-
Environmental Monitoring Report
This environmental monitoring report is a document of the
borrower. The views expressed herein do not necessarily represent
those of ADB's Board of Directors, Management, or staff, and may be
preliminary in nature.
In preparing any country program or strategy, financing any
project, or by making any designation of or reference to a
particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the
legal or other status of any territory or area.
Project Number: 35290-033 July 2019 Period: January 2019 – June
2019
IND: North Eastern Region Capital Cities Development Investment
Program (NERCCDIP) –T2 (Mizoram)
Submitted by: State Investment Program Management and
Implementation Unit (SIPMIU), Urban Development & Poverty
Alleviation Department, Government of Mizoram
-
SIPlt-fIO: AIZ.4 WL
GOVERNMENT OF MiZORAM OFFICE OF THE PROGRAM DJRECTOR
STATE INVESTMENT PROGRAM MANAGEMENT ANO !MPLE ENTATION UNIT
{SIPMIUl Urban Resource Centre, New Capitol Complex; Ope Dte. Of
Anti Corruption Burer;u(A.CBj_. Ai:z6wl-796 001 • Mi1oram
Phone: (O:I89)2335503 £moil.
es/[email protected]/[email protected] Fax; (0389} .1334527
No. W-110201-/2019-PD/SIPMiUfNERCCDIP) '11 Dated. izawl. to•h
July, 2019
To The Countrv Director Indian Res1dent Misston l11 'RM) Asian
Development Bank, 4 San Martin Ma1·g, Chanakyapun New Delhi
110021
Subject: Re- submission of Semi Annual Environment Monitoring
Report Tranche -2 and Tranche - 3, (January - June, 2019),
Aizawl.
Reference: Project Number: 36290 :Loan 2834 - IND & Loan
3337 - IND
Sir,
India: North Eastern Region Urban Development Program 2 & 3
(Aizaw!, Mizoram)
Referring to the Subject and Ref. cited above, I have the honour
to state that
'Semi Annual Environment Monitoring Report Tranche - 2 and
Tranche - 3, Oanuary -
June, 2019), Aizawl' is hereby re-submitted for favour of kind
information and necessary
action please.
ASIAN DEVELOPMENT BANK ~ !NRM
,1,'?f-: 11 JUL 1019 ~fr 9~
RECEIVED
Yours Sincerely,
(LAL HANGA) Progratn Director,
SIPMIU (NERCCDIP)
Memo.No. W-11020/7 /2019-PD/SIPMIU(NERCCDIP)/11 Dated Aizawl,
10th July, 2019 Copy to:
1. The Director (UD) Ministry of Urban Development (NERUDP CellJ
Room No. 213 (C), Nirman Bhavan, Government of India. New Delhi -
110011
2. Office copy.
Program Director, SIPMIU {NERCCDIP)
. ·'
-
Semi Annual Environmental Monitoring Report
Project Number: 36290
Loan 2834-IND
Period: January to June2019 Tranche 2 India: North-Eastern
Region Urban Development Program 2 (Aizâwl, Mizoram)
July 2019
Implementing Agency: State Investment Program Management and
Implementation Unit (SIPMIU)
Executing Agency:
Urban Development & Poverty Alleviation Department,
Government of Mizoram
-
1
CONTENTS
Sr.
No.
Subject Page
No.
I Introduction 3
II Implementation Progress 5
III Environmental Procedure Review 12
IV Compliance status with Environmental Management and
Monitoring Plan 14
V Environmental Monitoring and Evaluation 25
VI Consultation and Disclosure Conducted 32
VII Grievance Redressal Mechanism 32
VIII Findings, Recommendation and Action Plan 34
List of Tables
1 Sub-project Status of Tranche – 2 (Upto30th June 2019)- Aizâwl
city 6
2 Compliance of Environmental Loan Covenants 9
3 Environmental Legal Requirements Applicable for NERCCDIP
Tranche 2,
Aizâwl, Mizoram
13
4 Status of Compliance with National and State Legal
Requirements
(upto30th June)- Tranche 2
13
5 Compliance of EMP and Environment, Health Safety Norms:
Package:
Feeder Mains (WS) Water distribution-107.55 Km (P &
SN/WS/AIZ/T2/ICB-3) of Tranche – 2
16
6 Compliance of EMP and Environment, Health Safety Norms:
Package:
Providing, laying, jointing & Commissioning of Sewerage
Network (SEW)-
45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P
&
SN/SEW/AIZ/T2/ NCB-5) under Tranche – 2
20
7 Ambient air quality monitoring result 25
8 Ambient Noise Level Monitoring Data at Project Location Sites
and
Surroundings
27
9 Performance Fact Sheet for Required Environmental
Consents/Clearances of NERCCDIP, Aizâwl (June 2019) Tranche
2
30
10 Performance Fact Sheet for EMP Implementation of Tranche 2
(June
2019)
31
11 Indicative Schedule for Consultations and Disclosure 32
12 Recommendations, Suggestion and Action taken 34
List of Figures
1 Administrative Map, Aizâwl Urban planning area (2014) 4
2 Aizâwl city area 5
3 Institutional Responsibility- NERCCDIP 12
4 Grievance Redress Mechanism 33
Appendix
1 Photo Illustration 36
2 Monitoring Team Details 38
-
2
3 Consent to Operate Hot Mix Plant 39
4 Tree Felling NOC for 132 KV Transmission Line 41
5 Consent for Establishment- Sewage Treatment Plant and Tree
felling
permission for landfill site and STP site from Forest Dept.
42
6 Safety Rules for Work site 44
7 Training Program and Meeting – Environment Safeguard 59
8 Sample Training Documents of Contractors 66
9 Workman Compensation Policy 68
10 Tie up letter and Medical examination report for workers
70
11 Traffic Management Plan 74
12 Monitoring Result- Air quality, Noise Level and Water quality
76
13 Sample Public Consultation by Contractor 79
14 Grievance Register 81
-
3
I. INTRODUCTION
A. Background
1. The Government of India has implemented projects to improve
urban conditions in North Eastern region capital cities under North
Eastern Region Capital Cities Development Investment Programme
(NERCCDIP). The investment Programme will aim at improving
infrastructure and urban service, and also strengthening the urban
institutions for better service delivery and operation maintenance
of the assets. The capital cities under the Programme are Agartala
(In Tripura), Aizâwl (In Mizoram), Gangtok (In Sikkim), Kohima (In
Nagaland), and Shillong (In Meghalaya). This report for Tranche 2
deals with the proposed investment Programme (NERCCDIP: ADB Loan
2834 IND) for Aizâwl, the capital city of Mizoram.
2. The works under the investment Programme includes development
of urban infrastructure facilities in the sector for Water Supply,
Sewerage & Sanitation and Solid Waste Management system. The
budgetary allocation for Tranche 2 NERCCDIP program is 72 million
US Dollar.Location of Aizâwl in Mizoram is shown in Figure 1.Figure
2 shows Aizâwl city map.
B. Purpose of the Report
3. NERCCDIP has been classified by ADB as environmental
assessment category B (some negative impacts but less significant
than category A) and the impacts of subprojects were assessed
through Initial Environmental Examination (IEE) reports prepared
according to ADB Environment Policy (2002,2009) and Environmental
Assessment Guidelines (2003).
4. This report is the Semi-Annual Environmental Monitoring
Report (SAEMR) – Tranche 2 for the period January to June 2019 to
describe the “Environmental Compliance” including status of
implementation of the mitigation measures and monitoring
recommended in the Initial Environmental Examination (IEE).
-
4
Figure 1: Administrative Map Aizâwl Urban planning area
(2014)
-
5
Figure 2: Aizâwl city area
II. IMPLEMENTATION PROGRESS
A. Status of the Sub projects
5. Work of sub project for Tranche 1 has been successfully
completed and handed over to the concern authority and are in
function. The concern contractors have also been released, since
liability period for each work components has ended. Now work for
Tranche 2 is under progress.
6. InTranche 2 there are 11 packages covering water supply,
sewerage & sanitation and solid waste management. Out of the 11
packages work completed for 7 packages. Work to be completed
shortly for 1 package. One water supply package work (package -
PS/WS/AIZ/T2/ICB-3) stopped due to termination of contract. Rest 2
packages (1 water supplies -P & SN/WS/AIZ/T2/ICB-3 and
1sewerage sanitation - P & SN/SEW/AIZ/T2/ NCB-5) are under
implementation. But as such no work (only 3 to 4 % progress)during
last 6 months for those packages.
7. Table 1shows the status of the awarded packages, starting
date, and schedule date of completion, physical progress and work
components progress status for Tranche 2.
8. Photo illustration of project locations is shown in Appendix
1.
-
6
Table 1: Sub-project Status of Tranche – 2 (Upto30th June
2019)-Aizâwl city Sr. No.
Sub-projects (Package No.)
Work Components
Starting date of Implementation
Projected months of completion (as per Work order)
Schedule date of completion
Physical progress (%) as on 30.06. 2019
Works Completed / progress as of 30th June 2019
Corrective action
1 Water Supply: Booster Pumps (WS)-2
(EM&S/WS/AIZ/T2/NCB-1)
Construction of booster pumping stations at 2 locations
16.05.2012 17 months 31.10.2013 100% completed
Project completed
2 Water Supply: Water reservoir (WS)-3 (GLR/WS/AIZ/T2/NCB-3)
Construction of water reservoirs at 3 locations
25.06.2012 19 months 25.01.2014 100% completed
Project completed
3 Water Supply: Bulk -85
and domestic water meters (WS)- 20,000 (WM2/WS/AIZ/T2/ICB-2)
Supply of 85 nos. Bulk flow meter and domestic water meters
(WS)- 20,000
21.09.2012 39 months 30.04.2016
100% completed
Total of 20000 nos. of domestic meter and 55 Flow meters
installed
4 Water Supply: Feeder
Mains (WS) Water distribution-107.55 Km (P &
SN/WS/AIZ/T2/ICB-3)
Laying of 107.55 km Feeder main
29.08.2013 42 months Revised 70 months
28.02. 2017 Extended upto
31.12.2017 Then
extendedupto June 2018
Further extended upto30.06.19
87.05% Total Pipe laid distribution 86.66 Km & feeder mains
13.59 Km. (Total pipe layed = 100.25 Km) Out of 13275 House
connection, 8432 tapped out upto road shoulder and 617 connected.
Feeder main completed.
Very slow Progress. Only 4% work done in last 6 months. Planning
and increase of manpower will be required for timely completion of
project
5 Water Supply Dedicated
Power Supply (WS) (PS/WS/AIZ/T2/ICB-3)
Construction of 132 kVA substation at Dihmunzâwl, transmission
line through erection of 19 nos. towers
27.11.2013 36 months Revised 60 months
30.11.2016 Extended upto
30.11.2017 Further extension upto 31.05.2018 Third Extension
upto 31.12.2018
Further extension under process
88.14% Substation: Switchyard stringing completed. Erection of
all equipments completed. Main gate with boundary wall at front
is
No work for last 6 months. Contractor Terminated. Appointment of
new contractor just done
-
7
Sr. No.
Sub-projects (Package No.)
Work Components
Starting date of Implementation
Projected months of completion (as per Work order)
Schedule date of completion
Physical progress (%) as on 30.06. 2019
Works Completed / progress as of 30th June 2019
Corrective action
completed. Electrification at CRB completed. Transmission Tower:
13 nos. erection completed & 2 nos. foundation work completed
and 1 no earthwork and stringing of tower outstanding.
6 Sewerage & Sanitation:
Cesspool Cleaner (SEW)-5 nos.(SCM/SEW/AIZ/T2/ NCB-2)-
Environment non sensitive package
Procurement of Cesspool cleaner
18.05.2012 17 months 18.10.2013 100% completed
Project completed
7 Sewerage & Sanitation:
Community toilet blocks (SEW)- 10 nos. (CT/SEW/AIZ/T2/NCB-4)
Construction of community toilets
29.08.2013 26 months 31.10.2015 100% completed
Project completed
8 Sewerage & Sanitation:Providing
,laying, jointing & Commissioning of Sewerage Network
(SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI K7) (P
& SN/SEW/AIZ/T2/ NCB-5)
Sewage pipe laying -45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC &
1.58 Km-DI K7)
27.11.2013 42 months Revised 65 months
31.05.2017 Extended upto
31.12.2017 Then extended upto 31.12.2018 Further extended
upto30.06.2019
69.64% Main sewer pipe laid 24.35 Km. uPVC piped laid 12.04km.
Manholes 1050Nos.
Very slow progress.Only 3% work done in last 6 months. Planning
and increase of manpower will be required for timely completion of
project
9 Sewerage & Sanitation:
Site/Land Development & Approach Road to STP (AR &
LD/SEW/AIZ/T2/NCB-60)
Approach road – 285 m Asphalt road at Bethlehem Vêngthlang
(about 2 km from the city)
26.02.2013 46 months 31.12.2016 Extended upto
30.04.2017
100% completed
Project completed -
-
8
Sr. No.
Sub-projects (Package No.)
Work Components
Starting date of Implementation
Projected months of completion (as per Work order)
Schedule date of completion
Physical progress (%) as on 30.06. 2019
Works Completed / progress as of 30th June 2019
Corrective action
10 Sewerage & Sanitation:
10 MLD Construction of Sewerage Treatment Plant (STP)
(STP/SEW/AIZ/T2/NCB-7)
Construction of 10 MLD STP at Bethlehem Vêngthlang – technology
: Sequencing Batch Reactors (SBR)
27.11.2013 40 months Revised 64 months
31.03.2017 Extended upto
31.12.2017 Further extended
upto 31.10.18 Third extension upto 31.03.19
Fourth extension upto 30.06.2019
98.9% All civil, mechanical and electrical installation
completed. Transformer installed. Pre commissioning completed
Work almost completed. No major work in last 6 months
11 Solid waste management:
Procurement of Dustbins
Procurement and supply of 132200 nos. dustbin
16.06. 2016 5 months 16.11.2015 (Actual
Completion April 2017)
100% Completed
Project completed
-
9
9. Till date scope of the sub projects are not changed.
B. Compliance of Safeguard Loan Covenants
10. The loan agreement for NERCCDIP Project 2 was signed on 19th
November 2012 and available in ADB website
(http://www.adb.org/sites/default/files/project-document/74927/35290-033-ind-mlo1.pdf)).
Table 3provides a summary of compliance to the loan covenants
related to environmental safeguards.
Table 2: Compliance of Environmental Loan Covenants
Serial no. as per loan agreement
Program Specific Covenants Status / Issues
Environment
4 The Borrower shall ensure or cause the EA to ensure that the
preparation, design, construction, implementation, operation and
decommissioning of the Project, and all projects’ facilities comply
with (i) all applicable laws and regulations of the Borrower and
the State relating to environment, health, and safety; (ii) the
Environmental Safeguards; (iii) the EARF; and (iv) all measures and
requirements set forth in the respective IEE and EMP, and any
corrective or preventative actions set forth in a Safeguards
Monitoring Report.
Under compliance Document is prepared/ or under preparation by
complying all relevant State and National Laws, Safeguard Policy
Statement (SPS 2009) of ADB, Environment Assessment Review
Framework (EARF) for Tranche-2 program. For Tranche 2 project
Initial Environmental Examination (IEE), Environment Management
Plan (EMP) report prepared and approved by ADB. IEE for the Tranche
2 has been updated and that report has already been disclosed in
ADB website Updated IEE for Tr 2 sewerage has been done and
submitted to ADB for acceptance and disclosure. Report disclosed in
ADB website on July 2017 IEE will be revised further in case of any
change of scope and location. All measures and requirements as
prescribed in IEE/EIA and EMP are being considered during
implementation. Corrective or preventive action plans will be
reflected in Environment Monitoring Report and project
implementation authority will take care of such actions when
required.
Human and Financial Resources to Implement Safeguards
Requirements
7 The Borrower shall make available, or cause the EA to make
available, all necessary budgetary and human resources to fully
implement the Environment Management Plan (EMP) required.
Complied Budgetary provisions have been included in EMP of
Tranche 2 projects Human resource (project consultant, i.e
Environmental Specialist of DSMC) for implementation of EMPs is in
place for regular monitoring to secure complete compliance.
Safeguards – Related Provisions in Bidding Documents and Works
Contracts
http://www.adb.org/sites/default/files/project-document/74927/35290-033-ind-mlo1.pdfhttp://www.adb.org/sites/default/files/project-document/74927/35290-033-ind-mlo1.pdf
-
10
Serial no. as per loan agreement
Program Specific Covenants Status / Issues
8 The Borrower shall ensure, or cause the EA to ensure, that all
bidding documents and contracts for Works contain provisions that
require contractors to: (a) comply with the measures and
requirements relevant to the contractor set forth in the IEE, the
EMP, the RP and the IPP (to the extent they concern impacts on
affected people during construction), and any corrective or
preventative actions set out in a Safeguards Monitoring Report; (b)
make available a budget for all such environmental measures; (c)
provide the EA with a written notice of any unanticipated
environmental risks or impacts that arise during construction,
implementation or operation of the Project that were not considered
in the IEE, the EMP, the RP or the IPP; (d) adequately record the
condition of roads, agricultural land and other infrastructure
prior to starting to transport materials and construction; and (e)
fully reinstate pathways, other local infrastructure, and
agricultural land to at least their pre-project condition upon the
completion of construction.
Under compliance (a) Approved IEE, EMP for Tranche 2 project is
attached in Bidding documents. This process will be followed for
all the sub projects within the present Tranche. In case of any
change of scope, revised IEEs with EMP(s) will be prepared and
corrective measures will be disclosed to the contractor and same
will be reflected in the “Environment Monitoring Report”. Updated
IEE for Tr-2 sewerage has been done and submitted to ADB for
acceptance & disclosure. Report disclosed in ADB website on
July 2017 (b) IEE indicates budgetary provisions for implementation
of EMP. (c) During implementation of any sub project if additional
impacts/risks arise due to change in scope/area that will be
reflected in the revised IEEs, EMPs and Environment Monitoring
Report and accordingly project Executing Agency will inform the
Construction Agency for taking relevant corrective measures. (d)
Haul roads will be marked properly (by avoiding residential and
agricultural land) before commencement of transportation of
materials. (e) Pathways, infrastructure and land which are likely
to be affected for varying periods during implementation of the sub
project will be restored by concerned construction agency before
acceptance of the work. Restoration status will be reflected in
post construction monitoring report.
Safeguards Monitoring and Reporting
9 The Borrower shall cause the EA to do the following: (a)
submit semi-annual Safeguards Monitoring Reports to ADB and
disclose relevant information from such reports to affected persons
promptly upon submission;
(b) if any unanticipated environmental and/or social risks and
impacts arise during construction, implementation or operation of
the Project that were not considered in the
Under compliance (a) Submitted on regular basis. This is
Semi-annual safeguard monitoring report on Environment for the
period January to June2019. (b) During implementation of any sub
project, if additional impacts/risks arise due to change in
scope/area, those will be reflected in revised IEEs with EMPs
and
-
11
Serial no. as per loan agreement
Program Specific Covenants Status / Issues
IEEs, the EMPs, promptly inform ADB of the occurrence of such
risks or impacts, with detailed description of the event and
proposed corrective action plan; and (c) report any breach of
compliance with the measures and requirements set forth in the
EMPs, promptly after becoming aware of the breach.
accordingly Executing Agency (EA) will inform the ADB such
change along with corrective action plan which will be reflected in
the subsequent Monitoring Reports. (c) in case of any breach of
compliance with the measures and requirements set forth in the EMP,
EA will promptly inform ADB and suitable corrective action program
will be planned/initiated.
Prohibited List of Investments
10 The Borrower shall ensure or cause the State to ensure that
no proceeds of the Loan are used to finance any activity included
in the list of prohibited investment activities provided in
Appendix 5 of the SPS.
Complied Under Tranche 2there is no violation of prohibited
investment activities as per ADB SPS (2009) Appendix 5.
Other Social Measures
11 The EA shall ensure that civil works contracts under the
Project follow all applicable labor laws of the Borrower and the
State, and that these further include provisions to the effect that
contractors: (i) carry out HIV/AIDS awareness programs for labor
and disseminate information at worksites on risks of sexually
transmitted diseases and HIV/AIDS as part of health and safety
measures for those employed during construction; and (ii) follow
and implement all statutory provisions on labor (including not
employing or using children as labor, equal pay for equal work),
health, safety, welfare, sanitation, and working conditions. Such
contracts will also include clauses for termination in case of any
breach of the stated provisions by the contractors.
Complied in Bid documents and under compliance during
implementation Provision are included (as per EMP & BID
document) to carry out HIV/AIDS awareness programs for construction
contractor, application of all relevant labour laws for health and
safety including child labour law and engagement of local labours
(preferably from economically backward group) covering women
labours. In case of any breach of provision, necessary corrective
measures as per contract clauses shall be taken. Already awareness
program has been organized from DSMC. All activities including
awareness program will be reflected in “Monitoring Report”.
C. Implementation Arrangement
Details on the SIPMIU and DSMC environmental cell setup and
personnel
11. Environmental issues of the project coordinated by an
Environmental Specialist within the DSMC, who ensures that all
subprojects, comply with environmental safeguards. There is one
Environmental Officer (Assistant Engineer Environment) in SIPMIU.
The Safeguard Officer is responsible for implementing the
environmental safeguard provisions in the project including (i)
ensuring environmental criteria for subproject selection in the
EARF are followed, (ii) ensuring mitigation requirements are in
contractor bidding documents, and (iii) liasing with various
Central and State government agencies on compliance matters. The
SIPMIU appointed and manage Construction Contractors (CC) to build
elements of the infrastructure that are required to submit
Environmental Implementation Plans (EIPs) for SIPMIU approval. The
SIPMIU is assisted by the DSMC, who is responsible for design the
infrastructure, manage tendering of contracts, and supervise the
construction process.
12. An Environmental Specialist (ES) in the DSMC is responsible
for addressing the environmental issues in the project components
during design and implementation. The ES ensure all mitigation
requirements are in contractor bidding documents and EMPs, and
supervise the effective implementation of environmental provisions
during construction. In addition, the ES assist the SIPMIU on the
procurement needs and other project
-
12
implementation aspects and play a central role in ensuring
capacity building on environmental management of the SIPMIU,
Contractor and Line Departments through capacity development
support and training. Figure 3 shows institutional responsibility
for implementation of environmental safeguard monitoring at
different level.Appendix 2 shows safeguard team (Tranche 2) for
Aizâwl.
13. EMP shows that most of the mitigation measures are fairly
standard methods of minimizing disturbance from building in urban
areas (maintaining access, planning work to avoid sensitive times,
finding uses for waste material, etc), and experienced Contractors
should be familiar with most of the requirements. Monitoring of
such measures normally involves making observations in the course
of site visits, although some require more formal checking of
records and other aspects. There are also be some surveys of
residents, as most of the measures are aimed at preventing impacts
on people and the human environment.
Figure 3: Institutional Responsibility- NERCCDIP
III. ENVIRONMENTAL PROCEDURE REVIEW
A. Environmental Legal Requirement
14. Table 3 provides a list of national and state laws, rules,
policies and regulations applicable to NERCCDIP Tranche 2for
Aizawl, Mizoram.
-
13
Table 3: Environmental Legal Requirements Applicable for
NERCCDIP Tranche 2, Aizâwl, Mizoram
Component Applicable Legislation Compliance Action Required
All components that require acquisition of forest land
Forest (Conservation) Act 1980
Approval from State Forest Office, Principal Chief Conservator
of Forest and Ministry of Environment and Forests& Climate
Change (MoEFCC), Government of India
In case of tree felling permission as per requirement In case of
use of Forest Land , Forest clearance will be required
B. Compliance with Environmental Legal Requirements
15. Before implementation of the project compliance with
environmental policy, law and legislation is necessary.
16. Table 4below shows present clearance status for sub-project
under Tranche 2.
Table 4: Status of Compliance with National and State Legal
Requirements (upto30th June 2019)- Tranche 2
Package Main package work
National and State Legal Requirement
Status
Tranche 2
P & SN/ WS/AIZ/T2/ICB-3
Feeder Mains (WS) Water distribution-107.55 Km
Water (Prevention and Control of Pollution) Act. 1974
The Air (Prevention and Control of Pollution) Act, 1981, as
amended by Amendment Act, 1987
As per Act CTE and CTO from MPCB: (i) diesel generators; and
(ii) hot mix plants, wet mix plants, stone crushers, etc. if
installed for construction.
Noise Pollution (Regulation and Control) Rules, 2002 amended up
to 2010
During implementation of project compliance against Air Act ,
Noise Rules and Water Act continued Consent to Operate for hot mix
plant has been obtained from MPCB and which valid upto 6th July
2027 (Attached as Appendix 3)
PS/WS/AIZ/T2/ICB-3 Dedicated Power Supply (WS)
Water (Prevention and Control of Pollution) Act. 1974
The Air (Prevention and Control of Pollution) Act, 1981, as
amended by Amendment Act, 1987
Noise Pollution (Regulation and Control) Rules, 2002 amended up
to 2010
Forest (Conservation) Act 1980, Mizoram Forest Act 1955
During implementation of project compliance against Air Act,
Noise Rules and Water Act continued Permission needs to be obtained
for felling of the trees at project sites. Process completed for
marking of trees in presence of personnel from forest dept. NOC
from forest dept. received, attached as Appendix 4.
P & SN/ SEW/ AIZ/T2/ NCB-5
Providing ,laying, jointing & Commissioning of Sewerage
Network
Water (Prevention and Control of Pollution) Act. 1974
During implementation of project compliance against Air Act ,
Noise Rules and Water Act continued
-
14
Package Main package work
National and State Legal Requirement
Status
(SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58 Km-DI
K7)
The Air (Prevention and Control of Pollution) Act, 1981, as
amended by Amendment Act, 1987
As per Act CTE and CTO from MPCB: (i) diesel generators; and
(ii) hot mix plants, wet mix plants, stone crushers, etc. if
installed for construction.
Noise Pollution (Regulation and Control) Rules, 2002 amended up
to 2010
Tree felling NOC from forest dept. as per Forest (Conservation)
Act 1980, Mizoram Forest Act 1955
Consent to Operate for hot mix plant has been obtained from MPCB
and which valid upto 6th July 2027 (Attached as Appendix 3) In case
of tree felling NOC needs to be obtained from concerned
authority
STP/SEW/AIZ/T2/NCB–7
10 MLD Construction of Sewerage Treatment Plant (STP)
Water (Prevention and Control of Pollution) Act. 1974
Consent to Establish (CTE) for rehabilitation of WTP from
Mizoram Pollution Control Board
Consent to operate will be required before operation
Forest (Conservation) Act 1980; Mizoram Forest Act 1955 The Air
(Prevention and Control of Pollution) Act, 1981, as amended by
Amendment Act, 1987
Noise Pollution (Regulation and Control) Rules, 2002 amended up
to 2010.
Also for setting up (if any) hot mix plant, batching plant and
use of diesel generator Consent to Establish (CTE) and Consent to
Operate (CTO)
During implementation of project compliance against Air Act ,
Noise Rules and Water Act continued Consent to Establish obtained
from Pollution Control Board on 23.08.2012, renewal has been done
and which presently valid upto23.08.2019(Appendix 5). Tree felling
permission obtained from Principal Chief Conservator of Forests.
1st June 2011 (Appendix 5) Tree felled at STP site is 20 nos. and
will be replanted in the ratio of 1:2 (i.e for every one tree
felled two nos. of tree will be planted) Tree plantation done
IV. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND
MONITORING PLAN
17. In Tranche 2 there are 11 packages covering water supply,
sewerage & sanitation and solid waste management. Out of the 11
packages work completed for 7 packages. Work to be completed
shortly for 1 package. One water supply package work stopped due to
termination of contract. Rest 2 packages (1 water supplies and
1sewerage - sanitation) are
-
15
under implementation. But as such no work (only 3 to 4 %
progress)during last 6 months for those packages.
18. Compliance on EMP and Environment, Health Safety Norms for
two ongoing sub projects under Tranche 2 packages are shown in
Tables5 and 6. Due to termination of one water supply package
(package no. PS/WS/AIZ/T2/ICB-3)and no work for sewerage package,
(package no. STP/SEW/AIZ/T2/NCB-7) EMP monitoring not done for
those packages.
19. For implementation of EMP, arrangement of human safety,
provision of PPE for workers engaged in construction is being
implemented. Training is being provided to the contractor by DSMC’s
Environment Specialist. Moreover instruction is given to
contractors to follow the specified clause of BID document to
mitigate environmental and social impacts.
20. The contractors whose work requires environmental
implementation has been instructed to submit their environmental
management plan for approval. Environment Management Plan as
submitted by the contractor are scrutinized and checked, wherever
necessary environment criteria required is added.
21. Construction contractors provide all necessary safety
arrangement for individual safety and construction site, for
individual they provide all type of PPEs like Safety Vest, Safety
Helmet, Hand Gloves, Safety Shoes and respiratory mask, on site it
is observed that partial use PPEs, needs more awareness about need
of full use of PPE in between the laborers especially with risk
nature of the worksite job and type of PEE used for such type of
job. For construction site safety they provide safety caution tape,
cautionary signages, safe passage for traffic and road users and
awareness meeting with locality habitants about importance risk
nature of construction job.Appendix 6shows standard instruction and
guidelines for compliance of health and safety issues.
22. Environment Officer of SIPMIU and Environment Specialist
from DSMC carried out periodic monitoring of EMP implementation
through desk review of contractor’s records and site inspections.
Package wise findings are presented in compliance tables, Tables
5and 6. It may be noted, though most of the sites are
environmentally well managed, in a few cases in packages there are
scope for further improvement in site management measures as
mentioned below,
o Improvement of access at few locations for the package P &
SN/SEW/AIZ/T2/ NCB-5- Tranche 2
o Improvement of material storage for both P &
SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 packages–
Tranche 2
o Arrangement of First aid box with sufficient first aid
materials at all working locations for the package P &
SN/SEW/AIZ/T2/ NCB-5 and SN/WS/AIZ/T2/ICB-3 packages– Tranche 2
o Complete use of caution board and tape for both P &
SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 – Tranche 2
o Complete Use of PPE by contractors’ site workers and complete
use of caution tape at working sites for all the packages under
Tranche 2
o Public consultation on regular basis for both P &
SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 packages–
Tranche 2
23. The concerned contractors were instructed verbally and also
in writing. During subsequent field visits and from monthly
monitoring reports it was observed that such deficiencies are
mostly removed and site management has considerably improved.
-
16
Table 5: Compliance of EMP and Environment, Health Safety
Norms
Package: Feeder Mains (WS) Water distribution-107.55 Km (P &
SN/WS/AIZ/T2/ICB-3) of Tranche – 2 Sl. No Mitigation Activities
and
Method Location Responsible for
Mitigation Monitoring method Responsible for
Monitoring Compliance status
1
Site preparation work completed by SIPMIU including necessary
clearance
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied as per requirement
2 Shifting of Telephone lines, electric polesand wires, water
lines withinproposed project area
Working sites
Contractor
Site observations/ records
SIPMIU/ DSMC
Complied as per requirement
3 Consultation with archeological dept. to obtain an
expertassessment of the archaeologicalpotential of the site; in
case of ground disturbance can uncoverand damage archaeological
andhistorical remains
Working sites
Contractor
Site observations/ records
SIPMIU/ DSMC
Being complied, as and when required
4
Establishment of temporary camps and storage yard with available
water,sanitation facility and solid waste management
arrangement
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Compliedmostly Regular checks and instructions are being carried
out during site visit and found some improvement so far for all the
construction camps / cum storage yard. Needs to be maintained
5 Procurement of material from Govt. approved quarry. Improper
extraction of materials can disrupt natural land contours
andvegetation resulting in acceleratederosion, disturbance in
naturaldrainage patterns, ponding andwater logging, and water
pollution
Contractor
Record SIPMIU/ DSMC
Complied
-
17
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
6
Removal of overburden and excavated/ dismantling material from
working site and use / preservation of the same – as per mitigation
measures
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied mostly. Most of the overburden had been used for back
filling. The dismantled materials are transported to recycling
vendors. Necessary instruction has been given to contractors for
removal of the excess earthat earliest Also materials need to be
stored properly
7
Water sprinkling at construction site for arresting dust
All Sites
Contractor
Site observations
SIPMIU/ DSMC
No major issues of dust nuisance encountered so far. Instruction
has been given to contractor to comply as per site condition
8
Materials carrying vehicle are covered
All Sites
Contractor
Site observations SIPMIU/ DSMC
Not fully complied Instruction has been given to contractor to
comply the same
9
All vehicles and equipments mobilized to construction site and
producing emission, have Pollution Control Board Certification
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Since the work is within the city area public carrier are used.
(all public carrier are PUC certified, hence complied) For
equipments – contractor submitted the same
10
At sensitive locations enclosures provided around generator set
and concrete mixture or other noise producing machinery
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied. New Equipments are used hence noise produced from the
machines are controlled so far.
11
Regular maintenance of noise producing equipment done
All Sites
Contractor Site observations SIPMIU/ DSMC
Complied.
12 Require horns not be used unlessit is necessary to warn other
roadusers or animals of the vehicle’sapproach
All Sites
Contractor Site observations SIPMIU/ DSMC
Honking of vehicle and equipments is restricted at Aizawl. Horns
are not used within the city
13 Minimize noise from construction equipment by using vehicle
silencers,fitting jackhammers with noise reducingmufflers, and
portable streetbarriers the sound impact tosurrounding
sensitive
All Sites
Contractor Site observations SIPMIU/ DSMC
Instruction has been given to contractor for minimization of
noise by applying mitigation measures
-
18
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
receptor
14 Arrangement of drainage of waste water and arresting solid
waste from waste water generated at construction site
All Sites
Contractor
Site observations
SIPMIU/ DSMC
No waste water generated from pipe laying work
15 Felling of trees done (if necessary) with mitigation measures
i.e. planting of two trees for each tree fell.
All Sites
Contractor
Site observations
SIPMIU/ DSMC
No tree felling is required for water pipe laying work
16 Chances of water bodies pollution from construction
All Sites Contractor Site observations SIPMIU/ DSMC
NA. No water bodies nearby
17 Disposal of construction debris if any as per mitigation
measures done
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Most of the debris generated is used for backfilling, hence,
very little quantity to dispose which is transported to disposal
sites.
18 Local flooding from watering of excavation, flushing pipes
etc.
All Sites Contractor
Site observations
SIPMIU/ DSMC
NA. No flooding noticed till date. For water supply package no
deep excavation is required and generation of waste water from
excavation does not arise
19 Ensure use of Personal Protective Equipment like helmet,
gumboot, gloves, safety tape, nose mask and earplugs at work
place
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Contractor’s so far had provided PPEs to workers such as
helmets, safety vest, shoes, gloves etc. as per nature of work.
During site visit partial use of PPEs noted. However, Instruction
has been given to contractors for complete use of PPEs
20 Provide Health and Safety training to all personnel and
implement H & S plan
All Sites
Contractor
Site observations
SIPMIU/ DSMC
H & S training program has been arranged by DSMC and SIPMIU
for contractors, supervisor engineers.Appendix 7 shows detail of
the training program AIDS Awareness to all the Contractors workers
taken up by Social group of consultant Health and Safety officer
and Engineer from contractor arranged tool box training
-
19
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
for labourer and workers. Appendix 8 shows sample tool box
training detail
21 Compensation for workers in case of any injury Maintaining
Occupational Health & Safety Procedure
All sites Contractor Document available SIPMIU DSMC
Workman compensation health insurance policy available for the
package. Appendix 9shows policy Tie up letter with nearby health
center in case of emergency received (Appendix 10) Medical
examination for workers has been done, which also enclosed in
Appendix 10. No accident reported during report period
22 Plan truck routes to avoid city, narrow or congested roads,
important or fragile buildings, religious and tourist sites
All Sites
Contractor
Site observations
SIPMIU/ DSMC
So far all work is carried out without affecting traffic
movement.
23 Plan transport of waste to avoid peak traffic and tourist
season
All Sites Contractor Site observations SIPMIU/ DSMC
As per the state traffic law, contractor’s vehicle is
controlled
24 Suitable short term traffic diversion and implementation of
traffic management plan at construction site
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Present works haven’t encountered such issues. However, proper
plan have been implemented during laying of pipeline Particularly
road closure / diversion board placed Traffic management plan
prepared. Appendix 11 shows sample traffic management plan
25 Consideration of public safety - as per prescribed mitigation
measures- use of barricade, caution tape etc.
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Compliedpartially Safety caution tapes provided partially
Improvement required
26 Keep the site free from allunnecessary obstructions
All Sites
Contractor
Site observations
SIPMIU/ DSMC
All working sites planned without affecting movement of public.
Material storage needs to be improved, sometime obstructing
movement of vehicle and public
-
20
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
27 Leave spaces for access betweenmounds of soil;and Provide
walkways and metalsheets where required for people
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Access provided at working sites
28 Employ at least 50% of workforce from communities near
sites
All Sites
Contractor
Site observations
SIPMIU/ DSMC
This is being practice as per availability of workers willing to
work from the concern location.
29 Continuous monitoring on implementation of mitigation
measures.
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied. Carried out under regular site inspection.
Table 6: Compliance of EMP and Environment, Health Safety
Norms
Package: Providing,laying, jointing &commissioning of
Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC &
1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5) under Tranche – 2
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
1
Site preparation work completed by SIPMIU including necessary
clearance
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied as per requirement
2 Shifting of Telephone lines, electric polesand wires, water
lines withinproposed project area
Working sites
Contractor
Site observations/ records
SIPMIU/ DSMC
Complied as per requirement
3 Consultation with archeological dept. to obtain an
expertassessment of the archaeologicalpotential of the site; in
case of ground disturbance can uncovered and damage archaeological
andhistorical remains
Working sites
Contractor
Site observations/ records
SIPMIU/ DSMC
Being complied, as and when required
4
Establishment of temporary camps with available water,
sanitation facility and solid waste management arrangement
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied. Toilet and drinking water facility available
-
21
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
5 Procurement of material from Govt. approved quarry. Improper
extraction of materials can disruptnatural land contours
andvegetation resulting in acceleratederosion, disturbance in
naturaldrainage patterns, ponding andwater logging, and water
pollution
Contractor
Record SIPMIU/ DSMC
Complied
6
Removal of overburden and excavated/ dismantling material from
working site and use / preservation of the same – as per mitigation
measures
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied mostly. Most of the overburden had been used for back
filling. The dismantled materials are transported to recycling
vendors. Necessary instruction has been given to contractors for
removal of the excess at earliest
7
Water sprinkling at construction site for arresting dust
All Sites
Contractor
Site observations
SIPMIU/ DSMC
No major issues of dust nuisance encountered so far. Instruction
has been given to contractor to comply as per site condition
8
Materials carrying vehicle are covered
All Sites
Contractor
Site observations SIPMIU/ DSMC
Not fully complied Instruction has been given to contractor to
comply the same
9
All vehicles and equipments mobilized to construction site and
producing emission, have Pollution Control Board Certification
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Since the work is within the city area public carrier are used.
(all public carrier are PUC certified, hence complied) For
equipments – contractor submitted the samemostly
10
At sensitive locations enclosures provided around generator set
and concrete mixture or other noise producing machinery
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied. New Equipments are used hence noise produced from the
machines are controlled so far.
11
Regular maintenance of noise producing equipment done
All Sites
Contractor Site observations SIPMIU/ DSMC
Complied. Equipments are new at most the locations
-
22
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
12 Require horns not be used unlessit is necessary to warn other
roadusers or animals of the vehicle’sapproach
All Sites
Contractor Site observations SIPMIU/ DSMC
Honking of vehicle and equipments is restricted at Aizawl. Horns
are not used within the city
13 Minimize noise from construction equipment by using vehicle
silencers,fitting jackhammers with noise reducingmufflers, and
portable street barriers the sound impact tosurrounding sensitive
receptor;
All Sites
Contractor Site observations SIPMIU/ DSMC
Instruction has been given to contractor for minimization of
noise by applying mitigation measures
14 Arrangement of drainage of waste water and arresting solid
waste from waste water generated at construction site
All Sites
Contractor
Site observations
SIPMIU/ DSMC
No waste water generated from pipe laying work
15 Felling of trees done (if necessary) with mitigation measures
i.e. planting of two trees for each tree fell.
All Sites
Contractor
Site observations
SIPMIU/ DSMC
No tree felling is required for water pipe laying work
16 Chances of water bodies pollution from construction
All Sites
Contractor
Site observations SIPMIU/ DSMC
NA. No water bodies nearby
17 Disposal of construction debris if any as per mitigation
measures done
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Most of the debris generated is used for backfilling, hence,
very little quantity to dispose which is transported to disposal
sites.
18 Local flooding from watering of excavation, flushing pipes
etc.
All Sites Contractor
Site observations
SIPMIU/ DSMC
NA. No flooding noticed till date.
19 Ensure use of Personal Protective Equipment like helmet,
gumboot, gloves, safety tape, nose mask and earplugs at work
place
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Contractor’s so far had provided PPEs to workers such as
helmets, safety vest, shoes, gloves etc. as per nature of work.
During site visit partial use of PPEs- noted.However, Instruction
has been given to contractors for complete use of PPEs
-
23
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
20 Provide Health and Safety training to all personnel and
implement H & S plan
All Sites
Contractor
Site observations
SIPMIU/ DSMC
H & S training program has been arranged by DSMC and SIPMIU
for contractors, supervisor engineers. Appendix 7 shows detail of
the training program AIDS Awareness to all the Contractors workers
taken up by Social group of consultant Health and Safety office and
Engineer from contractor arranged tool box training for labourer
and workers. Appendix 8 shows sample tool box training detail
21 Compensation for workers in case of any injury Maintaining
Occupational Health & Safety Procedure
All sites Contractor Document available SIPMIU DSMC
Workman compensation health insurance policy available for the
package. Appendix 9shows policy paper Tie up letter with nearby
health center in case of emergency received (Appendix 10) Medical
examination for workers has been done, which also enclosed in
Appendix 10. No major or minor case of medical attention is
reported during report period Availability of First aid box with
sufficient first aid materials need to be ensured at all working
sites
22 Plan truck routes to avoid city, narrow or congested roads,
important or fragile buildings, religious and tourist sites
All Sites
Contractor
Site observations
SIPMIU/ DSMC
So far all work is carried out without affecting traffic
movement. No impact on fragile building, religious places
23 Plan transport of waste to avoid peak traffic and tourist
season
All Sites Contractor Site observations SIPMIU/ DSMC
As per the state traffic law, contractor’s vehicle is
controlled
24 Suitable short term traffic diversion and implementation of
traffic management plan at construction site
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Present works haven’t encountered such issues. However, proper
plan have been implemented during laying of pipeline Particularly
road closure / diversion board
-
24
Sl. No Mitigation Activities and Method
Location Responsible for Mitigation
Monitoring method Responsible for Monitoring
Compliance status
placed Traffic management plan prepared. Appendix 11 shows
sample traffic management plan
25 Consideration of public safety - as per prescribed mitigation
measures- use of barricade, caution tape etc.
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Compliedpartially Safety caution tapes provided partially
Improvement required
26 Keep the site free from allunnecessary obstructions
All Sites
Contractor
Site observations
SIPMIU/ DSMC
All working sites planned without affecting movement of public.
Material storage sometime obstructing movement of vehicle and
public. Instruction has been given for improvement.
27 Leave spaces for access betweenmounds of soil;and Provide
walkways and metalsheets where required for people
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Access provided at working sites, but improvement is needed at
few sites.
28 Employ at least 50% of workforce from communities near
sites
All Sites
Contractor
Site observations
SIPMIU/ DSMC
This is being practice as per availability of workers willing to
work from the concern location.
29 Continuous monitoring on implementation of mitigation
measures.
All Sites
Contractor
Site observations
SIPMIU/ DSMC
Complied. Carried out under regular site inspection.
-
25
V. ENVIRONMENTAL MONITORING AND EVALUATION
24. For effective monitoring, selected environmental parameters
have been identified as indicators which will be qualitatively and
quantitatively measured and compared over a period of time in order
to assess/ensure the compliance of EMP. The environmental
performance indicators are physical, biological and social
characteristics identified as most important in affecting the
environment at critical locations all along the subproject
locations. The parameters identified as performance indicators
are:
Air, noise and water quality
Compliance to EMP
Compliance to local/state/national environmental regulations
25. During report period air quality monitoring has been
conducted for only one package(P and SN/SEW/AIZ/T2/NCB-5) under
Tranche 2. Monitoring not done for package P &
SN/WS/AIZ/T2/ICB-3. Monitoring of rest of the packages not done.
Package PS/WS/AIZ/T2/ICB-3 was terminated and for
packageSTP/SEW/AIZ/T2/NCB civil work was completed.
26. All contractors have health and safety budget for
implementation of EMP and monitoring of pollution parameters.
27. Results of air quality monitoring are shown in Table 7
below. Value of all air quality parameters are within the standard
levels. Near Chite sewage pipeline area concentration ofPM10 and
PM2.5 comparatively higher due to commercial activity and more
traffic movement near pipe laying area. Strict application of EMP
is necessary to control air pollution.
Table 7: Ambient air quality monitoring result
Package Status of Ambient Air Quality of Aizâwl
Site name/ Date of Monitoring
Air pollutants (µg/m3)
RSPM-PM10
RSPM-PM2.5
SO2 NO2 CO
CPCB standard
100
CPCB standard
60
CPCB standard
80
CPCB standard
80
CPCB standard 2
Water Supply: Feeder Mains (WS) Water distribution-107.55 Km (P
& SN/WS/AIZ/T2/ICB-3) – Tranche 2
Base camp at Khatlâ/ 03.12.2016
46.0 56.0 45.0 BDL
Chawnpui/ 03.12.2016
38.0 41.0 53.0 BDL
New Secretariat / 15.03.2017
88.0 50.0 29.0 40.0 BDL
Durtlâng/ 15.03.2017
70.0 58.0 27.0 39.0 BDL
Mission Vêng/ 15.03.2017
89.0 54.0 41.0 53.0 BDL
New Secretariat/ 22.06.2017
76.0 49.0 34.0 36.0 BDL
Bâwngkâwn/ 22.06.2017
78.0 53.0 28.0 39.0 BDL
RamtharVêng/ 22.06.2017
67.0 46.0 31.0 43.0 BDL
New Secretariat / 12-15.10.2017
89.0 53.0 32.0 41.0 BDL
Durtlâng/ 12-15.10.2017
72.0 57.0 29.0 45.0 BDL
Mission Vêng/12- 15.10.2017
88.0 55.0 44.0 57.0 BDL
-
26
Package Status of Ambient Air Quality of Aizâwl
Site name/ Date of Monitoring
Air pollutants (µg/m3)
RSPM-PM10
RSPM-PM2.5
SO2 NO2 CO
CPCB standard
100
CPCB standard
60
CPCB standard
80
CPCB standard
80
CPCB standard 2
New Secretariat /24-25.04.2018
76.0 49.0 34.0 36.0 BDL
Bâwngkâwn South / 24-25.04.2018
78.0 53.0 28.0 39.0 BDL
Ramthar North/ 24-25.04.2018
67.0 46.0 31.0 43.0 BDL
New Secretariat /12-14.12.2018
73.0 51.0 72.0 48.0 BDL
Sewerage & Sanitation: Providing ,laying, jointing &
Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE,
6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5) -
Tranche 2
Base camp Chite/03.12.2016
56.0 65.0 56.0 BDL
Electric Vêng/ 03.12.2016
46.0 56.0 45.0 BDL
Armed Vêng/ 03.12.2016
45.0 45.0 50.0 BDL
ChawnpuiVêng/ 03.12.2016
38.0 41.0 53.0 BDL
Chitê /15.03.2017
88.0 57.0 30.0 54.0 BDL
ChhingaVêng/ 15.03.2017
94.0 64.0 38.0 41.0 BDL
RamtharVêng/ 15.03.2017
67.0 54.0 25.0 40.0 BDL
Chitê /20.06.2017
107 66.0 67.0 58.0 BDL
Lower Zârkawt /20.06.2017
87.0 54.0 68.0 55.0 BDL
TuithiangVêng/ 20.06.2017
57.0 46.0 36.0 40.0 BDL
Chitê /12-15.10.2017
72.0 40.0 33.0 38.0 BDL
ChhingaVêng/ 12-15.10.2017
94.0 63.0 39.0 41.0 BDL
RamtharVêng/12- 15.10.2017
71.0 54.0 25.0 42.0 BDL
Chitê base /24-25.04.2018
107.0 65.0 67.0 57.0 BDL
Bethlehem Vengthlang / 24-25.04.2018
89.0 57.0 67.0 55.0 BDL
SaronVeng/ 24-25.04.2018
57.0 46.0 37.0 41.0 BDL
Chitê base camp /12-14.12..2018
88.0 57.0 65.0 58.0 BDL
Chitê base camp /19.06..2019*
84.0 53.0 61.0 54.0 BDL
Water Supply Dedicated Power Supply (WS)
Electric Sub- station – Dihmunzawl/
31.1 18.2 11.3 17.2 BDL
-
27
Package Status of Ambient Air Quality of Aizâwl
Site name/ Date of Monitoring
Air pollutants (µg/m3)
RSPM-PM10
RSPM-PM2.5
SO2 NO2 CO
CPCB standard
100
CPCB standard
60
CPCB standard
80
CPCB standard
80
CPCB standard 2
(PS/WS/AIZ/T2/ICB-3) 28.05.2018
Electric Sub- station – Dihmunzawl/ 23.12..2018
36.5 21.2 10.2 18.5 BDL
10 MLD Construction of Sewerage Treatment Plant (STP)
(STP/SEW/AIZ/T2/NCB-7)
Entrance of STP Bethlehem Side bridge/ 10.05.2017
69.3 26.3 BDL 8.3 -
Inside of STP/12.05.2017
58.7 18.2 BDL BDL -
IPS inside Industrial growth center/13.05.2017
64.8 21.9 BDL 8.9 -
IPS outside Industrial growth center/15.05.2017
62.4 19.7 BDL 6.2 -
STP Chite/11.11.2017
57.0 35.0 31.0 25.0 -
(Note: Shaded results marked * monitored during report
period)
28. During report period noise level monitoring has been
conducted for one (P & SN/SEW/AIZ/T2/NCB-5) package under
Tranche 2,Monitoring not done for package P &
SN/WS/AIZ/T2/ICB-3. Monitoring of rest of the packages not done.
Package PS/WS/AIZ/T2/ICB-3 was terminated and for
packageSTP/SEW/AIZ/T2/NCB civil work was completed. Instruction has
been given for bi-annual monitoring for the running projects.
29. The measured noise levels are provided in Table 8below. It
is noted from the data below that noise level during report period
is above the standard. The generation of noise is mainly due to
commercial and human activities. Control of equipment and vehicle
noise is necessary for overall minimization of the noise
level.\
Table 8: Ambient Noise Level Monitoring Data at Project Location
Sites and Surroundings
Package Monitoring Locations Noise Level in dB (A)
Leq L Max L Min Standard
Water Supply: Feeder Mains (WS) Water distribution-107.55 Km (P
& SN/WS/AIZ/T2/ICB-3) – Tranche 2
Base camp at Khatlâ/ 03.12.2016
64.9 70.2 47.1 65.0
Chawnpui/ 03.12.2016 54.90 60.4 40.0 55.0
New Secretariat / 15.03.2017
68.5 74.1 40.3 65.0
Durtlâng*/ 15.03.2017 62.56 66.0 46.1 65.0
Mission Vêng/ 15.03.2017
64.27 68.6 45.7 65.0
New Secretariat / 22.06.2017
70.29 75.0 59.0 65.0
Bâwngkâwn / 22.06.2017 64.17 69.0 55.0 65.0
-
28
Package Monitoring Locations Noise Level in dB (A)
Leq L Max L Min Standard
RamtharVêng / 22.06.2017
61.45 65.0 55.0 65.0
New Secretariat / 15.10.2017
68.50 74.10 43.3 65.0
Durtlâng/ 15.10.2017 62.56 66.0 56.1 65.0
Mission Vêng/ /15.10.2017
64.27 68.6 45.7 65.0
New Secretariat /24.04.2018
70.29 75.0 59.0 65.0
Bâwngkâwn South / 24.04.2018
64.17 69.0 55.0 65.0
Ramthar North/ 24.04.2018
61.45 65.0 55.0 65.0
New Secretariat /12-14.12.2018
62.6 68.0 59.0 65.0
Bâwngkâwn South /12-14.12.2018
63.2 69.0 55.0 65.0
Sewerage & Sanitation:Providing ,laying, jointing &
Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE,
6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5) -
Tranche 2
Base camp Chite/03.12.2016
65.30 72.0 44.1 65.0
Electric Vêng/ 03.12.2016 64.90 70.2 47.1 65.0
Armed Vêng/ 03.12.2016 57.13 61.6 41.1 65.0
ChawnpuiVêng/ 03.12.2016
54.90 60.4 40.0 55.0
Chitê /15.03.2017
59.14 62.9 39.6 65.0
ChhingaVêng/ 15.03.2017
66.57 69.0 53.4 65.0
RamtharVêng/ 15.03.2017
60.59 64.0 38.0 65.0
Chitê /20.06.2017
83.35 89.0 74.0 65.0
Lower Zârkawt /20.06.2017
69.35 75.0 58.0 65.0
TuithiangVêng/ 20.06.2017
62.24 67.0 55.0 65.0
Chitê /15.10.2017
67.90 70.2 59.4 65.0
ChhingaVêng/-15.10.2017
66.57 69.0 53.4 65.0
RamtharVêng/ 15.10.2017
70.59 68.0 45.0 65.0
Chitê base /24.04.2018
93.35 99.0 74.0 65.0
Bethlehem Vengthlang / 24.04.2018
69.35 75.0 58.0 65.0
SaronVeng/ 24.04.2018 62.24 67.0 55.0 65.0
Chitê base camp /12-14.12.2018
60.7 66.0 58.0 65.0
Ramthar North/ 12-14.12.2018
66.2 72.0 58.0 65.0
Chitê base camp 66.5 76.8 56.3 65.0
-
29
Package Monitoring Locations Noise Level in dB (A)
Leq L Max L Min Standard
/19.06..2019*
Water Supply Dedicated Power Supply (WS)
(PS/WS/AIZ/T2/ICB-3)
Electric Sub- station – Dihmunzawl/ 28.05.2018
63.4 61.7 56.3 75.0
Electric Sub- station – Dihmunzawl/ 23.12.2018*
63.4 85.7 56.3 75.0
10 MLD Construction of Sewerage Treatment Plant (STP)
(STP/SEW/AIZ/T2/NCB-7)
Entrance of STP Bethlehem Side bridge/ 10.05.2017
65.0 - - 75.0
Inside of STP/12.05.2017 60.0 - - 75.0 IPS inside Industrial
growth center/13.05.2017
52.0 - - 75.0
IPS outside Industrial growth center/15.05.2017
54.0 - - 75.0
STP Chite/11.11.2017 64.7 69.0 47.9 75.0
(Note: Shaded results marked * monitored during report
period)
30. Water quality monitoring for drinking water has been
conducted for one package P & SN/SEW/AIZ/T2/NCB-5.Testing
results are shown in Appendix 12.It is noted that parameters of
water for sewerage package locations are within the standard.
31. All air quality, noise level and water quality testing
certificates are included as Appendix 12.
32. A performance monitoring fact sheet has been prepared to
facilitate tracking and quick reference on environmental monitoring
of Tranche 2 subproject packages. (Tables 9 and 10).
-
30
Table 9: Performance Fact Sheet for Required Environmental
Consents/Clearances of NERCCDIP Aizâwl (June 2019) Tranche 2
Package Number Name of
Contractor EMP Part of
contract Document(Yes
/ No)
Environmental Consents / Clearances Required
Tree Cutting Crusher Batching Plant Hot Mix Plant
Diesel Generator Set
Pollution Under Control (PUC) Certificates for
Contractor's Vehicles
Tranche 2
1 Water Supply: Feeder
Mains (WS) Water distribution-107.55 Km (P &
SN/WS/AIZ/T2/ICB-3)
M/s Tantia Construction Ltd., Kolkata
Yes Not required till date
Not required Not required Consent to Operate obtained
Consent will be required in case of placement of generator for
the project work
Obtained fully
2 Water Supply
Dedicated Power Supply (WS) (PS/WS/AIZ/T2/ICB-3)
Work Terminated
3 Sewerage & Sanitation:
Providing ,laying, jointing & Commissioning of Sewerage
Network (SEW)-45.92 Km (37.96 Km-DWCPE, 6.09 Km-RCC & 1.58
Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5)
M/s Tantia Construction Ltd., Kolkata
Yes Not required till date
Not required Not required Consent to Operate obtained
Consent will be required in case of placement of generator for
the project work
Obtained fully
4 Sewerage & Sanitation:
10 MLD Construction of Sewerage Treatment Plant (STP)
(STP/SEW/AIZ/T2/NCB-7)
M/s Eco Protection Engineers, Chennai
Yes Tree felling done after necessary permission
Not required Not required Not required Not required No physical
work for last 6 months
-
31
Table 10: Performance Fact Sheet for EMP Implementation of
Tranche 2(June2019)
Sr. No.
Package Number Name of
Contractor
EMP Part of contract Document(Yes / No)
Contractor Environment
Person
Overall Status of EMP
Implementation
Field Monitored as per EMP
Sou
rce
of M
ater
ials
Cam
p S
ites
Land
scap
e an
d A
esth
etic
s
Air
Qua
lity
Noi
se L
evel
Tra
ffic
Eco
logi
cal R
esou
rces
–
Ter
rest
rial
Acc
essi
bilit
y
Wat
er Q
ualit
y
Occ
upat
iona
l Hea
lth &
safe
ty
Com
mun
ity H
ealth
&
safe
ty
Soc
io c
ultu
ral r
esou
rces
Em
ploy
men
t gen
erat
ion
Tranche 2
1 Water Supply: Feeder Mains (WS) Water distribution-107.55 Km
(P & SN/WS/AIZ/T2/ICB-3)
M/s Tantia Construction Ltd., Kolkata
Yes Yes
(Mr. Mayank Yadav)
Partially Complied
Approved
sources
Constructed
Maintained Not
Done Not
Done
Traffic Manageme
nt plan maintained
No tree felling required
Yes Available
Done Complied partially
Complied mostly
No impact
Yes Locals
employed
2 Water Supply Dedicated Power Supply (WS)
(PS/WS/AIZ/T2/ICB-3)
M/s EMC Ltd., Kolkata
Yes
Work Terminated.
New contractor just
mobilized
3 Sewerage & Sanitation: Providing ,laying, jointing &
Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE,
6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5)
M/s Tantia Construction Ltd., Kolkata
Yes Yes
(Mr. Mayank Yadav)
Complied Approv
ed sources
Constructed
Maintained partially
Done Done
Traffic Manageme
nt plan applied
No tree felling required
Yes Available
but improvem
ent required
Done Complied partially
Complied mostly
No impact
Yes Locals
employed
4 Sewerage & Sanitation: 10 MLD Construction of Sewerage
Treatment Plant (STP) (STP/SEW/AIZ/T2/NCB-7)
M/s Eco Protection Engineers, Chennai
Yes
Yes (Mr.
LalhminglianaHnamate)
No Work for last 6 months
-
-
32
VI. CONSULTATIONS AND DISCLOSURES CONDUCTED
33. As per approved IEE, consultations and disclosure will be a
continuous process throughout Tranche 2 implementation involving
public consultations and focus group discussions. However, there
are no “planned” consultation and disclosures conducted during the
reporting period but informal consultation done with local people,
pedestrian.
34. The indicative schedule for consultations and disclosure is
presented in Table 11.Appendix 13shows sample consultation sheet as
provided by the contractor.
35. During consultation the issues will be discussed like,
Availability of alignment
Possible short term impact- accessibility
Application of mitigation measures for control of dust and
noise
Table 11: Indicative Schedule for Consultations and Disclosure
Type of Consultation/ Disclosure
Target Date Location Target Participants
Responsible Person and Source of Funds
Local level consultation
Weekly – to be continued
At all construction locations
General public, shop keepers, pedestrian population
Construction supervisor, Environment& safety officer of
contractor, Environmental officer of SIPMIU Project budget –
continuous process
Consultation – safety issues, implementation of EMP
Quarterly – Within July to September 2019
At SIPMIU office and project site office
DSMC’s Supervisor Engineer, SIPMIU Engineer, all safety and
environment staff of contractors
Environmental specialist of DSMC and Environmental Officer of
SIPMIU
36. Review and training program on safety and environment has
been arranged for contractors, supervisors by SIPMIU’s Environment
Officer and DSMC’s Environment Specialist on regular basis.
Appendix 7 shows training details.
37. Appendix 8 indicates sample training documents (tool box
training) as submitted by contractors.
VII. GRIVANCE REDRESSAL MECHANISM
38. Grievances of APs will first be brought to the attention of
the implementing NGO or RO. Grievances not redressed within 30 days
by the NGO or RO will be brought to the grievance redress committee
(GRC), established in each State. GRCs will comprise the Investment
Program Director, RO, LAO, implementing NGO representative, female
and male AP representatives (including vulnerable households), and
an eminent member of the community. The GRC will meet every month,
determine the merit of each grievance, and resolve grievances
within a month of receiving the complaint; failing which the
grievance will be addressed by the IPEC. Further grievances will be
referred by APs to appropriate courts of law. Records will be kept
of all grievances received including: contact details of
complainant, date that the complaint
-
33
was received, nature of grievance, agreed corrective actions and
the date these were affected, and final outcome. All costs involved
in resolving grievances will be borne by the SIPMIU. The SIPMIU
through the.DSMC will keep records of all grievances received
including: contact details of complainant, date that the complaint
was received, nature of grievance, agreed corrective actions and
the date these were effected, and final outcome. The grievance
redress process is shown in Figure 4.The GRCs will continue to
function throughout the project duration.Appendix 14shows GR
registration format.There are no as such grievances registered
during report period.
Figure 4: Grievance Redress Mechanism NGO: Non- Government
Organization, DSMC: Design Supervision Management Consultant,
SIPMIU: State Investment Program Management and Implementation
Unit
STATE LEVEL
1 Minister, UD&PA Department, Mizoram Chairman Mr. Tawnluia,
Minister
2 Deputy Commissioner Convener Mr. Vanlalngaihsaka, IAS
3 Secretary, UD&PA, Govt. of Mizoram Member Dr. C.
Vanlalramsânga, IES
4 Secretary, Law and Judicial Department Member Ms. MarliVankung
MJS
5 Commissioner , Aizâwl Municipal Corporation (AMC)
Member Mr. H. Lalthlangliana MCS
6 Program Director, SIPMIU Member Er. Lalrothanga, MES
CITY LEVEL
1 Deputy Commissioner, Aizâwl Chairman Mr. Vanlalngaihsaka,
IAS
2 Program Director, SIPMIU Convener Er. Lalrothanga, MES
3 Commissioner,Aizâwl Municipal Corporation (AMC)
Member Mr. H. Lalthlangliana MCS
4 Councilor of concern ward Member Concern AMC Councilor
5 Chairman of concerned Local Council Member Concern Local
Council
-
34
Chairman
6 Chief Engineer, PHED Member Er. C. Lallunghnema
7 Chief Engineer, PWD Member Er. R. Lalrintluanga
8 Director, UD&PA Member Mr. Joseph H. Lalramsanga
9 President Central YMA Member Mr. Vanlalruata
10 President, MUP Member Mr. RK Thanga
11 President, Mizoram Consumer Union Member Mr. Thanglura
12 President, MHIP Member Mrs. Saipuii
VIII. FINDINGS, RECOMMENDATIONSAND ACTIONS PLAN
39. Protection of local environment, health andsafety of workers
engaged during construction, application of mitigation measures
started as per specified EMP. Public consultation during
construction/implementation phase is being carried out, the general
recommendations as per present observations are given below.
40. As per ADB’s safeguard policy the project authority
established a mechanism to receive and facilitate resolution of
affected persons’ concerns, complaints and grievances about the
project’s environmental performance. The grievances mechanism
should be scaled to the risks and adverse impacts of the project.
It will address- affected peoples’ concerns and complaints
promptly, using an understandable and transparent process that is
gender responsive, culturally appropriate, and readily accessible
to all the affected people at no cost and without retribution. The
affected people will be informed by appropriate mechanism.
41. Table 12 provides the recommended corrective action plan
that has been devised and target dates that have been set so as to
remove these non-compliances. The concerned Contractors have been
suitably advised.
General Effort in implementing Environmental Management Plan is
carried out by the Contractors. The present status is found
satisfactory but there is scope for improvement in the
implementation of EMP such as – workers do not always wear proper
PPE and better barricading.
Instruction to contractors and monitoring for: Proper disposal
of debris and quick disposal of
excavated/dismantling surplus earth/iron material,
Complete use of PPE, Restoration/construction of approach road
at
earliest Camp site management, Public safety arrangement,
Maintenance of access, Material storage Water sprinkling during dry
season
Table 12: Corrective Action Plan
Partial complied issues Action Required Responsible Target Date
Indicator of Compliance
1 Improvement of access at few locations for the package P &
SN/SEW/AIZ/T2/ NCB-5- Tranche 2
Immediate improvement is required
Contractor 15th July 2019
Site observation and monitoring report
2 Improper material storage for both P & SN/SEW/AIZ/T2/
NCB-5 and P & SN/WS/AIZ/T2/ICB-3
Immediate improvement is required
Contractor 15th July 2019
Site observation and monitoring report
-
35
Partial complied issues Action Required Responsible Target Date
Indicator of Compliance
packages– Tranche 2
3 Incomplete arrangement of First aid box with insufficient
first aid materials at work locations for the package P &
SN/SEW/AIZ/T2/ NCB-5- Tranche 2 and SN/WS/AIZ/T2/ICB-3 packages–
Tranche 2
Immediate arrangement is necessary
Contractor 15th July 2019
Site observation
4 Partial use of caution board and tape for both P &
SN/SEW/AIZ/T2/ NCB-5 and P & SN/WS/AIZ/T2/ICB-3 – Tranche 2
Complete use at all working locations
Contractor 15th July 2019
Site observation
5 Irregular Public consultation for both P & SN/SEW/AIZ/T2/
NCB-5 and P & SN/WS/AIZ/T2/ICB-3 packages– Tranche 2
Regular public consultation
Contractor Immediate Site observation
6 Complete Use of PPE by contractors’ site workers and complete
use of caution tape at working sites for all the packages under
Tranche 2
Immediate arrangement Contractor Immediate Site observation
-
36
Appendix 1 Photo Illustration
Water Supply: Feeder Mains (WS) Water distribution-107.55 Km (P
& SN/WS/AIZ/T2/ICB-3)
Pipe laying work at Laipuitlang. No use of PPES Road restoration
work continued. Partial use of PPEs noted
Road restoration work continued. Partial use of PPEs noted
Night work continued. Caution board and tape noted
Water supply work at Mission Veng, no use of PPEs and caution
tape
Water supply night work at Mission Veng, no use of PPEs and
caution tape
-
37
Sewerage & Sanitation:Providing ,laying, jointing &
Commissioning of Sewerage Network (SEW)-45.92 Km (37.96 Km-DWCPE,
6.09 Km-RCC & 1.58 Km-DI K7) (P & SN/SEW/AIZ/T2/ NCB-5)
Restoration of road after pipe laying at Ramthar North. Partial
use of PPEs noted
Materials should store properly at work site. Access need to
improved
Caution tape noted at pipe laying site of Ramthar North. Access
need to be maintained
Safety Tool box training for workers
Road restoration work continued. Use of PPEs noted
Road restoration work continued. Partial use of PPEs noted
Road restoration at Chhingaveng Sewage pipe laying work at
Bethlehem
-
38
Appendix 2 Monitoring Team Details
Sl.No Name Position Contact
Number Email
1 Lalrothanga Program Director, SIPMIU 0389-2390532
9436146077
[email protected]
2 F. Lalliandinga EnvironmentalOfficer, SIPMIU 8414034482
[email protected]
3 Dorothy Laldinpuii Social Development Officer, SIPMIU
9862538566 [email protected]
4 ArdhenduMitra Environmental Specialist, DSMC
9830415953 [email protected]
5 VânlalruatiZotê CommunityDevelopment Specialist, SIPMIU
8794468004 [email protected]
6 Lalhmuaka Asst. Engineer (Environment &SWM), SIPMIU
9612195925 [email protected]
7 C.Dorema Evaluation &Monitoring Expert, DSMC
9436144127 NA
8 Ignatius Zomuankima Social Safeguard & Resettlement
Expert, DSMC
9436141236 [email protected]
9 Mayank Yadav Environment &Safety Officer, Tantia
ConstructionsLtd.(Contractor)
7983452079 [email protected]
10 Lalramdina Public Relations Officer,Tantia Constructions Ltd.
(Contractor)
9485140521 [email protected]
11 LalhminglianaHnamate Environment&Safety Officer, Eco
Protection Engineers Pvt. Ltd.(Contractor)
9862860429 [email protected]
mailto:[email protected]:[email protected]
-
39
Appendix 3 Consent to Operate – Hot Mix Plant
-
40
-
41
Appendix 4 Tree Felling NOC for 132 KV Transmission Line
-
42
Appendix 5 Consent for Establishment- Sewage Treatment Plant
(Renewed)
-
43
Tree felling permission for landfill site and STP site from
Forest Dept.
-
44
Appendix 6
SAFETY RULES for WORK SITE
ALLOFOURSAFETYRULESMUSTBEOBEYED.FAILURETODOSOWILL RESULT
INSTRICTDISCIPLINARYACTIONBEING TAKEN.
1. Keepyourmindonyourworkatalltimes. Nohorseplayonthejob.
Injuryor terminationor both can be the result.
2.
Personalsafetyequipmentmustbewornasprescribedforeachjob,suchas:
safetyglassesforeyeprotection,hardhatsatalltimeswithintheconfinesof
the constructionarea wherethere isa potentialfor fallingmaterialsor
tools, gloveswhenhandlingmaterials,andsafetyshoesare necessaryfor
protection against footinjuries.
3.
Precautionsarenecessarytopreventsunburnandtoprotectagainstburns
from hot materials.
4. If any partof yourbody should come incontact withan
acidorcaustic substance,rushtothe
nearestwateravailableandflushtheaffectedpart. Secure medical aid
immediately.
5. Watch where you are walking. Don't run.
6.
Theuseofillegaldrugsoralcoholorbeingundertheinfluenceofthesameon
theprojectshallbecausefortermination. Informyoursupervisoriftaking
strongprescriptiondrugs thatwarn against drivingor
usingmachinery.
7. Donotdistracttheattentionoffellowworkers.
8. Donotengageinanyact which would endanger another
employee.
9. Sanitationfacilitieshavebeenorwillbeprovidedforyouruse.
Defacingor damagingthesefacilitiesis forbidden.
10. Agoodjob isa cleanjob,anda cleanjob isthestartofasafejob.
Sokeepyour workingarea free fromrubbish and debris.
11. Do not use a compressorto blow dust or dirtfrom your
clothes, hair,orhands.
12.
Neverworkaloftifyouareafraidtodoso,ifyouaresubjecttodizzyspells,or
if you are apt to be nervous orsick.
13. Nevermoveaninjuredpersonunlessitisabsolutelynecessary.
Furtherinjury mayresult.
Keeptheinjuredascomfortableaspossibleandutilizejobsite
first-aidequipment untilan ambulance arrives.
14. Know where firefightingequipment islocated and be trained
onhow touse it.
15. Liftcorrectly-withlegs,nottheback.
IftheloadistooheavyGETHELP, Stayfit. Controlyourweight.
Dostretchingexercises. Approximately twenty percent
ofallconstructionrelated injuries resultfrom liftingmaterials.
16. Nobodybutoperatorshallbeallowedtorideonequipmentunlessproper
seatingis provided.
17. Do not use power tools and equipment until you have been
properly instructedinthe safe work methods and become authorized
touse them.\
18. Besurethatallguardsareinplace.
Donotremove,displace,damage,or destroy anysafety device orsafeguard
furnished or provided for use onthe job, nor interfere with the use
thereof.
19. Do not enter anarea which has beenbarricaded.
20. If you must work around power shovels, trucks, and dozers,
make sure operators can always seeyou. Barricades are required
forcranes.
21. Never oil, lubricates, orfuelequipment whileit is runningor
inmotion.
-
45
22. Before servicing, repairing, or adjusting any powered tool
or piece of equipment, disconnect it, lock out the source ofpower,
and tag it out.
23. Barricade danger areas. Guard rails orperimeter cables may
be required.
24. Trenchesoverfivefeet deepmustbeshoredorslopedasrequired.
Keepoutof trenchesor cutsthathavenotbeenproperlyshoredorsloped.
25. Excavatedor
othermaterialshallnotbestorednearerthantwofeetfromtheedge ofthe
excavation. Excavationslessthan5 ftmayalsorequire
caveinprotectionin some instances.
26. Usethe"fourandone"rulewhenusingaladder.
Onefootofbaseforevery fourfeet ofheight.
27.
Portableladdersinuseshallbeequippedwithsafetyfeetunlessladderistied,
blockedorotherwisesecured. Stepladdersshallnotbeusedasastraight
ladder.
28. Ladders must extend three feet above landingon roof for
proper use.
29. Defectiveladders mustbe properlytagged and removed from
service.
30. Keep ladder bases free of debris, hoses, wires, materials,
etc.
31. Buildscaffoldsaccordingtomanufacturers'recommendations.
Scaffold planks shall be properly lapped, cleared or otherwise
secured to prevent shifting.
32. Useonlyextensioncordsofthethree-prongtype.
Usegroundfaultcircuit interrupters at all times and when using
tools in wet atmosphere (e.g. outdoors) or with any temporary power
supply. Check t h e e l e c t r i c a l groundingsystem daily.
33.
Theuseofharnesseswithsafetylineswhenworkingfromunprotectedhigh
places is mandatory. Always keep yourline as tight as possible.
34. Neverthrowanything"overboard."
Someonepassingbelowmaybeseriously injured. Open fires are
prohibited.
35.
Knowwhatemergencyprocedureshavebeenestablishedforyourjobsite.
(Locationofemergency phone,firstaidkit,stretcher
location,fireextinguisher locations, evacuationplan, etc)
36.
Neverenteramanhole,well,shaft,tunnelorotherconfinedspacewhich
couldpossibly haveanon-respirableatmospherebecauseof
lackofoxygen,or
presenceoftoxicorflammablegas,orhasapossibilityofengulfment
bysolids orliquids.
Makecertainaqualifiedpersonteststheconfinedareawithan
appropriatedetectorbeforeentry,thatthe necessarysafetyequipment is
worn. Standby personmay be required to be stationedatthe
entrance.
Procedure for Using Personal Protective Equipments (PPE):
General ConstructionWork– Basic PPE for all construction
workers
1. Safety Helmet
2. Safety Gloves
3. Safety Shoes
Headprotectionwillbewornonjobsiteswhentherearepotentialsoffalling
objects, hairentanglement, burning, or electricalhazards.
Eye protection will be worn when there are potentials of hazards
from flying objects or particles, chemicals, arcing, glare, or
dust.
Protective footwear shall be worn to protect from falling
objects, chemicals, or stepping on sharp objects. Athletic or
canvas-type shoes shall not be worn.
Protective gloves or clothing shall be worn when required to
protect against a hazard.
-
46
Harnesses and lanyards shall be utilized for fall protection as
required in the Construction Safety Standards.
Specialty PPE shall be provided to workers in addition to or
lieu of the corresponding basic
PPE as the work or activity requires as follows:
Sr. No Construction Work/Activity Specialized PPE Remarks
1
Work near unprotected areas such as but