Top Banner
Entry Capacity Substitution Transmission Workstream – 6 th August 2009
34

Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

Dec 18, 2015

Download

Documents

Blake Johnston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

Entry Capacity Substitution

Transmission Workstream – 6th August 2009

Page 2: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

2

Agenda

Current Status

Methodology Statement: overview.

Charging Proposal.

Methodology Statement: retainers.

UNC Modification Proposal.

Page 3: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

3

Current Status

Three simultaneous processes with consultations aligned to complete prior to

Ofgem Impact Assessment.

Methodology Statement.

Consultation started 24th July; closes 24th August.

Submission to Authority for approval 7th September.

Charging Consultation.

Consultation (draft) started 28th July;

Formal consultation starts 11th August; closes 14th September.

UNC Modification Proposal.

Propose submission to UNC mod panel following discussion today.

Mod Panel meeting 20th August 2009.

Page 4: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

Methodology Statement: Overview

Transmission Workstream – 6th August 2009

Page 5: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

5

Proposed Entry Capacity Substitution Methodology

National Grid is proposing a methodology that uses “retainers” to limit the exposure of ASEPs to substitution.

Based on the “Option Approach” discussed at workshops.

Retainer considered to better describe the role of the new product.

Avoids confusion with existing Option products.

National Grid believes that this approach is a good compromise between the two extremes of the Mechanical Approach and the Two-Stage Auction.

Requires User Commitment

Relies on Shippers’ assessment of needs not National Grid judgement.

Relatively simple to implement.

Page 6: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

6

“Retainer” Approach

A retainer will prevent capacity at an ASEP from being substituted to a different ASEP in response to an incremental signal elsewhere.

The retainer requires a signal and commitment from Shippers.

The retainer

does not give rights to the Shipper to use the capacity covered by the retainer;

does not give the Shipper first option to buy the capacity; but

it would keep the capacity at the relevant ASEP.

Page 7: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

7

What is the Retainer?

It is proposed that the retainer:

identifies and excludes capacity from substitution processes thereby protecting capacity for the duration of the retainer;

is placed ahead of QSEC and applies for 12 months,

i.e. covers (normally) one QSEC and any ad-hoc QSECs before the next retainer window.

will be subject to a one-off NTS Entry Capacity Retention Charge. This will be a fixed price per unit of capacity and will be the same for all ASEPs.

for the purposes of defining refunds the retainer nominally applies in respect of the 12 months commencing Oct Y+4, i.e. from the default 42 month lead-time;

will still prevent capacity being substituted away if the incremental capacity is allocated earlier or later than the default lead time;

The retainer will not:

prevent other Shippers (or the relevant Shipper) buying capacity at that ASEP in the period covered by the retainer;

be sold in quantities above the quantity available in QSEC (usually 90% baseline – sold);

be available to non-Users. However, extending the process to non-Users could be an option to be considered for 2011.

The Retention charge will be discussed on later slides

Page 8: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

8

90 % of baseline capacity.

(May be higher if incremental capacity has previously been

released).

Time

Capacity Available for Substitution at Donor ASEPs

42 monthsDefault capacity release lead-time

at recipient ASEPs

Sold capacity

Capacity.

Retained quantity

Available capacity for substitution

A key factor in the substitution process is to identify the amount of capacity available at donor ASEPs that can be substituted. The retainer reduces the available quantity.

Page 9: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

9

Substitution Methodology – Associated Issues

National Grid is proposing an exchange rate cap of 3:1

This is significantly lower than the cap applied to Transfer and Trades.

With Shippers having an opportunity through the use of retainers to protect capacity is an additional constraint on substitution by way of any exchange rate cap appropriate?

Partial substitutions will be progressed

Where appropriate incremental capacity will be met through a combination of investment and substitution.

Entry Zones are proposed to be used for selecting potential donor ASEPs.

Within zone, donor ASEPs would be selected on the basis of best exchange rate. Out of zone, donor ASEPs would be selected on the basis of shortest pipeline distance from the recipient ASEP.

Network Analysis will be undertaken to determine substitution opportunities.

Analysis will be consistent with the Transmission Planning Code and hence assessment undertaken to determine investment requirements.

Page 10: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

10

Charging Consultation - NTS GCM 18

The retainer requires a signal and commitment from Shippers.

The charging consultation NTS GCM 18 will

determine the NTS Entry Capacity Retention Charge and

ensure any revenue streams appropriately offset other NTS transportation charges

The Licence requires that the charging methodology

1. Reflects the cost incurred

2. Takes account of developments within the transportation business, and

3. Facilitates effective competition between gas shippers and between gas suppliers

Page 11: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

11

Determination of Commitment Method A - 1

To determine a cost reflective charge National Grid has estimated the avoided costs of

entry capacity substitution.

If incremental capacity is released in a QSEC auction this results in incremental revenue and a

cost to industry.

Substitution avoids this cost.

The potentially avoided cost has been estimated from the average of the capitalised revenue drivers from the two ASEPs where capacity has been released during the present price control.

Have only considered the potential SO allowed revenue over 5 years which is the minimum value.

Capital investment would result in TO allowed revenue for a further 40 years

Dividing by the maximum substitutable quantity gives a unit Retention Charge Rate (p/kWh)

Page 12: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

12

Determination of Commitment Method A - 2

METHODOLOGY A SO Revenue over 5 years

Average Revenue Driver (£m) A £36.34

Substitutable Capacity (GWh) B 2,283.0

Retention Charge Rate

(p/kWh)

C=(100*A)/B 1.5919

Example retention of 10

mscm/d

Retained Daily Capacity

Quantity (mscm/d)

D 10.0

Retained Daily Capacity

Quantity (GWh/d)

E 110.0

Charge to retain 10 mscm/d

(£)

F=10^6*C*E/100 £1,751,106

Retention Charge Rate

(£/mscm/d)

C1=F/10 £175,111

Page 13: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

13

Determination of Commitment Method A - Issues

This calculation would result in an initial rate for the NTS Entry Capacity

retention charge of £175,111 for each mscm/d of capacity retained.

This calculation

has used a forward projection of historic costs and as such is not strictly reflective of the costs incurred;

requires a probability of whether incremental capacity would indeed be signalled and whether it could be met by substitution; and

The avoided costs assume all substitutable capacity is retained. If only half is retained substitution could still occur.

Page 14: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

14

Determination of Commitment Method B

So National Grid has considered an alternative approach which would comply with the

other relevant conditions.

- takes account of developments within the transportation business; and

- facilitates effective competition between gas shippers and between gas suppliers.

METHODOLOGY B

Minimum price over 32 quarters

Example retention of 10 mscm/d

Retained Daily Capacity Quantity (GWh/d) E 110.0

Minimum Price (p/kWh/d) G 0.0001

Charge for retaining 10mscm at an ASEP (£) H=(8*365)*G*E*10^6/100 £321,200

Retention Charge Rate (p/kWh) I=H*100/(E*10^6) 0.292

Retention Charge Rate (£/mscm/d) I1=H/10 £32,120

Page 15: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

15

National Grid’s Proposal (Draft)

National Grid’s proposal (draft)

Methodology B is recommended, which uses the minimal capacity charge rate

of 0.0001p/kWh/day applying over 32 quarters.

This results in a Retention Charge for retaining 10mscm at an ASEP of

£321,200.

This should provide suitable encouragement to purchase a retainer whilst

providing an appropriate level of commitment to the industry.

Any revenue streams relating to retention charges would be treated as TO

revenue and adjustments to the TO commodity charge would result as

necessary.

Page 16: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

16

Summary

The Retainer Approach protects capacity, but only to the extent that it is genuinely needed, as demonstrated by Shippers taking out Retainers.

A commitment is required from Shippers but this may be much lower than buying the capacity.

National Grid is proposing that retainer charges are refundable if the capacity is bought in later QSEC/AMSEC auctions.

The Retainer Approach allows and encourages Shippers to identify and protect their needs.

The amount of protected capacity is determined by Shipper actions not National Grid assumptions.

Page 17: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

Methodology Statement: Retainers

Transmission Workstream – 6th August 2009

Page 18: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

18

The Retainer Window

It is proposed that: The Retainer Window will be open for 2 “bid days” from 8am to 5pm;

There will be one day between the bid days;

Retainer requests will not be visible within the bid window but those granted shall be published before 7pm on the bid day;

This will consist of relevant ASEP and quantity.

The same data on retainers granted will be included in the QSEC invitation letter.

Retainers will be requested via fax. A pro-forma will be developed.

Any retainers requested cannot be removed or amended except where the request submitted is identified by National Grid as blatantly erroneous and is rejected.

National Grid will accept no liability in respect of erroneous applications, but will endeavour to resolve errors within the bid day. Those not resolved or rejected by 5pm will be accepted as submitted.

Any pro-rating due to retainers exceeding available capacity will be carried out at the end of each bid day.

The Retainer Window will be run in January (see timeline).

Avoid clash with AMSEC in February.

Page 19: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

19

Retainer Approach: Timeline for 2010 QSEC

Mid Dec

Invitation letter for retainers issued

7 Dec Approval of

Methodology Statement Charging Proposals and

UNC Mod Proposal

Mid Jan Retainer Window.

2 days plus1 day between

Mid Mar QSEC

Apr / May Bids Allocated - 2 months – as defined in UNC section B 2.6.7

Feb AMSEC

4 tranches with 2 days between

Early June Ad hoc invoice for retainers

as required (and refunds in future years)

NOV 09 DEC 09 JAN 10 FEB 10 MAR 10 APR 10 MAY 10 JUN 10 JUL 10

Mid Feb

QSEC invitation

letter

Mid JanNotice of

QSEC charges

N Grid AnalysisN Grid GovernanceOfgem Governance

Precise dates for QSEC auction to be confirmed

Mid Nov

2 month notice of charges*

* Notice conditional upon approval of charging proposals

Page 20: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

20

Retainers: QSEC Capacity Allocation

Allocations in the year a retainer is taken out:-

Unprotected capacity will be allocated first, then the

retained capacity will be allocated

The maximum quantity of capacity at the relevant ASEP

is retained and therefore not substituted.

Page 21: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

21

Retained Quantity

Existing Sold Capacity

“Unprotected”

Post-auction allocations

Sold Capacity

Retained Quantity

“Unprotected”

90% baseline

Capacity

Pre-auction capacity

Withheld from QSEC

Baseline capacity

Unsold Capacity

New Sold Capacity

Withheld from QSEC

Unprotected capacity will be allocated first,

then capacity under Retainer.

New Sold CapacityRefund

triggered

QSEC Capacity Allocation - In the year a retainer is taken out

Page 22: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

22

Retainers: QSEC Capacity Allocation

Allocations in subsequent auctions for refund allocation

Retained capacity will be allocated first, then unprotected

will be allocated

Therefore the maximum quantity of retained capacity at

the relevant ASEP is allocated in order to trigger a

refund.

Page 23: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

23

“Unprotected”

Existing Sold Capacity

Allocations in subsequent auctions

Capacity sold pre-2010

Retained Quantity

“Unprotected”

90% baseline

Capacity

Post-auction capacity in year Retainer applies(Oct 2013 – Sept 2014)

Withheld from QSEC

Baseline capacity

Unsold Capacity

Withheld from QSEC

Retained capacity will be allocated first, then unprotected and withheld capacity.

Capacity sold in 2010

Refund triggered

Retained QuantityCapacity sold in 2011

QSEC Capacity Allocation - In terms of calculating refunds

Page 24: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

24

Retainers: QSEC Capacity Allocation…Effect of Permits

Substitution opportunities are assessed from a 42 month default lead

time

Except for when an incremental signal is received and accepted earlier than the default.

e.g. for March 2010 QSEC, allocations from July 2013.

Substitutable capacity is calculated as the smallest unsold/un-retained quantity from the permit start date

For delaying permits, or requests for incremental capacity later than 42 months, substitutable capacity is still determined post-42 months.

Hence permits should not increase the quantity of capacity substituted from a donor ASEP.

Page 25: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

25

Retainers: Refunds

Refunds are triggered solely by the allocation of capacity in the period 42-54 months forward from QSEC when the retainer is taken out and will be paid after the final opportunity to obtain capacity, within the QSEC and AMSEC auctions, for this period has passed.

Applies regardless of which Shipper is allocated capacity – need for capacity proven.

Full allocation of capacity = full refund.

Extent of refund is triggered by extent of allocated capacity, not the price for allocated capacity. Price of capacity and retainer charge are not related.

Refunds will be pro-rated if not fully allocated.

Refunds will be pro-rated if more than one Shipper has relevant retainers, and the capacity is not fully allocated, irrespective of individual Shipper allocations.

Refunds will be determined on the basis of the quarters (or months) of maximum capacity allocation before and after the auction. This identifies the maximum quantity of retained capacity that is subsequently allocated. See later slide.

For each ASEP, refunds will be allocated, according to the formula; e.g. for Shipper A

Shipper A retained capacity

retained capacity (all Shippers)

retained capacity allocated (all Shippers)

retained capacity (all Shippers)

Retainer fee (all Shippers)* *

Page 26: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

26

Retainer Fee Refunds

Q1

10

Q2

10

Q3

10

Q4

10

Q1

11

Q2

11

Q3

11

Q4

11

Q1

12

Q2

12

Q3

12

Q4

12

Q1

13

Q2

13

Q3

13

Q4

13

Q1

14

Q2

14

Q3

14

Retainer taken

QSEC auction

Period covered by Retainer

Refund if capacity obtained for any month in this period

For a retainer taken out in 2010 a refund may only be triggered by capacity allocation for Q4 2013 to Q3 2014 made pursuant to a QSEC or AMSEC auction.

Why limit to QSEC / AMSEC?• Reserve price applies to these auctions so capacity retained cannot be obtained for zero cost.• Does not apply to RMTTSEC due to interaction with Transfer and Trades.

Why limit to Q4 2013 to Q3 2014?• Default date for release of incremental capacity and hence substitution.• To use a longer period would increase the duration over which retainers need to be tracked and more interacting auctions would need to be considered.

Page 27: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

27

Retainer Fee Refunds

Q1

10

Q2

10

Q3

10

Q4

10

Q1

11

Q2

11

Q3

11

Q4

11

Q1

12

Q2

12

Q3

12

Q4

12

Q1

13

Q2

13

Q3

13

Q4

13

Q1

14

Q2

14

Q3

14

Option taken

QSEC auction

Period covered by Option

Refund if capacity obtained for any month in this period

When can a refund be triggered?•Whenever capacity is allocated for Q4 2013 to Q3 2104 in a QSEC / AMSEC

• Hence, can only be in QSEC March 2011 or March 2012; or

• AMSEC February 2013 or February 2014. •NB 2014 AMSEC can only allocate capacity for Q2/Q3 2014.

Period covered by QSEC 11

Period covered by QSEC 12QSEC 11

QSEC 12

AMSEC 13

Period covered by AMSEC 13

AMSEC 14

Period covered by AMSEC 14

Page 28: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

28

“Unprotected”

Refunds - example

Capacity up to 2010*

90% baseline

Capacity

Baseline capacity

Peak sold before auction

Withheld from QSEC

E.g. Retainer taken in 2010. Applicable period for refunds is Q4 2013 to Q3 2014.

Retained Quantity

“Unprotected”

Capacity up to 2010*

Withheld from QSEC

Retained Quantity

“Unprotected”

Capacity up to 2010*

Withheld from QSEC

Retained Quantity

“Unprotected”

Capacity up to 2010*

Withheld from QSEC

Retained Quantity

Q4 2013 Q1 2014 Q2 2014 Q3 2014

The refund will be determined from peak sold level after auction minus peak sold level before auction (capped at retained quantity).

X

Shipper commitment

* And including QSEC 2010

Page 29: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

29

Retained Quantity

“Unprotected”

Refunds - example

Capacity up to 2010*

90% baseline

Capacity

Baseline capacity

Peak sold after auction

Withheld from QSEC

E.g. Retainer taken in 2010. Allocations made in QSEC 2011 or later.

Retained Quantity

“Unprotected”

Capacity up to 2010*

Withheld from QSEC

Retained Quantity

“Unprotected”

Capacity up to 2010*

Withheld from QSEC

Retained Quantity

“Unprotected”

Capacity up to 2010*

Withheld from QSEC

Capacity sold 2011

Q4 2013 Q1 2014 Q2 2014 Q3 2014

The refund will be determined from peak sold level after auction minus peak sold level before auction (capped at retained quantity): Y - X

X

Capacity sold 2011

Capacity sold 2011

Capacity sold 2011

YActual Shipper

booking

* And including QSEC 2010

Page 30: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

UNC Modification Proposal

Transmission Workstream – 6th August 2009

Page 31: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

31

UNC Modification Proposal

What does the proposal do?

The proposed entry capacity substitution methodology will introduce a new charge: the

“NTS Entry Capacity Retention Charge”.

The proposed UNC modification will create the new charge within UNC.

Why do we need a modification to UNC?

The Retention Charge is a Transportation Charge “in respect of transportation

arrangements under the Code” – UNC TPD Section B1.7.1(a)(i). Hence to enable

National Grid to invoice for the charges they need to be defined in UNC.

Defining the charge as a Transportation Charge enables treatment of retainer charge

revenues within the appropriate transportation revenue streams.

Page 32: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

32

UNC Modification Proposal: Relevant Objectives

How does the proposal better facilitate the achievement of the Relevant Objectives?

Standard Special condition A11 (c)

Promotes the efficient discharge National Grid’s Licence obligations by facilitating the introduction of entry capacity substitution as required by Special Condition C8D paragraph 10

Standard Special condition A11 (a)

Promotes efficient and economic operation of the pipeline system by facilitating the introduction of entry capacity substitution thus reducing the need for investment to meet the demand for incremental entry capacity.

Standard Special condition A11 (f)

Promotes efficiency in implementation of UNC as it facilitates administration of charges for retainers.

Disadvantages?

None identified; if substitution proposals are not approved it is expected that the Authority would reject this proposal.

Page 33: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

33

UNC Modification Proposal: Other Impacts

Impact on Security of Supply

Whilst concern has been expressed at the possible effect of substitution on security of supply these concerns do not apply to this modification proposal which, in itself, only introduces a new transportation charge.

IT Systems

No impact on IT systems is envisaged. Charges would be invoiced, and refunded, via ad-hoc invoice functionality. A specific invoice charge item could be created in future if necessary.

Page 34: Entry Capacity Substitution Transmission Workstream – 6 th August 2009.

34

UNC Modification Proposal: Timetable

Aim to align consultation on Modification Proposal, Methodology Statement and

Charging Consultation as much as is practicable.

Aim to have all three proposals with the Authority prior to, or very soon after,

commencement of Ofgem’s Impact Assessment.

Activity DateDiscussion at Transmission Workstream 6th August 2009

Submit to Mod Panel (subject to workstream agreement)20th August 2009

Issue for consultation (subject to Mod Panel approval)

Closeout for representations 11th September 2009

Mod Panel recommendation (accept at short notice)17th September 2009

FMR submitted to Authority

Proposed date of implementation 8th December 2009