Page 1
Environmental Monitoring Report Semestral Report January to June 2014
VIE: Power Transmission Investment Program, Tranche 2 Prepared by the Central Vietnam Power Project Management Board (CPPMB) for the National Power Transmission Corporation and the Asian Development Bank.
Page 2
NATIONAL POWER TRANSMISSION CORPORATION
CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD
SEMIANNUAL ENVIRONMENTAL MONITORING REPORT 2014
PROJECT
500KV PLEIKU-MY PHUOC-CAU BONG TRANSMISSION LINE
(POWER TRANSMISSION INVESTMENT PROGRAM - TRANCHE 2)
(LOAN 2959-VIE)
Da Nang, August 2014
Page 3
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 1/37
ACRONYMS
ADB : Asian Development Bank
AFD : Agence Française de Développement
CPMB : Central Viet Nam Power Projects Management Board
CPC : Commune People’s Committee
CSCC : Compensation and Site Clearance Committee
DPC : District People’s Committee
EVN : Viet Nam Electricity
EMP : Environmental Management Plan
F/S : Feasibility study
GOV : Government of the Socialist Republic of Vietnam
HH(s) : Household(s)
HPP : Hydropower Plant
HW(s) : Highway(s)
MONRE : Ministry of Natural Resources and Environment
NPT : National Power Transmission Corporation
PAP(s) : Project Affected Person(s)
PAH(s) : Project Affected Household(s)
PPC : Provincial People’s Committee
PECC4 : Power Engineering Consulting J.S Company 4
PECC2 : Power Engineering Consulting J.S Company 2
PO : Project Owner
Page 4
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 2/37
RP : Compensation, Allowances and Resettlement Plan
ROW : Right-of-Way
SMIC : Safeguard Monitoring Independent Consultancy
T/L(s) : Transmission Line(s)
VND : Vietnam Dong
Page 5
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 3/37
1. INTRODUCTION
1.1 Introduction of the project
1.1.1 Project background
- To implement the policy of industrialization and modernization of the country, the
Government of Vietnam has applied to ADB/AFD a loan to support the
construction of 500kV Pleiku - My Phuoc - Cau Bong transmission line, with total
length of 436, 673 km (437 km); construct 02 new optical repeaters synchronized
with the optical cable of 500kV Pleiku-My Phuoc-Cau Bong transmission line on
the territory of 05 provinces and one city, which are Gia Lai, Dak-Lak, Dak Nong,
Binh Phuoc - Binh Duong and Ho Chi Minh City . The project was prepared under
the technical assistance (PPTA) of 7742-VIE and is one part of the transmission
investment program (MFF). National Power Transmission Corporation (EVNNPT)
is the investor and Central Vietnam Power Project Management Board is
responsible for management and implementation of project.
- The benefits of the project are: Increasing the supply of reliable power for the
South of Vietnam, where the economic development is taking place rapidly,
especially the industrial zones and this is also a place accounting for 10% of the
whole country’s population.
1.1.2. Objective of the Project
- The 500kV Pleiku – My Phuoc – Cau Bong Transmission Line Project is a part of
the National Electricity Network, maintains the supply of electricity to the
development need of the South of Vietnam in the period of 2014-2015. Moreover,
the Project also ensures the connectivity of the transmission networks within
Vietnam, Laos and Cambodia to 2015.
- The Project helps to increase the reliability of power supply, reducing the risk of
electrical losses. It will also optimize capacity of power plants in order to provide
electricity continuously and safely to the sub-loading lines of the South in
particular and the whole country in general.
Page 6
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 4/37
1.1.3. Scale and scope of the Project
- The 500kV Pleiku- My Phuoc- Cau Bong Transmission Line (TL) takes place
within the boundaries of 06 provinces and one city, namely: Gia Lai, Dak Lak, Dak
Nong, Binh Phuoc, Binh Duong and Ho Chi Minh City. In particular:
+ In Gia Lai Province, the TL is 82.768km long and passes through 18 communes
which belong to 05 districts: Chu Pah, Ia Grai, Pleiku City, Chu Prong, Chu Puh;
+ In Dak Lak Province, the TL passes through 09 communes in the districts of Ea
Sup, Cu M’Gar and Buon Don with the total length of 74.841km;
+ In Dak Nong Province, there are 20 communes which the TL has gone through.
These communes belong to districts of Cu Jut, Dak Mil, Krong No, Dak Song, Tuy
Duc and Dak R’Lap. The TL in Dak Nong is 115.933km long;
+ Binh Phuoc Province has 102.892km of TL. The line passes through 15
communes in the following districts: Bu Dang, Bu Gia Map, Dong Phu and Chon
Thanh;
+ In Binh Duong Province, the TL passes through 10 communes in Ben Cat
Districts and Phu Giao Districts with the total length of 46.228km;
+ In the Cu Chi Districts of Ho Chi Minh City, the TL locates in the area of 04
communes and is 14.011km long.
500 kV Pleiku - My Phuoc - Cau Bong Transmission Line subproject has a total
length of 436.673 km. It starts from the existing Pleiku 500kV substation at Chu
Pah District in Gia Lai Province and terminate in Cau Bong substation, which is
planned to be constructed in Cu Chi District, Ho Chi Minh City. The components of
the Project include in Table 1 and the main project features are presented in Table 2.
Routes of Transmission Line are displayed in the Figures 1 and 2.
Page 7
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 5/37
Table 1: Components of the Transmission Line
Transmission Line
Components
Length
(km)
Starting point Ending
point
Number
of
Towers
Gia Lai Province
Transmission Line
Component
82.768 At 500 kV
busbar at Pleiku
500 kV
substation
G15 +
403m
173
Dak Lak Province
Transmission Line
Component
74.841 G13 (Picket
827+68)
G26
(Picket
1576+09)
163
Dak Nong Province
Transmission Line
Component
115.933 G25-G26
(Picket
1576+09)
G50-G51
(Picket
2735+42)
236
Binh Phuoc Province
Transmission Line
Component
102.892 G51 (Picket
2735+42)
G69-G70
(Picket
3764+34)
201
Binh Duong
Province
Transmission Line
Component
46.228 G70 (Picket
3764+34)
G81-G82
(Picket
4426+62)
99
HCMC
Transmission Line
Component
14.011 G81-G82
(Picket
4426+62)
At 500 kV
busbar at
Cau Bong
500kV
substation
54
Total length of TL 436.673 926
Page 8
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 6/37
Table 2: Summary of main features of 500 kV Pleiku- My Phuoc- Cau Bong
Transmission Line
Item Technical data
Length (km) 436.673 km
- Starting point At 500 kV busbar at Pleiku 500 kV substation
- End-point At 500 kV busbar at Cau Bong 500kV substation
Right of Way width 16m from either side of the centre line
Earth grounding width From 16m to within 72m from the centre line
Voltage 500 kV
Number of circuits 2
Conductor 4xACSR-330/43
Earth wire OPGW-90 & PHLOX-116
Optical repeater cable 24 fibres
Suspension towers
(number)
808
- Height Average 65m with the highest is 79m
-Area requirement/tower 337.62 m²
Tension towers (number) 118
- Height Average 60m with the highest is 72m
- Area requirement/tower 653.4 m²
Page 9
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 7/37
Figure 1: Location of the Pleiku - My Phuoc - Cau Bong 500 kV transmission line and
surrounding areas
Page 10
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 8/37
Figure 2: Transmission line and other closed places
National Parks National Reserves Cultural-Historic
500kv Pleiku-My Phuoc-Cau Bong
Water – flooded land
Page 11
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 9/37
1.1.4 Project Construction Progress
The project started from October 23, 2011 and was finished and put into operation on
May 05, 2014 with the warranty period of 24 months.
The construction progress updated until May 21, 2014 is as follows:
- Foundation digging: 926/926 position
- Foundation casting: 926/926 position
- Tower erection: 926/926
- Stringing conductors: 445.043 km /445.043 km
The construction packages and implementation progress are presented in Table 3
Table 3: The Project’s construction packages implementation progress
Page 12
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 11/37
Packages Constructors Length (km) Position
No.
Foundation
casting
Tower
erections
String
conductors
% of String
conductors
ĐĐ-G6 and OHL
feeder
Power Construction Company
Ltd No.4 27.244 58 58 58 27.244 100%
500kV Pleiku OHL feeder Acceptanced and energized on April 21, 2014
Pac. 02 (G6-G13) Vietnam Electricity Construction
Company 67.044 142 142 142 67.044 100%
Pac. 03 (G13-G17) Vietnam Electricity Construction
Company
Pac. 04 (G17-G21) Joint Venture of Power
Construction Company Ltd No.4
and Viet Trung Joint Stock
Company
26.506 56 56 56 26.506 100%
Pac. 05 (G21-G24)
Joint Venture of Viet A
Investment Commercial
Industrial Company and Dien
Dia Phuong Ltd Co.
20.803 46 46 46 20.803 100%
Buon Đon optical repeater
station Completed
Page 13
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 12/37
Pac. 06 (G24-G30) INCO Company 24.868 53 53 53 24.868 100%
Pac. 07 (G30-G36) Joint venture of Installation of
Machines and Electricity Joint
Stock Company and Electricity
and Construction Joint Stock
Company.
28.142 58 58 58 28.142 100%
Pac. 08 (G36-G45C) Joint Venture of Power
Construction Company Ltd
No.4, Alphanam Joint Stock
Company and Song Da 12 Joint
Stock Company
36.184 73 73 73 36.184 100%
Pac. 09 (G45C-G49) Song Da 11 Joint Stock
Company 26.981 52 52 52 26.981 100%
Pac. 10 (G49-G52) Song Da 11 Joint Stock
Company 28.359 58 58 58 28.359 100%
Pac. 11 (G52-G60)
Song Da 11-Thang Long Joint
stock Company 30.652 60 60 60 30.652 100%
Bu Dang optical repeater station Completed
Pac. 12 (G60-G64) Song Da 11-Thang Long Joint
stock Company 32.785 63 63 63 32.785 100%
Page 14
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 13/37
Pac. 13 (G64-G71) Power Construction Joint Stock
Company No.1 38.550 77 77 77 38.550 100%
Pac. 14 (G71-G79) Joint Venture of Power
Construction Joint Stock
Company No.1 and Thang Long
Joint Stock Company
30.566 64 64 64 30.566 100%
Pac.15 (G79-G85)
- Section of 110kV
Power Construction Company
Ltd No.2 14.422 39 39 39 14.422 100%
Pac. 16 (G85-ĐC and
OHL feeder) Power Construction Company
Ltd No.2
11.937 27 27 27 11.937 100%
Cau Bong OHL
feeder Completed
Total: 445.043 926 926 926 445.043 100%
Page 15
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 14/37
1.2 Purpose of the report:
In order to comply with AFD/ADB’s requirements on environment safeguards, EVNNPT-
CPMB is requested to prepare the semiannual environmental monitoring reports. These
reports are considered as an important and necessary part to evaluate the AFD/ADB’s
safeguard compliance of EVNNPT-CPMB.
This report presents environmental compliance, the need and method to environmental
inspection and management, environment aspects to be monitored of the 500kV Pleiku-My
Phuoc-Cau Bong transmission line subproject during the period from January 2014 to July
2014.
2. INCORPORATION OF ENVIRONMENTAL REQUIREMENTS INTO PROJECT
CONTRACTUAL ARRANGEMENTS
The civil works contracts have included the environment management work which must be
performed by contractors as per EVNNPT requirements. In order to ensure that the IEE
approved by ADB shall be fully and strictly complied by the contractors, CPMB has sent
the EMP and draft of CEMP (both Vietnamese and English versions) to contractors. In
addition, to monitor environmental compliance of contractors, CPMB has also sent official
letters to contractors requesting for implementation of the EMP, CEMP and other related
works. On that basis, the contractors have prepared CEMP for their units and strictly follow
the requirements of CPMB to meet the requirements in accordance with ADB's guidelines
on Environmental Management Plan (EMP).
The implemementation of EMP of contractors shall be supervised and monitored as an
intergral part of civil works contracts. Besides, the EMP has also been sent to supervising
units such as PTC3 (Power Transmission Company No.3) and PTC4 (Power Transmission
Company No.4) and related departments of EVNNPT-CPMB to supervise the
implementation of contractors.
3. SUMMARY OF ENVIRONMENTAL MITIGATIONS MEASURES REQUESTED
IN EMP.
Page 16
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 15/37
Table 4: Summary on the impacts and mitigation measures listed in the EMP
Impacts Proposed mitigation measures
CONSTRUCTION PHASE
Noise and vibration i. If particularly noisy activities are required work may need to be limited to daylight hours.
Dust management
When dust is carried towards residential areas or becomes problematic on-site, the contractor is to
apply dust control measures such as:
Materials have to be fully covered to prevent emissions to the atmosphere.
Spraying water on the area where there is dust. Watering the road of transportation when the weather
is dry.
Prevention of soil erosion on
construction site.
i. Apply soil conservation and erosion protection technologies.
ii. Avoid operating machinery in adverse ground conditions.
iii. Protect and revegetate newly excavated areas as soon as possible
Storage and handling of:
fuel and lubricants
i. Storage areas to be prepared to avoid deterioration of materials.
ii. All fuel storage areas to be security fenced and provided with oil and water separators. Fuel hoses
Page 17
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 16/37
Impacts Proposed mitigation measures
and shut off valve to be locked.
iii. All refueling to be done at least 20 m away from waterways by trained personnel.
iv. All waste oil and oil filters to be collected and if possible recycled, otherwise to be disposed
of to landfills.
v. The contractor is to train refueling personnel in these procedures.
vi. The contractor is to have developed an accidental spill handling action plan.
Public access to site
i. Erect warning signs and barriers around work areas.
ii. Site can only be accessed with permission of contractor.
iii. Visitors to be inducted to site with an explanation of the site hazards that may be experienced.
Community Safety from
increased vehicle movements
i. All vehicles to be properly maintained and operated in accordance with road laws.
ii. All loads to be properly secured and fugitive loads to be covered.
iii. Drivers to be fired if ignore safety requirements.
i. Use of hazardous materials
and
ii. Prohibited activities
i. Contractor to provide list of all HAZCHEM products to be used on site
ii. List verified against HAZCHEM.
Page 18
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 17/37
Impacts Proposed mitigation measures
Workplace health and safety
Contractor to abide by: Vietnamese Labour Code as amended 2002. Workers to be provided with
safe working environment including:
i. Erect warning signs and barriers around work areas
ii. No drugs or alcohol allowed on-site
iii. Noise and dust to be controlled.
iv. All workers provided with safety equipment appropriate for the task in which they are
employed.
v. To be supplied on-site for workers:
Potable water, chemical toilet, changing place with clothes storage, and washing and showering
facilities.
vi. Work Statements prepared for each activity
vii. Prior to entering site for first time workers to be inducted to site and site hazards explained
together with explanation of work site safety procedures.
ix. Medical and first aid facilities provided together with a person qualified in first aid.
Worker issues (i): Hiring of
Page 19
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 18/37
Impacts Proposed mitigation measures
workers and HIV/AIDS issues.
Contractor to implement HIV/AIDS awareness program.
Worker issues (ii): Location of
camps and employment of local
labour
i. Local communities to be preferentially offered employment for unskilled work.
ii. Camps to be sited to avoid social conflicts.
iii. Each camp should have a solid waste disposal site and a soakage pit to pre-treat camp wastewater
Worker issues (iii): Provision of
adequate living conditions within
campsite.
Camp conditions to meet Labour Law requirements. Provide:
i. adequate shelter
ii. potable water
iii. Sanitation and washing facilities
iv. Kitchen with adequate cooking facilities
v. Nutritionally adequate food rations
Worker issues (iv):
Camp water heating and
cooking. Use of fuel wood.
PREFERENTIALLY
i. the contractor will provide gas and kerosene for water heating and cooking.
ii. Locate camp away from significant forest areas, and: limit collection and use of fuel-wood.
Page 20
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 19/37
Impacts Proposed mitigation measures
Worker issues (v):
Hunting and sale of wildlife by
workers
i. Labour employment agreement enforced by contractor that bans hunting and trading in wildlife
by workers.
ii. Labour who disregards this requirement are handed over to Forest Protection Department for
prosecution and immediately dismissed. Contractor is to provide nutritionally adequate camp
rations.
Disposal of site waste
All waste materials to be collected and sorted; (i) those that can be recycled and (ii) those that need to
go to an approved landfill site for disposal.
Chance discovery of
archaeological and cultural sites
No known sites. Chance discoveries are to be notified to the SE who will advise the EO. EO to
advice on procedure for dealing with chance discoveries.
Clearance and rehabilitation of
construction sites and removal of
contractor’s facilities.
i. All solid waste to be removed from sites and disposed in approved landfills.
ii. All contaminated soil to be removed.
iii. All sites to be rehabilitated and restored to original condition.
iv. Drainage to be re-established.
v. To be included as part of Final Inspection before payment made.
Page 21
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 20/37
Impacts Proposed mitigation measures
OPERATION PHASE
Unsafe operation of transmission
line.
i. Vegetation cut and controlled to safe operating limits.
ii. Use hand labour
i. Unsafe habitation within RoW
ii. Unsafe operation of
transmission line.
i. All buildings kept out of 32 m RoW
ii. All buildings outside 16m RoW width from centreline to 72 m earthed.
Page 22
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 21/37
4. ENVIRONMENT COMPLIANCE INSPECTION AND
MANAGEMENT.
4.1 Environment compliance inspection
4.1.1 EMP implementation inspection of CPMB and related parties:
- Monitoring and compliance with the environmental management plan of
CPMB and the related parties are implemented according to the organization
structure and method of environmental management system shown in Figure 3. The
information on labor safety and environmental sanitation has been quickly reflected
to PMU, concurrently the duties of parties: PMU –construction monitoring unit –
contractors – local authorities have been determined clearly and closely.
Figure 3: Organization structure of environmental management system
- In order to effectively implement the tasks of environmental management,
CPMB and other units involved in environmental monitoring system
Contractors
PMU (CPMB)
Construction monitoring units (PTC3 & PTC4)
Construction monitoring engineers of contractors
Local authorities
Page 23
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 22/37
(contractors, local authorities, construction monitoring units: PTC3, PTC4 ...)
have to conduct their specific environmental management tasks; to monitor the
environmental impacts caused by project construction activities and other
related activities and ensured that the EMP has been followed during
construction of the project.
- Almost all of mitigation measures presented in the Contractor Environmental
Management Plan (CEMP) were performed relatively well under the
supervision of the power transmission companies (PTC3, 4) as well as the
staffs in charge of CPMB.
- The semiannual environment monitoring reports were prepared by CPMB
and submitted to ADB/AFD for review in August 2013, February 2014 and
August 2014.
- On August 27-29, 2013, CPMB and ADB consultants conducted site visit in
the area of Cu Chi and Binh Duong to check the compliance with the projects’s
environmental management plan.
- On the basis of submitted reports and the situation found in the site visit,
ADB had no objection letter dated September 03, 2013, which recognized the
compliance of the project on ADB’s environment, resettlement and ethnic
minority safeguards.
- From December 05-07, 2013, CPMB and ADB/AFD have conducted site
visits at some places of the project as Tan Thanh Dong commune, Cu Chi
district, Ho Chi Minh City; Lai Hung commune, Ben Cat district and Tan Long
commune, Phu Giao district of Binh Duong province.
- From April 01-04, 2014, CPMB and ADB have conducted site visit at some
places of the project belonging to Gia Lai and Dak Lak provinces (such as
Nghia Hoa commune of Chu Pah district, Gia Lai province; Tan Hoa commune
of Buon Don district, Dak Lak province; Tan Thanh Dong commune of Cu Chi
district, Ho Chi Minh city) to check the compliance with the EMP, social
safeguards and the issues of reforestation for the project.
Page 24
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 23/37
- CPMB evaluates the effectiveness of the implementation of mitigation
measures conducted by contractors during the construction period, based on
environmental compliance reports and the Minutes of environmental
compliance monitoring of contractors, and actual situation of environmental
management under the supervision of Power Transmission Companies, the
engineers who have supervised project construction of CPMB as well as local
authorities in the project area.
- CPMB has always monitored, supervised and urge prompted the contractors
to strictly implement of environmental management in accordance with
regulations.
4.1.2 Environment compliance inspection for Contractors:
- On the basis of CEMP and civil work contracts, the contractors have strictly
performed environmental management plan in accordance with the ADB's
guidelines and requirements of EVNNPT/CPMB.
- The contractors cooperate with CPMB and local authorities to disclose
information about the project construction activities to the local people and
deal with the local authorities, local people to work together to implement
CEMP well.
- Contractors assign environment experts to address the environment
information to workers and implement the mitigation measures during the
project duration.
- The contractors are willing to solve shortcomings arising during construction
after each inspection of the CPMB staff who are in charge of compliance with
the environmental management plan of the contractors.
- Contractors attended the meetings and give out solutions to shortcomings as
per CPMB’s request.
Page 25
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 24/37
- Contractors have set up criteria to implement the mitigation actions, which
are stated in the CEMP and report the compliance in the format guided by
ADB enclosed with Certified Minutes under the monitoring of CPMB.
- The contractors integrate, complete and submit reports to the CPMB before
the 25th date of each month. The report and the written certification complied
with ADB guidelines form and the content of the approved EMP. The reports
focus on the impacts incurred during the construction process and the
mitigation measures implemented by contractors that are summaried in table 5
below.
Table 5. Summary of the project environmental impacts and mitigation measures
conducted by contractors.
Impacts Mitigation measures taken by contractors Note
Dust and waste
There has been a person who regularly
checked the transportation vehicles,
equipment to handle the problem of air
pollution. Materials have been fully covered
to prevent emissions to the atmosphere.
The trucks moving materials have been
fully covered to ensure no pollution to the
air environment.
Reduced of vehicle traffic on roads
Sprayed water on the area where there is
dust. Watering the road of transportation
when the weather is dry.
Certified by Minutes *
Noise and
vibration
The construction activities have took place
during the day.
Used equipment with small capacity and
not so regularly, therefore the noise did not
affect the residential area and could be
acceptable.
The equipment, tools, machinery met
registered standards.
Complied with national technical regulation
on noise.
Page 26
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 25/37
Impacts Mitigation measures taken by contractors Note
Water waste of
construction
Collected and transported waste to the place
in accordance with local regulations.
Cement bags were collected and reused.
Excavated soil was used to backfill the pit
after construction.
Water waste was not discharged directly
into rivers, lakes around.
Arranged ditch surrounding the foundation
to collect water to a hole to reduce turbidity
before water is discharged into the pit
around.
Minimized the oil spillage of construction
machinery outside the site.
Soil erosion on
construction
site.
Restricted excavation expand, reduced soil
erosion potential.
Applied the land protection method at the
area where there is erosion.
Avoided using machinery to dig up the soil
in the humid conditions.
Excavation area was leveled soon after
completion of the work.
Protected new foundation immediately after
completion.
Grassed and embankment at the place
where it is easily eroded.
Solid waste
All construction waste materials including steel and wood
trim, sand, gravel, cement bags etc. ... were collected and
classified for reuse if possible, or treated at a regulated
place.
Page 27
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 26/37
Impacts Mitigation measures taken by contractors Note
Storage and
handling of
construction
materials
Storage areas have been prepared and
protected by security fences, locked
protection.
Fuel were stored in properly sealed
containers; regularly checked so that the
fuel does not flow into the environment.
All the filling of fuels were done at least a
distance of 20 m from the river, streams,
ponds and lakes and it was carried out by
trained personnel. Oil waste was collected
and treated as per regulations.
Developed training for the troubleshooting
process and explosives for employees to
handle problems related to fire and
explosion.
Community
Safety from
increased
vehicle
movements
All vehicles were properly maintained and
operated in accordance with road laws.
Used the transportation vehicles suitable
with the road
Drivers to be fined if ignore safety
requirements.
Erected warning signs at the dangerous
places or at the crossing place with the
traffic road.
Workplace
health and
safety
Erected warning signs and barriers around
work areas
There is no drug or wine at the site.
Dust and noise were controlled.
All the workers were provided with
protection equipment which is suitable for
their work.
All workers were provided with: clean
water, toilets, protection clothes and area
for bathing.
Before accessing the site for the first time,
Page 28
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 27/37
Impacts Mitigation measures taken by contractors Note
workers were introduced about the
dangerous places and were guided with
safety procedures at workplace.
There has been medicine cubicle at the site
for first aid.
Clearance and
rehabilitation of
construction
sites and
removal of
contractor’s
facilities.
All solid waste was removed from sites and
disposed in approved landfills.
All contaminated soil was removed.
Sites have been rehabilitated and restored to
original condition. There is the witness of
local authorities when returning of site.
Drainage were re-established as the original
condition
Public access to
site
Erected warning signs and barriers around
work areas.
Site could only be accessed with
permission of
contractors.
Visitors to site were explained site hazards
that may be experienced.
Worker’s health
and community
Enhanced awareness of workers about the
social evils. Implemented the preventive
measures against HIV / AIDS.
Provided adequate living conditions in the
camp area, to ensure hygiene for drinking
water and cooking.
Regional camps are located in high places,
dry, non-humid
Provided protective equipment for workers
and required workers to use while working.
Provided first aid facilities, medicines for
workers.
Cleaned the worker camps.
Page 29
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 28/37
Impacts Mitigation measures taken by contractors Note
Strictly prohibited hunting and trading of
wild animals
ev
* Certified Minutes: Environmental Compliance Monitoring Minutes of were certified by the
construction monitoring engineers of CPMB or PTC3, 4. The mitigations implemented by the
contractors have supervised and stated results in the Minutes. Most of mitigations were
evaluated according to effectiveness rating criteria to be good.
In order to effectively implement the tasks of environmental management, the CPMB
and other units involved in environmental monitoring system (construction monitoring
engineers; local government, PTC3, PTC4 ...) have supervised the above mentioned
activities of the contractors as well as other related activities of the project to ensure
that the EMP are followed during the construction and operation of the project.
4.2 Environment Management:
4.2.1. Environment Management performed by CPMB
1. Environment management is well performed by CPMB before and during the
project implementation.
2. All the conditions and requirements on the environment management which
must be performed by parties are strictly set forth by CPMB.
3. The implementation of the monitoring of environmental management in
accordance with EVNNPT’s requirement as well as the requirements of security,
public order and safety, fire prevention, environmental sanitation in particular
has been incorporated in the civil works contracts of the project and CPMB
follow up the implementation of the contractors.
4. To operate better environmental management system for the project, CPMB
dispatched officials who are responsible for environment to receive monthly
information, as a bridge between the CPMB and the unit related to timely
resolve issues of environmental safety.
Page 30
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 29/37
5. CPMB has prepared the monitoring criteria in Enviromental compliance Report
and Enviromental compliance monitoring Minutes, which were sent to the
contractors for implementation.
6. There is always technical expert of CPMB who is at site and urge the
contractors to comply the mitigation measures set forth in EMP during the
construction.
7. The meeting attended by the Contractor, Consultant and representative of
CPMB is maintained weekly under the chairmanship of the CPMB. Besides
meeting unexpected mechanism addressing the urgent issues is also proposed
depending of the actual conditions of the site.
8. Ready and full-participation meetings, training, seminars ... on the environment
management organized by ADB, absorb and overcome the deficiencies and
shortcomings.
4.2.2. Environment Management performed by constrution monitoring companies
Apart from monitoring the construction, monitoring companies (PTC3, PTC4)
are frequently at site and requesting contractors to fully prepared legal
formalities on the environment safety.
4.2.3. Environment Management performed by contractors
Contractors assign their experts to the site and monitor all the environment
issues, including: Supervision of contractors (CSE), Environmental Officer and
health safety (EHS), Community Expert Consultation (CLO). These staffs are
responsible for implementing and monitoring the implementation of CEMP,
responsible for monitoring compliance with the EMP, the health and safety
issues as a liaison between the local community and the contractors. Based on
approved EMP, the contractors take actions to minimize environmental impacts,
evaluate and report to CPMB to receive support information from the CPMB
and construction monitoring companies in the implementation of environmental
management at site.
Page 31
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 30/37
4.2.4. Participations of related parties at local in enviromental management
1. Local authorities at the place where the transmission line passes by also assign
some experts to cooperate with CPMB and contractors to address the project
activities to local people. Besides, supporting the contractors in compensation
for land, assets...affected when the contractors hire the area surrounding the
foundation, storage of construction materials...
2. PPC of communes/districts where the transmission line passes by requests
contractors to return the surface of the roads, where contractors use to transport
the construction materials, to the original condition after contractors complete
the construction of each item.
3. The participation of community during the project implementation is also highly
paid attention.
4.3 Mitigation compliance in operation phase
1. The expected adverse impacts during the operational phase of the 500kV
Pleiku- My Phuoc- Cau Bong transmission line are generally related to the
occupational and community health and safety issues. The impacts are
reversible, manageable, and can be mitigated with oper engineering and
management controls. Operations management units (PTC3 and PTC4) will be
responsible for the operation of the 500kV transmission line and its ancillary
services.
2. The actual survey on site along to 500kV Pleiku- My Phuoc- Cau Bong
transmission line, shows that the operating units has complied with the EMP
and well controlled the environmental safety measures during the period from
the start of the operation so far.
3. In addition, the exchange of information with the operations management units,
local authorities and the communities in the project area on the implementation
of the environment safety measures shows that the coordination between the
management and operation unit with the relevant departments and locals is well
done.
Page 32
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 31/37
4.4 Mitigation effectiveness
1. The environment monitoring has showed that most of mitigation measures in
CEMP are strictly performed under the monitoring of transmission companies,
CPMB and the experts of contractors. Criteria to implement the mitigation
measures were set up as per ADB’s instructions in EMP, which were stated in
CEMP and monthly environmental compliance reports of the contractors to
ensure that the EMP are followed during the construction.
2. In order to evaluate how the contractors have used the mitigation measures in
EMP, CPMB has refered to the Minutes of checking and compliance reports
stated above of the contractors, which are submitted to CPMB every month as
well as to check at site. It can be seen from these reports that mitigation
measures have been used quite well by the contractors such as: hanging alarm
signs at site, limit the noise, dust for the residential areas, limit the erosion, land
slide, mitigate the impacts on the water, mitigate the damages caused by trees
cutting, impacts to the agricultual land, manage the waste during the
construction; collect and storage the construction materials, restore the traffic
roads …The effectiveness of each contractors in the implementation mitigation
measures are summarized in Table 6 below:
Table 6: The summary of effectiveness of each contractor in mitigation
compliance during the construction:
Packages Contractors
Effectiveness
Evaluation
ĐĐ-G6 and OHL feeder Power Construction Company Ltd
No.4
Good
Pac. 02 (G6-G13)& Pac. 03
(G13-G17)
Vietnam Electricity Construction
Company
Good
Page 33
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 32/37
Pac. 04 (G17-G21) Joint Venture of Power Construction
Company Ltd No.4 and Viet Trung
Joint Stock Company
Good
Pac. 05 (G21-G24)
Joint Venture of Viet A Investment
Commercial Industrial Company and
Dien Dia Phuong Ltd Co.
Fair
Pac. 06 (G24-G30) INCO Company Fair
Pac. 07 (G30-G36) Joint venture of Installation of
Machines and Electricity Joint Stock
Company and Electricity and
Construction Joint Stock Company.
Good
Pac. 08 (G36-G45C) Joint Venture of Power Construction
Company Ltd No.4, Alphanam Joint
Stock Company and Song Da 12 Joint
Stock Company
Good
Pac. 09 (G45C-G49)& Pac. 10
(G49-G52)
Song Da 11 Joint Stock Company Good
Pac. 11 (G52-G60)& Pac. 12
(G60-G64)
Song Da 11-Thang Long Joint stock
Company Good
Pac. 13 (G64-G71) Power Construction Joint Stock
Company No.1 Good
Pac. 14 (G71-G79) Joint Venture of Power Construction
Joint Stock Company No.1 and Thang
Long Joint Stock Company
Good
Pac.15 (G79-G85)
- Section of 110kV & Pac. 16
G85-ĐC and OHL feeder)
Power Construction Company Ltd
No.2
Fair
5. Status of reforestation activities:
5.1. In Dak Lak province:
Page 34
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 33/37
a/ Affected forest square: 107,11ha
b/ Compensation result:
• Compensated forest square: 107,11ha
• Compensated forest cost: 10.816.764.158 VND, was transferred according to
Decision No. 485/ QĐ-UBND dated 07/03/2014 of the People Committee of
Dak Lak Province.
• Compensatory reforestation plan: is being appraising, after the People
Committee of Dak Lak Province approves, CPMB will transfer the approved
amount to Forest Protection and Development Fund of Dak Lak province.
c/ The reforestation to now: not yet performed
• Place for reforestation: At plots 4,5/group 262, plots 2,4,7/subdivision 264 of
Ea Lê commune, Ea Sup district and plots 3,6,7/subdivision 546, plots
5,6/subdivision 556 of Ea Kiet commune, Cư Mgar district.
• Square of reforestation: 107,11 ha.
• Time for reforestation: not yet performed
• Company who will be in charge of reforestation: Chu Ma Lanh Forestry
Company Limited in Ea Sup district, Dak Lak province and Buon Ja Wam
Company Limited at M'gar district, Dak Lak province.
5.2. In Gia Lai province:
a/ Affected forest square: 28,7 ha
b/ Compensation result: Department of Agricultural and Rural Development is
submitting the cost for compensated forest to People Committee of Gia Lai Province
for approval.
• Compensated forest square: 28,7 ha
Page 35
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 34/37
• Department of Agricultural and Rural Development is submitting the cost for
compensated forest to People Committee of Gia Lai Province: 2.628.822.420
VND
• Payment: Not yet been made. After People Committee of Gia Lai Province
approves, CPMB will transfer this amount to Forest Protection and
Development Fund of Gia Lai province
c/ The reforestation to now: not yet performed
• Place for reforestation: at plot 6/subdivision 229, Hoa Phu commune, Chu Pah
district, Gia Lai province.
• Square of reforestation: 28,7 ha.
• Time for reforestation: not yet performed
• Company who will be in charge of reforestation: Forest Protection Management
Unit of North Sea Lake, Gia Lai province.
6. CONCLUSION
Through the process of evaluation, management and monitoring the
construction of project, CPMB found that most of the contractors were relatively in
good compliance with the approved EMP. The problems exist in the construction
period to the present time have been overcame. CPMB and all related parties will
continue to troubleshoot if having any problems during the warranty period of the
project.
During construction and operation phase of 500kV Pleiku- My Phuoc- Cau
Bong transmission line, all the related stakeholders have complied with the EMP,
followed the progress plan and ensured the work quality and safety, which has
minimized the environmental impacts to people life in the project area.
The 500 kV Pleiku - My Phuoc - Cau Bong transmission line has been accepted
and put into operation since May 05, 2014. CPMB has transferred the project for
Page 36
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 35/37
Power Transmission Company 3 and 4 (PTC3 &PTC4) to directly manage and operate.
These units are responsible for regularly checking each item in the warranty period (24
months since starting the operation) for the timely detection and report to the project
owner to take solutions and enable the work going to stable and sustainable operation
in the future.
Initially, the monthly operation and maintenance of the Operation and
Management Units have been strictly implemented and complied with the
Government’s regulations on the high-voltage safety as well as other legal documents
of the electricity industry.
Through the construction of 500 kV Pleiku - My Phuoc - Cau Bong
transmission line, under ADB’s guideline and the implementation of the project
environmental management plan, CPMB and the units involved have learned out a
lesson for future similar projects to be organized more well and thoroughly.
Page 37
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 36/37
Figure 2: The local people have planted cassava inside the ROW of 500kV Pleiku- My
Phuoc- Cau Bong transmission line in Binh Phuoc Province.
Page 38
Enviromental Compliance Report, 500kV Pleiku‐ My Phuoc‐ Cau Bong TL, Tranche 2, MFF 37/37
Figure 3: Cassavas are growing very well