EOVSA SITE DEVELOPMENT Kjell Nelin OVSA Site Manager, Center for Solar-Terrestrial Research New Jersey Institute of Technology
10

Eovsa Site development

Feb 23, 2016

Download

Documents

Robert Graber

Kjell Nelin OVSA Site Manager, Center for Solar-Terrestrial Research New Jersey Institute of Technology. Eovsa Site development. Eovsa Site development. Sign for Building. Surveying Inner Antennas. Design conduit runs for entire system Determine diameter and length of all runs - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Eovsa  Site development

EOVSA SITE DEVELOPMENT

Kjell NelinOVSA Site Manager, Center for Solar-Terrestrial ResearchNew Jersey Institute of Technology

Page 2: Eovsa  Site development

EOVSA SITE DEVELOPMENT

Surveying Inner Antennas

Sign for Building

Page 3: Eovsa  Site development

BEFORE CONTACTING CONTRACTORS Design conduit runs for entire system

Determine diameter and length of all runs Determine possible expansion/future needs

Design concrete pads 13 antenna sites Breakout shed Transformer platforms at shed & building Pads for solar power systems at 12 & 13?

Page 4: Eovsa  Site development

BEFORE WORK STARTS Caltech/NJIT MOU (now in progress) DWP final go-ahead (by July 1, hopefully earlier) Obtain EPA permit for SWPPP (by July 1) Identify and schedule biologist (bird nesting) Arrange archeologist schedule Identify and schedule contractors, with all

paperwork done to permit them to work Identify and purchase materials not provided by

contractors.

Page 5: Eovsa  Site development

CONTRACTORS To be contacted in May:

Grading/Road contractor Trenching/conduit contractor Concrete contractor Fencing contractor Building contractor (handled by NJIT/CIT?)

Page 6: Eovsa  Site development

SCHEDULE OF CONSTRUCTION Construction period Aug. 5 – Dec. 15

Above dates may be modified due to weather Once ground disturbances are over, we can proceed with

construction of breakout shed, installation of cables, solar power, etc.

Task Date Duration Arch/Tribe Monitor?Bird Survey 1-Aug 1 day NoGrading/Clearing 8-Aug 5 days Yes, 1 dayTrenching/Conduit 15-Aug 5 days Yes, 1 dayRoad Improvement 22-Aug 5 days NoExcavate for concrete 29-Aug 5 days Yes, 1 dayPour concrete 5-Sep 5 days NoInstall fences 14-Sep 3 days No

Page 7: Eovsa  Site development

NEW ROADS

Page 8: Eovsa  Site development

GRADING

Page 9: Eovsa  Site development

TRENCHES/CONDUIT

Page 10: Eovsa  Site development

TRENCH + ARCHAEOLOGIST