Engineering Services N N O O R R T T H H S S I I D D E E I I N N D D E E P P E E N N D D E E N N T T S S C C H H O O O O L L D D I I S S T T R R I I C C T T Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION Richard De La Cruz ASSISTANT DIRECTOR OF ENGINEERING 2010/2007 Bond Update August 16, 2013
70
Embed
Engineering Services - Northside Independent School District€¦ · HVAC UPGRADES KNOWLTON ELEMENTARY SCHOOL Engineer – Wallis Engineering Group NISD Project Manager – Alfred
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION
Richard De La Cruz ASSISTANT DIRECTOR OF ENGINEERING
2010/2007 Bond Update August 16, 2013
FIRE ALARM SYSTEM REPLACEMENTS JERRY D. ALLEN ELEMENTARY SCHOOL & SUL ROSS MIDDLE SCHOOL
Engineer – CNG Engineering NISD Project Manager – A.J. Halbardier Contractor – Consolidated Electric Service, Inc. Contract Amount: $258,000.00 Construction Period – May 31, 2013 – August 16, 2013 Project Scope – Replace existing fire alarm system (2010 Bond Funds) 90% Complete
GLENOAKS ELEMENTARY SCHOOL & JACK C. JORDAN MIDDLE SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – A.J. Halbardier Contractor – Consolidated Electric Service, Inc. Contract Amount - $239,000.00 Construction Period – May 31, 2013 – August 16, 2013 Project Scope – Replace existing fire alarm system (2010 Bond Funds) 50% Complete
GLENOAKS ELEMENTARY SCHOOL
JACK C. JORDAN MIDDLE SCHOOL
ROBERT F. McDERMOTT ELEMENTARY SCHOOL & HOLMGREEN CENTER
Engineer – CNG Engineering NISD Project Manager – A.J. Halbardier Contractor – Convergint Technologies Contract Amount - $139,673.00 Construction Period – August 19, 2013 – November 22, 2013 Project Scope – Replace existing fire alarm system (2010 Bond Funds) 0% Construction
F.R. SCOBEE ELEMENTARY SCHOOL & STINSON MIDDLE SCHOOL
Engineer – Alderson & Associates NISD Project Manager – A.J. Halbardier Contractor – Consolidated Electric Service, Inc. Contract Amount - $262,000.00 Construction Period – August 19, 2013 – November 22, 2013 Project Scope – Replace existing fire alarm system (2010 Bond Funds) 0% Construction
HVAC UPGRADES COLONIES NORTH ELEMENTARY SCHOOL
Engineer – Wallis Engineering Group NISD Project Manager – Alfred Vitella III, P.E. Contractor – Flo-Aire Services, Inc. Contract Amount - $1,188,810.00 Construction Period – June 12, 2013 – August 9, 2013 Project Scope – Upgrade of the HVAC System (2007 Bond Funds) 95% Complete
COLONIES NORTH ES - HVAC RENOVATIONS (8-9-13)
HVAC UPGRADES KNOWLTON ELEMENTARY SCHOOL
Engineer – Wallis Engineering Group NISD Project Manager – Alfred Vitella III, P.E. Contractor – International Mechanical Services, Inc. Contract Amount - $1,145,000.00 Construction Period – June 12, 2013 – August 9, 2013 Project Scope – Chiller Replacement and Partial HVAC Renovation
(2010 Bond Funds) 90% Complete
KNOWLTON ELEMENTARY SCHOOL
HVAC UPGRADES ZACHRY MIDDLE SCHOOL
Engineer – Cleary Zimmermann Engineers NISD Project Manager – Alfred Vitella III, P.E. Contractor – Gillette Air Conditioning Co., Inc. Contract Amount - $1,070,000.00 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Central Plant Upgrades; unit ventilators replaced with
science addition project (2010 Bond Funds) 80% Complete
ZACHRY MIDDLE SCHOOL - CENTRAL PLANT UPGRADES (8-9-13)
BOILER REPLACEMENTS DISTRICT WIDE: CLARK HS, HOLMES HS, JONES MS, SUL ROSS MS, COKE STEVENSON MS, BRAUCHLE ES & GALM ES
Engineer – MS2 Consulting Engineers NISD Project Manager – Alfred Vitela III, P.E. Contractor – International Mechanical Services, Inc. Contract Amount - $758,425.00 Construction Period – June 2012 – August 2013 Project Scope – Replace end-of-life domestic Boilers (2010 Bond
Funds) 85% Complete Schools completed - Brauchle ES, Galm ES, Holmes HS and Clark HS Schools Remaining - Jones MS, Stevenson MS & Sul Ross MS
LIGHTING UPGRADES RAYBURN MIDDLE SCHOOL & NORTHSIDE LEARNING CENTER (NLC)
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Contract Amount - $45,000.00 Construction Period – June 10, 2013 – August 20, 2013 Project Scope – Lighting Retro-Fit (2010 Bond Funds) 94% Complete
RAYBURN MS & NLC
RAYBURN MS
NLC NLC
JERRY ALLEN ES, SUL ROSS MS & PAT NEFF MS
Engineer – CNG Engineering NISD Project Manager – Ramiro Guerrero Contractor – Excel Energy Group, Inc. Contract Amount - $137,433.97 Construction Period – June 10, 2013 – August 20, 2013 Project Scope – Lighting Retro-Fit (2010 Bond Funds) 94% Complete
JERRY ALLEN ES
SUL ROSS MS
PAT NEFF MS
F.R. SCOBEE ES & JOHN MARSHALL HS
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Contract Amount - $78,000.00 Construction Period – May 20, 2013 – August 9, 2013 Project Scope – Lighting Retro-Fit (2010 Bond Funds) 94% Complete
SCOBEE ES & MARSHALL HS
SCOBEE ES
MARSHALL HS
OAK HILLS TERRACE ELEMENTARY SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Quinney Electric, Inc. Construction Cost - $51,300.00 Construction Period – June 3, 2013 – August 20, 2013 Project Scope – Lighting Retro-fit (2010 Bond Funds) 94% Complete
OAK HILLS TERRACE ELEMENTARY SCHOOL
COKE R. STEVENSON MS & HENRY T. BRAUCHLE ES
Engineer – CNG Engineering NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Contract Amount - $108,000.00 Construction Period – June 10, 2013 – August 20, 2013 Project Scope – Lighting Retro-Fit (2010 Bond Funds) 94% Complete
COKE R. STEVENSON MS & HENRY T. BRAUCHLE ES
STEVENSON MS
BRAUCHLE ES
HELOTES ELEMENTARY SCHOOL & LEON VALLEY ELEMENTARY SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Excel Energy Group, Inc. Contract Amount - $105,541.34 Construction Period – May 20, 2013 – August 9, 2013 Project Scope – Lighting Retro-Fit (2010 Bond Funds) 94% Complete
HELOTES ELEMENTARY SCHOOL & LEON VALLEY ELEMENTARY SCHOOL
HELOTES ES
LEON VALLEY ES
EDUARDO VILLARREAL ELEMENTARY SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Contract Amount - $140,000.00 Construction Period – June 3, 2013 – August 20, 2013 Project Scope – Lighting Retro-Fit (2010 Bond Funds) 94% Complete
EDUARDO VILLARREAL ES
ELECTRICAL UPGRADES COLBY GLASS ELEMENTARY SCHOOL
Engineer – Wallis Engineering Group, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Big State Electric, Ltd. Contract Amount - $290,000.00 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Electrical Upgrades (2007 Bond Savings) 94% Complete
COLBY GLASS ES - Electrical Upgrades
SITE LIGHTING REPLACEMENT BRAUN STATION ELEMENTARY SCHOOL
Engineer – Alderson & Associates NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Contract Amount - $65,000.00 Construction Period – June 12, 2013 – August 9, 2013 Project Scope – Site Lighting Replacement (2010 Bond Savings) 95% Complete
BRAUN STATION ES - Site Lighting Replacement
PAVING / PARKING / DRAINAGE HENRY T. BRAUCHLE ELEMENTARY SCHOOL
Engineer – Bury+Partners-SA, Inc. NISD Project Manager – Richard De La Cruz, P.E. Contractor – R.L. Rohde General Contracting, Inc. Contract Amount - $57,500.00 Construction Period – June 8, 2013 – August 9, 2013 Project Scope – Drainage Improvements (2010 Bond Funds) 94% Complete
HENRY T. BRAUCHLE ES - Drainage Improvements
MURRAY E. BOONE ELEMENTARY SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – D&D Contractors, Inc. Contract Amount - $289,064.48 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Paving Improvements (2010 Bond Funds) 95% Complete
MURRAY E. BOONE ES - Paving Improvements
ED CODY ELEMENTARY SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rhode General Contracting, Inc. Contract Amount - $156,000.00 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Paving Improvements (2010 Bond Funds) 100% Complete – Construction Complete
ED CODY ELEMENTARY SCHOOL
BEFORE AFTER
HEALTH CAREERS HIGH SCHOOL
Engineer – Cude Engineers NISD Project Manager – Richard De La Cruz, P.E. Contractor – Alamo City Constructors, Inc. Contract Amount - $162,000.00 Construction Period – June 8, 2013 – August 9, 2013 Project Scope – Paving Improvements (2010 Bond Funds) 95% Complete – Substantial Completion Inspection performed;
awaiting close-out documents
HEALTH CAREERS HS - Paving Improvements
DR. MARTHA MEAD ELEMENTARY SCHOOL
Engineer – Bury+Partners-SA, Inc. NISD Project Manager – Richard De La Cruz, P.E. Contractor – Industrial Construction Co. Contract Amount - $33,428.00 Construction Period – June 8, 2013 – August 9, 2013 Project Scope – Drainage Improvements (2010 Bond Funds) 95% Complete
DR. MARTHA MEAD ES - Drainage Improvements
\
WILLIAM H. TAFT HIGH SCHOOL
Engineer – Cude Engineers NISD Project Manager – Richard De La Cruz, P.E. Contractor – D. Plata Construction Co., LLC Contract Amount - $87,844.72 Construction Period – June 8, 2013 – August 9, 2013 Project Scope – Paving Improvements (2010 Bond Funds) 94% Complete
WILLIAM H. TAFT HS - Paving Improvements
SANDRA DAY O’CONNOR HIGH SCHOOL
Engineer – Cude Engineers NISD Project Manager – Ramiro Guerrero Contractor – Yantis Company d/b/a YC Partners, Ltd. Contract Amount - $59,700.00 Construction Period – July 11, 2013- August 9, 2013 Project Scope – Paving Improvements (2010 Bond Funds) 95% Complete
SANDRA DAY O’CONNOR HIGH SCHOOL
PAVING/PARKING/DRAINAGE NISD CENTRAL OFFICE
Engineering Firm – Civil Engineering Consultants NISD Project Manager – Richard De La Cruz, P.E. Contractor – TBD Construction Cost - $300,000.00 Construction Period – December 2013 Project Scope – Reconstruct or overlay existing parking lot and
driveway (2010 Bond Funds) 100% Design – Not yet in construction. August 2013 Board approval.
PLAYGROUND UPGRADES BRAUN STATION ELEMENTARY SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Contract Amount - $203,000.00 Construction Period – July 1, 2013 – August 16, 2013 Project Scope – Upgrade playground equipment, install new wood fiber
surfacing and ADA accessibility upgrades in upper level playgrounds (2010 Bond Funds)
90% Complete – Pre-Construction Meetings held
DISTRICT-WIDE UPPER-LEVEL PLAYGROUNDS GROUP 4: (GALM, LEWIS, PASSMORE AND COON ELEMENTARY SCHOOLS)
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Contract Amount - $623,000.00 Construction Period – May 1, 2013 – August 16, 2013 Project Scope –Upgrade playground equipment, install new wood fiber
surfacing and ADA accessibility upgrades in upper level playgrounds (2010 Bond Funds)
95% Complete – Pre-Construction Meetings held; construction underway
PLAYGROUNDS GROUP 4: LEWIS ES
DISTRICT-WIDE UPPER-LEVEL PLAYGROUNDS GROUP 5: (CARSON, GLASS, NORTHWEST CROSSING AND VILLARREAL ELEMENTARY SCHOOLS)
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Contract Amount - $639,200.00 Construction Period – May 1, 2013 – August 16, 2013 Project Scope –Upgrade playground equipment, install new wood fiber
surfacing and ADA accessibility upgrades in upper level playgrounds (2010 Bond Funds)
95% Complete - Pre-Construction Meetings held; construction underway
DISTRICT-WIDE UPPER-LEVEL PLAYGROUNDS GROUP 6: (COLONIES NORTH, GLEN OAKS, LEON SPRINGS AND McDERMOT ELEMENTARY SCHOOLS)
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Contract Amount - $499,979.16 Construction Period – May 1, 2013 – August 16, 2013 Project Scope – Upgrade playground equipment, install new wood fiber
surfacing and ADA accessibility upgrades in upper level playgrounds (2010 Bond Funds)
95% Complete - Pre-Construction Meetings held; construction underway
Engineering Firm – Moy Tarin Ramirez Engineers, LLC. NISD Project Manager – Mike Boehmer Contractor – Suburban Construction Co. Contract Amount - $210,000.00 Construction Period – June 6, 2013 – August 2, 2013 Project Scope – Replace unsafe bleacher sections (2007 Bond Savings) 94% Complete – Pre-Construction Meeting held; construction
underway
GUSTAFSON STADIUM - Bleacher Replacements
COURTYARD IMPROVEMENTS HATCHETT ELEMENTARY SCHOOL Engineering Firm – Cude Engineers, LLC NISD Project Manager – Richard De La Cruz, P.E. Contractor – The GFP Group, LLC Contract Amount - $573,000 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Replacing concrete playcourt and adjusting existing
paving due to ground movement (2007 Bond Savings) 55% Complete
HATCHETT ELEMENTARY SCHOOL - Courtyard Improvements
HATCHETT ELEMENTARY SCHOOL - Courtyard Improvements
NAMS-NORTH (NORTHSIDE ALTERNATIVE MIDDLE SCHOOL – NORTH)
Engineering Firm – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Ramiro Guerrero Contractor – R.L. Rohde General Contracting, Inc. Contract Amount - $288,000.00 Construction Period – June 8, 2013 – August 9, 2013 Project Scope – Improvement to the Courtyard and driveways
(2007 Bond Savings) 70% Complete
NAMS-NORTH - COURTYARD IMPROVEMENTS
BEFORE
NAMS-NORTH - COURTYARD IMPROVEMENTS
DURING CONSTRUCTION
FLASHERS 2013 DR. SARA B. McANDREW ELEMENTARY SCHOOL
Engineer – Civil Engineering Consultants NISD Project Manager – Richard De La Cruz, P.E. Contractor – Saeco Electric & Utility Contract Amount - $24,999.00 Construction Period – May 7, 2013 – August 9, 2013 Project Scope – Install school flashers (2010 Bond Funds) 75% Complete
FLASHERS 2013 DR. FOLKS MIDDLE SCHOOL & KAY FRANKLIN ELEMENTARY SCHOOL
Engineer – Cude Engineering Consultants NISD Project Manager – Richard De La Cruz, P.E. Contractor – The Levy Company, LP Contract Amount - $55,650.00 Construction Period – May 7, 2013 – August 9, 2013 Project Scope – Install school flashers (2010 Bond Funds) 75% Complete
TENNIS COURTS O’CONNOR HIGH SCHOOL & PAT NEFF MIDDLE SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – Hellas Construction Contract Amount - $77,600.00 Construction Period – June 11, 2013 – August 9, 2013 Project Scope – Resurface Tennis Courts (2010 Bond Funds) 95% Complete – Construction complete; awaiting close-out documents
PAT NEFF MIDDLE SCHOOL - Tennis Courts
BEFORE
AFTER
O’CONNOR HIGH CHOOL - Tennis Courts
HIGH SCHOOL TRACKS HIGH SCHOOL TRACK PROJECTS–PACKAGE II: CLARK, MARSHALL, O’CONNOR, TAFT & WARREN - HIGH SCHOOLS
Engineering Firm – Cude Engineers NISD Project Manager – Richard De La Cruz, P.E. Contractor – Joeris General Contractor Phase II Contract Amount - $7,460,960.00 Construction Period – November 2012 - June 2013 Project Scope – Install eight (8) lane all-weather running tracks (2007
Bond Savings) Project Type – High School Tracks 95% Complete – Taft HS, Warren HS, Marshall HS, Clark HS, O’Connor
HS – under construction. Substantial Completion Inspections on O’Connor HS and Marshall HS - finalized.