Director’s Cost, Schedule and Status Review of the sPHENIX Infrastructure and Facility Upgrade Engineering Management and Coordination James Mills October 16-17, 2019 BNL
Director’s Cost, Schedule and Status Review of thesPHENIX Infrastructure and Facility Upgrade
Engineering Management and Coordination
James MillsOctober 16-17, 2019
BNL
Engineering Management and Coordination
October 16-17, 2019 2Director's Cost, Schedule and Status Review
This presentation will discuss the following:– Engineering Management and Staff– Engineering Controls– Standing Meetings– Technical Project Reviews - Status – sPHENIX Documents and Procedures - Status– Integration - Status
Engineering Management
October 16-17, 2019 3Director's Cost, Schedule and Status Review
sPHENIX Senior Engineering Staff– J. Mills – Project Engineer– R. Feder – Chief Mechanical Engineer – R. Ruggiero – Chief Design Engineer– L. Stiegler/A. Franz – Safety Engineering– C. Gortakowski – Quality Assurance
Departmental Engineering Management Support– J. Tuozzolo – Chief Mechanical Engineer – CAD– J. Sandberg – Chief Electrical Engineer – CAD– M. Anerella – Chief Mechanical Engineer – SMD– C. Folz – Head, Facilities and Experimental Support - CAD– B. Wahl – Chief Operation Officer (IO) / Deputy PM (nEXO)
• Experienced Senior Staff 25+ years experience
• Senior Engineering Support from CAD, SMD, NSLS II, and Instrumentation
• BNL ESH and Quality Support
WBS No. Detector Element Engineering Lead Institution-Dept Support Engineering1.02 TPC J. Cozzolino BNL - SMD S. Bellavia (CAD), M. Anerella (SMD), J. Kuczewski (ID), C. Miraval (ID), R. Pisani 1.03 EMCal S. Stoll BNL - PH D. Cacace (PH), R. Pisani (PH), E. Thorsland (UIUC)1.04 Hcal R. Feder BNL - PH R. Ruggiero, R. Pisani (PH), C. Pontieri (PH), J. Mills (CAD), D. Cacace (PH)1.05 CalElect S. Boose BNL - PH E. Mannel (PH), S. Polizzo (PH)1.06 DAQ/Trigger E. Desmond (Ret.) BNL - PH J. Kuczewski (ID)1.07 Min-Bias Trigger Detector Chi Columbia U. R. Ruggiero (PH)2.02 Magnet M. Anerella BNL - SMD R. Than (CAD), C. Schultheiss (CAD), P. Orfin (CAD), P. Rosas (CAD), T. Tallerico 2.03 Carriage - Structural Components C. Pontieri BNL - PH J. Hock (CAD), J. Mills (CAD)2.04 Infrastructure R. Pisani (Interim) BNL - PH B. Streckenbach (CAD), M. Mapes (CAD), J. Vasquez (PH)2.05 Installation and Integration R. Feder BNL - PH C. Pontieri (PH), D. Phillips (CAD), R. Ruggiero (PH), B. Streckenbach (CAD)3.01 INTT D. Cacace BNL- PH C. Miraval (ID)3.02 MVTX W. Sondheim LANL Jason Bessuille (MIT), James Kelsey (MIT), Joseph Dodge (MIT)
Safety Engineering L. Stiegler/A. Franz BNL - PH B. Streckenbach (CAD)Q/A C. Gortakowski BNL - PP&QM D. Passarello (CAD)
BNL-ID Instrumentation Division MIT Bates - Massachusetts Institute of TechnologyBNL-CAD Collider Accelerator Dept. LANL Los Alamos National Laboratory
BNL-PP&QM Planning, Performance and Quality Mngt. BNL-SMD Superconducting Magnet DivisionBNL-PH Physics Department UIUC University of Illinois Urbana-Champaign
sPHENIX Engineering Staff
October 16-17, 2019 4Director's Cost, Schedule and Status Review
Experienced Staff – Most Leads have been with sPHENIX since 2014. Some
turnover of key people.
Sheet1
WBS No.Detector ElementEngineering LeadInstitution-DeptSupport EngineeringWBS No.Detector ElementDesign Team
1.02TPCJ. CozzolinoBNL - SMDS. Bellavia (CAD), M. Anerella (SMD), J. Kuczewski (ID), C. Miraval (ID), R. Pisani (PH), D. Cacace (PH)S. Bellavia (CAD), M. Anerella (SMD), J. Kuczewski (ID), C. Miraval (ID), R. Pisani (PH)1.02TPCC. Miraval (ID)
1.03EMCalS. StollBNL - PHD. Cacace (PH), R. Pisani (PH), E. Thorsland (UIUC)D. Cacace (PH), R. Pisani1.03EMCalD. Cacace (PH), R. Ruggiero (PH)
1.04HcalR. Feder BNL - PHR. Ruggiero, R. Pisani (PH), C. Pontieri (PH), J. Mills (CAD), D. Cacace (PH)R. Pisani1.04HcalR. Ruggiero (PH), R. Faussete (NSLS II)
1.05CalElectS. BooseBNL - PHE. Mannel (PH), S. Polizzo (PH) 1.05CalElectS. Polizzo (PH)
1.06DAQ/TriggerE. Desmond (Ret.)BNL - PHJ. Kuczewski (ID)1.06DAQ/TriggerP. Hamblen (PH)
1.07Min-Bias Trigger DetectorChiColumbia U.R. Ruggiero (PH)N/A1.07Min-Bias Trigger DetectorR. Ruggiero (PH)
2.02MagnetM. AnerellaBNL - SMDR. Than (CAD), C. Schultheiss (CAD), P. Orfin (CAD), P. Rosas (CAD), T. Tallerico (CAD), D. Phillips (CAD)R. Than (CAD), C. Schultheiss (CAD), P. Orfin (CAD), P. Rosas (CAD), T. Tallerico (CAD), D. Phillips (CAD)2.02MagnetR. Meier (CAD), P. Kovach (SMD)
2.03Carriage - Structural ComponentsC. PontieriBNL - PHJ. Hock (CAD), J. Mills (CAD)J. Hock (CAD), J. Mills (CAD)2.03Carriage - Structural ComponentsJ. Scheblien (PH), D. Puleo (CAD), A. DeSantis (NSLS II)
2.04InfrastructureR. Pisani (Interim)BNL - PHB. Streckenbach (CAD), M. Mapes (CAD), J. Vasquez (PH)B. Streckenbach (CAD), M. Mapes (CAD), R. Pisani (PH)2.04InfrastructureP. Hamblen (PH), A. DeSantis (NSLS II)
2.05Installation and IntegrationR. FederBNL - PHC. Pontieri (PH), D. Phillips (CAD), R. Ruggiero (PH), B. Streckenbach (CAD)D. Phillips (CAD), R. Ruggiero (PH)2.05Installation and IntegrationR. Ruggiero (PH), R. Faussete (NSLS II)
3.01INTTD. CacaceBNL- PHC. Miraval (ID)3.01INTTD. Cacace (PH), C. Miraval (ID)
3.02MVTXW. SondheimLANLJason Bessuille (MIT), James Kelsey (MIT), Joseph Dodge (MIT)3.02MVTXLANL/MIT Designers
ID - BNL Instrumentation DivisionSMD - BNL Superconducting Magnet Division
Safety EngineeringL. Stiegler/A. FranzBNL - PHB. Streckenbach (CAD) B. Streckenbach (CAD)CAD - BNL Collider Accelerator Dept.MIT - Bates/MIT
Q/AC. GortakowskiBNL - PP&QMD. Passarello (CAD)D. Passarello (CAD)PH - BNL Physics DepartmentLANL - Los Alamos National Laboratory
NSLS II - BNL National Synchrotron Light Source II
BNL-IDInstrumentation DivisionMITBates - Massachusetts Institute of Technology
BNL-CADCollider Accelerator Dept.LANLLos Alamos National Laboratory
BNL-PP&QMPlanning, Performance and Quality Mngt.BNL-SMDSuperconducting Magnet Division
BNL-PHPhysics DepartmentUIUCUniversity of Illinois Urbana-Champaign
Engineering Design Staff
October 16-17, 2019 5Director's Cost, Schedule and Status Review
Chief Design Engineer/Detector Integration - R. Ruggiero (PH)
WBS No. Detector Element Design Team1.02 TPC C. Miraval (ID)1.03 EMCal D. Cacace (PH), R. Ruggiero (PH)1.04 Hcal R. Ruggiero (PH), R. Faussete (NSLS II)1.05 CalElect S. Polizzo (PH)1.06 DAQ/Trigger P. Hamblen (PH)1.07 Min-Bias Trigger Detector R. Ruggiero (PH)2.02 Magnet R. Meier (CAD), P. Kovach (SMD)2.03 Carriage - Structural Components J. Scheblien (PH), D. Puleo (CAD), A. DeSantis (NSLS II)2.04 Infrastructure P. Hamblen (PH), A. DeSantis (NSLS II)2.05 Installation and Integration R. Ruggiero (PH), R. Faussete (NSLS II) 3.01 INTT D. Cacace (PH), C. Miraval (ID)3.02 MVTX LANL/MIT Designers
ID - BNL Instrumentation Division SMD - BNL Superconducting Magnet Division
CAD - BNL Collider Accelerator Dept. MIT - Bates/MIT
PH - BNL Physics Department LANL - Los Alamos National Laboratory
NSLS II - BNL National Synchrotron Light Source II
Sheet1
WBS No.Detector ElementEngineering LeadInstitution-DeptSupport EngineeringWBS No.Detector ElementDesign Team
1.02TPCJ. CozzolinoBNL - SMDS. Bellavia (CAD), M. Anerella (SMD), J. Kuczewski (ID), C. Miraval (ID), R. Pisani (PH), D. Cacace (PH)S. Bellavia (CAD), M. Anerella (SMD), J. Kuczewski (ID), C. Miraval (ID), R. Pisani (PH)1.02TPCC. Miraval (ID)
1.03EMCalS. StollBNL - PHD. Cacace (PH), R. Pisani (PH)D. Cacace (PH), R. Pisani1.03EMCalD. Cacace (PH), R. Ruggiero (PH)
1.04HcalR. Feder BNL - PHR. Ruggiero, R. Pisani (PH), C. Pontieri (PH), J. Mills (CAD), D. Cacace (PH)R. Pisani1.04HcalR. Ruggiero (PH), R. Faussete (NSLS II)
1.05CalElectS. BooseBNL - PHE. Mannel (PH), S. Polizzo (PH) 1.05CalElectS. Polizzo (PH)
1.06DAQ/TriggerE. Desmond (Ret.)BNL - PHJ. Kuczewski (ID)1.06DAQ/TriggerP. Hamblen (PH)
1.07Min-Bias Trigger DetectorChiColumbia U.R. Ruggiero (PH)N/A1.07Min-Bias Trigger DetectorR. Ruggiero (PH)
2.02MagnetM. AnerellaBNL - SMDR. Than (CAD), C. Schultheiss (CAD), P. Orfin (CAD), P. Rosas (CAD), T. Tallerico (CAD), D. Phillips (CAD)R. Than (CAD), C. Schultheiss (CAD), P. Orfin (CAD), P. Rosas (CAD), T. Tallerico (CAD), D. Phillips (CAD)2.02MagnetR. Meier (CAD), P. Kovach (SMD)
2.03Carriage - Structural ComponentsC. PontieriBNL - PHJ. Hock (CAD), J. Mills (CAD)J. Hock (CAD), J. Mills (CAD)2.03Carriage - Structural ComponentsJ. Scheblien (PH), D. Puleo (CAD), A. DeSantis (NSLS II)
2.04InfrastructureR. Pisani (Interim)BNL - PHB. Streckenbach (CAD), M. Mapes (CAD), J. Vasquez (PH)B. Streckenbach (CAD), M. Mapes (CAD), R. Pisani (PH)2.04InfrastructureP. Hamblen (PH), A. DeSantis (NSLS II)
2.05Installation and IntegrationR. FederBNL - PHC. Pontieri (PH), D. Phillips (CAD), R. Ruggiero (PH), B. Streckenbach (CAD)D. Phillips (CAD), R. Ruggiero (PH)2.05Installation and IntegrationR. Ruggiero (PH), R. Faussete (NSLS II)
3.01INTTD. CacaceBNL- PHC. Miraval (ID)3.01INTTD. Cacace (PH), C. Miraval (ID)
3.02MVTXW. SondheimLANLJason Bessuille (MIT), James Kelsey (MIT), Joseph Dodge (MIT)3.02MVTXLANL/MIT Designers
ID - BNL Instrumentation DivisionSMD - BNL Superconducting Magnet Division
Safety EngineeringL. Stiegler/A. FranzBNL - PHB. Streckenbach (CAD) B. Streckenbach (CAD)CAD - BNL Collider Accelerator Dept.MIT - Bates/MIT
Q/AC. GortakowskiBNL - PP&QMD. Passarello (CAD)D. Passarello (CAD)PH - BNL Physics DepartmentLANL - Los Alamos National Laboratory
NSLS II - BNL National Synchrotron Light Source II
BNL-IDInstrumentation DivisionMITBates - Massachusetts Institute of Technology
BNL-CADCollider Accelerator Dept.LANLLos Alamos National Laboratory
BNL-PP&QMPlanning, Performance and Quality Mngt.BNL-SMDSuperconducting Magnet Division
BNL-PHPhysics Department
Engineering Controls
October 16-17, 2019 6Director's Cost, Schedule and Status Review
• Engineering –– Follows sPHENIX Procedures, CAD Procedures, BNL SBMS Engineering Design Standards, Applicable Industry
Codes and Standards
• Documentation –– Drawing Numbering Plan and Revision Control is documented in procedure. – Archiving of all Engineering Documents to be at sPHENIX Project office.– Final approval to be from the sPHENIX Project Office and L2 Managers.– Design changes will follow change control procedures, requiring approvals as appropriate and as designated
by project office.– Autodesk Vault to be used for sPHENIX released drawing and document revision control.
• Reviews –– Suite of Engineering Design and Production Readiness Reviews
• Fabrication –– Fabrication will follow BNL-Planning, Performance, and Quality Management Guidelines and Procedures.
Fabrication Documents at non-BNL facilities will be reviewed and approved by sPHENIX PM, Safety, and Q/A.
Engineering Meetings and Progress Review
October 16-17, 2019 7Director's Cost, Schedule and Status Review
• Regularly scheduled Subsystem-specific Engineering Working and Status Meetings – attended by subsystem lead engineer (designer and support engineers), sPHENIX Project Scientist, Chief
Engineer, Project Engineer, and L2/L3 scientists when appropriate.
• Bi-weekly sPHENIX Project Engineering Meeting – all engineers meet to review progress, problems and to discuss technical issues. General interface issues are
discussed with follow-up meetings scheduled. Chaired by sPHENIX Project Engineer and attended by Project Scientist and Chief Engineer.
• Weekly Construction Coordination and Safety Meeting – technical staff and project management meet to review ongoing scheduled work and planned future work.
Safety related issues and schedule discussed. Chaired by C. Pontieri, sPHENIX L2 Installation and Integration staff, attended by sPHENIX Project Director, PE, CE, Safety, Q/A, CAD Liaison Engineer, Liaison Scientist and CAD Safety, and often attended by BHSO.
• Standing Integration Meeting – Office of Systems Integration– Chaired by sPHENIX Chief Engineer Meetings are usually documented via INDICO and conducted using
BlueJeans video conferencing. INDICO documents are accessible for reference to all sPHENIX staff.
Technical Reviews
October 16-17, 2019 8Director's Cost, Schedule and Status Review
TYPES OF REVIEWS
• sPHENIX Conceptual Design, Preliminary Engineering and Design, Final Design Review, Interim Engineering Design Review
• sPHENIX Procurement/Production Readiness Review
• sPHENIX System Readiness and Safety Reviews to be conducted for all subsystems prior to the start of Subsystem Commissioning, Full Detector Operational Readiness Review
• Other BNL reviews - Laboratory Environment, Safety & Health Committee Review (LESHC), Experimental Safety Review (ESR), Lifting Safety (Critical Lifts), Pressure Vessel and Cryogenic Safety
All Reviews are part of the sPHENIX P6 Workflow
All engineering reviews are attended by sPHENIX Safety and Q/A
2.X Engineering Reviews 2015-2019
October 16-17, 2019 Director's Cost, Schedule and Status Review 9
• 28 Reviews Performed• Reviews are in sPHENIX Resource Loaded Schedule
DOE and Director's ReviewsOct. 2019 - 1008 Infrastructure and Facility Upgrade Cost, Schedule and Status ReviewApr. 2019 - Director's ReviewMar. 2018 - Director's Review PracticeFeb. 2018 - sPHENIX Cost and Schedule ReviewAug. 2017 - sPHENIX Director's ReviewJun. 2016 - sPHENIX Document Review and Drill DownNov. 2015 - Associate Laboratory Director’s Cost and Schedule Status Review of the sPHENIX Project
2.2 Magnet Cryogenics, Power Supply, Quench DetectionsPHENIX CRYOGENIC SYSTEM Procurement Readiness ReviewLESCH18-10 Review of the Cryogenic Systems for Sphenix SC Solenoid IP8sPHENIX Magnet Final Design ReviewsPHENIX Magnet ReviewMagnet Preliminary Design Review and Pressure Safety ReviewFinal Review Controls, PS, DR, Quench DetectionESRC/ASSRC Review High Current Cold Test - Power Supply and Qunch DetectorSafety Walk-Down High Field TestPreliminary Review Controls, PS, DR, Quench Detection
2.3.1, 2.3.4, 2.3.5 Cradle/CarriageCradle/Carriage Final Design ReviewsPHENIX Cradle/Carriage Preliminary Engineering ReviewCradle Carriage Cost ReviewCradle/Carriage Conceptual Design Review
2.3.3 OHCal SteelsPHENIX Outer HCAL Mechanics Final Design ReviewsPHENIX Outer HCal Sector Steel Review Follow Up ReviewsPHENIX Outer HCal Steel Sector Procurement Readiness/Final Design Review
HCAL System PDR and Final Design Requirements and Specifications Review (FDRASR)
HCAL Pre-CD-1 Conceptual Design Review2015 sPHENIX Hcal System Review
2.4, 2.5 Infrastructure and InstallationInfrastructure, Installation and Integration Pre-CD-1 Conceptual Design ReviewJan. 2015 sPHENIX Decommissoning and Installation Review
Sheet1
sPHENIX 2.x Reviews 2015-2019
DOE and Director's Reviews
Oct. 2019 - 1008 Infrastructure and Facility Upgrade Cost, Schedule and Status Review
Apr. 2019 - Director's Review
Mar. 2018 - Director's Review Practice
Feb. 2018 - sPHENIX Cost and Schedule Review
Aug. 2017 - sPHENIX Director's Review
Jun. 2016 - sPHENIX Document Review and Drill Down
Nov. 2015 - Associate Laboratory Director’s Cost and Schedule Status Review of the sPHENIX Project
2.2 Magnet Cryogenics, Power Supply, Quench Detection
sPHENIX CRYOGENIC SYSTEM Procurement Readiness Review
LESCH18-10 Review of the Cryogenic Systems for Sphenix SC Solenoid IP8
sPHENIX Magnet Final Design Review
sPHENIX Magnet Review
Magnet Preliminary Design Review and Pressure Safety Review
Final Review Controls, PS, DR, Quench Detection
ESRC/ASSRC Review High Current Cold Test - Power Supply and Qunch Detector
Safety Walk-Down High Field Test
Preliminary Review Controls, PS, DR, Quench Detection
2.3.1, 2.3.4, 2.3.5 Cradle/Carriage
Cradle/Carriage Final Design Review
sPHENIX Cradle/Carriage Preliminary Engineering Review
Cradle Carriage Cost Review
Cradle/Carriage Conceptual Design Review
2.3.3 OHCal Steel
sPHENIX Outer HCAL Mechanics Final Design Review
sPHENIX Outer HCal Sector Steel Review Follow Up Review
sPHENIX Outer HCal Steel Sector Procurement Readiness/Final Design Review
HCAL System PDR and Final Design Requirements and Specifications Review (FDRASR)
HCAL Pre-CD-1 Conceptual Design Review
2015 sPHENIX Hcal System Review
2.4, 2.5 Infrastructure and Installation
Infrastructure, Installation and Integration Pre-CD-1 Conceptual Design Review
Jan. 2015sPHENIX Decommissoning and Installation Review
Sheet1
sPHENIX 2.x Reviews 2015-2019
DOE and Director's Reviews
Oct. 2019 - 1008 Infrastructure and Facility Upgrade Cost, Schedule and Status Review
Apr. 2019 - Director's Review
Mar. 2018 - Director's Review Practice
Feb. 2018 - sPHENIX Cost and Schedule Review
Aug. 2017 - sPHENIX Director's Review
Jun. 2016 - sPHENIX Document Review and Drill Down
Nov. 2015 - Associate Laboratory Director’s Cost and Schedule Status Review of the sPHENIX Project
2.2 Magnet Cryogenics, Power Supply, Quench Detection
sPHENIX CRYOGENIC SYSTEM Procurement Readiness Review
LESCH18-10 Review of the Cryogenic Systems for Sphenix SC Solenoid IP8
sPHENIX Magnet Final Design Review
sPHENIX Magnet Review
Magnet Preliminary Design Review and Pressure Safety Review
Final Review Controls, PS, DR, Quench Detection
ESRC/ASSRC Review High Current Cold Test - Power Supply and Qunch Detector
Safety Walk-Down High Field Test
Preliminary Review Controls, PS, DR, Quench Detection
2.3.1, 2.3.4, 2.3.5 Cradle/Carriage
Cradle/Carriage Final Design Review
sPHENIX Cradle/Carriage Preliminary Engineering Review
Cradle Carriage Cost Review
Cradle/Carriage Conceptual Design Review
2.3.3 OHCal Steel
sPHENIX Outer HCAL Mechanics Final Design Review
sPHENIX Outer HCal Sector Steel Review Follow Up Review
sPHENIX Outer HCal Steel Sector Procurement Readiness/Final Design Review
HCAL System PDR and Final Design Requirements and Specifications Review (FDRASR)
HCAL Pre-CD-1 Conceptual Design Review
2015 sPHENIX Hcal System Review
2.4, 2.5 Infrastructure and Installation
Infrastructure, Installation and Integration Pre-CD-1 Conceptual Design Review
Jan. 2015 sPHENIX Decommissoning and Installation Review
sPHENIX Project Controls and Work Management Documents
October 16-17, 2019 10Director's Cost, Schedule and Status Review
1. sPHENIX Procedure Guidelines2. sPHENIX Configuration Management3. sPHENIX Document Control4. sPHENIX Quality Assurance Plan5. sPHENIX Conduct of Design Reviews6. sPHENIX Work Planning7. sPHENIX Awareness Training8. sPHENIX Bottom’s-Up Estimate Uncertainty Guidelines9. Interface Control Document/Interface Design Drawing 10. Integrated Safety Management Plan/Safety Hazard Analysis Document/CAD
Conduct of Operations11. Comment Resolution Database
• sPHENIX Procedures and Documents for Engineering, Design, Fabrication, and Installation
• Signed and released for use
Engineering Procedures
October 16-17, 2019 11Director's Cost, Schedule and Status Review
Typical sPHENIX Procedure - sPHENIX Q/A Plan, Conduct of Design Reviews, Configuration Management
Engineering Management and Coordination
October 16-17, 2019 12Director's Cost, Schedule and Status Review
Brookhaven National Laboratory SBMSThe Standards-Based Management System (SBMS) provides Laboratory-wide
procedures and guidelines for performing work safely and in compliance
with requirements. All work at the Laboratory must comply with the
minimum requirements specified in SBMS documents, including
management system descriptions, subject areas, interim procedures, BNL
manuals, and program descriptions.
sPHENIX Engineering Project Controls and Work Management Documents will meet all SBMS requirements but will be tailored to address complex multiple institutional and departmental collaborations.
Subject Areas• Engineering Standard• Design Standard• Configuration Control• Quality
Work Planning (SBMS)
October 16-17, 2019 13Director's Cost, Schedule and Status Review
Subject Area: Work Planning and Control for Experiments and Operations
Introduction
This subject area uses the Integrated Safety Management core functions and guiding principles to establish a process for ensuring all work, operational and experimental, is properly planned and implemented to prevent accidents, injuries, and regulatory violations. It establishes requirements at Brookhaven National Laboratory (BNL) so that all work is properly managed by using a level of planning and control commensurate to the Environment, Safety, Security, and Health (ESSH) hazards, job complexities, and work coordination needs.Line management is directly responsible for the protection of the public, the workers, and the environment.
1.01 Project Management
1.02TPC
1.03EMCal
1.04HCal
1.05Calorimeter Electronics
1.06DAQ/
Trigger1.07 Min Bias
2.02 SC Magnet
2.03 & 2.04 Infrastructure
2.05 Integration &
Installation3.01 INTT 3.02 MVTX
N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A1.01 Project
Management
sP.SE-ICD-031 N/A N/A N/A sP.SE-ICD-004 N/A N/A sP.SE-ICD-009 sP.SE-ICD-016 N/A N/A1.02TPC
sP.SE-ICD-032 P.SE-ICD-00 sP.SE-ICD-002 sP.SE-ICD-005 N/A N/A sP.SE-ICD-010 sP.SE-ICD-017 N/A N/A1.03
EMCal
sP.SE-ICD-03 sP.SE-ICD-003 sP.SE-ICD-006 N/A N/A sP.SE-ICD-011 sP.SE-ICD-018 N/A N/A1.04HCal
sP.SE-ICD-034 sP.SE-ICD-007 N/A N/A sP.SE-ICD-012 sP.SE-ICD-019 N/A N/A1.05
Calorimeter Electronics
sP.SE-ICD-035 sP.SE-ICD-008 N/A sP.SE-ICD-013 sP.SE-ICD-020 sP.SE-ICD-024 sP.SE-ICD-0271.06
DAQ/Trigger
sP.SE-ICD-036 N/A sP.SE-ICD-014 sP.SE-ICD-021 N/A N/A 1.07 Min Bias
sP.SE-ICD-037 sP.SE-ICD-015 sP.SE-ICD-022 N/A N/A2.02 SC Magnet
sP.SE-ICD-038 sP.SE-ICD-023 sP.SE-ICD-025 sP.SE-ICD-016282.03 & 2.04
Infrastructure
sP.SE-ICD-039 sP.SE-ICD-026 sP.SE-ICD-0292.05
Integration & Installation
sP.SE-ICD-040 sP.SE-ICD-030 3.01 INTT
sP.SE-ICD-041 3.02 MVTXWBS1.11.21.31.41.51.61.7
WBS2.12.2
2.3 & 2.42.5
WBS3.13.2
sPHENIX MIE Project ElementsProject Management
Time Projection ChamberElectromagnetic Calorimeter
Hadron CalorimeterCalorimeter Electronics
DAQ-TriggerMinimum Bias Trigger Detector
Infrastructure and Facility Upgrade ProjectProject Management
Superconducting Solenoid Magnet SystemInfrastructure and StructuresInstallation and Integration
Non-MIE Subsystems (funded from other sources)Intermediate Silicon Strip Tracker (INTT)
MVTX Maps Silicon Detector
Interface Control Document (ICD)
October 16-17, 2019 14Director's Cost, Schedule and Status Review
sPHENIX ICD MatrixICD Links 2 and only 2
Subsystems
Documents which subsystems require a formal technical Interface to another subsystem. Total of 30 required for sPHENIX.
Interface Control Document (ICD)
October 16-17, 2019 15Director's Cost, Schedule and Status Review
• Formal Handshake Between Subsystems• Describes Interface• Provides Technical Details of Interface• Specifies Deliverables between Subsystems and how to
measure success• Administered by the Office of Systems Integration
TBDContributors:
ABCDEFG
sPHENIX EMCal Engineer Dan Cacace For EMCal subsystemsPHENIX HCal Engineer Chris Pontieri For HCal subsystem
sPHENIX Chief Engineer Don Lynch 5/30/2018, for sPHENIX Engineering ManagementsPHENIX OSI Chairman Mickey Chiu For OSI, waiting approval
Approvals
Title Name Approval Date/Notes
sPHENIX Chief Engineer Don Lynch 10/12/17; 1st Draft
8. Power, Control and Signal Interface9. Thermal & Fluid Interface10. Subsystem Deliverables11. Compliance Demonstration12. Subsystem Interface Cross Reference
6. Interface Description7. Mechanical Interface7.1. General Description7.2 Hardware Description & Mounting7.3 Dimensional Specifications, Alignment Requirements and Tolerances
1. Change History Log (see above)2. Contents (this section)3. Acronyms & Abbreviations4. Reference Documents5. Purpose and Scope
1. Change History Log
Revision Effective Date: Description of Changes
2. Contents
Initial Issue
sPHENIX
Interface Control Document
Document Title:
Interface Control Document for sPHENIX EMCal and HCal (WBS 1.03 and 1.04 , respectively)
Document#
sP.SE-ICD-001
Date Effective:
Initial Issue (waiting for approvals)
Status:
J. LaJoie, C. Woody, A. Gordeev, D. Cacace, S. Stoll
Interface Control Design Drawing (ICDD)
October 16-17, 2019 16Director's Cost, Schedule and Status Review
• Dimensional Handshake Between Subsystems• Identifies Clearances and Stay Clear Zones• Released and Available to L2 Managers• Under Revision Control
Issues and Concerns
October 16-17, 2019 Director's Cost, Schedule and Status Review 17
Issues and Concerns Proposed Resolution Plan Status
Memorandum of Agreement for engineering support between sPHENIX and Collider Accelerator Department for Infrastructure needs to be finalized (4 of 5 MOAs Completed and Approved)
MOA with Requirements Document has been drafted and is now being edited for sign-off within the next 6 weeks
Signed by CAD/sPHENIX
Would like an additional designer for detailing.
Continuing to address needs and work with CAD Chief Engineer in order to supplement as needed.
Hired Job Shop Designer (F/T) and two NSLSII Designers (1 FTE)
Some engineers are shared across projects -concerned about competing priorities
Closely monitor engineering and design support and if required work with supporting department in order to establish clear priorities for staff.
MOA’s are completed, continuing to monitor and address any potential competing priorities
Summary
October 16-17, 2019 18Director's Cost, Schedule and Status Review
• Engineering Organization Stable, Experienced, and Effective
• Procedures and Configuration Control Rolled Out and Being Followed
• Reoccurring Meetings Provides Appropriate sPHENIX Oversight and Important Conduit for Communications.
Engineering Management and Coordination
October 16-17, 2019 19Director's Cost, Schedule and Status Review
Back Up
Design Software
October 16-17, 2019 20Director's Cost, Schedule and Status Review
CAD/3D modelling software to be used by engineers and designer consistent with their respective departmental requirements. Final Released Drawings to be delivered to sPHENIX project office as PDF’s with the corresponding 3D model and electronics simulation files to be supplied in industry standard format (i.e. STEP). Engineering Drawings, Specifications, and Statement of Work shall be reviewed and approved by sPHENIX Project Office, Quality, and Safety.
Department/InstitutionMechanical Computer Aided
Design Finite Element Analysis Electronics Electrical One-Lines* Gas Systems* Safety Systems*
Collider Accelerator Department PTC Creo, Autodesk InventorANSYS, ABAQUS, Mechanica N/A Autodesk AutoCAD Autodesk AutoCAD Autodesk AutoCAD
Superconducting Magnet Division PTC Creo ANSYS N/A N/A N/A N/APHYSICS Department Autodesk Inventor, Autocad ANSYS ORCAD/PADS N/A Autodesk AutoCAD Autodesk AutoCADInstrumentation Division N/A N/A ORCAD/PADS N/A N/A N/AColumbia University N/A N/A ORCAD/PADS N/A N/A N/ALos Alamos National Lab Solidworks ANSYSMIT-Bates Solidworks ANSYSNSLS II Autodesk Inventor, Autocad
* Final Documentation to be approved and reside at Collider Accelerator Department
Sheet1
Department/InstitutionMechanical Computer Aided DesignFinite Element AnalysisElectronicsElectrical One-Lines*Gas Systems*Safety Systems*
Collider Accelerator DepartmentPTC Creo, Autodesk InventorANSYS, ABAQUS, MechanicaN/AAutodesk AutoCADAutodesk AutoCADAutodesk AutoCAD
Superconducting Magnet DivisionPTC CreoANSYSN/AN/AN/AN/A
PHYSICS DepartmentAutodesk Inventor, AutocadANSYSORCAD/PADSN/AAutodesk AutoCADAutodesk AutoCAD
Instrumentation DivisionN/AN/AORCAD/PADSN/AN/AN/A
Columbia UniversityN/AN/AORCAD/PADSN/AN/AN/A
Los Alamos National LabSolidworksANSYS
MIT-BatesSolidworksANSYS
NSLS IIAutodesk Inventor, Autocad
* Final Documentation to be approved and reside at Collider Accelerator Department
Sheet2
Sheet3
�Director’s Cost, Schedule and Status Review of the�sPHENIX Infrastructure and Facility Upgrade��Engineering Management and Coordination ��Engineering Management and CoordinationEngineering ManagementsPHENIX Engineering StaffEngineering Design StaffEngineering ControlsEngineering Meetings and Progress ReviewTechnical Reviews2.X Engineering Reviews 2015-2019sPHENIX Project Controls and Work Management DocumentsEngineering ProceduresEngineering Management and CoordinationWork Planning (SBMS)Interface Control Document (ICD)Interface Control Document (ICD)Interface Control Design Drawing (ICDD)Issues and Concerns SummaryEngineering Management and CoordinationDesign Software