ERCOT MARKET EDUCATION Transmission 101
80

ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

Jun 13, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

ERCOT MARKET EDUCATION

Transmission 101

Page 2: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

2

This presentation provides a general overview of the Texas Nodal Market and is not intended to be a substitute for the ERCOT Protocols, as amended from time to time. If any conflict exists between this presentation and the ERCOT Protocols, the ERCOT Protocols shall control in all respects.

For more information, please visit:

http://www.ercot.com/mktrules/nprotocols/

Protocol Disclaimer

Legal

Page 3: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

3

Housekeeping

• Restrooms

• Refreshments

• Attendance sheet

• Exam

• Questions Please turn off cell phones & other electronics

Page 4: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

4

Course Audience

This course is designed for:• Transmission Service Provider Operators• ERCOT Transmission System Operators

Other audiences:• TSP/QSE Outage planning & coordination

personnel• Operations support & planning engineers• Engineering technicians• IT staff, Management

Page 5: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

5

Introductions

Please let us know your:

• Name

• Company for which you work

• Market Entity• QSE• TSP• ERCOT• Resource Entity• Other

• Experience in the industry

Page 6: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

6

• Overall structure of the ERCOT Nodal Market

• Network modeling rules & processes

• Outage coordination rules & processes

• Constraint management plans

• TSP activities which effect:

• Congestion Revenue Rights (CRR)

• Day-Ahead Market (DAM)

• Adjustment Period

• Real-Time Operations

Upon completion of this course, be able to describe:

Course Objectives

Page 7: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

7

Course Modules

Modules in this course include:

ERCOT Market at a GlanceModule 1

Module 2

Module 3

Module 4

Module 5

Module 6

Module 7

Network Modeling

Outage Coordination

Transmission Constraint Management

Congestion Revenue Rights

Day-Ahead through Real-Time

Additional Real-Time Topics

Page 8: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

Module 1:ERCOT Market at a Glance

Page 9: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

9

• Describe an overview of the ERCOT Nodal Market

• Describe ERCOT, TSP, and QSE/RE responsibilities

• Describe Locational Marginal Price (LMP) basics

• Describe relationships between transmission operations and LMP calculations

Upon completion of this module, you will be able to:

Module Objectives

Page 10: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

10

Compliance Relationships

Page 11: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

11

ERCOT Operations

Roles and Responsibilities

• Coordinate transmission system planning

• Process Network Model revision requests and outages

• Ensure transmission system reliability

• Facilitate markets [CRR, DAM, RTM, Retail Competition]

• Operate Ancillary Service, Day-Ahead and Real-Time Energy markets

• Provide timely information relevant to the operation of the ERCOT System and markets

Page 12: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

12

Transmission Service Providers (TSP)

Roles and Responsibilities (continued)

• Coordinate transmission system planning

• Update & validate Network Operations Models

• Keep ERCOT continually informed of transmission outages and updates

• Provide accurate and timely operational data

• Comply with ERCOT dispatch instructions

Page 13: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

13

QSE and Resource Entity (QSE/RE)

Roles and Responsibilities (continued)

• Update Network Operations Model through Resource Registration process

• Coordinate transmission operations of Resource interconnect

• Keep ERCOT continually informed of Resource and transmission outages and updates

• Provide accurate and timely operational data

• Comply with ERCOT dispatch instructions

Page 14: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

14

ERCOT Wholesale Market

Page 15: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

15

Overview: Registration

Page 16: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

16

Registration Basics

All Market Participants are required to register and sign a Standard Form Market Participant Agreement to participate in the ERCOT market.

Registration is not only a “One-time” event; but an ongoing obligation to maintain accurate data in ERCOT

systems

Page 17: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

17

Roles of Registrants

IndependentMIS Reg

Entity (IMRE)

Each Market Participant must register with ERCOT by submitting the applicable registration application.

Page 18: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

18

Roles of Registrants

Registrants demonstrate they are qualified to perform the functions they’ve registered

for per Protocol.

Page 19: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

19

Roles of Registrants

All Distribution Service Providers Designate a Transmission Operator.

T.O.

Page 20: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

20

Requirements for QSEs and CRR Account Holders

ERCOT settles financially with QSEs and CRR

Account Holders. QSEs and CRR Account

Holders must satisfy ERCOT’s

creditworthiness requirements.

Page 21: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

21

Overview: Network Modeling

Page 22: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

22

Network Model Management System (NMMS)

• Produces a Network Operations Model

• Provides model information for all other network models

• Provides a single repository for model information and management of model changes

Network Model Management System

Page 23: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

23

Network Operations Model Operational Impacts

• Real-Time Dispatch

• Reliability Unit Commitment

• Used to produce other Network Models

Network Operations Model

Page 24: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

24

Network Operations Model Operational Impacts

• Establishes the field for Market Operations

• Basis to modeling supply and demand

• Interface between market and power physics

Network Operations Model

Important to Market Transparency

Page 25: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

25

Overview: CRR Auction

Page 26: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

26

Congestion Revenue Rights

What is a Congestion Revenue Right (CRR)?

• A financial instrument that may be used as a hedge against congestion costs.

More information available at:http://www.ercot.com/services/training

Page 27: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

27

Overview: Day-Ahead Operations

Page 28: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

28

Day-Ahead Market

Day-Ahead Market (DAM)

• Daily, “co-optimized” process

• Voluntary participation

• Financially binding

Page 29: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

29

Evaluates Offers & bids to ensure best overall cost

Day-Ahead Market Co-Optimization

Energy Awards

PTP Obligation Awards

Ancillary Service Awards

Energy Bids & Offers

PTP Obligation Bids

Ancillary Service Offers

Co-Optimization

Engine

Day-Ahead Market

Page 30: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

30

Overview: Reliability Unit Commitment

Page 31: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

31

Day-Ahead Reliability Unit Commitment (DRUC)

Fundamentals

• One instance of RUC

• Ensures reliability - physically and financially binding

• Executed daily after the Day-Ahead Market

Day-Ahead Reliability Unit Commitment

Page 32: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

32

Hourly Reliability Unit Commitment (HRUC)

Fundamentals

• Another instance of RUC

• Ensures reliability - physically and financially binding

• Executed at least hourly

Hourly Reliability Unit Commitment

Page 33: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

33

Overview: Adjustment Period

Page 34: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

34

QSE Activities during the Adjustment Period

• Submit offers, trades, schedules

• Request Resource decommitments

Adjustment Period

Offers

Trades

Schedules

Page 35: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

35

Supplemental Ancillary Services Market (SASM)

• If insufficient AS capacity, ERCOT executes a SASM during the Adjustment Period

Adjustment Period

Page 36: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

36

• Update the Outage Scheduler as needed

TSP Activities in the Adjustment Period

• TSP ActivitiesAdjustment Period

Outage Scheduler impacts:• Day-Ahead Market

• Reliability Unit Commitment

• Hourly Transmission Security Analysis

Page 37: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

37

Overview: Real-Time Operations

Page 38: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

38

• Match generation with demand

• Operate transmission system within established limits

• Monitor and maintain voltage support

Purpose of Real-Time Operations

Real-Time Operations

Page 39: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

39

Real-Time Operations

Process used to determine optimal dispatch:

• Security Constrained Economic Dispatch (SCED)

Every 5 minutes, SCED calculates:• Resource-specific Base Points• Locational Marginal Prices

Page 40: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

40

Real-Time Operations

Frequency (Hz)

60. 0000

5 minutes 5 minutes

Base point

Base point

Base point

• Load Frequency Control (LFC)

• Matches generation with demand

• Responds to frequency deviations

• Deploys Regulation Reserve Service

Page 41: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

41

Overview: Settlements

Page 42: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

42

Day-Ahead Settlement• Daily statements include all Payments due and

Charges incurred• Statements posted to MIS Certified Area for

applicable Market Participant

Day-Ahead Settlements

Operating Day

Day 2Day Ahead

DAM Statement

Day 1

Page 43: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

43

Real-Time Settlements

Real-Time Settlement• Daily statements include all Payments due and

Charges incurred• Statements posted to MIS Certified Area for

applicable Market Participant

Day 180

Operating Day

Day 5

Initial Statement

Final Statement

True-Up Statement

Day 55

Page 44: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

44

Daily invoices include

• DAM Statement• RTM Statements

Real-Time Operations Settlements

Single Daily Settlement Invoice

44

InvoiceDay + 2

InvoiceDay + 3

ERCOT Issues Invoice• DAM • RTM Initial• RTM Final• RTM True-up

Payment Due (to ERCOT)

Payment Due (to Market

Participant)

InvoiceDay

17001700

Page 45: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

45

Settlement Pricing

ERCOT is an energy-only market … but what does that mean?

In ERCOT, these costs must be recovered with revenues from energy production and operating reserves.

It’s all about the recovery of costs to build generation.

Page 46: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

46

• Reserve Price Adder: the economic value of reserves that are available for energy dispatch in Real-Time

• LMPs and Reserve Price Adders are used together to form SPPs in Real-Time

Settlement Point Prices

Additional Real-Time pricing component…

43

LMPs are location-specific. Reserve Price Adders represent the value of reserves ERCOT-wide.

Page 47: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

47

Overview: Market Information System

Page 48: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

48

Three MIS Security Levels

Market Information System

• Information accessible by the general public

• Also available on ERCOT.com

• Restricted access to protected information

• Accessible by applicable Entities• Requires digital certificate

• Information accessible only by individual Market Participant

• Requires digital certificate

Page 49: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

Locational Marginal Price Basics

Page 50: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

50

Locational Marginal Pricing

What is Locational Marginal Pricing (LMP)?

Pricing: Cost Marginal: to serve the next increment of LoadLocational: at an Electrical Bus

Locational Marginal Pricing

Page 51: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

51

• Energy

• Congestion

LMP Components

Locational Marginal Pricing

In some markets, LMPs have a component for losses.

The Nodal Market does NOTinclude losses in LMPs.

Page 52: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

52

Settlement Point Prices

• LMPs and Settlement Point Prices• Every Hour

• LMPs• Every 5 minutes*

• Settlement Point Prices• Every 15 minutes

* LMPs generated at each SCED cycle (possibly more often than 5 minutes)

How often are LMPs & Settlement Point Prices calculated?

Page 53: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

53

• Calculated at “Network Nodes”

• Points of connection to grid

• Source (injection point)

• Sink (withdrawal point)

• Switching station

Calculating LMPS

Locational Marginal Pricing

Page 54: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

54

Transmission Limits

Generic Limits

• DC Power Flow model used to calculate LMPs

Calculating LMPS

Locational Marginal Pricing

Constraints

LMPs

Real Power

Studies:Voltage StabilityTransient Stability

DCModel

Page 55: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

55

Settlement Point Prices

ResourceNodes

LoadZones

Hubs

Three Types of Settlement Points:

Page 56: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

56

Resource Electrical Bus

An Electrical Bus where a Resource’s measured output is settled

What is a Resource Node?

Settlement Point Prices

Page 57: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

57

Resource Electrical Bus

Day-Ahead MarketLMP at the Resource Node

Real-Time OperationsTime-Weighted Averages of LMPs at Resource Node

Time-Weighted Average of Reserve Price Adders

Settlement Point Prices for Resource Nodes

+

Settlement Point Prices

Page 58: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

58

All Load must be assigned to a Load Zone for Settlement purposes

A group of Electrical Buses assigned to the same Load Zone

What is a Load Zone?

Settlement Point Prices

Page 59: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

59

Day-Ahead MarketLoad-Weighted Average of LMPs at Electrical Buses in Load Zone

Real-Time OperationsLoad-Weighted and Time-Weighted Averages of LMPsat Electrical Buses in Load Zone

Time-Weighted Average of Reserve Price Adders

Settlement Point Price for Load Zones

+

Settlement Point Prices

Page 60: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

60

• Competitive Load Zones

• Non Opt-in Entity Load Zones

• DC Tie Load Zones

Three types of Load Zones

Settlement Point Prices

Page 61: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

61

Settlement Point Prices

2003 Congestion Management zones

• North

• South

• West

• Houston

Competitive Load Zones

Page 62: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

62

Settlement Point Prices

Established by one or more NOIE(s)

Some large NOIEs required to establish own NOIE Load Zones

NOIEs that don’t establish NOIE Load Zone are assigned to Competitive Load Zone

Non Opt-in Entity Load Zones

Page 63: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

63

Settlement Point Prices

All Load must be assigned to a Load Zone for Settlement purposes

• Used to settle exports across DC Ties

• One for each DC Tie

• Contains only the electricalbus connected to the DC Tie

DC Tie Load Zones

Page 64: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

64

Settlement Point Prices

Hub

• Group of 345kV Hub-buses

• Defined by Protocols

What is a Hub?

Page 65: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

65

ERCOT Hub Average

ERCOT Bus Average

Six Hubs in ERCOT Market

Two Average Hubs

Four Regional Hubs

• North

• West

• South

• Houston

Settlement Point Prices

Page 66: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

66

Settlement Point Prices

Hub

Day-Ahead MarketSimple average of LMPs at Hub Buses in each Hub

Real-Time OperationsSimple average of Time-Weighted Average LMPs at the Hub Buses in the Hub

Time-Weighted Average of Reserve Price Adders

Settlement Point Price for Hubs

+

Page 67: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

67

Market Information System

Slide 67

• Day-Ahead Market SPPs

• Real-Time LMPs

• Real-Time SPPs

LMP Contour Map

Page 68: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

Transmission Operations and LMP calculations

Page 69: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

69

Telemetry input into ERCOT system operations• Power flow on transmission elements• Bus load• Voltages• Tap positions• Resource statuses• Device statuses• and more

Critical for market price formation

Telemetry of Real-Time Measurements

Settlement Point Prices

OutageOutage

Outage

OpenMWKv

OnRegMWMvar

Kv

MW MVar

Kv

Telemetry performance is critical for reliability and market operations

Page 70: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

70

Settlement Point Prices

OutageOutage

Outage

Remember: Different LMPs provide a signal that something reliability related is limiting

the network

• Outages and limits impact Locational Marginal Prices (LMPs)

• Impact on Settlement Point Prices• Price changes depend on affected

transmission elements

Impact of Outages on Prices

Page 71: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

71

In a perfect world there is… NO Congestion, NO Outages

SCENARIO

Scenario: Outages and LMPs

150 MW Load

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

Page 72: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

72

In a perfect world there is… NO Congestion, NO Outages

SCENARIO

Scenario: Outages and LMPs

150 MW Load

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

0 MW dispatched @ $30/MWh

150 MW dispatched @ $10/MWh

Page 73: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

73

In a perfect world there is… NO Congestion, NO Outages

SCENARIO

Scenario: Outages and LMPs (continued)

150 MW Load

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

0 MW dispatched @ $30/MWh

150 MW dispatched @ $10/MWh

Paid to Generators (G2)

G1 ( 0 MW * $30/MWh ) = $0 G2 ( 150 MW * $10/MWh ) = $1500

Charged to Loads (L1)

( 150 MW * $10/MWh ) = $1500

LMP = $10 / MWh

Page 74: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

74

In an IMPERFECT world Outages can cause Congestion

SCENARIO

Scenario: Outages and LMPs

150 MW Load

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

Page 75: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

75

In an IMPERFECT world Outages can cause Congestion and Cost Increases

SCENARIO

Scenario: Outages and LMPs

150 MW Load

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

50 MW dispatched @ $30/MWh

100 MW dispatched @ $10/MWh

Page 76: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

76

In an IMPERFECT world Outages can cause Congestion and Cost Increases

SCENARIO

Scenario: Outages and LMPs

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

50 MW dispatched @ $30/MWh

100 MW dispatched @ $10/MWh

Paid to Generators (G2)

G1 ( 50 MW * $30/MWh ) = $1500G2 ( 100 MW * $10/MWh ) = $1000

Charged to Loads (L1)

( 150 MW * $30/MWh) = $4500

150 MW Load

LMP = $30 / MWh

Page 77: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

77

In an IMPERFECT world Outages can cause Congestion and Cost Increases

SCENARIO

Scenario: Outages and LMPs (continued)

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

50 MW dispatched @ $30/MWh

100 MW dispatched @ $10/MWh

Paid to Generators (G2)

G1 ( 50 MW * $30/MWh ) = $1500G2 ( 100 MW * $10/MWh ) = $1000

Charged to Loads (L1)

( 150 MW * $30/MWh) = $4500

150 MW Load

LMP = $30 / MWh• Differences (between payments and

charges) goes into congestion rent• Covered in more detail later

Page 78: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

78

Sometimes Outages DO NOT impact LMPs . . .

SCENARIO

Scenario: Outages and LMPs

50 MW Load

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

0 MW dispatched @ $30/MWh

50 MW dispatched @ $10/MWh

LMP = $10 / MWh

Page 79: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

79

Sometimes Outages DO NOT impact LMPs . . .

SCENARIO

Scenario: Outages and LMPs

50 MW Load

G1 QSE offers 100 MW @ $30/MWh

G2 QSE offers 200 MW @ $10/MWh

L1100 MW Limit

0 MW dispatched @ $30/MWh

50 MW dispatched @ $10/MWh

LMP = $10 / MWh

Result:• Either line can support load• No change in LMPs

Page 80: ERCOT MARKET EDUCATION Transmission 101 · Transmission Operations and LMP calculations. 69 Telemetry input into ERCOT system operations • Power flow on transmission elements •

80

Module Summary

In this module we:

• Introduced the ERCOT Nodal Visual Process Map

• Identified key roles and responsibilities

• Discussed basics of Locational Marginal Prices (LMPs)

• Discussed outage impacts on LMPS