Energy Modelling and Passive Design Performance Complete an energy model using BCA Section J energy modelling Guidelines. Provide a report in accordance to show predicted energy consumption for each space type within the building and a predicted total value for the Building's annual energy use. 3 points: Demonstrate that the proposed building will perform a) at least 20% better than the reference building when the proposed building is modelled with the proposed services; and b) at least 10% better the reference building when the proposed building is modelled with the same services as the reference building Measure Project Name ENERGY MODELLING AND PASSIVE DESIGN [2.2] Submittal Form Page 1 of 5 Points Available 3 Points Claimed Date Name (print) Signature Project Team Representative Date Name (print) Signature Campus Infrastructure Services Sustainability Representative Sign-off: Pre-contract Design Stage By ticking this box the project team confirms the Pre-contract design stage meets the requirements of the measure and details are provided in this form. Mandatory Requirement 05/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES
5
Embed
ENERGY MODELLING AND PASSIVE DESIGN [2.2] Submittal Form
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Energy Modelling and Passive Design Performance Complete an energy model using BCA Section J energy modelling Guidelines. Provide a report in accordance to show predicted energy consumption for each space type within the building and a predicted total value for the Building's annual energy use.
3 points: Demonstrate that the proposed building will perform a) at least 20% better than the reference building when the proposed building is modelled with the proposed services; and b) at least 10% better the reference building when the proposed building is modelled with the same services as the reference building
Measure
Project Name
ENERGY MODELLING AND PASSIVE DESIGN [2.2] Submittal Form
By ticking this box the project team confirms the Pre-contract design stage meets the requirements of the measure and details are provided in this form.
By ticking this box the project team confirms the Energy Modelling assessment completed in the design stage meets the requirements of this measure
1.1 Energy Modelling Assessment Results - Base Building
Plant Model 1: Standard Practice Building [Benchmark] (MWh)
Model 2: Proposed Building Fabric with benchmark
building Services
Model 3: Proposed Building Fabric and Services (MWh)
Boiler Energy
Chiller Energy
Cooling Tower
Communications
Fans [AHU/FCU]
Mechanical Pumps
Hydraulic Pumps
Ventilation Fans
Lighting
Lifts
Domestic Hot Water
Other Please List
Totals
BCA Version Used
Confirm the following for the energy modelling assessment completed:
Any Specific Assumptions Made and Reference within Modelling Report
1.0 Pre-contract Design Stage - Energy Modeling and Passive Design
Complete the following table for Energy Modelling results breakdown:
Page 3 of 5
Complete the following table for energy modelling results and confirm overall savings:
ModelTotal Building Gas
Consumption (MWh)
Total Building Electricity
Consumption (MWh)
Total Building Energy
Consumption per annum (MWh)
% Improvement
Model 1: Standard Practice Building (Reference Building)
Model 2: Proposed Building Fabric with benchmark building Services
Model 3: Proposed Building Fabric with Proposed Services
Please advise on the estimated energy consumption for the building associated with Plug-in Loads (kWh) from Plug In Loads Analysis Submittal Calculation Form:
Page 4 of 505/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES
List of Reference documents
Energy Use Breakdown
List of Modelling Inputs [services, building fabric etc]
Model and Geometry [descriptions and images]
Software adopted and modelling methodology
Summary of Energy Results
Energy Modelling Report which includes the following minimum details:
Provide the following documents as part of the Pre-Contract signoff:
1.4 Reference Documents
List of any assumptions
Operational Profiles adopted
Building construction calculations including minimum thermal insulation specifications
Lighting Calculations
List of any protocols adopted and associated calculations
Plant and equipment energy power use and associated efficiencies
2.0 As-built Stage - Energy Modeling and Passive Design
If there have been any deviations in the AS-INSTALLED Plant or Building Fabric to details previously modelled please describe in brief below and provided updated Modelling Report:
2.1 Reference Documents
Provide the following documents as part of the As-built signoff:
Page 5 of 505/02/2015 Revision 1.0 CAMPUS INFRASTRUCTURE & SERVICES
List of Reference documents
Energy Use Breakdown
List of Modelling Inputs [services, building fabric etc]
Model and Geometry [descriptions and images]
Software adopted and modelling methodology
Summary of Energy Results
Energy Modelling Report which includes the following minimum details:
List of any assumptions
Operational Profiles adopted
Building construction calculations including minimum thermal insulation specifications
Lighting Calculations
List of any protocols adopted and associated calculations
Plant and equipment energy power use and associated efficiencies