Eskay Creek Mine Eskay Creek Mine
ESKAY CREEK MINEESKAY CREEK MINE–– April, 2004 April, 2004
OUTLINE
- Snapshot of Eskay
Creek.
- Eskay People
- Major Issues &
Exploration.
HistoryHistory
� To December 26, 2002, the
Mine has produced 2.86
million ounces of gold and
129.6 million ounces of
silver.
� 2002 production averaged
637t/day and is budgeted
at 700t/day in 2003.
It is still Intact and was left untouched on
the Rehabilitated Site of the Original
Exploration and Development Camp.
Tom MacKay’s Original Cabin.
MinesiteMinesite photo showing the photo showing the
general layout and location of thegeneral layout and location of the
orebodiesorebodies on the hillside. on the hillside.E
SK
AY
OR
EB
OD
IES
N
Production - January 1995 to Dec 27 2003:
1.53 million tonnes grading: 58.1 g/t Au
Proven and Probable Reserves at Dec 27, 2003:
0.84 million tonnes grading: 34.8 g/t Au
2635 g/t Ag
1604 g/t Ag
Indicated Geological Resource: 0.63 million tonnes grading: 12.9 g/t Au
359 g/t Ag
Eskay Creek MineEskay Creek Mine
Ore Reserves at Dec 27, 2002Ore Reserves at Dec 27, 2002
ESKAY CREEK MINEESKAY CREEK MINE2004 Budget2004 Budget
2004 Budget Statistics:
� DSO tonnes 135,000, 370 tpd.
� Mill tonnes, 110,000, 300 tpd.
� Grade: 42.1 gpt Au, 2060 gpt Ag.
� Payable Au ounces: 310,000.
� Payable Ag Ounces: 14,987,000.
ESKAY CREEK MINEESKAY CREEK MINE2004 Budget2004 Budget
2004 Budget Statistics:
• Capital Expenditures: $8.4 MM.
• Total Cash Costs: $654/tonne
CDN.
• Total Cash Costs: $110 US/ounce.
• Cash Flow: $66.2 MMUSD.
2004 BUDGET SITE COSTS
Services
9%
Exploration
DD
5%
Other
1%
Total
Transporation
12%
Mill
4%
G & A
4%
Roads
1%
Total Mining
21%
Total Smelter
43%
Eskay Creek Ore Bodies: 2004 Mine Plan
10200
10600
10800
11000
11200
800m
600m
21B
11400
400m
10400
10000
Resource models
21C-south pod
21C-north
NEX
HW
109
12EPumphouse
NEX&HW Deep
1000m
900m
800m
700m
600m
500m
400m
300m
10200
10600
10800
11000
11200
800m
1000m
600m
21B
11400
400m
10400
10000
Resource models
21C-south pod
21C-north
NEX
HW
109
12EPumphouse
NEX&HW Deep
1000m
900m
800m
700m
600m
500m
400m
300m
0
40
80
120
160
109 21B 21C HW NEX PMP
To
nn
es (
000s)
0.0
40.0
80.0
120.0
160.0
Au
E (
gp
t)
Tonnes
AuE
N
ESKAY CREEK MINEESKAY CREEK MINE–– April, 2004 April, 2004
- Snapshot of Eskay
Creek.
- Eskay People
- Major Issues &
Exploration.
ESKAY CREEK MINEESKAY CREEK MINE
General Manpower
Statistics
Barrick – 155
Contractors – 194
total – 349
Approximately a third
are from the Tahltan
First Nation
Involvement ofInvolvement of TahltanTahltan
First NationsFirst Nations
� Percentage of Employment 34%
� Joint Ventures (Arrow-Tahltan Trucking, Spatsizi Remote Site
Services, Procon-proposed also Tahltan Nation Development Corporation)
� Income and donations (to date -LOM): C$93M
� Apprenticeships (Mechanics, electricians, chefs, warehouse)
� Quarterly Meeting Updates – Opportunites for
Increased Involvement and Increased Capacity
ESKAY CREEK MINEESKAY CREEK MINE
Joint Ventures
1. Arrow – TNDC
Transportation
Systems
2. Spatsizi Remote
Services
ESKAY CREEK MINEESKAY CREEK MINE
Road maintenance and
material handling
contract with Tahltan
Nation Development
Corporation (TNDC)
ESKAY CREEK MINEESKAY CREEK MINE–– April, 2004 April, 2004
- Snapshot of Eskay
Creek.
- Eskay People
- Major Issues &
Exploration.
0
50,000
100,000
150,000
200,000
250,000
300,000
Mill Tonnes
DSO Tonnes
Mill Tonnes 120,450 120,780 122,230 127,750 127,750 67,586
DSO Tonnes 135,050 135,050 109,506
2003 2004 2005 2006 2007 2008
To
nn
es
MILL & DSO ORE (350tpd)MILL & DSO ORE (350tpd)
Major IssuesMajor Issues
- Exploration: Three main areas of focus.
- Mine & Mill throughput optimization.
- Effective and respectful transition to a mill only
operation at reduced production rates.
2004 DIAMOND DRILLING2004 DIAMOND DRILLING
Definition Exploration
Underground (m) 16,500 16,500
Surface (m) 3,000 2,000
Development req'd (m) - 300
Total $ ($US millions) 0.85$ 1.42$
21B Zone
Pumphouse
Zone
21C South
70 Stope
21E
Zone
NEX
Zone
HW
Zone
21A & 21C
Resource
Deep Adrian
Resource
109
Zone
21C North
Water Tower
Resource
21C ‘Mid’
Resource
21C South
76 Stope
N
RESERVES & RESOURCESRESERVES & RESOURCES
1000m
800m
600m
400m
200m
0m
HW Zones
Bowser
Sediments
500m
Contact
Mudstone 21B Zone
NEX Zone
109 Zone
msl
Basalt
sequence N
Longitudinal Section Looking West Across The Deposit
Deep Adrian
88
66
21 Zone
Deposits
22 Zone
>
>
>
>
>
>
1,000
*
0
metres
500
58
57
56
55
54
53
22 Zone22 Zone –– Location MapLocation Map
Major IssuesMajor Issues
- Exploration: Three main areas of focus.
- Mine & Mill throughput optimization.
- Effective and respectful transition to a mill only
operation at reduced production rates.
Major IssuesMajor Issues
- Exploration: Three main areas of focus.
- Mine & Mill throughput optimization.
- Effective and respectful transition to a mill only
operation at reduced production rates.