ERTMS Testing – an industry view ERA Conference, Lille, 29 March 2011 David Gillan, General Manager, UNISIG Emmanuel Brutin, Senior Public Affairs Manager, UNIFE
ERTMS Testing – an industry view
ERA Conference, Lille, 29 March 2011
David Gillan, General Manager, UNISIG
Emmanuel Brutin, Senior Public Affairs Manager, UNIFE
Two ERTMS paradoxes
Some observations on testing
The testing process
What is testing not about
A contribution to the solution
A view of the “Old process”
In conclusion
Presentation outline
2
TWO ERTMS PARADOXES
3
ERTMS Paradox (1)
At a national level, supplier-to-supplier compatibility
has been achieved (on-site testing played a crucial role)
However:
Tests made on a purely national basis, no European
process nor “cross-border” testing;
Hence lack of certainty that ERTMS OBUs can “run on
any line”
Two ERTMS
paradoxes
4
ERTMS Paradox (2)
ERTMS is in operation on 14,000km and 2,600
vehicles, mainly at a national level
More than 37,000km are contracted and it is a de
facto worldwide standard – and proved to be
attractive for railways everywhere in the world!
However:
Cross-border operation is still an issue
Two ERTMS
paradoxes
5
SOME OBSERVATIONS ON
TESTING
6
What is testing NOT about?
It is not about remedying a situation where
trackside and onboard units are running with
different SRS versions
For this an upgrade of equipment is needed! (cf
joint recommendations to simplify ERTMS)
It is not about transferring responsibilities to any
infrastructure manager or railway undertaking
Industry remarks on
testing
7
What is testing about?
In theory, proving that the OBU conforms to the TSI by
passing the Test Specification in Subset -076
However, the ERTMS specifications give some freedom to
implement functionalities. Given this freedom, there is no
100% evidence whether a track side and on-board "fit"
together even when both are compliant with the
specifications
UNISIG has therefore developed Subsets -110, -111 and -
112 which provide for laboratory testing between OBUs and
actual track conditions before going on site
Industry remarks
on testing
8
What is testing (really) all about?
Proving that the OBU is “fit for purpose”
At least that it conforms to the TSI/SRS
At least that it conforms to the different trackside
implementations on the lines over which it is going to
run
Subsets -110, -111 and -112 provide for the
laboratory testing of the actual OBU against the actual
trackside implementation
Remark: historically, with one single supplier or one
single customer, it would have been much easier
Industry remarks
on testing
9
THE TESTING PROCESS
10
Type of testing Reference document Test specification
Testing conformity to the
technical specifications
e.g. Subset 026 (SRS),
Subset 036 (Eurobalise),
etc.
- Public document
- Unique EU document
- Ruled by a Change
Control Process
- Public unique test
specifications (e.g.
Subset 076, Subset 085,
etc.)
Testing conformity to the
operational
specifications on the
lines on which it is going
to run
- In most cases National,
non-public and only
partly complete
-In any case, not
harmonised in Europe
- No European change
control
- Operational test
scenarios to prove that
each operational
requirement is met are in
most cases
existing/public
- No European change
control
The testing
process
11
TODAY
The testing
process
12
ERTMS can deal with such national variations, but the
process is complex and costly
The system is linked together and inter-
dependant
E.g. when an “interoperability constraint” is
exported by one of the trackside installations, it
may prevent all OBUs running on this installation
from being able to run on the other ETCS lines
(examples later)
Therefore “isolated/national actions” not only
cannot solve the problem, they make the situation
worse
The testing
process
13
A CONTRIBUTION TO THE SOLUTION
14
Cenelec based system delivery process
Installation
Design
Production
Implementation
Operational
Requirements
Technical
Specification
System
Validation
Integration
Installation Factory
Acceptance
Site
Acceptance
Subset 076 etc.
Operational Scenarios
- Migrate all
installations to
2.3.0d/B3
- Complete Subset -
076 for 2.3.0d/B3
- Collection of all
operational
scenarios in EU
database
- Collection of the
test specifications for
the scenarios in EU
database
- European Change
Control Management
for operational
scenarios/tests
Avoidance of
“tailored” or “specific”
functions
In addition, the following
medium to long-term
measures would facilitate
interoperability:
-Harmonisation of
operational rules
- Harmonisation of
engineering rules
- ERA to become a
certification authority
Commission
to take
necessary
measures
Ongoing by
ERA with
stakeholders
-Establishment of EU-
accepted format for
tenders
- ERA/EU involvement
in tenders conformity
checking?
- Scenarios to be first
written and notified in
an identical format by
Infrastructure Managers
- Tests to be first written
and notified in an
identical format
- ERA to manage
database
- To be organised via
the database/ERA
Proposed
solutions
16
Testing conformity to the
technical specifications e.g.
Subset 026 (SRS), Subset
036 (Eurobalise), etc.
Testing conformity to the
operational specifications
on the lines on which it is
going to run
A VIEW OF THE
“OLD PROCESS”
17
A real example of “old process”
• Country A has its version of ETCS (ATCS) and vehicle 001 has it installed on-board and authorised for Country A.
• Country B installs their version of ETCS (BTCS)
• Class 001 on-board needs a software change to be compatible with BTCS.
• This is done and it is authorised for country B
• This makes the Authorisation for Country A’s ATCS invalid!
• Class 001 on-board needs new authorisation for country A.
• This may not be possible if the changes for B make it incompatible with country A or
• If any software changes are required for the new authorisation in A then another new authorisation is required for Country B etc, etc.................... ad infinitum
The “old process” is worse than this because
• ETCS is actually different for each Project
• E.g. 3 x incompatible versions in one country
• Only one MS has published their specific ETCS on-board requirements
• And still their IM has installed a system that does not conform!
• Infrastructure is upgraded from time to time. Any upgrade on one infrastructure route would trigger a new round of on-board authorisations for all vehicles over all infrastructure in Europe.
• No ETCS installation conforms fully to the TSI
• If old processes (design and authorisation tools) continue to be used ETCS interoperability is a logical impossibility
The Solution
• Remove the old processes and rules and implement the directives.
• “Business as usual” will not work.
• Mixing the authorisation regimes (e.g. ETCS so far)is an economic and interoperability disaster
• The directives are the tools designed for managing open systems.
• To ensure Technical Compatibility and economic efficiency they must be used
The solution
So when will it get better? That depends... • On the Railway Operators, Suppliers and their Associations
• By lobbying insisting that MSs, NSAs, IMs and suppliers conform NOW
• And COMPLAINING FORMALLY at national and European level when they don’t. Case law is an essential motivator for Ministries and NSAs.
• Helping us close “open points” like EMC, by providing resources.
• On the Member States and National Safety Authorities
• Implementing the directive according to the common understanding
• “cleaning up” their rules for network-vehicle compatibility-taking them over these rules from the IMs
• On the Infrastructure Managers
• Making transparent the nature of their infrastructure
• Installing and maintaining infrastructure that conforms to the TSIs and national rules
IN CONCLUSION
22
Industry fully agrees with ERA that the “old process” has to be
changed
Unfortunately, such change takes a very long time and involves
a lot of vested interests; it is therefore vital to introduce interim
measures for the short to medium term
Industry welcomes the leadership of ERA and is committed to
participate fully
Industry will propose to the sector a new testing project to be
supported under the upcoming TEN MA 3rd Call
23