ELENA applied: the model of the Diputació de Barcelona (Barcelona Provincial Council) Thinking New models of urban PPPs delivering Europe 2020 Dr Domènec Cucurull Head of the Environment Department Barcelona Provincial Council Brussels, 13 October 2011
18
Embed
ELENA applied: the model of the Diputació de Barcelona (Barcelona Provincial Council) Thinking New models of urban PPPs delivering Europe 2020 Dr Domènec.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ELENA applied: the model of the Diputació de Barcelona (Barcelona
Provincial Council)
Thinking New models of urban PPPs delivering Europe 2020
Dr Domènec CucurullHead of the Environment DepartmentBarcelona Provincial Council
Brussels, 13 October 2011
BARCELONA PROVINCIAL COUNCIL AS SUPPORTING STRUCTURE OF THE COVENANT OF MAYORS
We did an analysis of the actions in the SEAPs to determine:
The type of the actions according to the size, localisation and density of the municipalities.
Priority actions.
Most feasible actions.
The actions that require higher investments.
At Barcelona province:
- 141 municipalities in the CoM
- 103 delivered SEAPs
Now it is time for the implementation!
Parameters Units Total results
Assessed SEAPs - 75
Population (2005) inhabitants 1,852,119
Expected energy savings kWh/year 3,540,479,393
Expected local renewable energy production
kWh/year 358,542,220
Expected CO2-eq reduction tn/year 1,602,378
Estimation of cost of investment € 746,775,539
SUMMARY OF SUSTAINABLE ENERGY ACTION PLANS IN THE PROVINCE OF BARCELONA
SUMMARY OF MAIN DATA
Results of the investments according to population sections
• 60% of the total investment estimated is expected in cities with more than 50,000 inhabitants.
• Small municipalities have to do an effort/inhabitant much higher than large municipalities, 10 times more than a municipality of 20,000 to 50,000 inhab. In these municipalities the role of Barcelona Provincial Council is where is more needed.
SUMMARY OF SUSTAINABLE ENERGY ACTION PLANS IN THE PROVINCE OF BARCELONA
3832124521.8202.430
0
500
1.000
1.500
2.000
2.500
3.000
< 1.000 1.000 a 5.000 5.000 a 20.000 20.000 a 50.000 > 50.000
Trams de població
€/ha
bita
nt
Results of investments according to scope of action
Local production of energy, public buildings and services, and planification are the main sectors.
SUMMARY OF SUSTAINABLE ENERGY ACTION PLANS IN THE PROVINCE OF BARCELONA
Producció local d'energia
45%
Adquisició pública de béns i serveis
0%
Altres6%
Transport4%
Planif icació20%
Participació ciutadana
1%
Equipaments i serveis
24%
Results of investments detected according to source of energy
SUMMARY OF SUSTAINABLE ENERGY ACTION PLANS IN THE PROVINCE OF BARCELONA
Renewable energy source
Expectation of CO2-eq reduction
(tn/year)% Investment
cost (€)%
Biogas 12,465 7.55 2,285,000 0.58
Biomass 30,72718.6
224,430,970 6.21
Diverse 10,718 6.50 898,000 0.23
Wind 134 0.08 165,140 0.04
Cold solar 48 0.03 495,000 0.13
Geothermal 8,803 5.34 3,052,241 0.78
Hydropower 532 0.32 1,759,613 0.45
Solar PV 80,14348.5
7350,196,385 89.00
Solar thermal 21,42812.9
910,196,530 2.59
Total 164,999 100 393,478,879 100
Results of investments detected in the sector of public buildings and services
1. Efficiency in public buildings
SUMMARY OF SUSTAINABLE ENERGY ACTION PLANS IN THE PROVINCE OF BARCELONA
Actions of energy efficiency in public
buildings
Expectation of CO2-eq
reduction (tn/year)
%Cost of
investment(€)
%
Public lighting* 4,242 34.90 6,534,730 22.01
HVAC 4,582 37.70 10,198,221 34.35
Isolation 2,283 18.78 12,334,176 41.55
Control systems 588 4.84 566,148 1.91
Renovation of equipments
460 3.78 55,230 0.19
Total 12,155 100 29,688,505 100
2. Efficiency in public lighting and traffic lights
Actions of energy efficiency in public lighting and traffic
lights
Expectation of CO2-eq reduction (tn/year)
%Cost of
investment (€)
%
Changing bulbs 15, 425 46.48 20, 288, 837 45.46
Public lighting management
8, 050 24.26 7, 453, 026 16.70
Public lighting planning
4, 604 13.87 9, 396, 913 21.06
Control systems 5, 107 15.39 7, 490, 003 16.78
Total 33, 186 100 44, 628, 779 100
SUMMARY OF SUSTAINABLE ENERGY ACTION PLANS IN THE PROVINCE OF BARCELONA
And how to finance all these actions?
?
FINANCING SOURCES OF THE COVENANT OF MAYORS
Own budget committed as Supporting Structure of the Covenant of Mayors
EIB funds through credits with local banks to promote renewables and energy efficiency projects
EU subsidy: technical assistance ELENA to promote the implementation of SEAPs