© 2015 – Hervé Baron HERVE BARON Engineering Training Welcome to this presentation. It is part of a suite of Engineering training modules. It shows the activities and deliverables of the Instrumentation & Control discipline. Comments are most welcome ([email protected]), which I will incorporate for the benefit of all. Please download this file so that you can see my trainer’s notes in the top left corner – latest Acrobat Pro feature. Hervé
76

eng-150324152625-conversion-gate01

Sep 13, 2015

Download

Documents

Markose

Engineering conversion
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 2015 Herv Baron

    HERVE BARON

    Engineering Training

    Welcome to this presentation.

    It is part of a suite of Engineering training modules.

    It shows the activities and deliverables of the Instrumentation & Control discipline.

    Comments are most welcome ([email protected]), which I will incorporate for the benefit of all.

    Please download this file so that you can see my trainers notes in the top left corner latest Acrobat Pro feature.

    Herv

  • 2015 Herv Baron

    HERVE BARON

    Engineering Training

    PROCESS

    PLANT LAYOUT

    EQUIPMENT

    SAFETY & ENVIRONMENT

    CIVIL

    PIPING

    PIPELINE

    INSTRUMENTATION

    ELECTRICAL

  • 2015 Herv Baron

    HERVE BARON

    Process design

    PFDs

    H&M balance

    Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.

    P&IDs

    Piping

    Instrumentation

    Layout

    Civil

    Electrical

    Process data sheet

    Equipment specification

    Vendor drawings

    We are here

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    PROCESS

    PLANT LAYOUT

    EQUIPMENT

    SAFETY & ENVIRONMENT

    CIVIL

    PIPING

    PIPELINE

    INSTRUMENTATION

    The discipline is commonly split in 3 specialties. Which ones?

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    PROCESS

    PLANT LAYOUT

    EQUIPMENT

    SAFETY & ENVIRONMENT

    CIVIL

    PLANT LAYOUT & PIPING

    PIPELINE

    INSTRUMENTATION Field instrumentation Systems Installation

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    PROCESS

    PLANT LAYOUT

    EQUIPMENT

    SAFETY & ENVIRONMENT

    CIVIL

    PIPING

    PIPELINE

    INSTRUMENTATION Field instrumentation Systems Installation

  • 2015 Herv Baron

    HERVE BARON

    Piping & Instrumentation Diagram (P&ID)

  • 2015 Herv Baron

    HERVE BARON

    Piping & Instrumentation Diagram (P&ID)

  • 2015 Herv Baron

    HERVE BARON

    Instrument list

  • 2015 Herv Baron

    HERVE BARON

    Instrument data sheet

  • 2015 Herv Baron

    HERVE BARON

    Level sketch

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    PROCESS

    PLANT LAYOUT

    EQUIPMENT

    SAFETY & ENVIRONMENT

    CIVIL

    PLANT LAYOUT & PIPING

    PIPELINE

    INSTRUMENTATION Field instrumentation Systems Installation

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    INSTRUMENTATION Field instrumentation Systems:

    Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems

    Installation

  • 2015 Herv Baron

    HERVE BARON

    PCS (Process Control System)

  • 2015 Herv Baron

    HERVE BARON

    System requisition

  • 2015 Herv Baron

    HERVE BARON

    System architecture drawing

  • 2015 Herv Baron

    HERVE BARON

    Control narrative Gas inlet

    Gas outlet

    93-E161

  • 2015 Herv Baron

    HERVE BARON

    Functional diagram

  • 2015 Herv Baron

    HERVE BARON

    Mimic display drawings

  • 2015 Herv Baron

    HERVE BARON

    Process automations & Process Shut Down (PSD)

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    INSTRUMENTATION Field instrumentation Systems:

    Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems

    Installation

  • 2015 Herv Baron

    HERVE BARON

    Package instrumentation & control

    PresenterPresentation NotesRight side (P2): cables from instruments to JB and JB included in Vendor scope of supply.

  • 2015 Herv Baron

    HERVE BARON

    Package instrumentation & control

    PresenterPresentation NotesRight side (P3): Package control system included.In both cases: Cables 2 supplied and installed by Vendor. Cables 3 supplied and installed by Purchaser.Cables 4 are special cables (encoder etc.) supplied by Vendor.Some brands of PLC may be specified in the Instrumentation Requirements for Packaged Units

  • 2015 Herv Baron

    HERVE BARON

    Package control

    Package controlled by Central Process Control System

  • 2015 Herv Baron

    HERVE BARON

    Package control

    Package controlled by Central Process Control System

  • 2015 Herv Baron

    HERVE BARON

    Package control

    Package controlled by own Unit Control System

    PresenterPresentation NotesVendor supplies its own system when proper control/shutdown function is linked to warranty.It is always the case for gas turbine/compressors.For boilers, the code (NFPA 85) requires independent burner management system (item 4.1.7.1 The burner management system shall be provided with independent logic, independent logic solving harware, independent input/output systems, and independent power supplies and shall be a device functionally and physically separate from other logic systems). The burner management safety functions (item 4.11.7.3) shall include purge interlocks and timing, safety shutdowns, trial timing for ignition and flame monitoring.

  • 2015 Herv Baron

    HERVE BARON

    Package control

    What documents from the package Vendor are needed by the DCS Vendor in this case?

    Package controlled by own Unit Control System

    PresenterPresentation NotesExchange table

  • 2015 Herv Baron

    HERVE BARON

    Package control

    Package controlled by Central Process Control System

    What documents from the package Vendor are needed by the DCS Vendor in this case?

    PresenterPresentation NotesP&IDs, narrative, C&E, logic diagrams

  • 2015 Herv Baron

    HERVE BARON

    Process Control System

    Process Control System Engineering by Vendor

    Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer.

  • 2015 Herv Baron

    HERVE BARON

    Process Control System

    Process Control System Engineering by Vendor

    Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer. Which documents are needed by the Vendor?

  • 2015 Herv Baron

    HERVE BARON

    Process Control System

    Process Control System Engineering by Vendor

    Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer. Which documents are needed by the Vendor?

    Engineering documents

    Vendor documents

  • 2015 Herv Baron

    HERVE BARON

    Process Control System

    Process Control System Engineering by Vendor

    Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer. Which documents are needed by the Vendor?

    Vendor documents

    P&IDs

    Control Narratives

    Cause & Effects

  • 2015 Herv Baron

    HERVE BARON

    Process Control System

    Process Control System Engineering by Vendor

    Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer.

    P&IDs

    Control Narratives

    Cause & Effects

    Packages with Unit Control System:

    Exchange table with PCS

    P&IDs

    Control Narratives

    Cause & Effects

    Control & logic diagrams

    Packages controlled by Central Control System:

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    INSTRUMENTATION Field instrumentation Systems:

    Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems

    Installation

  • 2015 Herv Baron

    HERVE BARON

    Emergency Shutdown (ESD) System

    PresenterPresentation NotesThe ESD System is also called the Instrumented Protection System (IPS). It implements all the Safety Instrumented Functions shown on the P&IDs. The IPS architecture is usually 2oo3Triple Modular Redundant. For all critical interlocks, 3 field devices shall be provided with 2 out of 3 (TMR) voting.

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD)

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD) SIL study

    Have you heard about SIL studies? What does it mean?

    What does SIL, SIF and SIS mean?

    Terms defined in ANSI/ISA-84.00.01-2004 (IEC 61511-1) Functional Safety: Safety Instrumented Systems for the Process Industry Sector

    SIF: Safety Instrumented Function

    SIS: Safety Instrumented System: Sensor + logic solver + final element

    SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD) SIL study

    Have you heard about SIL studies? What does it mean?

    What does SIL, SIF and SIS mean?

    Terms defined in ANSI/ISA-84.00.01-2004 (IEC 61511-1) Functional Safety: Safety Instrumented Systems for the Process Industry Sector

    SIF: Safety Instrumented Function

    SIS: Safety Instrumented System: Sensor + logic solver + final element

    SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD) SIL study

    Have you heard about SIL studies? What does it mean?

    What does SIL, SIF and SIS mean?

    ANSI/ISA-84.00.01-2004 (IEC 61511-1)

    Functional Safety: Safety Instrumented Systems for the Process Industry Sector

    SIF: Safety Instrumented Function

    SIS: Safety Instrumented System: Sensor + logic solver + final element

    SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD) SIL study

    Have you heard about SIL studies? What does it mean?

    What does SIL, SIF and SIS mean?

    ANSI/ISA-84.00.01-2004 (IEC 61511-1)

    Functional Safety: Safety Instrumented Systems for the Process Industry Sector

    SIF: Safety Instrumented Function

    SIS: Safety Instrumented System: Sensor + logic solver + final element

    SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD) SIL study

    Step 1: SIL Determination, assignment workshop

    Identification of Instrumented Interlocks on the P&IDs = inventory of Safety Instrumented Function (SIF)

    For each SIF: Qualitative evaluation of consequences if the event the SIF is

    designed to safeguard from Qualitative evaluation of the likelihood of the event Determination of risk level (likelihood * consequence) and

    resulting SIF required performance (SIL level)

    Deliverable: SIL assignment logsheet / worksheets

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD)

  • 2015 Herv Baron

    HERVE BARON

    Emergency shutdown (ESD) SIL study

    LIKELIHOOD CATEGORY DEFINITION POTENTIAL FREQUENCY

    A Possibility of repeated incidents 20 or more times per Facility life B Possibility of isolated incidents 5 times per Facility life C Possibility of occurring sometime Once in Facility life D Not likely to occur Once every 10 Facility lives E Practically impossible Once every 100 Facility lives

    CONSIDERATIONS CONSEQUENCE CATEGORY Health/Safety Public Disruption Environmental Impact Financial Impact

    Abbreviation S Safety P Public E Environmental F Financial

    I Fatalities/ Serious Impact on Public Large

    Community (10,000+)

    Major/Extended Duration/ Full Scale

    Response

    Major Impact to Company

    (>$50 million)

    II Serious Injury to

    Personnel/ Limited Impact on Public

    Small Community (1,000 to 10,000)

    Serious/Significant Resource

    Commitment

    Significant Impact To Company ($2 - $50 million)

    III Medical Treatment for Personnel/ No Impact

    on Public

    Minor (10 to 100)

    Moderate/Limited Response of Short

    Duration

    Moderate Impact To Company

    ($500M - $2 million)

    IV Minor Impact on Personnel Minimal to

    None (1 or 2)

    Minor/Little or No Response Needed

    Minor Impact To Company

    ($50M-$500M)

  • 2015 Herv Baron

    HERVE BARON

    SIL Study

    Step 1: SIL Determination, assignment workshop

    Deliverable: SIL assignment logsheet / worksheets

    Summary:

    What is the second step of the SIL?

  • 2015 Herv Baron

    HERVE BARON

    SIL Study

    Step 2: calculations and recommendation

    SIS Performance Verification

    Evaluate the performance of each SIF, based on device selection, architecture, voting, testing etc.

    Compare to required SIL level and specify modifications to the SIF design (device selection, component redundancy) or testing intervals

    Deliverable: SIS Performance Verification Results and recommendations

    PresenterPresentation NotesSometimes done by 3rd party for independence

  • 2015 Herv Baron

    HERVE BARON

    SIL Study Step 2 SIS Performance verification Results

    PresenterPresentation NotesSometimes done by 3rd party for independence

  • 2015 Herv Baron

    HERVE BARON

    SIL Study

    Step 2: calculations and recommendation - Summary

    PresenterPresentation NotesSometimes done by 3rd party for independence

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    INSTRUMENTATION Field instrumentation Systems:

    Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems

    Installation

  • 2015 Herv Baron

    HERVE BARON

    Fire & Gas system

  • 2015 Herv Baron

    HERVE BARON

    Fire & Gas system

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    INSTRUMENTATION Field instrumentation Systems:

    Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems

    Installation

  • 2015 Herv Baron

    HERVE BARON

    Systems

    The main systems are: the Process Control System (DCS), and Emergency Shutdown System (ESD),

    usually integrated: ICSS (Integrated Control and Safety System) the Fire & Gas system (F&G)?

    What other systems do we find?

    What does SIL, SIF and SIS mean?

    Terms defined in ANSI/ISA-84.00.01-2004 (IEC 61511-1) Functional Safety: Safety Instrumented Systems for the Process Industry Sector

    SIF: Safety Instrumented Function

    SIS: Safety Instrumented System: Sensor + logic solver + final element

    SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:

  • 2015 Herv Baron

    HERVE BARON

    Systems

    The main systems are: the Process Control System (DCS), and Emergency Shutdown System (ESD),

    usually integrated: ICSS (Integrated Control and Safety System) the Fire & Gas system (F&G)?

    What other systems do we find? Packaged equipment Control systems Machinery Monitoring System (MMS) for vibration & temperature monitoring Burner Management System (BMS) Compressor Anti-Surge System (CCC) Analyzers Data Acquisition system Fiscal Metering Systems afor Custody transfer and allocation Storage tank data acquisition (gauging) system Continuous Emissions Monitoring System (CEMS) Process Operator and Information System (POIS) / SCADA Advance Process Control (APC)

  • 2015 Herv Baron

    HERVE BARON

    Engineering disciplines: activities and deliverables

    PROCESS

    PLANT LAYOUT

    EQUIPMENT

    SAFETY & ENVIRONMENT

    CIVIL

    PIPING

    PIPELINE

    INSTRUMENTATION Field instrumentation Systems Installation

  • 2015 Herv Baron

    HERVE BARON

    Field Instrumentation

    PT JB

    Process line

    Field Marshalling

    cabinet System

    cabinet

    Equipment room Control room

    Operator

    station

    Secondary cable

    Multi cable

    PresenterPresentation NotesThe Marshalling cabinets contain terminal blocks and power supply unitsThe System cabinets contain main processors, I/O modules, communication modules and power supply units.The Instrument room is sometimes called Instrumentation Technical Room (ITR) or Satellite Instrument House (SIH).

  • 2015 Herv Baron

    HERVE BARON

    Main cable routings and Junction Box (JB) location drawing

  • 2015 Herv Baron

    HERVE BARON

    Instrument location & secondary cable routing drawings

  • 2015 Herv Baron

    HERVE BARON

    Telecommunication equipment layout drawing

  • 2015 Herv Baron

    HERVE BARON

    Typical installation drawings

  • 2015 Herv Baron

    HERVE BARON

    Junction box wiring

  • 2015 Herv Baron

    HERVE BARON

    Instrument location & secondary cable routing drawings Cable list

  • 2015 Herv Baron

    HERVE BARON

    Cable routing / section

  • 2015 Herv Baron

    HERVE BARON

    Instrumentation installation standards

  • 2015 Herv Baron

    HERVE BARON

    Instrument bulk material take-off

    ITEM QUANTITY DESIGNATION

    1 195 Gauge adapter x

    2 37 Block manifold 2 valves (Gas)

    3 23 Block manifold 5 valves (Gas)

    4 0 Ball valve 12mm

    5 300m Tubing 12mm OD x 1mm

    6 200 Reducer 12mm x

    7 50 Union tee 12 x 12 x 12mm

    8 50 Female connector 12mm x

    9 350 Male connector 12mm x

    10 9 Plug NPTF

    11 8 Plug NPTM

  • 2015 Herv Baron

    HERVE BARON

    Equipment layout drawings

  • 2015 Herv Baron

    HERVE BARON

    Instrument loop diagram

  • 2015 Herv Baron

    HERVE BARON

    Main schedule Milestone for Instrumentation

    The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

    - Software freeze, for the configuration of the DCS

    PT JB

    Process line

    Marshalling

    Cabinet System

    Cabinet

    Secondary cable

    Multi cable

    Operator

    station

  • 2015 Herv Baron

    HERVE BARON

    Main schedule Milestone for Instrumentation

    The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

    - Software freeze, for the configuration of the DCS

  • 2015 Herv Baron

    HERVE BARON

    Main schedule Milestone for Instrumentation

    The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

    - Software freeze, for the configuration of the DCS In your opinion, which Milestone is required to be reached first?

    PresenterPresentation NotesHardware freeze, for lead time of cabinets. Usually 3 month ahead of Software freeze.

  • 2015 Herv Baron

    HERVE BARON

    Main schedule Milestone for Instrumentation

    The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

    - Software freeze, for the configuration of the DCS In your opinion, which Milestone is required to be reached first? What are the Engineering documents required to reach each Milestone?

    PresenterPresentation NotesHardware freeze: Instrument index 100% complete. Number, type and location of instruments, including within packages for centrally controlled packages. Documents required: P&IDs, Plot Plan

    Software freeze: IFC P&IDs, C&E, narratives, control & logic diagrams

  • 2015 Herv Baron

    HERVE BARON

    Main schedule Milestone for Instrumentation

    The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,

    - Software freeze, for the configuration of the DCS In your opinion, which Milestone is required to be reached first? What are the Engineering documents required to reach each Milestone? What is challenging to meet the schedule?

    PresenterPresentation NotesAutomation Systems Supply: when several automation systems are integrated and control systems of machinery and packages engineered by Vendor are included, the consolidation of information to be transfered to the Integrated Control System Supplier is complex and requires a specific schedule to coordinate the achievement on time of HW & SW Freeze

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide 2nd edition

    Do you want to know more... Much more?

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide - 2nd edition

    Table of Contents

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide - 2nd edition

    Table of Contents

    This suite of training modules covered the discipline chapters of the book...

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide - 2nd edition

    Table of Contents

    The Guide contains much more:

    The overall picture, interfaces, methods & tools, etc.

  • 2015 Herv Baron

    HERVE BARON

    The Oil & Gas Engineering Guide 2nd edition

    Order direct from the publisher:

    http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html

    Engineering TrainingEngineering TrainingSlide Number 3Engineering disciplines: activities and deliverables Engineering disciplines: activities and deliverables Engineering disciplines: activities and deliverables Piping & Instrumentation Diagram (P&ID)Slide Number 8Instrument listSlide Number 10Level sketchEngineering disciplines: activities and deliverables Engineering disciplines: activities and deliverables Slide Number 14System requisitionSlide Number 16Control narrativeFunctional diagramMimic display drawingsProcess automations & Process Shut Down (PSD)Engineering disciplines: activities and deliverables Package instrumentation & controlPackage instrumentation & controlSlide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28Process Control SystemProcess Control SystemProcess Control SystemProcess Control SystemProcess Control SystemEngineering disciplines: activities and deliverables Slide Number 35Emergency shutdown (ESD)Emergency shutdown (ESD)SIL studyEmergency shutdown (ESD)SIL studyEmergency shutdown (ESD)SIL studyEmergency shutdown (ESD)SIL studyEmergency shutdown (ESD)SIL studyEmergency shutdown (ESD)Emergency shutdown (ESD)SIL studySIL StudySIL StudySIL StudyStep 2 SIS Performance verification ResultsSIL StudyEngineering disciplines: activities and deliverables Fire & Gas systemFire & Gas systemEngineering disciplines: activities and deliverables SystemsSystemsEngineering disciplines: activities and deliverables Field InstrumentationSlide Number 56Slide Number 57Slide Number 58Typical installation drawingsJunction box wiringSlide Number 61Slide Number 62Slide Number 63Instrument bulk material take-offEquipment layout drawingsInstrument loop diagramMain schedule Milestone for InstrumentationMain schedule Milestone for InstrumentationMain schedule Milestone for InstrumentationMain schedule Milestone for InstrumentationMain schedule Milestone for InstrumentationThe Oil & Gas Engineering Guide2nd editionThe Oil & Gas Engineering Guide - 2nd editionThe Oil & Gas Engineering Guide - 2nd editionThe Oil & Gas Engineering Guide - 2nd editionThe Oil & Gas Engineering Guide2nd edition