Top Banner
ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) STANDARD OPERATING PROCEDURE (SOP) DEPARTMENT OF ENERGY (DOE) OFFICE OF ENGINEERING AND CONSTRUCTION MANAGEMENT (OECM) NOVEMBER 2011
31

ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Mar 27, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB)

STANDARD OPERATING PROCEDURE (SOP)

DEPARTMENT OF ENERGY (DOE)

OFFICE OF ENGINEERING AND CONSTRUCTION

MANAGEMENT (OECM)

NOVEMBER 2011

Page 2: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board
Page 3: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

TABLE OF CONTENTS

1.0 INTRODUCTION………………………………………………………………………… 1

1.1 Background…………………………………………………………………………. 1

1.2 SOP Objectives…….……………………………………………………………... 1

1.3 Applicability………………………………………………………………………... 2

2.0 ESAAB PURPOSE…..……………………………………………………………………. 2

3.0 MEMBERSHIP AND RESPONSIBILITIES…………………………………………… 3

4.0 DETERMINING THE REQUIREMENT FOR AN ESAAB…………………………... 5

4.1 General 6

4.2 Critical Decisions and BCPs 6

5.0 ESAAB PROCEDURES 6

5.1 Scheduling ESAAB Meetings 6

5.2 ESAAB Preparation 6

5.3 Call for Special ESAAB Review 8

6.0 “PAPER” ESAAB 8

6.1 Procedures 8

7.0 ESAAB-EQUIVALENT MEETINGS 9

7.1 Procedures 9

LIST OF APPENDICES

APPENDIX A: LIST OF ACRONYMS A-1

APPENDIX B: ESAAB ACTIVITIES TIMELINE B-1

APPENDIX C: PRESENTATION OUTLINE FOR THE ESAAB MEETING C-1

APPENDIX D: ESAAB MEMBERS D-1

APPENDIX E: EXAMPLE OF THE DECISION MEMORANDUM E-1

APPENDIX F: EXAMPLE OF THE STAFF MEMORANDUM F-1

APPENDIX G: EXAMPLE OF THE ESAAB MEETING MINUTES G-1

Page 4: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board
Page 5: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

1

1.0 INTRODUCTION

This Standard Operating Procedure (SOP) discusses all elements of an Energy System

Acquisition Advisory Board (ESAAB) to include membership, member roles and

responsibilities, scheduling, procedures, and products. This SOP also assists those

responsible in preparation for ESAAB meetings, particularly the Office of Engineering

and Construction Management (OECM), Programs, and Project Teams.

1.1 BACKGROUND. Department of Energy Order 413.3 (DOE O 413.3B), hereafter

referred to as the Order, was updated on November 29, 2011, to enhance DOE program

and project management direction for the acquisition of capital assets with the goal of

delivering projects within the original performance baseline (PB), cost and schedule, and

fully capable of meeting mission performance, safeguards and security, and

environmental, safety, and health requirements unless impacted by a directed change.

ESAAB membership and responsibilities are spelled out in the Order. DOE O 413.3B

can be found at and downloaded from https://www.directives.doe.gov/directives.

1.2 SOP OBJECTIVES.

1.2.1 To establish consistent ESAAB processes and procedures to facilitate informed,

objective, and documented strategic and major system critical decisions and baseline

change proposals for all new missions.

1.2.2 To assist Programs and Project Teams in the scheduling and preparation for ESAAB

meetings.

1.3 APPLICABILITY.

1.3.1 This SOP should be used in the scheduling and preparing for a Senior Acquisition

Executive (SAE) ESAAB, facilitating the ESAAB decision-making process, and

determining when to consider using a streamlined ESAAB process.

1.3.2 Similar decision procedures may be applied to non-major system projects. These

procedures should be individually tailored by the designated AE to the size and

complexity of the project.

1.3.3 This SOP does NOT impose new requirements or constitute Department policy. Nor is

this SOP intended to modify the ESAAB process delineated in DOE Orders or policy

memorandums.

2.0 ESAAB PURPOSE

The purpose of the ESAAB is to assist the SAE in the decision-making process on critical

decision milestones, baseline change proposals, and site selections for major system

acquisitions and major projects. Furthermore, the ESAAB provides a formal,

Page 6: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

2

documented, and auditable management process for making decisions that affect major

system acquisitions and major projects.

3.0 ESAAB MEMBERSHIP AND RESPONSIBILITIES

ESAAB membership and responsibilities are delineated in DOE O 413.3B. A current list

(office symbol, name, phone #) of ESAAB, “As-Needed” ESAAB, and Pre-ESAAB

members is available at http://energy.gov/management/office-management/operational-

management/project-management/documents-and-publications.

4.0 ESAAB FUNCTION

4.1 General. An ESAAB assists the SAE in approving critical decisions related to Major

System Projects and performance baseline deviation dispositions. A critical decision

(CD) is a formal determination made by the SAE or AE at a specific point during the

project that allows the project to proceed to the next phase or CD. A Major System

Project is a project with a Total Project Cost (TPC) greater than or equal to $750M or as

designated by the Deputy Secretary. A performance baseline deviation occurs when the

approved TPC, CD-4 completion date, or performance and scope parameters cannot be

met.

5.0 SCHEDULING OF AN ESAAB

5.1.1 OECM normally provides staff support to the Acquisition Executive and board members

for ESAAB presentations (e.g., schedules, agenda, pre-briefing and presentation

requirements).

5.1.2 The steps outlined in Appendix B provide the framework and normal working times and

responsibilities for the activities prior to and immediately following the ESAAB. This

includes the steps to schedule pre-ESAAB meetings and ESAAB reviews and the

appropriate responsible office.

5.1.3 A decision/review schedule will be developed and maintained current by the ESAAB

Secretariat (OECM) for those projects which require a board review because of an

acquisition phase decision, siting decision, problems, or other project developments that

merit management attention. The activity timeline in Appendix B provides the necessary

steps leading up to the ESAAB meeting.

5.1.4 Upon approval by the Acquisition Executive, formal scheduling of reviews will be

accomplished by the ESAAB Secretariat.

5.1.5 Unscheduled board meetings may also be called at the request of the Acquisition

Executive or a PSO. These requests will be made through the ESAAB Secretariat.

6.0 ESAAB PROCEDURES

Page 7: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

3

6.1 General. An ESAAB assists the SAE in approving critical decisions related to Major

System Projects and performance baseline deviation dispositions. A Major System

Project is a project with a Total Project Cost (TPC) greater than or equal to $750M or as

designated by the Deputy Secretary.

6.2 Critical Decisions and BCPs. The Deputy Secretary serves as SAE for projects with a

TPC greater than or equal to $750M. Critical Decisions (CD) or BCPs for these projects

must be proposed by the appropriate PSO and approved by the SAE before proceeding to

the next project phase or critical decision. In addition, other projects may require SAE

approval of a BCP above certain threshold values as defined in DOE O 413.3B (current

version). The description and/or definitions of Critical Decisions and Baseline Change

Proposal are provided in DOE O 413.3B.

7.0 ESAAB PROCEDURES

The SAE makes critical decisions for major system projects and those delineated in DOE

413.3B. .

7.1 Scheduling ESAAB Meetings.

7.2 ESAAB Preparation. It is essential that the presenters brief (see Appendix C) the

significant issues and problems that are associated with the project. These issues and

problems should be fully coordinated well in advance with cognizant staff and program

officials. Also, the Acquisition Executive and the sponsoring PSO shall receive concise

pre-briefings to assure that an informed decision or review will occur.

7.2.1 Project Briefing Material and Supporting Documentation. A draft of the project

briefing material and supporting documentation should be provided to the Office of

Engineering and Construction Management (OECM) and representatives for the board

members by the cognizant PSO. The draft briefing will be reviewed for conformance to

Departmental orders and policies and to identify any remaining issues for discussion at

the Pre-ESAAB meeting.

7.2.1.1 Inspector General (IG) / Government Accountability Office (GAO) /

Congressional Report Check. The Program shall identify recent IG, GAO, and

Congressional audit activity, reviews, reports, interest/support to the Acquisition

Executive. This action shall be completed and reviewed at the pre-ESAAB meeting.

7.2.2 Pre-ESAAB Meeting. The program and project managers will schedule and conduct a

“dry-run” of the presentation for the sponsoring PSO for review and resolution of issues

prior to the ESAAB meeting. The Pre-ESAAB members should be invited to:

Participate in a final exchange of ideas;

Assure compliance with Departmental policy and procedures;

Page 8: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

4

Discuss and resolve outstanding issues;

Determine the status of any independent project review (e.g., EIR or IPR) issues;

Cover the status of administrative actions; and

Set a schedule for remaining actions.

At the conclusion of the “dry-run,” a recommendation shall be made by OECM to the

PSO on the readiness of the project to proceed with the scheduled ESAAB meeting based

on the completeness of material and administrative actions presented at the “dry-run.”

7.2.3 Acquisition Executive Pre-Brief Meeting. A pre-briefing is conducted by OECM for

the Acquisition Executive to assist in their preparation for the board meeting. The

objectives of this pre-brief are to:

Acquaint the Acquisition Executive with the background and description of the

project;

Provide an independent assessment of the project;

Provide an independent assessment of remaining issues/problems to be presented with

recommended solutions;

Clarify any technical and management items; and

Provide a final status on administrative actions so as not to consume too much time

during the formal meeting.

7.2.4 ESAAB Staff Memorandum. The Secretariat shall prepare a staff memorandum (see

Appendix F) summarizing the results of the meeting.

7.2.4.1 The staff memorandum will specify SAE decisions reached (see Appendix E,

Decision Memorandum), actions assigned, results of special studies and assessments,

limitations associated with approvals, resource levels which may be used for

budgetary and organizational planning, constraints on systems development and

definition, and schedules for accomplishing action items. A summary of the

approved cost, schedule, and technical baselines will be annotated within the meeting

minutes. The ESAAB meeting minutes (see Appendix G) will be attached to the

memorandum.

7.2.4.2 The Secretariat will coordinate the staff memorandum with the appropriate board

members and advisors prior to forwarding it to the SAE. Dissenting views will be

included in the package. Non-concurrence on a coordinated document (e.g., Paper

ESAAB) by a member shall not require resolution prior to forwarding the request to

Page 9: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

5

the SAE for a decision. Coordination from each board member will be obtained on

the final document.

7.3 Call for Special ESAAB Review. When an unforeseen review of a major system project

is required, the following steps should be taken:

7.3.1 ESAABs shall be requested by the Headquarters Program Secretarial Officer or their

PMSO director.

7.3.2 The memorandum shall be submitted 30-days prior to the proposed ESAAB date and

include a statement regarding the decision requested, background, supporting factors, and

any other relevant information.

7.3.3 The ESAAB Secretariat will coordinate subsequent actions with the Program Office.

8.0 “PAPER” ESAAB

In circumstances where the acquisition action is of relatively low monetary value, low

risk, and requires non-controversial decisions (i.e., baseline deviation and critical

decision approvals) that need Deputy Secretary approval, a streamlined ESAAB achieves

the required staff coordination and approval without convening a formal meeting of all

ESAAB members.

8.1 Procedures.

8.1.1 A streamline ESAAB process in lieu of convening a formal meeting should be

considered, when the following parameters are met:

Program Office requests OECM consider a streamline ESAAB in lieu of a formal

ESAAB meeting;

The Office of Management will determine: (1) if a streamline ESAAB is appropriate;

and (2) level of inter-office coordination required; and

At a minimum, all streamline ESAABs will be coordinated with OECM, the Chief

Financial Officer, and the Office of the General Counsel with the expectation of

expeditious concurrences. However, non-concurrence on a coordinated document by

a member shall not require resolution prior to forwarding the request to the SAE for a

decision.

9.0 ESAAB-EQUIVALENT MEETINGS

The Programs are authorized to make changes to projects that are smaller than the SAE

approval limits to include all non-major systems projects and projects with a TPC less

than $750M. The Programs shall create an ESAAB-equivalent entity to facilitate

decision making.

Page 10: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

6

9.1 Procedures.

9.1.1 The designated AE will:

Appoint and chair acquisition advisory boards to provide advice and

recommendations on key project decisions.

Be delegated to a level commensurate with the size and complexity of the project and

in accordance with Departmental policies and orders.

Operate within the specific limits of their delegated authority.

9.1.2 The advisory board should replicate functions performed by the ESAAB.

9.1.3 Members may be selected from within the AE’s organization; however, at least one

member not under the AE will be designated as a contributing member.

9.1.4 The OECM will provide a representative to each advisory board for projects with a TPC

greater than or equal to $100M.

9.1.5 The OECM may be invited to attend advisory boards for projects with a TPC less than

$100M, but will not be a board member.

9.1.6 The implementing documentation and composition of each advisory boards along with

meeting agendas and minutes will be provided to OECM.

Page 11: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix A

Page 1

APPENDIX A

LIST OF ACRONYMS

AE Acquisition Executive

BCP Baseline Change Proposal

BSF Biological Sciences Facility

CD Critical Decision

CFO Chief Financial Officer

CFR Code of Federal Regulations

CRL Capability Replacement Laboratory

CSF Computational Sciences Facility

DHS Department of Homeland Security

DOE Department of Energy

EERE Energy Efficiency and Renewable Energy

EIR External Independent Review

EM Office of Environmental Management

ESAAB Energy System Acquisition Advisory Board

ESH&Q Environmental, Safety, Health & Quality Assurance

EVMS Earned Value Management System

FE Fossil Energy

FPD Federal Project Director

FY Fiscal Year

GC Office of General Counsel

HS Office of Health, Safety and Security

Page 12: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix A DRAFT OECM SOP 413.3-1

Page 2 January 4, 2010

IPR Independent Project Review

IPT Integrated Project Team

KPP Key Performance Parameter

LDL Large Detector Laboratory

LM Legacy Management

M Million

MA Office of Management

MS Major System

NA Office of Defense Programs

NE Office of Nuclear Energy

NEPA National Environmental Policy Act

NNSA National Nuclear Security Administration

O Order

OECM Office of Engineering and Construction Management

OMB Office of Management and Budget

OPC Other Project Costs

P Policy

PEP Project Execution Plan

PNNL Pacific Northwest National Laboratory

PSF Physical Sciences Facility

PSO Program Secretarial Officer

REA Request for Equitable Adjustment

RW Radioactive Waste

Page 13: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix A

Page 3

SAE Secretarial Acquisition Executive

SC Office of Science

SOP Standard Operating Procedure

TPC Total Project Cost

WBS Work Breakdown Structure

Page 14: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board
Page 15: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix B

Page 1

APPENDIX B

ESAAB ACTIVITIES TIMELINE

The steps outlined below provide the framework and normal working times and responsibilities

for the activities prior to and immediately following the ESAAB:

Activity Responsible

Office

Calendar Days

Relative to Meeting

Notify ESAAB Secretariat PSO 90 days

Submit written request to Secretariat for ESAAB

review

PSO 60 days

Schedule pre-ESAAB meeting PSO 40 days

Prepare draft briefing material and supporting

documentation

PSO 30 days

Distribute briefing material for pre-ESAAB

meeting

PSO 25 days

Conduct pre-ESAAB meeting PSO 20 days

Comment on pre-ESAAB presentation ESAAB

Members

15 days

Confirm proposed ESAAB date with Acquisition

Executive

ESAAB

Secretariat

14 days

Submit ESAAB meeting request ESAAB

Secretariat

12 Days

Finalize briefing material and supporting

documentation

PSO 10 days

Distribute final briefing material to ESAAB

members

ESAAB

Secretariat

7 days

Conduct SAE pre-brief meeting ESAAB

Secretariat

2 days

Conduct ESAAB meeting SAE 0 days

Prepare staff memorandum of decision with

actions and provide required project

documentation (updated by PSO) reflecting

ESAAB decisions and submit for SAE approval

and issuance

ESAAB

Secretariat

+15 days

Page 16: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board
Page 17: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix C

Page 1

APPENDIX C

PRESENTATION OUTLINE FOR THE ESAAB MEETING

1. GENERAL. These guidelines have been prepared to aid program and project managers in

their preparation of presentation materials for ESAAB meetings.

2. COMPOSITION. Each presentation will be slightly different given the decision (e.g.,

baseline change proposal) required of the SAE. The following outline is a guide to assist in

compiling the ESAAB presentation.

a. CD-0, Approve Mission Need

Title Page

Mission / Objectives – Summarize the capability gap. Describe why the facilities,

equipment, or services currently existing are not sufficient to address the gap.

Explain the internal or external drivers (e.g., statute, regulation, legal agreement,

earmark, or Presidential directive).

Alternative Strategies – Identify high-level strategies/alternatives considered or to be

analyzed to meet the mission need.

Conceptual Scope

Conceptual Schedule and Cost Range

Readiness to Proceed

Assumptions and Constraints

Risk Management

Mission Validation Independent Review – Summarize the issues, their resolution, and

subsequent recommendations.

Summary and Recommendation

b. CD-1, Approve Alternative Selection and Cost Range

Title Page

Mission / Objectives

Alternatives: (Discuss sorting, grading, and selecting criteria.)

­ Strategies

­ Technologies

­ Locations

­ Acquisition Strategies (e.g., design-build) and Plan (e.g., M&O)

­ Life Cycle Cost and Schedule

Preferred Alternative

Project Technical Scope/Process

Conceptual Schedule and Cost Range

Readiness to Proceed

Assumptions and Constraints

Risk Management

Integrated Project Team

Long Lead Procurements

Summary and Recommendation

Page 18: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix C

Page 2

c. CD-2, Approve Performance Baseline, or BCP (see Section 3)

d. CD-3, Approve Start of Construction (see Section 3). Although using the same set of

slides as in CD-2, the Program should discuss the differences or what has changed since

CD-2 with the ESAAB members.

3. CHARTS. The charts may be augmented by additional charts that the Programs need to

illustrate project systems, problems, issues, or other pertinent factors. However, presentation

materials should be minimized to the extent possible. The outline that follows describes the

information that should be considered for inclusion on the presentation charts for a CD-2,

CD-3, or BCP approval request.

a. Title Page. Indicate the official name of the project, the name and organization of the

acquisition proponent, and the name of the presenters. State the ESAAB decision that

will be requested at the meeting.

b. Mission / Objectives. Indicate the original mission need statement. If the Program has

identified a credible performance gap between its current capabilities and stated goals,

then indicate the updates to the mission-related need. Also, state the key program and

project objectives. The relationship between the program and project objectives should

be clear.

c. Project Technical Scope / Process. Show a recent photograph or artist’s conception of

the project. Use a technical process flow chart or similar graphic to summarize how the

facility or machine is expected to function. Identify key requirements (or KPPs). Show

the basic technical baseline requirements for the project. A history of project related

events and a detailed technical description should be avoided due to time constraints.

The ESAAB members and advisors should be briefed by their respective staffs or may

request a briefing by the respective Program.

d. Baseline Project Summary Schedule. Provide an overview of project activity; display

the baseline schedule for the life of the project. Include all Acquisition Executive

decision points, other critical decisions and events, major milestones including ES&H

milestones that may impact the project’s critical path, and critical path for project

implementation. Also, state the tailoring strategy for adapting critical decision

requirements, if any.

e. Baseline Resource Plan. Show the funding authority profile available and anticipated.

Show both cumulative obligations and costs planned by fiscal year over the life of the

project. Actual costs and obligations to date shall be shown against these plans. All costs

and obligations shall be denoted in current-year dollars for the year of expenditure.

Address the basis of the cost/schedule estimate to include methodology and confidence

levels. Also, show the total estimated cost for design, construction, and startup to include

contingency, management reserve, fees, and ODCs. If a BCP, the Program must show

Page 19: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix C

Page 3

how much funding is required and where the funding is coming from in the Program.

f. Readiness to Proceed. In a very brief, bullet style manner, summarize the status of each

critical decision prerequisite. Succinctly state the problem, issue, or item of concern, list

the corrective actions taken, the additional corrective actions required (with dates), and an

assessment of the impact on the project. Prepare a separate chart for each topic to be

discussed with whatever illustrative material is appropriate to present the problem, issue,

or item of concern in a fully informative manner. [Highlight the major system critical

decision prerequisites (as prescribed in DOE O 413.3A) needed to bring a project to the

next major milestone in the acquisition phase.]

g. Assumptions and Constraints. Identify the assumptions and constraints related to the

project life cycle to include phases of design, construction, commissioning and

operations.

h. Risk Management. Summarize the key risks resulting from assumptions, requirements,

technology readiness, staffing and the like. Include your mitigation plans as well as the

likelihood of occurrence and consequence of impact.

i. Project Contract Status. Review or update the project’s acquisition plan and the

contractor’s performance to date.

j. Integrated Project Team. Show the participating organizations and their

responsibilities in the form of an organization chart. This is the opportunity to depict the

manner in which the project is being managed. Laboratory/contractor/partner

responsibilities should be included. Also show, in a separate box, a summary of the DOE

staffing, both on-board and planned.

k. ICE, EIR, and EVMS Summary. Summarize the resolution of ICE, major EIR

findings, and the status of EVMS certification.

l. Summary and Recommendation. Highlight the key points from the presentation,

restate the decision requested, and identify the next actions planned following the

requested decision by the Acquisition Executive.

Page 20: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board
Page 21: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

1

APPENDIX D

ESAAB MEMBERS

Full-time ESAAB Members Organization Symbol Principal Ext. Scheduler

Deputy Secretary, Secretarial

Acquisition Executive (ESAAB

Chair)

S-2 Dan Poneman 6-5500 Paige Fitzgerald

Associate Deputy Secretary S-2 Mel Williams 6-9500 John Stewart

Under Secretary for Energy

(Acting)

S-3 Vacant 6-7700 Miles Brundage

Under Secretary for Science S-4 Steve Koonin 586-

0505

Megan Chambers

Office of General Counsel GC-1 Sean Lev 6-5281 Katharine Dickerson

Administrator, Office of NNSA NA-1 Thomas D’Agostino 6-5555 David Alldridge

Director, Office of Management MA-1 Ingrid Kolb 6-2550 Robin Henderson

Office of the Chief Financial

Officer

CF-1 Owen Barwell 6-4171 Shannon Shriber

Assistant Secretary, Office of

Environmental Management

EM-1 David Huizenga 6-7709 Lori Schmader

Chief Health, Safety and

Security Officer

HS-1 Glenn Podonsky 3-3777 Frances Rose

Chief of Defense Nuclear Safety NA-

SH-10

Don Nichols 6-8216 Lalissa McKnight

Chief of Nuclear Safety S-5 Richard “Chip”

Lagdon

6-0799 Elaine Merchant

Deputy Administrator, Office of

Defense Programs

NA-10 Donald Cook 6-2179 Mary Laders-Haller

Director, Office of Science SC-1 William F. Brinkman 6-5430 Dionne Claxton

Director, Office of Engineering

& Construction Management

MA-50 Paul Bosco 6-3524 Rosalyn Matthews

Director of Procurement &

Management Assistance (Acting)

MA-60 Patrick Ferraro 7-1388 Sandra Addison

Page 22: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

2

Please note: this is the “As-Needed” list and all these members need not be invited.

As-Needed ESAAB Members Organization Symbol Principal Ext. Scheduler

Associate Administrator for

Acquisition and Project

Management

NA-APM-

1

Bob Raines 6-5627 Jim Fores

Director, Office of Budget CF-30 Christopher Johns 6-4049 Derrick Nayo

Deputy Director for Budget

Analysis

CF-31 Shalini Benson 6-6023 Derrick Nayo

Deputy Director for Budget

Operations.

CF-32 Hose Villar 6-8764 Derrick Nayo

Office of Engineering &

Construction Management

MA-50 Vacant 6-5627 Rosalyn Matthews

Chief Acquisition Officer MA-1 VACANT 6-2550 Robin Henderson

PSO – SC SC-28 Daniel Lehman 3-4840 Self

PSO – EM-10 EM-10 Vacant 3-5838 Self

Project Assistance & Assurance EM-11 Lowell Ely 3-6821 Self

DAS Acquisition & Contract

Mgmt

EM-80 Jack Surash 6-6382 Trina Johnson

PSO – NNSA NA-APM-

20

Mike Hickman 6-8872 Self

Assistant Secretary Fossil

Energy (FE projects only)

FE-1 Charles D.

McConnel

6-6660 Audrey Johnson-

Tolbert

Assistant Secretary EERE

(EERE projects only)

EE-1 Henry Kelly 6-9220 Meghan Condon

Director of Legacy Management LM-1 David Geiser 6-8324 Tianna Rodriquez

Assistant Secretary for Nuclear

Energy

NE-1 Peter Lyons 6-2240 Alison Kennedy

Page 23: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

3

Pre-ESAAB MEMBERS

Organization Symbol Principal Ext. Scheduler

Director, Office of Budget CF-30 Christopher Johns 6-4049 Derrick Nayo

Deputy Director for Budget

Analysis

CF-31 Shalini Benson 6-6023 Derrick Nayo

CFO/Cognizant Budget

Examiner (SC)

CF-30 John Stann 3-7790 Self

CFO/Cognizant Budget

Examiner (NNSA, SC)

CF-31 Mark Joseph 6-7717

Self

CFO/Cognizant Budget

Examiner (SC)

CF-31 Beverly Kipe 3-2254 Self

CFO/ Cognizant Budget

Examiner (SC)

CF-31 Natalia Melcer 6-5833

Self

CFO/Cognizant Budget

Examiner (EM)

CF-31 Greg Singleton 7-6092 Self

CFO/Cognizant Budget

Examiner (OE, PMAs)

CF-31 Alex Dey 6-5854 Self

EERE/Director, Sustainability

Performance Office

EE-2N Jennifer MacDonald 6-8645 Kristina Wheeler

OECM MA-50 Paul Bosco 6-3524 Rosalyn Matthews

OECM MA-50 Vacant Rosalyn Matthews

OECM/Cognizant Project

Analyst (Team Lead)

MA-50 Mike Peek 6-8223 Self

OECM/Cognizant Project

Analyst (EM-RL, ORP-Tank

Farm, SLAC, EM-INL)

MA-50 Mark Whitson 7-1697 Self

OECM/Cognizant Project

Analyst (NNSA)

MA-50 John White 6-3716

Self

OECM/Cognizant Project

Analyst (WTP, NNSA-Pantex,

EM-Oak Ridge, ETTP, Y-12,

PPPO)

MA-50 Darren Morton 7-1940

Self

OECM/Cognizant Project

Analyst (EM-SR, NE)

MA-50 Rick Elliott 7-1520 Self

OECM/Cognizant Project

Analyst (NNSA-SRS, EE)

MA-50 Tony Ermovick 6-8254 Self

OECM/Cognizant Project

Analyst (SC, EM-LANL/LLNL/

LBNL)

MA-50 Brian Huizenga 6-9588

Self

OECM/Cognizant Project

Analyst (ORP-WTP)

MA-50 Brian Kong 6-3151 Self

OECM/ Cognizant Project

Analyst (EM-Small Sites, FE)

MA-50 Tom Bruder 6-0199 Self

Page 24: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

4

Pre-ESAAB Members (cont.)

Organization Symbol Principal Ext. Scheduler

HSS HS-30 Jim O'Brien 3-1408 Self

HSS HS-31 Pranab Guha 3-7089 Self

NNSA NA-

APM-20

Katherine O'Mara 6-6867 Self

NNSA NA-

APM-20

Mike Hickman 6-8872

3-3357

Self

NNSA NA-

APM-20

Jane Gartner 3-8235 Self

Principal Deputy Assistant

Secretary for EM

EM-2 Tracy Mustin 6-5216 Lori Schmader

EM EM-10 VACANT Self

EM EM-11 Lowell Ely 3-6821 Self

EM EM-80 Jack Surash 6-6382 Trina Johnson

EM EM-80 Suneel Kapur 6-0110 Self

SC SC-28 Daniel Lehman 3-4840 Self

SC SC-28 Kin Chao 3-4116 Self

SC SC-28 Casey Clark 3-5451 Self

Assistant Secretary for Nuclear

Energy

NE-3 Richard Stark 3-4407 Self

Assistant Secretary for Nuclear

Energy

NE-31 Mary McCune 3-8152 Self

Office of Procurement and

Assistance Management

MA-60 David Boyd 7-1310 Sandra Addison

Chief of Nuclear Safety CNS Joseph “Tim” Arcano 3-0139 Self

Chief of Nuclear Safety CNS

Gustave “Bud”

Danielson

3-2954 Self

General Counsel GC-31 Steve Miller 6-2925 Self

General Counsel GC-50 Sean Lev 6-7347 Self

Office of NEPA Policy and

Compliance

GC-54 Carol Borgstrom 6-4600 Self

Office of NEPA Policy and

Compliance

GC-54 Jim Daniel 6-9760 Self

General Counsel GC-60 Gena Cadieux 6-3426 Lisa Brown

General Counsel GC-61 VACANT Lisa Brown

Page 25: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

DRAFT OECM SOP 413.3-1 Appendix E

January 4, 2010 Page 1

APPENDIX E

EXAMPLE OF THE DECISION MEMORANDUM

MEMORANDUM FOR RAYMOND L. ORBACH

UNDER SECRETARY FOR SCIENCE

THROUGH: INGRID KOLB

DIRECTOR, OFFICE OF MANAGEMENT

FROM: JEFFREY F. KUPFER

ACTING DEPUTY SECRETARY

SUBJECT: Critical Decision (CD)-3, Approve Start of Construction for the

National Synchrotron Light Source II at Brookhaven National

Laboratory

As the Secretarial Acquisition Executive for the Office of Science’s (SC) National Synchrotron

Light Source II (NSLS II) at Brookhaven National Laboratory, I approve the Start of

Construction (CD-3). The project was baselined at CD-2 with a Total Project Cost (TPC) of

$912M and a June 2015 completion date.

Any conditions coincident with this critical decision approval are reflected within the appropriate

Energy Systems Acquisition Advisory Board minutes.

cc: Bud Albright, Under Secretary of Energy

Page 26: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board
Page 27: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

DRAFT OECM SOP 413.3-1 Appendix F

January 4, 2010 Page 1

APPENDIX F

EXAMPLE OF THE STAFF MEMORANDUM

MEMORANDUM FOR DANIEL B. PONEMAN

DEPUTY SECRETARY

THROUGH: INGRID KOLB

DIRECTOR, OFFICE OF MANAGEMENT

FROM: PAUL BOSCO

SECRETARIAT, ENERGY SYSTEMS ACQUISITION

ADVISORY BOARD

SUBJECT: Meeting Minutes of the Energy Systems Acquisition Advisory Board

(ESAAB) for Review and Discussion of the Critical Decision-2

(Approve Performance Baseline) for the Physical Sciences Facility

(PSF) project at the Pacific Northwest National Laboratory (PNNL)

ISSUE: Need approval of CD-2 and ESAAB meeting minutes.

BACKGROUND: On June 22, 2007, the Deputy Secretary chaired a meeting of the

ESAAB to discuss CD-2 for the PSF project at PNNL. PSF is a line

item construction project within the Capability Replacement

Laboratory (CRL) Program that relocates PNNL functions to

accommodate EM clean-up within the Hanford 300 area.

SENSITIVIES: None

POLICY IMPACT: None

RECOMMENDATION: Sign the CD-2 approval and ESAAB meeting minute memorandums.

Attachments

Page 28: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board
Page 29: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

DRAFT OECM SOP 413.3-1 Appendix G

January 4, 2010 Page 1

APPENDIX G

EXAMPLE OF THE ESAAB MEETING MINUTES

MEMORANDUM FOR DANIEL B. PONEMAN

DEPUTY SECRETARY

THROUGH: INGRID KOLB

DIRECTOR, OFFICE OF MANAGEMENT

FROM: PAUL BOSCO

SECRETARIAT, ENERGY SYSTEMS ACQUISITION

ADVISORY BOARD

SUBJECT: Meeting Minutes of the Energy Systems Acquisition Advisory Board

(ESAAB) for Review and Discussion of the Critical Decision-2

(Approve Performance Baseline) for the Physical Sciences Facility

(PSF) project at the Pacific Northwest National Laboratory (PNNL)

BACKGROUND: On June 22, 2007, the Deputy Secretary chaired a meeting of the

ESAAB to discuss Critical Decision-2 (CD-2, Approve Performance

Baseline) for the Physical Sciences Facility (PSF) project at the Pacific

Northwest National Laboratory (PNNL). PSF is a line item

construction project within the Capability Replacement Laboratory

(CRL) Program that relocates PNNL functions to accommodate EM

clean-up within the Hanford 300 area. Prior Critical Decisions

include: CD-0 in September 2004, CD-1 in December 2005, and CD-

1R in December 2006.

The PSF project is managed by SC and is jointly sponsored (funded)

by SC ($98M), NNSA ($70M), and DHS ($56M) with a proposed

Total Project Cost (TPC) of $224M (the parenthetical monetary

numbers have been rounded). The success of the overall CRL mission

will depend on completion of several other related activities:

Construction of the Biological Sciences Facility (BSF) and the

Computational Sciences Facility (CSF) using a proposed

alternative financing strategy;

Area 300 utilities rerouting funded by EM;

Repairs/modifications to three retained buildings funded by

SC;

Installation of PSF Site utilities funded by the State of

Washington; and

Relocation of capabilities funded by PNNL.

Page 30: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

Appendix G DRAFT OECM SOP 413.3-1

Page 2 January 4, 2010

DISCUSSION: Following the presentation by Chad Henderson, the Federal Project

Director, much discussion followed, including the continued need to

designate the PSF project as a Major System (MS) project. Even

though the TPC of $224M is well below the MS threshold, the

Capability Replacement Laboratory (CRL) program was designated as

a MS project because of complex interfaces between the many sub-

projects under the CRL and the joint funding by the Offices of Science,

National Nuclear Security Administration and the Department of

Homeland Security. Marc Jones explained that the PSF project has

resolved most of these issues by agreeing to a funding strategy with the

sponsors in a Memorandum of Understanding and formalizing facility

turnover dates with EM. Mr. Jones also explained that the construction

scope is straightforward and the TPC is well below the dollar threshold

for a MS project. It was suggested that the SAE consider delegation of

specific AE authorities in conjunction with the requirement that SC

provide a quarterly briefing to the Deputy Secretary. Marc Jones

explained that delegation of authority for CD-3 to the Under Secretary

for Science was needed to maintain the project schedule. Charles

Anderson said that EM will miss milestones if the PSF project schedule

slips.

The Deputy Secretary asked whether there was any contamination

under building 325. Charles Anderson explained that EM was

confident that the contamination under the building was localized and

did not pose any risk of contributing to existing contamination plumes.

Cleanup of any contamination under the building after the mission life

of the facility would be straightforward.

Mary Egger asked about the relationship of the scope of the proposed

alternatively financed buildings to the PSF and the risk to the overall

CRL project if that proposal was not approved. Dr. Orbach stated that

the risk of moving forward with the PSF project before approval of the

business case was minimal. In his view, the alternative financing was

the best strategy. He recommended that the PSF project proceed while

the acquisition strategy for the other two facilities is decided.

A question was raised as to why DHS was not represented on the IPT.

SC explained that DHS is fully supportive of the approach and has

signed the Project Execution Plan (PEP). DHS has been and will be

kept informed through regular project reviews. SC was asked if this

project was in the DHS five-year budget plan. Dr. Orbach replied that

DHS does not have five-year budget plans, however DHS (Adm.

Cohen) has promised full support for the project and if DHS does not

come through because of Congressional action, or any other reason, SC

will fund the shortfall.

Page 31: ENERGY SYSTEM ACQUISITION ADVISORY BOARD (ESAAB) … SOP Nov_2011.pdf · This Standard Operating Procedure (SOP) discusses all elements of an Energy System Acquisition Advisory Board

DRAFT OECM SOP 413.3-1 Appendix G

January 4, 2010 Page 3

Ed Simpson asked how Battelle will be held accountable for

performance on this project. George Malosh stated that the Battelle

contract specifically includes metrics that measure cost and schedule

performance for construction projects. These metrics will influence

Battelle’s overall scorecard and the award fee. PNNL has made

significant personnel changes at the management level to address past

performance issues.

Regarding a question about safety risks, Chip Langdon stated that his

organization had reviewed the project safety documentation and found

that the project team had satisfactorily addressed all nuclear safety

issues.

MA recommended that the Deputy Secretary:

Approve PSF project performance baseline with TPC of

$224M and project completion date of Feb 2011 (CD-2).

Approve the PEP and delegate approval of future updates of

the PEP to the Under Secretary for SC.

Delegate approval of start of early construction for site

preparation (CD-3a).

Delegate approval of the business case for alternatively

financed facilities to the Under Secretary for Science.

RECOMMENDATION: Deputy Secretary sign the attached memorandum approving the

project performance baseline (CD-2) and delegating AE authority to

approve:

(1) Start of early construction for site preparation (CD-3a);

(2) Business case for alternative financing of the BSF and the CSF

(subject to successful review and agreement from OMB); and

(3) Future updates to the PEP.

Approved: _________________

Disapproved: _________________

Date: _________________