Top Banner
1 MINISTRY OF INDUSTRY AND TRADE THE WORLD BANK RENEWABLE ENERGY DEVELOPMENT PROGRAM Credit code: IDA Cr.4564-VN ENVIRONMENTAL MANAGEMENT PLAN TRUNG THU SMALL HYDRO POWER PROJECT DIEN BIEN PROVINCE Trung Thu Hydro Power Joint Stock Company Dien Bien, October 2014 E2041 V11 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
124

ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

Apr 26, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

1

MINISTRY OF INDUSTRY AND TRADE THE WORLD BANK

RENEWABLE ENERGY DEVELOPMENT PROGRAM

Credit code: IDA Cr.4564-VN

ENVIRONMENTAL MANAGEMENT PLAN

TRUNG THU SMALL HYDRO POWER PROJECT

DIEN BIEN PROVINCE

Trung Thu Hydro Power Joint Stock Company

Dien Bien, October 2014

E2041 V11 P

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

ed

Page 2: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

2

ABBREVIATIONS

BIDV Bank for Investment and Development of Vietnam

DARD Department of Agriculture and Rural Development

DOIT Department of Industry and Trade

DCST Department of Cultural Sport and Tourism

DSP Dam Safety Panel

EMP Environmental Management Plan

EPC Environmental Protection Commitment

REDP Renewable Energy Development Project

ESF Environmental safeguard framework

MSDS Material safety data sheet

PPC Province People’s Committee

PMU Project Management Unit

SHP Small hydropower project

Page 3: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

3

TABLE OF CONTENTS

Page

Screening of safeguard policies for subproject under REDP

1. Introduction

1.1. Project Background

1.2 Subproject Donor

1.3 Project objectives

1.4 Project management and EMP implementation

2. Project description

2.1. Location of project

2.2 Project description

2.3. Constructed management

3. Legal and technical basis to implementation of EMP

3.1. Legal and technical documents

3.2. Technical filamentous applied in EMP

4. Environmental and social issues

4.1. Key environmental issues

4.2. Key social issues

5. Impact mitigation plan

6. Environmental monitoring plan

7. Environmental complaint and penalization

8. Environmental management capacity building plan

9. Estimated cost for environmental management plan

10. Public consultation and disclosure

List of reference documents

List of people who met in the process of EMP preparation

Annex 1. List of persons prepared EMP

Annex 2. Responsibilities of environmental supervision staff during EMP implementation

Annex 3. The approval document on EPC

Annex 4. Minute of meeting of public consultation

Annex 5. Permission of providing land for project construction

Annex 6. On-site pictures

Page 4: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

4

SCREENING OF SAFEGUAR POLICIES

FOR SUBPROJECT UNDER REDP

TABLE A: TRUNG THU HYDRO POWER PROJECT SCOPING CHECKLIST

ISSUE

RELEVANT?

OUTCOME

Is the subproject located in or near a national

park or other government designated

protected area?

No

If a dam, is the subproject more than 15 m in

height ? Yes

DSP has reviewed

If a dam, is the subproject 3 million cubic

meters in capacity? Yes

DSP has reviewed

Will the subproject result in change of land

use and resettlement of affected people?

Yes

Agricultural land

has been acquired

for project. There is

not any household in

project area so

resettlement plan

has not been made.

Compensation plan

has been made.

Do ethnic minorities live or use the area

affected by the project? Yes

Ethnic plan has been

made.

Will the subproject affect physical or cultural

resources that may be significant? No

Is the subproject situated on or near to an

international waterway? Yes

Trung Thu SHPP is to

be located on Nam

Muc river, an

international river

originated from

Phong Sa Ly province

of Lao. Nam Muc

river is also a

tributary to Da river

which originates from

Van Nam province of

China. Trung Thu

SHPP is located down

steam of Nam Muc

Hydropower plant.

Therefore, the

international water

way of WB (OP/BP

Page 5: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

5

ISSUE

RELEVANT?

OUTCOME

7.05) is applied for

this project.

Has an EIA/EPC been completed?

Yes

EIA was approved by

Dien Bien PPC by

Decision No.

263/QĐ-UBND dated

21/04/2014.

Have all Approvals from Dien Bien

Province’s People’s Committee been

obtained?

Yes

Has public consultation of those people

potentially affected by the subproject been

undertaken?

Yes

Consultation meetings

were held by

developer with

participants from

representatives of

affected households

and local authorities

of Trung Thu, Sinh

Phinh, Muong Bang

communes, Tua Chua

district and Sa Tong,

Pa Ham, Nam Nen

communes, Muong

Cha district, Dien

Bien province.

Has an environmental management plan

been completed? Yes

Will the subproject affect downstream flows,

ecology and those living downstream? Yes

Consideration was

taken during

preparation of EMP

Have construction impacts been fully

mitigated? Yes

Consideration was

taken during

preparation of EMP

Will the subproject result in construction of

new access roads and how will access be

managed?

Yes

Consideration was

taken during

preparation of EMP

Page 6: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

6

TABLE B: TRUNG THU HYDRO POWER PROJECT

PRESCREENING DOCUMENT CHECKLIST

DOCUMENT

INCLUDED?

Feasibility Study Yes

Approved EIA Yes

Environmental Management Plan Yes

Compensation Plan Yes

Ethnic Minority Plan Yes

Approvals from Dien Bien PPC Yes

Dam safety review by Dam Safety Panel Yes

Other approvals: if required

TABLE C. SCREENING OF WB’S SAFEGUARD POLICIES

Environmental Assessment (OP/BP 4.01): potential environmental impacts of the

subproject includes those relevant to land acquisition, vegetation cover loss, impact

to terrestrial ecosystem, air pollution by dust, exhaust gases, noise from

construction activities, impact of surface water quality, water usage in downstream,

aquatic bio-diversity as well as impact of landslide, erosion, sedimentation etc.

These impacts can increase cumulative effects of the whole cascade. However,

these impacts could be mitigated.

Page 7: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

7

* Result from the surveys shows that land from sensitive areas is not acquired for project.

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES

OR NO

(tick )

OP/BP 4.04: Natural Habitats

Natural habitats are defined as land and water areas where the ecosystems' biological

communities are formed largely by native plant and animal species, and human activity

has not essentially modified the area's primary ecological functions.

1. Is the subproject located within any National Biological

Conservation Areas, (NBCAs), and National/Provincial/District

Protected Areas (NPAS, PPAs, DPAs)? (If yes, subproject is

excluded)

Yes

□ No

2. Will the subproject result in significant degradation or

conversion of habitats and/or forests in protected areas, proposed

protected areas or areas that are considered of special ecological

significance? If yes, what is the consequence?(If yes, subproject is

excluded)

Yes

□ No

3. Will the subproject aim to bring about changes to the

management, protection, or utilization of natural forests or

plantations, whether they are publicly, privately, or communally

owned?(If yes, subproject is excluded)

Yes

□ No

4. In the case of a biomass subproject, will the subproject

undertake commercial harvesting of forests (e.g., for fuel for

biomass plant)?

(If yes, subproject is excluded)

Yes

□ No

5. Is the subproject located within the buffer zone of any National

Biological Conservation Areas, (NBCAs), and

National/Provincial/District Protected Areas (NPAS, PPAs,

DPAs)? (if yes, subproject is eligible but requires permit)

Yes

□ No

6. Will the subproject affect a forested area? (If yes, subproject is

eligible but requires permit of the owner or of the district’s

People’s Committee).

Yes

No

Based on the above screening, does OP/BP 4.04 apply? No

If the answer to any of Questions 1-4 is YES, OP/BP 4.04 will apply and the subproject

is NOT ELIGIBLE for refinancing.

Page 8: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

8

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES

OR NO

(tick )

OP/BP 4.10: Ethnic Minorities (Indigenous Peoples)

Are ethnic minority people present/reside in the project area?* YES

NO

* The project made Ethnic Minority Planning Framework to implement

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES

OR NO

(tick )

OP/BP 4.11: Physical Cultural Resources Physical cultural resources include

movable or immovable objects, sites, and structures, groups of structures, natural

features and landscapes that have archeological, paleontological, historical,

architectural, religious, aesthetic or other cultural significance.

Will the subproject cause temporary or permanent relocation or

any other type of impact on physical cultural resources known to

be of local, regional or national significance based on national or

Provincial lists, proposed national or Provincial lists and/or

identified during public consultation with local affected groups?

YES

□ NO

Are any physical cultural resources considered especially

important or sensitive particularly to local groups (e.g. tomb

sites)?

YES

□ NO

Are chance find procedures in place? YES

NO □

Based on the above screening, does the physical Cultural

Resources Apply? NO

Page 9: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

9

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES OR

NO

(tick )

*There is not any households have to resettlement, compensation plan was prepared.

OP/BP 4.12 Involuntary Resettlement

The Involuntary Resettlement safeguard will apply in those situations involving involuntary

taking of land and involuntary restrictions of access to legally designated parks and

protected areas. The policy aims to avoid involuntary resettlement to the extent feasible, or

to minimize and mitigate its adverse social and economic impacts.

1. Is any land used by people/organizations likely to be acquired

as a result of the subproject? Yes No □

2. Will any subproject activity involve restrictions of use on

adjoining land? Yes □ No

3. Is land ownership affected by the subproject? Yes No □

4. Will there be a loss of housing or assets or incomes of local

people/organizations? Yes No □

5. Will any social or economic activities be affected by land use

related changes? Yes No

If the answer to any of the above questions is YES, OP/BP 4.12 Apply and a Resettlement

Plan in accordance with Resettlement Policy Framework is required.

Page 10: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

10

ENVIRONEMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES

OR NO (tick )

OP/BP 4.37 Dame Safety Policy

1. Is the dam height is 15 meters or greater? Yes

No

2. Is dam storage 3 million cubic meter or more? Yes

No

3. The dam height is between 10 and 15 meters but the dam

presents special complexities (for example large flood-handling

requirement, location in a zone of high seismicity, foundations

that are complex and difficult to prepare, or retention of toxic

materials?

Yes No

4. Is the dam is expected to become a large dam during the

operation of the facility?

Yes

□ No

5. Based on the above screening is the REDP subproject

considered to be a large dam and will a Dam Safety Assessment

be required?*

Yes

No

Page 11: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

11

ENVIRONMENTAL SAFEGUARD

SCREENING CRITERIA

APPLIES, YES

OR NO (tick )

* Trung Thu SHPP is to be located on Nam Muc river, an international river originated

from Phong Sa Ly province of Lao. Nam Muc river is also a tributary to Da river which

originates from Van Nam province of China. Trung Thu SHPP is located downstream of

Nam Muc Hydropower plant. Therefore, the international water way of WB (OP/BP 7.05)

is applied for this project.

Overall Safeguard Compliance

Does the subproject comply with the aforementioned World

Bank Safeguards?

YES

NO □

Based on the screening results above it could conclude that Trung Thu project is

categorized B level of WB environmental safeguard policy.

OP/BP 7.50 Projects on International Waterways

The objective of OP/BP 7.50 is to ensure that World Bank-financed projects affecting

international waterways would not affect relations between the World Bank and its

Borrowers and between states and also not affect the efficient utilization and

protection of international waterways. It applies to projects that involve the use and/or

potential pollution of international waterways. OP/BP 7.50 does not apply to run of

the river projects.

Is the subproject the first subproject downstream of a river that

flows from another country? YES

NO

Is the proposed subproject the last project on a river that flows

into another country? YES

NO

Will the subproject utilize water from or into a river or river

tributary that flows to or through or forms a border with a

neighboring country?

YES NO

Will the subproject discharge water from or into a river or river

tributary that flows to or through or forms a border with a

neighboring country?

YES NO

If a biomass subproject, does the subproject utilize or discharge

water from, or into a river or river tributary that flows to a

neighboring country, or that forms a boundary with a

neighboring country.

YES NO

Page 12: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

14

TABLE D: ENVIRONMENTAL CONCERNS AND EMP REQUIREMENTS

Issue or Environmental Concern

(Note: Social issues and concerns are dealt elsewhere)

Is Issue or Concern

Addressed in EIA or

EPC? Yes or No

(tick )

Is Issue or Concern

Addressed in EMP?

Yes or No

(tick )

Required

Action or

Follow-up

YES NO YES NO YES

Air quality impacts on local communities?

Noise?

Dust?

Is in a Seismically Active or Geotechnical Unstable

Area?

Affects Integrity of Protected Areas?

Impacts on Migratory, Rare, Threatened or Endangered

Species?

Impacts on Biodiversity?

Considers Downstream Impacts?

Affect Environmental Flows?

Affect Downstream Water Quality?

Page 13: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

15

Issue or Environmental Concern

(Note: Social issues and concerns are dealt elsewhere)

Is Issue or Concern

Addressed in EIA or

EPC? Yes or No

(tick )

Is Issue or Concern

Addressed in EMP?

Yes or No

(tick )

Required

Action or

Follow-up

YES NO YES NO YES

Affects Fish or Fisheries?

Considers Off-site Impacts (e.g. Borrow Pits and

Aggregates)?

Aesthetic and Visual Impacts?

Impacts Cultural Property or Resources?

Causes Increased Erosion and Sedimentation During

Construction?

Involves Construction of New Access Roads?

Involves Construction of Worker Camp(s)?

Has Chance Find Procedures In Place for Physical and

Cultural Resources?

Has Waste Management Plan (Solid and Liquid Wastes)

in Place?

Is there a Reclamation Plan In Place?

Have Subproject Contingency and Notification Plan in

Page 14: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

16

Issue or Environmental Concern

(Note: Social issues and concerns are dealt elsewhere)

Is Issue or Concern

Addressed in EIA or

EPC? Yes or No

(tick )

Is Issue or Concern

Addressed in EMP?

Yes or No

(tick )

Required

Action or

Follow-up

YES NO YES NO YES

case of Accident or Event (e.g. Release)?

Has Included EMP and Environmental Protection

Measures as Part of Contract Provisions?

Has EMP Monitoring and Supervision Procedures in

Place?

Includes Costs and Time line for EMP?

Are there any other issues of concern about the

subproject that is listed in the EIA over and above the

aforementioned issues that should be addressed?

Page 15: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

17

1. INTRODUCTION

1.1. Project background

Trung Thu small hydropower project is invested by Trung Thu hydropower

Joint Stock Company. The project is located on Nam Muc River which flows

through communes of Sa Tong, Pa Ham, Nam Nen, Muong Cha district and Trung

Thu, Sinh Phinh, Muong Bang, Tua Chua district, Dien Bien province.

Nam Muc River is the primary tributary of Da River. It derives from the high

mountain region at altitude over 1500 m of Lao Republic and flows along the

North-West direction then enter into upstream of Da river. Ta La Cao is the primary

tributary of Nam Muc river which is derived from Vietnam - Lao border then

flowing into Nam Muc River at location of Muong Cha district. Two small hydro

power projects namely De Bau and Ta La Cao are located in upstream of Ta La Cao

stream. Nam Muc hydropower plant which is on the Nam Muc River is upstream of

Trung Thu hydropower project. The whole basin of Nam Muc river is located in

both districts of Muong Cha and Tua Chua, Dien Bien province.

The headwork of Trung Thu small hydro power project is located nearby

confluence of Nam Muc and Da Rivers belonging to Pa Ham commune, Muong

Cha district and Trung Thu communes, Tua Chua district, Dien Bien province. The

project site is around 3 km far from the National Road No. 6 (Tuan Giao - Lai Chau

direction). It is 14 km far from the confluence of Nam Muc and Da Rivers and 12

km far from Nam Muc hydropower project towards upstream. The reservoir of

project is located in communes of Trung Thu, Sinh Phinh, Muong Bang, Tua Chua

district and Pa Ham, Nam Nen, Sa Tong communes, Muong Cha district.

The Trung Thu small hydro power project with the capacity of 30 MW is

categorized of impoundment, regulated by reservoir, annual electricity production

of 124.10 x 106 kWh. The headwork consists of gravity concrete dam with 252 m

length, 45 m height, and spillway with 45 m length. The right bank energy route

includes intake, penstock with 25 m length. Catchment area: 2,759 km2, reservoir

area corresponding to normal water level: 30.7 x 106 m

3. The switchyard is placed

at 238.5 m altitude in the upstream of power house. Ddesigned flow: 145.6 m3/s;

minimum flow through turbine: 16.3 m3/s.

Trung Thu hydropower was additional into master plan of small hydropower

of Dien Bien province and it was allowed by Dien Bien Provincial People’s

Committee to preparing investment report.

1.2. Project Donor and Participating Bank

Trung Thu project expects to be refinanced from REDP funded by WB

through the Bank of investment development Vietnam (BIDV), Hanoi branch.

1.3. Project objectives

The main objective of subproject is to exploit effectively the water resource

and natural topographical features of the local area to produce electricity with its

annual average power generation up to 124.10 million kWh. It supports to increase

power generation of the national power system. Concurrently, it helps to meet local

electrical power demand and to improve the local budget. The project also brings

Page 16: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

18

great significance to improve infrastructure, life quality for the local people in the

remote area of Muong Cha and Tua Chua districts, Dien Bien province that is facing

many difficulties due to its poor infrastructure and backward customs.

1.4. Project management & EMP implementation

Developer: Trung Thu hydropower joint stock company

Feasibility Study consultant: Power Engineering Consultant Company No 1

(PECC1).

The developer establishes a Project Management Unit under Trung Thu

hydropower joint stock Company to conduct Trung Thu small hydropower project.

An environmental and social staff has been assigned by project management unit to

manage all projects’ environmental activities.

According to the WB regulations, developer is responsible for preparing and

complying with EMP. The environmental consultant supports developer to prepare

EMP following ESF under REDP which was approved by MOIT and no objection

by WB.

According to the Vietnamese regulations, the reservoir’s gross storage

corresponding to the normal water level is 30.7 x 106 m

3 so the Environmental

Impact Assessment Report was prepared by developer and it was approved by Dien

Bien PPC by the confirmation letter No. 263/ QĐ-UBND dated April 21st 2014.

2. PROJECT DESCRIPTION

2.1. Location of project

The Trung Thu small hydro power project is on the Nam Muc River. It

locates on communes of Sa Tong, Pa Ham, Nam Nen, Muong Cha district;

communes of Trung Thu, Sinh Phinh, Muong Bang, Tua Chua district, Dien Bien

province. The project site is 80 km far from Tuan Giao town on the Northeast and

28 km far from Muong Lay town on the South. The reservoir of project located

along the old National Road No. 6. It is located at Northern latitude 21o56’27” and

Eastern longitude 103o15’20”.

The main project components include headwork and energy route. The

headwork consists of concrete dam, spillway, and discharged drain. The energy

route includes intake, penstock, power house and switchyard. The whole project

components are located on Trung Thu commune, Tua Chua district and Pa Ham

commune, Muong Cha district, Dien Bien province.

The reservoir and main components of Trung Thu hydropower project are 3

km far from residential areas of 6 communes listed above. There are not any

households, public works, irrigation/traffic systems within or nearby project site.

However, there is a hydro-logical station at reservoir area

Page 17: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

19

Figure 1. Location of the SHP Trung Thu in Dien Bien province

Trung Thu

hydropower

project

Page 18: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

20

2.2. Project description

Table 2.1. Parameters of main components of subproject

No. Parameter Unit Value

I Catchment

1 Catchment area

m2

2,759,000

2 Gross storage

106m

3 30.7

3 Reservoir area corresponding to normal

water level m

2 2,433,700

II Hydrology

1 Normal water level m 240

2 Death water level m 239

3 Annual average rainfall mm 1,800

4 Annual average flow rate m3/s 86.8

III Penstock

1 Number of penstock pipe 2

2 Length of pipe m 29

IV Dam

1 Type of dam Gravity concrete

2 Length m 30

3 Hmax m 45

V Spillway

1 Gate valve nxBxH m 3x12x14.5

2 Height m 225.5

VI Powerhouse

1 Max height of water level m 29.7

2 Min height of water level m 16.9

3 Designed flow m3/s 145.6

Page 19: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

21

4 Min flow m3/s 16.3

5 Installed capacity MW 30

6 Number of unit unit 2

7 Annual electricity production 106kwh 124.1

Source: Feasibility study report

2.3. Construction method

Material, equipment: Trung Thu hydropower joint stock company hires contractors

to build main components of project such as dam, powerhouse, penstock,

switchyard, transmission line and access-internal roads. Material for construction

project such as concrete, steel, fuel, lubricant etc is bought from shops which are

around 30 km far from project site. Sand is mined at place which is 10 km far from

the project site on the upstream. Rock for construction is reused from excavation

for foundations and mined from 2 quarries which are 1,5km and 500 m far from the

dam on the left side.

Transportation:

Access road: The National road No.6 is mainly used as access road (Tuan Giao -

Lai Chau direction). It takes around 2-3 km from National road No.6 to project site

belonging to Trung Thu commune, Tua Chua district and Pa Ham commune,

Muong Cha district.

Internal road: developer has to upgrade and construct new roads as below:

Internal road for construction/operation: from National road No.6 belonging to Pa

Ham commune to the downstream of dam left shoulder with the length of 3.3 km,

6.5 m roadbed width, asphalting structure.

Internal road for construction consists of 5 distances (i) from internal road No.1 to

auxiliary facilities of headwork; (ii) from internal road No.2 to explosive storage;

(iii) from downstream of dam right shoulder to dump-site at downstream of dam

right shoulder; (iv) from upstream of dam right shoulder to dump-site at upstream of

dam right shoulder; (v) from internal road No.1 to sand mine. Total length of this

road is 3.7 km, 5 m roadbed width, reused stone structure.

Switchyard and transmission line: electricity for construction is supplied from 35

kV national transmission line at Trung Thu commune. The 35/0.4 kV transformers

are provided at construction/auxiliary areas. The switchyard with altitude of 238.5

m locates on upstream powerhouse, the right bank of Nam Muc river. The site with

large, raised terrain is convenient for construction activity in both dry and rainy

seasons.

Developer has to build newly 15 km length of 110 kV transmission line from Trung

Thu switchyard to 110 kV Tuan Giao - Muong Lay transmission line which is

connected to Lai Chau hydropower plant to connect to national grid.

Page 20: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

22

Construction organization: It may take 2.5 years to completion of construction

phase. Activities of excavation/back-filling of soil/rock at all project components,

placing large grain size concrete at dam, placing concrete at spillway are done in

dry season while steel reinforcement, on-site form-work at powerhouse and

penstock is implemented in rainy season.

Water supply: Water for construction is taken from Nam Muc river. Domestic water

is taken from slots in the higher regions and wells then filtered by man-made tanks.

Campsites and auxiliary facilities: There are around 300 workers in the

construction site at peak time. Four campsites with area of 2 ha at the upstream of

dam on the left side are arranged that are quite far from Nam Muc river bank. These

campsites are provided wells, water filtered tanks, septic tanks. The concrete mixed

stations, form-work shop, rock grinded/screened stations, electro-mechanical

workshop, car parking areas, petrol/fuel storage etc with the area of 5 ha are

arranged at the upstream of dam on the left side. The rock reused storage with area

of 0.82 ha locates at upstream of dam on the left side. Two disposal areas of 4.84 ha

are arranged at right bank, upstream and downstream powerhouse. The explosive

storage locates separately and quite far from other auxiliary facilities, on the left

bank, at the end of internal road No.2.

3. LEGAL AND TECHNICAL BASIS TO IMPLEMENT EMP

3.1. The legal and technical documents

Water Resources Law No. 17/2012/QH13 dated June 21, 2012;

Environmental Protection Law No. 55/2014 / QH13 dated June 23, 2014;

Forest development and protection Law No. 29/2004/QH11 dated December 3,

2004;

Electricity Law No. 28/2004/QH11 dated December 3, 2004 and the Electricity

Law No. 24/2012/QH13 dated November 20, 2012, amending and supplementing

a number of articles of the Electricity Law No. 28/2004/QH11;

Land Acquisition Law No. 45/2013/QH13 dated November 29, 2013

Decree No. 149/2004 /ND-CP dated July 27, 2004 of the Government on

regulating the licensing of exploration, exploitation and use of water resources,

discharge of waste water into water sources;

Decree No.197/2004 /ND-CP of the Government dated December 3, 2004 on

"Compensation, support and resettlement when the State recovers land".

Decree No. 106/2005/ND-CP dated August 17, 2005 on regulating and guiding

the implementation of some articles of Electricity Law on safety protection of

high-voltage grid

Decree No. 23/2006/ND-CP dated March 3, 2006 of the Government on

enforcement of law of protect and develop forests;

Decree No. 32/2007/ ND-CP dated March 30, 2006 of the Government on

endangered animals and plants management

Decree No. 59/2007/ND-CP dated April 9, 2007 of the Government on solid

waste management

Page 21: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

23

Decree No. 72/2007 / ND-CP dated May 7, 2007 of the Government on dam

safety management.

Decree No. 112/2008/ND-CP dated October 20, 2008 of the Government on the

integrated exploitation of environmental resources and hydropower reservoirs

management and protection

Decree No. 81/2009/ND-CP dated October 12, 2009 of the Government

amending and supplementing a number of articles of Decree No. 106/2005/ND-

CP of the Government dated August 17, 2005 on regulation and guiding the

implementation of some articles of electricity Law on safety high-voltage grid

protection

Decree No. 69/2009/ND-CP of the Government dated August 13, 2009

additional regulations on land use planning, land prices, land recovery,

compensation, support and resettlement.

Decree No. 29/2011/ND-CP dated April 18, 2011 of the Government on the

regulation on strategic environmental assessment, environmental impact

assessment, environmental commitment

Decree No. 67/2012/ND-CP of the Government dated September 10, 2012

amending and supplementing a number of articles of Decree 143/2003/ND-CP of

the Government dated November 28, 2003 detailing a number of articles of the

Ordinance on exploitation and protection of irrigation building

Circular No. 24/2013/TT-BNN dated May 6, 2013 of the Ministry of Agriculture

and Rural Development regulation on alternative forest when converting forests

to other purposes

Circular No. 26/2011/TT-BTNMT July 18, 2011 of the Ministry of Natural

Resources and Environment regulate in detail a number of articles of Decree No.

29/2011/ND-CP dated April 18, 2011 of the Government on regulation of

strategic environmental assessment, environmental impact assessment,

environmental commitment.

Circular No. 12/2011/TT-BTNMT April 14, 2011 of the Ministry of Natural

Resources on hazardous waste management.

Decision of the Prime Minister No. 186/2006/QD-TTg dated August 14, 2006 on

forest management.

Decision No. 68/2008/QD-BLĐTBXH December 28, 2008 of the Ministry of

Labor, War Invalids and Social Affairs on regulation of list of equipment,

personal protective equipment for workers doing risk factors and hazardous jobs.

Decision No. 16/2008/QD-BTNMT December 31, 2009 of the Ministry of

Natural Resources and Environment on national environmental standards.

Decision No. 12/2008/QD-BTC of the Ministry of Industry and Trade dated June

17, 2008 on promulgating national standards of electrical safety.

Decision No. 18/2007/QD-PPC October 2, 2007 of Dien Bien People Committee

on regulation of environmental protection in Dien Bien province

Page 22: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

24

Decision No. 19/2007/QD-PPC October 2, 2007 of Dien Bien People Committee

promulgating the regulation on management of usage of water resources in the

Dien Bien province.

3.2. Technical basis applied in EMP

QCVN 05: 2013/BTNMT - National Technical Standard on ambient air quality.

QCVN 40: 2011/BTNMT - National Technical Standard on industrial waste

water

QCVN 26: 2010/BTNMT - National Technical Standard on noise

QCVN 27: 2010/BTNMT - National Technical Standard on vibration

QCVN 25: 2009 / BTNMT- National Technical Standard on waste water of

landfills

QCVN 19: 2009/BTNMT - National Technical Standard on industrial emissions

of dust and inorganic substances

QCVN 03: 2008/BTNMT - National Technical Standard on permissible limits of

heavy metals in soil

QCVN 08: 2008/BTNMT - National Technical Standard on surface water quality

QCVN 09: 2008/BTNMT - National Technical Standard on groundwater quality

QCVN 14: 2008/BTNMT - National Technical Standard on domestic waste

water

QCVN 02: 2008/BCT - Vietnam standards on safety in the storage, transport,

usage and disposal of industrial explosives

4. KEY ENVIRONMENTAL AND SOCIAL ISSUES

4.1. Environmental issues

Table 4. 1. Environmental issues of project

Page 23: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

25

No

Impacts

Impact description

PREPARATION AND CONSTRUCTION PHASE

1

Land acquisition Total area of acquired land for project is 302.64 ha

Permanent acquired land is 290 ha of which:

243.37 ha for reservoir

46.63 ha for main components such as headwork, intake,

penstock, powerhouse etc

Temporary acquired land:

12.64 ha for campsites, auxiliary facilities such as

disposals, material storage

The whole of acquired land is located in Trung Thu

commune, Tua Chua district and Pa Ham commune,

Muong Cha district, Dien Bien province. Share of land

use consists of cultivated forest land (long term trees),

agricultural land (paddy, cassava, and short term crops),

bush, bamboo and bald land etc.

(Refer Table 3.2 for more detail)

2 Landslide, erosion and

sedimentation

Cause of landslide/erosion:

Activities of excavation/back-filling of rock/soil at the

main components of headwork such as dam, spillway,

intake, penstock, powerhouse, switchyard during

construction phase lead to risk of landslide/erosion.

Construction of dam and storage water in reservoir will

impulse landslide especially at unstable ground.

Moreover, in case of long, heavy rain, water level rises;

the new land is submerged leading to partial landslide.

It is compulsory to blasting for construction of 7 km

length of internal road due to sloping mountainous/hill

terrain. Risk of landslide is easy occurred during

blasting.

Geological features of project site:

Geological structure of region consists of Nam Pia

terrigenous formation. Petrographic composition

includes shale, quartz.

There are four faulting systems in the region namely

Northeast Southwest, Northwest Southeast, sub latitude

and meridian. The faults have dimension from IV to V

level. The impact of these faults is small. Essential

geotectonic activities are mainly lifted-down activities

simultaneously which create by terrace and alluvial flat

with small dimension.

Page 24: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

26

No

Impacts

Impact description

Geological structure of dam site consists of rocks with

hard degree from weak-average to hard. Reservoir

region includes carbonate sedimentation formation,

shale and bazan rocks.

The whole project region now discover new activity

signs of faults.

The mines with economic worth still have not been

discovered in the reservoir area.

Impacts of landslide/erosion:

Sedimentation of Nam Muc river and reservoir

Reduce water quality

Changing of water flow in downstream

Features of project:

Project site is located on long narrow valley, nearby

confluence of Nam Muc, Nam Mu Rivers and Nam Tau

stream. The biggest characteristic of region is

mountainous/hill terrain with average altitude of 500 m.

Riverbed is narrow and high slope.

Due to quite stable geology at reservoir area so the risk

of landslide at large scale to reform reservoir bank is

limitation.

Reservoir is mainly formed base on riverbed. There is

not high level fault which cut crossing the reservoir so

that mitigation of water leakage into neighbor valley.

Process of landslide as well as reformation of reservoir

bank is small scale. Process of sedimentation is

estimated at low speed.

As estimated, speed of natural sedimentation in

reservoir area is low. The reservoir has short length and

large area so the flood area is mainly riverbed without

mountain/hill.

When water is kept in the reservoir, sedimentation

process may occur at low speed because of existing of

Nam Muc hydropower plant and Nam Pay stream in

upstream of reservoir.

Foundations cut through rock layers leading to easy

erosion of foundations.

Discharging water through spillway may cause partially

flood and erosion of area behind the spillway. However,

this area is mainly bald hill and at least 3 km far from

communities so that discharge of water through spillway

Page 25: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

27

No

Impacts

Impact description

do not effect to local people.

3 Impacts on surface

water quality

The main seasons cause to water surface pollution in the

construction phase:

o Domestic waste water from 300 workers in project site

(at peak time).

o This type of waste water contains BOD5, residue, TSS,

and organic substance.

o In average, each worker uses 40 water litters per day.

Total domestic waste water discharge from 300 workers

is 12 m3 per day.

o Constructed waste water from auxiliary facilities such as

machine repaired workshop, concrete mixed stations,

rock washed grounds etc. This waste water contains

mainly TSS, oil and grease, organic substances, metals

etc.

o Run-off water from the whole of project site sweeps out

impurities especially scattered oil, grease, dust which

come from concrete mixed workshops, fuel storage,

machines/equipment/vehicles loading etc.

o Scattered fuel: as estimated, the average volume of fuel

which is extracted from stored tanks to

machines/vehicles is 1,500 liters per day. The loss of

fuel is around 7.5 litters/day (lost norm of 0.5%)

o Domestic and constructed solid waste: in case of not

control well, this waste impacts remarkable to surface

water when solid waste is discharged directly into Nam

Muc river, reservoir.

o Organic waste is decomposed from dead bodies of

animal and vegetation in the reservoir.

Impacts of surface water pollution:

o Increasing of turbidity, reducing of water quality of

Nam Muc river water.

o Affecting to life of aquatic species

Project features:

o Investigation process shows that there are not any

activities of aquaculture or agriculture in project site due

to sloping terrain and low density of population.

o Local people often takes water from the higher regions

for their domestic usage therefore construction of the

project do not affect to water demand and quality water

of local people.

Page 26: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

28

No

Impacts

Impact description

4 Impact on air quality Causes of air pollution:

o Blasting for construction of internal road, digging of

foundations, quarrying

o Rock/soil excavation and back-filling

o Material transportation

o Operation of rock grinded/screened stations; concrete

mixed workshops;

o Operation of vehicles; constructed

machines/equipment

o Construction of main components.

For above items, estimated quantity of main works are:

o Excavation/back-filling of soil and rock: 3,150 x 103

m3

o Concrete works: 119.45 103 m3

o Steels of any kind: 1,931 tons.

Estimated dust quantity is emitted from excavation and

back-filling activities:

o Total quantity of excavation and back-filling: 3.150 x

103 m3 x 2 tons/m

3 = 6.300 10

3 tons

o Total dust quantity emits: 6.300 103 tons x 0,4

kg/tons = 2.520 103 kg

Dust is also strongly emitted from quarry and road

construction parallel with activities of rock/soil

excavation and back-filling; material/rock/soil

transportation; blasting for digging foundations.

In comparing with standard of QCVN 05:

2013/BTNMT, the dust concentration which emits in

project site may be exceeded the permission.

Beside, the operation of constructed machines, trucks

will emit toxic gas such as CO2, CO, SO2, NOx, dust

As estimated, materials/equipment/machines that serve

for project construction are transported in sequence

along National road No 6, internal communal roads to

project site.

All main project components including headword,

penstock, and powerhouse are at least 3-5 km far from

residential areas.

Project site is also quite far from inter communal roads.

There are not any households, public works such as

Page 27: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

29

No

Impacts

Impact description

irrigation/traffic systems within or near project site.

The quarry which is newly exploited for project is

located far from project site and the nearest

communities at least 10 km and 4-5 km; respectively.

This quarry is separated to the surrounding areas by

hills/mountains that are covered by tree so that the

impact of dust will be mitigated.

Dust and toxic gas pollution which emit in the

construction phase only affect to narrow, partly areas

and in short term depending to the construction time.

Air pollution only affects directly to workers who are

working in constructed sites but not to surrounded

communities.

Dust and toxic gas generated during transportation of

materials/equipment may affect to local people who live

along two sides of roads

5 Noise Main causes of noise pollution:

o Constructed facilities

o Materials/equipment transported vehicles

o Operation of concrete mixed stations, rock

grind/screened workshops

o Blasting, using drilling machines

According to statistic data: 8-12 tons loaded trucks,

excavator, air pressed driller have the noise level of 91-

98 dBA, 90-96 dBA, and 94 dBA; respectively.

As calculation, the average noise level of machines is

around 72-80 dBA within the distance of 120-200 m.

This noise level exceeds the permission following the

standards of QCVN 26:2010/BTNMTso it may affect to

workers who are working in the constructed site.

Noise pollution may cause seriously negative impacts to

workers who hand directly with blasting, using driller if

they are not quipped by labor safe equipment. The noise

level is not only generated by blasting, driller but it is

increased strongly by phenomenon of reverberation in

narrow mountainous terrain.

The main project components are quite far from the

residential areas of Pa Ham and Trung Thu communes

as well as the internal-communal roads. Additionally,

due to the low density of population in the project site

and the noise is only generated in certain daily time,

therefore noise may only affect directly to the workers

Page 28: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

30

No

Impacts

Impact description

on the sites during construction and local people who

live along 2 sides of roads during transportation.

6 Pollution cause by

solid waste

Sources of solid waste:

o Scattering rock/soil from quarries, material

transportation and discarded rock/soil from

excavation, drilling, blasting etc

o Scattering concrete: from concrete mixed stations,

constructed sites, concrete scattering in transportation

process

o Scattering steel: from constructed sites and

productive workshops

o Wood, bamboo: from constructed sites, reservoir

o Domestic solid waste: from campsites, constructed

sites

During construction phase, discarded rock/soil will be

discharged from excavation of topsoil, reservoir

vegetation clearance, quarries and constructed waste

containing cement, steel, wood etc. Disposal of

constructed waste without controlling may lead to

trespass forest/cultivated land and water pollution.

Domestic solid waste: 0.3 kg/person/day x 300 persons

= 90 kg/day (at peak time)

Domestic solid waste contains different types of waste

such as food waste, paper, cover of canned food. It may

cause unpleasant odor in case of not well controlling.

In case if clearance of reservoir does not well leading to

disintegrate animals/vegetable bodies that causes surface

water pollution.

The vegetation cover that collected after clearance may

cause risks of forest fire if it is not well controlled.

7 Loss of partly

vegetation cover

Total acquisition land for project is around 302.84 ha.

Since the terrain feature of project site is mainly

mountain and hill with high slope so the vegetation here

is not diverse. Almost the lost vegetation for project

construction is mixed forest such as brush, trees and

agricultural trees such as paddy, maize, cassava etc.

The loss of temporary vegetation cover for disposals,

borrowed pits etc will be restored after construction

phase...

8 Impacts of mining Sand is exploited at mine which is 10 km far from

Page 29: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

31

No

Impacts

Impact description

(sand, quarry etc) for

construction project

project site on the upstream. The mine is small alluvial

ground that located along Nam Lay River. This mine is

exploiting by local residents for construction of Nam He

hydropower project. Method of exploiting is suction

pump directly from the mine to borrow pits then

transport by vehicles to project site.

The quarry which is newly exploited for project is

located far from project site and the nearest communities

at least 10 km and 4-5 km; respectively. This quarry is

separated to the surrounding areas by hills/mountains

that are covered by tree so that the impact of dust will be

mitigated.

The first quarry is on the upstream, left side and 1.5 km

far from dam route. The second ones are on the

upstream, left side and 500 m far from dam route. They

are open-cast mines so the method of exploit is blasting

on the surface of mine.

Exploit of sand by direct suction pump may cause

exhaust sand resource leading to depression of river

bank and surrounding areas if it is not permitted and

supervised from local authorities.

Quarry by blasting on the surface of mine must to use

the explosive. It may cause accident at work due to mine

collapse leading to death/wounded of workers, residents

or asset losses in case if contractors do not comply with

safe regulations.

Blasting for quarry and process of transportation of

rock, sand from the borrow pits to project site may cause

air pollution by dust, toxic gases, noise, vibration.

Due to sloping terrain, difficult transportation and

almost none of resident live nearby mines and project

site so these impacts only effect to workers who work

directly in project site and local people who transports

nearby and they could be mitigated.

9 Impacts due to

construction of

transmission line and

access road

The developer has to do following items during

construction phase:

Building newly 7 km length of internal roads

Building newly 15 km length of 110 kV transmission

line from Trung Thu switchyard to 110 kV

transmission line of Tuan Giao – Muong Lay

connecting to national grid.

Construction of access/internal roads and transmission

line may cause the following impacts:

Page 30: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

32

No

Impacts

Impact description

Due to high slope so the vegetation cover of project area

does not diversify, mainly mixed forest with brush, trees

and partly agricultural trees such as paddy, maize,

cassava etc.

Acquisition land for road and transmission line is not

much. The transmission line is designed along the

National roads of No. 6 and No. 12 which is complied

with regulations of transmission line corridor safety.

The length of access and internal roads are only 7 km

without local residents living nearby so the effect is

negligible comparing to other hydropower projects.

The terrain of project area is mainly hill/mountain so it

is exposed to landslide leading to risks of health and life

for workers during excavation of pole foundation if the

safe measures are not complied. Because of almost none

of resident living nearby along the transmission line so

landslide does not effect to houses however, landslide or

soil/rock that are swept away to farm will effect to

cultivation.

Construction activities of access/internal roads, 110 kV

transmission line will lead air pollution those causes by

dust during excavation/back-filling of soil/rock, toxic

exhaust from operation of vehicles/machines, noise by

blasting, digging foundation and effect to transportation

safety. These impacts are not remarkable since the

almost none of local communities nearby project site.

The transmission line is dual circuit in which one circuit

is connected to 110 kV Tuan giao switchyard and the

rest is connected to 110 kV Lai Chau switchyard. It

create one closed circuit Tuan Giao-Lai Chau-Trung

Thu hydropower plant so this transmission line will

intersect with existing medium and low voltage

transmission lines and telecommunication cables. It may

damage these lines leading to cut-off

electricity/telecommunication signal for local area or

expose to risks of electrical accidents for workers or

residents. These impacts could mitigate.

Some distances of transmission line will go through the

National/Provincial roads so that it may obstruct traffic

and cause traffic accident during drawing cable.

The transmission line does not cross the army areas and

effect to the historical/cultural monuments of Dien Bien

province.

Terrain of project area is mainly sloping mountain/hill

so it may expose to risks of damaging to health or life of

Page 31: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

33

No

Impacts

Impact description

workers/local residents if the safe measures are not

complied during construction.

Project area has low density of population, inconvenient

traffic system. Construction of access/internal roads for

project will facilitate for traffic of residents since the

existing road is earthen, narrow so it is quite difficult,

dangerous for local transportation especially in rainy

season.

10 Effect to terrestrial

ecosystem

During construction phase, the below activities will

cause affects to terrestrial ecosystem:

Gathering of workers with high density in project site.

Access road system is constructed by developer that

facilitates for accessing to project surrounded areas.

Operation of trucks with high frequency

Blasting

The wild animals rarely appear in the project site. There

are only birds, small animals, fox, reptile etc. The above

activities will make the terrestrial fauna trending to

move far away from project site during construction

phase

11 Impacts on fish and aquatic life

The aquatic ecosystem will lose temporary living

environment due to water resource is contaminated by

high turbidity, run-off water contained cement, fuel, oil

and grease rock, soil, etc.

However, these impacts are not remarkable; only occur

in the short term because the civil constructed works are

almost done in the dry seasons.

After construction phase, the presence of reservoir

facilitates for animals to return and live surrounding the

reservoir because of its good living conditions.

12 Effect to traffic Construction material is bought from shops which are

30 km far from project site. Sand mine is 10 km far from

headwork and rock is reused from foundation

excavation and exploited from 2 quarries at left side,

upstream of dam which is around 1.5 km and 0.5 km far

from project site.

Transportation of materials/machines/equipment in

general does not affect to traffic of local people due to

low density of population and travel of communities is

not much.

Page 32: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

34

No

Impacts

Impact description

13 Effect on cultural/

historical properties

Results from surveys in the project area as well as

consultation with affected households and local

authorities shows that there are not any ranked

cultural/historical properties which are managed by the

district/provincial/national authorities. There are also not

any cultural and non-cultural properties that relate to the

ethnic minority people in the project area

According to survey, there are 25 tombs in the reservoir

area. Developer is working with affected households and

local authorities to deal with following to regulations. In

case there is any new tomb which is found during

construction phase, developer will coordinate to relevant

stakeholders for resettlement.

The developer prepared action plan in case if

cultural/historical properties are found in the

construction phase.

14 Effects to natural

preservation area/

national park

The project site is located quite far from the natural

preservative areas. The project activities do not impact

to natural preservation parks areas of Dien Bien

province.

15 Risks of mine and

underground works

It may expose risks of mine/bomb during

construction/operation phase that may be left after the

war in case do not detect carefully.

During construction process, the internal roads; 110 kV

transmission line, penstock etc must be built newly.

It is forced to blasting for construction such kind of

works because two sides of streams are mountainous

with high sloping terrain

Process of constructing underground works, blasting

may cause health, life damaged risks to workers and

local people in case safe measures are not complied

OPERATION PHASE

16 Change of flow in

downstream

Trung Thu small hydro power plant is under Nam Muc

cascade. The water level of downstream of Trung Thu

power plant will be affected by regulation regime of Son

La power plant when the water level of Son La reservoir

reaches from 208 m to normal water level of 215 m. The

regulation regime of Trung Thu power plant depends on

the ones of other plants in the same cascade.

A reservoir with the capacity of 30.7 million m3 is

formed after construction phase. Formation of reservoir

and regulation regime of Trung Thu hydro power plant

Page 33: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

35

No

Impacts

Impact description

will change the flow of distance Nam Muc River from

behind the dam to downstream. There are two different

flow regimes and their border is dam of Trung Thu

plant. At the upstream of dam, the river flow regime will

be replaced by reservoir hydrological regime with the

fluctuation of water level.

The upstream area of dam, due to project is categorized

impoundment hydropower plant so the water which is

used to generate electricity will be discharged back into

the main river behind the dam so it is not affected by

flow change or breaking off. It does not affect to water

usage of downstream otherwise, it has the positive

impact of controlling flood in downstream area.

The flow regime of downstream area depends on the

regulation regime of power plant. It is not regulated and

generates electricity following additional charge chart.

The variation in day of water level and downstream flow

is not remarkable. There are some small negative

impacts such as landslide, water usage for agriculture,

safety for life and asset etc. To mitigate these impacts,

developer must disseminate widely information on

operation regime of power plant as well as monitor

closely the negative impacts.

The downstream section with distance of 13 km far from

project site to confluence of Nam Muc and Da rivers is

quite sloping so it was not used for water way traffic by

local communities. On the other hand, due to sloping

mountainous terrain of this section, there is not any

households, agricultural/aquaculture activities so project

do not impact to water usage in downstream.

17 Impairment on water

quality In case if the waste such as domestic solid waste,

domestic waste water, lubricant contained waste water

from maintaining machines/vehicles is not well control,

it will lead to pollution of Nam Muc river. However,

this impact is not remarkable and could be mitigated.

When blocking water, if the reservoir is not cleared,

biomass (tree root, regenerated grass, organism death...)

and other substance (humus, mineral salt) which are

immerged in the reservoir will be decomposed leading

to water pollution due to reduce DO and increase BOD5.

Water pollution will cause negative affect to aquatic

life. This impact is negligible and may mitigate if

developer follows fully plan of reservoir clearance.

In case if the amount of phosphoric that discharges into

reservoir is higher 8.15 tons/year, eutrophication

Page 34: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

36

No

Impacts

Impact description

phenomenon may occurred leading to reduction of

water quality and affect to aquatic life.

18 Impacts on flora After formation of reservoir, climate in the project area

becomes cooler with higher humidity that facilitates for

development of vegetation cover

For the downstream behind the dam, the flow will be

lower than as the nature leading to loss of water at two

banks of river. The new natural terrestrial ecosystem

will be developed graduate.

19 Impacts on fauna After formation of reservoir, small animals (dog, fox,

mouse...), birds, reptiles, frog etc will come back to live

in the reservoir surrounded area.

20 Impacts on fish and

aquatic species

Increasing to turbidity of water river when construction

project will impact to aquatic species that leave in the

section from project site to downstream of project.

After formation of reservoir, the ecosystem of river

section that becomes reservoir will be changed from

river ecosystem to reservoir ecosystem. The formation

of reservoir has potential of developing aquatic species.

Some new aquatic species will be developed.

In the operation phase, the dam has negative impacts to

aquatic species and fishes that have emigration habit.

This impact do not prevent when constructing and

operating the hydropower plants.

21 Noise The operation of two units with installed capacity

of 15 MW/unit MW and other machines such as

lubricant pumped equipment will cause noise.

As experience from other small hydro power plants,

Trung Thu power plant is categorized as impoundment

power plant but not type of high water column so the

noise is not very high (only around 80 dB at distance of

1 m). This value of noise meets the National standard

QCVN 26:2010/BTNMT on noise.

22 EMF Operation of electrical equipment such as electrical

generator, transformer will arise the EMF. The EMF

only affects to workers who operate the electrical

equipment mentioned above if they do not comply

strictly to regulations on operation of electrical

equipment. The EMF does not affect to surrounding

communities since there is not any residents living

nearby and this impact could mitigate.

Page 35: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

37

No

Impacts

Impact description

In case the transmission line does not comply with

regulation on transmission line safe corridor, the EMF

will affect to person who work or living under in the

unsafe distance.

The statistic data shows that the intensity of EMF within

safe distance is less than 5kV/m that meet to WHO

standard on EMF.

23 Emergency case Emergency case in the power house: the electrical

accidents such as electrical leakage, short circuit, fire etc

may occur if do not comply to safe regulations on

powerhouse or electrical equipment operation. These

accidents may lead to damage the power plant.

Emergency case in the switchyard/transformer station:

fire accident due to short circuit/electrical leakage may

occur easily if do not follow strictly technological

design and regulations during construction and

operation. Compliance to procedures on transmission

line safety is extremely important task. It requires

workers have to obey strictly, fully all technological and

safe regulations during operation transmission line.

Emergency case in broken of dam, reservoir: these

disasters may occur in case of extraordinary weather

such as sweep flood or geological altering (earthquake,

crack, depression etc). These disasters cause serious

consequences leading damage to health and life as well

as assets especially in downstream area.

Page 36: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

38

Table 4.2. Land acquisition by main components in detail

No Item

Acquired

land Unit

A Permanent acquisition

1 Reservoir 2,433,700 m2

2 Dam, powerhouse, internal roads 466,300 m2

Total A 2,900,000 m2

B Temporary acquisition

1 Auxiliary facility 126,400 m2

Total A + B 3,026,400 m2

Source: Resettlement and compensation plan report

Table 4.3. Permanent acquisition by land use in detail

No Type of Land ha

1 Agricultural land 90.67

2 Forestry land 78.98

3 Others 120.55

Total 290

Source: Resettlement and compensation plan report

4.2. Key Social Issues

Table 4.4. Key social issues

No Social issues Information

PREPARATION AND CONSTRUCTION PHASES

1 Impacts to communities

There are not any households who have to

resettlement. There are 157 affected households on

land requisition and properties.

Most of people in the affected area are the Thai,

Mong, Kho Mu, Khang, Muong ethnic minorities

who still keep their backward customs so the

project may impacts on their daily life. However,

this disorder only affects few households and it is

only occurred in the construction phase.

Page 37: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

39

No Social issues Information

The transportation of materials and equipment

does not affect to the local people since the density

of population here is quite low and most of their

houses are far from the road. The distance from

nearest communities to access road is around 1

km.

Most of the local people expected that

development of project will facilitate to improve

their production and living standards.

2 Labor influx due to

construction workers and

conflict between workers and

communities.

According to feasibility study, there are around 300

staffs/workers that are mobilized for project

construction at the project site in the peak time.

Project site locates quite far from local communities

and internal-communal roads so this impact is not

remarkable.

As estimated, 4 separate camps will be arranged in

the downstream of dam. They are quite far from

residential areas of Pa Ham and Trung Thu

communes.

The relationship between developer and local

people who are living in the affected area is quite

good. The developer has experience in management

of workers and security in the local area when

building the former projects.

The security of Pa Ham and Trung Thu communes

is quite good. The social evils such as drugs, theft

and fight are seldom therefore conflicts between

workers and local people will be mitigated.

3 Increase sources of income

for the local people

At the beginning of construction phase, project will

gather large amount of staffs/workers so that it

could provide jobs and stable income for a part of

local residents in project site.

Demand in foodstuff and a series of services

facilitate for development of production and trading

of the local people.

OPERATION PHASE

4 Positive impacts on the local

socio-economic development

The routes of road which are upgraded and built

newly serving for project construction facilitate for

improving traffic system of local residents. They

help communities more convenient in term of goods

transportation, connecting the project area to other

places such as Tuan Giao town, Muong Lay town,

Dien Bien city etc.

Page 38: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

40

No Social issues Information

When finishing, project will supply stable power

with high quality for the local people. It will support

to development of industrial, handicraft and

traditional sectors in the locality

During construction and operation phases, project

creates jobs for local people.

Income from tax of water resource usage which is

provided from project will be added to provincial

budget.

The reservoir will allow to development of

aquaculture in the future which benefit for local

people in term of getting jobs and improving their

income.

5. MITIGATION MEASURES FOR NEGATIVE IMPACTS

During construction phase, the contracts will be signed between developer and

contractors who construct internal roads, switchyard and transmission line, main

components such as dam, penstock, powerhouse etc. These contractors will sign the

subcontracts with the sub-contractors who provide material/equipment. The responsibilities

of developer/contractors/subcontractors who must comply with mitigation measures are

presented in Table 5.1.

The mitigation measures must be put into the bid documents/contracts by

developer/contractors as requested conditions to the material provided/constructed

contractors. Trung Thu hydro power joint stock company is responsible for joining EMP

into detail technical design and construction biding contractor. Trung Thu hydropower

joint stock Company assigned one staff who is in charged in environmental management of

Trung Thu hydropower project. The environmental management staff presides and

coordinates to the relevant agencies to: (i) Monitoring the implementation of mitigation

measures following EMP and EIA; (ii) Supervising, suggesting measures to deal with

negative impacts on environment (if any); (iii) Making report on environmental

management implementation and submit to the district’s Department of Natural resource

and Environment and leaders of Trung Thu JSCo, BIDV Hanoi; (iv) Participating courses

on environmental management which are held by GDoE PMB and WB.

Page 39: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

41

Table 5.1 . Key Mitigation and Management Measures

Issues Mitigation and Management Measure

PREPARATION PHASE (Trung Thu hydropower joint stock company is responsible for implementation of mitigation measures)

1. Selection of project location Dam route location is chosen at area where there are not any residents. The dam site is located

at the section of two river banks which has high slope, narrow riverbed with the width of 30-40

m. This section of riverbed has original rock so it facilitates for arrangement of dam route.

Geological feature of the dam route area is disposed by clay and quartz schist with high

mountainous terrain along two river banks.

Selection of project site as presented above may mitigate the negative impacts to environment

due to minimized land acquisition, limitation of loss of vegetation cover, forest, convenience for

construction arrangement etc. It also limits to social impacts of local communities since the

agricultural land acquisition is reduced as well as dam site is quite far from local residents.

Supported facilities of project is chosen based on the criteria such as far from surface water

resource at least 100 m, explosive storage is arranged far from communities with minimum

radius of 500 m.

Transmission line and switchyard are chosen following the regulations and standards presented

in Decision No 34/2006/QD-BCN on safety of low voltage works.

2. Affected people Consulting with authorities of communes of Trung Thu, Sinh Phinh, Muong Bang, Tua Chua

district and communes of Sa Tong, Pa Ham, Nam Nen, Muong Cha district and affected

households to calculate the appropriate compensation plan which should meet expectation of

affected people.

Compensation plan and its implementation must be monitored by local authorities.

Consulting with representative authorities and households of Pa Ham and Trung Thu commune

Page 40: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

42

Issues Mitigation and Management Measure

on the location of two disposals to prevent the negative impacts to public health.

To minimize the acquisition of cultivated land and roads when arrangement of campsites,

material temporary loading or during construction of transmission line.

(See reports of compensation plan and ethnic plan for more details)

3. Risk of bombs and mines Hiring the functional agencies to detect bombs and mines at the following sites:

Area of all project component sites such as: powerhouse, dam, internal road...

Reservoir area corresponding to normal water level;

Transmission line

Auxiliary facilities (campsites, borrow pits, quarries, construction sites etc)

Compensation land areas.

CONSTRUCTION PHASE (Developer/constructed contractors/material, equipment provided sub-contractors are responsible for implementation

of mitigation measures)

4. Risks of mine Developer Coordinating with constructed contractors to arrangement of appropriate blasting plan.

Responsible for informing of blasting plan to local authorities and residents that aims to avoid

transportation and animal grazing at blasting areas.

Coordinating with constructed contractors to assigning the guard, using the warning alarm and

traffic arrangement when blasting.

Monitoring safe measures relating to management and using explosives which are done by

contractors

Constructed

contractors

To discuss and inform to developer on blasting plan so that developer can inform to local

authorities and communities on time.

Page 41: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

43

Issues Mitigation and Management Measure

To comply strictly with current regulations on explosive safety

Workers using explosives must be trained and certificated by the relevant authorities

To prohibit strictly person who do not have certification handing with the explosives.

To disseminate frequently to workers on safe regulations in handing with explosives

Blasting should be conducted at fix time to create watchful habit for local people. The time of

blasting should be arranged at low density of traffic so that it can mitigate impacts to local

transportation. The best is lunch time (from 11 am to 1 pm).

To coordinate with developer for assigning the guard, using the warning alarm and traffic

arrangement when blasting.

5. Mining of

quarries

Developer Coordinating with contractors to inform local authorities on plan of mining (sand, quarry etc)

Supervising safety of contractors in mining

Supervising environmental rehabilitation by contractors after closing the mine.

Contractors To establish the plan of mining that provides in detail technologies and machines as well as do

procedures to getting the permission by written from local authorities.

To deposit environmental fund before exploiting.

To comply strictly rules and regulations on technology and safety as well as environmental standards

during mining.

To ensure saving resources

Rehabilitation of environment after closing the mines (leveling and ramming the ground, plant

trees in the surface of mines)

6. Management of

constructed &

domestic solid

Developer To arrange 02 rock/soil storage sites with the total area of 0.82 ha that locates along internal road.

To arrange 02 solid waste disposal sites with the total area of 4.84 ha that locates at upstream and

downstream of dam right side. They must meet criteria such as at least 100 m far from surface water

Page 42: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

44

Issues Mitigation and Management Measure

waste resources, do not effect to surface water flow, cultivated land, do not locate in the areas which are

exposed dangers of landslide/erosion, should located in the hollow grounds to prevent run-off water.

Consulting with representatives of authorities and households of Pa Ham, Trung Thu communes on

solid waste disposal sites.

Prohibit workers to discharge the domestic and constructed solid waste into non-permitted places

especially where it can easily sweep out in to surface water flows.

The dumping sites which are used for domestic solid waste treatment are arranged at solid waste

disposal sites. The average volume of each dumping site is 20 m3 with estimated dimension per each

pit of 5m x 2m x 2m (5 m depth). Each dumping site is lined by anti-penetrative material called

HDPE with 1.5 mm thick. Spraying EM bio-product on the surface of waste, covering on the waste

surface by the 3-5 cm thick soil layer with frequency of 2-3 days to avoid odor and insects. Isolation

of dumping sites by gutter, cover is arranged to prevent sweep out when raining. Ramming, filling up

the soil, planting the tree on the top when finishing.

Monitoring the management of constructed/domestic solid waste of contractors which is presented in

item No 6 below.

Prohibiting to burn solid waste to prevent risk of fire.

Constructed

contractors

Top soil layer which is generated in process of excavation, road/transmission line construction

is kept in rock/soil storage sites and reused for planting trees after construction phase

Soil/rock which is generated from excavation, blasting, penstock construction etc is kept in

rock/soil storage sites and reused to back-filling the foundation of main components as well as

borrowed pits (material loads, concrete mixed stations, campsites etc)

The discarded rock/soil at disposal sites is leveled, rammed closely. The isolated gutter is built

to collect rock/soil in case runoff water happened. Planting tree on the surface of disposals after

construction phase to mitigate sweeping out of rock/soil to stream bed.

To prohibit workers discharge the domestic and constructed solid waste into non-permitted

Page 43: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

45

Issues Mitigation and Management Measure

places especially where it can easily sweep out into surface water.

Prohibiting to burn solid waste to preventing risk of fire

7. Vegetation

clearance of the

reservoirs and

construction sites

Developer To establish plan of reservoir clearance and treatment of hazardous substances before storage

water.

Before flooding, the reservoir is cleared carefully to mitigate eutrophication and reduction of

water quality.

The landmarks which determine boundary of reservoir area for vegetation clearance will be

marked.

Prohibiting cutting off trees in the areas that are outside of the reservoir boundary.

To harvest agricultural products before flooding reservoir

Big trees must be cut off at the foot and used for making form-work. Brushwood is cleared and

pulled out with the remaining part less than 20 cm.

If safe condition is ensured (without construction activities, transportation of vehicle, blasting,

water flooding and not in flood season etc), it is allowed to local people collecting trees,

products for their usage.

Developer is responsible for coordinating with local authorities and residents in the process of

vegetation removal in the reservoir and also checking safe conditions prior to permit people

collecting trees.

Burning of disposal biomass must be followed the plan preparing by developer and ensured

Page 44: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

46

Issues Mitigation and Management Measure

compliance with regulations on forest fire prevention. Site of burning points must be far away

each other at least 500 m. Do not burn trees in strong wind conditions to avoid the spread to

surrounding areas.

8. Erosion and

sedimentation

Developer o After construction phase, quarries, disposal sites... are backfilled by soil then rammed, pressed and

planted trees on the top to avoid erosion.

o Planting trees and managing well vegetation cover at surrounded areas of reservoir especially at

semi-flooding areas to stabilize the foundation of the reservoir bank, main components and the new

sedimentation areas.

o To coordinate closely with local authorities to manage well upstream watershed forest to prevent

swept-flood that cause landslide leading to reservoir sedimentation.

o To dredge reservoir bed every 1-2 years/time

o To prohibit exploiting of rock/soil or cultivation in the semi-flood areas within reservoir.

o Monitoring compliance of landslide/erosion mitigation measures of contractors

Constructed

contractors

It is necessary to describe foundations; monitoring blocks of rock which are exposed to risk of

landslide so that could provide warning and suggest the dealing measures during excavation of

foundation.

It should not drill blast with large amount of rock. The excavation should blast oriental to create

border of excavation.

Should have the measures to prevent landslide/erosion of rock which may be rolled from the top to

constructing foundation. The gutters that discharge water from the top should be digged to prevent

water run into the foundation. The gutters which could discharge water rapidly in the foundation area

should be created.

It must consolidate the embankments at the sites that are exposed to high risk of landslide/erosion at

the beginning of construction of new roads.

Page 45: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

47

Issues Mitigation and Management Measure

The isolated gutters are built at material temporary loads, concrete mixed stations, rock

grind/screened workshops etc to prevent run-off water which can sweep out rock/soil into stream.

After construction phase, the borrowed pits are backfilled by soil then rammed, pressed and planted

trees on the top to avoid erosion.

Activities of construction/excavation/back-filling are priority done in dry seasons.

9. Traffic and

transportation

Developer Monitoring implementation of mitigated measures which are done by contractors

Coordinating to contractors for repairing the damaged road in case the road is damaged because

of overload transportation.

Propagandize to improve awareness of compliance with traffic safe regulations for drivers

Constructed/materi

al supplied

contractors

To ensure all vehicles that use for transportation in project site have to meet standards of

technical safety and emission which are applied for vehicles.

Appropriate regulation of vehicles during construction phase to avoid traffic obstacles for local

people

Due to sloping terrain with quite a lot of bends so contractors should consider carefully in case

sending vehicles in the night time to ensure safety for drivers and local people.

To ensure all vehicles meeting loaded permission so that it could mitigate the damage of road.

Responsible for repairing the damaged road in case the road is damaged by contractors because

of overload transportation.

Propagandize to improve awareness of compliance with traffic safe regulations for drivers.

Page 46: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

48

Issues Mitigation and Management Measure

10. Construction of

access road and

transmission line

Constructed

contractors

The roads which will be newly built must meet the designed standards of road presented in

TCVN 8054-2005 (width of surface/foundation, slope, radius, visibility, angle of rotation, gutter

etc).

Transmission line and switchyard are complied with the regulations and standards presented in

Decision No 34/2006/QD-BCN on safety of low voltage works.

Location of electricity poles is chosen to avoid sloping points (the slope should be less than

300). It should limit excavation/back-filling in case of sloping sites.

To arrange the appropriate distance of poles to ensure the distance of transmission lines at the

intersection is larger than 3m-5m depending on each intersection. The fixing wire board is used

for insulator in the whole transmission line.

In the intersection between transmission line and the National/Provincial roads, the distance

from transmission line to the surface of road is larger than 7m to ensure meeting the safe

standard..

The contractors are responsible for repairing the existing medium and low voltage transmission

lines or telecommunication lines if they are damaged by contractors during construction and

drawing the cable.

During drawing the cable, the warning signals must be arranged at the intersection between

transmission line and the roads as well as the person to guiding transportation must be assigned.

To comply strictly regulations on safe corridor of transmission line (level of height, sag) to meet

EMF standards during operation phase.

Application of safe constructed measures and prevention of traffic obstacles to local people

Priority to reuse topsoil from excavation process to back-filling the foundation, do not use new

soil for that work.

Topsoil must be kept and stored in the right of way then reused to recover vegetation.

To backfill the borrowed pits, creation of the embankments, planting trees on the surface to

Page 47: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

49

Issues Mitigation and Management Measure

prevent erosion/landslide and landscape after construction phase

11. Management of

hazardous materials

(fuels, lubricants,

explosives etc.)

Constructed

contractors

01 fuel/lubricant storehouse is arranged at the left side, downstream of dam. It is ensured at least 300

m far from surface water and residential areas.

Storehouse floor must be lined by anti-seepage materials (thick nylon) or 5.0 cm thick concrete layer

to avoid contamination of oil and grease into ground and underground water.

Gutter to collect oil/grease is designed surrounding storage in case of oil spilling

To prepare the extinguishers and oil suction apparatus in case of happening faults.

Hazardous chemicals (fuel) must be stored in the tanks with their volume must be 110% of volume

as required.

To comply strictly with regulations of storage, transportation and usage of hazardous chemicals and

explosives.

Labors who work directly with fuel, explosives must be trained on safe technologies relating to

chemical, explosive, fire precaution, oil spilling etc.

To minimize storage of explosives at most on the construction site. In case of explosives are used

and stored in the short term, explosive storage must be located more than 100 m far from surface

water sources and 500 m from residential area.

Disseminating MSDS to labors who hand directly with hazardous chemicals. To mark warning

notices and regulations of safety on site when handing with hazardous chemicals.

Page 48: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

50

Issues Mitigation and Management Measure

It is compulsory for workers to use the labor safe equipment when handing with hazardous

chemicals.

12. Noise Developer Monitoring implementation of mitigated measures which are done by contractors

Propagandizing to improve workers’ awareness so that they do not make impact of noise to local

people.

Developer must coordinate to contractors for consulting Pa Ham and Trung Thu communal

authorities and local people in case of necessary to blasting or construction in night time

Constructed/materi

al supplied

contractors

Requesting to check regularly on technical status of machines and equipment to ensure they meet the

noise standards which are presented in QCVN 26:2010/BTNMTto mitigate impacts to workers

The appropriate working time should be arranged, avoiding to blasting and construction in night

time.

Must coordinate to developer for permission of Pa Ham and Trung Thu communal authorities and

local people in case of necessary to blasting or construction in night time,

Vehicles that transport the materials, machines have to use the horn with noise level meeting the

standards of noise for transportation.

Propagandizing to improve workers’ awareness so that they do not make impact of noise to local

people.

To avoid sending vehicles during night time to mitigate noise that affects to local people living along

roads.

13. Dust Constructed

contractors

Water spraying at least 1 to 2 times per day is carried out at necessary sites (dam, powerhouse etc) in

dry and windy conditions to prevent dust pollution in constructed sites that may affect to workers’

health.

Material transported vehicles must be covered by tarpaulin to avoid scattering rock/soil on the road.

Page 49: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

51

Issues Mitigation and Management Measure

Material supplied

contractors

Material transported trucks must be covered by tarpaulin to avoid scattering and dust.

During transportation along the roads or through the residential areas, drivers should give up way for

local people to prevent dust for them.

14. Domestic waste

water management

Developer As estimated, 4 campsites are arranged at downstream of dam.

Each apartment is arranged septic tanks to collect and treat domestic waste water of workers. The

waste water must meet the permission standards before discharging into the environment.

Constructed

contractors

Propagandizing to improve workers’ awareness on environmental hygiene for workers.

To prohibit workers discharging waste into streams which lead to contaminate domestic water of the

local people.

Punishing workers who do not comply with the above regulations.

15. Constructed

waste water

Constructed

contractors

To collect grease and oil generated from car parking and equipment/machines maintenance stations

then sell to companies who treat the hazardous waste.

To build the pits which collect mud/sand in the following sites before discharging waste water in to

environment:

Rock grinded stations

Concrete mixed stations

Cement waste water contained grounds etc

Page 50: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

52

Issues Mitigation and Management Measure

16. Chance find of

cultural artifacts,

and areas/structures

of local cultural

value

Developer To prepare the chance find procedures of historical/cultural/archeological artifacts and request

constructed contractors must to comply during construction

If main components (transmission line, internal road, penstock, etc) go through or locate in the areas

that have tombs, the developer must cooperate closely with consultant companies to adjust design.

Beside, the developer consults authorities and local people to find suitable solutions to move ashes

following the local customs.

Constructed

contractors

In case of any historical/cultural/archeological artifacts that may be encountered during excavation:

excavation works must be stopped and the Trung Thu, Sinh Phinh, Muong Bang, Sa Tong, Pa Ham,

Nam Nen communal people committees and/or Tua Chua, Muong Cha district people

committees/Dien Bien Department of Culture, Sport and Tourism must be immediately informed; the

locale must be guarded to solve by local authorities

Prohibiting workers to remove any historical/cultural/archaeological artifacts. This is supposed

illegal action.

Construction work will only be continued after being permitted with notice in writing from the

authorities.

17. Water supply Constructed

contractors

To arrange pipelines which take water from higher mountain/hill parallel with digging wells for

domestic water usage?

To build man-made tanks which use to filter for domestic usage of workers?

18. Safety issues in

the construction

process

Developer Coordinating with constructed contractors to establish labor safe regulations which force workers to

comply.

Assigning 01 staff to supervise labor safe issues of contractors.

Coordinating with contractors to solve on time the risks/accidents which happen during construction.

Page 51: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

53

Issues Mitigation and Management Measure

Constructed

contractors

The constructors are responsible for ensuring work safety for the whole engineers and workers on the

construction site as in details:

It is mandatory for workers to attend training courses on labor safety before they are recruited to

work for company.

Supervise period on compliance to labor safe measures of workers at project sites.

Training courses on labor safety for workers are held periodically to improve their knowledge and

awareness in term of compliance with safe measures.

To provide necessary safe facilities for workers.

A person will be assigned to work as safe staff. He/she is responsible for supervising and speeding

up the compliance with regulations of labor safety of workers;

To have timely measures in the event of happening accidents;

Do suspend all work absolutely during heavy rains or emergencies of any kind in anticipation of

landslide, accidents caused by open circuit that may lead damage for worker’s health and life

To equip fully fire extinguishers in the building and the construction sites.

19. Management of

sanitary and safety

and prevention of

disease infection in

campsites.

Developer 01 staff that is responsible for health care of workers in the project site will be assigned by developer.

Coordinating with constructed contractors to make plan of workers’ health care during construction

phase.

Coordinating with contractors to establish the precautionary program of sexual transmitted diseases,

especially HIV/AIDS precautionary program, among labors.

Supervising the implementation of mitigated measures in term of food safety, environmental

sanitation, disease transmitted precaution which must be done by contractors.

Constructed 01 staff that is responsible for health care of workers in the project site will be assigned by

Page 52: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

54

Issues Mitigation and Management Measure

contractors contractors.

A first aid kit will be provided at each construction site to ensure patients can receive first aid timely

before transporting them to the medical station/hospital.

Monitoring regularly to keep sanitary in campsite, construction sites in order to precaution of

pathogenesis/disease transmission relating to digestive and respiratory system. To require workers

using mosquito nets to prevent petechial/marsh fever.

To propagandize food safety and hygiene for workers;

To build septic tanks in campsite which must meet environmental standards. To prohibit discharging

of domestic solid waste directly in to the environment. Domestic solid waste must be hygienically

collected, stored, transported and treated.

Coordinating with developer to establish and carry out the precautionary program of sexual

transmitted diseases, especially HIV/AIDS precautionary program, among labors.

Coordinating with developer to make and implement plan of workers’ health care during

construction phase.

Provide communication/entertainment facilities for workers.

20. Worker Code Developer Coordinating with contractors to establish worker code and manage them during construction phase.

If constructed contractors recruiting workers who come from the other regions, they must be

informed to developer to register temporary residence with the Trung Thu, Pa Ham communal

authorities;

Developer is responsible with the Trung Thu, Pa Ham communal authorities for all issues relating to

worker management during they stay in locality for project construction.

Page 53: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

55

Issues Mitigation and Management Measure

Constructed

contractors

Coordinating with developer to set up worker code

Responsible for worker management during construction phase

Informing to developer in case the workers coming from other regions to register temporary

residence with the Trung Thu, Pa Ham communal authorities;

The following activities are prohibited on or near project site:

Cutting of trees for any reason outside the approved construction area;

Hunting, fishing, wildlife capture, or plant collection;

Disturbance to anything with architectural or historical value;

Building fires outside camp areas;

Use of firearms (except authorized security guards);

Use of alcohol by workers during Project hours;

Washing car, motorbikes or machinery in streams or creeks.

Doing maintenance (change of oils and filters) of cars and equipment outside authorized areas.

Disposing trash in unauthorized places;

Driving in an unsafe manner in local roads.

Having caged wild animals (especially birds) in camps.

Working without relevant safety equipment (including boots and helmets).

Creating nuisances and disturbances in or near communities.

Disrespecting local customs and traditions

21. Rehabilitation

of all Project sites

Developer Recover vegetation in all project components to prevent erosion in rainy season.

After construction phase, planting trees/grass in the surface of all borrow pits (disposal sites,

Page 54: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

56

Issues Mitigation and Management Measure

after construction

phase

campsite, material temporary loading etc)

Planting in combination of 3 types of trees including long term trees, grass, and shrub with priority

of indigenous plants especially in re-vegetation areas.

Landscaping at project site after construction phase.

22. Effected people

by project

Developer Arrangement jobs as well as guiding local residents on livelihoods after construction phase.

Providing documents on compensation of land and property on land to local authorities and affected

households.

Upgrading/Repairing irrigation system to ensure supplying fully water for agricultural activities of

local communities in case if is damaged by project.

To ensure hygienic environmental conditions for local residents during material transportation and

construction process.

Upgrading/Repairing water supply pipeline for affected households in case if is damaged by project.

Maintenance of flow to ensure development of aquatic life and do not affect to fishing based on

natural condition which is done by local people

OPERATION PHASE (Trung Thu hydropower joint stock company is responsible for implementation of mitigation measures)

23. Noise (from the hydropower plant) Turbines and/or associated equipment should be designed to meet standards on noise (QCVN

26:2010/BTNMT)).

Design and procurement of equipment should specify requirements to meet standards of noise;

Monitoring periodically the noise level outside the fence of hydropower plant. To implement the

measures of noise reduction in the outside of hydropower plant in case it exceeds the standards.

24. Labor safety issues and worker code To arrange fire-extinguishers at necessary places

Page 55: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

57

Issues Mitigation and Management Measure

To set up the procedures of safe operation;

To arrange the first aid cabinet so that it can carry out the first aid measures on site;

To assign a staff in each shift who is responsible for labor safety

Labor code is defined similar to in the construction phase which is presented in the item 19.

25. Change in downstream flows For the reservoir: the flow is controlled strictly by developer following the regulations on reservoir

operation, discharging water. Developer is responsible for informing in time on plan of water

discharging to local authorities to prevent damage of health, life or assets of downstream

communities.

Developer is responsible for informing widely to local residents, organizations and authorities on

water level fluctuation of Trung Thu flow in downstream to ensure safety for health and asset as well

as production and agricultural activities in the downstream area.

Developer is responsible for compensating in case of damaging to asset of communities due to

discharging flood.

For the downstream distance after the power plant: developer commits to comply strictly the

approved operation procedures of reservoir. During operation phase, developer will regularly

coordinate to local authorities in monitoring water level and erosion to provide suitable mitigation

measures.

26. Impairment of water quality To clear vegetation cover before flooding reservoir to prevent pollution of water;

Embankments are build at sites which are exposed to danger of landslide

To built separated systems of domestic and industrial waste collection and treatment which meet

permitted standards prior to discharge into the environment;

Domestic solid waste is hygienically managed then transported to the dump site for treatment;

Recovering vegetation at construction sites to mitigate erosion and water resource protection.

Page 56: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

58

Issues Mitigation and Management Measure

27. Plant plankton residing in the reservoir In case of increasing too much plankton which leads to water pollution so it is necessary to remove

vegetation from the reservoir

Pesticide is prohibited to use for plankton treatment.

28. Reservoir sedimentation Prohibition of cultivated activities in the semi flood area.

To coordinate to local authorities in supervising of prohibition of destroy forest in reservoir

surrounding area especially the semi flood area.

To monitor erosion of reservoir bank two times per year. To take the initiative in implementing

mitigation measures such as planting trees, building breakwaters at points that expose to serious

erosion.

After construction phase, the borrow pits must be rehabilitated by leveling, ramming then planting

trees on the surface to mitigate erosion and sedimentation of reservoir.

Discharging sediment through bottom culvert and dredging the reservoir if necessary.

To mitigate erosion of the river banks behind power house, the energy eliminated hole is designed to

reduce flow rate after discharging canal of power plant so that the flow returning to original flow of

river.

To monitor erosion of river banks in downstream and provide the appropriate mitigation measures

such as building breakwater, dealing to breakdowns that occur by erosion.

29. Maintaining the replanted vegetation

cover

To monitor and maintain annually vegetation cover which is replanted after construction phase to

rehabilitation of environment and mitigation of erosion.

30. Management of hazardous substances

( fuel, lubricant, etc)

The same to the measures presented in item No 11.

31. EMF To provide facilities of EMF protection and request staffs/workers who work directly in the EMF

Page 57: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

59

Issues Mitigation and Management Measure

arise areas comply strictly rules on labor safety.

As statistic data, in the safe distance of transmission line, the intensity of EMF is less than 5kV/m

that meets to WHO standards on EMF. The local resident who is living or working in the safe

distance of transmission line will not be affected by EMF.

To supervise period transmission line (lowest sag) to ensure meeting the standards on EMF safety.

32. Emergency cases Storage of water and reservoir operation procedures must be complied to regulation of reservoir.

Annually, before flooding season, the director of Trung Thu power plant make report and organize

the meeting with representatives from flood control steering committees of districts of Muong Cha,

Tua Chua and Dien Bien province to approve the detail plan of flood control. The minute of meeting

must be sent to each members of flood control steering committees of Muong Cha, Tua Chua

districts for coordination in implementation. The detail plan of flood control will be submitted to

flood control steering committees of Dien Bien province for supervision.

Annually, from June, Trung Thu power plant must check the whole equipment, machines, hydrolic

works such as generators, communication facilities, equipment to monitoring water level, practice

and checking of technology and procedures of flood discharging.

To comply strictly rules on operation, maintaining, preparing of electrical equipment, regulations of

power plant, transmission line and switchyard.

To train period on electrical safety, prevention of fire for staffs

To disseminate electrical safe regulations at work places for staffs.

To monitor and provide regularly fire-extinguishers at necessary places and provide emergency aid

for staffs in case of fire.

Page 58: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

60

Chance finds procedures

If the Contractor discovers archeological/historical sites, monuments and objects,

including graveyards and / or individual graves unearthed during construction, the

contractor will be responsible for:

To stop the construction activities in the chance find area.

To delineate the location or found area.

To protect the area to prevent the object from being damage and lost. For artifacts or

remains, the night guard will be allocated directly until the local government has the

responsibility or the Department of Culture and Information takeover.

Inform the Investor to notify for the local government or the nations undertaking the

cultural heritage of Viet Nam (within 24 hours)

Relevant local/central authorities will be responsible for the area protection and

conservation before providing the decision on the later appropriate procedures. Then

they will implement the preliminary evaluation on the excavated findings. The

significance and importance of these findings should be evaluated according to various

criteria relevant to cultural heritage, including aesthetic value, historical or scientific

research, economic and social values

The decision of findings treatment will be made by the responsible agency. This

decision covers the layout (such as in case of detecting the rest of the cultural or

archeological importance cannot be moved) conservation, preservation, restoration and

salvage.

If the cultural area and/or heritage evaluated by the experts and the Cultural Relics

Management agency’s regulation are valuable and should be preserved, the developer

have to change the design in accordance with the required conservation of the area

The decisions of findings management will be notified in writing by the related agency

Page 59: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

61

6. ENVIRONMENTAL MONITORING PLAN

Table 6.1. Parties involved in environmental monitoring

No. Units Main responsibility Content and form

of report

Frequency

1 Contractor To carry out the proposed mitigation measures in EMP

Making report of implementation of mitigation measures

to developer

Refer to the table

6.3

Submitting reports to

developer monthly

2 Developer To join EMP into detail technology design and

construction bidding contractors.

To carry out the proposed mitigation measures in EMP

To monitor construction activities and ensure that the

contractors comply to environmental requirements in the

contracts and EMP (Terms of reference for environmental

staff in monitoring EMP is presented in the Annex 2)

Making report of implementation of mitigation measures

to BIDV Hanoi/GDoE PMB

Refer to the table

6.3

Submitting reports to

BIDV Hanoi/GDoE PMB

monthly

3 Safeguard

Monitoring

Independent

Consultant

To monitor (by observation) and assess environmental

quality based on parameters suggested by this EMP

report.

To conduct public consultation to received comment,

assessment of local people on environmental management

of the Project.

Refer to the table

6.4

Submitting reports to

BIDV Hanoi/GDoE PMB

half-yearly

Page 60: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

62

Table 6.2. Environmental monitoring plan

Parameters How to monitoring

Sites of monitoring

1. CONSTRUCTION PHASE

Sitting of campsites and

material temporary loading

Visual observation the following issues:

- Camp sites

- Water supply resources

Location of campsites:

- How are they far from stream and residential areas?

- How developer arrange water supply?

- Does developer build filter tanks to filter water?

Location of borrowed pits:

- How are they far from stream and residential areas?

Location of disposals/dump sites:

- How are they far from stream/worker’s rooms

- Concrete mixed stations

- Vehicles, machines parking

- Material loading

- Equipment/machine repaired

workshops

Vegetation clearance and

topsoil stripping

Check and visual observation the following issues: The flora gathering area after

its cut-off;

Vegetation clearance plan

Measures of vegetation clearance

Page 61: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

63

Parameters How to monitoring

Sites of monitoring

Topsoil stored areas (disposal sites) are applied measures of protection from

erosion/run-off water?

Does project build holes/gutters/embankments?

Topsoil temporary stored site

Work with developer

Does project has landscape rehabilitation plan/Does it implements? Work with developer

Detect bombs and mines Checking bomb and mines disarming document proposed in the project Work with developer

Domestic and constructed

solid waste management

Visual observation the following issues:

Does project generate discarded rock/soil?

Do discarded rock/soil affect on water quality or flow of water?

How to collect domestic solid waste?

How to treat domestic solid waste?

How to manage dump sites?

Disposal sites

Dump sites

Topsoil storage sites

Camp sites

Removal of discarded

vegetation out of reservoir

area

Visual observation the following issues:

Checking the plan of vegetation clearance

Is it correct to cut off trees in the required areas?

Does collection of valuable wood out of the reservoir implement?

Is burning the remaining tree leaves/wood well done?

Work with Developer

Check the reservoir bed.

Erosion and sedimentation Visual observation the following issues: The construction sites

Do construction activities carry out in dry season?

Page 62: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

64

Parameters How to monitoring

Sites of monitoring

Are measures to mitigate erosion/landslide applied at construction sites?

Are holes/ditches/embankments built at danger sites of landslide in construction

areas?

The sites expose risk of high

erosion/landslide

Transportation and traffic

management

The following issues should be checked:

Certification of vehicles that serve for project meet technological/emitted

standards

Attested document of vehicles/machine periodic maintenance

Do vehicles cause traffic jam or damage the road?

Contracts signed with contractors supplying materials/equipment

- Working with developer

- Dam area

- Powerhouse

Management of hazardous

substances

The following issues should be checked and assessed:

Hazardous substance storage:

Is it lined by anti-seeped ground?

Is it protected with cover?

Is it locked and isolated with surrounding area?

Check permission of Dien Bien province’s Department of Industry and Trade if

explosives is stored ;

Check dissemination and material supply about toxicity, safe manual with

hazardous substance ;

- Work with Developer

Check the storage

Page 63: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

65

Parameters How to monitoring

Sites of monitoring

Noise The following issues should be checked and assessed:

Does noise level at the construction sites impact on the nearest residential area?

Interview local people and leaders living in the nearest area whether the project

makes noise in rest time, evening time?

Interview local people whether developer asks their permission to work in

evening time?

If there is any claim about the noise, request developer to measure the noise level

and give appropriate measures to mitigate its impact.

Contracts signed with material supplied contractors

Project area,

The nearest residential area

Interview the local people

and authorities

Working with developer

Dust The following issues should be checked and assessed:

Is water sprayed fully in dry season at sensitive sites?

Does trucks used for transport material covering by tarpaulin?

Contracts signed with material/machine supplied contractors

Interview with local people about dust pollution cause by project

- The construction site

- Material transported trucks

- Working with developer

Page 64: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

66

Parameters How to monitoring

Sites of monitoring

Water quality management The following issues should be checked and assessed:

How does sewage collection and treatment system implement at campsites? Are

there septic tanks?

Does sewage discharge directly into environment without treatment?

Do the septic tanks in campsites keep sanitary?

Are oil and grease from vehicles/machines maintenance collected?

Are ditches/pits/embankments built at borrowed pits to collect sand/soil/cement

before discharging into environment?

Is collection of over spill sewage from tunnel performed?

Is water quality measured periodically as presented in EMP/EIA?

- Campsites;

- Borrowed pits

- Vehicle maintenance area;

- Working with Developer on

document of water quality

measurement

Safety Visual observation (combine with information collection on health protection plan

and safety issues):

Is health and safety plan prepared?

Are safe tools & equipment provided to and being used by workers?

Are laborers trained and disseminated information on safety?

Are there any warming notice and boards guiding safety handling to hazardous

chemicals?

- Construction sites

- Storage area

- Working with developer

Labour health care

Are first-aid kits for labours equipped?

Do they dig well the drainage? Is there mosquito net for sleeping?

Are workers trained about food safety and prevent sexually infected diseases?

Is there any disease for labours and did they treat by local health care station?

- Camps

- Working with developer

- Interview workers

Page 65: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

67

Parameters How to monitoring

Sites of monitoring

Worker code To assess implementation of regulations for workers as specified in item 19 of Table

4.1.

Chance find of cultural

artifacts, and areas/structures

of local cultural value

Observation, information collection, assessment of the below-mentioned issues:

Excavation area of soil/rock

Interview workers

Along transmission line

Let check whether contractors/ developers/ related persons inform the relevant

organizations if accidental find of articles of cultural value?

Do contractors and related persons have followed chance find procedures in

place

Are there findings on cultural property and historical heritage in the soil/rock

excavation?

How are chance find procedures in place when accidental find of articles of

cultural value?

Location of tombs or valuable structures to local people

OPERATION PHASE

Noise Observation at site, interview people to assess the following issues:

Does noise from the powerhouse affect the local people?

- The area out of the fence of

powerhouse.

If there is any claim about the noise, request the developer to measure noise at

site. - The nearest residential area

Safety and regulations to

staffs

The following issues should be checked and assessed:

Are fire extinguishers equipped at site?

Check complying regulations for people as item 19 in Table 4.1

Powerhouse area

Operation house and

workers’ houses (if any)

Page 66: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

68

Parameters How to monitoring

Sites of monitoring

Management of water quality

in reservoir

The following issues should be checked and assessed:

Is there any erosion at reservoir side? Are reinforcing measures applied?

Is domestic waste collected and treated prior discharging into the environment?

Is there phenomenon of eutrophication in reservoir? Does developer remove

floating vegetation from the reservoir?

In the reservoir bed

Operation house and

powerhouse

Management of hazardous

materials (fuels, lubricants,

explosives etc.)

The following issues should be checked and assessed:

Are hazardous materials stored in safe conditions?

Does the developer equip facilities, provide information and guide safe process

to hazardous materials?

In the plant and fuel, material

and chemical storage areas.

Page 67: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

69

Table 6.3. Form of in-site environmental monitoring report

(Applying for contractors/developer)

Project name: Project location:

Name of Contractor:

Commencement of Project report or monthly report:

Date of report:

No. Issue Mitigation measures implemented Note

Construction phase

1 Sitting of construction camps and supported facilities

2 Vegetation clearance and topsoil stripping

3 Disarm bomb and mines

4 Domestic and constructed solid waste management

5 Removal of discarded vegetation out of reservoir area

6 Soil erosion and sedimentation

7 Transportation and traffic management

8 Management of hazardous substances

9 Noise

10 Dust

11 Water quality management

12 Safety

13 Labour health care

14 Worker code

Page 68: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

70

15 Chance find of cultural artifacts, and areas/structures of local

cultural value

16 Vegetation cover including reforestation

Operation phase

1 Noise

2 Surface water quality

3 Waste water

4 Solid waste

5 Vegetation cover maintenance

6 Environmental flow

7 Management of hazardous materials

8 Safety

9 Labour health care

10 Worker code

Name of person prepared this Report: Title:

Address: Telephone:

Page 69: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

71

Table 6.4. Form of EMP implementation monitoring report

(Applying for environmental monitoring report of technical supervisor/consultant)

Project name: Project location:

Date of report:

No Parameter Assessment of Consultant/ community

complaints

Comments/Recommendations

Construction phase

1 Sitting of construction camps and supported facilities

2 Vegetation clearance and topsoil stripping

3 Disarm bomb and mines

4 Domestic and constructed solid waste management

5 Removal of discarded vegetation out of reservoir area

6 Soil erosion and sedimentation

7 Transportation and traffic management

8 Management of hazardous substances

9 Noise

10 Dust

11 Water quality management

Page 70: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

72

No Parameter Assessment of Consultant/ community

complaints

Comments/Recommendations

12 Safety

13 Labour health care

14 Worker code

15 Chance find of cultural artifacts, and areas/structures of local

cultural value

16 Vegetation cover including reforestation

Operation phase

1 Noise

2 Surface water quality

3 Waste water

4 Solid waste

5 Vegetation cover remaining

6 Environmental flow

7 Management of hazardous materials

8 Safety

9 Labour health care

Page 71: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

73

No Parameter Assessment of Consultant/ community

complaints

Comments/Recommendations

10 Worker code

Report prepared by:

Address and contact information:

Page 72: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

74

Table 6.5. Requirements on environmental management reporting System

No. Contents 1st reporting level

2nd

reporting level

(A copy sent to the district’s

Environment Management

Department )

3nd

reporting level

(A copy sent to the district’s

Environment Management

Department )

CONSTRUCTION PHASE

1 Implementation of

mitigation measures

and on- site

environmental

management

By: Contractor

Frequency: Monthly

To: Developer

By: Developer

Frequency: Monthly

To: BIDV Hanoi/GDoE

By: Vietcombank Hanoi

Frequency: half-yearly

To: GDoE

No. Contents 1st reporting level

2nd

reporting level

(A copy sent to the district’s

Environment Management

Department )

CONSTRUCTION PHASE

1 Environmental

monitoring

By: Independent Consultant

Frequency: Half-yearly

To: Developer/BIDV Hanoi

By: Independent Consultant

Frequency: Half-yearly

To: GDoE/WB

OPERATION PHASE

Page 73: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

75

1 Labor safety and

environmental

monitoring

By: Developer

Frequency: Half-yearly for first two years

To: BIDV Hanoi

By: BIDV Hanoi

Frequency: Half-yearly for first two

years

To: WB/GDoE

Page 74: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

76

7. COMPLAINATION ON ENVIRONMENT AND PENALTY

While monitoring the scene if supervising/monitoring environmental officers discover

that there is non-compliance with regulations on the implementation of measures to

minimize environmental impacts mentioned in EMP then monitoring construction

staff/ environmental supervisor shall make the records and report the investor .The

investor will stop paying that month expense for the contractor until the contractor

performed adequate measures to minimize environmental effects. The contractor will

be extended one time (due to the construction supervision consultant / supervisor of

environmental regulate) to correct this violation. If the contractor performs the repairs

within the time extension he will not be penalized. However, if the contractor does not

conduct the repairs needed in the extension period, the contractor will have to pay for a

third party to repair the damage (this cost will be taken from retained). Investors must

make provisions for compliance and sanctions for environmental violations in the

contract with the contractor.

In case supervision staff / monitoring environmental officers find non-compliance with

the environmental regulations of the contractor, the contractor shall have to pay the

cost to repair the violation.

The investor is responsible for monitoring and implementing the EMP effectively. If

he does not fulfill the implementation of the EMP, the slow disbursement from the

project to the investors will happen

Environmental offices of the contractor will be the place to receive complaints from

citizens against environmental influences such as dust, noise, traffic safety,... The

Contractor’s Chief Engineer and Personnel Assistant with the safety and environment

officers will be responsible for carrying out or giving solutions to handle the above

issues. Officer safety and environmental construction supervision consultant (or team

management environment of the investor) will be provided with copies of the

complaints of the people and must confirm that the problems are properly resolved by

the contractor in a similar incidents were discovered when examining at site.

8. ENVIRONMENTAL MANAGEMENT CAPACITY BUILDING PLAN

8.1. In the preparation phase:

Developer will send staffs who are assigned to manage environmental

protection of project to participate the WB/GDoE training courses on preparation of

EMP and public consultation.

8.2. In the construction and operation phases:

The assigned staffs shall participate the training courses on WB’s safeguard

policies under REDP. The developer will appoint 1-2 environmental staffs to attend

the short-term training courses on environment which are held by the local authorities.

Additionally, book, papers and documents will be bought by developer so that they

could update the environmental protection information

Page 75: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

77

Table 8.1. Cost estimation for environmental management capacity building

TT Activities Costs (VND)

CONSTRUCTION PHASE

1 To appoint staffs to participate training courses held by WB:

2 persons x 5,000,000 VND/person/training course x 2 times

20,000,000

2 To appoint staffs to attend training courses held by the local

environmental authorities.

2 persons x 1,000,000 VND/person/time x 2 time

4,000,000

3 Purchase of books, documents, papers to update information 10,000,000

TOTAL 34,000,000

OPERATION PHASE

4 Cost for annual training in the project running phase

(10,000,000 VND/year x 20 year)

200,000,000

TOTAL 234,000,000

9. ENVIRONMENTAL MANAGEMENT COST ESTIMATION

Table 9.1. Estimated cost for EMP implementation

No. Items Construction phase During operation phase

(20 years of life cycle)

1 Mitigation measures The cost is covered in

investment cost

The cost is covered in

operation cost

2 Recover vegetation at

project sites after

construction phase

40,000,000 VND

(The cost is covered in

investment cost)

3 Detect mine 30,000,000 VND

(The cost is covered in

investment cost)

4 Monitoring costs for

the Project.

(By technical

The cost is covered in

investment cost

The cost is covered in

operation cost

Page 76: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

78

supervisor of Trung

Thu JSCo)

5 Environmental

quality monitoring

2 times/year x 10,000,000

VND/time x 2.5 years =

25,000,000 VND

2 times/year x

10,000,000 VND/time x

20 years = 400,000,000

VND

6 Monitoring costs for

independent

environmental

monitoring

consultant*

Lump-sum

(2 times/year x 2 years x

20,000.000/time) =

80,000,000 VND

Sub-total 175,000,000 VND 400,000,000 VND

This cost is covered in

production cost

Total 575,000,000 VND

* This cost is paid by Project Management Board under GDoE

Page 77: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

79

10. PUBLIC CONSULTATION AND DISCLOSURE

10.1. Public consultation

In the preparation phase, Trung Thu JSCo carried out the following tasks:

The feasibility study report and investment report of Trung Thu project were

submitted to communal People Committees of Sa Tong, Pa Ham, Nam Nen,

Trung Thu, Sinh Phinh, Muong Bang. Based on the comments from above local

authorities on locations of the main components, the developer can revise

promptly project documents to get effective investment and mitigate

compensation and impacts on environment and communities.

Social survey by interview directly representatives of local authorities and

affected households was done by developer. Results from these investigations

show that almost households and local authorities support to construction of

project since it provides benefits for local residents. Project also facilitates for

local traffic from internal roads.

Survey and statistic of environmental impacts as well as affected households

were done.

Preparing EMP report

Consultation meetings on EMP report and other related issues were held at the

offices of Communal People Committees of affected communes Sa Tong, Pa

Ham, Nam Nen, Trung Thu, Sinh Phinh, Muong Bang from 16-18 June, 2014.

Participants consist of representatives from developer, local authorities of

communes of Sa Tong, Pa Ham, Nam Nen, Trung Thu, Sinh Phinh, Muong

Bang, environmental and social consultants, affected households (Minute of

meetings and list of participants are presented in the Annex 2). The main

content of consultation meetings as below:

Developer presented the main information of project:

Trung Thu small hydropower project has with the capacity of 30 MW is

categorized of impoundment, regulated by reservoir, annual electricity

production of 124.10 x 106 kWh. The headwork consists of gravity concrete

dam with 252 m length, 45 m height, and spillway with 45 m length. The right

bank energy route includes intake, penstock with 25 m length. Catchment area:

2,759 km2; reservoir area corresponding to normal water level: 30.7 x 10

6 m

3.

The swichtyard is placed at 243 m altitude. Designed flow: 145.6 m3/s;

minimum flow 16.3 m3/s. Trung Thu hydropower project is under small

hydropower master plan that was approved by Dien Bien provincial people

committee.

Construction of Trung Thu small hydropower project as the same other ones

will cause some negative/positive impacts to environment and social and these

negative impacts are unavoidable. EMP is prepared following to the World

Bank safeguard policies and commits to complying to mitigation measures so

that the negative impacts could limit. Developer also develops CDM for Trung

Thu hydropower project and hope to have support from local authorities as well

as residents for project.

Page 78: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

80

Environmental consultant presented generally the environmental

negative/positive impacts and mitigation measures which will be applied by

developer/contractors during project implementation as below:

Positive impacts:

Around 4.2 km length of internal road and an bridge crossing Nam Muc river

will be built newly serving for project construction facilitate for improving

traffic system of local residents. They help communities more convenient in

term of goods transportation, connecting the project area to other places such as

Tuan Giao town, Muong Lay town, Dien Bien city etc.

When finishing, project will supply stable power with high quality for the local

people. It will support to development of industrial, handicraft and traditional

sectors in the locality

During construction and operation phases, project creates jobs for local people.

After formation of reservoir, climate in the project area becomes cooler with

higher humidity that facilitates for development of vegetation cover, trees and

reservoir aquatic species such as fish, snail, shrimp etc. The reservoir could

allow developing aquaculture in the future which provides new jobs and income

for local residents.

Income from tax of water resource usage which is provided from project will be

added to provincial budget.

Project has installed capacity of 30 MW with annual electricity production of

124.10 million kWh. Project also applied CDM and as estimated the

certification emission reduction is received around 69,000 ton of CO2 per year.

Negative impacts:

Construction and operation of project must block river, storage water, build the main

components such as dam, penstock, powerhouse, switchyard, transmission line etc that

cause some unavoidable impacts as below:

290.2 ha land will be appropriated permanently for building components of

headwork and 12.64 ha land will be acquired temporary for auxiliary facilities.

Construction activities of components of headwork such as dam, spillway,

intake, penstock, powerhouse and switchyard have to excavation of soil/rock

that cause landslide/erosion at these sites.

Process of blocking river, constructing dam bringing about increasing turbidity

and reduction of water quality of Nam Muc river.

Activities such as blasting, excavation of foundation, quarry, leveling soil and

rock, material transportation, rock grind, concrete mixing, operation of

constructed machines, construction etc will impact to environment causing air

pollution in case the mitigation measures are not applies.

In the construction phase, the operation of constructed/transported facilities,

concrete mixing, rock grind, blasting, using driller etc will create noise that

disturb to local residents.

Page 79: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

81

Constructed and domestic solid waste that discharged from workers will cause

pollution of air and Water River if it is not well controlled.

In the construction phase, the aquatic species may lose temporary living

condition due to reduction of surface water quality that cause by random

spilling or rain sweeping away concrete, petrol, oil, gear, soil, rock etc.

However, this is only temporary and negligible impacts. They may be mitigated

because project has small scale and the construction time takes only 2.5 year.

Storage of water in the reservoir as well as operation of Trung Thu hydropower

plant will cause changing of Nam Muc river flow regime from behind dam to

downstream of powerhouse. In the project site, rive flow regime will replace by

reservoir hydrography regime that performs by fluctuation of water level. In the

operation phase, the reservoir has negative impacts to aquatic species and fish

which have habit of emigration. This affect is unavoidable when construction

and operation of hydropower projects.

Some key main negative impacts:

Environmental consultant presented briefly draft EMP which will be complied by

developer to mitigate negative impacts with some key measures as below:

The permanent and temporary acquired land due to project construction will be

compensated following compensation plan which is approved by local

authorities. During construction phase, cultivate and public transportation

acquired land for campsites, transmission line and auxiliary facilities will be

limited by contractors.

The contractors are responsible for inform to local authorities and residents on

blasting time so that they do not travel or release cattle in the blasting areas.

Disposals have to meet criteria: far from surface water at lease 100m, do not

affect to surface water, cultivate land, do not locate on the risk of erosion,

should locate on the hollow sites to mitigate sweep away by runoff water.

To establish the worker code at construction site containing regulations such as

prohibiting workers to discard domestic/construction waste into surrounding

areas, river, stream or places which may sweep away to surface water.

Do not allow to burn solid waste to mitigate risks of forest fire.

After construction phase, the mine, borrow pits or disposals etc must be

restored by leveling ground then planting trees to prevent erosion.

Planting trees and controlling vegetation cover at reservoir surrounding area

especially in the places of semi-flooding, main components for more stability of

ground.

To arrange storehouses of petrol, fuels etc at minimum safe distances of 300 m

from surface water, local communities.

Developer commits to comply with EMP with the main issues presented above.

Questions and answers are summarized as below:

Trung Thu commune, Tua Chua district:

Page 80: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

82

Questions from representatives of local authorities and affected households

Chairman and vice chairman of communal people committee request developer

to provide related documents of compensation to affected households. They

suggest developer should have harmonized compensation level and support

stable livelihood for affected households.

Almost affected households consent to project construction but some of them

wonder about compensation such as land areas and price of compensation.

Answers of developers and environmental consultants

Developer will provide documents relating to compensation to communal

authorities. Developer do not prepare resettlement plan since it is not require to

acquire any housing land. The method to calculate acquired land as well as

compensated expenses will be based on the current regulations setting by the

government. Measures of livelihood stability for affected households will be

studied by developer.

Sinh Phinh commune, Tua Chua district:

Questions from representatives from local authority and affected households

Chairman of communal people committee supports to project construction

however he requires developer to deal with complaints from affected persons on

compensated procedures and expenses, count of property on land.

Affected people complain on compensated land and expenses, livelihood after

acquired land for reservoir. They request developer to provide jobs and

livelihood for them when power plant is put into operation.

Some of affected residents raises issue of landslide because of power plant

construction and proposes that developer should compensate more land in case

if landslide occurs due to formation of reservoir.

Answers from developer and consultant:

Compensation of land areas, expenses as well as procedures will be done by

current regulations. Developer will coordinate to local authority to harmonize

the compensated requirements from affected households.

The landslide will be mitigated by developer during construction phase and

reservoir operation.

Regarding to supporting livelihood and providing new jobs for affected

residents, developer will try to deal with at the best effort.

Muong Bang commune, Tua Chua district

Questions from representatives from communal people committee and affected

households:

Vice chairman of Muong Bang communal people committee support to

construction project

Cultivate land in the commune is reclamation of residents from surrounding

areas so vice chairman requests developer coordinate to local authorities

supporting them on land ownership during compensated implementation.

Page 81: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

83

Answers from developer and consultant:

Developer will coordinate to local authorities and affected household preparing

compensated plan based on current regulations.

Issue of land ownership is responsible for local authority not developer.

Nam Nen commune, Muong Bang district

Questions from local authority and affected households:

Mr. Ton Van Cham, chairman of communal people assembly support to power

plant construction. He request developer to revise the list of affected households

since almost of affected household address of Phieng Dat A hamlet under Nam

Nen commune were wrong. It is necessary to revise with the aim of supporting

for compensated issue later. He also request developer to provide documents of

compensation to local authorities and affected households

Mr. Lo Van Thuan, chairman of communal fatherland front supports to project

and requires clarifying on compensated expense, area, committee etc.

Some participants said that beside compensation of land and property on land,

developer should compensate the tombs which are located on the project area.

Answers of developer and consultant:

Regarding to list of affected households from Phieng Dat A hamlet, developer

committed to coordinate to local authority supplement survey and revise it.

Regarding to issue of documents on compensation of land and property on land,

developer committed to providing to local authority and affected households

after revising list of affected households and compensated plan.

Regarding to compensation of land area, expense, committee etc, and developer

will comply with current regulations on clearance and compensation.

Regarding to ensure of hygienic issue during material transportation and

construction as well as coordinate to local authorities in security, developer

prepared mitigation measures reducing impacts to communities during

construction and operation phases.

Regarding to provide new jobs for affected people, developer try to support at

best effort but it has to depending on ability of residents.

Regarding to removing tombs, at present, developer did not detect any tomb

during survey. During construction phase in case if detecting any tomb,

developer will coordinate to affected people providing compensated plan and

supporting following regulations.

Sa Tong commune, Muong Cha district

Questions from local authorities and affected households:

The chairman of communal people committee said that construction of project

will impact to feeding cattle of community. Residents of Sa Tong commune do

not use water from Nam Muc River for agricultural and fishing purposes.

Land official of Sa Tong commune mentioned in reclamation that residents

resettle from Pa Ham commune to Sa Tong commune. It is requested developer

Page 82: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

84

coordinating to local authorities of Pa Ham and Sa Tong communes to provide

land ownership for affected people so that they could get compensation from

developer.

Answers from developer and consultant:

Regarding to impact of feeding cattle of local residents, developer

acknowledged and committed applying mitigation measures so that this impact

is negligible.

Developer will comply compensated policies of government. Issue of provide

land ownership for affected households is not responsible for developer.

Pa Ham commune, Muong Cha district

Questions from local authorities and affected households

Representatives from communal people committee supported project

construction but mentioned in complaining from residents and requested

developer to explain more detail on land compensation.

The chairman of communal people committee said that construction of Trung

Thu project cause loss of special fishing as well as benefit of local residents.

Mr. Lo Van Khuyen complained on compensation of land area and expense. He

also asked developer providing information on expense and property on land.

Mr. Lo Van Song supported to construct power plant but complained on

compensation and suggested developer to build new branch of irrigation system

for residents.

Mr. Lo Van Ong complained on low compensated expenses and suggested that

acquired land must be compensated by other land.

Mr. Lo Van Chu wanted that acquired land must be compensated by new land

or higher compensated expenses.

Mr. Lo Van Thang said that he lost water resource for cultivation due to project

construction damaged his pipeline. He requested developer to repair this

pipeline for his farm.

Mr Lo Van Liem complained on compensated land for this family which is

located in reservoir as well as counting his property on land.

Answers of developer and consultant:

Developer acknowledged on complains of losing fishing benefit and special

species. However, these impacts only occur during construction phase. After

formation of reservoir, the river ecosystem will be replaced by reservoir

ecosystem. Formation of reservoir will facilitate to local residents in feeding

and getting benefit from fishing. Moreover, project is categorized impoundment

type without changing of water flow so the minimum flow behind power plant

will be maintained to ensure development of aquatic ecosystem.

Regarding to ideal of building domestic water pipeline, developer committed to

repaired water pipelines in case if they are damaged by project. On the

Page 83: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

85

suggestion of ensuring social security in commune, developer committed to

establishing worker codes so that this impact will be mitigated.

Regarding to suggestion of providing compensated expenses of land and

property on land, developer committed to publish information of compensation.

Regarding to suggestion of building new branch of irrigation system in

commune, developer acknowledged and study more.

Regarding to ideal of low compensated expenses and suggested that acquired

land should be compensated by land, developer will comply with policies of

government. Parallel, developer will discuss with compensation committee,

local authorities to prepare satisfied compensated plan.

6. To revise EMP following to comments from local authorities and affected

people in the consultation meetings as well as in surveys.

7. To provide EMP to communal people committee of Sa Tong, Pa Ham, Trung

Thu, Sinh Phinh, Muong Bang to get comments from them.

8. To revise EMP again based on comments.

9.2. Disclosure

As policy of WB’s disclosure, developer will implement steps as below:

To provide EMP (approval by WB) in Vietnamese version to Tua Chua, Muong

Cha DONREs, Tua Chua, Muong Cha District People Committees of, Sa Tong,

Pa Ham, Nam Nen, Trung Thu, Sinh Phinh, Muong Bang Communal People

Committees.

The approved EMP in Vietnamese version will be disclosure at project site

during project implementation.

To provide EMP in both English and Vietnamese versions to Information

Development Center, 63 Ly Thai To street, Hanoi so that they are accessed by

NGOs and communities. EMP in English version is sent to WB Info shop for disclosure.

Page 84: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

86

List of reference documents

1 The compensation Plan of the project- Trung Thu hydropower joint stock company

2 Investment Report of Trung Thu hydropower project – Trung Thu hydropower

joint stock company

3 The World Bank’s Safeguard policies;

4 Environmental Impact Assessment of Trung Thu small hydropower project

5 Environmental safeguard framework for Vietnam Renewable Energy Development

Project- MOIT 2008, revised 2014.

6 Statistical yearbook- statistic publishing house

Page 85: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

87

Annex 1. List of people who prepared EMP

No. Name Agency

1 Mr. Nguyễn Xuân Bình

Director of Trung Thu hydropower joint stock

company

2 Mr. Vũ Ánh Dương

Head of Hydropower projects management

board

3

Mrs. Lại Thị Nhu

Environmental staff, Trung Thu hydropower

joint stock company

4 Mrs. Lê Thị Thanh Nhàn Environmental expert

Page 86: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

88

Annex 2: Responsibilities of safe and environmental supervising officer

The Target

The safe and environmental supervising officer supports the EMP efficiently during

the Trung Thu hydropower construction

To achieve the target of diminishing the environmental negative impacts of the project,

the contractor needs to comply with this management plan. Therefore, implementing

him environmental management plan will relate to the following units:

The safe and environmental officers of the contractor are responsible for supervising

the EMP and problems about safety and environment of the construction

The safe and environmental supervising officers of the developer are responsible for

the construction inspection and guarantee that the contractor will comply with the

requests in the contract and EMP

Tasks:

Overall responsibilities of the safe and environmental supervising officers including

supervision and inspection of construction activities to ensure that the mitigation

measures are implemented as appropriate in the plan so that environmental

management and the negative impact of the project on the environment is diminished.

The contractor is responsible for ensuring compliance with the environmental

management plan of the project and the contract conditions during construction under

the supervision of safety and the environment officer. Therefore, safety and the

environment officer is an independent supervisory personnel to ensure compliance

with the environmental management plan and ensure the full implementation of the

contractor for environmental issues

Personnel monitoring and environmental safety will examine monitor and implement

the environmental review for tenders and contracts for road construction. Supervisors

on safety and the environment have much knowledge and experience in monitoring

and verification of environmental issues and advise investors on implementation issues

of the project environment project. Personnel monitoring and environmental safety

should be familiar with the project work through the review of relevant reports,

including the report on environmental impact assessment (EIA) Trung Thu

hydropower project, environmental Management plan as well as the relevant technical

standards and contract documents.

Being a part of the construction examiner group, safety and environmental staff is

obliged to the following tasks

Phase 1: Preparation

The objective of Phase I is taking foundation for successful implementation of the

project. During this period, supervisors, safety and environment must: (i) consider the

DTM, environmental management plan, project design and technical standards to

assert not to miss these mitigation measures ; (ii) prepare guidelines for contractors in

the implementation of Environmental Management Plan; and (iv) develop and

implement training programs for activities related to construction.

Main tasks for this phase are:

Page 87: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

89

Desk study: supervisors on safety and the environment will review the DTM,

environmental management plan, project design and technical standards and certify in

writing expressly not to omit any mitigation measures. If problems arise, safety and

environment officers propose to the investor for additional updates in the

environmental management plan, project design and technical standards of this issue.

When the Investors, Board of Management and the World Bank project GDoE ratify,

personnel monitoring and environmental safety will conduct additional updates

environmental management plan

Environmental supervision directory: The safety and environment officers need to

create an examination directory during the construction for supervising the

implementation of the contractor. This includes the core issue of the project, the

requested mitigation measures and implementation plan

Diary: safety and environment supervising staff of the Contractor shall keep diaries to

record events or changes possibly implicate the assessment of environmental impact

and non-compliance attached to the proposals. Diaries must be always ready to serve

when the supervisory staff support as mentioned in the environmental management

plan and contract suggest. Safety and environment staff of the investor will verify this

diary.

Environmental training : Environmental safety staff of the investors are obliged to

design and implement a comprehensive training program for the Supervision Engineer,

Owner, environmental safety officers of the contractor (and workers as part of training

for supervisors, safety and environment), the environmental requirements of the

project and methods for monitoring and evaluation, especially should pay attention to:

Environmental management plan: the requirements of the Environmental Management

Plan, approved check list in supervising environmental, environmental sample

monitoring and processing methods for non-compliance with the management plan

environment and all the issues will be mentioned. Special attention should be paid to

the specific terms of the contract emphasized on compliance with the environmental

management plan

Health and safety: Health and safety requirements of the project must be apparently

verified and coordinated to the contractors and the investor (included in the technical

standard environment for the contractors

At the end of training, the contractor will sign a confirmation through training grasp of

environmental regulations, the environmental management plan and compliance

framework, on the health and safety obligations. Construction supervisors must sign

the certification through training understand the oversight responsibilities.

Phase 2 Construction activities supervision

Safety and environment officer of the investors will represent the Owner and

monitoring Chief Engineer:

Examining and monitoring independently the implementation of the

Environmental management plan

Performing random checks and review the profiles of environmental safety staff

of the Contractor

Page 88: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

90

Proceeding the inspection frequently in the building section

Reviewing the implementation of the mitigation measures is not right with the

environmental management plan and contract documents

Reviewing the effectiveness of the mitigation measures and the implementation

of environmental problems;

Reviewing the terms acceptable environmental construction methodology

(including temporary works and permanent works), designs and related

submissions. If necessary, staff safety and the environment have to research and

propose solutions to the environmental impacts discussed with the designers,

contractors and Investors

Verifying survey cases of non-compliance of environmental quality and

effectiveness of the remedial measures;

Providing feedback to the Owner and Chief Engineer under the supervision of

the process of non-compliance with the Environmental Management Plan;

Organizing training programs, including team environmental safety staff of the

contractors, evaluating issues identified an improve environmental compliance

method;

To conduct the contractors to repairs within the prescribed time, conducting

additional monitoring, if required, in accordance with the provisions of the

contract and procedures in case of non-compliance and complaints

To conduct the contractor to take measures to minimize the impact and comply

with the environmental management process required in the case of non-

compliance and inconsistency

To conduct the contractor to stop the construction activities which can cause

negative effects, and / or if the contractor fails to perform the requirements of

the Environmental Management Plan / not conduct operations as directed the

supervisor of environmental safety.

Review of the plan at site: To ensure the consistency throughout the project, safety

and the environment staff must consider the entire plan could affect the environment.

These plans include, but are not limited to: plan pits and dumps. Supervisors on safety

and the environment will be considered and approved the environmental management

of the project and plans to restore the landscape of the contractor. What parts of the

plan does not comply with the environmental management plan, environmental impact

assessment, personnel and environmental safety of the investors will work with the

Chief Engineer and the Contractor to take appropriate measures.

Health and Safety: To ensure consistency throughout the project, the environmental

safety officer must consider all of the safety plan of the contractor, and on the basis of

this plan, with the data of the investor's input, to create a comprehensive plan for

safety projects. Comprehensive Plan about project safety must include processes such

as blast management and safety in the construction process, preventing landslides / soil

erosion during the rainy season, ... These plans must be reviewed on an annual basis

and must be updated as necessary.

Page 89: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

91

The supervisors on safety and the environment must ensure compliance with the

provisions of health and safety in the contract documents. This Compliance includes,

but is not limited to: (i) the construction activities; (ii) dissemination of education on

HIV / AIDS; (iii) comply with the labor law of Vietnam; and (iv) traffic safety. For the

prevention of HIV / AIDS, not only focusing on the construction site, but also pay

attention to the nearby communities.

In case of violation in the requirements of technical standards, or contractual

conditions or non-compliance with the environmental management plan, safety and the

environment monitor immediately notify to the Chief Engineer of the Contractor ,

Chief Engineer supervision and investor. Safety and the environment supervisors must

also report violations to the Investor as part of the monthly report.

Diary of safety and the environment staff must always be ready to provide, upon

request by the support team of project management

Safety and the environment supervisors have to regularly review records of the

Contractor to ensure that all records are updated in accordance with reality and meet

the requirements of the Environmental Management Plan (etc the records of

complaints about environmental issues).

The unintended effect: In case of the incident which was not anticipated in the

environmental management plan and DTM, safety and the environment monitors must

be closely coordinated with the investor, the contractor and the project manager to

confirm that the problem has been resolved. Safety and the environment supervisors

must update Environmental Management Plan and implement guidelines, based on

that training for contractor personnel

Monthly Payment: safety and the environment monitoring officer must certify the

monthly payment for activities related to the environment as proposed by the

Monitoring Officer safety and the environment to the investor.

Roadwork’s and landscaping restore: safety and the environment monitoring

officer must closely monitor the operation to restore the site and landscaping in areas

such as land mines, quarries, wash stations vehicles, to ensure that activities are carried

out according to acceptable standards. Safety and the environment supervisors must be

consistent with the contractor about the recovery plan which should be implemented

before the end of construction activities.

Human Resource for the Project: safety and environmental supervisors and building

monitors group is expected to be mobilized 1 month prior to construction

commencement. In January, the safety and environmental monitor will be familiar

with the project, project design, specifications, contract documents, environment

protection commitment, environment management plan and other reports and

documents related to the project. Based on the review, monitoring officer safety and

the environment will report a summary of the issues that may arise in the process of

implementing the environmental management plan and the conditions of the contract

the recommend the Manager the best option to improve the process of implementing

the environmental management plan.

Supervisors and safety are expected to be mobilized in the early stages of the contract

to prepare the guidelines, documentation, training,

Page 90: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

92

Report: environmental safety officers must make a minimum of the following

documents: ...

Weekly reports on issues of non-compliance;

Monthly report summarizes the main issues and findings during surveillance

activities;

Quarterly report from the contractor's monthly report

Reports and data must be provided as required by the project manager.

At the end of the project, safety and environment monitoring staff set up a final report

summarizing the main findings, the non-compliance, the solutions ... as well as

guidance on implementing orientation this mission later.

Page 91: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

93

Annex 3. The approval documents on EIA

Page 92: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

94

Page 93: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

95

Page 94: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

96

Page 95: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

97

Page 96: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

98

Annex 4. Minute of Public Consultation Meetings

Page 97: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

99

Page 98: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

100

Page 99: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

101

Page 100: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

102

Page 101: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

103

Page 102: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

104

Page 103: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

105

Page 104: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

106

Page 105: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

107

Page 106: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

108

Page 107: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

109

Page 108: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

110

Page 109: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

111

Page 110: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

112

Page 111: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

113

Page 112: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

114

Page 113: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

115

Page 114: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

116

Page 115: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

117

Page 116: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

118

Page 117: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

119

Page 118: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

120

Page 119: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

121

Annex 5. Permission of providing land for project construction

Page 120: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

122

Page 121: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

123

Page 122: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

124

Page 123: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

125

Annex 6. Some pictures of consultation meetings and vegetation cover of project site

Page 124: ENVIRONMENTAL MANAGEMENT PLAN - Documents & Reports · 2016-07-12 · 9. Estimated cost for environmental management plan 10. Public consultation and disclosure List of reference

126