Top Banner
Electricity Network Connectivit Between the GCC Countries Presented By: Adnan I. Al- Mohaisen May 17, 2005
16

Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

Dec 26, 2015

Download

Documents

Spencer Hunt
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

Electricity Network ConnectivityBetween the GCC Countries

Presented By:Adnan I. Al-Mohaisen

May 17, 2005

Page 2: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

2

BIRTH OF THE GCC POWER GRID

• Originated in the early 1980’s by a local GCC committee from the electricity sector.

• In 1986 the first project study was conducted by a committee from the GCC in coordination with the Kuwait Research Institute and King Fahad University of Petroleum and Minerals.

• The study was updated in 1990 by Gulf Investment Bank and SNC-Lavalin to confirm the interconnection was economical and financially viable.

• In 2003 another study update was undertaken as a final preparation for the project financing and tendering, in which the following topics were covered:

•Techno-Economic Analysis•Market Study•Financial Analysis•Interconnection Agreement•Implementation Strategy

Page 3: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

GCC INTERCONNECTION AUTHORITY

• Established in July 2001 by a Royal Decree No. M/21.

• Owned by the six GCC Countries the authorized share capital is ($US 1,100,000,000) divided into (1,100,00) shares of ($US 1,000) each share.

• The Authority is managed by a (twelve member) Board of Directors; each member country is represented by two members. The Chairmanship is rotated among the member states every three years.

• The official domicile of the Authority is Dammam, with the Control Center to be located in Ghunan, Saudi Arabia.

• The primary objective of the Authority is to:• link up the power grids of the six GCC countries• operate and maintain the interconnection

Page 4: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

INTERCONNECTION SHARE CAPITAL

Founders No. of Shares Nominal Value Percent

United Arab Emirates 169 ,400 $169 ,400 ,000 15 .40 %

Kingdom of Bahrain 99 ,000 99 ,000 ,000 9.00 %

Kingdom of Saudi Arabia 347 ,600 347 ,600 ,000 31 .60 %

Sultanate of Oman 61 ,600 61 ,600 ,000 5.60 %

State of Qatar 128 ,700 128 ,700 ,000 11 .70 %

State of Kuwait 293 ,700 293 ,700 ,000 26 .70 %

1,100 ,000 $1,100 ,000 ,000 100 .00 %Total

Based on the 1990 Project Study it was determined that the share of the cost of the interconnection will be the present worth of the capacity savings.

Page 5: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

INTERCONNECTION LINK

• The interconnection is to be constructed in 3 phase, namely:

PhaseI

PhaseIII

Phase

II

• Phase I will interconnect Al-Zour (Kuwait), Al-Fadhili, Ghunan, Salwa (KSA) and Doha South (Qatar) with a 400 kV OHL, and a 400 kV Land & Submarine cable with Al-Jasra (Bahrain).• Phase III will interconnect Salwa and Shuwaihat with 400 kV OHL and Al-Ouhah and Al-Waseet in Oman with a 220 kV OHL.

• Phase II will integrate the UAE system with a 400 kV OHL from Shuwaihat to Al-Ouhah.

Page 6: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

INTERCONNECTION CRITERIA

BAHRAIN

U.A.E.

EMIRATES NATIONAL GRID

AL OUHAH 220kV 220kV

AL FADHILI 400kV

JASRA 400kV GHUNAN

400 kV

600MW

SALWA 400kV

SALWA 400kV

QATAR

750MW

90km 90km

DOHA SOUTH SUPER 400kV DOHA SOUTH SUPER 400kV

290km 290km

150km 150km

SHUWAIHAT 400kV 400kV

900 MW

OMAN

OMAN NORTHERN GRID

AL WASEET 220 kV

400MW

52km

112km

100km 100km

KUWAIT AL ZOUR

400kV AL ZOUR

400kV

310km

1200 MW SAUDI ARABIA

SEC - ERB HVDC BACK -TO -BACK

1200MW

Page 7: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

SINGLE-LINE DIAGRAM

Page 8: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

Upon the completion of Phase-I and the reduction of generation capacity the total Upon the completion of Phase-I and the reduction of generation capacity the total cost savings rate of return after 4 years from operations is 2.5 billion US Dollars.cost savings rate of return after 4 years from operations is 2.5 billion US Dollars.

•PHASE I•: •CUMULATIVE PW OF BENEFITS AND COSTS IN •$ MILLION •(•Jan•. •2008• @ •6%•)

•0

•500

•1000

•1500

•2000

•2500

•3000

•200

8•2

010

•201

2•2

014

•201

6•2

018

•202

0•2

022

•202

4•2

026

•202

8

•Year

• Cu

mu

lati

ve P

W o

f

• Ben

efit

s a

nd

Co

sts

•Phase I Benefits •Phase I Costs

BENEFITS & COSTS

Page 9: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

Upon the completion of Phase-III the total cost savings rate of return after 3 years Upon the completion of Phase-III the total cost savings rate of return after 3 years from operations is 3.35 billion US Dollars.from operations is 3.35 billion US Dollars.

•PHASE I&III •: •CUMULATIVE PW OF BENEFITS AND COSTS IN •$ MILLIONS •(•Jan•. •2008• @ •6%•)

•0

•500

•1000

•1500

•2000

•2500

•3000

•3500

•200

8•2

010

•201

2•2

014

•201

6•2

018

•202

0•2

022

•202

4•2

026

•202

8

•Year

• Cu

mu

lati

ve

PW

of

Be

ne

fits

an

d C

os

ts

•Phase I & III Benefits •Phase I&III Costs

BENEFITS & COSTS

Page 10: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

PROJECT ECONOMICS

•The capital cost of constructing Phase I estimated at US$ 1,189 million is depicted below:

•It is further estimated that it will cost approximately $ 30 million annually to operate and maintain the Grid:

Total O&M Cost

14646

301

Lot

Transmission LinesCable SystemSubstations

Converter StationControl Station

Total 1,189

39229317230230

Capital Cost

•The estimated cost for constructing Phase III is $US 137 million. •Although the construction of Phase II is not under GCCIA task it is estimated that its construction to be approximately $US 300 million.

Page 11: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

PROJECT ECONOMICS

•The GCC Grid is expected to reduce the amount of new generation capacity required by the GCC member states by sharing the reserve capacity that needs to be maintained by each system to ensure reliability and provide protection against outages. The capacity benefits to Year 2028 are shown below:

Load (MW) Total Installed Capacity Reserve (MW)

93 781 105 781 MW 12 085

Isolated System

Interconnected System

Load (MW) Total Installed Capacity Reserve (MW)

93 781 100 726 MW 6 945

•The cumulative benefit in MW of the interconnected system as opposed to isolated systems will be 5,113 MW.

Page 12: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

INTERCONNECTION BENEFITS

• Reduce generation reserves;

• Provide power exchange and strengthens supply reliability;

• Improve the economic efficiency of the electricity power systems;

• Strengthens operational efficiency;

• Promoting utilities to construct larger generation units to share extra generated power;

• Provide opportunities for industrial customers and utilities to shop around for more attractive supply of power;

• Adopt technological development and use the best modern technologies;

• Providing long-term environmental advantages by reducing waste emissions from increasing generation plants.

Page 13: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

GLOBAL INTEGRATION

• The technical and economical feasibility study for the GCC Interconnection has been proven.

• The GCC Interconnection will enhance the Power Systems of the GCC Countries.

• The GCC Countries will be a significant part of the Pan-Arab Grid.

• The GCC Interconnection is the main gateway towards a Regional and Pan-Arab Power Pools.

• The Power Grid is a fundamental step leading to the liberalization of regional power market.

Page 14: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

PROJECT STATUS

• September 2004 SNC-Lavalin of Canada was hired to perform the Tendering and Adjudication for the Phase I Project.

• Thirty three (33) out of the sixty five (65) companies were pre-qualified; where some companies qualified for only one lot and some qualified for all five lots.

Substations

HVDC

OHL

Cable

Control

4

22

6 7

4

• Pre-qualified companies were from local GCC and international countries.

• GCCIA will engage an international consulting firm affiliated with a local GCC firm for the Supervision of the Construction of the Phase-I Project.

Page 15: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

PROJECT SCHEDULE

TASKS DATE

Pre-Qualification Exercise August 2004

Pre-Tender Meetings March 2005

Tender Submittals June 2005

Technical Bid Opening June 2005

Commercial Bid Opening TBA

Evaluations August 2005

Contract Awarding October 2005

Operations Commencement 1st Qtr 2008

Page 16: Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.

For further information you can

access our website at:

www.gccia.com.sa

THANK YOU