MV SWITCHGEAR SITE ACCEPTANCE TEST (SAT) REPORTS CLIENT ADDC PROJECT D10590/B2- Al Sila’a Al Gharbia Emarati Housing Project –Infrastructural Works CONSULTANT PB POWER SUB-CONTRACTOR AL HUSAM GEN. CONTR. CONTRACTOR PIVOT SUBSTATION Energisation Check List Sl No PANEL REFERENCE OK NOT OK 1 Existing permit for the Installation and testing Job is cancelled. (if applicable) 2 All Open point Earth switch are removed. 3 Switchgear Room is clean and all unwanted materials are Removed 4 All the tools and Testing equipments are removed from site. 5 HSE Clearance Obtained for Energisation 6 Fire Extinguishers are available 7 Substation Earthing done as per specification. 8 All Feeders Disconnector switch in OFF position. 9 Main source feeder MV cable tested and connected to 11 KV switchgear. 10 Final Relay setting is uploaded for all protection relays and trip test done 11 All CT Circuits are through and shorting links opened 12 All MCB in ON position 13 Emergency Light Available at site Tested By Witnessed By Approved By Approved By Signature Name Date Company AL HUSAM KEO PB POWER ADDC 2