EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members <progress in the last 1 year> at Mar.2008
21

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

Mar 29, 2015

Download

Documents

Ariana Witting
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Status

N. Kamikubota, KEK

and J-PARC Control members

<progress in the last 1 year>

at Mar.2008

Page 2: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC

• Japan Proton Accelerator Research Complex

• A joint project between JAEA* and KEK *JAEA – Japan Atomic Energy Agency, formerly JAERI

• Construction site is in JAEA in Tokai, Ibaraki, Japan

Page 3: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Facility (on Nov.2006)

Linac(181MeV)

3GeV RCS(25Hz,1MW)

50GeV MR(0.75MW) MLF

(neutron)

HD(hadron)

NU(neutrino)

CCR (Central Control Room)

J-PARC = Japan Proton Accelerator Research Complex

Page 4: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Site

Tsukuba

KEK-Tsukuba

Tokyo

Tokai

Tokyo-Narita

Int’l Airport

JAEA-Tokai

50km

KEK-Tokai

J-PARC is a Joint project:

-> JAEA - Linac and RCS

-> KEK - MR

Shuttle Bus

(80min.)

Page 5: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Schedule and Milestones

• 2002 - Construction started in JAEA-Tokai

• Nov.2006 Linac - Beam commissioning started• Jan.2007 Linac - Beam accelerated to 181MeV• Sep.2007 RCS - Beam commissioning started• Oct.2007 RCS - Beam accelerated to 3 GeV• Dec.2007 MR - Off-beam commissioning started

• May.2008 MR – Beam Commissioning (3GeV) will start• Dec.2008 MR – Beam Commissioning (30GeV) will start

Page 6: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Accelerator

Page 7: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Progress in the Recent 1-year• Linac and RCS

– Proton beam was accelerated successfully to the design values (181 MeV/ Linac, 3 GeV/RCS, respectively).

Linac – on Jan.24.2007 RCS on Oct.31.2007

Page 8: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Progress in the Recent 1-year (Continued)

• Linac : Goal is 181MeVx{30mA,500us,25Hz}– Studies toward high power operation

• {5mA,20us,2.5Hz} in Jan.2007 #1st successful beam• -> Jun.2007: {5mA,50us,25Hz}, {5mA,250us,5Hz} # high duty• -> Jan.2008: {30mA,50us,1Hz} # high beam-current

– Various improvements using beam diagnostics systems• But more studies needed

• RCS : Beam accelerated to the design value, 3GeV– 1 bunch operation: 4.4x10^12 ppb with 25Hz (52.5kW)

• peak current 25mA, bunch width 560ns, for 4 minutes• Beam loss is at injection collimators

– Toward “stable” operation with 20kW output in 2008• Not enough RF power for higher power operation • More spare parts for MR test and future regular operation

Page 9: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Progress in the Recent 1-year (Continued)

• MR (by KEK) : will start beam commissioning in May– Installation of accelerator components are in progress

• Installation is in the final phase• MR members are working very hard

– Off-beam commissioning was started • Powering of magnet power-supplies since Dec.24.2007

– Still … on schedule, but very tight

• MR : beam commissioning plan – May-June.2008: 3GeV DC operation– Dec.-Feb.2009: Accelerate beam to 30 GeV, Beam extraction to HD facility– Apr.-June.2009: Beam extraction to NU facility

Page 10: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

MR – Off-beam Commissioning of Magnets (Bend, Q, Sx) Progress in the Recent 1-year (Continued)

MR Arc-C area

MEDM screen

Page 11: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Control System

Page 12: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Progress in the Recent 1-year• Infrastructure - CCR (Central Control Room)

– Another temporary(?) Control Room in the RCS building– Two control rooms will be (must be !) merged

Page 13: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Progress in the Recent 1-year (Continued)• Infrastructure - Computers

– CPU Servers : Blade-type servers (IBM Blade Center) • 16 CPU-blades were introduced during Nov.2006-Oct.2007• For software development, operation, simulation, ..• Old servers were replaced by them

– Disk Server : Dedicated storage disk (IBM N3600/NetApp) • User’s operational size is 1TB(program)+7TB(data)• Introduced in Feb.2008, will be in operation very soon

Blade server (8 blades in) Disk server system

Page 14: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Control – Use EPICS and ?

Accelerator OPI ApplicationBasic High-Lvl.

IOC/VMEOS,H/W

Drivers(works before 2005)

Linac Java+MEDM

XAL/JCE

VxWorks PowerPC

Adv7501

- VME I/O Modules mainly by Advanet- TeraDev for PLC

RCS Java+MEDM SAD

VxWorks PowerPC

Adv7501

- VME I/O Modules mainly by Advanet- TeraDev for PLC

MR MEDM(or EDM)

SAD Python

Linux Intel-basedGE Funac

and Sanritz

(Network devices)-NetDev for PLC, BPMC, EMB-LAN-WE7000 drivers

• Divide Project between JAEA & KEK– Linac : JAEA is in charge of Linac control– RCS : JAEA asked RCS controls to a company– MR : KEK is in charge of MR control– HLAppl. have been developed by commissioning teams

Page 15: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Control – So far• Linac and RCS

– The control system(s) has been developed and used successfully • Most of RCS devices are controllable, but partly not yet

• HLA – High Level Application– HLA for Linac and RCS

• developed by commissioning staff using XAL/JCE and SAD• Contributed to beam commissioning successfully

– HLA for MR• Under development using SAD

– More details will be given by Yamamoto-san on Mar.14(Fri)

Page 16: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Control - MR• MR

– IOC side • Use Intel-based VME-bus IOC with Linux

– GE Funac VMIVME7807 (Pentium4M, high-performance)– GE Funac VMIVME7700 (Celeron), VMEbus-access Lib.– Sanritz SVA041 (Celeron), for network devices

• EPICS 3.14.7, Scientific Linux 4.4

– Implementations are in the final phase• EPICS db creation and OPI(MEDM,EDM) development are

underway• High-level application will be developed by the commissioning

group• Cabling with device groups is also underway

Page 17: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Control – MR (Cont.)

• Linux/VME IOCs for off-beam commissioning 7807 (waveformhandling)

7700 (bus-IO)

041 (net devices)

Timing Receiver

(VME module)

Page 18: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Summary

Page 19: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Accelerator - Summary• Linac

– Started operation in Nov.2006– Succeeded to accelerate proton to 181MeV in Jan.2007– Studies toward higher beam-power operation

• RCS– Started in Sept.2007, beam accelerated to 3 GeV in Oct.– Upgrade issues to achieve stable operation

• MR – Beam commissioning will be started in May 2008 – Hardware installation is in the final phase– Off-beam commissioning started already

Page 20: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

J-PARC Control - Summary• Linac control by JAEA Team

– Beam commissioning was started in Nov.2006– Succeeded to contribute to the beam commissioning– HLA applications (XAL/JCE) were used successfully

• RCS control by a company/JAEA– Beam commissioning was started in Sept.2007– HLA applications (SAD) have been used successfully

• MR control by KEK Team– Beam commissioning will be started in May 2008 – Implementation of Intel-based VME-bus CPUs are in progress– software development (db+GUI) is also in progress (@@ hurrying up!! @@) together with device groups

Page 21: EPICS at SSRF/Shaghai in March.2008, n.kami, KEK J-PARC Status N. Kamikubota, KEK and J-PARC Control members at Mar.2008.

EPICS at SSRF/Shaghai in March.2008, n.kami, KEK

Thank you for your attention