the field staff as well as for other personnel, schedules and plans
for temporary facilities, tools and equipment, and labour force
build-up and run-down of the supplier and Subcontractors. 2.5.2.12
Distribute correspondence originating with the Contractor in
accordance with the Correspondence Project Procedure. 2.5.2.13
Ensure all aspects of the Project are carried out fully in
accordance with the requirements of the Contract. 2.5.2.14 Ensure
progress of the Project meets the requirements of the Baseline
Control Project Schedule and milestone dates, and the Control
Budget. 2.5.2.15 Ensure that the Project Quality Plan is
implemented and is effective in controlling the quality of critical
items in the Projects.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 10 of 58
2.5.2.16 Ensure that the Project Safety Plan is implemented and
is effective in controlling the safe implementation of the
Projects. 2.5.2.17 Develop and provide reports to the Eskom Project
Manager detailing the status and anticipated completion of the
Projects, in terms of cost, schedule, progress, earned value and
quality. These reports must be developed by the Contractor and
formatted in accordance with Eskom requirements. 2.5.2.18 Liaise
with the Eskom Project Manager regarding the status of the Projects
and specific problem areas. 2.5.2.19 In a timely manner, review
with the Eskom Project Manager any aspect of the Projects or the
Project that the Contractor believes could have an impact on total
cost, schedule, or quality of the Project and agree to a course of
action. 2.5.2.20 Liaise with local and regional authorities during
approvals and ensure that all statutory requirements are met. This
shall include developing proposals and applications on behalf of
Eskom for statutory and third party approvals or submissions as may
be required. (Some sites will require all liaisons with local and
regional Authorities to be addressed via their own Eskom
representative.) 2.5.2.21 Provide Eskom with evidence and
assistance in demonstrating the integrity of the design,
engineering and management services, and control over execution of
the Project as may be required. 2.5.2.22 Ensure that timely and
efficient procedures and work methods are adopted during the
execution of the Project. (These should be detailed for the
individual project.) The Contractor is particularly required to
address areas of interfaces with other Eskom organisations and
departments. 2.5.2.23. The Contractor shall, at least 90 days prior
to the start of Construction, provide Eskom with a detailed
procedure for setting up the Project Bank Account. The procedure
shall also describe a detailed process to administer the account
including the use of the application for funding
3. ESKOM RIGHTS (not limited to the following): To expect that
the Works will be conducted in accordance with the contract between
the parties. Access to Contractors information as determined by
applicable legislation Eskom reserve the right to oversee
Contractor audit programs by participating in selected audits
as an observer, and by assessing Contractor at key work stages.
Eskom will coordinate with Contractor to develop an oversight
schedule aligned with Contractor audit schedule.
To obtain access to any audit reports performed by the
Contractor reflected in the audit programme
To conduct independent quality audits during all phases of the
contract and the contractor shall provide all resources to support
these activities.
Eskom shall have the right to participate or request for a
technical investigation to be launched and conducted on the
Contractor and subcontractors premises or other sites, when risk to
Eskom products or service deliverables are identified.
To participate in and/or lead investigations related to
incidents involving its products. To require from contractors to be
responsible for the cost of re-inspections To withhold payment from
Contractors as a result of outstanding non-conformances
irrespective
of the agreed payment schedule and in accordance with the
conditions of contract. Shall be granted electronic and hard copy
access to all quality plans, procedures, documentation,
and other quality records relating to the Work including but not
limited to data extracts.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 11 of 58
Reserves the right to review, inspect and audit any or all parts
of the Contractor QMS as well as any documentation, materials or
equipment associated with the Work, at any time or Project Work
location.
Shall carry out assessments and audits on all new Contractors
and subcontractors Reserves the right to appoint resident quality
inspectors that can be based at the Contractor
or subcontractors premises and on site where the work is being
performed. Reserves the right to select witness and hold points
within all developed Supplier QCP/ITPs for
Eskom oversight of selected functions and to perform
surveillance or audits of the Work. Shall be given access at all
reasonable times before, during and after manufacture and
before
delivery, construction, erection, commissioning to measure, test
and inspect the products and workmanship as necessary on the
Contractors premises and on Eskom sites.
Reserves the right to suspend any pending deliveries, by the
issuing of a cease delivery order at any time and for any portion
of the work that is not being performed in accordance with the
specified/agreed requirements.
To expect the Contractor to use Eskoms electronic system for the
automation and management of quality and other relevant aspects of
the project (Achiever Plus).
3.1 GENERAL REQUIREMENTS
3.1.1 QUALITY MANAGEMENT POLICY
Contractor Quality Management Program shall be based upon a
Quality Management Policy and a series of Quality Objectives and a
Project Quality Organizational Structure. Contractor Quality
Management Policy shall be based on the following Quality
Management principles:
Meeting Customer expectations Leadership Involvement of people
Process approach System approach to management Continual
improvement Factual approach to decision making Mutually beneficial
Project - Supplier relationships
Contractor shall ensure efficient and effective communication of
Project Quality Policy and Objectives to Contractor and
subcontractor organizations. Communication of and discussion around
project Quality Policy and Objectives shall be conducted at a
frequency supportive of project management commitment to workforce
engagement and continual improvement Contractor Project Quality
Management System (QMS) is the system of processes by which
Contractor will provide Eskom with assurance that Contractor Work
deliverables are in conformance with Contract specifications
3.1.2 IMPLEMENTATION
Contractor QMS shall support Eskom and Contractor Project
Management Objectives for safe, efficient and effective
implementation of all Work processes and procedures.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 12 of 58
Contractor CQP shall be implemented through utilization of a
comprehensive QMS. The QMS shall incorporate Quality management
processes and procedures tailored to support Project Quality
Policy, Goals and Objectives in all Work functional areas and for
all Work deliverables. Project Work functional areas include
Engineering, Procurement, Project Controls, Logistics, Materials,
Fabrication, Transportation, Preservation, Construction/Erection,
Commissioning, Quality, HES, Security, Informational Management and
other functional areas under Contractor Work scope.
The Contractor shall follow a graded approach and establish
critical products and services, endorsed by Eskom. Contractors,
subcontractors and all other suppliers of such products and
services shall ensure compliance with QMS performance expectations.
Eskoms position is to contract with Contractors who fully
demonstrate commitment to the development, implementation and
maintenance of a Quality Management System that conforms to the
requirements of ISO 9001:2008 (or latest applicable revision). or
equivalent. The priority is to encourage Contractors to continually
improve their quality management system and enhance service
delivery by obtaining ISO 9001:2008 (or latest applicable
revision). compliance and certification.
It is the Contractors obligation to ensure that their operations
and the products and services it provides to Eskom comply with any
applicable statutes and or regulations. Any non-compliance by the
Contractor and the resultant corrective actions shall be the
responsibility of the Contractor.
The Contractor shall ensure that he complies with the works
information and that appropriate quality requirements (as in the
main contract) are included in subcontracts placed by Contractors
to ensure subcontractors compliance with the Works Information.
3.1.3 QUALITY MANAGEMENT IN ENGINEERING
3.1.3.1 Design Quality Plan
Contractor shall develop and implement an Engineering Design
Quality Plan incorporating all processes, procedures and supporting
documents required to assure delivery of Engineering Work scope
deliverables in FEED, Detailed Design, Fabrication and Construction
and commissioning. Contractor Engineering Design Quality Plan shall
obtain a minimum of DRC2 status and ready for implementation within
thirty (30) days of the date of Contract award. However, all
documents must obtain the DRC1 status prior to distribution for
use.
3.1.3.2 Design Planning and Control
Planning, control, and verification of design activities shall
be achieved by Contractor through use of documented processes and
procedures that describe the organizational and technical
interfaces and that define the necessary information to be
documented, transmitted and reviewed as per the process defined in
Document Control and Exchange Specification. The Contractor
shall:
submit for Eskom review documented processes for the execution
of the Engineering Work scope including but not limited to the
sequencing of Work
develop a list of Engineering deliverables and an Engineering
Deliverables Responsibility Matrix. Provide to Eskom within thirty
(30) days following contract award the Engineering deliverables
and Engineering Deliverables Responsibility Matrix as per the
process defined in Document Control and Exchange Specification.
The Contractor shall further ensure that:
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 13 of 58
Engineering deliverables and the Engineering deliverables
responsibility matrix shall obtain a minimum of DRC2 status and a
DRC1 prior to distribution for use. Matrix should describe the
internal approval cycle for the Contractor.
Engineering Design Quality Plan processes shall define work
processes including use of design software, alternative calculation
requirements, and responsibilities for design activities for each
Engineering discipline engaged in the design Work scope.
Organizational and technical design interfaces shall be
identified and shall be controlled by engineering work processes
including assignment of personnel with appropriate authority to
assure coordination between Eskom, Contractor, subcontractors and
Suppliers.
Engineering Design Quality Plan processes shall provide for
Contractor discipline subject matter expert systematic and
controlled review of all design activities (e.g. establishing Basis
of Design (BOD) requirements, reviewing design inputs, approving
design outputs, etc.). Contractor discipline subject matter expert
review and approval shall be documented prior to submittal of
engineering deliverables for Eskom review.
3.1.3.3 Design Quality Planning
The Contractor shall: prepare an Engineering Design Quality Plan
or equivalent listing all Quality-affecting activities
and deliverables to be performed by each engineering discipline.
Design documents including specifications, data and other
information contained in the Work scope shall form the basis for
design planning.
utilize detailed review of the Work scope to determine
deliverables, including deliverable Quality activities, and
delivery schedules represented in the Engineering Design Quality
Plan. Based on the activities identified, each engineering
discipline shall identify, in a discipline specific plan, the
processes, procedures and work instructions to be followed to
execute the discipline assigned Work scope.
ensure that suitably qualified and experienced design engineers
are assigned to perform designated work. Contractor Engineering
Design Quality Plan shall specify the position identity,
responsibility, and authority levels of engineering discipline team
members to whom elements of project engineering Work scope
execution will be assigned.
The Contractor Engineering Design Quality Plan shall: document
the basis for checking deliverables and shall incorporate reference
checklists and other
tools to be used for deliverables review. document verification
activities, such as inter-discipline squad checks and formal design
review
requirements. specify the engineering discipline or other
technically qualified manager responsible for
verification that engineering discipline specific design plans
are consistent with project Work scope and are executed.
incorporate a design review and verification process to assure
alignment between project functional areas external to
Engineering.
Plans, processes and procedures for management and control of
project-related computer hardware and software shall be described
in Contractor Automation Plan. All computer software deployed in
support of Contractor design activities shall be systematically
verified by Contractor in accordance with ISO 90003, Software
Engineering Guidelines for the Application of ISO 9001 prior to
deployment to demonstrate fitness for purpose.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 14 of 58
Contractor Automation Plan shall receive DRC 1 status prior to
implementation.
3.1.3.4 Criticality Assessment and Application
Contractor shall: Utilize Quality Assurance and Quality Control
activities (e.g. audits, assessments, verification and
testing processes and procedures) commensurate with assessment
of Criticality. The level of Supplier verification and oversight by
the Eskom and/or Contractor is driven by criticality rating that
each item or piece of equipment receives.
Assess Criticality in compliance with Eskom Criticality Rating
Program and shall obtain a DRC 1 status for Contractor criticality
rating processes and process deliverables.
Utilize Criticality Process outputs in planning for and
execution of verification of engineering, design, procurement,
construction, installation, hook-up and commissioning
activities.
Obtain DRC 1 status for verification plans. Ensure Criticality
Ratings have been defined prior to issuing the first RFQ
Incorporate criticality process outputs into Contractor Engineering
Design Quality Plan. The criticality rating process should be used
as a tool to reach an action plan that minimizes risk
to Eskom. The initial criticality rating may be amended
(over-ridden) to a higher Criticality Rating during the Supplier
selection process based on their known current historical
experience and previous knowledge of the applicable potential
Supplier and/or Sub-Supplier.
Contractor criticality process outputs shall be considered a key
determinant in development of Quality audit and surveillance
schedules and in development of Quality Control Inspection and Test
Plans.
Eskom reserves the right to provide criticality rating for any
or all Work scope deliverables. The criticality rating system
applied shall be commensurate with the following Eskom
classification of parts system described as follows:
Classification of Parts
Class-1 (Vital). Those parts that (1) have no redundancy and (2)
are subjected to significant fatigue loads, failure of which could
cause a catastrophic effect to/loss of equipment and/or life.
Class-2 (Critical). Parts, the failure of which could lead to
one or more of (1) structural collapse, (2) a reduction or loss of
functional capabilities, (3) unintentional operation or
system/equipment shutdown essential to the safe functioning of the
equipment and/or (4) injury to personnel. (Immediate action: system
shut-down.)
Class-3 (Significant). Those parts (1) falling within Class-1 or
2, but with such high safety margin that the probability of failure
is so rare that it can be demonstrated only by analysis, or (2)
parts not within Class-1 or 2, but (a) the failure of which will
cause problems w.r.t. efficiency, or (b) the design philosophy
and/or materials used in the manufacturing process are so new that
particular qualification tests are required to demonstrate their
reliability.
Class-4 (Non-Significant). All parts not covered by Class-1, 2
or 3.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 15 of 58
NOTE 1: Class-1 parts must be uniquely identified by a S/N,
Class-2 parts should be serialised, Class-3 parts do not normally
require serialisation but may be identified by a S/N, Class-4 parts
do not require serialisation.
NOTE 2: Installations cannot be classified as vital. However, if
a faulty component could cause the loss of the equipment/life, this
means that it contains a potentially vital characteristic and an
independent double check requirement (i.e. "dual inspection") must
be identified.
3.1.3.5 Design Inputs
Contractor Engineering Design Quality Plan shall: Include
processes and procedures to assure applicable design input
requirements, including
latest local, state, national and international regulations, and
applicable industry codes and standards are identified, documented
and reviewed for adequacy. Incomplete, ambiguous or conflicting
requirements shall be identified and referred to the appropriate
authority for resolution.
Include processes and procedures to assure interfaces are
reviewed for effectiveness in sharing of information and in
communication of design input detail, timing and quality of
information needs. Disciplines shall include both internal and
external interfaces.
3.1.3.6 Design Outputs
Project design requirements shall be translated into
specifications, drawings, data sheets, instructions, etc.,
(referred to collectively as design documents) as necessary to
enable subsequent detail design, manufacture, installation and
operation to be performed in accordance with Work specifications.
Contractor Engineering Design Quality Plan shall include processes
and procedures to assure interfaces are reviewed for effectiveness
in sharing of information and in communication of design output
detail, timing and quality of information needs. Disciplines shall
include both internal and external interfaces. Contractor shall
include design output milestones, solicitation of key internal and
external end-user/customer comments, requests for clarification and
requirements for design outputs. Design output shall be prepared
and maintained in a readily accessible format in accordance with
Work specifications. Request by Contractor or by Eskom for revision
of design output format shall be subject to formal review by
Contractor and by Eskom project management. Authorization to
proceed by Eskom shall be required prior to execution of any
request for generation of design output in a format not provided
for in the Work scope.
3.1.3.7 Design Verification
Contractor shall document processes for design verification
including, but not limited to: Check and approval of all design
documents by suitably qualified and authorized personnel prior
to release for use Levels of competency of engineering personnel
having checking and approval authority. Conducting technical
audits/internal assessments. Where required, witnessing of
verification activities by specialist engineers or an authorized
third
party in accordance with Contract, engineering code or
specification or regulation. Contractor Engineering Design
Verification process shall include procedures for formal review and
approval of all design documents by suitably qualified and
authorized personnel prior to design document release for use.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 16 of 58
3.1.3.8 Inter-discipline Check and Review (Squad Check)
Contractor shall designate a Lead Discipline Engineer for each
engineering discipline. Contractor Lead Discipline Engineer shall
be responsible for verification that interdisciplinary checks and
reviews required by the applicable discipline Engineering Design
Quality Plan are performed by all affected internal and external
interfacing disciplines including Eskom. The issuing discipline
will examine all comments received and incorporate them into an
updated design or other project document as appropriate. If the
issuing discipline disagrees with any comments, the issue will be
discussed with the reviewer (discipline organization) concerned
until agreement on resolution is reached. No further work may be
performed on the disputed activity until satisfactory resolution
has been achieved. Responsibility for filing the original check
prints or equivalent on which comments are recorded, including
documentation of issue resolution, will reside with the issuing
Contractor Lead Discipline Engineer. Each issuing discipline will
maintain a file of inter-discipline review records where all
comment copies are maintained for the duration of the Project.
3.1.3.9 Design Validation (Including Software Validation)
Contractor shall develop and implement an Engineering Design
Validation process. Contractor Engineering Design Validation
process shall:
provide for a documented, comprehensive, and systematic
examination of design elements serving to establish the extent to
which Work scope deliverables have achieved compliance with Project
requirements.
incorporate but is not limited to design review, performance
(simulation) testing, alternative calculation methodologies,
mechanical completion checks, commissioning and ready for start-up
testing.
include procedures for establishing qualification and competency
of engineering personnel assigned design development, design review
and design approval authority.
include procedures for conducting discipline technical audits
and internal Quality assessments as work progresses toward
identified schedule milestones.
include procedures providing for witnessing of verification
activities by specialist engineers or by an authorized third party
in accordance with engineering code, project specification or
regulatory requirement.
Contractor Design Validation process and any performance
(simulation) testing proposals shall obtain DRC 1 status prior to
implementation. Contractor shall ensure performance (simulation)
tests are witnessed by Contractor qualified specialist engineers
and shall provide a minimum of fourteen (14) days notice of
proposed performance (simulation) testing to facilitate observation
by Eskom. Contractor shall employ performance verified and
validated computer software during design activities. New computer
software deployed in support of Contractor design activities shall
be systematically verified in accordance with ISO 90003, Software
Engineering Guidelines for the Application of ISO 9001 prior to
deployment to demonstrate fitness for purpose.
3.1.3.10 Design Changes
Contractor shall: control all design changes and maintain a
Design Change Log. All design changes and
supporting documents shall be subject to review by Eskom.
Changes to Eskom approved
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 17 of 58
preliminary design will be controlled, reviewed, and approved in
the manner, and as far as practical, by the Engineering team
members responsible for the original design.
obtain written Eskom approval for post-design freeze design
changes. Supply risk assessment data with request prepare a formal,
written statement of rationale accompanied by a report detailing
engineering,
operational, construction, health, environment, safety, and
other relevant discipline considerations for any post design freeze
design change request.
ensure that any proposed design change is evaluated for
adequacy, safety, conformance with specifications, suitability to
fulfil the purpose for which it is proposed and for cost and
schedule impact.
obtain Eskom Approval prior to commencement of detailed design
change. develop and efficiently and effectively implement a
post-design freeze Design Management of
Change (MOC) process for any Eskom approved detailed design
change. Contractor Design MOC process shall incorporate validation
of efficient and effective use of Engineering and other discipline
design processes and in particular shall ensure utilization of
Contractor inter-discipline check and review processes.
include in its processes for control of detailed design changes,
a Process Safety Management of Change Procedure to identify and
review changes that occur on documents used for the Design Hazard
Review. The procedures shall be applicable to any changes in these
documents through turnover. Changes to documents used in process
hazard analysis shall be controlled using appropriate Eskom and/or
national and international standards as a guideline e.g.US OSHA
1910.119.
All design changes shall be reviewed by the responsible
discipline team member and approved by Contractor discipline lead
engineer and all other discipline leads that are impacted by the
change. Revised sections of design documents shall be marked and
numbered for easy and quick identification. A Detailed description
of design changes shall be logged and recorded on the revised
drawing or other design document prior to submittal for Eskom
review. On achieving approval of the change, revised documents
shall be re-issued in accordance with Contractor document
distribution and control procedures and DRC1 status achieved prior
to implementation. Records of changes shall be kept for the
prescribed contract period agreed by all parties.
3.1.3.11 System and Sub-System Lists
Contractor shall complete System and Sub-System Lists during
FEED, Detailed Design and prior to issuance of work authorization
for Fabrication and Construction. Identification of System and
Sub-System and associated Quality verification documents shall be
prepared prior to initial stages of construction to facilitate
development and implementation of Construction Contractor tracking
systems. During Construction, Identification of System and
Sub-System Lists shall serve as the basis for tracking, completing
and compiling construction Quality verification documentation.
Identification of System and Sub-System Lists, and their Eskom
Quality verification documents, shall be developed and maintained
in a format suitable for ease of incorporation into handover to
operations Systems Dossiers.
3.1.3.12 Design Element Identification, Traceability, and
Composition Verification
Contractor engineering design procedures shall include provision
for unambiguous identification of design elements including but not
limited to materials, systems, equipment and other components.
Contractor shall comply with Eskom specification regarding
traceability and Positive Material Identification (PMI) for design
elements identified as subject to Eskom requirements.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 18 of 58
Design elements identified for enhanced control, e.g.
(Criticality 1, 2 and as required 3) systems or system elements,
shall be managed under Contractor product identification and
traceability program from completion of detailed design through all
subsequent Project phases, including handover to operations.
Contractor engineering shall ensure efficient and effective
communication of design element components subject to enhanced
control through positive identification and traceability procedures
to project Procurement and Quality.
3.1.3.13 Design, Safety and Model Reviews.
Contractor shall: document processes for conducting design,
safety and model reviews. These processes shall
receive DRC1 status prior to implementation. Design and safety
reviews shall include a process hazards analysis using appropriate
Eskom and/or national and international standards as a guideline
e.g.US OSHA 1910.119. Design, safety and model reviews shall be
planned, formal meetings during which an appropriately qualified
multi-discipline team examines aspects of the design. The reviews
shall at minimum consider compliance with Eskom Safety in Design
standard and Eskom Operations Assurance Process requirements.
Contractor process document shall provide for and describe Eskom
role in design, safety and model reviews.
provide Eskom a minimum fourteen (14) day notice of design,
safety and model reviews to allow for appropriate Eskom personnel
representation. Design, safety and model Review timing shall be
reflected in the project schedule.
3.1.3.14 Constructability Maintainability, Operability
Reviews
Contractor shall: document processes for implementation of
constructability maintainability, operability reviews
which include consideration for working at heights, safety in
design, and other hazardous work conditions. These reviews shall be
planned, formal meetings during which an appropriately qualified
multi-discipline team examines aspects of constructability,
maintainability and operability.
provide Eskom a minimum fourteen (14) day notice of such reviews
to allow for appropriate Eskom personnel representation. The timing
of constructability, maintainability, operability reviews shall be
reflected in the project schedule
document outputs from reviews and make these available to Eskom
on request.
3.1.4 QUALITY MANAGEMENT IN FABRICATION & CONSTRUCTION
3.1.4.1 General
Contractor fabrication, construction and completions Quality
Management organization shall be independent from those performing
the Work.
Fabrication, construction and completions Quality Management
organization chart shall clearly illustrate reporting relationship
between Contractor fabrication and construction site project
Quality Management organizations and Contractor home office Quality
Management organization.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 19 of 58
Contractor shall document and make available for Eskom review a
comprehensive fabrication, construction and completions Quality
Management Plan (CFCCQMP). CFCCQMP shall include all Quality
Management plans, processes, procedures and methods.
CFCCQMP and organization structure, including a bar chart
representation of the schedule proposed for personnel mobilization,
shall be submitted for Eskom review not later than sixty (60) days
prior to start of Work at any Fabrication or Construction site.
Such mobilization shall be in compliance with Project Quality
Personnel Qualification Specification.
CFCCQMP, Quality Management organization structure and
mobilization schedule shall obtain DRC 1 or 2 statuses prior to
implementation.
CFCCQMP shall ensure Fabrication and Construction Quality
Management requirements for Work scope systems, system components,
equipment, materials and other procured goods are clearly and
unambiguously documented, and are efficiently and effectively
communicated to Project Procurement, Logistics, Construction
Management, Quality, Security and other Project functional areas
(as required for efficient and effective support of Fabrication and
Construction Work scope).
All applicable codes, standards, and relevant acceptance
criteria documents are available at the work location and that
Eskom representatives on site shall have on going access to this
information. Workplace documentation shall be available in English
and in any workforce appropriate language.
Contractor fabrication, construction and completions Management
shall develop and implement a process for efficient and effective
communication to Project Engineering, Security, Procurement,
Logistics and other Project functional areas regarding
environmental, workforce, community, government or other
challenges, threats or factors which impose a need for change in
Fabrication or Construction site management process or
procedure.
Key characteristic Manufacturing processes can be improved
through adequate planning and effective management of key
characteristic variation. The key characteristics focus is intended
to improve confidence for part features whose variation has a
significant influence on end-products form, fit, performance,
service life and manufacturability.
What is a Key Characteristic? For a part, subassembly or system,
it is defined as selected geometrical, material properties,
functional and/or cosmetic features, which are measurable, whose
variation control is necessary in meeting customer requirements and
enhancing customer satisfaction. Key characteristics are also
selected measurable parameters of a process whose control is
essential to manage variation of part or system key
characteristics.
How are Key Characteristics defined? The key characteristics
owner normally defines them. The owner is either a person or
function that recognizes the reasons for selection of the key
characteristic. Typically, these responsibilities are held by
internal or external design, quality or manufacturing engineering,
and should be identified by a cross-functional team.
Key characteristics shall be defined, by the OEMs and at the
discretion of Eskom, to direct Quality Control efforts.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 20 of 58
3.1.4.2 Quality Audits and Related Quality Performance
Reviews
Quality Audits and related Quality performance reviews are
intended to provide an objective evaluation of compliance with
performance expectations defined in this specification, in
Contractor CQP and in any other project Work scope
specification.
Quality Audits and related Quality performance reviews include
but are not limited to any Quality or other project functional area
audits, assessments, verification of compliance reviews,
surveillance, inspections, or other interim or final assessments of
Work scope deliverables provided by Contractor, subcontractors or
Suppliers.
Quality Audits and related Quality performance reviews shall be
carried out by trained, accredited and experienced personnel in
accordance with procedures documented in the CQP.
Contractor shall submit for Eskom review documented processes
for conducting project Work scope Quality Audits and related
Quality performance reviews. Contractor Quality Audits and related
Quality performance review processes shall be designed to address
evaluation of progress toward completion of project functional area
deliverables as well as final deliverable quality.
Contractor shall provide a schedule of anticipated Quality
Audits covering all functional areas and related Quality
performance reviews at the time of first post-contract award CQP
submittal.
Contractor shall maintain an accurate Quality Audit and related
Quality performance review schedule and shall incorporate the
current schedule as an attachment to the Contractor CQP.
Contractor Quality Audit and related Quality performance review
schedule development process shall be designed to incorporate
consideration of information generated by previously conducted
audits and reviews, by input from project risk management
evaluations (Risk Register) or from Eskom, Contractor, or
subcontractor subject matter expertise
Eskom reserve the right to oversee Contractor audit programs by
participating in selected audits as an observer, and by assessing
Contractor at key work stages. Eskom will coordinate with
Contractor to develop an oversight schedule aligned with Contractor
audit schedule.
Eskom will have right to obtain access to any audit reports
performed by the Contractor reflected in the audit programme
Eskom reserves the right to conduct independent Quality Audits
scheduled and unscheduled - during all phases of the Contract.
Contractor shall provide all resources to support these
activities.
Eskom shall be given access at all reasonable times before,
during and after manufacture and before delivery, construction,
erection, commissioning to measure, test and inspect the products
and workmanship as necessary on the Contractors premises and on
Eskom sites.
The Contractor shall obtain access for Eskom to measure; test,
witness tests, and inspects products which are being manufactured
by any subcontractor. This includes surveillances.
Assessments and audits shall be carried out on all new
Contractors and its subcontractors. Eskom shall have the right to
participate or request for a technical investigation to be
launched
and conducted on the Contractor and subcontractors premises or
other sites, when risk to Eskom products or service deliverables
are identified.
Qualification requirements for Contractor and subcontractor
personnel engaged in conducting Quality Audits and related Quality
performance reviews shall be defined in the Contractor CQP and
shall be in compliance with Project Quality Personnel Qualification
Specification.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 21 of 58
3.1.4.3 Eskom Right of Access
Eskom: shall be granted electronic and hard copy access to all
quality plans, procedures, documentation,
and other quality records relating to the Work including but not
limited to data extracts. reserves the right to review, inspect and
audit any or all parts of the Contractor QMS as well as
any documentation, materials or equipment associated with the
Work, at any time or Project Work location.
shall carry out assessments and audits on all new Contractors
and subcontractors Contractor:
Shall support Eskom effort to monitor, verify and/or witness any
activities associated with the Work at any time.
Shall cooperate with Eskom requests for documentation, records,
and inspection and witnessing. Eskom participation in audits,
appraisals, assessment of plan and verification shall be conducted
at no extra cost to Eskom
Shall ensure supplier provides access to Eskom to all Work
procedures, quality records, and to all supporting documentation
through provision of access to view and photocopy as required to
support verification of Work scope requirements. Access shall
include the ability to photograph Eskom equipment, systems, system
components, materials, etc.
Provide access to all Quality related information pertaining to
activities performed by itself or subcontractors, which Eskom might
not have participated in the witnessing of quality assurance or
control thereof (this refers to inspections, audits, etc.,
performed by the Contractor on its own subcontractors)
Eskom shall be allowed to assess, audit, approve or reject any
sub-contractors employed by Eskom's Contractors/Suppliers to assist
with the product and/or service delivery to Eskom.
Shall ensure above requirements are flowed down to
subcontractors
3.2 TENDER SUBMISSION PHASE
3.2.1 Contractor documents with the tender
The Contractor shall submit the following documents with the
tender: (All documentation submitted shall be in English).
a1] The Contractor shall complete and sign Form A
(Enquiry/Contract/Quality Requirements) a2] The Contractor shall
complete and sign Form B (Quality Requirements for Quality
Management
ISO series) a3] The Contractor shall attach the following: a4] A
copy of the CV/Resume of the Contractors quality management
representative a5] The Contractor shall attach a copy of ISO
9001:2008 (or latest applicable revision). certificate
or objective evidence (e.g. copy of a compliance audit report)
of a QMS that complies with ISO 9001:2008(or latest applicable
revision).
a6] The Contractor shall attach a copy of the latest
structure/organogram of the quality function/ department, including
an abridged indication of qualifications of personnel. This
structure
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 22 of 58
shall indicate to whom the organizations quality management
representative reports in the organization
a7] Information on similar work performed (at most within the
last two years) a8] Sample CQP (including a QCP and ITP) from a
similar project carried out within the last two
years. a9] A sample Non-conformance report shall be attached to
tender a10] A sample of a corrective and preventive action report
shall be attached to tender a11] A sample of an audit schedule and
report on a sub-Contractor a12] A detailed description of the
process and procedure for the evaluation, selection and control
of
suppliers and subcontractors shall be attached to the tender
a13] Any quality management accreditations (NDT/ NDE/ Welding) and
special processes requiring
certification a14] List of long lead items a15] Preliminary
manufacturing schedules a16] Preliminary risk assessment data a17]
Preliminary list of critical characteristics
3.2.2 The Contractor shall submit a draft Contract Quality Plan
(CQP) with the tender. The CQP shall contain the following
information (Refer Annexure C):
b1] A cover page containing the following information: a. The
draft contract title b. The Eskom tender number c. The draft
contract commencement and completion dates d. The names,
designations, signatures, of personnel responsible for preparing
and
approving CQP e. Provision for Eskom acceptance of CQP f. An
index of contents g. A full description of the Works Information h.
A description of the communication channels between the Contractor
and Eskom
regarding all quality related issues (fixed contract meetings)
i. An organogram showing the structure of the Contractor, which
shall show the quality
management representative, and all other personnel responsible
for control of quality activities/processes
j. An index of all the interfacing documents between the
Contractor and Eskom k. A schedule (Index) of documents / records
that shall be:
i. Submitted to Eskom during the contract ii. Captured on the
Contractors QMS iii. Submitted to Eskom prior to the completion of
the works/contract iv. A list of all sub-Contractors that shall be
utilized during the contract.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 23 of 58
l. This list shall indicate: i. the scope of supply of product
and or service, ii. a method of acceptance of these sub-Contractors
by Eskom shall be indicated iii. An indication of how the
sub-Contractors shall be controlled and monitored during
contract execution iv. Objective evidence that Contractors
sub-Contractors will work to the specified
quality standard v. An index of products that shall be:
a. Manufactured by Contractor /subcontractor b. Refurbished by
Contractor /subcontractor c. Purchased as a new product
vi. A list of products/processes for which QCPs, ITPs WILL BE
and WILL NOT BE prepared
vii. A list of products/processes/services that require special
controls (e.g. welding, NDT/NDE)
viii. A description of the interface of the sub-Contractors and
Contractors/suppliers QMS and applicable documents, procedures and
work instructions
ix. An index of all standards, specifications for all processes,
products, materials and plant applicable to the works/contract
x. A description of how all quality records shall be controlled
(e.g. identified, completed, retained and disposition)
xi. A list of purchase orders for quality critical products
showing purchase order number and scope of supply
xii. Application for defects acceptance (concessions) registers
to be updated during the Contract.
xiii. A typical copy of the suppliers/ Contractors concession
request register which shall be updated during the
project/contract
xiv. Databook index and O&M Manual xv. Spare parts
inter-changeability records
3.3 TENDER EVALUATION, ADJUDICATION AND NEGOTIATION PHASE
a) Eskom shall carry out a full technical and QMS assessment on
a Contractor. b) Eskom shall carry out an evaluation of quality
documentation submitted with each tender. c) Eskom shall have the
authority and right to assess all of the Contractors
subcontractors
before Contract award and to reject any that do not meet its
requirements.
3.3.1 Subcontracting
a) Submission of subcontractors contract administration plan
(CAP). The Contractor shall compile and submit a contract
administration plan for Eskoms acceptance. The CAP must contain the
following:
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 24 of 58
- a full schedule of subcontractors to be used during the
lifecycle of the project. Such schedule shall include past
performance of subcontractors as well as capabilities matrix
- the portion of the works information or volume of work to be
subcontracted to each subcontractors with monetary value
- a schedule indicating how subcontractors were or will be
pre-qualified, - the form of contract that will govern and regulate
relationships between the main
Contractor and all subcontractors including term and conditions
of contract - subcontractors performance monitoring and control
strategies - a risk register listing all foreseeable contractual
risks associated with the usage of
subcontractors, sub consultants and suppliers with relevant and
applicable risk management strategy.
All risks/foreseeable risks must be listed under contract data
provided by the Contractor. Risks to be carried by the main
Contractor shall be separated from those to be carried by
subcontractors
The risk management strategy must be aligned to actual costs and
percentages stated in the schedule of costs components
- subcontractors respective high level programmes including
subcontractors execution statements and respective interfaces
- subcontractors schedule of insurances - a contract
communication plan whenever there is deviation from the
communication
plan presented by Eskom and/or the NEC applicable contract - a
guaranteed performance. This refers to the quality and conditions
in which the works
will be upon completion and hand over to Eskom - subcontractors
payment schedule processes - subcontractors change management
processes - termination processes
b) Pre-qualification of subcontractors by the Contractor the
Contractor shall pre-qualify all subcontractors in respect of
overall competence and
capability and quality management system, by mean of a formal
audit or assessment. All subcontractors shall comply with the
requirements of ISO 9001:2008 (or latest applicable revision).or
equivalent
c) Supplier and subcontractor Qualification and Selection
Contractor shall develop and execute an effective and efficient
program to ensure Project
Supplier and subcontractor qualification is conducted in
compliance with Eskom Project Supplier Qualification Program.
Eskom shall be allowed to assess, audit, approve or reject any
sub-contractors employed by Eskom's Contractors/Suppliers to assist
with the product and/or service delivery to Eskom.
Contractors/Suppliers shall unambiguously acknowledge that
Eskoms acceptance of the quality credentials of sub-contractors
does not relieve the Contractors/Suppliers from any of their
contractual and regulatory obligations. The Contractors/Suppliers
remains fully responsible for compliance with all the provisions of
the contract and furnishing products/services
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 25 of 58
which meet all applicable requirements of the contract, whether
such products are manufactured, processed, provided or procured by
the Contractors/Suppliers for the contract.
Contractor shall source all services, materials, supplies,
equipment, systems, system components, etc. from firms identified
in Eskom Approved Vendors List (AVL). Should Contractor identify
the need for sourcing from a firm or firms not currently included
in Eskom AVL, Contractor shall notify Eskom in accordance with
process defined in Project Supplier Qualification Program
(Contractor Request)
Use of services, materials, supplies, equipment, systems, system
components, etc. from unlisted sources prior to receiving Eskom
approval shall be subject to immediate incident investigation to
determine the origin and nature of deviation from procedure and
system requirements. Proposed incident corrective action shall be
submitted to Eskom for approval. Repair and or replacement expense
shall be assigned to Contractor account.
Where corrective action includes independent testing, such
testing may include: mechanical testing (tensile strength,
elongation, charpy, etc.), chemical composition (wet chemical
analysis), and any other supplemental testing required by the
original material specification or Project requirements. Contractor
shall be responsible for the cost of additional testing regardless
of test results. Should Eskom elect to deny use of the material,
all replacement material shall be furnished at Contractor cost.
d) Management of subcontractors during project execution phase
the Contractor shall submit the names of all proposed and qualified
subcontractors for approval
by the Project Manager. The Contractor doesnt appoint a
subcontractor or make use of his services or allow him to
access site without prior written consent / acceptance of Eskom.
the subcontractor and the conditions and terms governing the
contractual relationship between
the Contractor and subcontractors must also be presented to the
Eskom for acceptance the Contractor and all his subcontractors
shall acts in accordance with the health and safety
requirements as stated in the works information The Contractor
shall, for the duration of the contract, maintain a list of
approved
subcontractors including the scope of supply for which they are
approved. The Contractor shall at all times ensure that the
following particulars in respect of all its
subcontractors are submitted to Eskom, within 4 weeks of
contract placement. The Eskom reserves the right to satisfy itself
on the validity thereof:
Name and Address; Portion of the Works Information to be
subcontracted; subcontractors QMS and certificate number (if
certified) or audit report number (if not certified); Current scope
of supply as recorded on their ISO 9001:2008 certificate; or other
proof Previous experience in supplying identical or similar work;
Approved by Contractor: Yes/No; Date of Approval. The Contractor
shall not replace a subcontractor without informing Eskom Changes
of subcontractors or their details must be communicated to Eskom
prior to execution
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 26 of 58
3.4 CONTRACT AWARD PHASE
a) Access to premises, facilities, documentation and
information: i. Eskom or its inspection agency shall be afforded
access to all areas of the
Contractors and Subcontractors premises and facilities, to
conduct quality audits, surveillance, investigations, expediting
and inspections to verify compliance with the agreed
requirements.
ii. Eskom reserves the right to participate in incident
investigations if the quality and / or technical characteristics of
product and/or services to Eskom are affected, irrespective of
whether the incident occurred on an Eskom site or the contractors
premises.
iii. All quality system documentation, records, reports, etc.,
shall be made available for review when requested by Eskom or its
appointed inspection agency. The Contractor shall give written
permission to its product and quality management system
certification bodies, and/or any inspection/testing authority
acting on its behalf, to make available all information at its
disposal, and without any reservation, for review by Eskom, or by
its appointed inspection agency
iv. The Contractor shall provide suitable facilities to Eskom or
its appointed inspection agency, and shall supply any assistance
necessary for the performance of any audit, surveillance,
assessment and/or inspection activities to be conducted by
Eskom
v. The Contractor shall provide timely notification to Eskom of
changes to any agreed-upon request for inspection
vi. The Contractor shall ensure a safe working environment for
Eskom or its appointed inspection agency, by informing it of the
necessary safety requirements and possible safety hazards
b) Eskom non-conformance & inspection defect/reject reports:
i. Non-conformance reports raised by Eskom and issued against the
Contractor shall
be investigated by the Contractor as a matter of urgency, in
order to determine the root cause, corrective action and preventive
measures as required, with the implementation time-frames. Initial
response within 3 working days.
ii. A formal response shall be prepared in respect of the
defined criteria, and submitted to Eskom for its review, evaluation
and acceptance, within a maximum of fourteen (14) calendar days
from the date of issue of the non-conformance report see note at
bottom of page on hard copy
iii. Eskom may at its discretion request a response sooner, and
in any case before the supplier proceeds with any pending/further
intervention or corrective action as may be required by Eskom.
iv. Should Eskom or its inspection authority/agency identify any
non-conforming products/service during the conduct of its
audits/surveillances/inspections, the supplier shall be deemed to
be in breach of contract, and shall be held liable for any repair,
rework and/or associated replacement costs. The Contractor may in
such instances also be held liable for the full costs associated
with the conduct of follow-up audits/surveillances/inspections
v. The nature, magnitude and/or frequency of non-conformance or
inspection defect/rejection reports raised by Eskom or its
appointed inspection authority/agency, shall form the basis of any
action to rescind the suppliers qualification status.
-
CONTROLLED DISCLOSURE When downloaded from the EDS database,
this document is uncontrolled and the responsibility rests with the
user to ensure it
is in line with the authorized version on the database.
Supplier Contract Quality Requirements Specification
Unique Identifier: QM-58 Revision: 0 Page: 27 of 58
3.5 CONTRACT AWARD AND QUALITY CONTROL PHASE
3.5.1 Pre-contract execution
3.5.1.1 Supplier and subcontractor Quality Management Plan
Contractor shall require Suppliers and subcontractors to submit
project Quality plans and associated documentation in accordance
with requirements of Project Quality Management System processes
applicable to subcontractor or Supplier Work scope. Contractor
shall, where applicable based on Work scope Criticality, ensure
Procurement documents clearly and unambiguously require Supplier
and subcontractor submission of a Supplier or subcontractor CQP for
Contractor and Eskom review. Supplier or subcontractor CQP shall
achieve DRC 1 status prior to implementation. Contractor shall
ensure Supplier or subcont