1 Energy Mart 2004 FUEL OPTIONS FOR POWER SECTOR FUEL OPTIONS FOR POWER SECTOR PLANNING AND LOGISTICS FOR PLANNING AND LOGISTICS FOR NATURAL GAS NATURAL GAS Dr. S.C. Sharma Dr. S.C. Sharma PETRONET LNG LIMITED PETRONET LNG LIMITED NEW DELHI-INDIA NEW DELHI-INDIA 21 21 st st January, 2004 January, 2004
32
Embed
Energy Mart 2004 1 FUEL OPTIONS FOR POWER SECTOR PLANNING AND LOGISTICS FOR NATURAL GAS Dr. S.C. Sharma PETRONET LNG LIMITED NEW DELHI-INDIA 21 st January,
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1Energy Mart 2004
FUEL OPTIONS FOR POWER FUEL OPTIONS FOR POWER SECTOR PLANNING AND LOGISTICS SECTOR PLANNING AND LOGISTICS
FOR NATURAL GASFOR NATURAL GAS
Dr. S.C. SharmaDr. S.C. SharmaPETRONET LNG LIMITEDPETRONET LNG LIMITED
NEW DELHI-INDIANEW DELHI-INDIA2121stst January, 2004 January, 2004
2Energy Mart 2004
OVERVIEWOVERVIEW
INDIA’S ENERGY REQUIREMENTINDIA’S ENERGY REQUIREMENT GAS A PREFERRED FUEL FOR POWERGAS A PREFERRED FUEL FOR POWER PLANNING FOR GAS DEVELOPMENTPLANNING FOR GAS DEVELOPMENT LNG IMPORTSLNG IMPORTS PETRONET LNG LIMITEDPETRONET LNG LIMITED CREATING GAS TRANSPORTATIONCREATING GAS TRANSPORTATION ISSUES AND CHALLENGESISSUES AND CHALLENGES CONCLUSIONCONCLUSION
3Energy Mart 2004
INDIA’S ENERGY INDIA’S ENERGY REQUIREMENTREQUIREMENT
4Energy Mart 2004
WORLD ENERGY OUTLOOK WORLD ENERGY OUTLOOK 20252025
CREATING GAS IMPORT CREATING GAS IMPORT INFRASTRUCTUREINFRASTRUCTURE
LNG Terminal Capacity (MMTPA)
Dahej 5
Dahej Exp 5
Kochi 2.5
Shell Hazira 2.5
Dabhol 2.5
Mangalore 5.0
Kakinada 2.5
Total 25
About 22.5 MMTPA of LNG by next 5 - 10 years
11Energy Mart 2004
NATURAL GAS FOR POWER NATURAL GAS FOR POWER SECTORSECTOR
– Low gestation period
– Lower capital cost compare to coal base plant.
– 56% guaranteed gas turbine efficiency.
– Cheaper peak load power generation.
– Committed supply for power plant life cycle.
– Utilization of cold energy from LNG to enhance efficiency by 3 to 4%
– Natural gas is the most viable source to meet the power demand
12Energy Mart 2004
POWER GENERATION POWER GENERATION CAPACITY ADDITION(MW)CAPACITY ADDITION(MW)
0
10000
20000
30000
40000
50000
8th plan 9th plan 10th plan
Planned Achieved
Cap
acit
y (M
W)
•Fuel Supply – Major constrain for power capacity addition•Power capacity addition target achieved at •About 50% level in 8th & 9th plan
13Energy Mart 2004
WHY LNG /GAS IMPORTS TO WHY LNG /GAS IMPORTS TO INDIA ?INDIA ?
Large emerging demand Location advantage Environment concerns Imported Crude prices Lower share of natural gas Use of liquid fuels by gas based
industries Focus on shifting from
LPG/kerosene to gas Plan to replace 20% liquid fuels
by gas
India imports about 90 MMTPA of crude oil, 20% of of liquid products replaced by LNG can result in saving of 1.5 to 2.0 billion US$ on import of crude oil.
NATURAL GSREQUIREMENT FOR NATURAL GSREQUIREMENT FOR CNGCNG
CNG fastest growing market due to environment concerns
Currently about 160 CNG filling stations
175,000 Vehicles on CNG Program to implement CNG in
other major cities like Kanpur, Lucknow, Ahmedabad, Vadodara, Faridabad & Hyderabad.
Large incentive on cost of fuel using
CNG Conversion potential of 1.47 million vehicles assessed in Mumbai & Delhi itself
20% replacement will require 10 MMTPA of natural gas/LNG.
29Energy Mart 2004
PRICING OF NATURAL GASPRICING OF NATURAL GAS
Price of domestic gas currently controlled by Government
Gas price revision under consideration. Gas prices moving towards market parity. PLL had made facilities on most competitive terms. Price most competitive for new power capacity. Affordable for fertilizer capacity creation. Very high affordability for liquid fuel based fertilizer
plants. High affordability to replace MS / diesel / naphtha / FO
in transport, domestic, fertiliser and other industries.
30Energy Mart 2004
COST OF POWER WITH LNGCOST OF POWER WITH LNG
Fixed charges Rs/kwh
Variable Charges Rs/kwh
Total cost
Rs/kwh
Existing Gas based projects
LNG Price $/MMBTU
4.0$ / MMBTU
New Projects
LNG Price 4.25$ / MMBTU
Project-Imported Coal-New
0.60*
0.90*
1.25
1.35
1.35
1.25
1.95
2.25
2.50
*Average fixed charges for all the gas based projects HBJ/Gujarat*Fixed charges for new gas based project
Natural gas a viable fuel for power etc.
Higher combined cycle efficiencies
Facilitating peak load power
Lower emissions
31Energy Mart 2004
ISSUESISSUES
•Dismantling of Administered prices in phases
• Setting up of Petroleum Regulatory Board
• Introduction of Open Access principle
• Framework of Transportation Tariff
• Unbundling of Transportation and distribution
• Multiple producer prices
• Distance based transmission tariff
32Energy Mart 2004
THANKSTHANKS
DISHA TO PROVIDE RIGHT FUEL FOR LARGE DISHA TO PROVIDE RIGHT FUEL FOR LARGE SCALE POWER DEVELOPMENT IN INDIASCALE POWER DEVELOPMENT IN INDIA