1 Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA TMB and RAT Status Report Outline: • Current status of TMB and RAT boards • Noise measurements • Design and layout changes • Production plan
1Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
TMB and RAT Status Report
Outline:• Current status of TMB and RAT boards• Noise measurements• Design and layout changes• Production plan
2Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
TMB and RAT Current Status• Parts for full production of 516 boards are in hand• Made 29 working sets (TMB-base, RAT) • Made 40 X2V4000 mezzanine cards• Noise problems in ALCT data transmission through
RAT found at test beam and in bench tests:• Too few grounds for 80 MHz RATTMB data transmission
• Cross-talk between signals on RAT and perhaps TMB as well (M. Johnson)
• Prototype of revised RAT board and testing backplane done, noise greatly reduced
• Layout of revised TMB board well underway
3Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
Recall: TMB2004 Logic 1 on RAT2004Logic 1
Clock off
Logic 1
Clock ON
Logic 1
Clock ON &
ALCT 1 MHz
!
4Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
LVTTL (from +3.3v) Logic Levels• Typical outputs 0.4v low, 2.4v high, transition ~1.5v• Worst case output supposed to be 0.8v low, 2.0v high• Measurements showed violation of that:
5Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
Remedies• Make the grounding for RAT like any other
board in the peripheral crate:• Add one ground pin on every row of RAT pins. 651 ground
pins.
• Add backplane ground connections
• Requires more total pins:• Replace 55-pin X3 and 125-pin X18 connectors by two 110-
pin Type-A connectors
• 40 more pins, all “C” column pins used for grounding
• Also more robust alignment pins (noticed RAT alignment pins already broken before Sept beam test)
• Reduce crosstalk between long traces:• Space them further apart
• Change order of board layers to put traces next to ground plane
6Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
“Halfway Test” of Noise Reduction• RAT2005 board layout and new test
backplane
• Many ground connections to backplane, but uses existing TMB2004 board• Eliminates large inductive loops on RAT side and
greatly reduces cross-talk between traces on RAT side.
• Doesn’t eliminate large inductive loops or reduce cross-talk between traces on TMB side.
• Naïve expectation: reduce noise level up to ~factor 4:– x2 due to inductive loops
– maybe x2 more if cross-talk on RAT is also important
7Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
RAT2005 Changes• RAT2005 design changes:
• On-board 1.8v regulator for Spartan-3 core voltage:– Previously on TMB, this eliminates transmission noise
• Change buffer ICs from high-drive to balanced light-drive devices:– Reduces ground bounce from signal transitions
– Reduces inductive effects with slower edge speeds
• Additional filter capacitors
• RAT2005 layout changes:• New connector layout
• Increase trace-to-trace separation for 80 MHz buses
8Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
“Half-way Test” Peak-to-Peak Noise
0
1
2
3
4
5
6
7
8
9
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
RAT2004 Pk-Pk Noise (mV)
Num
ber o
f Sig
nals
0
5
10
15
20
25
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
RAT2005 Pk-Pk Noise (mV)
Num
ber o
f Sig
nals
0
200
400
600
800
1000
1200
0 200 400 600 800 1000 1200
RAT2004 Pk-Pk Noise (mV)
RAT2
005 P
k-Pk N
oise (
mV)
RAT2004Mean=434 mV
RAT2005
Mean=124 mV
(Reduction factor 3.5)
Little correlation (signal positions have changed)
9Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
TMB2005 Changes• TMB2005 design changes (done):
• Change buffer ICs from high-drive to balanced light-drive devices
• Delete legacy ALCT cable receiver ICs (removes “T” structures on circuit traces)
• +3.3v for RAT comes from TMB power plane instead of a separate circuit.
• Additional filter capacitors by driver ICs
• Replace 1.5v regulator with more stable type
• ALCT clock continues during hard reset (bug fix)
• TMB2005 layout changes:• New connector layout
• Increase trace-to-trace separation for 80 MHz buses
11Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
Status of TMB2005 Layout•Over last 5 weeks:
• Creation of footprints done
• Component placement done
• Routing done for most major sections
•Expect 5 more weeks of layout
Section Done Not Done
CFEB √
DMB √
ALCT √
CCB ~√
MPC √
RPC √
VME √
JTAG √
Clock √
Power √
Mezz. conn. √
Test points √
12Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
TMB/RAT Production Plan• 468+10%=515 boards each type• Agreed delivery schedule (Dec. 17):
• 10 pairs in May (preproduction)• 30 (total) by end of July• 150 by end of August• 270 by end of September• 390 by end of October• 510 by end of November• 540 by end of December
• Requirements:• Layout done by April 1• (10) Proto. boards by April 21• 3 or 4 weeks for testing 10 pairs• Then place large PCB and assembly orders to companies• Summer mass testing will need lots of students
13Endcap Muon meeting: UC Davis, Feb. 25-26, 2005 J. Hauser UCLA
Virtex-2 Mezz Cards• Principle: keep well ahead of TMB schedule• All parts in hand• First 100:
• 40 cards already assembled (no changes)
• +60 cards being assembled, arrive April 1
• Thereafter 3 cycles:• 1 month for assembly and 1 month for testing
• +120 arrive June 1 (total 220)
• +120 arrive Aug. 1 (total 340)
• +180 arrive Oct. 1 (total 520)