Errors and Omissions (E&O) by Professional Engineers on Department Contracts Siddhartha Kamath, P.E.
39

Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

May 13, 2018

Download

Documents

vudieu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Errors and Omissions (E&O)by Professional Engineerson Department Contracts

Siddhartha Kamath, P.E.

Page 2: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

LET’S FIRST DO A POLL.

• FDOT Design

• FDOT Construction

• Consultants• Design• CEI

• Others?

Page 3: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

PREVIOUS DESIGN EXPO E&O SESSIONS*

• Did you attend a previous E&O Session?

• 2014

• 2015

• 2016

Page 4: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

WHAT WILL BE PRESENTED

• E&O – What it is

• Why it is important

• Why FDOT seeks recovery

• Process from Discovery to Resolution

• Examples

• What FDOT has learned

Page 5: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Terms

• CCEI / EOR: Consultant (Construction/ Design)

• CPM / DPM: Project Manager (Construction/ Design)

• E&O: Errors and Omissions

• Premium Cost: Cost paid to contractor for non-value-added work

• E&O Premium Cost: Premium Cost fault of consultant

Page 6: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

FDOT/CONSULTANT RELATIONSHIP

• FDOT expects a Design consultant (EOR) to produce complete and constructible plans for construction.

• DOT expects a CEI consultant to oversee construction activities in executing work shown in the plans produced by the EOR.• Expecting PERFECTION is unreasonable.• Consultant must be held accountable for errors.

Page 7: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

SOME QUOTES

Will Rogers: “Good judgment comes from experience, and a lot of that comes from bad judgment.”

Ashleigh Brilliant: “It’s human to make mistakes and some of us are more human than others.”

Page 8: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Scenario

• Contractor discovers an existing condition not indicated in construction plans, notifies CCEI, and estimates cost to deal with condition will be $76,543.

• CCEI confirms contractor’s observation.

• FDOT approves a $76,543 Supplemental Agreement.

Page 9: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Scenario Questions*

• Question 1: Was there E&O

• Question 2: Was there Premium Cost?

• Question 3: Who should be held accountable?

Answer: It depends.

Page 10: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

E&O – WHAT IT IS

Definition: Errors / Omissions by consultant in performing contractual services for the Department

• EOR Design Consultant

• CCEI Construction Engineering and Inspection Consultant

Page 11: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

E&O – WHY FDOT SEEKS RECOVERY*

• Statutory Requirement – 337.015(3), F.S.

To protect the public interest, the department shall vigorously pursue claims against contractors and consultants for time overruns and substandard work products.

• The FDOT must hold consultants accountable for Avoidable E&O.

Page 12: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

PROCESS – DISCOVERY TO RESOLUTION

• Discovery – by Construction (contractor/CCEI)

• Premium Cost – Construction determines

• E&O – FDOT determines

• E&O Premium Cost (< Premium Cost) – FDOT assesses

• E&O Recovery (< E&O Premium Cost) – Negotiation

• E&O recovery from consultant• Payment• Service In Kind (infrequent)• Combination

Page 13: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

PROCESS – Design E&O

• Discovery – by Construction (contractor/CCEI)

• Premium Cost – Construction determines

• E&O – FDOT Design determines

• E&O Premium Cost (< Premium Cost) – FDOT Design

• E&O Recovery (< E&O Premium Cost) – Negotiation with EOR

• E&O recovery from consultant• Payment• Service In Kind (infrequent)• Combination

Page 14: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

PROCESS – CCEI E&O

• Discovery – by FDOT Construction

• Premium Cost – Construction determines

• E&O – FDOT Construction determines

• E&O Premium Cost (< Premium Cost) – FDOT Construction

• E&O Recovery (< E&O Premium Cost) – Negotiation with CCEI

• E&O recovery from consultant• Payment• Service In Kind (infrequent)• Combination

Page 15: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Statute of Limitations

Negligence – 4 years

• Begins from issue discovery

• Department Legal – involve as soon as possible

Page 16: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Discovery

• Clock begins ticking upon issue Discovery – when issue is discovered.

EOR E&O: Department’s reviews of EOR’s submittals is not an obligation, but a practice adopted to identify fatal flaws, contractual violations, etc.

• EOR bears ultimate responsibility for accuracy, quality, constructability, etc.

• CCEI E&O: CCEI bears responsibility for fulfilling contractual obligations while overseeing construction.

Page 17: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Premium Cost*

• Definition: Cost paid to contractor for non-value added work

• Categories (CPAM2):• Work Delays or Inefficiencies• Rework• Extra Work

2 CPAM Construction Projects Administration Manual

Page 18: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR E&O – EXAMPLE 1 (DELAY)

Situation: A field conflict was identified with the proposed storm sewer between structures S-180 and S-183 (Sta. 779+18 to 784+20 RT) and the existing overhead electric line poles.

Page 19: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR E&O – EXAMPLE 1 (DELAY)

Analysis: EOR did not identify this conflict and showed existing to remain.

Page 20: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR E&O – EXAMPLE 1 (DELAY)*

Decision: Most efficient course of action was for utility to relocate their pole line, 85 compensable days.

Total cost of SA, due to delay: $789,000

Page 21: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR E&O – EXAMPLE 2 (REWORK)

Situation: Due to plan error, incorrect offsets were provided in the plans, resulting in a 14% commercial driveway slope.

Page 22: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR E&O – EXAMPLE 2 (REWORK)*

Analysis: Additional work is necessary in order to reconstruct the driveway to comply with the maximum 10% slope required at commercial driveways.

Total cost of WO, due to rework: $4,445

Page 23: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR E&O – EXAMPLE 3 (EXTRA WORK)Situation: In Revision 7, EOP elevation at S-128 was changed. Drainage riser for S-128 had been cast and not placed. S-128 inlet had to be lowered to meet revised elevation which changed from 17.01’ to 16.6’.

RFI 46 noted that the EOP grades on each side of S-128 did not correlate, and requested a resolution to the grade differences.

Page 24: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR E&O – EXAMPLE 3 (EXTRA WORK)*Analysis: EOR’s response revised EOP grades, necessitating the change.

Total cost of WO, due to extra work: $1,493

Page 25: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

CCEI E&O – EXAMPLE 1 (DELAY)

Situation: Phasing or plan components were not constructible as shown in plans.

Page 26: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

CCEI E&O – EXAMPLE 1 (DELAY)

Analysis: Compensable time ($ 37,347)

Premium cost due to delay: $37,347

Page 27: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

CCEI E&O – EXAMPLE 1 (REWORK)

Situation: A field conflict was identified which involved avoidable rework.

Page 28: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

CCEI E&O – EXAMPLE 1 (REWORK)

Analysis: Inaccurate directions were given to contractor by CCEI during construction.

Premium cost due to rework: $23,000

Page 29: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

CCEI E&O – EXAMPLE 1 (EXTRA WORK)

Situation: Avoidable Extra Work resulting from CCEI directions to contractor.

Page 30: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

CCEI E&O – EXAMPLE 1 (EXTRA WORK)

Analysis: Inaccurate directions were given to contractor by CCEI during construction.

Premium cost due to extra work: $173,996

Page 31: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

E&O Premium Cost (Fault)*

Premium Cost / Consultant E&O

• EOR E&O – DPM’s call

• CCEI E&O – CPM’s call

Page 32: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

WHAT FDOT HAS LEARNED

• Notification / Timeliness

• Resolution Tracking Data

• Resolving Issues – Benefit/Cost Analysis

Page 33: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

Notification / Timeliness*

• Premium Cost / Consultant E&O

• Communication – essential

• EOR E&O• CCEI > CPM > DPM > EOR• Untimeliness / CCEI liability

• CCEI E&O: CPM > CCEI

Page 34: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

RESOLUTION TRACKING DATA – EOR*

• E&O records (5/01/17): 958

• Largest Issue Premium Cost: $4,500,000

• Recovered amounts: Majority < $50,000, many $0

• Issues exceeding $50,000 Premium Cost: 68

• Issues settlement time: varies from days to years

Page 35: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR – RESOLVED ISSUES*

$0

$83,509

Page 36: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR – RESOLVING UNDEBATABLE ISSUES

• Immediately commence action to recover E&O Premium Cost

• Postpone action• Potential to combine with additional pursuable E&O

issues on same project.

Page 37: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

EOR – RESOLVING DEBATABLE ISSUES

• Benefit/Cost (B/C) Analysis• Eliminate arbitrary thresholds across districts• Consistent approach, to be used by all districts

• Recovery Decision• B/C < 1: Drop action OR Delay action• B/C > 1: Commence action OR Delay action

Re: OIG Audit

Page 38: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

RECAP – WHAT WAS PRESENTED

• E&O – What it is

• Why it is important

• Why FDOT seeks recovery

• Process from Discovery to Resolution

• Examples

• What FDOT has learned

Page 39: Errors and Omissions (E&O) by Professional Engineers on ...€¦ · by Professional Engineers on Department Contracts Siddhartha Kamath, P.E. LT’S IRST O A POLL.

QUESTIONS?

Siddhartha Kamath, P.E.

FDOT, Production Support Office

Tel.: (850) 414-4343

Email: [email protected]