Entry Capacity Substitution Transmission Workstream – 6 th August 2009
Dec 18, 2015
2
Agenda
Current Status
Methodology Statement: overview.
Charging Proposal.
Methodology Statement: retainers.
UNC Modification Proposal.
3
Current Status
Three simultaneous processes with consultations aligned to complete prior to
Ofgem Impact Assessment.
Methodology Statement.
Consultation started 24th July; closes 24th August.
Submission to Authority for approval 7th September.
Charging Consultation.
Consultation (draft) started 28th July;
Formal consultation starts 11th August; closes 14th September.
UNC Modification Proposal.
Propose submission to UNC mod panel following discussion today.
Mod Panel meeting 20th August 2009.
5
Proposed Entry Capacity Substitution Methodology
National Grid is proposing a methodology that uses “retainers” to limit the exposure of ASEPs to substitution.
Based on the “Option Approach” discussed at workshops.
Retainer considered to better describe the role of the new product.
Avoids confusion with existing Option products.
National Grid believes that this approach is a good compromise between the two extremes of the Mechanical Approach and the Two-Stage Auction.
Requires User Commitment
Relies on Shippers’ assessment of needs not National Grid judgement.
Relatively simple to implement.
6
“Retainer” Approach
A retainer will prevent capacity at an ASEP from being substituted to a different ASEP in response to an incremental signal elsewhere.
The retainer requires a signal and commitment from Shippers.
The retainer
does not give rights to the Shipper to use the capacity covered by the retainer;
does not give the Shipper first option to buy the capacity; but
it would keep the capacity at the relevant ASEP.
7
What is the Retainer?
It is proposed that the retainer:
identifies and excludes capacity from substitution processes thereby protecting capacity for the duration of the retainer;
is placed ahead of QSEC and applies for 12 months,
i.e. covers (normally) one QSEC and any ad-hoc QSECs before the next retainer window.
will be subject to a one-off NTS Entry Capacity Retention Charge. This will be a fixed price per unit of capacity and will be the same for all ASEPs.
for the purposes of defining refunds the retainer nominally applies in respect of the 12 months commencing Oct Y+4, i.e. from the default 42 month lead-time;
will still prevent capacity being substituted away if the incremental capacity is allocated earlier or later than the default lead time;
The retainer will not:
prevent other Shippers (or the relevant Shipper) buying capacity at that ASEP in the period covered by the retainer;
be sold in quantities above the quantity available in QSEC (usually 90% baseline – sold);
be available to non-Users. However, extending the process to non-Users could be an option to be considered for 2011.
The Retention charge will be discussed on later slides
8
90 % of baseline capacity.
(May be higher if incremental capacity has previously been
released).
Time
Capacity Available for Substitution at Donor ASEPs
42 monthsDefault capacity release lead-time
at recipient ASEPs
Sold capacity
Capacity.
Retained quantity
Available capacity for substitution
A key factor in the substitution process is to identify the amount of capacity available at donor ASEPs that can be substituted. The retainer reduces the available quantity.
9
Substitution Methodology – Associated Issues
National Grid is proposing an exchange rate cap of 3:1
This is significantly lower than the cap applied to Transfer and Trades.
With Shippers having an opportunity through the use of retainers to protect capacity is an additional constraint on substitution by way of any exchange rate cap appropriate?
Partial substitutions will be progressed
Where appropriate incremental capacity will be met through a combination of investment and substitution.
Entry Zones are proposed to be used for selecting potential donor ASEPs.
Within zone, donor ASEPs would be selected on the basis of best exchange rate. Out of zone, donor ASEPs would be selected on the basis of shortest pipeline distance from the recipient ASEP.
Network Analysis will be undertaken to determine substitution opportunities.
Analysis will be consistent with the Transmission Planning Code and hence assessment undertaken to determine investment requirements.
10
Charging Consultation - NTS GCM 18
The retainer requires a signal and commitment from Shippers.
The charging consultation NTS GCM 18 will
determine the NTS Entry Capacity Retention Charge and
ensure any revenue streams appropriately offset other NTS transportation charges
The Licence requires that the charging methodology
1. Reflects the cost incurred
2. Takes account of developments within the transportation business, and
3. Facilitates effective competition between gas shippers and between gas suppliers
11
Determination of Commitment Method A - 1
To determine a cost reflective charge National Grid has estimated the avoided costs of
entry capacity substitution.
If incremental capacity is released in a QSEC auction this results in incremental revenue and a
cost to industry.
Substitution avoids this cost.
The potentially avoided cost has been estimated from the average of the capitalised revenue drivers from the two ASEPs where capacity has been released during the present price control.
Have only considered the potential SO allowed revenue over 5 years which is the minimum value.
Capital investment would result in TO allowed revenue for a further 40 years
Dividing by the maximum substitutable quantity gives a unit Retention Charge Rate (p/kWh)
12
Determination of Commitment Method A - 2
METHODOLOGY A SO Revenue over 5 years
Average Revenue Driver (£m) A £36.34
Substitutable Capacity (GWh) B 2,283.0
Retention Charge Rate
(p/kWh)
C=(100*A)/B 1.5919
Example retention of 10
mscm/d
Retained Daily Capacity
Quantity (mscm/d)
D 10.0
Retained Daily Capacity
Quantity (GWh/d)
E 110.0
Charge to retain 10 mscm/d
(£)
F=10^6*C*E/100 £1,751,106
Retention Charge Rate
(£/mscm/d)
C1=F/10 £175,111
13
Determination of Commitment Method A - Issues
This calculation would result in an initial rate for the NTS Entry Capacity
retention charge of £175,111 for each mscm/d of capacity retained.
This calculation
has used a forward projection of historic costs and as such is not strictly reflective of the costs incurred;
requires a probability of whether incremental capacity would indeed be signalled and whether it could be met by substitution; and
The avoided costs assume all substitutable capacity is retained. If only half is retained substitution could still occur.
14
Determination of Commitment Method B
So National Grid has considered an alternative approach which would comply with the
other relevant conditions.
- takes account of developments within the transportation business; and
- facilitates effective competition between gas shippers and between gas suppliers.
METHODOLOGY B
Minimum price over 32 quarters
Example retention of 10 mscm/d
Retained Daily Capacity Quantity (GWh/d) E 110.0
Minimum Price (p/kWh/d) G 0.0001
Charge for retaining 10mscm at an ASEP (£) H=(8*365)*G*E*10^6/100 £321,200
Retention Charge Rate (p/kWh) I=H*100/(E*10^6) 0.292
Retention Charge Rate (£/mscm/d) I1=H/10 £32,120
15
National Grid’s Proposal (Draft)
National Grid’s proposal (draft)
Methodology B is recommended, which uses the minimal capacity charge rate
of 0.0001p/kWh/day applying over 32 quarters.
This results in a Retention Charge for retaining 10mscm at an ASEP of
£321,200.
This should provide suitable encouragement to purchase a retainer whilst
providing an appropriate level of commitment to the industry.
Any revenue streams relating to retention charges would be treated as TO
revenue and adjustments to the TO commodity charge would result as
necessary.
16
Summary
The Retainer Approach protects capacity, but only to the extent that it is genuinely needed, as demonstrated by Shippers taking out Retainers.
A commitment is required from Shippers but this may be much lower than buying the capacity.
National Grid is proposing that retainer charges are refundable if the capacity is bought in later QSEC/AMSEC auctions.
The Retainer Approach allows and encourages Shippers to identify and protect their needs.
The amount of protected capacity is determined by Shipper actions not National Grid assumptions.
18
The Retainer Window
It is proposed that: The Retainer Window will be open for 2 “bid days” from 8am to 5pm;
There will be one day between the bid days;
Retainer requests will not be visible within the bid window but those granted shall be published before 7pm on the bid day;
This will consist of relevant ASEP and quantity.
The same data on retainers granted will be included in the QSEC invitation letter.
Retainers will be requested via fax. A pro-forma will be developed.
Any retainers requested cannot be removed or amended except where the request submitted is identified by National Grid as blatantly erroneous and is rejected.
National Grid will accept no liability in respect of erroneous applications, but will endeavour to resolve errors within the bid day. Those not resolved or rejected by 5pm will be accepted as submitted.
Any pro-rating due to retainers exceeding available capacity will be carried out at the end of each bid day.
The Retainer Window will be run in January (see timeline).
Avoid clash with AMSEC in February.
19
Retainer Approach: Timeline for 2010 QSEC
Mid Dec
Invitation letter for retainers issued
7 Dec Approval of
Methodology Statement Charging Proposals and
UNC Mod Proposal
Mid Jan Retainer Window.
2 days plus1 day between
Mid Mar QSEC
Apr / May Bids Allocated - 2 months – as defined in UNC section B 2.6.7
Feb AMSEC
4 tranches with 2 days between
Early June Ad hoc invoice for retainers
as required (and refunds in future years)
NOV 09 DEC 09 JAN 10 FEB 10 MAR 10 APR 10 MAY 10 JUN 10 JUL 10
Mid Feb
QSEC invitation
letter
Mid JanNotice of
QSEC charges
N Grid AnalysisN Grid GovernanceOfgem Governance
Precise dates for QSEC auction to be confirmed
Mid Nov
2 month notice of charges*
* Notice conditional upon approval of charging proposals
20
Retainers: QSEC Capacity Allocation
Allocations in the year a retainer is taken out:-
Unprotected capacity will be allocated first, then the
retained capacity will be allocated
The maximum quantity of capacity at the relevant ASEP
is retained and therefore not substituted.
21
Retained Quantity
Existing Sold Capacity
“Unprotected”
Post-auction allocations
Sold Capacity
Retained Quantity
“Unprotected”
90% baseline
Capacity
Pre-auction capacity
Withheld from QSEC
Baseline capacity
Unsold Capacity
New Sold Capacity
Withheld from QSEC
Unprotected capacity will be allocated first,
then capacity under Retainer.
New Sold CapacityRefund
triggered
QSEC Capacity Allocation - In the year a retainer is taken out
22
Retainers: QSEC Capacity Allocation
Allocations in subsequent auctions for refund allocation
Retained capacity will be allocated first, then unprotected
will be allocated
Therefore the maximum quantity of retained capacity at
the relevant ASEP is allocated in order to trigger a
refund.
23
“Unprotected”
Existing Sold Capacity
Allocations in subsequent auctions
Capacity sold pre-2010
Retained Quantity
“Unprotected”
90% baseline
Capacity
Post-auction capacity in year Retainer applies(Oct 2013 – Sept 2014)
Withheld from QSEC
Baseline capacity
Unsold Capacity
Withheld from QSEC
Retained capacity will be allocated first, then unprotected and withheld capacity.
Capacity sold in 2010
Refund triggered
Retained QuantityCapacity sold in 2011
QSEC Capacity Allocation - In terms of calculating refunds
24
Retainers: QSEC Capacity Allocation…Effect of Permits
Substitution opportunities are assessed from a 42 month default lead
time
Except for when an incremental signal is received and accepted earlier than the default.
e.g. for March 2010 QSEC, allocations from July 2013.
Substitutable capacity is calculated as the smallest unsold/un-retained quantity from the permit start date
For delaying permits, or requests for incremental capacity later than 42 months, substitutable capacity is still determined post-42 months.
Hence permits should not increase the quantity of capacity substituted from a donor ASEP.
25
Retainers: Refunds
Refunds are triggered solely by the allocation of capacity in the period 42-54 months forward from QSEC when the retainer is taken out and will be paid after the final opportunity to obtain capacity, within the QSEC and AMSEC auctions, for this period has passed.
Applies regardless of which Shipper is allocated capacity – need for capacity proven.
Full allocation of capacity = full refund.
Extent of refund is triggered by extent of allocated capacity, not the price for allocated capacity. Price of capacity and retainer charge are not related.
Refunds will be pro-rated if not fully allocated.
Refunds will be pro-rated if more than one Shipper has relevant retainers, and the capacity is not fully allocated, irrespective of individual Shipper allocations.
Refunds will be determined on the basis of the quarters (or months) of maximum capacity allocation before and after the auction. This identifies the maximum quantity of retained capacity that is subsequently allocated. See later slide.
For each ASEP, refunds will be allocated, according to the formula; e.g. for Shipper A
Shipper A retained capacity
retained capacity (all Shippers)
retained capacity allocated (all Shippers)
retained capacity (all Shippers)
Retainer fee (all Shippers)* *
26
Retainer Fee Refunds
Q1
10
Q2
10
Q3
10
Q4
10
Q1
11
Q2
11
Q3
11
Q4
11
Q1
12
Q2
12
Q3
12
Q4
12
Q1
13
Q2
13
Q3
13
Q4
13
Q1
14
Q2
14
Q3
14
Retainer taken
QSEC auction
Period covered by Retainer
Refund if capacity obtained for any month in this period
For a retainer taken out in 2010 a refund may only be triggered by capacity allocation for Q4 2013 to Q3 2014 made pursuant to a QSEC or AMSEC auction.
Why limit to QSEC / AMSEC?• Reserve price applies to these auctions so capacity retained cannot be obtained for zero cost.• Does not apply to RMTTSEC due to interaction with Transfer and Trades.
Why limit to Q4 2013 to Q3 2014?• Default date for release of incremental capacity and hence substitution.• To use a longer period would increase the duration over which retainers need to be tracked and more interacting auctions would need to be considered.
27
Retainer Fee Refunds
Q1
10
Q2
10
Q3
10
Q4
10
Q1
11
Q2
11
Q3
11
Q4
11
Q1
12
Q2
12
Q3
12
Q4
12
Q1
13
Q2
13
Q3
13
Q4
13
Q1
14
Q2
14
Q3
14
Option taken
QSEC auction
Period covered by Option
Refund if capacity obtained for any month in this period
When can a refund be triggered?•Whenever capacity is allocated for Q4 2013 to Q3 2104 in a QSEC / AMSEC
• Hence, can only be in QSEC March 2011 or March 2012; or
• AMSEC February 2013 or February 2014. •NB 2014 AMSEC can only allocate capacity for Q2/Q3 2014.
Period covered by QSEC 11
Period covered by QSEC 12QSEC 11
QSEC 12
AMSEC 13
Period covered by AMSEC 13
AMSEC 14
Period covered by AMSEC 14
28
“Unprotected”
Refunds - example
Capacity up to 2010*
90% baseline
Capacity
Baseline capacity
Peak sold before auction
Withheld from QSEC
E.g. Retainer taken in 2010. Applicable period for refunds is Q4 2013 to Q3 2014.
Retained Quantity
“Unprotected”
Capacity up to 2010*
Withheld from QSEC
Retained Quantity
“Unprotected”
Capacity up to 2010*
Withheld from QSEC
Retained Quantity
“Unprotected”
Capacity up to 2010*
Withheld from QSEC
Retained Quantity
Q4 2013 Q1 2014 Q2 2014 Q3 2014
The refund will be determined from peak sold level after auction minus peak sold level before auction (capped at retained quantity).
X
Shipper commitment
* And including QSEC 2010
29
Retained Quantity
“Unprotected”
Refunds - example
Capacity up to 2010*
90% baseline
Capacity
Baseline capacity
Peak sold after auction
Withheld from QSEC
E.g. Retainer taken in 2010. Allocations made in QSEC 2011 or later.
Retained Quantity
“Unprotected”
Capacity up to 2010*
Withheld from QSEC
Retained Quantity
“Unprotected”
Capacity up to 2010*
Withheld from QSEC
Retained Quantity
“Unprotected”
Capacity up to 2010*
Withheld from QSEC
Capacity sold 2011
Q4 2013 Q1 2014 Q2 2014 Q3 2014
The refund will be determined from peak sold level after auction minus peak sold level before auction (capped at retained quantity): Y - X
X
Capacity sold 2011
Capacity sold 2011
Capacity sold 2011
YActual Shipper
booking
* And including QSEC 2010
31
UNC Modification Proposal
What does the proposal do?
The proposed entry capacity substitution methodology will introduce a new charge: the
“NTS Entry Capacity Retention Charge”.
The proposed UNC modification will create the new charge within UNC.
Why do we need a modification to UNC?
The Retention Charge is a Transportation Charge “in respect of transportation
arrangements under the Code” – UNC TPD Section B1.7.1(a)(i). Hence to enable
National Grid to invoice for the charges they need to be defined in UNC.
Defining the charge as a Transportation Charge enables treatment of retainer charge
revenues within the appropriate transportation revenue streams.
32
UNC Modification Proposal: Relevant Objectives
How does the proposal better facilitate the achievement of the Relevant Objectives?
Standard Special condition A11 (c)
Promotes the efficient discharge National Grid’s Licence obligations by facilitating the introduction of entry capacity substitution as required by Special Condition C8D paragraph 10
Standard Special condition A11 (a)
Promotes efficient and economic operation of the pipeline system by facilitating the introduction of entry capacity substitution thus reducing the need for investment to meet the demand for incremental entry capacity.
Standard Special condition A11 (f)
Promotes efficiency in implementation of UNC as it facilitates administration of charges for retainers.
Disadvantages?
None identified; if substitution proposals are not approved it is expected that the Authority would reject this proposal.
33
UNC Modification Proposal: Other Impacts
Impact on Security of Supply
Whilst concern has been expressed at the possible effect of substitution on security of supply these concerns do not apply to this modification proposal which, in itself, only introduces a new transportation charge.
IT Systems
No impact on IT systems is envisaged. Charges would be invoiced, and refunded, via ad-hoc invoice functionality. A specific invoice charge item could be created in future if necessary.
34
UNC Modification Proposal: Timetable
Aim to align consultation on Modification Proposal, Methodology Statement and
Charging Consultation as much as is practicable.
Aim to have all three proposals with the Authority prior to, or very soon after,
commencement of Ofgem’s Impact Assessment.
Activity DateDiscussion at Transmission Workstream 6th August 2009
Submit to Mod Panel (subject to workstream agreement)20th August 2009
Issue for consultation (subject to Mod Panel approval)
Closeout for representations 11th September 2009
Mod Panel recommendation (accept at short notice)17th September 2009
FMR submitted to Authority
Proposed date of implementation 8th December 2009