-
KHANH HOA PROV1NCIAL PEOPLE'S COMMITTEE
NHA TRANG CITY ENVIRONMENTAL SANITATION PROJECT MANAGEMENT
UNIT
ENVIRONMENTAL IMPACT ASSESSMENT
REPORT
FOR
COASTAL CITIES ENVIRONMENTAL SANITATION PROJECT
NHA TRANG SUB-PROJECTS - PHASE 2
COMPONENT 3 - SOLID WASTE MANAGEMENT (FINAL REPORT)
NHA TRANG, FEBRUARY, 2011
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
wb371432Typewritten TextE1295 V14
wb371432Typewritten Text
wb371432Typewritten Text
-
., "',,,'
-
KHANH HOA PROVINCIAL PEOPLE'S COMMITTEE NHA TRANG CITY
ENVIRONMENTAL SANITATION PROJECT MANAGEMENT UNIT
ENVIRONMENTAL IMPACT ASSESSMENT COASTAL CITIES ENVIRONMENTAL
SANITATION PROJECT-
NHA TRANG SUB-PROJECTS
COMPONENT 3 • SOLID WASTE MANAGEMENT
INVESTOR
NHA TRANG CITY ENVIRONMENTAL SANITATION PROJECT MANAGEMENT
UNIT
G ~ lDOC
CONSULTANT
LAC VIET INVESTMENT, ENVIRONMENTAL TECHNOLOGY
AND INFRASTRUCTURE TECHNIQUES JOINT STOCK
COMPANY (LAVIC)
-----..
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Suh-project Component 3 - Solid Waste
Management
TABLE OF CONTENTS
Page .
1. BACKGROUND OF THE PROJECT
...............................................................................
1
2. LEGAL DOCUMENTS
.....................................................................................................
2
3. IMPLEMENTATION
........................................................................................................
6
CHAPTER 1: EXECUTIVE SUMMARY OF THE PROJECT
............................................... 7
1.1. PROJECT TITLE
...........................................................................................................
7
1.2. PROJECT OWNER
........................................................................................................
7
1.3. OVERVIEW OF COMPONENT 3 PHASE 2
............................................................. 7
1.3.1. Location of the Sub-project
....................................................................................
7
1.3.2. Procurement of equipments
..................................................................................
11
1.3.3. Construction of waste collection points and Transfer
points ............................... 11
1.3.4. Transport leachate from Ru Ri landfill to the Luong Hoa
landfilL ..................... 13
1.3.5. Redesign of Landfill Luong Hoa
..........................................................................
14
1.3.5.1. Adjustment of Rock Excavation
....................................................................
14
1.3.5.2. Redesign of liner system
................................................................................
15
1.3.5.3. Improvment of leachate management
............................................................ 15
1.3.5.4. Shift and redesign of hazardous waste cell
.................................................... 15
1.3.5.5. Redesign Luong Hoa Leachate Treatment Plant..
.......................................... 16
1.3.6. Total capital investment and operation schedule of
Component 3 ...................... 18
CHAPTER 2: NATURAL, ENVIRONMENTAL AND SOCIO-ECONOMIC CONDITIONS
..........................................................................................................................
20
2.1. NATURAL CONDITIONS
..........................................................................................
20
2.1.1. Geotechnical and hydro-geological conditions
.................................................... 20
2.1.1.1. Geo-technical conditions
................................................................................
20
2.1.1.2. Hydro-geological features
..............................................................................
20
2.1.1.3. Topography
....................................................................................................
22
2.1.2. Climate
.................................................................................................................
22
2.1.2.1. Air temperature
...............................................................................................
22
2.1.2.2. Rainfall
...........................................................................................................
23
2.1.2.3. Wind
...............................................................................................................
23
2.1.2.4. Moisture
..........................................................................................................
23
2.1.2.5. Evaporation
....................................................................................................
24
2.1.2.6. Solar radiation
................................................................................................
24
2.1.2.7. Typhoon
..........................................................................................................
24 ,.;f
2.1.3. Ecosystem
.............................................................................................................
25
2.2. SOCIO-ECONOMIC CONDITIONS
..........................................................................
25
2.2.1. Economic development situation
.........................................................................
25
EIA, LA VIC Consultant, February 2011 i
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
2.2.1.1. Development of industry
................................................................................
25
2.2.1.2. Development of agriculture - forestry - aquaculture
..................................... 26
2.2.1.3. Tourism and services
......................................................................................
26
2.2.1.4. Cultural works
................................................................................................
26
2.2.2. Social development situation
................................................................................
27
2.2.2.1. Population
.......................................................................................................
27
2.2.2.2. Culture
............................................................................................................
27
2.2.2.3. Education
........................................................................................................
27
2.2.2.4. Health service
.................................................................................................
27
2.3. CURRENT SITUATION OF TECHNICAL INFRASTRUCTURES
.......................... 28
2.3.1. Flooding and inundations
.....................................................................................
28
2.3.2. Current situation of solid waste collection in Nha Trang
City ............................. 28
2.3.2.1. Composition of solid waste
............................................................................
28 .
2.3.2.2. Solid waste generation
....................................................................................
29
2.3.2.3. Current Situation of Urban Waste Collection
................................................ 32
2.3.2.4. Current Situation of Waste Collection from the Islands
................................ 33
2.3.2.5. Current Situation of Medical Waste Collection and
Treatment ..................... 33
2.3.2.6. Current Situation of Collection of Construction Waste
and Debris ............... 33
2.3.2.7. Current Situation of Industrial Waste Collection
(Hazardous Wastes) .......... 33
2.3.2.8. Solid Wastes in Rivers and Beaches
..............................................................
34
2.4. EXISTING ENVIRONMENTAL STATUS
................................................................
34
2.4.1. Air environment
...................................................................................................
34
2.4.2. Surface water environment.
..................................................................................
37
2.4.3. Underground water
...............................................................................................
38
2.4.4. Leachate Quality
...................................................................................................
38
CHAPTER 3: ENVIRONMENT IMPACT ASSESSMENT
.................................................. 40
3.1. SOURCES OF IMPACTS
............................................................................................
40
3.1.1. Sources of impact
.................................................................................................
40
3.1.2. Objects of impact.
.................................................................................................
40
3.2. ENVIRONMENTAL IMPACTS
.................................................................................
41
3.2.1. Preparation Phase
.................................................................................................
41
3.2.2. Construction Phase
...............................................................................................
41
... 3.2.3. Operation Phase
....................................................................................................
43 3.2.3.1. Impacts on health
............................................................................................
43
3.2.3.2. Impacts on labour
...........................................................................................
44
3.3. ENVIRONMENTAL PROBLEMS AND RISKS
.......................................................................
44
3.3.1. Risk
.......................................................................................................................
44
3.3.2. Labour and traffic accidents
.................................................................................
44
CHAPTER 4: MITIGATION MEASURES
............................................................................
45
EIA, LA VIC Consultant, February 2011 ii
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
4.1. MITIGATION MEASURES IN CONSTRUCTION PHASE
...................................... 45
4.2. MITIGATION MEASURES IN OPERATION PHASE
.............................................. 45
4.2.1.1. For Luong Hoa landfill
...................................................................................
45
4.2.1.2. For collection and transfer points
...................................................................
45
4.3. FIRE AND EXPLOSION PREVENTION MEASURES
............................................. 46
4.4. HYGIENE AND LABOR SAFETy
.............................................................................
46
4.5. COMMUNICATION AND EDUCATION
..................................................................
47
CHAPTER 5 : ENVIRONMENTAL MANAGEMENT PLAN
.............................................. 48
5.1. MITIGATION MEASURE PLAN
...............................................................................
48
5.1.1. Summarized plan for mitigation measures during three
principal stages ............ 48
5.1.2. Public information program and community relation
.......................................... 49
5.2. ENVIRONMENTAL MONITORING PROGRAME
.................................................. 50
5.3. ORGANIZATION OF ENVIRONMENTAL MANAGEMENT AND ii
RESPONSIBILITY
..............................................................................................................
53
5.4. COSTS ESTIMATED FOR ENVIRONMENTAL MANAGEMENT PROGRAM ....
55
5.4.1. Monitoring cost ofIndependent Environmental Monitoring
Consultant (IEMC)56
5.4.2. Implementation cost of monitoring program
........................................................ 56
5.4.3. Total Estimated Budget Cost for EMP implementation
....................................... 56
CHAPTER 6: PUBLIC CONSULTATION
............................................................................
58
6.1. THE OBJECTIVES OF PUBLIC CONSULTATION
................................................. 58 I
6.2. PUBLIC CONSULTATION IMPLEMENT
................................................................
59
6.2.1. Public consultation in accordance with WB' policy
............................................ 59
6.2.2. Public consultation in accordance with Circular No.
OS/2008/TT-BTNMT ........ 60
6.3. RESULTS OF PUBLICCONSULTATION
.................................................................
60
." 6.3.1. Results of public consultation
..............................................................................
60 6.3.2. Opinions from local governments
........................................................................
61
6.4. PUBLIC DISCLOSURE
..............................................................................................
61
CONCLUSIONS, RECOMMENDATIONS AND COMMITMENTS
................................... 62
1. CONCLUSIONS
..............................................................................................................
62 .m
2. RECOMMENDATIONS
.................................................................................................
62
3. COMMITMENT
..............................................................................................................
63
-
ElA, LA VIC Consultant, February 2011 iii
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
LIST OF TABLES
Page
Table 1-1: list of equipments
....................................................................................................
11
Table 1-2: list of waste collection points at markets in Nha
Trang .......................................... 11
Table 1-3: Project implementation schedule of Component 3
................................................. 19
Table 2-1: Wind speed in dominant directions (m/s)
...............................................................
23
Table 2-2: Average monthly and annual air humidity at Nha Trang
station (%) ..................... 23
Table 2-3: Total of monthly and annual evaporation capacity (mm)
....................................... 24
Table 2-4: Average monthly and annual sunshine hour variation in
Nha Trang station (%) ... 24
Table 2-5: Some features of typhoons in Khanh Hoa
..............................................................
24
Table 2-6: Production value at current price ofNha Trang City
divided by economic sectors in 2005 - 2007
.......................................................................................................................
25
Table 2-7: Production value of agriculture at current price
ofNha Trang City ....................... 26
Table 2-8: Average population ofNha Trang City 2004 - 2008
............................................. 27
Table 2-9: Quantities of waste collected in 2009 (URENCO, 2010)
....................................... 30
Table 2-10: Predicted solid waste quantities generating in Nha
Trang .................................... 31
Table 2-11: Results of ambient air quality
...............................................................................
34
Table 2-12: Analysis results of surface water quality in the
study area ................................... 37
Table 2-13: The analysis results of groundwater quality at
project area .................................. 38
Table 2-14: The results ofleachate quality and flow at Ru Ri
landfill .................................... 39 fi '
Table 3-1: Sources, objects and degree of impacts during
implementing Component 3 ......... 40
Table 3-2: Characteristics of the construction items of the
Component 3 - Phase 2 .............. 41
Table 5-1: Summarized plan for mitigation measures
.............................................................
48
Table 5-2: Environmental Monitoring Supplement for Component 3
in Phase 11 ................... 50
Table 5-3: Locations of ambient air monitoring supplement for
Component 3 in Phase II ..... 51
Table 5-4: Institutional Responsibilities
...................................................................................
54
Table 5-5: Cost for Environmental Monitoring Program for
Component 3 - Phase II ........... 56
Table 5-6: Total cost for environmental management plan
..................................................... 56
Table 6-1: First round public consultation conducted by LA VIC
............................................ 59
Table 6-2: Second round public consultation conducted by LAVIC
....................................... 60
EIA, LA VIC Consultant, February 2011 iv
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
LIST OF FIGURES
Page
Figure 1-1: Map oflocations of Component 3 - Phase 2
........................................................... 8
Figure 1-2: Transportation pipe between Ru Ri and Luong Hoa
Landfills ................................ 9
Figure 1-3: Locations of transferred solid waste stations and
the main transportation routes to landfill
................................................................................................................................
10
Figure 1-4: Basic design collection point
.................................................................................
13
Figure 1-5: Proposal for moving hazardous cell out oflandfill
pit.. ....................................... 16
Figure 1-6: Chart of Leachate treatment process in the Luong Hoa
Landfill .......................... 17
Figure 2-1: Composition of household waste
...........................................................................
28
Figure 2-2: Composition of waste from restaurants
.................................................................
28
Figure 2-3: Composition of waste from market..
.....................................................................
29
Figure 2-4: Composition of waste from offices
.......................................................................
29
Figure 2-5: Sampling loactions of eEnvironmental quality in
Component 3 - Phase 2 .......... 36
Figure 5-1: Map of environmental monitoring program for
Component 3 - Phase 2 ............. 52
Figure 5-2: Flowchart ofEMP implementation reporting
........................................................ 53
; ,
ElA, LA VIC Consultant, February 2011 v
-
.. ~i
,""
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project
ADB CAS DOC DOF DPI DONRE EAI EMP EIRR FIRR FS GSO GoV MOF
LAVIC
MOC MPI MOSTE NRW NPV O&M PPC PMU PC PM URENCO USD VND VAT
WB WSDC wrp
Component 3 Solid Waste Management
ABBREVIATION
Asian Development Bank Country Assistance Stratergy Department
of Construction Department of Finance Department of Planning and
Investment Department of Natural Resources and Environment
Environment Impact Assessment environment management plan Economic
internal rate of return Financial Internal Rate of Return
Feasibility Study General Statistics Office Government of Vietnam
Ministry of Finance Lac Viet Investment, Environmental Technology
and Technical Infrastructure Joint-Stock Company Ministry of
Construction Ministry of Planning and Investment Ministry of
Science Technology and Environment NonRevenue Water Net Present
Value Operation and Maintenance Provincial People's Committee
(Vietnam) Project Management Unit People's Committee Prime Minister
(Vietnam) Urban Service and Environment Company United Sates Dollar
Vietnam Dong Value Added Tax World Bank Water Supply and Drainage
Company Water Treatment Plant
EIA, LA VIC Consultant, February 2011 vi
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
INTRODUCTION
1. BACKGROUND OF THE PROJECT
Nha Trang City Environmental Sanitation Project is one of the
three sub-projects under
the Coastal Cities Environmental Sanitation Project (including
Quy Nhon, Dong Hoi and
Nha Trang). The Project has been proposed in order to solve the
existing serious
environmental sanitation problems, improve environmental
sanitation conditions of the
cities, improve the local resident's living standards as well as
to ensure sustainable
economic development.
The Project shall be financed under the World Bank's loan and on
the basis of experiences
from other projects funded by the WB such as environmental
sanitation projects in Ho Chi
Minh and Hai Phong cities.
The project shall be divided into 2 phases (phase 1: 2006-2011;
Phase 2: 2011-2014) and
include 6 components:
Component 1: Drainage, Flood Controlling and Wastewater
Collection;
Component 2: Wastewater Treatment Plant;
Component 3: Solid Waste Management;
Component 4: Development of Resettlement Areas;
Component 5: Sanitation Revolving Fund
Component 6: Capacity Building and Executive Assistance.
According to the Credit Agreement, the Component 3 shall be
implemented in two phase.
The Phase 1 included:
Build the Luong Hoa landfill of 6ha areas, which ensure that
meet the safely
deposal of solid waste in Nha Trang City.
- Rehabilitate the existing landfill and close Ru Ri
landfill.
- Purchasing equipments (dustbins and solid waste pressing cars)
to improve the
effective of solid waste collection in the central areas and new
urban areas in the
north and the south ofNha Trang City.
So far, Only the purchasing equipments has been completed, and
the construction of
Luong Hoa landfill is in process.
Implementation of Compo 3, Phase 2 according to the Credit
Agreement consists of
following contracts:
• Supply of Solid Waste Equipment (NT-3.3)
EIA, LA VIC Consultant, February 2011 1
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
• Development of Luong Hoa Landfill Site (ph2) (NT-3.4)
• Transfer and Collection Points (NT-3.5)
However, in its letter dated January 22, 2010 PMU requested the
consultant not to
take into consideration extension of the landfill but to review
existing design for phase 1
with the aim to:
• Re-evaluate all equipment and installations according to the
reduced
capacity;
• Improve the design to increase the capacity;
• Aim to cover increasing costs by design adjustments
• Develop new drawings and BoQs accordingly.
In order to complete necessary legal procedures, the Project
Owner has collaborated with the consulting unit - Lac Viet
Investment, Environmental Technology and Infrastructure Engineering
JSC (LAVIC) - to prepare the environmental impact assessment report
and the environment management plan in accordance with the
regulation on environment protection of the Vietnamese Government
and the World Ban1e
In the framework of this report, the Consultant LACVIC shall
evaluate the impacts on environment, social and environment
management plan for the implementation of Component 3. The impacts
include potential, positive and negative, direct and indirect, long
tenn and short tenn. Based on these forecast and assessment,
mitigation measures (include management and technical measures)
shall be proposed to take full advantage of the positive impacts
and minimize the negative impacts on natural and social environment
during the project implementation.
2. LEGAL DOCUMENTS
2.1. Legal basis
- Law on Environmental Protection No. 52/2005/QH 11 dated
November 29, 2005 by the National Assembly of the Socialist
Republic of Vietnam;
- Decree No. 80 12006/ND-CP dated August 9, 2006 by the Go V in
regard of detail stipulation and guideline for execution of some
articles of the Law on
Environmental Protection;
- Decree No. 2112008/ND-CP dated February 28, 2008 in regard of
amendment and
addition of some articles of the Decree No. 80/2006/ND-CP dated
August 9,2006 by the Go V in regard of detail stipulation and
guideline for execution of some
articles of the Law on Environmental Protection;
- Circular No. OS/2008fIT-BTNMT dated December 8, 2008 by the
Ministry of
Natural Resource and Environment in regard of guideline for
strategic
EfA, LA VIC Consultant, February 2011 2
-
-••
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
environmental assessment, environmental impact assessment and
environmental protection commitment;
- Decree No. 209/2004/ND-CP dated of December 16,2004 by the GoV
in regard
of quality management of construction works;
Decree No. 16/2005/ND-CP dated February 7, 2005 by the GoV in
regard of
management of construction investment projects;
- Decree No. 11212006/ND-CP dated September 29, 2006 by the GoV
in regard of amendment and addition of some articles of the Decree
No. 16/2005/ND-CP in
regard of management of construction investment projects;
- Decision No. 13/2007/QD-BXD dated December 18, 2006 by the
Ministry of
Natural Resource and Environment in regard of compulsory
application of
Vietnamese Standards on Environment;
Letter No. 175112007 IBXD-VP dated August 14, 2007 by the
Ministry of
Construction in regard of issuance of Norms on project
management costs and
consulting costs for the construction investment projects.
2.2. Related documents
Decision No. 65!TTg-CN dated January 11,2006 in regard of
approval of the Pre-FS Report for the Coastal Cities Environmental
Sanitation Project including Nha
Trang City sub-project;
Memorandums of the Coastal Cities Environmental Sanitation
Project and
Memorandums prepared by the preparation delegation of Nha Trang
City Sub-
project;
Memorandum dated March 5, 2004 between WB's Missions and Khanh
Hoa PPC
in Nha Trang city;
Terms of Reference (TOR) dated March 25, 2004 by the WB's
Mission and the
Project Preparation Delegation;
General Adjusted Master Plan of Nha Trang to 2020 and General
Master Plan of
Con Minh Area to 2020 (under preparation); and
Report on Project Viewpoint by the International Coordinator;
Reports by the
international experts on wastewater treatment, solid waste and
resettlement; Policy
frame on resettlement assistance.
The standards and regulations applied for the environmental
sanitation subproject of Nha Trang City are listed as bellows:
EIA, LA VIC Consultant, February 2011 3
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
.....
Standard No Contents
22TCN 224-93 Road mechanical means - Specifications on technical
safety inspection and environment protection.
TCVN 5298-1995 General requirements for usage of wastewater and
its sediment sludge for irrigation and production of
fertilizer.
TCVN 5302-1995 General requirements for land reclamation (mining
activities and coverage of Landfills).
TCVN 5524-1995 General requirements for protection of surface
water against contamination.
TCVN 5525-1995 General requirements for protection of
underground water.
QCVN 05: 2009 National Technical Specifications on quality of
surrounding air.
QCVN 06: 2009 National Technical Specifications on some toxic
substances surrounding air.
QCVN 07:20081BINMT National Technical Specifications on
dangerous solid wastes.
QCVN 08:20081BINMT National Technical Specifications on surface
water quality.
QCVN 09:20081BINMT National Technical Specifications on
underground water quality.
QCVN 14:20081BINMT National Technical Specifications on domestic
wastewater.
QCVN 25:20081BINMT National Technical Specifications on
wastewater from the solid waste Landfills.
TCVN 5948-1995 Maximum allowable noise level for the road
transportation means.
TCVN 5949-1995 Maximum allowable noise level in public and
residential areas.
TCVN6962:2001: Vibration and Seism - Vibration due to
construction activities and industrial production - Maximum
allowable level in public and residential areas.
TCVN 5970-1995 Preparation of plans for monitoring of
surrounding air quality.
TCVN 5980-1995 Water quality - Standards of groundwater
quality.
TCVN 5999-1995 Instructions for wastewater sampling (ISO
5667-10:1992).
TCVN 6431-1998 Road traffic means - Polluting exhaust fumes from
vehicles and motors with gasoline engines.
TCVN 6436-1998 Noise from road traffic means while parking.
TCVN 6438-2001 Air quality - Exhaust fumes from road traffic
means - Maximum allowable limit.
- TCXD 66-1991 Operation of water supply and drainage systems -
Safety Regulations.
TCVN 6772:2000 Water quality - Domestic wastewater - Pollution
limit.
TCVN 6774:2000 Water quality - Quality of fresh water -
Protection of aquatic life.
EfA, LA VIC Consultant, February 2011 4
-
~ I
.'
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
Standard No Contents ....
TCVN 6696- 2000 Solid wastes - Sanitary landfills - General
requirements on environment protection.
TCVN6705 Non-hazardous solid wastes - Classification.
TCVN6706 Hazardous solid wastes - Classification.
TCVN7222: 2002 General requirements on environment for the
centralized wastewater treatment plants.
QCVN 0112009IBYT National Technical Specifications on drinking
water quality.
QCXDO 1/2008IBXD Vietnamese Construction Specifications -
Construction Masterplan.
2.3. Environmental policies of the World Bank
Besides the environmental review and approval procedures of the
Vietnamese Government applied to coastal cities environmental
project, Nha Trang City sub-project must be prepared and
implemented in compliance with environmental and social safety
policies of the World Bank. According to these safety policies, the
World Bank has classified the project as type A project that has
negative impacts on the environment, at a large scale and has multi
- dimensional and unprecedented impacts. These effects can cover a
large area than the construction area.
According to the requirements of World Bank, the environmental
assessment (EA) of projects has to prepare and propose a financing
bank to ensure that they are environmentally sound and sustainable,
and thus to improve decision making. The polices, requirements and
regulations ofWB are applied for EIA and RAP including:
• Environment assessment - Operation Process I Procedures of the
Bank (OPIBP 4.01): • Physical Cultural Resource (OPIBP 4.11) •
Involuntary Resettlement (OPIBP 4.12)
Consultation: According to the operation procedures of the World
Bank and the Decree No. 2112008JND-CP, an A-type project must be
consulted two times, the content of each consultation program must
be recorded.
The first consultation will be conducted for households who can
be affected by the project component implementation. This
consultation process shall be conducted with the Program of
economic-social survey and the environmental data collection from
the project implementation area. The second consultation about the
Draft Report on Environmental impact assessment for Component 3 was
conducted in May 2010. Meeting minutes of the consultation meetings
are attached in the annex.
Disclosure of information: According to the operation procedures
of the World Bank and the Decree No. 80/2006JND-CP and the Decree
No. 2112008JND-CP, Report on Environmental impact assessment must
be mass published. The Report on Environmental impact assessment
must be displayed at Washington DC, Vietnam Development Information
Center (VDIC) in Hanoi, People's Committee ofNha Trang City, Khanh
Hoa Department of Natural Resources and Environment, Project
Management Unit of the
EIA, LA VIC Consultant, February 2011 5
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
Project for improvement of environmental sanitation of Nha Trang
City, People's Committee of communes in the research area of the
project.
3. IMPLEMENTATION
3.1. EIA Report Preparation Agency
Lac Viet Investment, Environment and Infrastructure Engineering
Joint Stock Company (LA VIC)
Representative:
Position:
Address:
Tel:
E-mail:
Mr. Nguyen Phan Anh
Director
No.9, Duong Thanh Street, Hoan Kiem District, Hanoi.
(04) 3 923 2977
[email protected]
3.2. Applied Methods and Implementation
The EIA Report of the Component 3 "Solid Waste Management" shall
be made by the
following methods:
- Statistical Method: Collection of meteorological,
hydrological, river and socio-
economic data, reports and information on annually measured
environmental data
and processing of such collected data;
- Method of Onsite Survey and Sampling and Laboratory Analysis
of environmental
quality parameters: Determination of parameters of current
situation of
environment.
- Method of Rapid Assessment: Calculation of pollution tonnage
on the basis of
pollution coefficient in each phase of the Project.
- Method of Socio-economic Investigation: Investigation of
Project areas and the
areas affected by the Project, determination of existing
situation of the popUlation
and their awareness on environment, community consultation on
environment
impacts during the Project implementation period.
EM, LA VIC Consultant, February 2011 6
-
....
....
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
CHAPTER 1: EXECUTIVE SUMMARY OF THE PROJECT
1.1. PROJECT TITLE
Coastal Cities Environmental Sanitation Project (CCESP) - Nha
Trang City Environmental
Sanitation Sub-project, Phase 2 ~ Component 3.
1.2. PROJECT OWNER
The Khanh Hoa Provincial People's Committee (Khanh Hoa PPC).
1.3. OVERVIEW OF COMPONENT 3 - PHASE 2
1.3.1. Location of the Sub-project
Nha Trang City Environmental Sanitation Sub-project (Hereinafter
referred to as Nha
Trang Sub-project) under the Coastal Cities Environmental
Sanitation Project that
includes 3 cities of Nha Trang, Dong Hoi and Quy Nhon. At
present, there are 19
urban wards and 8 suburban communes in Nha Trang City. Solid
waste collection and
management has undertaken in the entire Nha Trang City by the
Nha Trang Urban
Environment Company (URENCO). The location ofNha Trang
Sub-project is shown
in the Figure 1-1.
EfA, LA VIC Consultant, February 2011 7
-
01; , • i II, i I .. t Coastal Cities Environmental Sanitation
Project (CCESP) - Phase 2 Nha Trang City Sub-project
600.000 &15.000 610.000 25QO 5000m
EfA, LA VIC Consultant, February 2011
'" 111; III
615,000
..,
620.000
Component 3 - Solid Waste Management
FIGURE 1-1: MAP OF LOCATIONS OF COMPONENT 3 - PHASE 2
(Scale: 1 : 12500)
LEGEND:
,:, Dislrict People Committee House
CAM R.'1NH Name 01 Oistric:1lCity
"" - Name of CommuneNVard
River
-(i}- National Road and Number
--[1!i2!- Provincial Road and Name --c:::J-- Railway and
Sialion
01herRoad
Boundary Lina
!,OCATIQIIS OE.J:llJ>;.
~ Transfer Points
~ leachale Pipe
o Landfils (Luong Hoa and Ru Ri)
8
-
....
-
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
Den Stream Leachate Pipe
Figure 1-2: Transportation pipe between Ru Ri and Luong Hoa
Landfills
EM, LA VIC Consultant, February 2011 9
-
Coastal Cities Environmental Sanitation Project (CCESP) - Pbase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
\
32.0 17M
1,0 Vinh Hal Market transfer point
Dam Market transfer point
I.e
Vinh Truong ward transfer point
Figure 1-3: Locations of transferred solid waste stations and
the main transportation routes to landfill
EIA, LA VIC Consultant, February 2011 10
-
.. II
II
..
...
•
IlL
... l1li.
-'. -'lill
.M
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
1.3.2. Procurement of equipments
In the Phase 2 of Component 3, the equipments and vehicles will
be invest as follows:
Table 1-1: list of equipments
No Equipment Quatities
1 Dustbins 660 liters 720
2 ins 240 liters 77
3 Push carts 75
4 Dump truck 4 tons 6
5 Dump truck 5 tons 1
6 Dump truck 7 tons 2
7 Boat for servicing the islands 1
8 Press container for transfer point 5
9 Skip truck for press container 1
10 Compactor for landfill 1
11 Wheel loader for landfill 1
1.3.3. Construction of waste collection points and Transfer
points
.:. Collection points:
•
After surveyed all places at the hospitals, schools, markets and
supermarkets where the land-use belongs to the public, it is
recommended to prepare these 25 sites as collection points during
Phase 2 (see Table 1-2) .
1
Table 1-2: list of waste collection points at markets in Nha
Trang
BaLang VinhLuong On Duong Hien Quyen St., 50 m fromDien Bien Phu
St.
2 Dai Han Crossing VinhHoa On 2/4 St., near North Coach
Station
3 VinhHai VinhHai At the corner between Nguyen Khuyen Street and
2/4 St.
on Thuy VinhPhuoc
5 Vinh Tho Vinh Tho
6 Dam Van Thanh
7 Flea Market VanThang
8 Phuong Sai Phuong Son
EIA, LA VIC Consultant, Fehruary 2011
122 Son Thuy St., from 214 St. 500m
On 2/4 Street, 200m from Xom Bong bridge on the North
I The area surrounded by Xuong Huan St., Nguyen Hong Son St. and
Nguyen Thai Hoc S1.
At the corner between Yet Kieu St. and Tran Quoc Toan .St
On Phuong Sai St., 1 km from Thong Nhat St.
11
-
iii
iii
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
9 Vinh Ngoc Vinh Ngoc Far away Dua bridge 2 km on the north
10 VinhHiep
11 Vinh Thai
12 Ga Vinh Thanh
13 Vinh Tnmg
14 Lac Long Quan
15 XomMoi
16 Flea Market
17 DongNai
18 Phuoc Tin
19 Hoang Dieu
20 Binh Tan
21 CuaBe
22 DiemCang
23 HonRo
24 HienNhi
25 VinhLuong
Vinh Hiep On 23/1 0 Street, 50m from Dua bridge
Vinh Thai From 23/1 0 Street 1 km on the south
Vinh Thanh
VinhTnmg
PhuocTan
Tan Lap
Phuoc Tien
PhuocHai
PhuocLong
VinhNguyen
Phuoc Long
Vinh Truong
VinhNguyen
PhuocDong
VinhPhuoc
VinhLuong
on Trung Tam Xa Street, 50 m from 23/1 0 Street on the north
Km 7, 23/10 Street
on Lac Long Quan St., 50m from Van Kiep St.
The area surrounded by Vo Tru St., Ngo Gia Tu .St and Huynh Thuc
Khang St.
At the comer between Truong Dinh St. and Tran Binh Trong St.
on Dong Nai Street
end of Be Van Dan Street
on Hoang Dieu St., near Vinh Nguyen 1 school, lkm from Tran Phu
St.
At the comer between Truong Sa St. and Vo TIll Sau St.
91 Vo TIll Sau street
At the comer between Tran Phu St. and Phan Van Tri St.
At the comer between Nguyen Xi St. and Ton Duc Thang St.
Near Ha Ra bridge
At Vo Tanh Village
Locations for dustbins: Dustbins shall be placed on the
pavements. On these places, a small slope shall be provided for
convenience in moving and drawing dustbins.
The area of collection point: 5.30m x 1.36m = 7.20 m2•
The basic design collection point is shown in following
figure:
EIA, LA VIC Consultant, February 2011 12
-
•
II
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
COLLECTION POINT Case 2
HOUSE OR PLOT
FOOTPATH
STREET
Figure 1-4: Basic design collection point
.:. Transfer points:
In accordance with URENCO transfer points are recommended
at:
• Vinh Hai market (public toilets existing), area of 100m2;
• Dam market (public toilets existing), area of 160m2;
SECTION 9-8 .$:* !/lX'
• Vinh Truong Village including transfer of waste from islands
(public toilets existing), area of 120m2•
The basic design of transfer points are decribed in figures in
Annex.
1.3.4. Transport leachate from Ru Ri landfill to the Luong Hoa
landfill
- Transmission of leachate via tanker (option I)
- Transmission of leachate via pump and pipeline (option 2)
The first option includes the purchase of a tanker. The settling
basin would serve as the
storage and balancing tank. Depending on the size of the tanker
app. 4 to 6 trips during
the day would be required for the estimated leachate
quantities.
Investment cost is lower for the second option.
Operation cost are considerably lower, taking into account that
in option I a driver! operator must be available 7 days a week.
Also fuel cost is much lower compared to a
full size diesel truck.
EIA, LA VIC Consultant, February 2011 13
-
II
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
Maintenance cost is also considerably lower and the service
easier for a small pump as required.
For these reasons, it is recommended to follow Option 2.
Pumping station will be located at the site of the e settling
tank and pipes are laid in the
shoulder of the new access road to Luong Hoa landfill. No
additional land is required.
Option 2 includes:
Construction of a small pump station (Q= 3.6 cbmlh, H= 15m).
- Pressure line to the highest point of the access road to LH
landfill near the administration building, L=360 m, location in the
embankment of the access road (width 1m).
Power supply cable and data transfer cable (L=360 m) parallel to
pressure line.
Gravity line to the inlet of the leachate treatment Luong Hoa,
L= 570m.
1.3.5. Redesign of Landfill Luong Hoa
By request from PPC (pMU letter dated 22.01.2010), no expansion
of Luong Hoa landfill
will be implemented, instead revision of existing design Phase 1
will be carried out.
The design of Luong Hoa landfill Phase 1 has been reviewed by
the Consultant. Based
on the new data of under-construction Luong Hoa landfill, a
number of changes have
been proposed aiming on increasing the capacity, improving the
landfill performance,
adjusting problematic or inappropriate design and gaining more
cost efficiency.
Landfill redesigning is to solve the issues as follows:
- Re-designing rock excavation in the reasonable volume,
technical geometry to reduce the cost of excavation;
- Re-designing the lining system to avoid using qualitative
natural clay required that cannot found in Khanh Hoa province
region;
- Generating possible measures by re-design to compensate the
lost volume of landfill capacity caused by reduction of rock
excavation.
- Redesign the leachate collection system to improve the
performance of the landfill and leachate treatment efficiency to
meet current standard.
1.3.5.1. Adjustment of Rock Excavation
• Reducing landfill area at Southern embankment;
Areas at the Southern embankment, which require massive
excavation works, will be excluded from landfill bed and therefore
from liner construction. At the South-East comer ofthe landfill a
strip of2.700 m2 will be excluded.
• Construction of steep slopes
At several locations of the landfill steep slopes up to 1: 1
will be constructed in order to reduce excavation.
EIA, LA VIC Consultant, February 2011 14
-
II
II
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
1.3.5.2. Redesign of liner system
F or several reasons the liner system need to be adjusted. The
natural clay is not available on site and needs to be replaced by
geo synthetic material. A geo synthetic clay liner (GCL) is
recommended. In steeper areas, the proposed protection and drainage
layer (sand, gravel) is not stable. In these areas, the drainage
layer will be replaced by drainage textiles. In the newly designed
steep rock excavation areas (up to 1:1), the entire liner system
will be constructed by mainly geo synthetic components (GCL,
drainage textiles, geo textiles).
1.3.5.3. Improvment of leachate management
• Leachate collection improvement
In order to reduce the amount of leachate, the leachate
collection shafts (collection pit)
and transportation pipes will be adjusted. The future concept
enables discharging
unpolluted water directly to the storm water channels. While
redesigning the pipe
system, the incorrect placement of shafts (at the deepest point
of the embankment) can
be corrected. Redesign drawings have already been fmalized.
Redesign of pipe
collection can be served for leachate circulation that can
improve the landfill
performance.
• Leachate treatment
The leachate quality measurements at Ru Ri indicate that
significant Ammonia concentrations should be expected at Luong Hoa.
It is unlikely that the treatment plant
according to the current design has sufficient capacity for
nitrogen removal. An
additional nitrogen elimination step (stripping) should be
added.
1.3.5.4. Shift and redesign of hazardous waste cell
According to current design, the hazardous waste cell is
unfavorably placed at the municipal solid waste dumping area. This
creates adverse operational problems, particularly since the
hazardous waste cell is not operating level with the same speed as
the adjacent municipal solid waste areas, as a result of reductions
of airspace. It is recommended to move the hazardous waste cell to
a separate place outside the solid waste site. A 4000 m2 area next
to the Northern (slope) road is available and feasible. The flat
area allows a leachate free waste storage under installed roof.
Thus, the leachate tank including peripheral installations
(pumping, pressure pipe) can be cancelled.
EM, LA VIC Consultant, February 2011 15
-
41
• ..
-
' ..
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 Solid Waste Management
Shift of hazardous waste cell Example: Roofed hazardous landfill
Rondeshs-gan (Germany)
Figure 1-5: Proposal for moving hazardous cell out of landfill
pit
The former hazardous waste cell will be turned into solid waste
disposal area providing additional 200.000 m3 airspace.
1.3.5.5. Redesign Luong Hoa Leachate Treatment Plant
Redesign of the treatment plant at the landfill is required
because the proposed process
technology acceptable effluent values cannot be reached.
Design criteria are:
- use of the already constructed ponds as biological treatment
step
use of technology available and used in Vietnam
flexibility and ease of operation
Compared to domestic waste water leachate contains a high
concentration of nitrogen mostly in the form of ammonium as
landfills develop anaerobic conditions.
The existing design proposes for the leachate treatment 3
ponds.
Considering inflow data and reviewing experiences at other
operating landfills in the South of Viet Nam, it should be noted
that leachate is very difficult to treat even using several high
loading steps of treatment. For example at an advanced landfill in
Ho Chi Minh city, process includes a step of physical-chemicals
treatment and two steps of biological treatment for removal of
organic matter. Additionally two steps of anoxic treatment to
remove nitrogen and two steps of physical treatment to remove
suspended solid were implemented (CENTEMA, 2008). However, nitrogen
parameters sometimes could not meet the standard. The modified
technology of leachate treatment plant in Luong Hoa landfill are
shown in Fig. 1-6.
EIA, LA VIC Consultant, February 2011 16
-
"
• ..
.. Iii
.. •
jlh
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
The raw leachate
Ca(OH)2 NaOH
Collection pit
Pump hole 1
r----'-'-'-' I
~.-.~ t ,-P_u_m_p_ho_l_e 2---'~J
NaOH ~ ~ - -- -- - --1L.... __ c_a_us_tl_·c_ta_n_k_.....l
----+11101 Pump hole 3 I
Alz(SOMl
Polymer, HCI "'"'------- L.......-__ -.--__ .....J ........ (~
.......... ~L.......-_S_IU_d __ ge~ta_n_k_...I
r'-'-'-'-'-' ~.- .... \0 .
I ~.-.-.-.-.-.
Receiving body (QCVN 25:2009/BTNMT, B2)
Water pipe
Sludge pipe
.
. t
Landfill
II>
........... ~ Air pipe - • - • ~
Chemical pipe - - - ..
Figure 1-6: Chart of Leachate treatment process in the Luong Boa
Landfill
The presence of nitrogen in the leachate is mainly in the form
of ammonium produced
under anaerobic conditions in the landfill. As experiences of
leachate treatment at Nam Binh Duong Landfill (Binh Duong Province)
and Soc Son Landfill (Ha Noi) show,
currently the most suitable process to remove ammonia is
stripping. During the process
the pH of leachate is raised to 11 or 12, and most of the
ammonium converses to
ammonia that can be removed by air stripping.
EM, LA VIC Consultant, February 2011 17
-
..
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
In addition to the biological step as designed under phase 1 the
removal of nitrogen by stripping is strongly recommended.
For the organic matter and COD, the existing and already
constructed pond system is sufficient and operation must include
intensive aeration.
In comparison with the domestic wastewater, leachate contains a
high content of Nitrogen, mainly under the type of Ammonium. The
treatment technology proposed in the Phase 1 is to use 3 lakes for
treatment of leachate. However, the treatment of leachate is very
difficult, especially treatment of Nitrogen contained therein.
Therefore, within this Phase the Consultant proposes to add 2 more
stripping towers. Size of the treatment plant is proposed as
follows:
1. Collection Well: 500m3
2. Lime mixing tank: HRT: 30 minutes, D=1.2 m x H=2.8
3. Stripping Tower 1: D=3m x H = 8m;
4. Stripping Tower 2: D=3m xH = 8m;
5. Neutralization (eliminating lime): HRT: 3 hours; D=2.8 x
H=6m.
6. Anaerobic pond 1: HRT: 111 days (15,000m3).
7. Anaerobic pond 2: HRT: 111 days (l5,000m\
8. Oxidization ditch: HRT: 66 days (9000m\
The leachate, after treated, will meet the class B2, the
National Technical Regulation on Wastewater of the Solid Waste
Landfill Sites QCVN 25 :2009 (for BOD, COD, total nitrogen and
ammonia), and follow the class B, the QCVN 24:2009 (for other
parameters) .
1.3.6. Total capital investment and operation schedule of
Component 3
.:. Operation schedule of the component 3
According to the Credit Agreement, the total investment cost is
follows:
- Supply of Solid Waste Equipment (NT-3.3): 580.500 USD
- Development of Luong Hoa Landfill Site (Ph2) (NT-3.4): 278.124
USD
- Transfer Station (NT-3.5): 100.000 USD
.:. Schedule of project implementation
The schedule of project implementation is shown in Table 1-4. In
the Table 1-4, the symbol of book is report, line is the
implementing time from the beginning to fmishing (solid line is
expected time, dash line is extention time), triangle is signed
time.
EIA, LA VIC Consultant, February 2011 18
-
i. Ii I. '" • It if If
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project
..- 4 .. • •
Table 1-3: Project implementation schedule of Component 3
EIA, LA VIC Consultant, February 2011
Component 3 - Solid Waste Management
19
-
"
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
CHAPTER 2: NATURAL, ENVIRONMENTAL AND SOCIO-ECONOMIC
CONDITIONS
2.1. NATURAL CONDITIONS
2.1.1. Geotechnical and hydro-geological conditions
2.1.1.1. Geo-technical conditions
General geological characteristics ofNha Trang City are as
follows:
a) The coastal area: most of the covering layers are sand in
which several areas have thickness of 3m, followed by layers of
clay with good pressure strength (R;:::l kglcm2)
b) Hillside: includes layers in order:
- Medium crushed sand layer with R;:::1 Kglcm2
Carved stone and local coral layer, met at the depth of3+6.5m,
thickness of3+3.2m
- Pebble and clay layer, encountered at depth of 6.5+7.5 m,
thickness ofO.8+1m
- Mixed clay layer, encountered at depth of7+7.6 m, ending at
depth of8.8+9.0m
- Bedrock layer, encountered at depth of 8.8+9m, firm.
c) Low-lying area (western of the city, located at two sides
ofQuan Truong River): The area is usually flooded every year,
terrain elevation is less than I meter, strata includes following
layers:
- Top layer is gray white sand in soft plastic status, thickness
from 1.5 to 2.5 m, this layer is widely distributed throughout the
area.
- Next layer is a black clay sludge and shell layer in
stretching status, thickness of about 7m.
- Under clay sludge layer is sludge layer, gray, stretching
status, thickness of2.5 m
- At a depth of about 20m is yellow grey layer, semi-solid to
solid status at depth of -20m to-25m.
2.1.1.2. Hydro-geologicalfeatures
Currently, Nha Trang City has large reserves of underground
water; however, the water is mostly contaminated with salinity in
coastal areas and at river outlets in Cai and Quan Truong
River.
According to the geological survey report of Phase 1 and Phase 2
by VIW ASE implemented in September 2005 and May 2009, the
hydrological characteristics in the project area are summarized as
follows:
EfA, LA VIC Consultant, February 2011 20
-
•
II
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
• Tide:
Nha Trang City is close to Nha Trang Bay. Tidal regime in Nha
Trang Bay is not even.
According to observation data in Cau Do hydrological station in
Khanh Hoa province,
there are 18-20 diurnal tide days per month, time of rising tide
is more than time of falling
tide. Fluctuation water has relatively clear periodicity with
the largest amplitude of 2.4 m;
the average amplitude of tidal period is 1.2-2 m. Tidal water
level ranges from -1.37 m to
+ 1.03 m (VN2000 National Coordinate System) .
• Wave:
Maximum wave height was observed in the coast of Khanh Hoa
provincal People's Committee office, which was 2.5 m (November 15,
1990). In Nha Trang Bay observable waves are greater than 2.0 m in
height.
• River:
- Cai River (Nha Trang):
In many years, the average annual flow on Cai River in Dong
Trang area with basin area of 1,244 km2 basin reaches 56.5 m3/s,
corresponding to the module number of flow which is 45.5 l/s/km2
and total flows are 1.78 billion m3/year.
However, the annual flow variation in years is not great.
Coefficient of variation (Cv) of annual flow is 0.37. Annual flow
with frequency of 75% is 41.3 m3/s or 1.3 billion m3 of water.
Flow in Hood season: Annual flood of Cai River in Nha Trang
starts from September to December (time maybe different a few
weeks).
Flood peak discharge at peak Ha Ra - Xom Bong is as follow:
P% 1 3
Qmax( m3/s) 4551 3692
Water levels measured in Nha Trang City are:
Hmax=2.05m
Htb=0.48 m
- Tac and Quan Truong River
5
3202
10
2446
Hydrological regime of the Quan Truong River directly affects
the South of Nha Trang airport. It's just a branch of Cai River in
Nha Trang; during the dry season there is no water, in the rainy
season, water from Cai River in Nha Trang sweeps through adding
with field water in Dien Khanh, concentrating and discharging into
Be river outlet, Dong Bo river, causing flooding in two
riverbanks.
According to the plan, Quan Truong River will be improved,
straightened to go close to the expansion area of the city to the
west to ensure flood discharging in part of Cai River to Be
outlet.
EM, LA VIC Consultant, February 2011 21
-
•
Ii
... •
Ii;.,
, ".
, I
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Suh-project Component 3 - Solid Waste
Management
• Flood:
In this area, there are often 2-5 floods each year, as mentioned
above part of flood flow discharges to Tac River to go to Be
outlet. High speed of flood on the river often causes serious
flooding to low land. Submerged time can last 2-3 days. Historic
floods in 1964 lasted for a week. The most dangerous case is when
encountering wave combining with flood tide. In Nha Trang city, the
most frequent flooded areas are Dien Khanh district and low areas
such as: Vinh Thai, Vinh Ngoc, Vinh Hiep, Vinh Thanh, Vinh Phuoc,
Vinh Hai and Ngoc Hiep Ward.
2.1.1.3. Topography
Topographic and geomorphic characteristics ofNha Trang City are
generalized to three areas as follows:
• The Northern ofCai River:
This area included the residential areas of Vinh Hai and Vinh
Tho Ward, has relatively flat terrain with elevations from 3 m to
3.5 m; only the area near the end of emission station is low with
elevation from 0.37m to 1.86m. This area is heavily affected by the
flood from Hon Kho Mountain; this area is often flooded when it
rains .
Residential area in Vinh Tho, Vinh Phuoc ward has terrain along
the pied of Hon Chong and Hon San Mountain so it is very slope with
elevation from 5.1 m to 24m. Son Thuy residential area along Cai
River has elevation from 0.5 m to 5.1 m.
• Central area:
The urban roads are flat terrain; elevation is from 3.9 m to 4.2
m.
Urban area to the west ofLe Hong Phong Street and Tac River
through the western plain is lying terrain, elevation is from 0.5 m
to 1.5m.
• Southern area:
Southern area is flat terrain; average elevation is from 2.4 to
3.5 m.
2.1.2. Climate
Nha Trang City has characteristics of tropical climate with two
distinct rainy and dry
seasons.
2.1.2.1. Air temperature
With its mild climate, in the whole year, Nha Trang City has the
summer which is lots of sunshine but not hot and the winter which
is rainy but not cold. The details are as follows:
- Average annual temperature:
- Minimum temperature:
- Maximum Temperature:
- Monthly average temperature:
EM, LA VIC Consultant, February 2011
26.600C
14.60oC
39.50oC
28.40oC (June, July, August)
22
-
•
Ii
-
,..,
ldI
-d
~
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nba Trang City Sub-project Component 3 - Solid Waste
Management
- Monthly average temperature: 24.30° C (January, December)
- The total amount of heat during the year: 98,2000C
2.1.2.2. Rainfall
Rainfall varying from 1,000-1 ,500mm accounts for 51 %, rainfall
under 1,000mm to 700mm accounts for 20%, the rest is rainfall from
1,500mm to 2,500mm, in which the rainfall over 2,000 mm accounting
for 12%.
- The average annual rainfall: 1,252mm and maximum: 1,061mm
(November -1917)
- The highest annual rainfall: 2,552mm; lowest: 641mm
Rainfall is unevenly distributed in the year: 85% of rainfall
concentrating in the rainy months (September to December).
2.1.2.3. Wind
Main prevailing wind direction in the year in Nha Trang City is
North and Northeast, Southeast with average wind speed of 6mJs; dry
heat Southwest wind appear less. Overall, Nha Trang City is rarely
affected by typhoons, cyclones.
Table 2-1: Wind speed in dominant directions (mls)
Average annual air moisture in Nha Trang City varies from 77% +
80%, the details are
shown in following table:
Table 2-2: Average monthly and annual air humidity at Nha Trang
station (%)
2005 77 74 78
2006 77 77 76 75 76 75 79
2007 78 76 80 80 81 78 78 80 81 84 83 79
2008 81 79 81 81 80 78 76 78 81 81 85 82 80 Source: Statistic
yearbook ofNha Trang City, 2008.
EIA, LA VIC Consultant, February 2011 23
-
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
2.1.2.5. Evaporation
Average annual evaporation is 3.2 mmJday equivalent to the
annual rainfall, but focusing
on the dry months so the lack of water occurs in production and
life.
Table 2-3: Total of monthly and annual evaporation capacity
(mm)
Trang 133 115 123 117
Cam 152 130 140 125 141 159 155
Ranh
2.1.2.6. Solar radiation
Average annual hours of sunshine in Nha Trang City in 2008 was
2,404.7 hours. Total of
average daily sunshine hours is 6-7 hours. Variations of
sunshine hours in months and
years in 2004-2008 are shown in the following table.
Table 2-4: Average monthly and annual sunshine hour variation in
Nha Trang station (%)
2005 206.0 231.0
2006 136.5 190.4
2007 122.5
2008 157.3
Source: Statistic yearbook ofNha Trang City, 2008.
2.1.2.7. Typhoon
From 1976 to 2007, 11 hurricanes and 1 tropical depression
landed on the territory of
Khanh Hoa. The strongest wind intensity was level 6, level 7
(39-61 km/h) accounting for
55%; level 8, level 9 (62-88K.m1h) accounts for 33%, level 10
(89-102 km/h) accounts for
12%.
Table 2-5: Some features of typhoons in Khanh Hoa
Cam Ranh Nha Trang Cam Ranh Nha Trang Cam Ranh Nha Trang
KhanhHoa 14/10/81 3/11178 23/10/92
20-S 26-W 98.5 133.3 98.5 20-NW 24-W 345 246 345 6-NE 20-E 222
103 130
EfA, LA VIC Consultant, February 2011 24
-
· "
--
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
2.1.3. Ecosystem
The project area has very limited flora and fauna due to the
urban development in recent years. The non-urban areas are widely
used for agricultural purposes, which are mainly rice fields,
shrimp farms. In the hills, cashew and coconut are grown.
No indigenous animal and vegetable breeds do exist in the
region. Nearby beach area is mostly sand or sludge and offshore dip
slope. Most nearest coral reefs is about 15km from the coast
including Hon Mun Marine Protected Area, which is the most diverse
place on coral of Vietnam.
The number of fish in eai and Tac rivers decline sharply in
recently years according to local fishermen due to the fmishing and
pollution from human activities. Over use of chemical, foodstuff
for aqua farming cultivation, that effected water body quality.
2.2. SOCIO-ECONOMIC CONDITIONS
2.2.1. Economic development situation
Nha Trang is one key economic area in Khanh Hoa Procince, the
economic growth of the city is relatively high. The average annual
GDP increases l3.13% (2003 - 2007), trade - services increases
15.54%, industrial output value increases 14.87%.
Total production value at current price of province in 2007 was
1,208,984,514 million VND. The details are shown in the following
table:
Table 2-6: Production value at current price of Nha Trang City
divided by economic sectors in 2005 - 2007
X~4~;',!)t~onoiDi~'$ec~4)1$'! i~!;:':i!'!i ·,1·,:
;':!2006i;,!!,>< '9!
Agriculture, Value (million 361,276 438,003 452,003
1 forestry, don r-----~----r---------_+--------_+------~--~
aquaculture Rate (%) 0.07% 0.06% 0.04% Investment, Value
(million
5,850,949 6,206,667 6,302,511
1.14% 0.91% 0.52% 2 construction, VND)
r-----~----r---------_+--------_+------~~ industry Rate %
Value (million 505,364,000 678,545,000 1,202,230,000
3 Service, tourism VND)
r-----~----r----------+--------_+--------~
Rate (%) 98.79% 99.03% 99.44% Value (million
511,576,225 685,189,670 1,208,984,514 Toal ~
r---~~----r---------_+--------_+--------~
Source: Statistical Yearbook ofNha Trang City in, 2008,
2.2.1.1. Development of industry
100% 100% 100%
In 2008, the value of industry production in Nha Trang is
6.672.540 million VND (by conversion price of 1994). Nha Trang has
2058 industrial establishments and small industries, with 31,396
employees, including state-owned enterprises. Nha Trang city has a
share of 34.4% of the total value of industrial output across the
province, mainly food industry, tobacco, textiles, clothing,
leather dyeing, manufacture of metal products, wood appliances.
EIA, LA VIC Consultant, February 2011 25
-
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
2.2.1.2. Development of agriculture -forestry - aquaculture
- Agriculture: In first half of 2009, the total area of the
cultivation is 2,061 ha. Winter-spring rice areas in period of 2008
- 2009 are 750 and 720 hectares with average productivity of 59.6
quintals per hectare. In late 2008, the city has granted support of
40.5 tons of seed rice due to flood damage to the communes, wards
for sowing of winter-spring season with a total value of335 million
VND.
- Fishery: the total fishing output is about 18,996 tons. For
shrimp hatching, the fanning area of shrimp consist of 200 ha with
a productivity of 145 tons/year.
The agricultural production value of Nha Trang City in 2008 is
70,059 million VND, of which the cultivation production value
accounts for 63.88%, followed by the livestock raising production
value which accounts for 32.7% and the value of the agricultural
service sector accounts for 3.42%, the details are shown as
follows:
Table 2-7: Production value of agriculture at current price of
Nha Trang City
in period of 2004 - 2008 Unit: Million VND
""......,,=-:~r:-==
51,042 44,759 2. Livestock raising 34,207 22,931 3. Agricultural
service 2,115 2,369 Total 87,364 66,379 69,556 71,470 70,059
Source: Statistical Yearbook ofNha Trang City in, 2008.
2.2.1.3. Tourism and services
Nha Trang is one of the popular tourist areas of the country and
all over the world with famous landscapes: Nha Trang Beach,
Vinpearl Land Bay, Thap Ba PoNagar, etc., which has become a
highlight in tourism development, landscape conservation,
contributing to economic development.
Tourism plays important role of major economic sectors in Nha
Trang City, the tourism and service revenue dominates about 40%
City's GDP. With nice and famous landscapes, the City attracts a
huge tourists amount every years. In 2007, the total amount of
tourists is 925.000 visitors, in which international tourists are
294.000 visitors. In 2008, due to effect of the global economic
crisis, the amount of tourism visitors reduce, there are 776,000
visitors, in which the number of international tourists is 162,000
visitors. The total tourism revenue is 1,282,000 million VND and
773,704 million VND, respectively.
Items 2005 2006 2007 2008
Tourism revenue (million VND) 505,364 678,545 1,202,230
1,282,000
2.2.1.4. Cultural works
Khanh Roa province in general and Nha Trang City in particular
has many valuable cultural and historical works. Especially the
Cham relics still exist in many parts of the city, notably Ba
Ponagar tower located in the North of Xom Bong Bridge, Vinh Rai
EM, LA VIC Consultant, February 2011 26
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
Ward, Nha Trang City. This is one of the largest Champa temples
in the Central of Vietnam, which was built from 7th century to 12th
century.
Long Son Pagoda at the foot of Trai Thuy Mountain is the largest
Buddhist pagoda among more than 20 pagodas in Nha Trang, which was
built in the 19th century.
In addition, Nha Trang has many cultural works, historical works
such as Dong Bo War zone, Alexandre Yersin Relic, Tram Huong Tower,
mountain church, and many other small temples, pagodas.
All cultural and historical works locate far from the project
areas; therefore, there are no effects and damages to cultural and
historical works in the area.
2.2.2. Social development situation
2.2.2.1. Population
By the end in 2008, the city has 19 wards and 8 communes and a
total area of 252,596 km2, total population of 380,552 people, and
average population density of 1,506 persons /km2• Total number of
households is 83,220 households, on average of 4.5 persons per
household. Average population of the City changed over the years
from 2004 to 2008 which are shown in tables following:
Table 2-8: Average population of Nha Trang City 2004 - 2008
Source: Statistical Yearbook ofNha Trang City, 2008.
2.2.2.2. Culture
Nha Trang is a culture - society city. The authorities cooperate
with the city's organizations and unions to conduct many
information and communication activities, cultural activities, and
sport tournaments to celebrate the important national days,
anniversaries, political and economical events of the city. The
City organized successfully the Ceremony of the Decision of Prime
Minister on recognition of Nha Trang as a Grade I city directly
under the province.
2.2.2.3. Education
There are 72 schools in Nha Trang City, including: 39 primary
schools, 22 secondary schools, 01 secondary and high schools and 10
high schools with a total of 1,712 classes and 2,932 teachers and
63,673 pupils (2008).
2.2.2.4. Health service
In Nha Trang City, there are 04 hospitals; 06 local clinics,
City maternity homes and 27 communes/wards medical stations.
Infrastructure of the city's health sector is relatively good with
large numbers of hospital beds and medical and pharmaceutical
staffs.
EIA, LA VIC Consultant, February 2011 27
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
2.3. CURRENT SITUATION OF TECHNICAL INFRASTRUCTURES
2.3.1. Flooding and inundations
Nha Trang City only has storm water drainage system with the
limitation of capacity, the flooding and inundation sill happen in
some areas ofNha Trang City, especially in rainy season. There is
no wastewater drainage system, the dredging of drainage culverts
and canals, etc. is very limited, the encroachment of residents and
development of trees in some drainage ditches preventing traffic
flow, accumulating of waste water causing pollutions and flooding
after heavy rains.
2.3.2. Current situation of solid waste collection in Nha Trang
City
2.3.2.1. Composition of solid waste
In 2009, the consultant Fichtner has conducted four waste
analyses to show the difference of the particular sources. The
following figures show the result of the composition of waste from
four different waste generators: Households, restaurants,
offices.
Sand,soil,stone 20/0
Paper 13
Ceram ic 1 0/0
Food waste 690/0
nylon+soft plastic 120/0
Cloth 3%
Figure 2-1: Composition of household waste
soft· box (styrofoam) 1 %
Shoes' 1 Uf_-__
Paper' 8%
Food-waste 65%
nylon+soft plastic 11 016
Cloth·5%
.... ..---~Glass,4%
Figure 2-2: Composition of waste from restaurants
EIA, LA VIC Consultant, February 2011 28
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
Sand,s:oil,
Wood 1%
Paper 30/0
soft box (styrofoam) 1%
Shoes 20/0
Food waste 810/0
Nylon+soft plastic 50/0
Hard plastic 0/0
Cloth 1%
Figure 2-3: Composition of waste from market
Garden waste 21%
soft box ;tyrofoam) 1 %
7%
Rubber 2%
Electric waste 3%
Wood 6%
nylon+soft plastic 12%
Figure 2-4: Composition of waste from offices
2.3.2.2. Solid waste generation
• Existing solid waste generation
Cloth 2%
Food waste 16%
The following table shows the quantities of waste collected by
URENCO in 2009 from the general public and small enterprises as
shops, offices, restaurants and hotels and public institutions.
These data include also the waste generated by the tourists.
EIA, LA VIC Consultant, February 2011 29
-
lOll
....
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
Table 2-9: Quantities of waste collected in 2009
(URENCO,2010)
Trips Waste Daily waste
Month Monthly average
days quantity quantity per
total per load person month per day
(pop385.482
tons No. tons/trip day tons kglpers*day
January 6,606 1,513 4.37 31 213 0.553
I February L 7,581 1,722 4.40 28 271 0.702 : March 8,324 1,950
4.27 31 269 0.697
• April 8,282 1,933 4.28 30 276 0.716
May 8,914 2,084 4.28 31 288 0.746
i June 8,949 2,164 4.14 30 298 0.774
July 9,091 2,170 4.19 31 293 0.761
August 8,769 2,107 4.16 31 283 0.734
September 8,270 1,990 4.16 30 276 0.715
October 8,509 2,051 4.15 31 274 0.712
November 9,340 2,271 4.11 30 311 0.808
December 8,709 2,030 ! 4.29 31 281 0.729
. Total 101,344 23,985 4.23 365 278 0.720
According to the data received from URENCO the average rate for
collected waste in 2009 is only 0.72 kg per capita and day. This
value is in contradiction to the design criteria of 1,3 kg/person
and day. Data on the ratio of waste collected by the infonnal
sector to be recycled is not available. Since the infonnal sector
is collecting light recyclable materials like plastic and paper,
the reduction of the total waste quantity is not as high to be
considered in the calculation of the transportation capacity. The
volume is more relevant regarding the intennediate storage within
the waste bins. As long as there are no data available on the
number of recyclers and the quantity and composition of recyclables
it is not advisable to modify the given design criteria.
According to the data presented in Table 2-9 the yearly
generation of waste has been
101.344 tons in 2009, this means the collection rate was below
70 %, compared with the estimation based on official baseline data.
It has to be emphasized that the estimation is based on a design
criteria, which seems a little high compared with international
expenences.
The collection rate depends mainly on the access to the waste
generators and how the general public assists by putting the waste
properly where it can be collected by URENCO. All wide streets in
the urban wards are serviced daily, the attached alleys are
serviced 2 times a week. The rural communes are not serviced every
day as reported by URENCO.
EIA, LA VIC Consultant, February 2011 30
-
t
l1li
is
.. '
--,d
""
, ...
"'" :,'!if
... "j
T (4
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nba Trang City Suh-project Component 3 - Solid Waste
Management
• Future solid waste generation
In 2009 municipal waste includes besides household waste
(garbage) also waste from shops, hotels, restaurants, offices and
small scale industries. The daily waste collection includes also
the waste generated by the tourists collected from hotels,
restaurants and the beach.
Present waste generators will be also waste generators in the
future. But there will be a significant change in Nha Trang: The
tourist industry will bring more tourists during the specific
seasons and therefore the quantity of waste will presumably change
from month to month. The present data base is not sufficient to
project the waste generation of tourist in detail. The tourist will
increase the volume of packing waste according to their consumption
profile. The consultant predicts that this increase will be
absorbed by the recyclers rather than added to the general waste.
Since the design criteria for the future waste generation are quite
high the Consultant does recommends to add a tourist factor.
Table 2-10: Predicted solid waste quantities generating in Nha
Trang Unit: kg! day
Phuong Son 12,694 13,742 15,173 16,917
Phuong Sai 13,241 14,335 15,827 17,647
Vinh Hai 30,832 33,379 36,853 41,089 45,812
VinhPhuoc 36,013 38,988 43,045 47,993 53,510
Vinh Tho 13,523 14,640 16,163 18,021 20,093
VinhHoa 20,139 21,803 24,072 26,839 29,924
VinhLuong 19,495 21,105 23,302 25,980 28,967
i Vinh Phuong 16,668 18,045 19,923 22,213 24,766
Van Thang 14,204 15,377 16,978 18,929 21,105
XuongHuan 14,110 i 15,275 16,865 18,804 20,965
Van Thanh 15,002 16,242 17,932 19,993 22,291
Loc Tho 15,810 17,116 18,897 21,069 23,491
Phuoc Hoa 15,920 17,235 19,029 21,216 23,655
Tan Lap 17,649 19,107 21,096 23,520 26,224
Phuoc Tan 17,739 19,205 21,203 23,641 26,358
Phuoc Tien 11,654 12,617 13,930 15,531 17,317
! Phuoc Hai 26,277 28,448 31,409 35,019 39,044
Phuoc Long 36,916 39,965 44,125 49,197 54,852
Vinh Thai 13,024 14,100 15,567 17,357 19,352
Phuoc Dong 25,793 27,924 30,830 34,374 i 38,325
EIA, LA VIC Consultant, February 2011 31
-
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Component 3 - Solid Waste Management
Vinh Ngoc
. Vinh Thanh 14,684 15,897 19,569 21,819
VinhHiep 10,375 11,232 12,401 13,826 15,415
Vinh Trung 10,804 11,697 12,914 14,399 16,054
VinhNguyen 26,987 29,216 32,257 35,965 40,099 i
Vinh Truong 20,977 22,710 25,074 27,956 31,169
Total 517,816 560,589 618,935 690,080 769,403
2.3.2.3. Current Situation ofUrhan Waste Collection
Nearly 100% quantity of wastes has been collected in the inner
city wards ofNha Trang, despite of the fact that it is very
difficult to collect all of wastes from small and narrow roads,
alleys and riverbanks where the local villagers still have a habit
of free discharging their wastes directly to the rivers. The solid
waste management is described as follows:
, ! i ! Public I I 110' I
! insiifutions I i I waste I houses along
I f
H 1101
I Wide streets I I collection I I
I Markets H Transfer I I I point .; .... i I vehicles .. i fill
I I I
I
I I I
I I Commercial ,
I ;
I .:
I entltles .... I t I
I Remole houses H Collection i I in narrow alleys
"I
pOint
I Recycling dealers
I I I
Existing methods of collection:
• The household gathers their family waste bags to the
collection points on the roads waiting for dump trucks to
collect;
• Collection by trolleys: Wastes shall be collected from the
streets, residential areas, along the alleys by trolleys. These
trolleys shall later gather at the "waste collection points"
waiting for the dump trucks to collect.
• Public dustbins: Some streets and residential areas are
provided with dustbins with a capacity of 140 liters and 240
liters. Households around these areas shall pour their wastes into
such dustbins. Dump trucks shall collect wastes from these
dustbins.
EIA, LA VIC Consultant, February 2011 32
-
•
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub-project Component 3 - Solid Waste
Management
• Market wastes: Solid wastes arisen from the shops shall be put
in baskets and then transferred to an intermediate waste conveyance
point within the markets. Normally, the intermediate waste
conveyance points within the markets are not properly designed.
Currently, almost of the dump trucks in Nha Trang City do not
have lifting equipment, thus the workers must use canvas as lifting
tools to load collected waste into the dump trucks. The wastes
shall be put on the canvas and 4 workers will raise the canvas to
load the wastes on the trucks.
2.3.2.4. Current Situation of Waste Collection from the
Islands
At present, URENCO has been in charge of collecting wastes from
almost of the islands except for the Vinpearl Resort. According to
the URENCO, total quantity of population on the islands is
estimated 3,000 persons living in about 700 households that belong
to Vinh Nguyen ward. Those persons living at the aquatic farms for
raising lobsters and shrimps are now discharging a lot of special
wastes. According to the URENCO, the quantity of wastes daily
collected from islands as follows:
- Tri Nguyen Island: 22 barrels of240 liters;
- Bich Dam Island: 5 barrels of240 liters;
- Dam Vinh Island: 2 barrels of240 liters;
- Hon Mot Island: 2 barrels of240 liters;
- Vung Ngan Island: 5 barrels of240 liters.
Wastes from the households and streets are directly collected by
the URENCO's workers and stored in the dustbins at the collection
points until they are conveyed by boats to the mainland. Currently,
URENCO has not been in charge of collecting wastes from the
Vinpearl Resort. Instead, the wastes therein are collected and
conveyed to the Ru Ri Landfill by its staff in charge.
2.3.2.5. Current Situation of Medical Waste Collection and
Treatment
Toxic wastes from the hospitals such as infection-risk wastes,
chemical contaminated wastes, etc. These wastes are classified and
safely treated at the incinerators of the Dermatology Hospital.
2.3.2.6. Current Situation of Collection of Construction Waste
and Debris
Construction waste and debris (C&D) is a mixture of
construction materials and other components used at the
construction sites such as pieces of wood, metal or plastic broken
pieces. It is rather expensive to convey such C&D that is
normally used for the site leveling within the construction
projects in the city as an alternative. Debris is transported to
the Landfills. Normally, debris is sold on a basis of measuring by
vehicle trips. Only debris mixed with other urban wastes shall be
allowed to be conveyed to the Ru Ri Landfill.
2.3.2.7. Current Situation of Industrial Waste Collection
(Hazardous Wastes)
Currently, only a few factories in Nha Trang are discharging
industrial wastes, especially toxic wastes. Collection and
treatment of such toxic wastes shall be undertaken and paid by the
discharging factories themselves. These factories often hire
private companies to
EIA, LA VIC Consultant, February 2011 33
-
W-:~-;i
"""
'lIP
'1~.
-L1!A'
'.
Coastal Cities Environmental Sanitation Project (CCESP) - Phase
2 Nha Trang City Sub~project Component 3 - Solid Waste
Management
conduct collection and treatment of toxic wastes. Until 2010,
the collection of toxic industrial wastes has not been undertaken
by the URENCO.
2.3.2.8. Solid Wastes in Rivers and Beaches
URENCO has, at present, used a special kind of equipment for
cleaning beaches. However, it is also necessary to take proper
measures to mitigate solid wastes from the upstream areas to the
sea. Boats have been used by URENCO for fishing the floating wastes
out of water in the Cai River. However, capacity and effects of
this boat is very low.
2.4. EXISTING ENVIRONMENTAL STATUS
2.4.1. Air environment
In order to evaluate the air environmental situation in project
area, the Consultant conducted survey, measurement of some targets
of air environmental quality at the expected construction locations
of the transferring solid waste station, access T - junction
between Nguyen Khuyen and April3rd road; T- junction between Tan
Trang and Nguyen Hong Son street; opposite the way go to Be gate on
Vo Thi Sau road. The air quality in those areas can be affected by
smell, smoke, dust, noise, fly... which is caused by transferring
solid waste station operation.
The environmental parameters were measured at the most typical
locations for the basic air quality and reflect fairly accurately
the current situation of preparing areas for project construction.
The samples were taken continuously in Ihour; dust indicators PMIO
and lead dust were measured in 24 consecutive hours. Monitoring
locations were at 1; 7.5; 15; 30; 60m a part from selected site at
the height of 1.2 to 1.5 m. The average value was taken and shown
in Table 2-11.
Table 2-11: Results of ambient air quality
2
3 Wind speed
4 Suspended dust 0.3 QCVN 05:2008
5 Dust PM 10 0.01 0.15 QCVN 05:2008
6 CO 12.5 11.9 13.1 30 QCVN 05:2008
7 N02 0.08 0.07 0.07 0.2 QCVN 05:2008
8 S02 0.09 0.18 0.13 0.35 QCVN 05:2008
9 H2S 0.18