Originator: COPI COPI Group Owner: UO – Engineering – Onshore Sumatra Area: General Location: General System: General System Document Type: Final Report Discipline / Sub discipline: Old COPI Document No.: - Printed initials in the approval boxes confirm that the document has been signed. The originals are held within Document Management. Document Title: Final Report ENERGY MANAGEMENT ASSESSMENT / AUDIT FOR PSC CORRIDOR (SUBAN-GRISSIK-RAWA) COPI Doc No.: 1 IFR 14 Dec 07 Issued for Review 2 IFR 14 Jan 08 Issued for Review Rev Status Issue Date Reason for Issue Prepared Checked Approvals
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Originator: COPICOPI Group Owner: UO – Engineering – Onshore SumatraArea: GeneralLocation: GeneralSystem: General SystemDocument Type: Final ReportDiscipline / Sub discipline:Old COPI Document No.: -
Printed initials in the approval boxes confirm that the document has been signed.The originals are held within Document Management.
Document Title: Final ReportENERGY MANAGEMENT ASSESSMENT / AUDIT FOR PSC CORRIDOR (SUBAN-GRISSIK-RAWA)
COPI Doc No.:
1 IFR 14 Dec 07 Issued for Review
2 IFR 14 Jan 08 Issued for Review
Rev Status Issue Date Reason for Issue Prepared CheckedApprovals
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 2 of 109
Revision Sheet
REVISION DATE DESCRIPTION OF CHANGE
1 14 Dec 07 Issued for Review
2 14 Jan 08 Issued for Review
ConocoPhillips Indonesia Inc. LtdPT.E M I (Persero)
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 3 of 109
CONTENTS
I. INTRODUCTION
II. METHODOLOGY
2.1 METHODOLOGY OF ENERGY ASSESSMENT
2.2 METHODOLOGY OF CALCULATION
2.2.1 CALCULATION OF EQUIPMENT
2.2.2 CALCULATION OF SYSTEM
III. ENERGY ASSESSMENT AT SUBAN GAS PLANT
3.1. GENERAL PLANT OPERATION AND PERFORMANCE
3.3.1. GENERAL PLANT OPERATION OF SUBAN GAS PLANT
3.3.2. GENERAL PLANT PERFORMANCE OF SUBAN GAS PLANT
3.2. PERFORMANCE EVALUATION EACH SYSTEM
3.2.1. SEPARATION & COOLER SYSTEM
3.2.2. AMINE SYSTEM
3.2.3. CONDENSATE STABILIZING SYSTEM
3.2.4. DEW POINT CONTROL AND REFRIGERATION SYSTEM
3.2.5. GAS COMPRESSION SYSTEM
3.2.6. GAS TURBINE GENERATOR
3.2.7. AIR COMPRESSOR
3.2.8. ELECTRICAL MAP SUBAN GAS PLANT
3.3. FINDINGS AND RECOMMENDATIONS
IV. ENERGY ASSESSMENT AT GRISSIK CENTRAL GAS PLANT
4.1. GENERAL PLANT OPERATION AND PERFORMANCE
4.1.1. GENERAL PLANT OPERATION OF GRISSIK GAS PLANT
4.1.2. GENERAL PLANT PERFORMANCE OF GRISSIK GAS PLANT
4.2. PERFORMANCE EVALUATION EACH SYSTEM
4.2.1. GAS PRETREATMENT AND MEMBRANE SYSTEM
4.2.2. AMINE SYSTEM
4.2.3. REFRIGERATION SYSTEM
4.2.4. CONDENSATE STABILIZING SYSTEM
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 4 of 109
4.2.5. DEHYDRATION SYSTEM
4.2.6. WASTE HEAT BOILER
4.2.7. GAS TURBINE GENERATOR
4.2.8. AIR COMPRESSOR
4.2.9. ELECTRICAL MAP CENTRAL GRISSIK GAS PLANT
4.3. FINDINGS AND RECOMMENDATIONS
V. ENERGY ASSESSMENT AT RAWA OIL PLANT
5.1. GENERAL PLANT OPERATION AND PERFORMANCE
5.2. PERFORMANCE EVALUATION
5.2.1. GENERAL PERFORMANCE5.2.2. PERFORMANCE EVALUATION OF MAIN EQUIPMENT
5.3. FINDINGS AND RECOMMENDATIONS
VI. PERFORMANCE MONITORING INDICATOR
6.1. EQUIPMENTS
6.1.1. Fired Heater
6.1.2. Waste Heat Boiler
6.1.3. Gas Turbine Generator
6.1.4. Residue Gas Compressor
6.1.5. Air Compressor
6.1.6. Propane compressor
6.1.7. Pumps
6.1.8. Air Cooler
6.1.9. Heat Exchanger
6.2. SYSTEM
6.2.1. Gas Pretreatment
6.2.2. Membrane System
6.2.3. Amine System
Amine Contactor
Amine Regenerator
6.2.4. Dehydration System
6.2.5. Dew Point Control System
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 5 of 109
Gas Chiller
Low Temperature Separator
6.2.6. Condensate Stabilizer
6.2.7. Depropanizer
APPENDICES
1. SCHEDULE OF ENERGY ASSESSMENT/AUDIT
2. MEASUREMENT DATA
3. LABORATORY ANALYSIS
4. LIST OF DATA HAS BEEN COLLECTED
5. SPREAD SHEET OF EFFICIENCY AND ENERGY CONSUMPTION EQUIPMENTS
SUBAN GAS PLANT
GRISSIK CENTRAL GAS PLANT
RAWA OIL PLANT
6. SPREAD SHEET OF PERFORMANCE MONITORING INDICATOR
EQUIPMENTS
SYSTEMS
7. SIMULATION RESULT OF SUBAN GAS PLANT
8. SIMULATION RESULT OF GRISSIK CENTRAL GAS PLANT
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 6 of 109
I. INTRODUCTION
As a part of energy management program, in the year of 2007 the Indonesia Business Unit of ConocoPhillips committed to develop plan regarding various efforts to conserve sources and to reutilize waste, energy utilization and to reduce emission reduction for each operating asset. Since 2004, emission level forecasts were generated as part of environmental performance report that shall be further followed up in actual action plans. This assessment is intended to guide the company in identifying energy-related business opportunities and appropriate methods and developing the strategic framework for realizing them. By performing this assessment / audit, it could also find emission reduction opportunities in onshore operating asset.
The aim of this assessment is to identify where and how much energy is used in a facility and for determining energy saving and emission reduction opportunities in onshore operating asset.
The objectives of this assessment / audit are as followed;
1. Provide clear direction or appropriate method as to potential inherent in a strategic approach to energy planning and management.
2. Define specific facilities that consume high energy and generate high emission.
3. To observe and evaluate the present situation of those plants in regards with energy consumption, process efficiency or performance and emission reduction opportunities.
4. Provide options based on a set of criteria (measures) and select the most promising options for implementation.
5. Provide recommendations and action plans in order to reduce energy consumption, increase plant efficiency and reduce emission rate in onshore operating assets by implementing energy diversification, energy efficiency and optimization and possibility to reuse energy waste.
The Scope of this assessment / audit are as followed;,
1 Preliminary Energy Audit / Assessment which includes : Review and prepare additional information, Identification and inventory energy consumption and production data; Analyze data to determine which equipment will get high priority to be assessed and; prepare action plan to perform energy management audit / assessment
2 Performing Energy Audit / Assessment which includes : Identifies area of high energy usage and where energy waste occurs; Develop priorities for reducing energy waste and emission; Provides a criteria of measures which improvements could be implemented and; Generate spreadsheet for energy consumption per equipment
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 7 of 109
3 Establish Calculation Performance Monitoring Indicators per equipment and system
4 Provide Recommendation for Improvements a part of COPI energy management program
To achieve the targets and to establish interactive cooperation of involved personnel without disturbing surveyed objects routine activities, the procedure of the Energy Assessment / Audit at Suban Gas Plant, Grisik Central Gas Plant and Rawa Oil Plant are as follows:
Preparation of the plant survey,
Field inspection and data collection,
Data verification (of the data collected)
Discussion
Data analysis and evaluation
Preliminary report,
Discussion
Field verification
Interim Report/Draft Final Report
Presentation,
Final Report.
The preparation of the plant survey has been held on 10 – 21 September 2007. The activity are includes define the boundaries, define data to be collected, define instruments / meter related to the data to be collected and prepare checklist for interview.
The Field inspection and data collection has been held on 24 September – 5 October 2007. The activity are includes collection of technical data of main energy-consuming equipment, operation data, historical data, interview data, and direct measurement with portable equipment. Principally, the data collected should be enogh to calculate material and heat balance in each equipment.
During data collecting period at Suban Gas Plant, Grissik Central Gas Plant and Rawa Oil Plant, not all the data requirement for analysis has been collected. Some of the data are completed from COPI Office Jakarta and the other data are completed during 2nd field inspection. Direct measurement are done for all fired heater at Suban Gas Plant and Waste Heat Boiler at Grissik Central Gas Plant.
In order to crosscheck the data gathered are accurate and reliable before carrying out analyses, it is need to do the data verification. The data verification, has been held on 8 - 10 October 2007 and the discussion regarding the result of data verification has been held on 23 October 2007.
Data analysis and evaluation has been held on 22 October – 23 November 2007. The activity of the analysis are includes preparation of calculation methodology, spread
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 8 of 109
sheet of equipment, develop heat and material balance, performance evaluation, identification/quantification of heat loss and calculation of energy conservation opportunities. The result of data analysis and evaluation are reported in the Preliminary Report on 26 November 2007 and discussion regarding this report has been held on 29 – 30 November 2007.
2nd field survey has been held on 3 – 7 December 2007 at Suban and Grissik. The activity during 2nd field survey are includes :
Measurement of flue gas composition and temperature of Heater and Waste Heat Boiler.
Electrical data records for rotating equipments.
Presentation of draft final report has been held on 18-19 December 2007
The Schedule of Energy Assessment, data has been collected and measured, laboratory analysis are summarized in the appendices no.1 – no. 4.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 9 of 109
II. METHODOLOGY
2.1. METHODOLOGY OF ENERGY ASSESSMENT/AUDIT
Obviously, the Methodology of Energy Assessment / Audit at Suban Gas Plant, Grisik Gas Plant and Rawa Oil Plant will involve :
Collect and Analyze Energy-Usage Data
Review, identify and inventory energy consumption data
Identify the main energy consumption system and equipments
Performance evaluation and identify the main energy consumption equipment.
Quantity energy waste and emission.
Recommendation.
The information regarding plant operation has been collected during data collection period from 24 September to 5 October 2007.
The data will be used in the analysis are include;
Daily Log Sheets
Computer logged data (for Suban and Grissik)
Laboratory analysis
Direct measurement during plant survey
Design data
After all the data has been collected, It is need to develop mass balance of each unit in order to verify the accuracy of flow meter reading. If there are discrepancy between mass inlet and outlet, ones of the mass flow should be adjusted, and than the data that has been verified will be used as data basis for development of heat and mass balance each equipment and system.
By using Spreadsheet and Process Simulation, a plant model will be created to calculate performance aspect of the equipments and compare with design or available references.
The plant model spreadsheet is constructed based on material and energy balance each equipment, energy efficiency and losses. Process Simulation used to develop material and energy balance for overall process gas plant.
Especially on the fired heater and waste heat boiler the spreadsheet is constructed based on the calculation of energy efficiency, losses and emission level of each equipment. Based on the data that has been collected, performance of each equipment, efficiency level, energy waste and emission reduction potential of equipment will be calculated and quantified.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 10 of 109
Based on the energy and emission reduction potential level of each equipment and refer to technical and financial criteria, recommendation for improvement measure will be identified.
All of the results of the evaluation / analysis will be discuss, present and reported to ConocoPhillips.
The reporting of energy assessment / audit wil include preliminary report, interim/draft final report and final report.
The preliminary report which covers : energy audit methodology, all data collected, all formula for calculations and preliminary findings.
The interim/draft final report which covers : energy audit methodology, all data collected, energy performance analysis result, quantity of all energy waste and emission, energy waste and emission reduction opportunities and performance monitoring system.
The final report which contains of: executive summary, evaluation result during audit / assessment, spreadsheet of energy consumption, spreadsheet of performance monitoring indicators and detail recommendation report.
2.2. METHODOLOGY OF CALCULATION
The methodology of calculation are developed in two model which includes the calculation of equipment and the calculation of process system.
The Calculation of Equipment are includes : Fired Heater; Waste Heat Boiler; Gas Turbine Generator; Residual Compressor; Air Compressor; Propane Compressor; Pumps; Air Cooler; Heat Exchanger .
The Calculation of Process system are includes : Separation system; Amine System; Dehydration System; Condensate Stabilizer System, Depropanizer System and Refrigeration System
All of the calculation are explained regarding the efficiency and performance of each equipment and process system.
2.2.1. CALCULATION OF EQUIPMENTS
2.2.1.a. Fired Heater
The biggest energy consumption in the operation of gas plant is fired heater, so the evaluation of fired heater especially the efficiency and performance are very important in this assessment.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 11 of 109
Efficiency of Fired Heater can be calculated in two ways ie. :
Direct Method
Heat Loss Method *
* Refer to Enercon Handbook
a. Direct Method :
The step of calculation are as follows,
Calculate heat duty of fired heater, k cal/hr
Calculate LHV of fuel gas (refer to lab test), kcal/hr
heat duty of fired heater
Efficiency = X 100% LHV of fuel gas
b. Heat Loss Method
Fired Heater Efficiency are calculated based on the heat loss of :
dry flue gas
H2O from combustion of H2
H2O moisture from fuel gas
H2O moisture from air
radiation and convection (refer to design)
%O2, T stack
T out
Fluid Flow
T in
Ta(ambient air temp)
FIRED HEATER
AIR
FUEL
Proc Fluid
Rad.Conv. Flue Gas
Proc Fluid
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 12 of 109
The step of calculation of heat loss method in the fired heater are as follows,
a. Measure Ta, Tstack and % O2 in flue gas
b. Calculate combustion air for stoichiometry condition
c. Calculate excess air at % O2 as measure
d. Calculate flue gas flow, kg/h (flue gas flow = fuel + comb air stoch + excess air)
e. Calculate flue gas loss, kcal/hr (flue gas loss = flue gas flow x Cp x (Tst – Ta))
LHV of Flue Gas – flue gas loss – Rad & Conv Loss**
Efficiency = X 100% LHV of Fuel Gas
** Refer to design condition
The efficiency calculated from heat loss method can be used to check the accuracy of fuel gas flow meter recorded at each fired heater. The step of calculation are as follows :
calculate heat duty of fired heater based on the different enthalpy of BFW (steam) inlet and outlet.
calculate the heat release of fired heater based on the calculated efficiency (ie. the heat duty divided by efficiency).
heat release from the calculation can be used to check the accuracy of fuel gas flow meter recorded at each fired heater
2.2.1.b. Waste Heat Boiler (WHB)
The calculation methodology of WHB is similar with fired heater, the small different is in the calculation of steam flow which is calculated based on BFW flow rate minus blow down flow rate.
Efficiency of Waste Heat Boiler also can be calculated in two ways ie. :
Direct Method
Heat Loss Method *
* Refer to Enercon Handbook
a. Direct Method
(Hst – HBFW) x ST.FlowEfficiency = X 100%
L.H.V. (Fuel Gas + Pem Gas + Acid Gas)
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 13 of 109
b. Heat Loss Method
The step of calculation are as follows,
a. Measure Ta, T stack and % O2 in flue gas
b. Calculate combustion air of acid gas, permeate gas and fuel gas for stochiometry condition
c. Calculate excess air at actual condition
d. Calculate dry flue gas flow at actual conditions, kg/hr
e. Calculate total loss, kcal/hr
Total loss = dry flue gas loss + blow down loss + rad & conv. loss
Dry flue gas = flue gas flow x Cp x (Tst – Ta)
Blow down loss = % blow down *x ST. Flow x ( H Saturate – HBFW)
*Assume % blow down (± 2%)
** Refer to design condition
LHV (Total) – Total loss
Efficiency = X 100% LHV (Total)
Ta (ambient air temp)
Flow, P, Tsteam
% O2 , Tstack
WASTE HEAT BOILER
Rad.Conv. Flue Gas
Steam
AIR
Fuel Gas
Water
Acid Gas
Permeat Gas
Blow Down
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 14 of 109
2.2.1.c. Gas Turbine Generator
GTG
AIR
FUEL
Flue GasConvRad.
BHP G ELECTR
IC
kWh x 860.1 x 3.968
Efficiency = X 100% LHV Fuel Gas x Flow F.G (Btu/h)
LHV Fuel Gas x Flow Fuel Gas
Performance = kWh
Efficiency of Gas Turbine also can be calculated by using heat loss method, which include heat loss of :
dry flue gas
H2O from combustion of H2
H2O moisture from fuel gas
H2O moisture from air
radiation and convection (refer to design)
2.2.1.d. Residual Gas Compressor
Fuel gas input
Energy loss
compressor
Mechanical work derived from pressure
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 15 of 109
Mechanical workEfficiency = Heat from fuel gas input
Z R T n Pd n-1Mechanical Work * = Q x x x ( ( ) n - 1 ) / (33,000 x 0.77)
Fouling Factor Performance are calculated based on the value of Overall heat transfer coefficient (Uo):
Uo = Q / (A Tlm)
Q : actual heat load (Q act)
A : Heat transfer Area
Sg = Specific grafity
Ht = Total Head (feet)
Fv = Correction factor related to viscousity
Pw (hp) = fv.(Sg x Ht) / 3960
T in h
T in l
T out l
T out h
Electric power input
Energy loss
m, p
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 19 of 109
Tlm : Log Mean Temperature Different
2.2.1.j. Heat Exchanger
Evaluation of heat exchanger are include the performance of heat transfer coefficient compare to design condition. If the heat transfer coefficient are lower it is could be caused by fouling or there are change in quality or quantity in the process side.
VAP. OUT VAP. OUT
VENT
LIQ. OUT VAP. IN VAP. IN CONDENSATE OUT
STEAM IN
a. Performance Calculation:
Performance = [Heat load based on actual data calculation]
[Heat load based on basic design calculation]
= Q act / Q design
b. Fouling Factor Performance are calculated based on the value of Overall heat transfer coefficient (Uo):
Uo = Q / (A Tlm)
Q : actual heat load (Q act)
A : Heat transfer Area
Tlm : Log Mean Temperature Different
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 20 of 109
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 23 of 109
Yield of Stabilization = BBL Treated Condensate (bbl/ bbl)
BBL Raw Condensate
Quantity total of condensate refer to percentage of feed inlet
Stabilizer Performance = BTU(steam) (BTU/ bbl)
BBL Treated Condensate flow
2.2.2.e. Depropanizer
DEPROPANIZER
FEED LIQUID
CONDENSATEPRODUCT
PROPANE PRODUCT
Yield of Stabilization = mole Propane product (lbmole/ lbmole)
Mole Feed HC
Deprop. Performance = kWh(Electric) (kWh/ lbmol)
Lbmole Propane product
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 24 of 109
III. ENERGY ASSESSMENT AT SUBAN GAS PLANT
3.1. GENERAL PLANT OPERATION AND PERFORMANCE
3.1.1. GENERAL PLANT OPERATION OF SUBAN GAS PLANT
Gas from well head is delivered to CGP with flow line about 1 km length to the separation unit, HP Production Separator. Because gas produced from HP Production Separator still contain CO2, H2S and H2O in high concentration, it has to be treated by CO2/H2S Removal Package and Dehydration Unit to meet the gas delivery condition requirements.
A selective Amine based on MDEA solvent shall be provided for removal of CO2 & H2S in feed gas from Gas Scrubber, to meet the sales gas specification. The system shall also include the regeneration of the MDEA solvent used to absorb H2S.
Acid Gas Removal Unit is installed with capacity 700 MMSCFD (total 4 trains) Sour Gas and should be removed CO2 / H2S until meet sales gas specification (3%). Acid gas released from Acid Gas Removal unit should be routed to The treated gas scrubber Unit with enough pressure approximately 1400 psig to ensure Acid Gas have enough pressure for next processes.
A Ethylene Glycol based gas dehydration unit shall be provided to dehydrate gas from amine unit to achieve the sales gas specification (5-7 Lb/SCF). EG Dehydration Unit is with capacity 700 MMSCFD (Total 4 trains).
The treated gas will be compressed by GTC (Gas To Compressor) with capacity 235 MMSCFD (There are 4 GTC, each of GTC has 235 MMSCFD Capacity) to increase sales gas pressure until 1280 psig. The other part of treated gas is delivered to Fuel Gas Filter as Fuel Gas for Gas Turbine Generator (GTG),Gas Turbine Compressor or as fuel gas for the CPP gas engine equipment.
The Condensate from Horizontal Separator is routed to Stabilizer Feed Drum for further separation process from carry over gas. To meet the Condensate Delivery Condition, the condensate produced is stabilized with Condensate Stabilization Units, with capacity are 44,349 Lb/hr for train 1 & 82,211 Lb/hr for train 2, and then stored in the Condensate Storage Tank with capacity is 30,000 BBL. The condensate pumps will be used to dispatch the condensate to Condensate Truck Loading.
Water collect from separation unit is automatically drained to a common header and then to be processed in the produced water treatment system.
Blow down system is used for over pressure protection or for reducing the CGP pressure either in emergency (ESD) or at the operator’s discretion in a shutdown and blocked condition. The blow down system shall be capable of relieving the entire CPP
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 25 of 109
Gas to Flare
Acid Gas
Sales Gas
Suban Gas Well Gas Seperation Unit Amine System TEG Dehydration Unit Residual Compressor
Condensate
Condensate Stabilizer
Liquid water
T T1 T2 3
4
T 5 6T
7
8 T
9
10
11
equipments from the highest possible shut-in pressure down to half times in 15 minutes. The blow down system is arranged with automatic blow down valves which is fitted at the downstream of the separation units and at the discharge of CNG Compressor to blow down through the HP Flare vent line.Localized venting of gas to atmosphere is also provided for piping and vessels via manual vents and pressure relieving devices, i.e. relief valves.
Fire water will be supplied from the fire water make up pump to a Fire Water Pond. Fire water is distributed to the fire water main ring by three fire water pumps (two pumps act as main pumps, and one as jockey) in a duty standby arrangement. Foam tank and foam pump are provided to protect the condensate storage tank. The CGP shall be fully equipped with fire and gas detection system.
All electric instruments shall be hard-wired to CGP Control Room and communicated to Programmable Logic Control (PLC) and Human Machine Interface (HMI) to monitor and control the process.
The simple process flow of Suban field is shown with block diagram in figure 2.1
Figure 3.1. Simple Block Diagram
Gas from Inlet Separator still contains CO2 and H2O in high concentration. The gas shall be treated in purification unit before the gas is delivered to Grissik Central Gas Processing plant by Pipe line system.
3.1.2. GENERAL PLANT PERFORMANCE OF SUBAN GAS PLANT
The Energy source of Suban Gas Plant actually are fuel gas from Scrubber which is consumed by GTG, GTC and Fired Heater (thermal oxidizer, amine re-boiler heater and heat medium heater).
Based on 29 September 2007, the fuel gas consumption for each equipment are shown in table below;
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 26 of 109
Table 3-1 : Fuel gas consumption
Fuel Gas to Flare
248-FQI-2131B D 0.200 MMSCFD
248-FQI-2231B D 1.000 MMSCFD
TOTAL C 1.200 MMSCFD
Fuel Gas to Heater
Thermal Oxidixer
225-H-102 D 0.314 MMSCFD
225-H-202 D 0.161 MMSCFD
0.475 MMSCFD
Amine Reb Heater
225-H-111 D 0.620 MMSCFD
225-H-211 D 0.563 MMSCFD
1.183 MMSCFD
Heat Medium Heater
257-H-101A D 0.121 MMSCFD
257-H-101B D 0.016 MMSCFD
257-H-201A D 0.152 MMSCFD
257-H-201B D 0.138 MMSCFD
C 0.428 MMSCFD
Fuel gas to GTG
247-GT-101A -
247-GT-101B -
247-GT-201A C 0.900 MMSCFD
247-GT-201B C 0.900 MMSCFD
247-GT-201C C 0.900 MMSCFD
D 2.700 MMSCFD
Fuel gas to GTC
242-KT-101 D 0.590 MMSCFD
242-KT-201 D - MMSCFD
242-KT-301 D 0.730 MMSCFD
242-KT-401 D 0.700 MMSCFD
C 1.430 MMSCFDTOTAL - 2
C 6.22 MMSCFD
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 27 of 109
TOTALC 7.42 MMSCFD
Note : D = Data ; C = Calculated
The total fuel consumption at 29 September 2007 (including fuel gas to flare) is 7.42 MMSCFD. There are two type of fuel gas used in Suban Gas Plant ie. : LP Fuel gas and HP Fuel gas. LP Fuel gas is used to fired heater and HP Fuel gas is used to GTG and GTC. The heating value (HHV) of LP Fuel gas is around 1,574 Btu/SCF and HP Fuel Gas is around 1,130 Btu/SCF.
Based on the heat balance calculation of Fired Heater, GTG and GTC, the energy picture on 29 September 2007 which are includes Heat Release, Heat Absorb, Heat Loss and CO2 emission are as follows :
TOTAL 456,657,336 123,208,143 298,360,993 689 131,598
Plant Performance :
The production rate at 29 September 2007 is 94,023 BOE which include 517 MMSCFD of sales gas (note : 1 SCF = 6000 BOE) and 7,823 barrel of condensate, and total heat released including flare gas is 456,657,336 Btu/hr. The performance of Suban Gas Plant as shown in table below :
Table 3-3 : Suban Gas Plant performance
PRODUCTION RATESales Gas = 517.20 MMSCFD
= 86,200.00 BOE
Condensate = 7,823.00 BOE
Total Prod => 94,023.00 BOE
ENERGY CONSUMEExcluding Flare 377,456,674.27Including Flare 456,657,336.12 Btu/hr
ENERGY INTENSITYExcluding Flare 4,014.51 Btu/BOEIncluding Flare 4,856.87 Btu/BOE
It shown that the energy consumption to produce one BOE (= Energy Intensity) at Suban Gas Plant is 4,014.51 Btu/BOE (Excluding Flare) or 4,856 Btu/BOE (including flare) . (Note : No design data to compare the Actual Energy Intensity).
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 29 of 109
This condition can not compare with another gas plant, because every plant have its own characteristic. The important thing is how to reduce energy consumption based on its own characteristic.
3.2 PERFORMANCE EVALUATION EACH SYSTEM
3.2.1 SEPARATION & COOLER SYSTEM
A. DESCRIPTION
Gas from manifold enters the Inlet Separator which will separate gas from the bulk liquid. The separator are designed for gas flow 160 MMSCFD (for train 1,2) and 214 MMSCFD (for train 3,4), whereas liquid flow are designed about 1973 gallon/min ( for train 1,2) and 2640 gallon/min (for train 3,4) . Production Separator will be normally operated at pressure 1188 psig and temperature 240 °F.
The Inlet Separator is a three phase separator to provide primary gas-condensate-water separation. This is to ensure that no significant carry-over/under of the respective phases.
B. PERFORMANCE
Main equipment of Separation and cooler system are include : Inlet Cooler 215-E-101A/B, 215-E-201A/B, 215-E-401A/B and 215-E-301A/B. The performance of main equipment are as follows.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 30 of 109
ELECTRIC CONSUMPTION, KW
13.13 13.13 13.13 13.13 16.41
ACTUAL FAN OPERATED 4.00 4.00 4.00 4.00 4.00
CALCULATE FAN OPERATED
3.04 3.04 3.44 3.44 4.00
The above table shows that the actual heat duty of each inlet cooler are less than design. It means that the actual cooling rate needs less energy than design. The heat duty on Train #1 and #2 are operated at 60% of design.
The heat transfer rates of exchangers are closed to the design. Based on actual condition, the performance of cooler is still in good condition.
Losses at inlet cooler are described from cooler outlet temperature. If the outlet temperature higher than the design outlet temperature, it means the cooling rate is not good. At this case, the exchangers are still in good condition.
3.2.2 AMINE SYSTEM
A. DESCRIPTION
The feed gas from Inlet Separator contains CO2 5.42% by mole and small of H2S content. A typical feed condition is 114 oF and 1163 psia; The products specifications is designed for the CO2 content is 3.4 % by mole respectively. The acid gas removal package uses activated methyl-di ethanolamine (MDEA) to remove the acid gases (H2S & CO2) by means of counter-current mass transfer in an Amine Contactor unit.
The gas from the inlet separator will be fed to the Acid Gas Removal Package. As the inlet gas is a saturated gas stream, there is a possibility of hydrocarbon and water condensation prior to inlet of the amine contactor. To minimise liquid carry-over to the system, a Horizontal filter unit is provided. The horizontal filter unit will have level control drain-off valves, both on the upstream and downstream of the filter element, whereby the liquid is sent to the flare system for disposal.
The liquid free gas from the Horizontal filter is then fed to the Amine Contactor, whereby the gas is in contact with lean aqueous MDEA solution (amine). The enhanced solubility of the acid gas in lean amine would soluble the acid gas component, thus stripping it of H2S and CO2.
The rich amine from the contactors flows to the rich amine flash drums. The rich amine flows under level/flow control through the lean/rich amine exchangers where it is heated to about 206 oF by heat exchange with the hot lean amine from the two regenerators. The rich amine feeds the regenerator above the stripping section which contains stainless steel structured packing. CO2 and H2S are stripped from the rich solution by heat produced in the regenerator re-boilers.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 31 of 109
B. PERFORMANCE
Main equipment of Amine System are includes :
Amine Heat Medium Heater (225-H-111; 225-H-211); Amine Reg. Reboiler (225-E-102 A/B, 225-E-202 A/B); Treated Gas Cooler (225-E-105, 225-E -205, 225-E -305, 225-E -405), Amine Charge Pump (225-P-102A/B/C), Amine Booster Pump (225-P-101A/B/C) and Amine Heat Medium Circ. Pump (225-P-111A/B/C, 211A/B/C).
The performance of main equipment of Amine System are as follows.
Amine Heat Medium Heater :
Table 3-5 : Performance of Amine Heat Medium Heater
225-H-111 225-H-211 DESIGN
FUEL,
Flow, MMSCFD 0.62 0.56 1.13
FLUE GAS
T out, F 404.60 361.40 412.00
O2, % 6.50 9.20 3.00
Excess Air, % 41.00 83.15 15.27
HOT WATER
lb/hr 2,285,233 2,004,973 2,910,000
T in, F 257 257 285
T out, F 270 270 305
P in, Psi 280 280 285
P out, Psi 270 270 274
PERFORMANCE
Heat absorption (LHV), MMBtu/hr
31.81 28.70 57.98
Heat absorption (HHV), MMBtu/hr
32.20 28.94 58.12
Efficiency (LHV), % 85.80 84.87 89.11
Efficiency (HHV), % 78.95 78.06 81.18
CO2 EMISSION
CO2 Emission from fuel gas, lb/hr
5,730 5,203 10,609
The heat duty of Amine H-M Heater was only 55 % and 50 % load compare to design condition.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 32 of 109
The efficiency by using heat loss method are calculated based on the flue gas composition and temperature measurement by using portable analyzer and thermometer. No meter of temperature and O2 analyzer in flue gas line.
The flue gas temperature at actual condition is lower than design condition but the excess air is too high and the operating load is too low. The efficiency at actual condition is around 85 % compare to design condition which is 89 %. This efficiency is low compare to design condition, it is caused by higher excess air and lower operating load.
Amine Regenerator Reboiler:
Table 3-6 : Performance of Amine Regenerator Reboiler
The above table shows that the heat duty operated closed to the design. The difference between actual heat duty and design only 10%. The operated temperature higher than design value.
The performance of heat exchanger can be evaluated from the value of overall heat transfer rate (U). The U at actual condition is 85 BTU/(Hr/Ft2.F) and 93 BTU/(Hr/Ft2.F) compare to design value which is 101 BTU/(Hr/Ft2.F..
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 33 of 109
Treated Gas Cooler :
Table 3-7 : Performance of Treated Gas Cooler
225-E-105 225-E-205 DESIGN
WATER+ACID GAS
Pressure,psig 1206 1202 1162
Temp inlet, F 147.90 152.00 139.80
Temp outlet, F 120.70 125.70 120.00
Flowrateof Acid gas, MMSCFD 138.92 119.56 151.80
AIR COOLANT
Temp inlet, F 92.00 92.00 95.00
Temp outlet, F 110.00 112.00 118.40
Delta T LMTD 33.09 36.76 26.50
HEAT DUTY, Btu/hr 4,622,698 3,873,942 4,300,000
ELECTRIC CONSUMPTION, KW 56.79 55.61 59.68
ACTUAL FAN OPERATED 2 2 2
CALCULATE FAN OPERATED 2.1 1.8 2.0
HEAT TRANSFER RATE, BTU/HR.FT2.F
3.9 3.0 5.2
225-E-305 225-E-405 DESIGN
WATER+ACID GAS
Pressure,psig 1206 OFF 1162
Temp inlet, F 147.90 OFF 139.80
Temp outlet, F 126.50 OFF 120.00
Flowrateof Acid gas, MMSCFD 204.82 OFF 203.40
AIR COOLANT
Temp inlet, F 92.00 OFF 95.00
Temp outlet, F 110.00 OFF 118.40
Delta T LMTD 33.09 OFF 26.5/23
HEAT DUTY, Btu/hr 5,346,317 OFF 5,810,000
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 34 of 109
ELECTRIC CONSUMPTION, KW 59.15 OFF 59.68
ACTUAL FAN OPERATED 2 OFF 2
CALCULATE FAN OPERATED 1.9 OFF 2.0
HEAT TRANSFER RATE, BTU/HR.FT2.F
4.5 OFF 5.4
The above table shows that the actual heat duty closed to the design. The difference between actual and design only +/- 10%. Electric power consumption for motor fan drivers also close to design with deviance not more than 7%. The fan running at actual condition also same as design, each exchanger have 2 (two) fans running. This indicates that the process is in good condition. Temperatures of gas outlet from these exchangers all meet the specification process condition, 120.7 and 125.7 deg F for train#1 and #2, and 126 deg F for train#3 refer to the design is 120 and 203.4 deg F respectively.
The performance of heat exchanger can be evaluated from the value of overall heat transfer rate (U). The U at operating condition give value of 3.9 and 3.0 BTU/(Hr/Ft2.F) for train#1 and train#2 and 4.5 BTU/(Hr/Ft2.F) for train#3. The design value is 5.2 and 5.4 BTU/(Hr/Ft2.F).
Regenerator Reflux Condenser :
Table 3-8 : Performance of Regenerator Reflux Condenser
225-E-101 225-E-201 DESIGN
WATER+ACID GAS
Pressure,psig 11.9 12 26.9
Temp inlet, F 194.40 226.4 205.00
Temp outlet, F 135.60 120.5 120.00
Flowrateof Acid gas, MMSCFD 5.50 7.3 8.76
AIR COOLANT
Temp inlet, F 92.00 92 92.00
Temp outlet, F 140.00 145 144.00
Delta T LMTD 48.80 50.41 48.60
HEAT DUTY, Btu/hr 9,259,749 13,234,590 16,824,662
ELECTRIC CONSUMPTION, KW 17.67 40.04 44.00
ACTUAL FAN OPERATED 2 4 4
CALCULATE FAN OPERATED 2.2 3.1 4.0
HEAT TRANSFER RATE, 1.9 2.7 3.0
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 35 of 109
BTU/HR.FT2.F
The above table shows that regenerator reflux condenser is operated at 55% load for 225-E-101 and 78% load for 225-E-201 compare to design condition. This caused by the flow rate of acid gas are 62% and 83% compare to design condition.
Actual fan operated for the cooler 225-E-101 is 2 fans running, but the calculated fan should be operated is 3 fans (2.2). This causes the temperature of the outlet of cooler is higher than the design. Design value state the temperature is 120 deg F, but this cooler operated at 135 deg F. The outlet temperature of cooler 225-E-201 is meet to the design value.
The U (overall heat transfer rate) at actual condition is 1.9 and 2.7 BTU/(Hr/Ft2.F) for 225-E-101 and 225-E-201 compare to design is 3.0 BTU/(Hr/Ft2.F).
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 36 of 109
The above table shows that the actual heat duty of 225-E-103 and 225-E-203 are rated at 50% compare to the design. This caused by the flow rate of lean amine only about 50% - 60% from design capacity.
The flow rate of lean amine affects to the power required of fan cooler driver.
The actual operated fans for 225-E-103 and 225-E-203 are 2 fans compare to 4 fans for design. This condition affects the performance of cooler, especially with heat transfer rate.
The value of U (overall heat transfer rate) at actual condition is 1.6 BTU/(Hr/Ft2.F) for 225-E-103 and 1.5 for 225-E-203 compare to design 1.8 BTU/(Hr/Ft2.. This difference indicated that the performance of coolers are still have good performance.
Rich-Lean Amine Exchanger :
Table 3-10 : Performance of Rich-Lean Amine Exchanger
225-E-104A-B 225-E-204A-B DESIGN
RICH AMINE SIDE
Pressure, psig 90.00 100.00 100.00
Temp inlet, F 105.00 105.00 138.20
Temp outlet, F 190.00 210.00 210.20
Flowrate of Rich Amine, USGPM 458.20 483.40 1,138.90
The flow rate of fluid in Rich-lean amine exchanger is about 40% from design capacity. This will affect the heat load for these exchangers at 40% for 225-E-103 and 50% for 225-E-203.
LMTD between hot fluid and cold fluid are higher than the design specification. This case will affect the heat transfer rate for these exchangers. The temperature inlet of Rich amine is lower compare to the design value. This is indicate the amine contacting process in the field running on lower temperature than the design specification.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 37 of 109
Lean Amine Charge Pump :
Table 3-11 : Performance of Lean Amine Charge Pump
DESCRIPTION UNIT 225-P-102A 225-P-102B 225-P-102C Design
value value value value
specific gravity 1.05 1.05 OFF 1.00
Temperature F 137.00 137.00 OFF 125.00
suction pressure psia 111.00 111.00 OFF N/A
discharge pressure psia 1550.00 1550.00 OFF N/A
flow GPM 265.00 265.00 OFF 1165.00
Total head ft 3180.05 3180.05 OFF 2550.00
Electric motor power HP 575.00 575.00 OFF 1000.00
Mechanical work HP 227.34 227.34 OFF 766.69
Efficiency % 39.54 39.54 OFF 76.67
Two Amine Charge pumps were running at 265 GPM each, and had efficiency of 39.54%. This efficiency is quite low compare with 76.67% efficiency at design condition. This is due to very low flow rate they handled. The 76.67% efficiency can be achieved at 1165 GPM.
The sum of fluid flow rate for each pump (530 GPM) is still far below the design flow rate for one pump. Higher efficiency could be achieved should the fluid flowing is handled by one pump only.
Amine Reboiler H/M Circulation Pump :
Table 3-12 : Performance of Amine Reboiler H/M Circulation Pump
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 38 of 109
Electric motor power
HP 168.00 168.00 152.00 152.00 190.00
Mechanical work HP 117.31 115.99 101.40 101.40 141.41
KW 87.52 86.53 75.64 75.64 105.49
Efficiency % 69.83 69.04 66.71 66.71 74.43
Two of the three pumps were working to feed Amine re-boiler medium heater, so four pumps worked to serve two Amine re-boiler medium heater. Each circ.-pump (P-111 A/B) worked at 2211 and 2186 GPM, with 69% efficiency and P-211 A/B worked at 1911 GPM, with 66% efficiency. All pumps are operated close to design efficiency.
Lean Amine Booster Pump :
Table 3-13 : Performance of Lean Amine Booster Pump
DESCRIPTION UNIT 225-P-101A 225-P-101B Design
specific gravity 1.05 1.05 1.00
Temperature F 137.00 137.00 125.00
suction pressure psia 16.70 16.70 N/A
discharge pressure psia 131.70 131.70 N/A
flow GPM 225.00 225.00 1430.00
Total head ft 115.00 115.00 244.00
Electric motor power HP 70.00 70.00 122.00
Mechanical work HP 15.43 15.43 90.05
Efficiency % 22.04 22.04 73.81
The worst case was found at Amine booster pumps, the efficiency of P-101-A/B is only 22 %. The production process utilized two of the three pumps to support Lean amine charge pumps. Each of these booster pumps pumping out fluid at 225 GPM.
The sum of fluid flow rate (450 GPM) is still far below the design flow rate for one pump. Higher efficiency could be achieved should the fluid flowing is handled by one pump only.
3.2.3 CONDENSATE STABILIZING SYSTEM
A. DESCRIPTION
Hydrocarbon liquid from inlet separator and LTS are sent to the stabilizer feed drum. Gas from the feed drum is sent under back pressure control to the low pressure fuel gas system.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 39 of 109
The hydrocarbon liquid from the feed drum is fed under level control to the top tray of the condensate stabilizer. The stabiliser reboiler is a kettle type shell and tube exchanger utilizing hot water from Medium Heater at operation.
The condensate product from the stabilizer is sent via the HC condensate cooler bundle in the refrigerant condenser air cooled exchanger frame and a kettle type hydrocarbon condenstae cooler by propane refrigerant, gas blanketed, condensate storage tank.
B. PERFORMANCE
Main equipment of Condensate Stabilizing system are includes : Heat medium heater 257-H-101A/B, 257-H-201A/B; Stabilizer Re-boiler 235-E-101A/B, 235-E-201A/B; Condensate Cooler 235-E-102, 235-E-102
Heat Medium Heater :
Table 3-14 : Performance of Heat Medium Heater
257-H-101A DESIGN
FUEL,
Flow, MMSCFD 0.12 0.10
FLUE GAS
T out, F 511.20 629.00
O2, % 13.90 3.00
Excess Air, % 179.07 15.27
HOT WATER
, lb/hr 106,647.53 110,000.00
T in, F 310.00 316.60
T out, F 350.00 360.00
P in, Psi N/A 200.00
P out, Psi N/A 200.00
PERFORMANCE
Heat absorption (LHV), MMBtu/hr 5.34 4.76
Heat absorption (HHV), MMBtu/hr
5.45 4.76
Efficiency (LHV), % 73.57 83.00
Efficiency (HHV), % 67.94 75.49
CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 1,122.86 937.53
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 40 of 109
Table 3-14 : Performance of Heat Medium Heater
257-H-201A 257-H-201B DESIGN
FUEL,
Flow, MMSCFD 0.15 0.14 0.17
FLUE GAS
T out, F 568.80 525.60 629.00
O2, % 8.50 10.20 3.00
Excess Air, % 62.20 86.38 15.27
HOT WATER
, lb/hr 228,820.95 180,110.31 164,900.00
T in, F 300.00 300.00 316.6
T out, F 330.00 330.00 360
P in, Psi N/A 225.00 227.5
P out, Psi N/A 210.00 200
PERFORMANCE
Heat absorption (LHV), MMBtu/hr 7.38 6.66 7.94
Heat absorption (HHV), MMBtu/hr 7.48 6.76 8.00
Efficiency (LHV), % 81.18 80.73 84.00
Efficiency (HHV), % 74.76 74.36 76.77
CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 1,404.86 1,275.47 1,552.85
The above table shows that H-101 A, H-201 A and H-201-B are operated close to design condition. The efficiency by using heat loss method are calculated based on the fuel gas heating value, flue gas composition and temperature measurement by using flue gas analyzer.
Flue gas temperature is lower than design condition but the excess air is very high. Calculated Efficiency of 257-101-A is 73 % compare to design is 84 % and the efficiency of 257-201-A/B is around 81 % compare to design is 84 %. The lower efficiency is caused by higher excess air of the heater.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 41 of 109
Temp Condensate to reboiler, F 278.00 278.00 298.00
Delta T LMTD 34.78 32.93 45.36
HEAT DUTY, Btu/hr 2,214,754 2,053,347 3,000,000
HEAT TRANSFER RATE, (BTU/Hr.Ft2.F) 39.14 38.32 40.65
The above table shows that actual condition of heat duty of 235-E-201 and 235-E-101 is lower than design. The reboiler of 235-E-201 have capacity higher than 235-E-101 but the heat transfer rate are close to design.
Condensate Cooler :
Table 3-16 : Performance Condensate Cooler
235-E-102 235-E-202 DESIGN
CONDENSATE
Temp inlet, F 288.00 288 304.30
Temp outlet, F 106.60 106.5 120.00
Flowrate, GPM 101.89 193.4 287
AIR COOLANT:
Temp inlet, F 92.00 92 95.00
Temp outlet, F 136.00 136 139.90
Delta T LMTD 58.65 58.52 74.00
HEAT DUTY, Btu/hr 1,976,054 3,752,578 7,841,737
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 42 of 109
HEAT TRANSFER RATE, BTU/HR.FT2.F
1.11 2.12 2.36
ELECTRIC CONSUMPTION **), KW
8.83 9.42 11.00
The above table shows that the condensate cooler have heat duty only 25% for 235-E-102 and 48% for 235-E-202 refer to the design value. This caused by the flow rate of condensate, and LMTD.
The flow rate for 235-E-102 is 35% and 235-E-202 is only 67% refer to the design. LMTD value for cooler 235-E-102 and 235-E-202 are 80% from LMTD design. This affect the value of heat load (Q) of coolers, because the heat load is straight forward with condensate flow rate and LMTD.
The overall heat transfer rate (U) at actual condition is 1.11 BTU/(Hr/Ft2.F) for 235-E-102 and 2.12 BTU/(Hr/Ft2.F for 235-E-202 compare to the design is 2.36BTU/(Hr/Ft2.F).
3.2.4 DEW POINT CONTROL AND REFRIGERATION SYSTEM
A. DESCRIPTION
The propane refrigerant gas from gas chiller via suction scrubber enter the 1st stage propane compressor. The propane refrigerant gas from the 1st compressor discharge and from the economizer goes to the propane compressor 2nd stage than the discharge of 2nd stage goes to the condenser cooler and enter to the accumulator. Propane refrigerant from the accumulator goes to the economizer (flushing).
Propane gas from the economizer enter the suction of 2nd stage compressor and the propane refrigerant enter the gas chiller via propane subcooler. The design flowrate of the 1st stage propane compressor is 38,200 lbs/hr and the 2nd stage of propane compressor is 52,800 lbs/hr.
There are 3 propane compressor driven by electric motor 1300 KW each and via refrigerant header supply refrigerant for 4 gas chillers (1 gas chiller for 1 train). At the actual condition only 2 compressor are in operation.
B. PERFORMANCE
Main equipment at Refrigeration system are includes propane condenser, propane compressor and gas chiller.
Propane Condenser :
Table – 3.17 : Performance of Propane Condenser
230-E-104 DESIGN
PROPANE :
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 43 of 109
Pressure, psig 250 265
Temp inlet, F 140.00 180.00
Temp outlet, F 119.00 121.00
Flowrate, MMSCFD (gas) 30.00 32.90
AIR COOLANT:
Temp inlet, F 92.00 95.00
Temp outlet *), F 112.00 117.50
Delta T LMTD 27.50 26.30
HEAT DUTY, Btu/hr 19,151,470 25,387,806
ELECTRIC CONSUMPTION **), KW 17.67 22.00
HEAT TRANSFER RATE, BTU/HR.FT2.F 2.59 3.29
The above table shows that actual condition of heat duty of 230-E-104 is 75% compare to design. The heat duty impact on the power required for fan driver which is 80% electric consumption respectively.
The U value (overall heat transfer rate) at actual condition is 2.59 BTU/(Hr/Ft2.F) and 3.29 BTU/(Hr/Ft2.F for the design value.
Entirely, the performance of propane condenser is operated at good condition.
Propane Compressor:
Table – 3.18 : Performance of Propane Compressor
UNITS DESIGN K 101 A K 101 C
PROPANE FLOW ST. 1 38,160.00 30,669.25(calculated)
25,861.64 (calculated)
PROPANE FLOW ST. 2 52,800.00 42,446.24(calculated)
35,792.51(calculated)
ABSL SUCTION PRESSURE ST.1 24.50 24.00 24.00
ABL.DISCHARGE PRESS ST 1 101.00 100.00 100.00
ABSL DICHARGE PRESSURE ST. 2 265.00 260.00 260.00
TOTAL POWER REQUIRED 1,214.78 966.64 815.11
ACTUAL POWER 1,300.00 1,110.00 936.00
COP 1.89
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 44 of 109
The above table shows that the propane compressor operated at 70-80 % load. The calculated propane flow of stage-1 K-101 A and K-101 C are 30,669 lb/hr and 25,861 lb/hr with the actual power are 1110 KW and 936 KW . The design propane flow of stage-1 is 38,160 lb/hr with the power is 1,300 KW. It means that the propane compressor is still operated at normal conditions.
The design COP of the propane compressor is 1.89. COP at actual condition can not be calculated accurately because no meter for propane flow.
Gas Chiller:
Table – 3.19 : Performance of gas chiller
UNITS DESIGN GAS CHILLER (230-E-
102/201/302/402)
GAS INTAKE TEMP.AT EVAP. DEG F 1.00 16.00
GAS OUTPUT TEMP.AT EVAP. DEG F (10.00) 5.00
SALES GAS FLOW MMCFD 300.00 533.00
CONDENSATE FLOW BBL/D 4,000.00 3,000.00
HEAT RELEASE MMBtu/hr 16.52 11.80
TOTAL POWER KW 2,600.00 1,930.00
C.O.P 1.86 1.79
The above table shows the cooling load of gas chiller is 71 % load and two of propane compressor are operated to handle the refrigeration system.
Performance of each gas chiller can not be calculated, because two propane compressors serve four gas chillers simultaneously. However total performance still can be calculated.
The operating condition of four gas chiller almost similar (T gas inlet = 16 F , T out gas = 5 F). Total COP of gas chiller is 1.79. It’s still close to design condition.
3.2.5 GAS COMPRESSION
A. DESCRIPTION
The pressure of treated gas after Amine System and Refrigeration System is decrease lower than 1000 psig. To meet the pressure requirement of sales gas it needs to compress sales gas by using Residual Gas Compressor. There are 4 gas compressor 2 x 235 MMSCFD and 2 x 300 MMSCFD driven by gas turbine generator. At the actual condition only 3 GTC in operation and 1 GTC standby
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 45 of 109
B. PERFORMANCE
Main equipment at Gas Compression System are 242-K-101, 242-K-102, 242-K-301 and 242-K-401,
ENERGY INTENSITY Btu/HP 7,936.81 9,896.28 9,940.95
DESIGN 242-K-101 242-K-201
SALES GAS FLOW ( Q ) MMSCFD 10,905.10 150.00 OFF
SUCTION PRESSURE PSIA 955.00 910.00
DISCHARGE PRESSURE PSIA 1,215.00 1,110.00
FUEL CONSUMPTION MMBtu 40.92 20.19
POWE REQUIRE (POLYTROPIC) HP 4,653.97 1,940.43
ENERGY INTENSITY Btu/HP 8,792.49 10,406.28
The above table shows that the compressor are operated at 80 % load compare to design condition.
The Energy Intensity (Btu/HP) of 242-K-101, 242-K-301 and 242-K-401 are higher compare to design value. This condition is caused by the lower operating load of compressors. To know the performance of compressor, it should be compare with design performance of gas turbine compressor (see table below).
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 46 of 109
Gas Turbine :
Table – 3.21 : Performance of Gas Turbine Compressor
29-Sep-07 DESIGN
242-KT-101 242-KT-201 242-KT-101 /201
A TURBINE
Fuel gas :
flow, MMSCFD 0.59 OFF 1.02
Flue gas :
Temperature, C 1,213 OFF 1,160
O2, % 14 OFF 14
Excess Air, % 191 OFF 185
Eff, % 19 OFF 25
Btu/HP 13,256 OFF 10,115
B COMPRESSOR
Power Required, KW 1,447 OFF 3,471
, HP 1,940 OFF 4,653
29-Sep-07 DESIGN
242-KT-301 242-KT-401 242-KT-301/ 401
A TURBINE
Fuel gas :
flow, MMSCFD 0.73 0.70 1.05
Flue gas :
Temperature, C 1,261 1,237 1,175
O2, % 14 14 14
Excess Air, % 168 174 174
Eff, % 23 23 27
Btu/HP 10,946 11,225 9,401
B COMPRESSOR
Power Required, KW 2,115 1,978 3,409
, HP 2,835 2,651 4,570
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 47 of 109
In the daily operation, the gas turbines efficiency is around 23 %, these efficiency is less than the design condition (27%). Based on the design performance below, the performance of gas turbine at low load are close to design figure.
POWER, HP 5,000.00 4,000.00 3,000.00 2,000.00 1,000.00
BTU/KWH 10,100.00 10,700.00 11,600.00 13,200.00
17,000.00
3.2.6 GAS TURBINE GENERATOR
A. DESCRIPTION
Electrical power Generator driven by Gas turbine generator, with the gas supplied from HP (high pressure) fuel gas system. There are 2 GTGs each 1173 KW from Suban phase-1 and 3 GTGs each 5820 KW from Suban phase-2.
The Generator specification are 5820 KW of power, 6600 volt, freq 50 Hz, cos Q 0.85. The large motors (lean amine charge pump, Amne reboiler HM Pump, propane compressor) are supplied by 6600 volt and the other motors using 400 volts.
B. PERFORMANCE
The main equipment of gas turbine generator are 247-GTG-101A/B and 247-GTG-201A/B/C
The performance of GTG are as follow :
Table – 3.22 : Performance of GTG
29-Sep-07 DESIGN
247-GT-201A 247-GT-201B
247-GT-201C
247-GT-201A
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 48 of 109
TURBINE
Fuel gas :
flow, MMSCFD 0.90 0.9 0.90 1.62
Flue gas :
Temperature, F 916 921 925 946
O2, % 16 16 16 15
Excess Air, % 312 309 308 243
Turbine Eff, % 18.04 18.04 18.01 30
Btu/kwh 16,925 16,926 16,950 11,336
CO2 emission :
Flow, lb/hr 5,611 5,611 5,611 4,446
GENERATOR
Power Output, KW 2,146 2,102 2,178 5,821
PF 0.83 0.83 0.83 0.84
Voltage, V 6,600 6,600 6,600 6,600
Frequency, Hz 50 50 50 50
GTGs are operated less than 40 % load each, total load is around 6,426 KW. This load actually can be handle by two GTGs with 55 % load each. If any disturbanceoccurs, the load shading system will shut off un-priority load, so system black out can be avoided. The low load of GTG caused low efficiency of gas turbine.
The stack temperature of GTG are close to design condition but the calculated efficiency is only 18 % compare to design which is 30 %. The decreasing efficiency is caused by lower operating load which will increased radiation and convection loss.
Compare to the design performance of gas turbine generator (table below) , the performance GTG at low load are still in good condition
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 49 of 109
3.2.7 AIR COMPRESSOR
A. DESCRIPTION
Instrument and utility air are supplied by the 1x340 scfm and 1x140 scfm screw type compressor. The compressed air is filtered and then dried in heatless adsorption type dries which are on automatic regeneration cycles. The instrument air compressor packages are provided with local electronic control panels. The instrument air receiver is normally operated between 110 and 120 psig.
B. PERFORMANCE
There are four compressors Atlas Copco GA 37 x 2 and GA 75 x 2 with design capacity is 960 SCFM, the duty of each equipment are as follows,
The performance of air compressor are as follows :
Table 3-24 : Performance of Air Compressor
251-A-101A (ATLAS COPCO GA 75)
DESIGN ACTUAL
POWER 72.60 45.93
COMPRESS AIR FLOW 340.00 266.66
ACTUAL PERFORMANCE 0.20 0.20
251-A-101 B (ATLAS COPCO GA 37)
DESIGN ACTUAL
POWER 44.00 28.27
COMPRESS AIR FLOW 140.00 129.90
ACTUAL PERFORMANCE 0.33 0.25
The above table shows that the compressor is operated at low load. Actual power of 251-A-101 A is 45.93 KW compare to design 72.6 KW and 251-A-101 B is 28.27 KW compare to design 44 KW.
Actual performance of air compressor calculated by :
(Actual power / Qs x ((Pd/Ps)^0.2857 – 1)) Note : Qs = air flow
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 50 of 109
225-P-102A/B/CLean Amine Charge pump A/B/C
1130 HP x3
225-EM-101/201 A/B/C/DRegenerator reflux condenser fan
11 KW x8
225-PM-105Amine transfer pump
14.7 HP
225-PM-104Amine sump pump
14.7 HP
215-EM-301/401/A/B 1-2Inlet cooler fan
22 KW x8
225-P-111A/B/CAmine reboiler H/M circ pump A/B/C
185 HP x3
225-P-211A/B/CAmine reboiler H/M circ pump A/B/C
185 HP x3
225-EM-103A/B/C/DLean Amine cooler fan
19 KW x4
225-EM-105/205/305/405 ATreated gas cooler fan
19 KW x4
225-P-102A/B/CLean Amine booster pump A/B/C
112 HP x3
6.6 KV
400 V
225-EM-203A/B/C/DLean Amine cooler fan
19 KW x4
225-EM-105/205/305/405 BTreated gas cooler fan
19 KW x4
400 V
229-PM-302/402/A/BGlycol Injection pump
26.8 HP
400 V
3.2.8 ELECTRICAL MAP SUBAN GAS PLANT
Electrical map is derived from single line diagram, and intend to get a closer and clear point of view to one that need brief description on power consumption at each process. This map is made simple as possible so, it doesn't show how the electric system is distributed. Emphasize is given to voltage, and power required for each equipment. Note that the power mentioned below is the power in normal design condition.
A. Inlet Gas System
B. Amine System
C. Dehydration system
225-PM-103A/BRegenerator reflux pump A/B
3.73 HP x2
225-PM-203A/BRegenerator reflux pump A/B
3.73 HP x2
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 51 of 109
230-EM-104 A/B/C/D 1-2Propane condenser fan A-D
22 KW x8
230-K-101-EM1-6L.O. cooler fan propane compr. A/B/C
7.15 KW x6
230-K-101-PM 1-3L.O. pump for propane compr. A/B/C
6.7 HP x3
230-PM-101Depropaniser overhead feed pump
7.1 HP
230-EM-107A/BDepropaniser overhead condenser fan
7.5 KW x2
230-PM-102Depropaniser reflux pump
1.7 HP
230-H-106Depropaniser reboiler heater
106 HP
235-PM-102D/ECondensate shipping pump
40 HP x2
235-EM-202A/BCondensate cooler fan
11 KW x2
235-KM-201Vapoor recovery compr.
29.5 HP
242-EM-301/401 A-DResidue gas compr. After cooler
15 KW x8
251-KM-201 A/BAir compressor A/B
120 HP x2
252-PM-101 C-GWell water lift pump
5.36 HP x5
400 V
6.6 KV
400 V
400 V
400 V
252-PM-105 A/BAmine makeup water pump A/B
15 HP x2
251-A-201N2 generation
30 KW
252-PM-104 A/BPortable water pump
7.4 HP x2
D. Propane Compressor System
E. Depropanizer and Condensate Stabilization System
F. Residue Gas Compressor System
G. Air Compressor, and Utility
230-KM-101 A/B/CPropane compressor A/B/C
1306 KW x3
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 52 of 109
248-P-101/201 A/BFlare KO drum A
3 HP x8
258-PM-202 A/BProduced water injection pump A/B
60 HP x2
400 V
257-PM-201 A/B/CHeat medium circ. pump A/B/C
49.5 HP x3
H. Flare, and Water handling
3.3 FINDINGS AND RECOMENDATION
1. Instrumentation and Metering
Based on the site survey founded that many metering and instrument are not work properly. Findings and recommendations of metering and instrumentation at Suban Gas Plant are as follows :
Equipments Findings Recommendations
1. Amine Reb H-M Heater
There are inaccurate temperature indicator of circulation Hot Water
Combustion analyzer in each HM Heater not work properly
the oxygen analyzer should be repaired
Need to calibrate meter of hot water temperature indicator
2 H-M Heater No Oxygen analyzer
The calculated efficiency of HM Heater from direct method difference with heat loss method. This discrepancy maybe caused by lack ofaccuracy of Temperature indicator and hot water circulation flow meter.
Need to install oxygen analyzer in order to monitor the performance of this equipment
Need to calibrate temperature indicator and hot water circulation flow meter
3 Gas Turbine Generator
There is no flow meter of fuel gas in each GTG.
Some indicator/sensor of GTGs have no link to DCS in CCR
Need to install fuel gas flow meter and link to DCS
4 Gas Turbine Compressor
lack of accuracy fuel meter
Need to calibrate fuel flow meter and
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 53 of 109
link to DCS
5 Propane compressor
No power record for propane compressor
Need to implement continues record for propane compressor to evaluate COP
6 Chiller Temperature inlet and outlet gas chiller are inaccurate
need to install temperature indicator inlet and outlet gas chiller for performance evaluation and link to DCS
7 Air compressor
No power meter for air compressor
need to install meter of air compressor for performance evaluation and link to DCS
8 Pumps No power meter for lean amine booster pump
need to install meter of lean amine booster pump for performance evaluation and link to DCS
9 Heat Exchanger
No temperature and pressure indicator at gas-gas exchanger
Temperature indicator of steam at amine Re-boiler are not accurate
Need to install temperature indicator at gas-gas exchanger for performance monitoring
Need to calibrate the steam temperature indicators at amine re-boiler
10 Amine system Temperature indicator between inlet and outlet are not accurate
Recalibration of temperature indicator
11 Electric Distribution
No continue recording for electrical distribution
Need to record electrical distribution (6000 V line) at daily records
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 54 of 109
2. Heater
Based on the calculation bellows are the efficiency, heat absorb and CO2 emission of fired heater at Suban Gas Plant
EFFICIENCY HEAT DUTY CO2 EMISSION
% MMBtu/hr Lb/hr
AMINE REB H-M HEATER
DESIGN 89.11 57.98 10,609.42
225-H-111 85.80 31.81 5,730.36
225-H-211 84.87 28.70 5,203.54
HEAT MEDIUM HEATER
DESIGN 257 H-101A/B 84.00 4.37 712.53
257-H-101A 73.60 5.35 1,122.86
257-H-101B OFF OFF OFF
DESIGN 257 H-201A/B 84.00 7.94 1,552.85
257-H-201A 81.18 7.38 1,404.86
257-H-201B 80.73 6.66 1,275.47
Finding :
The above tables shows that :
The heat duty of Amine H-M Heater is only 50 % and 44 % load compare to design condition. The Gas Plant are operated at 517 MMSCFD of sales gas or 74 % load compare to design condition. This condition means that the design of fired heater is too large.
Amine H-M Heater is operated at high excess air (44 % and 71 % ) compare to the design figure which is 15 % excess air. This excess air will impact lower efficiency of H-M Heater
HM Heater is operated at high excess air (62 %, 86 % and 179 % ) compare to the design figure which is 15 % excess air. This excess air will impact lower efficiency of Heater (Calculated Efficiency from heat loss method will be around 70 % compare to design is 84 %)
Recommendation :
Design Amine H-M Heater is too large, so the heater can be handle for revamping until 125 % Amine Capacity.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 55 of 109
Amine H-M Heater is the main energy consuming equipment in the amine system, so its performance should be monitored daily. Hence, it needs temperature and O2 meters at flue gas line to support the monitoring activity.
Amine H-M Heater should be operated close to the design excess air (15%) to achieve better efficiency,
HM Heater should be operated close to the design excess air (15%) to achieve better efficiency
5. Gas turbine generator
Based on the calculation, bellows are the efficiency, heat rate, BHP and CO2 emission of GTG at Suban Gas Plant:
GAS TURBINE GENERATOR EFFICIENCY HEAT RATE BHP CO2 EMISSION
% BTU/KWH KW Lb/hr
DESIGN 30.43 11,336.00 6,063.54 9,803.22
247-GT-201A 18.04 16,924.65 2,235.42 5,610.65
247-GT-201B 18.06 16,908.92 2,189.58 5,610.65
247-GT-201C 18.01 16,949.55 2,268.75 5,610.65
Finding :
Three GTGs load are low in daily operation ( less then 40%),.the average efficiency is around 18 % (design = 30 %)
Heat rate of three GTGs are around 16.9 MBtu/KWH compare to design 11.3 MBtu/KWH
Recommendation :
To achieve better efficiency, GTGs should be operated at more then 50 % load (two GTGs in operation)
Load shading should be operated properly to sustain two GTGs in operation
6. Gas turbine Compressor
Power require and energy intensity of residue gas compressor are as follows :
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 56 of 109
Turbine efficiency, heat rate and CO2 emission are as follows :
TURBINE Turbine Eff, Heat Rate CO2 emission :
% Btu/BHP lb/hr
DESIGN 242-KT-301 29.13 7,878.86 5,341.69
242-KT-301 23.53 9,746.77 1,838.04
242-KT-401 23.35 9,942.20 1,753.20
DESIGN 242-KT-101 25.89 8,793.54 6,070.11
242-KT-101 21.78 10,737.29 1,385.60
242-KT-102 OFF OFF OFF
Finding :
Max capacity of KT-401 and KT-301 are 235 MMSCFD each, with suction press 950 psi and discharge 1280 psi
Max capacity of KT-201 and KT-101 are 300 MMSCFD each, with suction press 950 psi and discharge 1200 psi
Actual turbine efficiency of KT-401 and KT-301 is around 23 % and KT-101 is 22 % compare to design efficiency of KT-401 and KT-301 are 29 % and KT-101 is 26 %
Based on the design flow rate, 3 GTCs can handle 770 MMSCF
7. Propane Compressor
Performance of propane compressor are as follows :
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 57 of 109
PROP COMPRESSOR POWER REQUIRED, KW
ACTUAL POWER, KW
COP
DESIGN 1,214.78 1,300.00 1.89
230-K 101 A 966.64 1,110.00 1.78
230- K 101 C 815.11 936.00 1.78
Finding :
Inlet flow of refrigerant vapor to propane compressors come from one header, so difficult to evaluate COP each compressor.
Design COP of propane compressor is 1.89, calculated COP at actual condition (based on heat absorb) is around 1.78
8. Gas Chiller
Performance of gas chiller are asfollows :
GAS CHILLER UNITS DESIGN EVAPORATOR (102,201,302,402)
GAS INTAKE TEMP.AT EVAP. DEG F 1.00 16.00
GAS OUTPUT TEMP.AT EVAP. DEG F (10.00) 5.00
SALES GAS FLOW MMCFD 300.00 533.00
CONDENSATE FLOW BBL/D 4,000.00 3,000.00
HEAT RELEASE MMBtu/hr 16.52 11.80
TOTAL POWER KW 2,600.00 1,930.00
C.O.P 1.86 1.79
Finding :
Inlet flow of refrigerant to gas chiller come from one header, so difficult to evaluate COP for each gas chiller
Heat duty of four gas chiller is 11.8 MMBTU/hr compare to design is 16.52 MMBTU/hr. The motor power of propane compressor is 2046 kW
Design COP of gas chiller is 1.86, calculated COP at actual condition (based on heat release) is around 1.79
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 58 of 109
9. Pump
Finding :
Calculated efficiency of pumps are as follows;
PUMPS Flow, GPM Efficiency, %
Actual Design Actual Design
Amine Charge Pump
225-P-102A 265.00 1165.00 39.54 76.67
225-P-102B 265.00 39.54
Amine Booster Pump
225-P-101A 225.00 1430.00 22.04 73.81
225-P-101B 225.00 22.04
Amine Reboiler H/M Circulation Pump
225-P-111A 2211.00 3044.00 69.83 74.43
225-P-111B 2186.00 69.04
225-P-211A 1911.00 66.71
225-P-211B 1911.00 66.71
Amine charge pumps and Amine booster pumps were running in low efficiency. This is due to very low of fluid rate they handled. Should two split of flow that flowing through “Amine booster pumps is merged together to flow through one pump only(530 GPM), its total flow still far below the rate of design (1165 GPM).
The similar case was found at Amine booster pumps. Two pumps were running to handle 225 GPM rate each.
Recommendation :
Higher efficiency could be achieved should the fluid flowing is handled by one pump only (If total rate of flow not exceed flow rate at design).
10. Cooler
Findings :
Calculated of coolers are as below:
No.
COOLER HEAT DUTY HEAT TRANSFER RATE
ELECTRIC/HEAT DUTY
(MMBTU/HR) (BTU/HR.FT2.oF) ( % )
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 59 of 109
1. Inlet Gas Cooler
215-E-101 28.37 4.46 0.63%
215-E-201 28.37 4.46 0.63%
215-E-301 43.04 3.08 0.42%
215-E-401 43.04 3.08 0.42%
2. Treated Gas Cooler
225-E-105 4.62 3.91 4.19%
225-E-205 3.87 2.95 4.90%
225-E-305 5.35 1.89 3.77%
225-E-405 OFF OFF OFF
3. Regenerator Reflux Condenser
225-E-101 9.26 1.94 0.65%
225-E-201 13.23 2.68 1.03%
4. Lean Amine Cooler
225-E-103 16.78 1.60 0.72%
225-E-203 16.25 1.53 0.74%
5. Condensate Cooler
235-E-102 1.98 1.11 1.53%
235-E-202 3.75 2.12 0.86%
6. Propane Cooler 230-E-104 19.15 2.59 0.31%
Power required to drive motors of fan coolers are below 1% due to their heat duties. This condition indicate that the power consumption of these coolers are in good condition except Treated gas cooler and Condensate cooler.
Recommendations :
Need to check again the performance of Treated gas cooler and Condensate cooler, especially motor driver of fan coolers.
11. Heat Exchanger
Findings :
Calculated of Heat Exchangers are as listed below:
No. HEAT EXCHANGER HEAT DUTY HEAT TRANSFER RATE
DIRTY FACTOR
(MMBTU/HR) (BTU/HR.FT2.oF) ACTUAL DESIGN
1. Stabilizer Reboiler
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 60 of 109
235-E-101 2.21 39.14 0.0009 0.0010
235-E-201 3.02 48.13 0.0034 0.0010
2. De-C3 Reboiler 230-E-106
0.18 N/A N/A N/A
3. Rich/Lean Amine Exch.
225-E-104A/B 16.40 N/A N/A N/A
225-E-204A/B 20.96 N/A N/A N/A
4. Gas-Gas Exch. 230-E-307
14.00 157.31 0.0023 0.0020
The performance of heat exchangers still in good condition, except for Stabilizer Reboiler 235-E-201, because the dirty factor more than design specification.
12. Energy Losses, Potential Saving and Emission Reduction Potential
Based on heat balance calculation, energy losses from high temperature flue gas at Suban is coming from Stack of Thermal Oxidizer, GTG and GTC.
STACK LOSS, Btu/hr
TEMP, Deg F
Thermal Oxidizer
225-H-102 35,495,414 932
225-H-202 8,303,983 2,012
GTG
247-GT-201A 33,163,974 916
247-GT-201B 29,310,275 921
247-GT-201C 29,397,944 925
GTC
242-K-101 21,555,786 1,213
242-K-301 22,755,271 1,261
242-K-401 21,806,787 1,237
TOTAL 201,789,433 1,177
a. Energy Losses :
Total losses from flue gas is around 201 MMBtu/hr with average temperature 1,177 deg F. Actually, by utilizing economizer with stack temperature around 500 deg F, this Flue gas losses can be used to generate saturated steam about 120,000 lb/hr.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 61 of 109
b. Potential Saving :
Based on the evaluation, shows that the potential saving are coming from :
Optimize operation of GTG will increase efficiency from 18 % to 23 % that will reduced HP Fuel consumption about 0.14 MMSCFD
Optimize operation of all heater will increase efficiency around 5 %, that will reduced LP fuel consumption about 0.1 MMSCFD
Utilized flare gas that will reduced fuel consumption about 0.8 MMSCFD
Energy Conservation Opportunities :
Optimize operation of GTGs can be implemented by load shading
Optimize operation of Heater and utilized flare gas can be implemented by installing booster compressor to compress gas up to 180 psig. This fuel gas can be used for Gas turbine and in turn it will reduce HP Fuel consumption. The simple calculation are as follows :
Fired Heater-saving, MMSCFD 0.10
, US $/Year 123,750.00
Flare Gas-saving, MMSCFD 0.80
, US $/Year 990,000.00
Total, MMSCFD 0.90
, US $/Year 1,113,750.00
*Cost to install the system for recovery gas which includes : gas compressor, KO Drum, Instrumentations , US $
2,400,000.00
Operation and Maintenance Cost , US $/year 120,000.00
Net income , US $/Year 993,750.00
Estimated payback period to install the system , Years
2.42
* = refer to Beak Pacifik Report - Energy Audit at Cilacap Refinery Complex
(Beak Pacific Inc. , Vancouver, Canada)
c. Emission Reduction Potentials
CO2 emission at suban gas plant is 127,901 lb/hr. its come from combustion of fuel gas at flare gas, heater, GTC and GTG.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 62 of 109
CO2 reduction, lb/hr
Optimized operation of GTG 642
Optimized operation of Heater 824
utilized flare gas 7,394
Total 8860
Optimised operation and utilized flare gas will reduce CO2 emission , %
7%
13. Reporting system
Findings :
Existing daily report just only for production activity, it does not cover the data for plant performance evaluation purposes
No data acquisition and evaluation based on daily log sheet .
Important data for plant performance not covered in daily log sheet
Recommendation :
Daily reporting must covers production activity and plant performance indicator
Regulars summary of log sheet regarding plant performance should be evaluate.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 63 of 109
IV. ENERGY ASSESSMENT AT GRISSIK CENTRAL GAS PLANT
4.1. GENERAL PLANT OPERATION AND PERFORMANCE
4.1.1. GENERAL PLANT OPERATION OF GRISSIK GAS PLANT
The Central Gas Processing – Grissik plant was designed firstly for processing gas from four field in the Corridor Block, South Sumatra: Dayung/Sumpal and GLT (Gelam/Letang/Tengah) field. The quality gas from Dayung field has high CO2
content (31 %) and the gas quality from GLT has high condensate content.
The source of inlet gas to be processed in CGP has changed after the Suban Gas Plant was operated. Partly of Suban Gas sales line also was processed in CGP if the specification of Suban Gas Sales was nearly out of specification, especially on the CO2 content. So, the mixed gas from Suban plant and CGP plant will meet specification at the gas sales pipeline.
The simple process flow of CGP-Grissik Plant is shown with block diagram in figure 1.1 below:
T
Dayung Gas Gathering Station
T
Gelam Gas/Liq Gathering Station
T
Suban Gas Sales to processed in CGP
T
Gas/Liquid Separation
1 T
Gas Pretreatment
2A T
Amine System
4 7 T
GasDehydration System
9
65
T3
8
10
11
Condensate Stabilization & C3 Recovery
Gas Sales to pipeline
Condensateproduct to Bentayan
Acid GasPermeate Gas
Flare Gas
Gelam Gas
Gelam Liquid
2B
T
Suban Gas Sales bypass
T PropaneChil ler
Figure 4.1 Gas Processed Block Diagram of CGP plant
The flow diagram of CGP Grissik plant that obtained from basic design and field survey can be described below:
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 64 of 109
Based on overall process, the processing load of CGP plant during field survey activity is 54.6% of capacity design. This condition is caused by shut down condition for repairing of the Amine Regenerator 25-C-202.
4.1.2. GENERAL PLANT PERFORMANCE OF GRISSIK CENTRAL GAS PLANT
The HP fuel gas supply for the plant is obtained from the Back-up sales gas line and Suban taping gas line via the pressure control valve. Gas heated by steam, under back pressure control, goes to the high pressure fuel gas scrubber which is operated at about 260 psig. The high pressure fuel gas supplies fuel the gas turbine and partly sent to Bentayan field.
The LP fuel gas from the stabilizer feed drum and stabilizer overhead is supplied for TEG regeneration heater, gas pretreatment heater, fuel gas for WHB incenerator and flare purge gas, flare stack pilot, tank blanket.
The HP fuel gas is supplied to GTG and to the LP fuel gas, when the LP gas demand exceeds the available LP fuel gas supply.
CGP Grissik plant used three (3) type of energy for the process, utility and offsites facilities. The types of energy that used are : LP Fuel gas, steam from WHB and electricity from GTG.
Based on 2 October 2007, the amount of fuel gas coming from scrubber is 5.910 MMSCFD. The distribution of fuel gas as shown in table below;
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 65 of 109
Table 4.3 : Fuel gas distribution
1 Fuel Gas to Flare
C 1.460
2 Fuel Gas to WHB
46-B-101 D 1.550
46-B-201 D -
D 1.550
3 Fuel gas to Heater
41-H-101 C 0.023
41-H-201 C 0.023
41-H-301 C -
C 0.045
4 Fuel gas to Regen Heater
21-H-101 C 0.161
21-H-201 C -
0.161
5 Fuel gas to GTG
47-GTG-101A C 0.70
47-GTG-101B C 0.78
47-GTG-101C C -
D 1.48
6 Fuel gas to Bentayan
D 1.560
There are two type of fuel gas used, LP Fuel gas which is consumed by fired heater and HP Fuel gas which is consumed by GTG. The heating value of LP Fuel gas is around 1,060 Btu/SCF and HP Fuel is around 1,484 Btu/SCF
Based on heat balance calculation in WHB and GTG, the energy picture based on 2 October 2007 which includes total energy input/heat released, heat absorbed, heat loss and CO2 emission as shown in table below,
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 66 of 109
Table 4-4 : The energy picture based on 2 October 2007
TOTAL 344,741,441 142,631,970 166,781,807 468 182,585
Plant Performance :
The plant performance at 2 October 2007 are as follows :
Table 4-5 : Plant Performance of Grissik Central Gas Plant
PRODUCTION RATESales Gas = 186.50 MMSCFD
= 31,083.33 BOE
Condensate = 1,234.00 BOE
Total Prod => 32,317.33 BOE
ENERGY CONSUMEExcluding Flare 256,621,725.71 Btu/hrIncluding Flare 347,461,746.16 Btu/hr
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 67 of 109
ENERGY INTENSITYExcluding Flare 7,940.68 Btu/BOEIncluding Flare 10,751.56 Btu/BOE
Total heat input to WHB, GTG,Regeneration Gas Heater and Glycol Heater is 253,901,420 Btu/hr and total heat released including flare gas is 344,741,441 Btu/hr. The production rate is 32,317.33 BOE which include 186.5 MMSCFD sales gas and 1,234 Barrel of condensate, means the energy consumed to produce one BOE (energy intensity) is 7,940.68 BTU/BOE (Excluding flare) and 10,751.56 BTU/BOE Including flare).
4.2. PERFORMANCE EVALUATION EACH SYSTEM
4.2.1. GAS PRETREATMENT & MEMBRANE SYSTEM
A. DESCRIPTION
The Gas Pre-Treatment Unit has been designed to operate at 2 x 50% each train with a total gas throughput capacity of 230 MMSCFD and designed to remove heavy hydrocarbons (C6+) from 380 ppm to 39 ppm.
The overall process works on the principles of Adsorption, Regeneration and, Cooling and, is commonly referred to a Thermal Swing Adsorption (TSA) process. Each train has 4 Adsorber Towers. Under normal operation each train has 2 Adsorber towers in operation mode,one Adsorber Towers in Regeneration mode and one Adsorber Towers in cooling mode.
The pretreatment consists of the following four steps process, i.e :
Coalescing filter for the removal of aerosols and particulates;
Heater to ensure the gas is above the dewpoint temperature;
Guard bed for the removal of heavy hydrocarbons and glycol;
Polishing filter
The Dayung gas from inlet separator is sent to the membrane unit to remove CO2, lowering the CO2 content of the gas from about 30.5 mole% to less than 15.0%.
The Membrane CO2 separation unit was designed to process the Dayung gas to reduce the CO2 content of the gas from 31% to 15%. The remainder of the CO2 in the Dayung gas is then removed in the Amine-treating Unit, allowing the gas to meet the sales gas pipeline specification for CO2, which has a minimum value of 5%. As the Dayung gas flows through the semipermeable polimide membranes, approximately 63% of the CO2, 60% of the H2S, and 8% of the Methane is separated into the permeate gas stream. The permeate Gas, consisting of about 80% CO2 and 20% Methane, is sent to the Waste Heat Boilers as fuel gas.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 68 of 109
B. PERFORMANCE
The main equipment at Gas Pretreatment (TSA) system are Regenerator Gas Heater and Regen Gas/Gas Exchanger
The performance of main equipment are as follows :
Table 4-6 : Performance of Performance of Regenerator Gas Heater :
2-Oct-07 DESIGN
21-H-101 21-H-201 21-H-101/201
1 FUEL,
Flow, MMSCFD 0.16 OFF 0.31
2 FLUE GAS
T out, F 430.00(Estimated)
OFF 430.40
O2, % 14.00(Estimated)
OFF 14.00
Excess Air, % 185.64 OFF 185.64
3 PERFORMANCE
Heat absorption (LHV), MMBtu/hr
5.75 OFF 11.06
Heat absorption (HHV), MMBtu/hr
5.80 OFF 11.16
Efficiency (LHV), % 74.65 OFF 74.62
Efficiency (HHV), % 68.40 OFF 68.38
4 CO2 EMISSION
CO2 Emission from fuel gas, lb/hr
1,376.93 OFF 2,651.23
Regen gas heater is operated at 60% load compare to design condition and the fuel consump is 0.16 MMSCFD
The stack temperature and oxygen content are estimated close to design condition with the efficiency is 74.65 %
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 69 of 109
Table 4-7 : Performance of Regen Gas/Gas Exchanger (21-E-101/201)
21-E-101 21-E-201 DESIGN
Gas to Membrane (Shell side)
Pressure, psig 1097 OFF 1153
Temp inlet, F 85.00 OFF 85.78
Temp outlet, F 100.00 OFF 110.40
Flowrate of Gas, MMSCFD 26.00 OFF 215.07
Hot Gas (Regen Gas)
Temp inlet, F 230.00 OFF 309.90
Temp outlet, F 109.00 OFF 95.00
Delta T LMTD 62.74 OFF 61.89
HEAT DUTY, Btu/hr 475,664 OFF 7,497,708
HEAT TRANSFER RATE, BTU/(Hr/Ft2.F) 3.12 OFF 6.26
Table 4-8 : Performance of Cooler Gas/Gas Exchanger (21-E-102/202)
21-E-102 21-E-202 DESIGN
Regen Heater Gas/Hot Gas (Shell side)
Pressure, psig 1097 OFF 1155
Temp inlet, F 400.00 OFF 541.60
Temp outlet, F 230.00 OFF 309.90
Flowrate of Gas, MMSCFD 20.00 OFF 25.93
Cold Gas (Regen Gas)
Temp inlet, F 102.00 OFF 85.90
Temp outlet, F 120.00 OFF 335.60
Delta T, LMTD 194.18 OFF 212.40
HEAT DUTY, Btu/hr 4,674,675 OFF 8,267,466.11
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 70 of 109
HEAT TRANSFER RATE, BTU/(Hr/Ft2.F) 44.17 OFF 55.43
The above table shows that the heat duty operated only about 0.475 MMBTU/hr for E-101 and 4.67 MMBTU/hr for E-102, although the design heat duty is 7.5 MMBTU/hr for E-101 and 8.26 MMBTU/hr for E-102. This heat duty value produce capacity only about 6.34 % for E-101 and 56.54 % for E-102 compare to design capacity.
This condition caused by the feed gas to TSA unit only 26 MMSCFD (110,283 lb/hr) for adsorption and 20 MMCSFD (87,483 lb/hr) for cooling condition compare to the design capacity for gas process adsorption is 115 MMSCFD (20% capacity).
The different between design and operation are the LMTD value. Actual LMTD is 62.74 oF for E-101 and 44.17 oF for E-102 compare to design is 61.9 F for E-101 and 55.43 oF for E-102.
The performance of heat exchanger can be evaluated from the value of overall heat transfer rate (U). The U at operating condition give value about 3.12 BTU/(Hr/Ft2.F) for 21-E-101 and 44.17 BTU/(Hr/Ft2.F for 21-E-102, while the design value is 6.26 BTU/(Hr/Ft2.F) for 21-E-101 and 55.43 BTU/(Hr/Ft2.F) for 21-E-102.
4.2.2. AMINE SYSTEM
A. DESCRIPTION
The gas treating process consists of three identical amine contactors, two normally treating about 114 MMSCFD of Dayung gas each (referred design base) and the third treating about 129 MMSCFD of Gelam, Letang, Tengah (GLT) gas. The amine units are designed to produce treated gas containing less than 2% CO2 and 4 ppmV H2S consequently the bypasses allow the sales gas still to meet its specification of 5% CO2 and 8 ppmV of H2S.
Amine unit feed gas stream enters the bottom of an amine contactor where it is counter-currently contacted with lean 50 wt% UCARSOL solution with main composition is MDEA solution. CO2 and H2S are absorbed by the lean amine and the treated gas exits the top of the tower. The amine contactor contains stainless steel structured packing.
The design lean amine circulation rate to the Dayung gas contactors is about 1640 US gpm and the design lean amine circulation rate to GLT gas is about 1621 USgpm based on maximum allowable rich amine loading of 0.49 mole (CO2+H2S)/mole UCARSOL (MDEA solution).
The rich amine from the contactors flows under level control to the rich amine flash drums. Gas from the flash drums flows under back pressure control to the waste gas incenerators. The rich amine flows under level/flow control through the lean/rich amine exchangers where it is heated to about 206 oF by heat exchange with the hot lean amine from the two regenerators.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 71 of 109
The rich amine feeds the regenerator above the stripping section which contains stainless steel structured packing. CO2 and H2S are stripped from the rich solution by steam produced in the regenerator reboilers which consist of 4 (four) kettle type shell and tube heat exchanger for each regenerator.
B. PERFORMANCE
The main equipment of amine system are Regenerator Reflux Condenser 25-E-101/202, Amine Reg. Reboiler 25-E-102A-D /202A-D , Lean amine cooler 25-E-103/203, Rich / Lean Amine Exchanger 25-E-104A/B, 25-E-204A/B; Amine Charge Pump 25-P-102A/B/C; Amine Booster Pump 25-P-101B/C
Table 4-9 : Performance of Amine Regenerator Re-boiler:
25-E-102A-D 25-E-202A-D DESIGN
STEAM SIDE (SHELL):
Pressure, psig 63.00 OFF 50.00
Temp sat'd steam, F 300.00 OFF 297.00
Flowrate Steam (25-FIC-121), Lb/hr 101,954.00 OFF 101,564.00
Flowrate Steam (25-FIC-122), Lb/hr 102,586.00 OFF 101,564.00
AMINE SIDE (TUBE):
Temp amine to Regenerator, F 259.50 OFF 261.00
Flow of Rich Amine to be regenerated, Lb/hr
1,309,729 OFF 1,299,665
Delta T 44.25 OFF 39.25
HEAT DUTY, Btu/hr 184,589,323 OFF 194,088,804
HEAT TRANSFER RATE, BTU/(HR.Ft2.degF)
132 OFF 173
The above table shows that the actual heat duty is closed to the design. The difference between actual heat duty and design value only 5%, although the flow rate regenerated rich amine higher than design, the temperature outlet of amine reboiler less than design (actual is 249.5 deg F and design value is 262 deg F).
The overall heat transfer rate (U) at actual condition is 132 BTU/(Hr/Ft2.F) compare the design is 173 BTU/(Hr/Ft2.F. This condition caused by the LMTD of actual is higher than design value.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 72 of 109
Table 4-10 : Performance of Lean Amine Cooler :
25-E-103 25-E-203 DESIGN
LEAN AMINE side:
Pressure, psig 110.00 110.00 180.00
Temp inlet, F 190 190 224
Temp outlet, F 106 104 120
Flowrate of Lean Amine, Lb/hr 799,305 670,882 1,375,016
The above table shows that the heat duty actual of 25-E-103 and 25-E-203 are operated at 50% to the design. This caused by the flow rate of lean amine to be cooled also only about 50% - 60% from design capacity.
The flow rate of lean amine does not affect to the power required of fan cooler driver, so the power required to motors also higher than calculated value. At this case, the actual fan be operated closed to design (11 fans for 25-E-103 and 12 fans running for 25-E-203). This condition related with performance of cooler, especially with heat transfer rate. The U (overall heat transfer rate) at operating condition give value about 2 BTU/(Hr/Ft2.F) for operated and 3 BTU/(Hr/Ft2.F for the design value. This difference indicated that the performance of cooler lower than the design performance.
Table 4-11 : Performance of Rich-Lean Amine Exchanger:
25-E-104A/B 25-E-204A/B DESIGNRICH AMINE SIDE
Pressure, psig 108.00 OFF 95.00Temp inlet, F 155.00 OFF 167.00
Temp outlet, F 203.00 OFF 206.00
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 73 of 109
Flowrate of Rich Amine, USGPM 2,572.00 OFF 2,496.80 LEAN AMINE SIDE
Temp inlet, F 250.00 OFF 261.00 Temp outlet, F 229.00 OFF 224.00 Delta T LMTD 59.48 OFF 55.99
HEAT DUTY, Btu/hr 53,656,356 OFF 42,413,111 HEAT TRANSFER RATE, BTU/(Hr/Ft2.F) N/A OFF N/A
The above table shows that the heat duty operated of exchanger 25-E-104A/B is higher than design value. The difference is about 25% higher than design.
The different heat load should be caused by :
Design amine is CR302, but the actual operation is AP-16668. The difference of amine causes different specific heat.
Flow rate of rich amine at operation is higher than the design value (3.5% difference)
The difference between operated LMTD and design is 6.5%.
Table 4-12 : Performance of Regenerator Reflux Condenser :
25-E-101 25-E-201 DESIGN
ACID GAS SIDE :Temp inlet, F 218.47 OFF 217.00
Temp outlet, F 143.15 OFF 120.00Flow of acid gas removed, MMSCFD 20.60 OFF 23.25
AIR COOLANT SIDE :Temp inlet, F 92.00 OFF 95.00
Temp outlet, F 132.00 OFF 131.60Delta T LMTD 67.27 OFF 57.60
HEAT DUTY, Btu/hr 55,701,905 OFF 61,714,112
ELECTRIC CONSUMPTION, KW 23.79 OFF 29.84ACTUAL FAN OPERATED 11.00 OFF 12.00
CALCULATE FAN OPERATED 10.83 OFF 12.00HEAT TRANSFER RATE,
BTU/(HR.Ft2.degF)3.57 OFF 4.19
The above table shows that regen reflux condenser and amine regenerator re-boiler are operated close to design condition. It has difference of heat duty about 11% than the design value. This caused by the flow rate of acid gas to be removed also only
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 74 of 109
13% less than the design capacity (operated is 20.6 MMSCFD, and the design value is 23.25 MMSCFD).
Power required of motor fan driver also proportional with the exchanger heat duty. At this condition the actual operate 11 fans, and the calculated result is also same fans to be operated.
Caused by the flow rate capacity of cooler load, the overall heat transfer also follow with this condition. The U (overall heat transfer rate) at operating condition give value about 3.57 BTU/(Hr/Ft2.F) and 4.19 BTU/(Hr/Ft2.F for the design value.
Table 4-13 : Performance of Amine Charge Pump
DESCRIPTION UNIT 25-P-102C Design
value value
specific gravity 1.03 1.00
Temperature F 245.00 70.00
suction pressure psia 98.00 25.00
discharge pressure psia 1210.00 1185.00
flow GPM 2862.00 2487.00
Total head ft 2,503.97 2679.60
Electric motor power HP 2240.00 2059.00
Mechanical work HP 1946.39 1719.89
Efficiency % 86.89 83.53
Only one Amine charge pump (Charge pump C) was running very close to design condition. It’s efficiency reached 86.89% with flow rate of 2862 GPM, This pump is designed to running with 83.53% efficiency at 2487 GPM flow rate. The pump was running actually in even higher efficiency than the design condition. Attention should be addressed to this situation since the pump draw consumed electric power of 2240 HP. It just below it's maximum power rating: 2250 HP.
Table 4-14 : Performance of Amine Booster Pump
DESCRIPTION UNIT 25-P-101B 25-P-101C Design
value value value
specific gravity 1.03 1.03 1.00
Temperature F 180.00 180.00 70.00
suction pressure psia 16.70 18.70 N/A
discharge pressure psia 119.70 129.70 N/A
flow GPM 1556.00 1306.00 2871.00
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 75 of 109
Total head ft 231.93 249.95 188.00
Electric motor power HP 142.00 136.00 170.00
Mechanical work HP 98.02 88.66 139.30
Efficiency % 69.03 65.19 81.94
Two of the Amine booster pumps were running. They were Amine Booster pump B and C. Their efficiencies are 69.03% at 1556 GPM and 65.19% at 1306 GPM respectively. At the other side, we have data from design condition when each pump handles 2871 GPM. At this design condition, we got 81.94% efficiency. These two pumps were running in good condition and within the range of operation.
4.2.3. REFRIGERATION SYSTEM
A. DESCRIPTION
Propane refrigerant gas from gas chiller at 75 psig, compress by propane compressor (single stage screw compressor). The compressor discharge at about 252 psig goes to the propane condenser where it is totally condensed at about 122 oF. The propane condenser is an air cooled heat exchanger.
The condensed propane goes to the propane accumulator and then to the gas chiller via the level control valve. The refrigerant chills the sales gas from 57 F to 45 F and then goes to LTS to separate the gas from the condensate.
B. PERFORMANCE
The main equipment at Refrigeration System are Exchanger (Gas chiller 30-E-102), Propane compressor 30-K-101A/B and Gas/Gas Exchanger.
Table 4-15 : Performance of Gas Chiller
UNITS DESIGN EVAPORATOR
TEMPERATURE GAS IN DEG.F 57.00 57.00
TEMPERATUR GAS OUT DEG.F 45.00 45.00
GAS FLOW MMCFD 100.00 39.00
CONDENSATE FLOW BCD 700.00 700.00
HEAT RELEASE BTU/H 2,477,633.80 841,348.85
ACTUAL POWER KW 260.00 110.00
C.O.P 2.79 2.24
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 76 of 109
The above table shows that the refrigeration system operated at low load and the propane chiller are operated at 40 % load (39 MMSCFD ) at actual power 110 KW compare to design condition. The COP at actual condition is 2.24 compare to design value is 2.79
Table 4-16 : Performance of propane compressor
Only one compressor is operated to handle the refrigeration system. The operating conditions are as follows;
At the actual condition, the refrigerant flow is 7191 lb/hr at actual power 110 KW and COP = 2.87. Compare to design condition, the refrigerant flow is 14,000 lb/hr at power design 260 KW and COP = 3. It means that the performance of compressor is still in good condition.
Table 4-17 : Performance of Gas/Gas Exchanger
30-E-101 DESIGN
HOT GAS (FR GELAM CONTACTOR):
Pressure, psig 1000 1120
Temp inlet, F 130.00 129.60
Temp outlet, F 60.00 64.40
Flow rate of Gas, MMSCFD 39.39 114.00
GELAM SALES GAS side:
Temp inlet, F 40.00 50.00
Temp outlet, F 120.00 117.00
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 77 of 109
Delta T LMTD 14.43 13.48
HEAT DUTY, Btu/hr 3,159,954 10,705,230.41
HEAT TRANSFER RATE, BTU/(Hr/Ft2.F) 0.23 0.30
The above table shows that gas/gas exchanger at the dew point control system have heat duty only 30% refer to the design value. This caused by the flow rate of gas also only 35%. The temperature profile of gas also not have high different between operated and design value.
Caused by the flow rate capacity of gas to the gas/gas exchanger, the overall heat transfer also follow with this condition. The U (overall heat transfer rate) at operating condition give value about 0.23 BTU/(Hr/Ft2.F) and 0.30 BTU/(Hr/Ft2.F for the design value.
4.2.4. CONDENSATE STABILIZING SYSTEM
A. DESCRIPTION
The hydrocarbon liquid from the feed drum is fed under level control to the top tray of the condensate stabilizer. The stabilizer is a 32 inch ID reboiled stripping column containing 18 stainless steel valve trays.
The stabiliser reboiler is a kettle type shell and tube exchanger utilizing about 3404 lb/h of 140# steam at normal operation. During normal operation about 1738 bbl/day of 10 psi RVP condensate are produced. The condensate product from the stabilizer is sent via the HC condensate cooler bundle in the refrigerant condenser air cooled exchanger frame.
B. PERFORMANCE
The main equipment at Condensate Stabilizing system are Stabilizer Re-boiler 35-E-102, and Condensate cooler 35-E-101
Table 4-18 : Performance of Stabilizer Reboiler 35-E-102 :
35-E-102 DESIGN
STEAM SIDE (SHELL)
Pressure, psig 117.00 150.00
Temp sat'd steam, F 330.00 330.00
Flow rate (35-FIC-006), Lb/hr 803.00 3,751.35
CONDENSATE SIDE (TUBE)
Temp Condensate to re-boiler, F 278.00 261
Delta T 66.00 69.40
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 78 of 109
HEAT DUTY, Btu/hr 700,201 3,470,000
HEAT TRANSFER RATE, (BTU/Hr.Ft2.F) 6.52 30.73
The above table shows that actual heat duty of 35-E-102 is only 20 % compare to design condition because the flow rate of feed liquid to the stabilizer is only 20 % - 25% compare to design.
Due to the flow rate of stabilizer re-boiler is only 20% than the design, the U (overall heat transfer rate) at operating condition give value about 6.52 BTU/(Hr/Ft2.F) compare with the design value, 30.73 BTU/(Hr/Ft2.F
Table 4-19 : Performance of Propane Condenser and Condensate Cooler
The arrangement of cooler in this area is designed to serve three stream cooling fluid, i.e : Propane condenser, Propane overhead condenser and condensate stabilizer. Only one fans cooler installed to cool them. At the plant survey, the propane overhead condenser was off.
Heat Load total at actual condition of two condenser (30-E-105 and 35-E-101) are 3.8 MMBTU/hr compare with the design value is 5.7 MMBTU/hr. This heat load gives
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 79 of 109
percentage about 65 % of heat load capacity similar with electrical consumption is 65 % too.
4.2.5. DEHYDRATION SYSTEM
A. DESCRIPTION
The water saturated gas from the three amine trains is dehydrated by contacting it with lean triethylene glycol (TEG) in the three, identical glycol contactors. The design water content of the dry gas is 10 lb H2O per MMSCFD. The dehydrated GLT gas is recombined with the GLT amine unit bypass gas, sent through the dewpoint unit and then to sales. The Dayung/Suban gases from two of the glycol contactors and the Dayung/Suban amine unit bypass gas are sent directly to Sales.
Lean glycol is fed to the top of the glycol contactor at a rate of about 30-USgpm. A coil is provided in the top of the tower to cool the glycol from about 210 oF to less than 150 oF by heat exchange with the dried gas leaving the contactor. The glycol flows downwards through the structured packing in the column counter-currently contacting and absorbing water from the gas flowing upwards through the packing.
The rich glycol accumulates on the chimney tray and is sent under level control to the glycol regeneration skid. The dry gas exits the top of the contactor with the Dayung/Suban gasses going to sales and the GLT gas going to the hydrocarbon dew-point control unit.
The three glycol regeneration skids are identical. There are no connections between the glycol regeneration skids or between the glycol lines in each train.
B. PERFORMANCE
Table 4-20 : Performance of Rich – Lean Glycol Exchanger
41-E-101 41-E-201 41-E-301 DESIGN
LEAN TEG SIDE
Pressure, psig 10.50 11.50 11.00 50.00
Temp inlet, F 380.00 370.00 360.00 360.00
Temp outlet, F 150.00 165.00 160.00 225.00
Flow rate of Lean TEG, USGPM 20.18 24.00 24.00 30.48
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 80 of 109
HEAT TRANSFER RATE, BTU/(Hr/Ft2.F)
104.88 88.55 92.66 128.20
The above table shows that Rich/Lean Glycol Exchanger are operated close to design condition. Its heat duty is only 5% differ than the design value, although the flow rate of glycol at the operation only 70% - 80% than design capacity. This condition is caused by the difference of LMTD between operated and design value. The operating condition gives temperature outlet of Lean glycol lower than design value.
Due to the flow rate capacity of cooler load, the U (overall heat transfer rate) at operating condition give value about 70%-80% than the design value.
Table 4-21 : Performance of Glycol Heater
2-Oct-07
41-H-101 41-H-201
1 FUEL,
Flow, MMSCFD 0.02 0.02
2 FLUE GAS
T out, F 430.00 430.00
O2, % 7.00 7.00
Excess Air, % 45.77 45.77
3 PERFORMANCE
Heat absorption (LHV), MMBtu/hr 0.91 0.91
Heat absorption (HHV), MMBtu/hr 0.92 0.92
Efficiency (LHV), % 84.91 84.91
Efficiency (HHV), % 77.08 77.08
4 CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 191.42 191.42
The heat duty of Glycol heater is 0.91 mmbtu/hr (calculated from process site). Assuming the oxygen content of flue gas is 7%, the calculated efficiency is 84.91%.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 81 of 109
4.2.6. WASTE HEAT BOILER
A. DESCRIPTION
Permeate gas from membranes, rich amine flash drum gas, and acid gas from the amine reflux accumulators are combined and sent to the waste gas incenerator. In the incenerator, the waste gas is incenerated by burning fuel gas at a sufficient high temperature to ensure the complete destruction (oxidation) of the H2S and hydrocarbons. The minimum exit gas temperature at the top of the stack is 450 oF to ensure that the allowable ground level SO2 concentration is not exceeded.
150 psig saturated steam is produced by two heat recovey boilers with each capacity of 230,000 lb/h. Normally, two boilers are operated to supply necessary steam for all users in CGP.
B. PERFORMANCE
The main equipment of Waste Heat Boiler system are Waste Heat Boiler 46-B-101/201, and BFW pump 46-P-102A/B/C.
Table 4-22 : Performance of Waste Heat Boiler
2-Oct-07 DESIGN
46-B-101 46-B-101/102
1 INLET GAS,
Fuel Gas Flow, MMSCFD 1.55 1.77
Acid Gas Flow, MMSCFD 20.23 48.11
Permeat Gas Flow, MMSCFD 8.35 68.39
2 FLUE GAS
T out, F 376.00 416.00
O2, % 7.00 2.62
Excess Air, % 45.77 13.17
3 BFW
lb/hr 200,392.00 245,000.00
T in Economizer, F 200.00 251.00
T out Evaporator, F 347.00 375.00
P in Economizer, Psi 132.40 175.70
P out Evaporator, Psi 123.00 170.00
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 82 of 109
4 PERFORMANCE
Heat Release (LHV), MMBtu/hr 149.52 822.94
Heat Release (HHV), MMBtu/hr 164.41
Heat Loss (LHV), MMBtu/hr 29.91 380.55
Heat Loss (HHV), MMBtu/hr 43.92
Heat absorption (LHV), MMBtu/hr 119.60 442.38
Heat absorption (HHV), MMBtu/hr 120.49
Efficiency (LHV), % 79.99 no Dsg Eff
Efficiency (HHV), % 73.29 no Dsg Eff
5 CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 29,070.86 no Dsg CO2
CO2 Emission from Acid gas, lb/hr 103,029.15 no Dsg CO2
CO2 Emission from Permeat gas, lb/hr 42,586.20 no Dsg CO2
Total CO2 Emission, lb/hr 174,686.21 no Dsg CO2
The above table shows that the WHB are operated at only 50 % load compare to design condition, and the calculated efficiency is 80%. The temperature in flue gas are lower than design condition and the excess air is higher than design.
Table 4-23 : Performance of BFW Pump
DESCRIPTION UNIT 46-P-102A 46-P-102C Design
value value value
specific gravity 1.00 1.00 1.00
Temperature F 245.00 245.00 70.00
suction pressure psia 21.10 21.10 8.00
discharge pressure psia 274.70 274.70 230.00
flow GPM 380.00 380.00 528.00
Total head ft 585.82 585.82 512.82
Electric motor power HP 95.00 95.00 110.00
Mechanical work HP 57.45 57.45 69.88
Efficiency % 60.48 60.48 63.53
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 83 of 109
Like Amine booster Pumps, the two BFW pumps were running within the specification, and the efficiency reached is accepted. This BFW pump is designed to run with 63.53% efficiency at 528 GPM flow rate. Actually, two pumps were running at same rate of flow (380 GPM) with 60.48% efficiency.
4.2.7. GAS TURBINE GENERATOR
A. DESCRIPTION
Electrical power is generated and distributed to provide the prower requirements for the gas plant and offsites. Electrical power Generator driven by Gas turbine generator, which gas supplied from HP (high pressure) fuel gas system. Three gas turbine are provided with two generator running and one on the standby mode. The design capacity of generator is 4500 kW each unit. The actual capacity on the field survey only about 2100 kW each turbine generator (45% of design capacity) and running two of three generators.
Generator specification is power 4688, voltage 4160, freq 50 Hz, cos Q 0.85. The large motor (lean amine charge pump, WHB Blower, propane compressor) supply by 6600 volt and the other motors using 400 volts.
B. PERFROMANCE
Gas turbine generators at Utility system are 47-GTG-101A/B/C
Table – 4.24 : performance of GTG
2-Oct-07 DESIGN
47-GT-101A 47-GT-101B 47-GT-101A/B/C
TURBINE
Fuel gas :
flow, MMSCFD 0.89 0.92 1.31
Flue gas :
Temperature, F 0 0 900
O2, % 16 16 16
Excess Air, % 296 281 267
Turbine Eff, % 21 21 30
Btu/kwh 16,571 16,077 11,559
CO2 Emission
lb/hr 4,870 5,034 7,914
GENERATOR
Power Output, KW 2,158 2,265 4,688
PF 0.81 0.83 0.84
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 84 of 109
V 4160 4160 4160
Frequency, Hz 50 50 50
The above table shows that GTG operated at 50 % load compare to design condition.
The calculated efficiency is only 21 % compare to design which is 30 %. The decreasing of efficiency of GTG is caused by low load and will be impact the increasing of the heat loss,
The heat rate of 47-GT-101A is 16,571 Btu/kwh, greather than design 16000 Btu/kwh but 47-GT-101B 16,077 Btu/kwh close to design.
Table 4-25 : The design performance of GTG are as follows
Instrument and utility air are supplied by the two 340 scfm, screw type compressor connectod in a lead-lag configuration. The compressed air is filtered and then dried in heatless adsorption type dries which are on automatic regeneration cycles. The instrument air compressor packages are provided with local electronic control panels.
The instrument air receiver is normally operated between 110 and 120 psig. The utility air take-off is equipped with a shut off valves to prevent utility air usage from drawing down the instrument air pressure.
B. PERFORMANCE
There are three compressors Atlas Copco GA 75 , 51-A-101A /B/C with design capacity is 340 SCFM, the performance of each equipment are as follows,
Table 4-26 : Performance of air compressor :
UNITS DESIGN ACTUAL
SUCTION PRESS PSI 14.70 14.70
DISCHARD PRESS. PSI 182.00 132.30
COMPRESS AIR FLOW SCFM 340.00 257.45
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 85 of 109
25-P-102 A/B/CAmine Charge pump A/B/C
2250 HP x3
25-PM-101 A/B/CLean amine booster pump A/B/C
200 HP x3
25-EM-103 A-MLean Amine cooler fan A-M
37.3 KW x13
25-PM-104Amine Sump pump
15 HP
25-EM-201 A-MRegenerator reflux condenser fan A-M
29.8 KW x13
25-EM-101 A-MRegenerator reflux condenser fan A-M
29.8 KW x13
25-PM-203A/BRegenerator reflux pump A/B
7.50 HP x2
25-AM-101/102Anti foam injection pump
2 HP x2
4.16 KV
480 V
25-EM-203 A-MLean Amine cooler fan A-M
37.3 KW x13
POWER KW 72.60 44.17
ACTUAL PERFORMANCE 0.20 0.20
The above table shows that the compressor is operated at low load. The performance can not be evaluate accurately because no flow meter of air
4.2.9. ELECTRICAL MAP CENTRAL GRISSIK GAS PLANT
Electric map for Central Grissik Plant is like the one for Suban Gas plant. It is derived from single line diagram, and intend to get a closer and clear point of view to one that need brief description on power consumption at each process. It Emphasize the voltage, and power required for each equipment.
The power mentioned at each equipment is the power in normal design condition.
A. Amine System
25-PM-105Amine Transfer pump
9 HP
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 86 of 109
30-PM-102Depropaniser reflux pump
3.5 HP
30-PM-101Depropaniser feed pump
5 HP
30-E-104Depropaniser reboiler heater
69 KW
35-PM-102 A/BCondensate shipping pump A/B
75 HP x2
480 V
30-EM-105 A/BPropane condenser fan A/B
22.3 KW x2
30-K-101 A/BPropane Compressor A/B
350 HP x2
4.16 KV
30-PM-103Propane Transfer pump
3 HP
30-K-101A/B-KM1Propane Compr. A/B L.O. cooler fan
5 HP x2
30-K-101A/B-PM1Propane Compr. A L.O. pump motor
5 HP x2
480 V
41-PM-102/2020/302 A/BGlycol circulation pump
25 HP x6
480 V
46-K-101/201Inc. Blower train A/B
400 HP
4.16 KV
B. Propane Chiller System
C. Depropanizer and Condensate Stabilization System
D. Dehydration System
E. Incinerator/Heat recovery System
41-PM-101Glycol transfer pump
1.74 HP
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 87 of 109
46-PM-103 A/BCondensate pump A/B
25 HP x2
46-PM-102 A/B/CBFW pump A/B/C
150 HP
46-EM-101 A/BExcess steam condenser fan A/B
22.3 HP x2
480 V
51-AM-101 A/BInstr. Air compressor A/B
125 HP x2
48-PM-101 A/BFlare KO drum pump A/B
3 HP x2
480 V
51-AM-101 A/B -2Instr. Air compressor A/B cooler fan
4 HP x2
55-PM-201 A/BUtility water pump A/B
15 HP x2
480 V
53-PM-201 A/BSoftened water pump A/B
7.5 HP x2
54-PM-201 A/BPortable water pump A/B
7.5 HP x2
F. BFW steam and Condensate System
G. Flare and Air compressor System
H. Utility System
4.3. FINDINGS AND RECOMMENDATION
1. Instrumentation and Metering
Based on the site survey founded that many metering and instrument are not work properly. Findings and recommendations of metering and instrumentation at Grissik Central Gas Plant are as follows :
Equipments Findings Recommendations
1. WHB There are unbalance between BFW flow and steam flow that will impact the direct method efficiency calculation is not accurate.
Oxygen analyzer not work properly ( direct measurement = 7 % , on
Need to calibrate meter of steam and BFW
Need to install sampling point to measure Boiler water quality and control the blow down
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 88 of 109
line analyzer = 14 %)
No Sampling point for water quality at steam drum
2 Glycol & Regen Heater
No meter fuel gas at the heater
The position of flue gas sampling point is far from platform
need to install fuel gas meter
need to install sampling line of flue gas close to the platform
3 GTG There are no flow meter of fuel gas in each GTG.
Need to install flow meter of fuel gas
Need to install sampling line of flue gas for each GTG
4 Propane Comp
No continue record of electric consumption for motor compressor
Need to records continously
5 Electric Distribution
No continue recorded for electric distribution
Need to record electric distribution (4160 line) at daily records
2. Waste Heat Boiler
Calculation result of WHB :
EFFICIENCY HEAT ABSORB
CO2 EMISSION
% MMBtu/hr Lb/hr
W H B - INCENERATOR 46-B-101
DESIGN N/A 442.38 N/A
46-B-101 79.99 119.60 174,686.21
46-B-102 OFF OFF OFF
Finding :
WHB is operated at high excess air (77 %) compare to the design figure which is 27 % excess air. The efficiency is 80 %
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 89 of 109
WHB is operated at low load ( 50 % load)
Recommendation :
WHB should be operated close to the design excess air
3. Heater
Calculation result of heater :
EFFICIENCY HEAT ABSORB CO2 EMISSION% MMBtu/hr Lb/hr
REG GAS HEATER : 21-H-101/201 DESIGN 74.62 11.06 2,651.2321-H-101 74.65 5.75 1,376.9321-H-201 OFF OFF OFF
Finding :
The heater are operated at low load (50 % load)
4. GTG
Calculation result of GTG :
EFFICIENCY HEAT RATE BHP CO2 EMISSION % BTU/KWH KW Lb/hr
GAS TURBINE GENERATOR DESIGN 29.52 11,558.78 4,687.50 7,914.10 47-GT-101A 20.59 16,571.34 2,158.33 4,869.94 47-GT-101B 21.23 16,077.04 2,264.58 5,034.10 47-GT-101C OFF OFF OFF OFF
Findings :
GTG are operated at lower load is around 50 % compare to design, but the performance ( heat rate ) are still close to design at low load
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 90 of 109
Based on the actual data, the refrigeration load is only 50 % compare to design condition, but the COP is 2.87 compare to design COP is 3. It means that the compressor is still in good condition
6. Gas Chiller
Calculation result of gas chiller :
UNITS DESIGN GAS CHILLER
GAS INTAKE TEMP.AT EVAP. DEG F 58.00 57.00 GAS OUTPUT TEMP.AT EVAP. DEG F 45.00 45.00 SALES GAS FLOW MMCFD 100.00 39.00 CONDENSATE FLOW BBL/D 700.00 700.00
HEAT RELEASE MMBtu/hr 2,645,934.62 841,348.85 TOTAL POWER KW 260.00 110.00 C.O.P 2.98 2.24
(Calculated)
Findings :
the temperature indicator inlet and outlet are still in good conditions
COP at gas chiller is 2.24 compare to design 2.98
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 91 of 109
7. Air cooler
Calculation result of coolers are as below:
Findings :
Power rated required for drive motors of fan coolers are below 1% - 2% due to their heat duties, except for Lean Amine 25-E-203 and Condensate cooler (25-E-101). This case indicate that power consumption of these coolers more waste energy (less efficiency).
Recommendations :
Need to check the cooler system of Lean amine cooler, because at the plant survey, they have high power consumption although the capacity of heat load only a half than design.
Need to check again the properties of amine used in operation, because it can effect the calculation performance of cooler and exchanger system in amine system.
No. COOLER HEAT DUTY HEAT TRANSFER RATE
ELECTRIC/HEAT DUTY
(MMBTU/HR) (BTU/HR.FT2.oF) ( % )
1. Amine Regen Reflux Cooler25-E-101 55.70 3.57 1.60%25-E-201 OFF OFF OFF
4. Gas-Gas Dew Point Control HE30-E-101 3.16 0.29 0.09 0.10 -
5. Amine Regen Reboiler25-E-102 A-D 184.59 132.16 0.002 0.001 -25-E-202 A-D OFF OFF OFF OFF OFF
6. Stabilizer Reboiler 35-E-102
0.70 6.52 0.001 0.001 -
7. Depropanizer Reboiler 30-E-105
0.14 N/A N/A N/A 102.32%
Findings :
Entirely, the performance of heat exchangers in Grissik plant still in good condition, except for Gas/GAs Exchanger in TSA unit is needed to check again for the fouling condition, because it’s dirty factor have higher than their specification (design).
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 93 of 109
9. Gas Pretreatment & Membrane system
CALCULATION OF MEMBRANE SYSTEM
Membrane Separation Rate 0.321556 lbmole/ lbmoleDesign Value of Membrane Separation 0.511022 lbmole/ lbmole
HYDROCARBON SLIP Rate 0.030709 lbmole/ lbmoleDesign Value of Hydrocarbon Slip Rate 0.063241 lbmole/ lbmole
Findings :
The Thermal swing adsorber (TSA) system running on good condition, because the C6+ concentration at the feed gas to membrane is 29 ppm compare to the design is 39 ppm.
The membrane system separation only give separation rate is 32% compare to the design 50% of CO2 feed, so the CO2 content in gas to contactor still high than design value.
Recommendation :
Need to check again the membrane module system to upgrade the separation rate.
10. Amine System
Findings :
The absortion rate capacity of amine contactor is only 38% refer to the design capacity rate. This case caused by the flowrate of gas processing capacity of lean amine only 40% than design.
Recommendation :
Need to operate full gas processing capacity to increase absorption rate in amine contactor due to reduce the energy consumption in amine system
11. Energy Conservation
a. Energy Losses :
Based on heat balance calculation, energy losses from high temperature flue gas (more than500deg F) at Grissik is coming from Stack of GTG. Total losses is 57,821,543 Btu/hr.
STACK LOSS, Btu/hr
TEMP, Deg F
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 94 of 109
GTG
247-GT-201A 30,471,332 949
247-GT-201B 27,350,211 967
247-GT-201C 0 0
TOTAL 57,821,543 958
Actually, by utilizing economizer with stack temperature around 500 deg F, this Fluegas losses can be used to generate saturated steam about 28,000 lb/hr.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 95 of 109
b. Potential Saving :
Based on the evaluation, shows that the potential saving are coming from :
Optimize operation of WHB by reducing excess air (7 % O2 to 3% O2) increase efficiency aroumd 4 %, that will reduced LP fuel consumption to 0.06 MMSCFD
Utilized flare gas that will reduced fuel consumption to 1.0 MMSCFD
Energy Conservation Opportunities :
Optimized operation of GTG can be implemented by load shading
Optimized operation of Heater and utilized flare gas can be implemented by installing booster compressor to compress gas up to 180 psig. This fuel can be used for Gas turbine and in turn it will reduce HP Fuel consumption. The simple calculation are as follows :
WHB-saving, MMSCFD 0.06
, US $/Year 76,725.00
Flare Gas-saving, MMSCFD 1.00
, US $/Year 1,237,500.00
Total, MMSCFD 1.06
, US $/Year 1,314,225.00
*Cost to install the system for recovery gas which includes : gas compressor, KO Drum, Instrumentations , US $
3,000,000.00
Operation and Maintenance Cost , US $/year 120,000.00
Net income , US $/Year 1,194,225.00
Estimated payback period to install the system , Years
2.51
* = refer to Beak Pacifik Report - Energy Audit at Cilacap Refinery Complex
(Beak Pacific Inc. , Vancouver, Canada)
c. Emission Reduction Potentials
CO2 emission at suban gas plant is 182,886 lb/hr. its come from combustion of fuel gas at flare gas, heater, WHB and GTG. Optimized operation and utilized flare gas can reduce CO2 emission around 5 %
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 96 of 109
CO2 reduction, lb/hr
utilized flare gas 8,507.79
Total 8,507.79
Utilized flare gas will reduce CO2 emission , %
5%
12. Reporting system
Findings :
Existing daily report just for production activity it does not cover data for plant performance evaluation purpose
No data acquisition and evaluation based on daily log sheet .
Important data for plant performance not cover in daily log sheet
Recommendation :
Daily reporting must cover production activity and plant performance indicator
Regular summary of log sheet regarding plant performance should be evaluate.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 97 of 109
V. ENERGY ASSESSMENT AT RAWA OIL PLANT
5.1 GENERAL PLANT OPERATION AND PERFORMANCE
5.1.1. PLANT OPERATION
There are wells at ConocoPhillips South Sumatra area that contents oil in significant amount and high gas concentration. Rawa plant is designed to process this oil, and re inject the gases to the injection wells.
High-pressure oil & gas came firstly from wells entering the plant via manifold, before entering the production processes. The first process is High-pressure separator (HP separator). Oil, MP Gas and Water is separated in this process. MP gas (450 psig) leave the top separator and water leave the bottom of the separator and then store it in the production water tank before send to Central Ramba.
Oil & LP gas mixture goes to medium pressure (MP) separator. In MP Separator, Oil & HP gas is separated. Oil is stored to the crude oil tank before ship to Plaju. LP Gas (50 psig) compressed by LP Gas compressor (gas engine) to raise it the pressure until 450 psig.
MP gas from HP separator mix with MP Gas from LP Compressor and then the HP Compressor driven by gas turbine to rise the pressure until 1200 psig. Water content in HP Gas is reduced by glycol system before injected to the wells. The design of HP Compressor is 45 MMSCFD and about 1 MMSCFD of process gas used for fuel.
The simplified process flow diagram of Rawa field is shown at diagram in figure 1.1
1 2
3
Prod water tank
5
Oil wells
HP Compressor
Glycol System
4
LP Compressor
InjectionTo wells
4Oil
Send to Plaju and Bentayan
Gas ScrubberMP Separator
To Ramba
HP Separator
Figure 5.1. Rawa prod. Block diagram (simplified)
MP Gas
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 98 of 109
Data from production records taken from 1-10 Aug 2007 at table 1 shows that oil extracted from wells is about 300-320 barrels/day (0.001%) and water produced is 1500-1600 (0.003%). About 21 MMSCFD gas derived is re injected to injection wells while the other product, i.e. fuel gas, is sent to Ramba station.
Table -5.1 : Oil Production Data
5.1.2. GENERAL PERFORMANCE EVALUATION
The Energy Source of Rawa oil Plant is LPgas used for gas turbine compressor (LP and HP) and Glycol Regenerator which comes from LP Separator. LP Compressor driven by gas engine to increase the LP Gas pressure from 60 psi to 450 psi and HP Compressor driven by gas turbine to increase the MP gas from LP Compressor and HP Separator to 1200 psi.
Fuel flow meter only for total consumption. There is no flow meter for eachconsumers. The total consumption is 0.7 – 1.1 MMSCFD
Rawa oil processing plant doesn't have electric power generation systems inside the plant itself. Electric power derived from Ramba power plant via medium voltage lines, 11KV, 3, 50 Hz. Incoming power line then is stepped down by a transformer to 380V/220V, 3, and in turn, this voltage system is applied to all the electrical equipments and machines inside the plant. There is no KW Meter in main panel. The estimate load is about 150 KW.
For emergency purposes, there is a diesel fueled electric generator (380V, 3, 50 Hz) that has capacity of 505 KVA. This generator set needed extra maintenance due to this machine is of the old type, and have been used over a long period of time.
5.2 PERFORMANCE EVALUATION OF MAIN EQUIPMENT
The main equipment at rawa oil plant are . HP Compressor 5000-PK-100 , LP Compressor 5000-PK-101 and Glycol Reboiler 3600-HT-103
The performance of HP and LP Compressor are as follows :
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 99 of 109
HP Compressor 5000-PK-100
Table -5.2 : Performance of HP Compressor 5000-PK-100
Injection gas flow at actual condition is 39.20 MMSCFD (87 % load) compare to design (45 MMSCFD) and power require is 2860 HP compare to 3525 HP
Table -5.3 : Performance of turbine 5000-PK-100
21-Dec-07 DESIGN
HP Turbine 5000-PK-100
HP turbine 5000-PK-100
A TURBINE
Fuel gas :
flow, MMSCFD 0.85 0.89
Flue gas :
Temperature, C 1,062 900
O2, % 15 16
Excess Air, % 234 279
Eff, % 22 27
Btu/BHP 11,460 9,392
CO2 emission :
Flow, lb/hr 2,217 2,450
B COMPRESSOR
Power Required, KW 2,134 2,630
, HP 2,860 3,525
Turbine is operated at 72 % load (2860 HP) compare to design (3525 HP) and heat rate is 11.460 Btu/HP compare to the design heat rate is 10500 Btu/HP.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 100 of 109
Table -5.4 : Design performance of turbines
POWER,HP 4000 3500 3000 2500 2000 1500 1000
BTU/BHP 9500 9700 10500 11000 12000 12700 14000
LP Compressor 5000-PK-101
Table -5.5 : Performance LP Compressor 5000-PK-101 are as follows
UNITS ACTUAL DESIGN
INJECTION GAS MMCFD 6.00 15.00
ABSL.SUCTION PRESSURE (Ps) PSIA 75.00 75.00
ABSL. DISCHARED PRESSURE (Pd) PSIA 445.00 450.00
FUEL CONSUMPTION MCFD 250.00 400.00
POWER REQUIRE HP 533.05 1,439.09
ENERGY INTENSITY Btu/HP 19,541.46 11,581.36
LP compressor is operated at low load (less than 40 %) compare to design it will impact the energy intensity very high (19,541 BTU/HP compare design value 11,581 BTU/HP)
5.3 FINDINGS AND RECOMMENDATION
Findings :
A. Instrumentation
no flow gas meter for each gas consumer,
no control monitoring system that can be used to monitor the operation of the compressor from control room.
No meter indicators for electric equipments.
B. Compressor
Compressors is operated at low load for LP (less then 40%)
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 101 of 109
HP compressor is operated 70% load compare to design, the heat rate is higher then design heat rate at 70 % load.
LP compressors shut down frequently and causing increase of flare gas from 1 MMSCFD to 4-9 MMSCFD.
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 102 of 109
VI. PERFORMANCE MONITORING INDICATOR
6.1. EQUIPMENTS
6.1.1. Fired Heater
Function : converting energy from fuel gas into thermal in order to increase the temperature of process fluid
Key Performance Indicator :
Efficiency which is consist of combustion efficiency and heat transfer efficiency
Variable should be Measured :
% O2 in flue gas
Stack Gas Temperature
Ambient Temperature
Fuel gas flow, composition
Fuel gas heating value
Spread sheet :
See Appendix no.6.1
6.1.2. Waste Heat Boiler
Function : converting energy from fuel gas and permeat gas into thermal in order to produce steam and oxidize H2S from acid gas
Key Performance Indicator :
Efficiency which consist of combustion efficiency and Heat transfer efficiency
Variable should be Measured :
% O2 in flue gas
Stack Gas Temperature
Ambient Temperature
Flow and composition of fuel gas, permeat gas and acid gas
Heating value of fuel gas, permeat gas and acid gas
Spread sheet :
See Appendix no.6.2
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 103 of 109
6.1.3. Gas Turbine Generator
Function : converting energy from fuel gas to mechanical energy to produce electricity
Key Performance Indicator :
Efficiency which is consist of gas turbine efficiency and generator efficiency
Variable should be Measured :
Fuel gas flow (input)
Fuel gas heating value (LHV)
Generator Output
Oxygen content in flue gas
Flue gas temperature
Spread sheet :
See Appendix no.6.3
6.1.4. Gas Turbine Compressor
Function : converting energy from fuel gas to mechanical energy to compress sales gas
Key Performance Indicator :
Efficiency which consist of gas turbine efficiency and compressor efficiency
Energy Intensity which is representing by fuel gas divided by mechanical energy to compress sales gas
Variable should be Measured :
Fuel gas flow (input)
Fuel gas heating value (LHV)
Oxygen content in flue gas
Flue gas temperature
Suction and discharge pressure of sales gas
Flow of sales gas
Spread sheet :
See Appendix no.6.4
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 104 of 109
6.1.5. Air Compressor
Function : converting energy from electricity to compress air
Key Performance Indicator :
Actual power / Qs x ((Pd/Ps)^0.2857 – 1)
Note : Qs = air flow
Variable should be Measured :
Electricity power (input)
Pressure of compressed air
Spread sheet :
See Appendix no.6.5
6.1.6. Propane compressor
Functions : to evaporate refrigerant and to condense refrigerant vapor
Key Performance Indicator :
Coefficient of Performance (COP)
Variable should be Measured :
Electricity power (input)
Evaporation Temperature
Condensing Temperature
Spread sheet :
See Appendix no.6.6
6.1.7. Pumps
Functions : to transfer or to lift up the liquid
Key Performance Indicator :
Efficiency which consist of pump efficiency
Variable should be Measured :
Electricity power (input)
Liquid flow
Suction and discharge pressure
Spread sheet :
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 105 of 109
See Appendix no.6.7
6.1.8. Air Cooler
Functions : to cooling the fluid or to condense the vapor
Key Performance Indicator :
Overall heat transfer coefficient (U)
Variable should be Measured :
Electricity power (input)
Liquid flow
Temperature and Pressure of fluid inlet and outlet
Composition of fluid
Spread sheet :
See Appendix no.6.8
6.1.9. Heat Exchanger
Functions : to transfer heat from high temperature to low temperature of fluid
Key Performance Indicator :
Overall heat transfer coefficient (U)
Variable should be Measured :
Fluid flow
Temperature inlet and outlet of hot side and cold side
Operating Pressure of hot side and cold side
Composition of fluid
Spread sheet :
See Appendix no.6.9
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 106 of 109
6.2. SYSTEM
6.2.1. TSA System
Functions : to reduce heavy hydrocarbon content of feed gas
Key Performance Indicator :
Adsorption Rate
TSA Regeneration Rate
Variable should be Measured :
Feed gas flow
Temperature of feed gas
Pressure inlet and outlet gas
Composition of feed gas and outlet gas
Spread sheet :
See Appendices no.6.10
6.2.2. Membrane System
Functions : to reduce CO2 content of feed gas
Key Performance Indicator :
Membrane separation rate
HC Slipped rate
Variable should be Measured :
mole CO2 in Permeate Gas
Mole CO2 in Feed Gas
mole HC in Permeate Gas
Mole HC in Feed Gas
Spread sheet :
See Appendices no.6.11
6.2.3. Amine System
Functions : to reduce acid gas (CO2 & H2S) content of treated gas
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 107 of 109
A. Amine Contactor
Functions : to absorb acid in treated gas by amine liquid
Key Performance Indicator:
Absorbtion Rate
Variable should be measured:
mole-CO2 absorbed
Mole pure lean amine
Spread sheet :
See Appendix no.6.12
B. Amine Regenerator
Functions : to desorb/strip acid in rich amine by heating
Key Performance Indicator:
Amine Regeneration Rate
Variable should be measured:
CO2 content in lean amine and CO2 content in acid gas flow
Quantity of steam or fuel gas consumption
Operating temperature and pressure of regenerator
Spread sheet :
See Appendix no.6.13
6.2.4. Dehydration System
Functions : to remove moisture in treated gas by glycol
Key Performance Indicator:
Absorbtion Rate
Glycol Regeneration Rate
Variable should be measured:
Flow of gas and glycol
water content inlet and outlet of treated gas
water content in lean glycol
Operating temperature and pressure of contactor
Spread sheet :
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 108 of 109
See Appendix no.6.14
6.2.5. Dew Point Control System
A. Gas Chiller
Functions : chilling treated gas
Key Performance Indicator:
COP (heat released by fluid divide by power of compressor unit)
Variable should be measured:
Flow of sales gas and condensate
Composition of sales gas and condensate
Temperature inlet and outlet of chiller
Spread sheet :
See Appendices no.6.15
B. Low Temperature Separator
Functions : to separate of sales gas and condensate.
Key Performance Indicator:
Percentage of condensate content in sales gas compared to design value
Variable should be measured:
Flow of sales gas and condensate
Composition of sales gas and condensate
Operating Temperature and Pressure of separator
Spread sheet :
See Appendices no.6.16
6.2.6. Condensate Stabilizer
Functions : to remove light hydrocarbon from condensate.
Key Performance Indicator:
Yield of Stabilization
Stabilizer Performance
Variable should be measured:
Flow of raw condensate
Flow of treated condensate
Final Report ID-N-GN-00000-00000-00068 Energy Management Audit / Assessment for PSC CorridorConocoPhillips Indonesia Page 109 of 109