Top Banner
Environmental Monitoring Report This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 35290-033 July 2019 Period: January 2019 – June 2019 IND: North Eastern Region Capital Cities Development Investment Program (NERCCDIP) –T2 (Mizoram) Submitted by: State Investment Program Management and Implementation Unit (SIPMIU), Urban Development & Poverty Alleviation Department, Government of Mizoram
84

Environmental Monitoring Report...(P & SN/WS/AIZ/T2/ICB-3) pipe layed = km Feeder main 42 months Revised 70 months 28.02. 2017 Extended upto 31.12.2017 Then extendedupto June 2018

Feb 07, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • Environmental Monitoring Report

    This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

    In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

    Project Number: 35290-033 July 2019 Period: January 2019 – June 2019

    IND: North Eastern Region Capital Cities Development Investment Program (NERCCDIP) –T2 (Mizoram)

    Submitted by: State Investment Program Management and Implementation Unit (SIPMIU), Urban Development & Poverty Alleviation Department, Government of Mizoram

  • SIPlt-fIO: AIZ.4 WL

    GOVERNMENT OF MiZORAM OFFICE OF THE PROGRAM DJRECTOR

    STATE INVESTMENT PROGRAM MANAGEMENT ANO !MPLE ENTATION UNIT {SIPMIUl Urban Resource Centre, New Capitol Complex; Ope Dte. Of Anti Corruption Burer;u(A.CBj_. Ai:z6wl-796 001 • Mi1oram

    Phone: (O:I89)2335503 £moil. es/[email protected]/[email protected] Fax; (0389} .1334527

    No. W-110201-/2019-PD/SIPMiUfNERCCDIP) '11 Dated. izawl. to•h July, 2019

    To The Countrv Director Indian Res1dent Misston l11 'RM) Asian Development Bank, 4 San Martin Ma1·g, Chanakyapun New Delhi 110021

    Subject: Re- submission of Semi Annual Environment Monitoring Report Tranche -2 and Tranche - 3, (January - June, 2019), Aizawl.

    Reference: Project Number: 36290 :Loan 2834 - IND & Loan 3337 - IND

    Sir,

    India: North Eastern Region Urban Development Program 2 & 3 (Aizaw!, Mizoram)

    Referring to the Subject and Ref. cited above, I have the honour to state that

    'Semi Annual Environment Monitoring Report Tranche - 2 and Tranche - 3, Oanuary -

    June, 2019), Aizawl' is hereby re-submitted for favour of kind information and necessary

    action please.

    ASIAN DEVELOPMENT BANK ~ !NRM

    ,1,'?f-: 11 JUL 1019 ~fr 9~

    RECEIVED

    Yours Sincerely,

    (LAL HANGA) Progratn Director,

    SIPMIU (NERCCDIP)

    Memo.No. W-11020/7 /2019-PD/SIPMIU(NERCCDIP)/11 Dated Aizawl, 10th July, 2019 Copy to:

    1. The Director (UD) Ministry of Urban Development (NERUDP CellJ Room No. 213 (C), Nirman Bhavan, Government of India. New Delhi - 110011

    2. Office copy.

    Program Director, SIPMIU {NERCCDIP)

    . ·'

  • Semi Annual Environmental Monitoring Report

    Project Number: 36290

    Loan 2834-IND

    Period: January to June2019 Tranche 2 India: North-Eastern Region Urban Development Program 2 (Aizâwl, Mizoram)

    July 2019

    Implementing Agency: State Investment Program Management and Implementation Unit (SIPMIU)

    Executing Agency:

    Urban Development & Poverty Alleviation Department, Government of Mizoram

  • 1

    CONTENTS

    Sr.

    No.

    Subject Page

    No.

    I Introduction 3

    II Implementation Progress 5

    III Environmental Procedure Review 12

    IV Compliance status with Environmental Management and Monitoring Plan 14

    V Environmental Monitoring and Evaluation 25

    VI Consultation and Disclosure Conducted 32

    VII Grievance Redressal Mechanism 32

    VIII Findings, Recommendation and Action Plan 34

    List of Tables

    1 Sub-project Status of Tranche – 2 (Upto30th June 2019)- Aizâwl city 6

    2 Compliance of Environmental Loan Covenants 9

    3 Environmental Legal Requirements Applicable for NERCCDIP Tranche 2,

    Aizâwl, Mizoram

    13

    4 Status of Compliance with National and State Legal Requirements

    (upto30th June)- Tranche 2

    13

    5 Compliance of EMP and Environment, Health Safety Norms: Package:

    Feeder Mains (WS) Water distribution-107.55 Km (P &

    SN/WS/AIZ/T2/ICB-3) of Tranche – 2

    16

    6 Compliance of EMP and Environment, Health Safety Norms: Package:

    Providing, laying, jointing & Commissioning of Sewerage Network (SEW)-

    45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P &

    SN/SEW/AIZ/T2/ NCB-5) under Tranche – 2

    20

    7 Ambient air quality monitoring result 25

    8 Ambient Noise Level Monitoring Data at Project Location Sites and

    Surroundings

    27

    9 Performance Fact Sheet for Required Environmental

    Consents/Clearances of NERCCDIP, Aizâwl (June 2019) Tranche 2

    30

    10 Performance Fact Sheet for EMP Implementation of Tranche 2 (June

    2019)

    31

    11 Indicative Schedule for Consultations and Disclosure 32

    12 Recommendations, Suggestion and Action taken 34

    List of Figures

    1 Administrative Map, Aizâwl Urban planning area (2014) 4

    2 Aizâwl city area 5

    3 Institutional Responsibility- NERCCDIP 12

    4 Grievance Redress Mechanism 33

    Appendix

    1 Photo Illustration 36

    2 Monitoring Team Details 38

  • 2

    3 Consent to Operate Hot Mix Plant 39

    4 Tree Felling NOC for 132 KV Transmission Line 41

    5 Consent for Establishment- Sewage Treatment Plant and Tree felling

    permission for landfill site and STP site from Forest Dept.

    42

    6 Safety Rules for Work site 44

    7 Training Program and Meeting – Environment Safeguard 59

    8 Sample Training Documents of Contractors 66

    9 Workman Compensation Policy 68

    10 Tie up letter and Medical examination report for workers 70

    11 Traffic Management Plan 74

    12 Monitoring Result- Air quality, Noise Level and Water quality 76

    13 Sample Public Consultation by Contractor 79

    14 Grievance Register 81

  • 3

    I. INTRODUCTION

    A. Background

    1. The Government of India has implemented projects to improve urban conditions in North Eastern region capital cities under North Eastern Region Capital Cities Development Investment Programme (NERCCDIP). The investment Programme will aim at improving infrastructure and urban service, and also strengthening the urban institutions for better service delivery and operation maintenance of the assets. The capital cities under the Programme are Agartala (In Tripura), Aizâwl (In Mizoram), Gangtok (In Sikkim), Kohima (In Nagaland), and Shillong (In Meghalaya). This report for Tranche 2 deals with the proposed investment Programme (NERCCDIP: ADB Loan 2834 IND) for Aizâwl, the capital city of Mizoram.

    2. The works under the investment Programme includes development of urban infrastructure facilities in the sector for Water Supply, Sewerage & Sanitation and Solid Waste Management system. The budgetary allocation for Tranche 2 NERCCDIP program is 72 million US Dollar.Location of Aizâwl in Mizoram is shown in Figure 1.Figure 2 shows Aizâwl city map.

    B. Purpose of the Report

    3. NERCCDIP has been classified by ADB as environmental assessment category B (some negative impacts but less significant than category A) and the impacts of subprojects were assessed through Initial Environmental Examination (IEE) reports prepared according to ADB Environment Policy (2002,2009) and Environmental Assessment Guidelines (2003).

    4. This report is the Semi-Annual Environmental Monitoring Report (SAEMR) – Tranche 2 for the period January to June 2019 to describe the “Environmental Compliance” including status of implementation of the mitigation measures and monitoring recommended in the Initial Environmental Examination (IEE).

  • 4

    Figure 1: Administrative Map Aizâwl Urban planning area (2014)

  • 5

    Figure 2: Aizâwl city area

    II. IMPLEMENTATION PROGRESS

    A. Status of the Sub projects

    5. Work of sub project for Tranche 1 has been successfully completed and handed over to the concern authority and are in function. The concern contractors have also been released, since liability period for each work components has ended. Now work for Tranche 2 is under progress.

    6. InTranche 2 there are 11 packages covering water supply, sewerage & sanitation and solid waste management. Out of the 11 packages work completed for 7 packages. Work to be completed shortly for 1 package. One water supply package work (package - PS/WS/AIZ/T2/ICB-3) stopped due to termination of contract. Rest 2 packages (1 water supplies -P & SN/WS/AIZ/T2/ICB-3 and 1sewerage sanitation - P & SN/SEW/AIZ/T2/ NCB-5) are under implementation. But as such no work (only 3 to 4 % progress)during last 6 months for those packages.

    7. Table 1shows the status of the awarded packages, starting date, and schedule date of completion, physical progress and work components progress status for Tranche 2.

    8. Photo illustration of project locations is shown in Appendix 1.

  • 6

    Table 1: Sub-project Status of Tranche – 2 (Upto30th June 2019)-Aizâwl city Sr. No.

    Sub-projects (Package No.)

    Work Components

    Starting date of Implementation

    Projected months of completion (as per Work order)

    Schedule date of completion

    Physical progress (%) as on 30.06. 2019

    Works Completed / progress as of 30th June 2019

    Corrective action

    1 Water Supply: Booster Pumps (WS)-2 (EM&S/WS/AIZ/T2/NCB-1)

    Construction of booster pumping stations at 2 locations

    16.05.2012 17 months 31.10.2013 100% completed

    Project completed

    2 Water Supply: Water reservoir (WS)-3 (GLR/WS/AIZ/T2/NCB-3)

    Construction of water reservoirs at 3 locations

    25.06.2012 19 months 25.01.2014 100% completed

    Project completed

    3 Water Supply: Bulk -85

    and domestic water meters (WS)- 20,000 (WM2/WS/AIZ/T2/ICB-2)

    Supply of 85 nos. Bulk flow meter and domestic water meters (WS)- 20,000

    21.09.2012 39 months 30.04.2016

    100% completed

    Total of 20000 nos. of domestic meter and 55 Flow meters installed

    4 Water Supply: Feeder

    Mains (WS) Water distribution-107.55 Km (P & SN/WS/AIZ/T2/ICB-3)

    Laying of 107.55 km Feeder main

    29.08.2013 42 months Revised 70 months

    28.02. 2017 Extended upto

    31.12.2017 Then

    extendedupto June 2018

    Further extended upto30.06.19

    87.05% Total Pipe laid distribution 86.66 Km & feeder mains 13.59 Km. (Total pipe layed = 100.25 Km) Out of 13275 House connection, 8432 tapped out upto road shoulder and 617 connected. Feeder main completed.

    Very slow Progress. Only 4% work done in last 6 months. Planning and increase of manpower will be required for timely completion of project

    5 Water Supply Dedicated

    Power Supply (WS) (PS/WS/AIZ/T2/ICB-3)

    Construction of 132 kVA substation at Dihmunzâwl, transmission line through erection of 19 nos. towers

    27.11.2013 36 months Revised 60 months

    30.11.2016 Extended upto

    30.11.2017 Further extension upto 31.05.2018 Third Extension upto 31.12.2018

    Further extension under process

    88.14% Substation: Switchyard stringing completed. Erection of all equipments completed. Main gate with boundary wall at front is

    No work for last 6 months. Contractor Terminated. Appointment of new contractor just done

  • 7

    Sr. No.

    Sub-projects (Package No.)

    Work Components

    Starting date of Implementation

    Projected months of completion (as per Work order)

    Schedule date of completion

    Physical progress (%) as on 30.06. 2019

    Works Completed / progress as of 30th June 2019

    Corrective action

    completed. Electrification at CRB completed. Transmission Tower: 13 nos. erection completed & 2 nos. foundation work completed and 1 no earthwork and stringing of tower outstanding.

    6 Sewerage & Sanitation:

    Cesspool Cleaner (SEW)-5 nos.(SCM/SEW/AIZ/T2/ NCB-2)- Environment non sensitive package

    Procurement of Cesspool cleaner

    18.05.2012 17 months 18.10.2013 100% completed

    Project completed

    7 Sewerage & Sanitation:

    Community toilet blocks (SEW)- 10 nos. (CT/SEW/AIZ/T2/NCB-4)

    Construction of community toilets

    29.08.2013 26 months 31.10.2015 100% completed

    Project completed

    8 Sewerage & Sanitation:Providing

    ,laying, jointing & Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5)

    Sewage pipe laying -45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7)

    27.11.2013 42 months Revised 65 months

    31.05.2017 Extended upto

    31.12.2017 Then extended upto 31.12.2018 Further extended upto30.06.2019

    69.64% Main sewer pipe laid 24.35 Km. uPVC piped laid 12.04km. Manholes 1050Nos.

    Very slow progress.Only 3% work done in last 6 months. Planning and increase of manpower will be required for timely completion of project

    9 Sewerage & Sanitation:

    Site/Land Development & Approach Road to STP (AR & LD/SEW/AIZ/T2/NCB-60)

    Approach road – 285 m Asphalt road at Bethlehem Vêngthlang (about 2 km from the city)

    26.02.2013 46 months 31.12.2016 Extended upto

    30.04.2017

    100% completed

    Project completed -

  • 8

    Sr. No.

    Sub-projects (Package No.)

    Work Components

    Starting date of Implementation

    Projected months of completion (as per Work order)

    Schedule date of completion

    Physical progress (%) as on 30.06. 2019

    Works Completed / progress as of 30th June 2019

    Corrective action

    10 Sewerage & Sanitation:

    10 MLD Construction of Sewerage Treatment Plant (STP) (STP/SEW/AIZ/T2/NCB-7)

    Construction of 10 MLD STP at Bethlehem Vêngthlang – technology : Sequencing Batch Reactors (SBR)

    27.11.2013 40 months Revised 64 months

    31.03.2017 Extended upto

    31.12.2017 Further extended

    upto 31.10.18 Third extension upto 31.03.19

    Fourth extension upto 30.06.2019

    98.9% All civil, mechanical and electrical installation completed. Transformer installed. Pre commissioning completed

    Work almost completed. No major work in last 6 months

    11 Solid waste management:

    Procurement of Dustbins

    Procurement and supply of 132200 nos. dustbin

    16.06. 2016 5 months 16.11.2015 (Actual

    Completion April 2017)

    100% Completed

    Project completed

  • 9

    9. Till date scope of the sub projects are not changed.

    B. Compliance of Safeguard Loan Covenants

    10. The loan agreement for NERCCDIP Project 2 was signed on 19th November 2012 and available in ADB website (http://www.adb.org/sites/default/files/project-document/74927/35290-033-ind-mlo1.pdf)). Table 3provides a summary of compliance to the loan covenants related to environmental safeguards.

    Table 2: Compliance of Environmental Loan Covenants

    Serial no. as per loan agreement

    Program Specific Covenants Status / Issues

    Environment

    4 The Borrower shall ensure or cause the EA to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project, and all projects’ facilities comply with (i) all applicable laws and regulations of the Borrower and the State relating to environment, health, and safety; (ii) the Environmental Safeguards; (iii) the EARF; and (iv) all measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.

    Under compliance Document is prepared/ or under preparation by complying all relevant State and National Laws, Safeguard Policy Statement (SPS 2009) of ADB, Environment Assessment Review Framework (EARF) for Tranche-2 program. For Tranche 2 project Initial Environmental Examination (IEE), Environment Management Plan (EMP) report prepared and approved by ADB. IEE for the Tranche 2 has been updated and that report has already been disclosed in ADB website Updated IEE for Tr 2 sewerage has been done and submitted to ADB for acceptance and disclosure. Report disclosed in ADB website on July 2017 IEE will be revised further in case of any change of scope and location. All measures and requirements as prescribed in IEE/EIA and EMP are being considered during implementation. Corrective or preventive action plans will be reflected in Environment Monitoring Report and project implementation authority will take care of such actions when required.

    Human and Financial Resources to Implement Safeguards Requirements

    7 The Borrower shall make available, or cause the EA to make available, all necessary budgetary and human resources to fully implement the Environment Management Plan (EMP) required.

    Complied Budgetary provisions have been included in EMP of Tranche 2 projects Human resource (project consultant, i.e Environmental Specialist of DSMC) for implementation of EMPs is in place for regular monitoring to secure complete compliance.

    Safeguards – Related Provisions in Bidding Documents and Works Contracts

    http://www.adb.org/sites/default/files/project-document/74927/35290-033-ind-mlo1.pdfhttp://www.adb.org/sites/default/files/project-document/74927/35290-033-ind-mlo1.pdf

  • 10

    Serial no. as per loan agreement

    Program Specific Covenants Status / Issues

    8 The Borrower shall ensure, or cause the EA to ensure, that all bidding documents and contracts for Works contain provisions that require contractors to: (a) comply with the measures and requirements relevant to the contractor set forth in the IEE, the EMP, the RP and the IPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report; (b) make available a budget for all such environmental measures; (c) provide the EA with a written notice of any unanticipated environmental risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, the RP or the IPP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and (e) fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

    Under compliance (a) Approved IEE, EMP for Tranche 2 project is attached in Bidding documents. This process will be followed for all the sub projects within the present Tranche. In case of any change of scope, revised IEEs with EMP(s) will be prepared and corrective measures will be disclosed to the contractor and same will be reflected in the “Environment Monitoring Report”. Updated IEE for Tr-2 sewerage has been done and submitted to ADB for acceptance & disclosure. Report disclosed in ADB website on July 2017 (b) IEE indicates budgetary provisions for implementation of EMP. (c) During implementation of any sub project if additional impacts/risks arise due to change in scope/area that will be reflected in the revised IEEs, EMPs and Environment Monitoring Report and accordingly project Executing Agency will inform the Construction Agency for taking relevant corrective measures. (d) Haul roads will be marked properly (by avoiding residential and agricultural land) before commencement of transportation of materials. (e) Pathways, infrastructure and land which are likely to be affected for varying periods during implementation of the sub project will be restored by concerned construction agency before acceptance of the work. Restoration status will be reflected in post construction monitoring report.

    Safeguards Monitoring and Reporting

    9 The Borrower shall cause the EA to do the following: (a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

    (b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the

    Under compliance (a) Submitted on regular basis. This is Semi-annual safeguard monitoring report on Environment for the period January to June2019. (b) During implementation of any sub project, if additional impacts/risks arise due to change in scope/area, those will be reflected in revised IEEs with EMPs and

  • 11

    Serial no. as per loan agreement

    Program Specific Covenants Status / Issues

    IEEs, the EMPs, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) report any breach of compliance with the measures and requirements set forth in the EMPs, promptly after becoming aware of the breach.

    accordingly Executing Agency (EA) will inform the ADB such change along with corrective action plan which will be reflected in the subsequent Monitoring Reports. (c) in case of any breach of compliance with the measures and requirements set forth in the EMP, EA will promptly inform ADB and suitable corrective action program will be planned/initiated.

    Prohibited List of Investments

    10 The Borrower shall ensure or cause the State to ensure that no proceeds of the Loan are used to finance any activity included in the list of prohibited investment activities provided in Appendix 5 of the SPS.

    Complied Under Tranche 2there is no violation of prohibited investment activities as per ADB SPS (2009) Appendix 5.

    Other Social Measures

    11 The EA shall ensure that civil works contracts under the Project follow all applicable labor laws of the Borrower and the State, and that these further include provisions to the effect that contractors: (i) carry out HIV/AIDS awareness programs for labor and disseminate information at worksites on risks of sexually transmitted diseases and HIV/AIDS as part of health and safety measures for those employed during construction; and (ii) follow and implement all statutory provisions on labor (including not employing or using children as labor, equal pay for equal work), health, safety, welfare, sanitation, and working conditions. Such contracts will also include clauses for termination in case of any breach of the stated provisions by the contractors.

    Complied in Bid documents and under compliance during implementation Provision are included (as per EMP & BID document) to carry out HIV/AIDS awareness programs for construction contractor, application of all relevant labour laws for health and safety including child labour law and engagement of local labours (preferably from economically backward group) covering women labours. In case of any breach of provision, necessary corrective measures as per contract clauses shall be taken. Already awareness program has been organized from DSMC. All activities including awareness program will be reflected in “Monitoring Report”.

    C. Implementation Arrangement

    Details on the SIPMIU and DSMC environmental cell setup and personnel

    11. Environmental issues of the project coordinated by an Environmental Specialist within the DSMC, who ensures that all subprojects, comply with environmental safeguards. There is one Environmental Officer (Assistant Engineer Environment) in SIPMIU. The Safeguard Officer is responsible for implementing the environmental safeguard provisions in the project including (i) ensuring environmental criteria for subproject selection in the EARF are followed, (ii) ensuring mitigation requirements are in contractor bidding documents, and (iii) liasing with various Central and State government agencies on compliance matters. The SIPMIU appointed and manage Construction Contractors (CC) to build elements of the infrastructure that are required to submit Environmental Implementation Plans (EIPs) for SIPMIU approval. The SIPMIU is assisted by the DSMC, who is responsible for design the infrastructure, manage tendering of contracts, and supervise the construction process.

    12. An Environmental Specialist (ES) in the DSMC is responsible for addressing the environmental issues in the project components during design and implementation. The ES ensure all mitigation requirements are in contractor bidding documents and EMPs, and supervise the effective implementation of environmental provisions during construction. In addition, the ES assist the SIPMIU on the procurement needs and other project

  • 12

    implementation aspects and play a central role in ensuring capacity building on environmental management of the SIPMIU, Contractor and Line Departments through capacity development support and training. Figure 3 shows institutional responsibility for implementation of environmental safeguard monitoring at different level.Appendix 2 shows safeguard team (Tranche 2) for Aizâwl.

    13. EMP shows that most of the mitigation measures are fairly standard methods of minimizing disturbance from building in urban areas (maintaining access, planning work to avoid sensitive times, finding uses for waste material, etc), and experienced Contractors should be familiar with most of the requirements. Monitoring of such measures normally involves making observations in the course of site visits, although some require more formal checking of records and other aspects. There are also be some surveys of residents, as most of the measures are aimed at preventing impacts on people and the human environment.

    Figure 3: Institutional Responsibility- NERCCDIP

    III. ENVIRONMENTAL PROCEDURE REVIEW

    A. Environmental Legal Requirement

    14. Table 3 provides a list of national and state laws, rules, policies and regulations applicable to NERCCDIP Tranche 2for Aizawl, Mizoram.

  • 13

    Table 3: Environmental Legal Requirements Applicable for NERCCDIP Tranche 2, Aizâwl, Mizoram

    Component Applicable Legislation Compliance Action Required

    All components that require acquisition of forest land

    Forest (Conservation) Act 1980

    Approval from State Forest Office, Principal Chief Conservator of Forest and Ministry of Environment and Forests& Climate Change (MoEFCC), Government of India

    In case of tree felling permission as per requirement In case of use of Forest Land , Forest clearance will be required

    B. Compliance with Environmental Legal Requirements

    15. Before implementation of the project compliance with environmental policy, law and legislation is necessary.

    16. Table 4below shows present clearance status for sub-project under Tranche 2.

    Table 4: Status of Compliance with National and State Legal Requirements (upto30th June 2019)- Tranche 2

    Package Main package work

    National and State Legal Requirement

    Status

    Tranche 2

    P & SN/ WS/AIZ/T2/ICB-3

    Feeder Mains (WS) Water distribution-107.55 Km

    Water (Prevention and Control of Pollution) Act. 1974

    The Air (Prevention and Control of Pollution) Act, 1981, as amended by Amendment Act, 1987

    As per Act CTE and CTO from MPCB: (i) diesel generators; and (ii) hot mix plants, wet mix plants, stone crushers, etc. if installed for construction.

    Noise Pollution (Regulation and Control) Rules, 2002 amended up to 2010

    During implementation of project compliance against Air Act , Noise Rules and Water Act continued Consent to Operate for hot mix plant has been obtained from MPCB and which valid upto 6th July 2027 (Attached as Appendix 3)

    PS/WS/AIZ/T2/ICB-3 Dedicated Power Supply (WS)

    Water (Prevention and Control of Pollution) Act. 1974

    The Air (Prevention and Control of Pollution) Act, 1981, as amended by Amendment Act, 1987

    Noise Pollution (Regulation and Control) Rules, 2002 amended up to 2010

    Forest (Conservation) Act 1980, Mizoram Forest Act 1955

    During implementation of project compliance against Air Act, Noise Rules and Water Act continued Permission needs to be obtained for felling of the trees at project sites. Process completed for marking of trees in presence of personnel from forest dept. NOC from forest dept. received, attached as Appendix 4.

    P & SN/ SEW/ AIZ/T2/ NCB-5

    Providing ,laying, jointing & Commissioning of Sewerage Network

    Water (Prevention and Control of Pollution) Act. 1974

    During implementation of project compliance against Air Act , Noise Rules and Water Act continued

  • 14

    Package Main package work

    National and State Legal Requirement

    Status

    (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7)

    The Air (Prevention and Control of Pollution) Act, 1981, as amended by Amendment Act, 1987

    As per Act CTE and CTO from MPCB: (i) diesel generators; and (ii) hot mix plants, wet mix plants, stone crushers, etc. if installed for construction.

    Noise Pollution (Regulation and Control) Rules, 2002 amended up to 2010

    Tree felling NOC from forest dept. as per Forest (Conservation) Act 1980, Mizoram Forest Act 1955

    Consent to Operate for hot mix plant has been obtained from MPCB and which valid upto 6th July 2027 (Attached as Appendix 3) In case of tree felling NOC needs to be obtained from concerned authority

    STP/SEW/AIZ/T2/NCB–7

    10 MLD Construction of Sewerage Treatment Plant (STP)

    Water (Prevention and Control of Pollution) Act. 1974

    Consent to Establish (CTE) for rehabilitation of WTP from Mizoram Pollution Control Board

    Consent to operate will be required before operation

    Forest (Conservation) Act 1980; Mizoram Forest Act 1955 The Air (Prevention and Control of Pollution) Act, 1981, as amended by Amendment Act, 1987

    Noise Pollution (Regulation and Control) Rules, 2002 amended up to 2010.

    Also for setting up (if any) hot mix plant, batching plant and use of diesel generator Consent to Establish (CTE) and Consent to Operate (CTO)

    During implementation of project compliance against Air Act , Noise Rules and Water Act continued Consent to Establish obtained from Pollution Control Board on 23.08.2012, renewal has been done and which presently valid upto23.08.2019(Appendix 5). Tree felling permission obtained from Principal Chief Conservator of Forests. 1st June 2011 (Appendix 5) Tree felled at STP site is 20 nos. and will be replanted in the ratio of 1:2 (i.e for every one tree felled two nos. of tree will be planted) Tree plantation done

    IV. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN

    17. In Tranche 2 there are 11 packages covering water supply, sewerage & sanitation and solid waste management. Out of the 11 packages work completed for 7 packages. Work to be completed shortly for 1 package. One water supply package work stopped due to termination of contract. Rest 2 packages (1 water supplies and 1sewerage - sanitation) are

  • 15

    under implementation. But as such no work (only 3 to 4 % progress)during last 6 months for those packages.

    18. Compliance on EMP and Environment, Health Safety Norms for two ongoing sub projects under Tranche 2 packages are shown in Tables5 and 6. Due to termination of one water supply package (package no. PS/WS/AIZ/T2/ICB-3)and no work for sewerage package, (package no. STP/SEW/AIZ/T2/NCB-7) EMP monitoring not done for those packages.

    19. For implementation of EMP, arrangement of human safety, provision of PPE for workers engaged in construction is being implemented. Training is being provided to the contractor by DSMC’s Environment Specialist. Moreover instruction is given to contractors to follow the specified clause of BID document to mitigate environmental and social impacts.

    20. The contractors whose work requires environmental implementation has been instructed to submit their environmental management plan for approval. Environment Management Plan as submitted by the contractor are scrutinized and checked, wherever necessary environment criteria required is added.

    21. Construction contractors provide all necessary safety arrangement for individual safety and construction site, for individual they provide all type of PPEs like Safety Vest, Safety Helmet, Hand Gloves, Safety Shoes and respiratory mask, on site it is observed that partial use PPEs, needs more awareness about need of full use of PPE in between the laborers especially with risk nature of the worksite job and type of PEE used for such type of job. For construction site safety they provide safety caution tape, cautionary signages, safe passage for traffic and road users and awareness meeting with locality habitants about importance risk nature of construction job.Appendix 6shows standard instruction and guidelines for compliance of health and safety issues.

    22. Environment Officer of SIPMIU and Environment Specialist from DSMC carried out periodic monitoring of EMP implementation through desk review of contractor’s records and site inspections. Package wise findings are presented in compliance tables, Tables 5and 6. It may be noted, though most of the sites are environmentally well managed, in a few cases in packages there are scope for further improvement in site management measures as mentioned below,

    o Improvement of access at few locations for the package P & SN/SEW/AIZ/T2/ NCB-5- Tranche 2

    o Improvement of material storage for both P & SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 packages– Tranche 2

    o Arrangement of First aid box with sufficient first aid materials at all working locations for the package P & SN/SEW/AIZ/T2/ NCB-5 and SN/WS/AIZ/T2/ICB-3 packages– Tranche 2

    o Complete use of caution board and tape for both P & SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 – Tranche 2

    o Complete Use of PPE by contractors’ site workers and complete use of caution tape at working sites for all the packages under Tranche 2

    o Public consultation on regular basis for both P & SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 packages– Tranche 2

    23. The concerned contractors were instructed verbally and also in writing. During subsequent field visits and from monthly monitoring reports it was observed that such deficiencies are mostly removed and site management has considerably improved.

  • 16

    Table 5: Compliance of EMP and Environment, Health Safety Norms

    Package: Feeder Mains (WS) Water distribution-107.55 Km (P & SN/WS/AIZ/T2/ICB-3) of Tranche – 2 Sl. No Mitigation Activities and

    Method Location Responsible for

    Mitigation Monitoring method Responsible for

    Monitoring Compliance status

    1

    Site preparation work completed by SIPMIU including necessary clearance

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied as per requirement

    2 Shifting of Telephone lines, electric polesand wires, water lines withinproposed project area

    Working sites

    Contractor

    Site observations/ records

    SIPMIU/ DSMC

    Complied as per requirement

    3 Consultation with archeological dept. to obtain an expertassessment of the archaeologicalpotential of the site; in case of ground disturbance can uncoverand damage archaeological andhistorical remains

    Working sites

    Contractor

    Site observations/ records

    SIPMIU/ DSMC

    Being complied, as and when required

    4

    Establishment of temporary camps and storage yard with available water,sanitation facility and solid waste management arrangement

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Compliedmostly Regular checks and instructions are being carried out during site visit and found some improvement so far for all the construction camps / cum storage yard. Needs to be maintained

    5 Procurement of material from Govt. approved quarry. Improper extraction of materials can disrupt natural land contours andvegetation resulting in acceleratederosion, disturbance in naturaldrainage patterns, ponding andwater logging, and water pollution

    Contractor

    Record SIPMIU/ DSMC

    Complied

  • 17

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    6

    Removal of overburden and excavated/ dismantling material from working site and use / preservation of the same – as per mitigation measures

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied mostly. Most of the overburden had been used for back filling. The dismantled materials are transported to recycling vendors. Necessary instruction has been given to contractors for removal of the excess earthat earliest Also materials need to be stored properly

    7

    Water sprinkling at construction site for arresting dust

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    No major issues of dust nuisance encountered so far. Instruction has been given to contractor to comply as per site condition

    8

    Materials carrying vehicle are covered

    All Sites

    Contractor

    Site observations SIPMIU/ DSMC

    Not fully complied Instruction has been given to contractor to comply the same

    9

    All vehicles and equipments mobilized to construction site and producing emission, have Pollution Control Board Certification

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Since the work is within the city area public carrier are used. (all public carrier are PUC certified, hence complied) For equipments – contractor submitted the same

    10

    At sensitive locations enclosures provided around generator set and concrete mixture or other noise producing machinery

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied. New Equipments are used hence noise produced from the machines are controlled so far.

    11

    Regular maintenance of noise producing equipment done

    All Sites

    Contractor Site observations SIPMIU/ DSMC

    Complied.

    12 Require horns not be used unlessit is necessary to warn other roadusers or animals of the vehicle’sapproach

    All Sites

    Contractor Site observations SIPMIU/ DSMC

    Honking of vehicle and equipments is restricted at Aizawl. Horns are not used within the city

    13 Minimize noise from construction equipment by using vehicle silencers,fitting jackhammers with noise reducingmufflers, and portable streetbarriers the sound impact tosurrounding sensitive

    All Sites

    Contractor Site observations SIPMIU/ DSMC

    Instruction has been given to contractor for minimization of noise by applying mitigation measures

  • 18

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    receptor

    14 Arrangement of drainage of waste water and arresting solid waste from waste water generated at construction site

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    No waste water generated from pipe laying work

    15 Felling of trees done (if necessary) with mitigation measures i.e. planting of two trees for each tree fell.

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    No tree felling is required for water pipe laying work

    16 Chances of water bodies pollution from construction

    All Sites Contractor Site observations SIPMIU/ DSMC

    NA. No water bodies nearby

    17 Disposal of construction debris if any as per mitigation measures done

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Most of the debris generated is used for backfilling, hence, very little quantity to dispose which is transported to disposal sites.

    18 Local flooding from watering of excavation, flushing pipes etc.

    All Sites Contractor

    Site observations

    SIPMIU/ DSMC

    NA. No flooding noticed till date. For water supply package no deep excavation is required and generation of waste water from excavation does not arise

    19 Ensure use of Personal Protective Equipment like helmet, gumboot, gloves, safety tape, nose mask and earplugs at work place

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Contractor’s so far had provided PPEs to workers such as helmets, safety vest, shoes, gloves etc. as per nature of work. During site visit partial use of PPEs noted. However, Instruction has been given to contractors for complete use of PPEs

    20 Provide Health and Safety training to all personnel and implement H & S plan

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    H & S training program has been arranged by DSMC and SIPMIU for contractors, supervisor engineers.Appendix 7 shows detail of the training program AIDS Awareness to all the Contractors workers taken up by Social group of consultant Health and Safety officer and Engineer from contractor arranged tool box training

  • 19

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    for labourer and workers. Appendix 8 shows sample tool box training detail

    21 Compensation for workers in case of any injury Maintaining Occupational Health & Safety Procedure

    All sites Contractor Document available SIPMIU DSMC

    Workman compensation health insurance policy available for the package. Appendix 9shows policy Tie up letter with nearby health center in case of emergency received (Appendix 10) Medical examination for workers has been done, which also enclosed in Appendix 10. No accident reported during report period

    22 Plan truck routes to avoid city, narrow or congested roads, important or fragile buildings, religious and tourist sites

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    So far all work is carried out without affecting traffic movement.

    23 Plan transport of waste to avoid peak traffic and tourist season

    All Sites Contractor Site observations SIPMIU/ DSMC

    As per the state traffic law, contractor’s vehicle is controlled

    24 Suitable short term traffic diversion and implementation of traffic management plan at construction site

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Present works haven’t encountered such issues. However, proper plan have been implemented during laying of pipeline Particularly road closure / diversion board placed Traffic management plan prepared. Appendix 11 shows sample traffic management plan

    25 Consideration of public safety - as per prescribed mitigation measures- use of barricade, caution tape etc.

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Compliedpartially Safety caution tapes provided partially Improvement required

    26 Keep the site free from allunnecessary obstructions

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    All working sites planned without affecting movement of public. Material storage needs to be improved, sometime obstructing movement of vehicle and public

  • 20

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    27 Leave spaces for access betweenmounds of soil;and Provide walkways and metalsheets where required for people

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Access provided at working sites

    28 Employ at least 50% of workforce from communities near sites

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    This is being practice as per availability of workers willing to work from the concern location.

    29 Continuous monitoring on implementation of mitigation measures.

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied. Carried out under regular site inspection.

    Table 6: Compliance of EMP and Environment, Health Safety Norms

    Package: Providing,laying, jointing &commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5) under Tranche – 2

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    1

    Site preparation work completed by SIPMIU including necessary clearance

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied as per requirement

    2 Shifting of Telephone lines, electric polesand wires, water lines withinproposed project area

    Working sites

    Contractor

    Site observations/ records

    SIPMIU/ DSMC

    Complied as per requirement

    3 Consultation with archeological dept. to obtain an expertassessment of the archaeologicalpotential of the site; in case of ground disturbance can uncovered and damage archaeological andhistorical remains

    Working sites

    Contractor

    Site observations/ records

    SIPMIU/ DSMC

    Being complied, as and when required

    4

    Establishment of temporary camps with available water, sanitation facility and solid waste management arrangement

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied. Toilet and drinking water facility available

  • 21

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    5 Procurement of material from Govt. approved quarry. Improper extraction of materials can disruptnatural land contours andvegetation resulting in acceleratederosion, disturbance in naturaldrainage patterns, ponding andwater logging, and water pollution

    Contractor

    Record SIPMIU/ DSMC

    Complied

    6

    Removal of overburden and excavated/ dismantling material from working site and use / preservation of the same – as per mitigation measures

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied mostly. Most of the overburden had been used for back filling. The dismantled materials are transported to recycling vendors. Necessary instruction has been given to contractors for removal of the excess at earliest

    7

    Water sprinkling at construction site for arresting dust

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    No major issues of dust nuisance encountered so far. Instruction has been given to contractor to comply as per site condition

    8

    Materials carrying vehicle are covered

    All Sites

    Contractor

    Site observations SIPMIU/ DSMC

    Not fully complied Instruction has been given to contractor to comply the same

    9

    All vehicles and equipments mobilized to construction site and producing emission, have Pollution Control Board Certification

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Since the work is within the city area public carrier are used. (all public carrier are PUC certified, hence complied) For equipments – contractor submitted the samemostly

    10

    At sensitive locations enclosures provided around generator set and concrete mixture or other noise producing machinery

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied. New Equipments are used hence noise produced from the machines are controlled so far.

    11

    Regular maintenance of noise producing equipment done

    All Sites

    Contractor Site observations SIPMIU/ DSMC

    Complied. Equipments are new at most the locations

  • 22

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    12 Require horns not be used unlessit is necessary to warn other roadusers or animals of the vehicle’sapproach

    All Sites

    Contractor Site observations SIPMIU/ DSMC

    Honking of vehicle and equipments is restricted at Aizawl. Horns are not used within the city

    13 Minimize noise from construction equipment by using vehicle silencers,fitting jackhammers with noise reducingmufflers, and portable street barriers the sound impact tosurrounding sensitive receptor;

    All Sites

    Contractor Site observations SIPMIU/ DSMC

    Instruction has been given to contractor for minimization of noise by applying mitigation measures

    14 Arrangement of drainage of waste water and arresting solid waste from waste water generated at construction site

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    No waste water generated from pipe laying work

    15 Felling of trees done (if necessary) with mitigation measures i.e. planting of two trees for each tree fell.

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    No tree felling is required for water pipe laying work

    16 Chances of water bodies pollution from construction

    All Sites

    Contractor

    Site observations SIPMIU/ DSMC

    NA. No water bodies nearby

    17 Disposal of construction debris if any as per mitigation measures done

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Most of the debris generated is used for backfilling, hence, very little quantity to dispose which is transported to disposal sites.

    18 Local flooding from watering of excavation, flushing pipes etc.

    All Sites Contractor

    Site observations

    SIPMIU/ DSMC

    NA. No flooding noticed till date.

    19 Ensure use of Personal Protective Equipment like helmet, gumboot, gloves, safety tape, nose mask and earplugs at work place

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Contractor’s so far had provided PPEs to workers such as helmets, safety vest, shoes, gloves etc. as per nature of work. During site visit partial use of PPEs- noted.However, Instruction has been given to contractors for complete use of PPEs

  • 23

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    20 Provide Health and Safety training to all personnel and implement H & S plan

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    H & S training program has been arranged by DSMC and SIPMIU for contractors, supervisor engineers. Appendix 7 shows detail of the training program AIDS Awareness to all the Contractors workers taken up by Social group of consultant Health and Safety office and Engineer from contractor arranged tool box training for labourer and workers. Appendix 8 shows sample tool box training detail

    21 Compensation for workers in case of any injury Maintaining Occupational Health & Safety Procedure

    All sites Contractor Document available SIPMIU DSMC

    Workman compensation health insurance policy available for the package. Appendix 9shows policy paper Tie up letter with nearby health center in case of emergency received (Appendix 10) Medical examination for workers has been done, which also enclosed in Appendix 10. No major or minor case of medical attention is reported during report period Availability of First aid box with sufficient first aid materials need to be ensured at all working sites

    22 Plan truck routes to avoid city, narrow or congested roads, important or fragile buildings, religious and tourist sites

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    So far all work is carried out without affecting traffic movement. No impact on fragile building, religious places

    23 Plan transport of waste to avoid peak traffic and tourist season

    All Sites Contractor Site observations SIPMIU/ DSMC

    As per the state traffic law, contractor’s vehicle is controlled

    24 Suitable short term traffic diversion and implementation of traffic management plan at construction site

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Present works haven’t encountered such issues. However, proper plan have been implemented during laying of pipeline Particularly road closure / diversion board

  • 24

    Sl. No Mitigation Activities and Method

    Location Responsible for Mitigation

    Monitoring method Responsible for Monitoring

    Compliance status

    placed Traffic management plan prepared. Appendix 11 shows sample traffic management plan

    25 Consideration of public safety - as per prescribed mitigation measures- use of barricade, caution tape etc.

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Compliedpartially Safety caution tapes provided partially Improvement required

    26 Keep the site free from allunnecessary obstructions

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    All working sites planned without affecting movement of public. Material storage sometime obstructing movement of vehicle and public. Instruction has been given for improvement.

    27 Leave spaces for access betweenmounds of soil;and Provide walkways and metalsheets where required for people

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Access provided at working sites, but improvement is needed at few sites.

    28 Employ at least 50% of workforce from communities near sites

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    This is being practice as per availability of workers willing to work from the concern location.

    29 Continuous monitoring on implementation of mitigation measures.

    All Sites

    Contractor

    Site observations

    SIPMIU/ DSMC

    Complied. Carried out under regular site inspection.

  • 25

    V. ENVIRONMENTAL MONITORING AND EVALUATION

    24. For effective monitoring, selected environmental parameters have been identified as indicators which will be qualitatively and quantitatively measured and compared over a period of time in order to assess/ensure the compliance of EMP. The environmental performance indicators are physical, biological and social characteristics identified as most important in affecting the environment at critical locations all along the subproject locations. The parameters identified as performance indicators are:

    Air, noise and water quality

    Compliance to EMP

    Compliance to local/state/national environmental regulations

    25. During report period air quality monitoring has been conducted for only one package(P and SN/SEW/AIZ/T2/NCB-5) under Tranche 2. Monitoring not done for package P & SN/WS/AIZ/T2/ICB-3. Monitoring of rest of the packages not done. Package PS/WS/AIZ/T2/ICB-3 was terminated and for packageSTP/SEW/AIZ/T2/NCB civil work was completed.

    26. All contractors have health and safety budget for implementation of EMP and monitoring of pollution parameters.

    27. Results of air quality monitoring are shown in Table 7 below. Value of all air quality parameters are within the standard levels. Near Chite sewage pipeline area concentration ofPM10 and PM2.5 comparatively higher due to commercial activity and more traffic movement near pipe laying area. Strict application of EMP is necessary to control air pollution.

    Table 7: Ambient air quality monitoring result

    Package Status of Ambient Air Quality of Aizâwl

    Site name/ Date of Monitoring

    Air pollutants (µg/m3)

    RSPM-PM10

    RSPM-PM2.5

    SO2 NO2 CO

    CPCB standard

    100

    CPCB standard

    60

    CPCB standard

    80

    CPCB standard

    80

    CPCB standard 2

    Water Supply: Feeder Mains (WS) Water distribution-107.55 Km (P & SN/WS/AIZ/T2/ICB-3) – Tranche 2

    Base camp at Khatlâ/ 03.12.2016

    46.0 56.0 45.0 BDL

    Chawnpui/ 03.12.2016

    38.0 41.0 53.0 BDL

    New Secretariat / 15.03.2017

    88.0 50.0 29.0 40.0 BDL

    Durtlâng/ 15.03.2017

    70.0 58.0 27.0 39.0 BDL

    Mission Vêng/ 15.03.2017

    89.0 54.0 41.0 53.0 BDL

    New Secretariat/ 22.06.2017

    76.0 49.0 34.0 36.0 BDL

    Bâwngkâwn/ 22.06.2017

    78.0 53.0 28.0 39.0 BDL

    RamtharVêng/ 22.06.2017

    67.0 46.0 31.0 43.0 BDL

    New Secretariat / 12-15.10.2017

    89.0 53.0 32.0 41.0 BDL

    Durtlâng/ 12-15.10.2017

    72.0 57.0 29.0 45.0 BDL

    Mission Vêng/12- 15.10.2017

    88.0 55.0 44.0 57.0 BDL

  • 26

    Package Status of Ambient Air Quality of Aizâwl

    Site name/ Date of Monitoring

    Air pollutants (µg/m3)

    RSPM-PM10

    RSPM-PM2.5

    SO2 NO2 CO

    CPCB standard

    100

    CPCB standard

    60

    CPCB standard

    80

    CPCB standard

    80

    CPCB standard 2

    New Secretariat /24-25.04.2018

    76.0 49.0 34.0 36.0 BDL

    Bâwngkâwn South / 24-25.04.2018

    78.0 53.0 28.0 39.0 BDL

    Ramthar North/ 24-25.04.2018

    67.0 46.0 31.0 43.0 BDL

    New Secretariat /12-14.12.2018

    73.0 51.0 72.0 48.0 BDL

    Sewerage & Sanitation: Providing ,laying, jointing & Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5) - Tranche 2

    Base camp Chite/03.12.2016

    56.0 65.0 56.0 BDL

    Electric Vêng/ 03.12.2016

    46.0 56.0 45.0 BDL

    Armed Vêng/ 03.12.2016

    45.0 45.0 50.0 BDL

    ChawnpuiVêng/ 03.12.2016

    38.0 41.0 53.0 BDL

    Chitê /15.03.2017

    88.0 57.0 30.0 54.0 BDL

    ChhingaVêng/ 15.03.2017

    94.0 64.0 38.0 41.0 BDL

    RamtharVêng/ 15.03.2017

    67.0 54.0 25.0 40.0 BDL

    Chitê /20.06.2017

    107 66.0 67.0 58.0 BDL

    Lower Zârkawt /20.06.2017

    87.0 54.0 68.0 55.0 BDL

    TuithiangVêng/ 20.06.2017

    57.0 46.0 36.0 40.0 BDL

    Chitê /12-15.10.2017

    72.0 40.0 33.0 38.0 BDL

    ChhingaVêng/ 12-15.10.2017

    94.0 63.0 39.0 41.0 BDL

    RamtharVêng/12- 15.10.2017

    71.0 54.0 25.0 42.0 BDL

    Chitê base /24-25.04.2018

    107.0 65.0 67.0 57.0 BDL

    Bethlehem Vengthlang / 24-25.04.2018

    89.0 57.0 67.0 55.0 BDL

    SaronVeng/ 24-25.04.2018

    57.0 46.0 37.0 41.0 BDL

    Chitê base camp /12-14.12..2018

    88.0 57.0 65.0 58.0 BDL

    Chitê base camp /19.06..2019*

    84.0 53.0 61.0 54.0 BDL

    Water Supply Dedicated Power Supply (WS)

    Electric Sub- station – Dihmunzawl/

    31.1 18.2 11.3 17.2 BDL

  • 27

    Package Status of Ambient Air Quality of Aizâwl

    Site name/ Date of Monitoring

    Air pollutants (µg/m3)

    RSPM-PM10

    RSPM-PM2.5

    SO2 NO2 CO

    CPCB standard

    100

    CPCB standard

    60

    CPCB standard

    80

    CPCB standard

    80

    CPCB standard 2

    (PS/WS/AIZ/T2/ICB-3) 28.05.2018

    Electric Sub- station – Dihmunzawl/ 23.12..2018

    36.5 21.2 10.2 18.5 BDL

    10 MLD Construction of Sewerage Treatment Plant (STP) (STP/SEW/AIZ/T2/NCB-7)

    Entrance of STP Bethlehem Side bridge/ 10.05.2017

    69.3 26.3 BDL 8.3 -

    Inside of STP/12.05.2017

    58.7 18.2 BDL BDL -

    IPS inside Industrial growth center/13.05.2017

    64.8 21.9 BDL 8.9 -

    IPS outside Industrial growth center/15.05.2017

    62.4 19.7 BDL 6.2 -

    STP Chite/11.11.2017

    57.0 35.0 31.0 25.0 -

    (Note: Shaded results marked * monitored during report period)

    28. During report period noise level monitoring has been conducted for one (P & SN/SEW/AIZ/T2/NCB-5) package under Tranche 2,Monitoring not done for package P & SN/WS/AIZ/T2/ICB-3. Monitoring of rest of the packages not done. Package PS/WS/AIZ/T2/ICB-3 was terminated and for packageSTP/SEW/AIZ/T2/NCB civil work was completed. Instruction has been given for bi-annual monitoring for the running projects.

    29. The measured noise levels are provided in Table 8below. It is noted from the data below that noise level during report period is above the standard. The generation of noise is mainly due to commercial and human activities. Control of equipment and vehicle noise is necessary for overall minimization of the noise level.\

    Table 8: Ambient Noise Level Monitoring Data at Project Location Sites and Surroundings

    Package Monitoring Locations Noise Level in dB (A)

    Leq L Max L Min Standard

    Water Supply: Feeder Mains (WS) Water distribution-107.55 Km (P & SN/WS/AIZ/T2/ICB-3) – Tranche 2

    Base camp at Khatlâ/ 03.12.2016

    64.9 70.2 47.1 65.0

    Chawnpui/ 03.12.2016 54.90 60.4 40.0 55.0

    New Secretariat / 15.03.2017

    68.5 74.1 40.3 65.0

    Durtlâng*/ 15.03.2017 62.56 66.0 46.1 65.0

    Mission Vêng/ 15.03.2017

    64.27 68.6 45.7 65.0

    New Secretariat / 22.06.2017

    70.29 75.0 59.0 65.0

    Bâwngkâwn / 22.06.2017 64.17 69.0 55.0 65.0

  • 28

    Package Monitoring Locations Noise Level in dB (A)

    Leq L Max L Min Standard

    RamtharVêng / 22.06.2017

    61.45 65.0 55.0 65.0

    New Secretariat / 15.10.2017

    68.50 74.10 43.3 65.0

    Durtlâng/ 15.10.2017 62.56 66.0 56.1 65.0

    Mission Vêng/ /15.10.2017

    64.27 68.6 45.7 65.0

    New Secretariat /24.04.2018

    70.29 75.0 59.0 65.0

    Bâwngkâwn South / 24.04.2018

    64.17 69.0 55.0 65.0

    Ramthar North/ 24.04.2018

    61.45 65.0 55.0 65.0

    New Secretariat /12-14.12.2018

    62.6 68.0 59.0 65.0

    Bâwngkâwn South /12-14.12.2018

    63.2 69.0 55.0 65.0

    Sewerage & Sanitation:Providing ,laying, jointing & Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5) - Tranche 2

    Base camp Chite/03.12.2016

    65.30 72.0 44.1 65.0

    Electric Vêng/ 03.12.2016 64.90 70.2 47.1 65.0

    Armed Vêng/ 03.12.2016 57.13 61.6 41.1 65.0

    ChawnpuiVêng/ 03.12.2016

    54.90 60.4 40.0 55.0

    Chitê /15.03.2017

    59.14 62.9 39.6 65.0

    ChhingaVêng/ 15.03.2017

    66.57 69.0 53.4 65.0

    RamtharVêng/ 15.03.2017

    60.59 64.0 38.0 65.0

    Chitê /20.06.2017

    83.35 89.0 74.0 65.0

    Lower Zârkawt /20.06.2017

    69.35 75.0 58.0 65.0

    TuithiangVêng/ 20.06.2017

    62.24 67.0 55.0 65.0

    Chitê /15.10.2017

    67.90 70.2 59.4 65.0

    ChhingaVêng/-15.10.2017

    66.57 69.0 53.4 65.0

    RamtharVêng/ 15.10.2017

    70.59 68.0 45.0 65.0

    Chitê base /24.04.2018

    93.35 99.0 74.0 65.0

    Bethlehem Vengthlang / 24.04.2018

    69.35 75.0 58.0 65.0

    SaronVeng/ 24.04.2018 62.24 67.0 55.0 65.0

    Chitê base camp /12-14.12.2018

    60.7 66.0 58.0 65.0

    Ramthar North/ 12-14.12.2018

    66.2 72.0 58.0 65.0

    Chitê base camp 66.5 76.8 56.3 65.0

  • 29

    Package Monitoring Locations Noise Level in dB (A)

    Leq L Max L Min Standard

    /19.06..2019*

    Water Supply Dedicated Power Supply (WS) (PS/WS/AIZ/T2/ICB-3)

    Electric Sub- station – Dihmunzawl/ 28.05.2018

    63.4 61.7 56.3 75.0

    Electric Sub- station – Dihmunzawl/ 23.12.2018*

    63.4 85.7 56.3 75.0

    10 MLD Construction of Sewerage Treatment Plant (STP) (STP/SEW/AIZ/T2/NCB-7)

    Entrance of STP Bethlehem Side bridge/ 10.05.2017

    65.0 - - 75.0

    Inside of STP/12.05.2017 60.0 - - 75.0 IPS inside Industrial growth center/13.05.2017

    52.0 - - 75.0

    IPS outside Industrial growth center/15.05.2017

    54.0 - - 75.0

    STP Chite/11.11.2017 64.7 69.0 47.9 75.0

    (Note: Shaded results marked * monitored during report period)

    30. Water quality monitoring for drinking water has been conducted for one package P & SN/SEW/AIZ/T2/NCB-5.Testing results are shown in Appendix 12.It is noted that parameters of water for sewerage package locations are within the standard.

    31. All air quality, noise level and water quality testing certificates are included as Appendix 12.

    32. A performance monitoring fact sheet has been prepared to facilitate tracking and quick reference on environmental monitoring of Tranche 2 subproject packages. (Tables 9 and 10).

  • 30

    Table 9: Performance Fact Sheet for Required Environmental Consents/Clearances of NERCCDIP Aizâwl (June 2019) Tranche 2 Package Number Name of

    Contractor EMP Part of

    contract Document(Yes

    / No)

    Environmental Consents / Clearances Required

    Tree Cutting Crusher Batching Plant Hot Mix Plant

    Diesel Generator Set

    Pollution Under Control (PUC) Certificates for

    Contractor's Vehicles

    Tranche 2

    1 Water Supply: Feeder

    Mains (WS) Water distribution-107.55 Km (P & SN/WS/AIZ/T2/ICB-3)

    M/s Tantia Construction Ltd., Kolkata

    Yes Not required till date

    Not required Not required Consent to Operate obtained

    Consent will be required in case of placement of generator for the project work

    Obtained fully

    2 Water Supply

    Dedicated Power Supply (WS) (PS/WS/AIZ/T2/ICB-3)

    Work Terminated

    3 Sewerage & Sanitation:

    Providing ,laying, jointing & Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5)

    M/s Tantia Construction Ltd., Kolkata

    Yes Not required till date

    Not required Not required Consent to Operate obtained

    Consent will be required in case of placement of generator for the project work

    Obtained fully

    4 Sewerage & Sanitation:

    10 MLD Construction of Sewerage Treatment Plant (STP) (STP/SEW/AIZ/T2/NCB-7)

    M/s Eco Protection Engineers, Chennai

    Yes Tree felling done after necessary permission

    Not required Not required Not required Not required No physical work for last 6 months

  • 31

    Table 10: Performance Fact Sheet for EMP Implementation of Tranche 2(June2019)

    Sr. No.

    Package Number Name of

    Contractor

    EMP Part of contract Document(Yes / No)

    Contractor Environment

    Person

    Overall Status of EMP

    Implementation

    Field Monitored as per EMP

    Sou

    rce

    of M

    ater

    ials

    Cam

    p S

    ites

    Land

    scap

    e an

    d A

    esth

    etic

    s

    Air

    Qua

    lity

    Noi

    se L

    evel

    Tra

    ffic

    Eco

    logi

    cal R

    esou

    rces

    Ter

    rest

    rial

    Acc

    essi

    bilit

    y

    Wat

    er Q

    ualit

    y

    Occ

    upat

    iona

    l Hea

    lth &

    safe

    ty

    Com

    mun

    ity H

    ealth

    &

    safe

    ty

    Soc

    io c

    ultu

    ral r

    esou

    rces

    Em

    ploy

    men

    t gen

    erat

    ion

    Tranche 2

    1 Water Supply: Feeder Mains (WS) Water distribution-107.55 Km (P & SN/WS/AIZ/T2/ICB-3)

    M/s Tantia Construction Ltd., Kolkata

    Yes Yes

    (Mr. Mayank Yadav)

    Partially Complied

    Approved

    sources

    Constructed

    Maintained Not

    Done Not

    Done

    Traffic Manageme

    nt plan maintained

    No tree felling required

    Yes Available

    Done Complied partially

    Complied mostly

    No impact

    Yes Locals

    employed

    2 Water Supply Dedicated Power Supply (WS) (PS/WS/AIZ/T2/ICB-3)

    M/s EMC Ltd., Kolkata

    Yes

    Work Terminated.

    New contractor just

    mobilized

    3 Sewerage & Sanitation: Providing ,laying, jointing & Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5)

    M/s Tantia Construction Ltd., Kolkata

    Yes Yes

    (Mr. Mayank Yadav)

    Complied Approv

    ed sources

    Constructed

    Maintained partially

    Done Done

    Traffic Manageme

    nt plan applied

    No tree felling required

    Yes Available

    but improvem

    ent required

    Done Complied partially

    Complied mostly

    No impact

    Yes Locals

    employed

    4 Sewerage & Sanitation: 10 MLD Construction of Sewerage Treatment Plant (STP) (STP/SEW/AIZ/T2/NCB-7)

    M/s Eco Protection Engineers, Chennai

    Yes

    Yes (Mr.

    LalhminglianaHnamate)

    No Work for last 6 months

    -

  • 32

    VI. CONSULTATIONS AND DISCLOSURES CONDUCTED

    33. As per approved IEE, consultations and disclosure will be a continuous process throughout Tranche 2 implementation involving public consultations and focus group discussions. However, there are no “planned” consultation and disclosures conducted during the reporting period but informal consultation done with local people, pedestrian.

    34. The indicative schedule for consultations and disclosure is presented in Table 11.Appendix 13shows sample consultation sheet as provided by the contractor.

    35. During consultation the issues will be discussed like,

    Availability of alignment

    Possible short term impact- accessibility

    Application of mitigation measures for control of dust and noise

    Table 11: Indicative Schedule for Consultations and Disclosure Type of Consultation/ Disclosure

    Target Date Location Target Participants

    Responsible Person and Source of Funds

    Local level consultation

    Weekly – to be continued

    At all construction locations

    General public, shop keepers, pedestrian population

    Construction supervisor, Environment& safety officer of contractor, Environmental officer of SIPMIU Project budget – continuous process

    Consultation – safety issues, implementation of EMP

    Quarterly – Within July to September 2019

    At SIPMIU office and project site office

    DSMC’s Supervisor Engineer, SIPMIU Engineer, all safety and environment staff of contractors

    Environmental specialist of DSMC and Environmental Officer of SIPMIU

    36. Review and training program on safety and environment has been arranged for contractors, supervisors by SIPMIU’s Environment Officer and DSMC’s Environment Specialist on regular basis. Appendix 7 shows training details.

    37. Appendix 8 indicates sample training documents (tool box training) as submitted by contractors.

    VII. GRIVANCE REDRESSAL MECHANISM

    38. Grievances of APs will first be brought to the attention of the implementing NGO or RO. Grievances not redressed within 30 days by the NGO or RO will be brought to the grievance redress committee (GRC), established in each State. GRCs will comprise the Investment Program Director, RO, LAO, implementing NGO representative, female and male AP representatives (including vulnerable households), and an eminent member of the community. The GRC will meet every month, determine the merit of each grievance, and resolve grievances within a month of receiving the complaint; failing which the grievance will be addressed by the IPEC. Further grievances will be referred by APs to appropriate courts of law. Records will be kept of all grievances received including: contact details of complainant, date that the complaint

  • 33

    was received, nature of grievance, agreed corrective actions and the date these were affected, and final outcome. All costs involved in resolving grievances will be borne by the SIPMIU. The SIPMIU through the.DSMC will keep records of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, and final outcome. The grievance redress process is shown in Figure 4.The GRCs will continue to function throughout the project duration.Appendix 14shows GR registration format.There are no as such grievances registered during report period.

    Figure 4: Grievance Redress Mechanism NGO: Non- Government Organization, DSMC: Design Supervision Management Consultant, SIPMIU: State Investment Program Management and Implementation Unit

    STATE LEVEL

    1 Minister, UD&PA Department, Mizoram Chairman Mr. Tawnluia, Minister

    2 Deputy Commissioner Convener Mr. Vanlalngaihsaka, IAS

    3 Secretary, UD&PA, Govt. of Mizoram Member Dr. C. Vanlalramsânga, IES

    4 Secretary, Law and Judicial Department Member Ms. MarliVankung MJS

    5 Commissioner , Aizâwl Municipal Corporation (AMC)

    Member Mr. H. Lalthlangliana MCS

    6 Program Director, SIPMIU Member Er. Lalrothanga, MES

    CITY LEVEL

    1 Deputy Commissioner, Aizâwl Chairman Mr. Vanlalngaihsaka, IAS

    2 Program Director, SIPMIU Convener Er. Lalrothanga, MES

    3 Commissioner,Aizâwl Municipal Corporation (AMC)

    Member Mr. H. Lalthlangliana MCS

    4 Councilor of concern ward Member Concern AMC Councilor

    5 Chairman of concerned Local Council Member Concern Local Council

  • 34

    Chairman

    6 Chief Engineer, PHED Member Er. C. Lallunghnema

    7 Chief Engineer, PWD Member Er. R. Lalrintluanga

    8 Director, UD&PA Member Mr. Joseph H. Lalramsanga

    9 President Central YMA Member Mr. Vanlalruata

    10 President, MUP Member Mr. RK Thanga

    11 President, Mizoram Consumer Union Member Mr. Thanglura

    12 President, MHIP Member Mrs. Saipuii

    VIII. FINDINGS, RECOMMENDATIONSAND ACTIONS PLAN

    39. Protection of local environment, health andsafety of workers engaged during construction, application of mitigation measures started as per specified EMP. Public consultation during construction/implementation phase is being carried out, the general recommendations as per present observations are given below.

    40. As per ADB’s safeguard policy the project authority established a mechanism to receive and facilitate resolution of affected persons’ concerns, complaints and grievances about the project’s environmental performance. The grievances mechanism should be scaled to the risks and adverse impacts of the project. It will address- affected peoples’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to all the affected people at no cost and without retribution. The affected people will be informed by appropriate mechanism.

    41. Table 12 provides the recommended corrective action plan that has been devised and target dates that have been set so as to remove these non-compliances. The concerned Contractors have been suitably advised.

    General Effort in implementing Environmental Management Plan is carried out by the Contractors. The present status is found satisfactory but there is scope for improvement in the implementation of EMP such as – workers do not always wear proper PPE and better barricading.

    Instruction to contractors and monitoring for: Proper disposal of debris and quick disposal of

    excavated/dismantling surplus earth/iron material,

    Complete use of PPE, Restoration/construction of approach road at

    earliest Camp site management, Public safety arrangement, Maintenance of access, Material storage Water sprinkling during dry season

    Table 12: Corrective Action Plan

    Partial complied issues Action Required Responsible Target Date Indicator of Compliance

    1 Improvement of access at few locations for the package P & SN/SEW/AIZ/T2/ NCB-5- Tranche 2

    Immediate improvement is required

    Contractor 15th July 2019

    Site observation and monitoring report

    2 Improper material storage for both P & SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3

    Immediate improvement is required

    Contractor 15th July 2019

    Site observation and monitoring report

  • 35

    Partial complied issues Action Required Responsible Target Date Indicator of Compliance

    packages– Tranche 2

    3 Incomplete arrangement of First aid box with insufficient first aid materials at work locations for the package P & SN/SEW/AIZ/T2/ NCB-5- Tranche 2 and SN/WS/AIZ/T2/ICB-3 packages– Tranche 2

    Immediate arrangement is necessary

    Contractor 15th July 2019

    Site observation

    4 Partial use of caution board and tape for both P & SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 – Tranche 2

    Complete use at all working locations

    Contractor 15th July 2019

    Site observation

    5 Irregular Public consultation for both P & SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 packages– Tranche 2

    Regular public consultation

    Contractor Immediate Site observation

    6 Complete Use of PPE by contractors’ site workers and complete use of caution tape at working sites for all the packages under Tranche 2

    Immediate arrangement Contractor Immediate Site observation

  • 36

    Appendix 1 Photo Illustration

    Water Supply: Feeder Mains (WS) Water distribution-107.55 Km (P & SN/WS/AIZ/T2/ICB-3)

    Pipe laying work at Laipuitlang. No use of PPES Road restoration work continued. Partial use of PPEs noted

    Road restoration work continued. Partial use of PPEs noted

    Night work continued. Caution board and tape noted

    Water supply work at Mission Veng, no use of PPEs and caution tape

    Water supply night work at Mission Veng, no use of PPEs and caution tape

  • 37

    Sewerage & Sanitation:Providing ,laying, jointing & Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5)

    Restoration of road after pipe laying at Ramthar North. Partial use of PPEs noted

    Materials should store properly at work site. Access need to improved

    Caution tape noted at pipe laying site of Ramthar North. Access need to be maintained

    Safety Tool box training for workers

    Road restoration work continued. Use of PPEs noted

    Road restoration work continued. Partial use of PPEs noted

    Road restoration at Chhingaveng Sewage pipe laying work at Bethlehem

  • 38

    Appendix 2 Monitoring Team Details

    Sl.No Name Position Contact

    Number Email

    1 Lalrothanga Program Director, SIPMIU 0389-2390532 9436146077

    [email protected]

    2 F. Lalliandinga EnvironmentalOfficer, SIPMIU 8414034482 [email protected]

    3 Dorothy Laldinpuii Social Development Officer, SIPMIU

    9862538566 [email protected]

    4 ArdhenduMitra Environmental Specialist, DSMC

    9830415953 [email protected]

    5 VânlalruatiZotê CommunityDevelopment Specialist, SIPMIU

    8794468004 [email protected]

    6 Lalhmuaka Asst. Engineer (Environment &SWM), SIPMIU

    9612195925 [email protected]

    7 C.Dorema Evaluation &Monitoring Expert, DSMC

    9436144127 NA

    8 Ignatius Zomuankima Social Safeguard & Resettlement Expert, DSMC

    9436141236 [email protected]

    9 Mayank Yadav Environment &Safety Officer, Tantia ConstructionsLtd.(Contractor)

    7983452079 [email protected]

    10 Lalramdina Public Relations Officer,Tantia Constructions Ltd. (Contractor)

    9485140521 [email protected]

    11 LalhminglianaHnamate Environment&Safety Officer, Eco Protection Engineers Pvt. Ltd.(Contractor)

    9862860429 [email protected]

    mailto:[email protected]:[email protected]

  • 39

    Appendix 3 Consent to Operate – Hot Mix Plant

  • 40

  • 41

    Appendix 4 Tree Felling NOC for 132 KV Transmission Line

  • 42

    Appendix 5 Consent for Establishment- Sewage Treatment Plant

    (Renewed)

  • 43

    Tree felling permission for landfill site and STP site from Forest Dept.

  • 44

    Appendix 6

    SAFETY RULES for WORK SITE

    ALLOFOURSAFETYRULESMUSTBEOBEYED.FAILURETODOSOWILL RESULT INSTRICTDISCIPLINARYACTIONBEING TAKEN.

    1. Keepyourmindonyourworkatalltimes. Nohorseplayonthejob. Injuryor terminationor both can be the result.

    2. Personalsafetyequipmentmustbewornasprescribedforeachjob,suchas: safetyglassesforeyeprotection,hardhatsatalltimeswithintheconfinesof the constructionarea wherethere isa potentialfor fallingmaterialsor tools, gloveswhenhandlingmaterials,andsafetyshoesare necessaryfor protection against footinjuries.

    3. Precautionsarenecessarytopreventsunburnandtoprotectagainstburns from hot materials.

    4. If any partof yourbody should come incontact withan acidorcaustic substance,rushtothe nearestwateravailableandflushtheaffectedpart. Secure medical aid immediately.

    5. Watch where you are walking. Don't run.

    6. Theuseofillegaldrugsoralcoholorbeingundertheinfluenceofthesameon theprojectshallbecausefortermination. Informyoursupervisoriftaking strongprescriptiondrugs thatwarn against drivingor usingmachinery.

    7. Donotdistracttheattentionoffellowworkers.

    8. Donotengageinanyact which would endanger another employee.

    9. Sanitationfacilitieshavebeenorwillbeprovidedforyouruse. Defacingor damagingthesefacilitiesis forbidden.

    10. Agoodjob isa cleanjob,anda cleanjob isthestartofasafejob. Sokeepyour workingarea free fromrubbish and debris.

    11. Do not use a compressorto blow dust or dirtfrom your clothes, hair,orhands.

    12. Neverworkaloftifyouareafraidtodoso,ifyouaresubjecttodizzyspells,or if you are apt to be nervous orsick.

    13. Nevermoveaninjuredpersonunlessitisabsolutelynecessary. Furtherinjury mayresult. Keeptheinjuredascomfortableaspossibleandutilizejobsite first-aidequipment untilan ambulance arrives.

    14. Know where firefightingequipment islocated and be trained onhow touse it.

    15. Liftcorrectly-withlegs,nottheback. IftheloadistooheavyGETHELP, Stayfit. Controlyourweight. Dostretchingexercises. Approximately twenty percent ofallconstructionrelated injuries resultfrom liftingmaterials.

    16. Nobodybutoperatorshallbeallowedtorideonequipmentunlessproper seatingis provided.

    17. Do not use power tools and equipment until you have been properly instructedinthe safe work methods and become authorized touse them.\

    18. Besurethatallguardsareinplace. Donotremove,displace,damage,or destroy anysafety device orsafeguard furnished or provided for use onthe job, nor interfere with the use thereof.

    19. Do not enter anarea which has beenbarricaded.

    20. If you must work around power shovels, trucks, and dozers, make sure operators can always seeyou. Barricades are required forcranes.

    21. Never oil, lubricates, orfuelequipment whileit is runningor inmotion.

  • 45

    22. Before servicing, repairing, or adjusting any powered tool or piece of equipment, disconnect it, lock out the source ofpower, and tag it out.

    23. Barricade danger areas. Guard rails orperimeter cables may be required.

    24. Trenchesoverfivefeet deepmustbeshoredorslopedasrequired. Keepoutof trenchesor cutsthathavenotbeenproperlyshoredorsloped.

    25. Excavatedor othermaterialshallnotbestorednearerthantwofeetfromtheedge ofthe excavation. Excavationslessthan5 ftmayalsorequire caveinprotectionin some instances.

    26. Usethe"fourandone"rulewhenusingaladder. Onefootofbaseforevery fourfeet ofheight.

    27. Portableladdersinuseshallbeequippedwithsafetyfeetunlessladderistied, blockedorotherwisesecured. Stepladdersshallnotbeusedasastraight ladder.

    28. Ladders must extend three feet above landingon roof for proper use.

    29. Defectiveladders mustbe properlytagged and removed from service.

    30. Keep ladder bases free of debris, hoses, wires, materials, etc.

    31. Buildscaffoldsaccordingtomanufacturers'recommendations. Scaffold planks shall be properly lapped, cleared or otherwise secured to prevent shifting.

    32. Useonlyextensioncordsofthethree-prongtype. Usegroundfaultcircuit interrupters at all times and when using tools in wet atmosphere (e.g. outdoors) or with any temporary power supply. Check t h e e l e c t r i c a l groundingsystem daily.

    33. Theuseofharnesseswithsafetylineswhenworkingfromunprotectedhigh places is mandatory. Always keep yourline as tight as possible.

    34. Neverthrowanything"overboard." Someonepassingbelowmaybeseriously injured. Open fires are prohibited.

    35. Knowwhatemergencyprocedureshavebeenestablishedforyourjobsite. (Locationofemergency phone,firstaidkit,stretcher location,fireextinguisher locations, evacuationplan, etc)

    36. Neverenteramanhole,well,shaft,tunnelorotherconfinedspacewhich couldpossibly haveanon-respirableatmospherebecauseof lackofoxygen,or presenceoftoxicorflammablegas,orhasapossibilityofengulfment bysolids orliquids. Makecertainaqualifiedpersonteststheconfinedareawithan appropriatedetectorbeforeentry,thatthe necessarysafetyequipment is worn. Standby personmay be required to be stationedatthe entrance.

    Procedure for Using Personal Protective Equipments (PPE):

    General ConstructionWork– Basic PPE for all construction workers

    1. Safety Helmet

    2. Safety Gloves

    3. Safety Shoes

    Headprotectionwillbewornonjobsiteswhentherearepotentialsoffalling objects, hairentanglement, burning, or electricalhazards.

    Eye protection will be worn when there are potentials of hazards from flying objects or particles, chemicals, arcing, glare, or dust.

    Protective footwear shall be worn to protect from falling objects, chemicals, or stepping on sharp objects. Athletic or canvas-type shoes shall not be worn.

    Protective gloves or clothing shall be worn when required to protect against a hazard.

  • 46

    Harnesses and lanyards shall be utilized for fall protection as required in the Construction Safety Standards.

    Specialty PPE shall be provided to workers in addition to or lieu of the corresponding basic

    PPE as the work or activity requires as follows:

    Sr. No Construction Work/Activity Specialized PPE Remarks

    1

    Work near unprotected areas such as but