ELECTRICAL INSTALLATIONSGeneral Scope Of WorksSECTION
IDescription A. The works to be executed under the contract shall
be in accordance with the FIDIC Conditions of Contract for
Electrical and Mechanical Works, Part I - General Conditions and
Part II Special Conditions, The Specifications, Schedule of Prices
and Drawings as enumerated in the Appendix to the Specifications
and such other drawings or details as may be furnished or approved
I writing by The Employer.Scope of WorksB. The Works shall
include:1. Metering and panel boards.2. Cables3. Internal and
external lighting4. Power outlets.5. Complete wiring for lighting,
power and telephones.6. Testing and commissioning of the entire
electrical system.7. Payment of all testing and inspection
fees.General ProvisionsSECTION 2Extent of WorksA. Provide all
labour, materials, services, Contractors equipment and everything
whether of a temporary or permanent nature, required for the
supply, installation, testing, setting to work and maintenance of
the works, so far as the necessity for providing the same is
specified in or reasonably to be inferred from the
Contract.Variations and OmissionsA. Do not alter any of the works
except as directed in writing by the Employer.B. Carry out any
variation and omission authorized by the Employer as though the
same were stated in the Specifications.C. Before carrying out any
variation which will, in the opinion of the Contractor, involve any
increase or decrease in the Contract Price, notify the Employer to
that effect as soon as possible and request the Employers
confirmation of instructions.D. On receipt of the Employers
confirmation of instructions in respect of any variation, proceed
immediately to carry out such instructions. Do not delay the work
pending agreement of price.Codes and StandardsA. Do complete
installation in compliance with the National Electrical Code,
Latest Edition, Occupational Safety and Health Standards, the
Electricity and Telephone Utilities and other Government Agencies
requirements, except where specified otherwise.Government Agencies
- Permits and FeesA. Submit to Electrical Inspectorate, Factory
Inspectorate, etc. necessary number of drawings and specifications
for examination and approval prior to commencement of work.B. Pay
associated fees.SubmissionsSubmit the Employer for review, such
drawings, product data and samples as specified, or as the Employer
may reasonably require.Tender Drawings and SpecificationsA. Tender
drawings are generally diagrammatic but are sufficient to enable
tenders to be obtained.B. Any doubts as to the full intent of the
drawings and the specifications shall be resolved by the Tenderer
prior to completion of the Tender.C. In case of variations between
the drawings and the specifications the drawings take precedence.D.
Detail drawings shall be take precedence over small scale
drawings.Contract Drawings, Specifications and other DocumentsA.
Notwithstanding any dimensions which may be given on the drawings,
the contractor shall check, at his own expense, all dimensions
required for the manufacture of any materials or products.B. The
Contractor shall draw to the Employers attention any significant
discrepancies between drawings or drawings and specifications
before assuming a particular interpretation.C. In case of
variations from Codes, Standards, Statutory Regulations, etc., the
drawings and specifications shall take precedence.D. The Contractor
shall refer any such discrepancies to the Employer before assuming
a particular interpretation.Installation DrawingsA. The Contractor
shall, prior to manufacture and installation, prepare installation
drawings for all the electrical services work.B. Two (2) prints of
each installation drawing shall be marked For Examination and
issued to the Employer for approval.C. When drawings are returned
with no comments, the Contractor shall issue one negative and two
prints of each drawing to the Employer for stamping For
Construction.D. When drawings are returned with comments, the
Contractor shall amend the drawings and re-submit for examination.
The procedure for re-submittal shall be the same as an initial
submittal. Each re-submitted drawing must be treated as a
revision.E. Irrespective of whether or not the drawings have been
examined by the Employer, responsibility for errors shall remain
with the Contractor and no additional costs whatsoever will be
payable as a result of any error.F. The Contractor shall correct
any discrepancies, errors or omissions in the drawings and other
particulars supplied by him, whether or not such drawings and
particulars have been examined by the Employer.G. The following
drawings shall form the installations drawings:1. Wiring diagrams
for electrical equipment. Wiring diagrams shall be prepared for all
plant requiring electrical connections. Where manufacturers
original drawings are used, they shall be specific to the relevant
plant and all references to optional features, etc. shall be
deleted. All plant and equipment requiring electrical connections
shall have adequate wiring diagrams fixed inside panels, etc.2. Any
details drawings or manufacturers drawings required prior to or
found necessary during erection, manufacturer or progress of the
works.3. Detail drawings of all fabricated steelwork, brackets,
supports and all other items of a similar nature.4. Detail plans,
sections and elevations showing all required builders work,
including size and position of all bases, plinths, holding down
bolts, chases, trenches etc., in the structure or building fabric
related where applicable to the column/building grid lines, to be
built in or attached to the structure.Working and As-built
DrawingsA. The Contract Drawings shall not be considered to be the
working drawings.B. Sepia copies of the Contract Drawings can be
provided at current rates if these are considered by the Contractor
to be a suitable base from which the working drawings can be
prepared.C. The Contract Drawings show the location in principle
for the various services. The detailed position shall be determined
and coordinated by the Contractor and shown on the working
drawings.D. The Contractor shall keep a spare set of working
drawings on site in order that all conduit runs, positions of
points, etc. can be checked by the Employer.Working and As-Built
DrawingsA. The Contractor shall adjust his working drawings to
allow for site tolerances and discrepancies and changes in building
layout where the principle and intent of the design of the services
are not affected.B. Where the principle and intent of the design
are affected, notice of the conflict shall be given to the
Employer.C. The Employer shall have the right at all reasonable
times to inspect on the Contractors premises all drawings for any
portion of the works.D. The Contractor shall submit marked-up
working drawings and other information to reflect progressive
as-built status of the works at regular intervals, or as required
by the Employer.E. The Contractor is responsible for all errors,
omissions and deviations in marked-up drawings from actual as-built
status of the works.Product Data and SamplesA. Where appropriate,
manufacturers standard catalogue sheets, drawings, or other
descriptive data may be submitted in lieu of samples.B. Above will
be accepted if they conform to the following:1. Delete information
which is not applicable.2. Provide all additional information
applicable.C. Contractors responsibility for errors and omissions
and deviations in submissions from the requirements of Contract
Documents is not relieved by the Employers review of submission.D.
Until the Employer gives written acceptance of specified
deviations, work involving relevant products may not
proceed.Builders WorkA. Builders work which is considered normal
for the trade is included in this contract.B. Builders work shall
mean:1. Cuttings and forming of holes, chases and recesses for
services through walls, floors, ceilings, partitions, roofs, etc.
and making good.2. Buildings-in of brackets, ragbolts or other form
of services suspension, or plant fixing.3. Formation of concrete
bases, plinths, etc.4. Building of concrete manholes, trenches,
etc. for covered distribution.C. Excavation of trenches for buried
services and filling-in of same after services are laid.D. Builders
work drawings shall be prepared by the Contractor which show all
builders work requirements. The drawings shall show overall weight
of items of equipment where necessary.E. Openings in structural
concrete shall be incorporated during the design. The Contractor
shall check that services can be installed in the openings
provided.F. The supervising of all required builders work shall be
carried by the Contractor to meet the requirements of the Contract
Programme.G. No holes shall be cut in any steelwork, reinforced
concrete or precast concrete without express permission in writing
from the Employer.H. Holes shall not be cut in precast pre-stressed
concrete under any circumstances.I. Any holes in steel-work that
are approved must be drilled. Burning holes by means of welding
equipment shall not be permitted unless by the Employers special
written approval.Operating and Maintenance InstructionsA. The
Contractor shall include for editing, printing, binding and
producing three (3) copies of operational and maintenance manuals
to the approval of the Employer.B. Prior to printing, two (2) draft
copies of each booklet shall be submitted for the Employers
approval, one (1) month prior to the contract completion.C. The
Employer reserves the right to modify the draft copies prior to
printing without incurring additional cost to the tender price.D.
The manuals shall be completed in sufficient detail to enable the
employers or building users trained staff to maintain, dismantle,
reassemble and adjust all parts of the works.E. Completed manuals
shall be of a standard equal to this specification with durable
binders and properly printed covers. F. The manuals shall have a
comprehensive index and he complied into sections for each system
of the installation.Certificates from Governments AgenciesA.
Furnish certificates of acceptance from the relevant Government
Agencies on completion of Works.
Environmental ConditionsA. Equipment located outdoors shall
generally be considered located in a tropical area subject to
severe weather conditions. B. In addition, hazardous area or other
special conditions will be specified in such cases.C. The equipment
shall be capable of operating in specified conditions without
damage.FinishesA. Finish all equipment to SpecificationsEquipment
IdentificationA. Identify electrical equipment with nameplates and
labels to Specifications.Wiring IdentificationB. Identify wiring
with permanent identifying markings, either by number or colored
plastic tape on both ends of phase conductors and other circuit
wiring.C. Maintain phase sequence and colour coding throughout.D.
Use colour coded wires in control and communication cables, matched
throughout the system.Conduit and Cable IdentificationA. Colour
code conduits and metallic sheathed cable to Specifications.Wire
TerminationsA. To be suitable for copper conductors.Manufacturers
LabelsB. To be visible and legible after equipment is
installed.ProtectionA. Protect exposed live equipment during
construction for personnel safety.B. Shield and mark all live parts
LIVE 230 VOLTS or with appropriate voltage in English.Inspection
and Testing during ManufactureA. Where required, obtain permission
for the Employer to inspect and test on the manufacturers premises
any plant to be supplied under the Contract.B. In the case of tests
on the premises of the Contractor or any Sub-Contractor, provide
such assistance, apparatus, etc., as may be reasonably demanded to
conduct such tests efficiently.C. Where applicable, furnish to the
Employer duly certified copies of tests during manufacture.D. Such
inspections and tests if made shall not release the Contractor from
any obligation under the Contract.DefectsA. Correct as soon as
possible any defects arising from the defective design (other than
a design furnished by the Employer and for which the Contractor has
disclaimed responsibility in writing within a reasonable time after
the receipt of the Employers instructions) materials or workmanship
that may develop at any time up to the expiry of the Defects
Liability Period.B. If required by the Employer, search for the
cause of any defect or fault under the direction of the
Employer.Tests on CompletionA. Before the Works are taken over by
the Employer, conduct and pay for all tests specified including
tests of:1. All grounding systems.2. Equipment insulation.3.
Polarity.4. Phase sequence.5. Protective devices.6. Lighting.7.
Loading.8. Signal circuits and systems.B. Carry out tests in the
presence of the Employer or his representative.C. Provide
instruments, metres, equipment and personnel required to conduct
tests during and at conclusion of project.D. Submit test results.E.
Give to the Employer in writing 21 days notice of the date after
which tests on completion will commence. Unless otherwise agreed,
the tests shall take place within 10 days of the said date on such
day as the Employer shall in writing notify the Contractor.F.
Repeat within a reasonable time, the appropriate tests of any
portion of the works which had failed to pass the said tests and
bear all reasonable expenses to which the Employer may be put by
the repetition of the tests.G. Except where otherwise specified,
provide such materials as may be requisite and reasonably demanded
to carry out such tests efficiently.H. Carry out the tests in the
following sequence:1. visual inspection2. continuity of branch
circuit conductors3. continuity of protective (grounding)
conductors, including main and supplementary equi-potential
bonding4. earth electrode resistance 5. insulation resistance:i.
use 500V megger for equipment up to 350V ratingii. USE 1.000V
megger for equipment of 350-660V rating6. insulation of site-built
and factory-built assemblies7. protection by electrical operation8.
insulation of non-conducting floors and walls9. polarity10. earth
fault impedance 11. earth leakage protective devices12. phase
sequence13. prospective short circuit current to terminal and
intermediate equipment14. load balance:I. Submit, at completion of
work, a report listing all phases and neutral currents on relevant
panel boards operating under normal load. State hour and date on
which each load was measured and voltage at time of test.SECTION
3GENERAL - PART 1ScopeA. The scope of this work includes:1.
Trenching and backfilling2. Underground ducts3. Concrete
foundations for lighting poles4. Direct buried cables.PART 2 -
PRODUCTSPVC DuctsA. Provide the following or equal approved:1.
Schedule 40 rigid PVC ducts for general work below grade.2.
Schedule 80 rigid PVC ducts in locations where ducts are subject to
physical damage.B. Provide the following two types of ducts:1. Type
I duct suitable for direct burial without concrete encasement.2.
Type 2 duct suitable for concrete encasement.3. Type I duct shall
be capable of withstanding continued loading likely to be
encountered after installation.4. Ducts shall be designed for
connection to couplings, fittings and boxes by the use of a
suitable solvent-type cement.5. Ducts shall be free from cracks,
holes and other defects.TrenchesA. Provide trench of sufficient
width to allow proper laying and jointing of ducts.B. Grade trench
bottom and remove all stones 75 mm diameter and larger.C. Do not
alter trench routes without the Employers permission.DuctsA. Grade
ducts away from buildings to prevent water entering buildings.B.
Make all joints waterproof according to the solvent manufacturers
instructions.C. Where indicated, provide a minimum of 75 mm
concrete encasement to PVC ducts.BackfillingA. Backfill trenches
using selected granular fill free from stones or organic matter and
placed in layers not exceeding 100mm thickness.B. Where necessary
compact backfill by hand to avoid damage to ducts.C. Compact until
fill has reached a density equivalent to 95% Standard Proctor
DensityConcrete Foundations for Lighting PolesA. Provide
foundations as specified on the Drawings.Grounding ConnectionsA.
Provide connectors of type specified.B. Carry out grounding
connections in the manner specified.C. The approval of the Employer
shall be obtained before grounding connections are covered up or
buried.Direct Buried CablesA. Where indicated, provide cables of
size and type specified for direct burial.B. Install cables as
indicated on the Drawings.C. The approval of the Employer shall be
obtained before cables are covered up or buried.INSTALLATION OF
CABLES IN TRENCHES AND DUCTSSECTION 4PART 1 - GENERALA. Payment for
the supply and installation of cables in trenches and ducts shall
be per linear meter of trench.PART 2 - PRODUCTSGeneralA. Use bright
colour electrical marker tape with the label WARNING - BURIED
ELECTRICAL CABLE in all electrical trenches.PART 3
EXECUTIONTrenching and BackfillingA. Trench along routes for ducts
and cables as shown on drawings.B. Before commencing work,
establish location and extent of existing underground cables in
areas of excavation. Use cable detector to locate underground
cables. Avoid damaging existing underground cables throughout this
contract. Make good and pay for damage to existing cables resulting
from work.C. No guarantee is given on completeness or accuracy of
known underground cable indicated.D. Do not commence backfilling
until area of work to be backfilled has been inspected and approved
by the Employer.E. Areas to be backfilled shall be free from any
debris.Trenching and BackfillingA. Place and compact fill materials
in continuous horizontal layers not exceeding 300mm loose depth.B.
Use common or granular backfill material as indicated or
directed.C. The surface shall be restored to its original level and
condition.D. Maintain one diameter width of duct separation minimum
between ducts in common trench.Cable Installation in DuctsA.
Install cables in ducts as indicated.B. Do not pull spliced cables
inside ducts.C. Install multiple cables in duct simultaneously.D.
Use approved lubricants of type compatible with cable jack to
reduce pulling tension.E. Before pulling cable into ducts and until
cables are properly terminated, seal ends of cables with moisture
seal tape.F. After installation of cables, seal duct ends with duct
sealing compound.TestingA. Perform tests in accordance with Section
2.B. Perform tests using qualified personnel only. Provide
necessary instruments and equipment to demonstrate that:1. Circuits
are continuous and free from short circuits and grounds;2. Circuits
are free from unspecified grounds; that resistance to ground of
circuits is not less than 50 mg ohms.3. Provide the Employer with a
list of test results showing location at which each test was made,
circuit tested and result of each test.PANEL BOARDSSECTION 5PART 1
- GENERALType of Panel boardsA. This specification covers
distribution panel boards where applicable as well as lighting and
appliance panel boards.B. Operating environment Tropical with 32
degrees C average ambient and 92 % R.H.SubmittalsA. Within one (1)
month of order being placed submit manufacturers specifications on
all products listed in this Specification.PART 2 -
PRODUCTSEnclosuresA. Provide galvanized sheet steel cabinet type
enclosures, minimum 14 gauge thickness, in sizes and NEMA types as
indicated.B. Design for surface or recessed mounting as appropriate
with ample wiring gutters on top, sides and bottom for all wires
and connections.C. Provide sufficient number of adequately sized
knock-outs for termination glands.D. Provide enclosures fabricated
by same manufacturer as panel boards, and which mate properly with
panel boards to be enclosed.E. Provide Tropicalised, anti-corrosive
treatment and baked gray enamel finish.F. Equip cabinet doors with
flush locks.G. Provide with interior circuit-directory frame and
card with clear plastic covering.Panel boardsA. Construct with
solid copper busbars, securely mounted and braced.B. Provide solder
less lugs on the main bars, approved for copper conductors.C.
Provide full sized neutral bus with suitable lugs for feeders
requiring neutral connections.D. Provide a bare uninsulated
grounding bar, bolted to enclosure, with suitable lugs for feeders
requiring grounding connections.E. Provide moulded case main and
branch circuit breaker for each circuit.F. Provide all circuit
breakers from one manufacturer.Circuit BreakerA. Provide moulded
case circuit breaker, tropicalised for 90 % relative humidity at
40oC ambient.B. All breakers shall provide over-current and short
circuit protection.PART 3 - EXECUTIONInstallationA. Make good any
damage to panel finishes arising during handling and erection.B.
Provide panel schedule identifying the circuits associated with
each breaker.C. Submit copy of panel schedule to the
Employer.TestingA. Arrange for testing and acceptance of the panel
boards in the manner approved by the Government Electrical
Inspectorate or relevant Authority.B. Submit copy of Acceptance
Certificates to the Employer.WIRES AND CABLESSECTION 6PART 1 -
GENERAL A. The scope of work includes supply and installation of
all wires and cables, together with connector and other accessories
necessary to complete all circuitry indicated by the Drawings and
schedules.PART 2 - PRODUCTSA. Material shall confirm to the
following or equal approval:B. PVC Wire & Cable (non-armoured)
- BS 6004 - 1990C. PVC Wire & Cable (armoured) - BS 6346 -
1989.D. XLPE Wire and Cable - BS 5467 - 1989Low Voltage Cables
& Wires (Lighting and Power)E. Low voltage wires and cables
shall be stranded copper, 70o C, PVC insulated and 90o C, XLPE
insulted, 600/1000 volt grade, with steel wire armour and PVC
sheath where specified.F. No wire shall be smaller than 2.5
sq.mmTelephone WireA. Tinned 22 AWG (0.645 mm) solid round copper
wire, polythylene insulated, fully identified with colour coding,
with overall polyvinyl jacket.Material Schedule B. Provide wires
and cables listed in schedule or shown on Drawings.PART 3
EXECUTIONGeneral InstallationA. Install cables, prepare ends and
terminate.B. Sizes of wires and cables are indicated on the
drawings and schedules.C. Install wires and cables as indicated on
the Drawings or in an approved manner as agreed with the
Employer.D. Use an extra conductor core in each circuit for
equipment grounding. In the case of armoured cables, the armour
shall provide equipment grounding on condition that cable
terminations are made in an approved manner.E. Carry out all wiring
in the loop in system. No joining is permitted. All main feeder
circuits shall run their entire length in continuous pieces without
joints or spices.F. Contractor shall make use of approval wiring
methods using raceways, wireways, and approved methods of
support.G. Wiring clipped to surface will not be accepted without
the Employers approval.INTERIOR BUILDING LIGHTINGSECTION 7PART 1
GENERALManufacturer A. Provide materials from manufacturers of
interior lighting fixtures to types required, whose products have
been in satisfactory use in similar service for at least 5
years.Fixtures CatalogueA. Fixture products of manufacturers other
than those specified may be proposed, provided they are of similar
design, efficient and are approved by the Employer.SubmittalsA.
Submit two (2) copies of manufacturers data on lighting fixtures,
including photometric data, to the Employer.B. Submit samples of
fixtures for the Employers approval where requested.PART 2
PRODUCTSGeneral A. Provide fixtures complete with housing, lamps,
ballasts and with all fittings and wiring.B. Provide florescent
fixtures with energy efficient lamps.HID Lamp BallastA. Provide
high power factor energy efficient ballasts (90% min.).Fluorescent
Lamps BallastA. Provide ballasts with high power factor (90% min.),
rapid-start, low-noise features, Class P, with internal thermal
protection or with electronic ballast (whichever is specificed)Exit
SignsA. Provide illuminated exit signs with integral battery
packs.B. Construct housing of 20-gauge steel and finish in baked
white enamel.C. Equip for pendant mounting and 115 volt
operation.D. Provide green EXIT letters stencil type face. Do not
provide glass face.E. The lettering for these signs shall not be
less than 127 mm in size.F. Equip with sealed re-chargeable Ni-Cad
battery pack and charger unit, capable of standby operation for at
least 90 minutes.G. Equip with fluorescent lamps.PART 2
PRODUCTSFixtures TypesA. Refer to lighting layout drawing and Bill
of Quantities.PART 3 EXECUTIONInstallationA. Install fixtures in
accordance with manufacturers written instructions.B. Fasten
fixture securely to structural support; ensure that solid pendant
fixtures are plumb.C. Protect installed fixtures from damage during
remainder of construction period.D. Clean fixtures of dirt and
debris upon completion of installation.Field Quality ControlA. Test
fixtures upon completion of installation.B. Correct malfunctioning
units; remove and replace with new units where necessary and
retest.C. At the time of Taking-Over, replace lamps which are
noticeably dimmed after Contractors use and testing.D. Replace
defective and burnt out lamps for a period of one year after date
of Taking-Over.GroundingA. Provide tight equipment grounding
connection to each fixture and standard as indicated.EXTERNAL
LIGHTINGSECTION 8PART I GENERALManufacturerA. Provide materials
from manufacturers of outdoor lighting fixtures of types required,
whose products have been in satisfactory use in similar service for
at least 5 years.Fixtures CatalogueA. Fixture products of
manufacturers, other than those specified may be proposed,
providing they are of similar design, equally efficient and are
approved by the Employer.SubmittalsA. Submit two (2) copies of
manufacturers data on lighting units including poles, brackets,
luminaries and lamps to the Employer.B. Submit photometric data for
each fixture to the Employer.Material Delivery Storage and
HandlingA. Deliver fixtures and fittings wrapped in factory
containers.B. Store and protect all materials from construction
traffic and debris.C. Handle lighting poles, brackets, etc.
carefully to prevent breakage, denting and damage to finish.PART 2
PRODUCTSGeneralA. Provide fixtures complete with housing, lamps,
ballast and all fittings and wiring.B. Comply with additional
fixture requirements shown on drawings.Lighting PolesA. Provide
metal, raceway-type lighting poles. Equip with grounding
connections readily accessible from hand hole; and complying with
the following features:Material:Galvanised steel or Aluminium
(extruded or spun) as specified on the
Drawings.Configuration:Anchor base type with hand hole and
cover.Accessories:Anchor bolts, etc., as recommended by pole
manufacturers.BracketsA. Provide metal brackets of sizes and types
to accommodate fixture attachments:Material:Galvanised
steel.Pole-Mounted FixturesA. Provide the fixtures as specified in
the Drawings and Bills of Quantities.B. Provide photoelectric
control including photocell to individual fixtures or where
specified, group control of fixtures to be lighting contactor with
photoelectric control.PART 3 EXECUTIONInstallationA. Install
lighting units in accordance with manufacturers written
instructions to ensure that units fulfill requirements.B. Use belt
slings or rope (not chain or cable) to raise and set finished poles
to protect finishes.C. Set poles plumb. Support adequately during
anchoring to foundations.Field Quality ControlA. Test lighting
system upon completion of installation.B. Correct malfunctioning
units; remove and replace with new units where necessary and
retest.C. At the time of substantial completion, replace lamps
which are noticeably dimmed after Contractors use and testing, as
judged by the Employer. Replace defective and burnt out lamps for a
period of one year after date of substantial completion.Grounding
A. Provide tight equipment grounding connection to each fixture and
pole as indicated.GROUNDING SECTION 9PART 1 GENERALScopeA. The
scope of the work includes grounding of the following:1. All
non-current carrying equipment enclosures.2. Panel boards.3.
Transformer neutrals.B. The extent of the work is indicated on the
Drawings.PART 2 PRODUCTSStandardsA. Unless otherwise indicated,
grounding shall conform to BS CP 1013 : 1965.Copper ConductorsA.
Bare, stranded, tinned, soft annealed, sized per drawings.Rod
ElectrodesB. Copper clad steel 10 mm diameter by 3 meters
long.Copper Flexible Jumper StrapsA. Protect braid with copper bolt
on both ends.B. Use flexible jumper for grounding hinged doors to
main frame of electrical equipment enclosures.Panel Ground BarsA.
Provide full size ground bars in each lighting and appliance panel
board.Field WeldingA. Use Cadweld joints for all below-ground
connections.B. Obtain Employers approval for other types of
joints.Bolted ConnectorsA. Use bolted connectors for grounding
connections to equipment provided with lugs.PART 3
EXECUTIONGeneralA. Install accessories to manufacturers
instructions.B. Protect any exposed grounding conductors from
damage by enclosing in metallic duct.C. Provide computer circuits
with a separate ground bar.Inspection A. Do not proceed with work
until conditions are satisfactory.B. Do not cover up work until it
has been inspected and approved by the Employer.TestingA. Carry out
ground resistance test on completion.B. Where tests show resistance
to ground is over 3 ohms take steps to reduce resistance to 3 ohms
or less by driving additional electrodes and/or chemical treatment
of soil; re-test to check compliance.RACEWAYS FOR BUILDING
WIRINGSECTION 10PART I GENERALTypes of RacewaysA. Types of raceways
in this section include:1. Electrical metallic tubing (EMT)2.
Surface metal raceways3. Rigid PVC conduit.SubmittalsA. Before
commencement of work, prepare samples of material to used for the
Employers approval.PART 2 MATERIALSGeneral A. Provide metallic
conduit, tubing and fittings of types, grades and sizes for each
service indicated. Where types and grades are not indicated,
provide proper selection determined by Contractor to fulfill wiring
requirements, and complying with, applicable portions of IEE
Regulations or other approved code for wireways.EMTB. Electrical
Metallic Tubing (MT) to the following or approved:C. CSA C22.2 No.
83 1976EMT FittingsA. Use Type 2 fittings for concrete tight
connections.B. Use Type 3 fittings for other miscellaneous
connections.PVC Conduit and TubingA. Provide rigid PVC conduit and
tubing to the following or approved equal CSA C 22.2 No. 136
1966.B. Use NEMA Type I or equal approved material for encasement
in concrete.C. Use NEMA Type 2 and Type 3, Schedule 40 PVC or equal
approved for normal above ground duty.PVC Conduit and Tubing
FittingsA. Match with conduit/tubing type material.Surface Metal
RacewaysA. Provide surface metal raceways of sizes indicated.B.
Open type, constructed of heavy gauge Aluminium with knockouts for
strapping cables along the route.PART 3 EXECUTIONInstallationA.
Co-ordinate with other work as necessary.B. Level and square
raceway and install at proper elevations.C. Complete raceway
installation before installing corresponding cable/wires.D.
Wherever possible, install horizontal raceway runs above water
piping.E. Ensure that all raceways are free of obstruction and
leave fish-wires in conduit/tubing for future pulling-in of wire
and cables.F. In exposed areas install all raceways embedded in
concrete/blockwork unless physical constrains dictate otherwise.G.
The Employers permission must be obtained for all surface wiring or
surface installation of raceways.12.37ELECTRICAL BOXES AND
FITTINGSSECTION 11PART 1 GENERALType of MaterialA. Types of
material in this section include:1. outlet boxes2. junction boxes3.
pull boxes 4. conduit boxes5. bushings6. locknuts7. knockout
closuresB. Materials shall be metallic or alternatively of PVC to
suit raceway system selected by Contractor.SubmittalsC. Submit
samples of all materials for Employers approval.PART 2
MATERIALSInterior Outlet BoxesA. Provide outlet boxes of suitable
sizes with threaded screw holes and corrosion resistant screws for
securing box covers and wiring devices.B. Provide outlet box
accessories as required, which are compatible with boxes being
used.Interior Outlet BoxesA. Choice of accessories is Contractors
option.Weatherproof Outlet BoxesA. Metallic weatherproof boxes
shall be cast-metal.B. Weatherproof boxes shall have face plates,
gaskets and corrosion-resistant fasteners.Junction and Pull BoxesA.
Provide boxes suitable for each location and installation.B. Equip
with stainless steel nuts, bolts, screws and washers or approved
equal corrosion resistant material.Conduit BodiesA. Provide conduit
bodies suitable for each use and installation.B. Equip with
removable covers and corrosion resistant screws.Bushings, Lockouts
and Knockouts ClosuresA. Provide corrosion resistant material of
types and sizes to suit each use and installation.PART 3
EXECUTIONInstallationA. Co-ordinate installation of boxes and
fittings with other work.B. Provide weatherproof outlets for
interior and exterior locations exposed to weather or moisture.C.
Provide knockout closures to cap unused knockout holes where blanks
have been removed.D. Install boxes and conduit bodies such as to
ensure ready accessibility of electrical wiring.E. In exposed areas
install boxes and fittings in such a way that covers finish flush
with finished surfaces.F. The Employers permission must be obtained
for all surface mounted boxes and fittings.WIRING DEVICESSECTION
12PART I GENERALTypes of DevicesA. Types of devices in this section
include:1. Receptacles (convenience outlets)2. Switches3. Wall
plates.SubmittalsA. Submit samples of devices for Employers
approval.PART 2 MATERIALSGeneralA. Provide devices of types, colour
and electrical ratings as indicated and complying with the
following or approved equal standards for wiring devices:1. NEMA
Standard Pub. No WD 1.
B. Provide devices with white thermoplastic faces and faceplates
for internal areas except as otherwise indicated.C. Colour
selection to be verified with Employer.ReceptaclesGeneral Duty
DuplexA. Provide polarized 2-pole and earth, 3 wire grounding, 15
A, 115 V outlet switched or unswitched.B. Provide both standard
grade and tamper-resistant types.C. Tamper-resistant receptacles
are to have spring loaded sliding shutters fitted directly behind
the polarized blade slots. Operation will be such that any object
placed in either single opening cannot move the internal mechanism
to expose the contacts. The slides will move only if the two
receptacles openings are penetrated simultaneously.230 V Duty
DuplexD. Provide 2 pole and earth, 3 wire grounding, 230 V,
industrial outlets of amperage specified in the Drawings and
complying with BS 196.SwitchesSnapA. Provide general-duty flush one
way and two way switches, 20A, 115 V with white, thermoplastic
cover plates for internal areas.B. Provide heavy-duty 20A, 115V
switches with steel cover plates for all other areas.Wall PlatesC.
Provide switch and duplex outlet wall plates of types, sizes and
with ganging and cutouts as indicated.D. Construct with metal
screws for securing plates to devices; screw heads coloured to
match finish of plates; plates coloured to match devices to which
attached.E. Provide wall plates with the following
features:Thermoplastic, smooth finish-internal areasStainless steel
plate-all other areasPART 3 EXECUTIONInstallationA. Delay
installation of wiring devices until wiring work is complete.B.
Delay installation of wall plates until painting work is
complete.GroundingA. Provide electrical continuous, tight grounding
connections for wiring devices.TestingA. Prior to energising
circuitry, test devices for electrical continuity and proper
polarity connections.B. After energising circuitry, test devices to
demonstrate compliance with requirements.ProtectionC. At time of
Taking-Over, replace those items which have been damaged, including
those burned or scorched by faulty plugs.ELECTRICAL CONNECTIONS FOR
EQUIPMENTSECTION 13PART 1 GENERALDescription of WorkA. connections
are hereby defined to include, but not necessarily limited to,
connections for providing electrical power to equipment.B. Types of
electrical power connections specified in this section include but
are no limited to the following:1. Panel boards2. Outlets3. Earth4.
Lighting FixturesManufacturersA. Provide materials from
manufacturers engaged in manufacture of electrical connectors and
terminals, of types and ratings required, and ancillary connection
materials, including electrical insulating tape, electrical flux
and cable ties, whose products have been in satisfactory use in
similar services for not less than 5 years.SubmittalsA. Product
Data: Submit manufacturers data on electrical connectors, terminals
and materials.PART 2 PRODUCTSGeneralA. For each electrical
connection indicated, provide complete assembly of materials,
including but not necessarily limited to, pressure connectors,
terminals (lugs), electrical insulating tape, heat-shrinkable
insulating tubing, cable ties, solderless wire nuts, and other
items and accessories as needed to complete splice and terminations
of types indicated.Metal Conduit, Tubing and FittingsGeneralA.
Provide metal conduit, tubing and fittings of types, grades, sizes
and weights (wall thickness) indicated for each type service. Where
types and grades are not indicated proper selection as determined
by Installer to fulfill wiring requirements; comply with NEC
requirements for raceways. Provide materials in accordance with the
following listing.i. Electrical metallic tubingii. EMT fittingiii.
PVC conduit.Wire, Cable and ConnectorsWireA. Unless otherwise
indicated, provide wires/conductors for electrical connections
which match wires/connectors of wiring supply power.Connectors and
TerminalsA. Provide electrical connectors and terminals as
recommended by connector and terminal manufacturer for intended
applications.Electrical Connection AccessoriesA. Provide electrical
insulating tape heat-shrinkable insulating tubing and booths, wire
cable ties as recommended for use by accessories manufacturers for
the type of services indicated.FIRE DETECTION AND ALARM
SYSTEMSECTION 14PART I GENERALType of SystemA. Combination, zoned,
non-coded.Quality AssuranceManufacturerA. Firms whose products have
been in satisfactory use for not less than 5
years.12.40.3InstallerA. Qualified with at least 5 years successful
installation experience on similar work.ComponentsA. Provide system
components which are UL listed and labelled.SubmittalsA. One mouth
after order is placed, submit two (2) sets manufacturers data on
system including but not limited to, instructions for installation,
operation and maintenance and a 1-year list of spares as
recommended by the manufacturer. Also include standard or typical
riser and wiring diagrams.B. Submit the Tender the priced list of
recommended spares.PART 2 PRODUCTSManufacturersA. Subject to
compliance with requirements, approved manufacturers include, but
are not limited to the following:i. Edwards Co. Inc.ii. Walter
Kiddle and Co. Ltd.iii. General Signal Corp.iv. Honeywell, Inc.v.
McGraw-Edison Co.vi. Pyrotronics Div., Baker Protective Services
Inc.vii. Simplex Time Recorder Co.General System DescriptionA.
Combination, zoned, non-coded system: Either manual activation of a
fire alarm station or activation of an automatic initiating device
energising all fire alarm signalling devices, sounding a non-coded
alarm and providing zone identification on an annunciator
panel.12.40.8WiringA. Power supply to the system shall be 115 V, 60
Hz.B. Provide wiring in accordance with manufacturers
recommendations.C. Wire resistance in alarm receiving circuits
shall not exceed 50 ohms.D. Voltage drop in audible signal
circuits, shall not exceed 10%.E. Temperature rating of cables
shall not be less than 85o C.Control UnitA. House control unit in a
surface mounted cabinet with a lockable hinged door.B. Provide unit
with the number of alarm initiating and signalling circuits as
indicated in the drawings and Bill of Quantities.C. Provide
necessary indications, visible when cabinet door is closed,
including the following:1. power on2. common trouble3. signal
silence4. separate alarm lamps.D. DProvide necessary controls and
indicators, visible when cabinet door is open, including the
following:1. lamp test push-button2. reset push-button3. ground
indicator4. separate trouble indicators.Smoke DetectorsA. Provide
dual chamber, plug-in type, ionization smoke detectors, mounted to
a lock base.B. Field adjustments and sensitivity measure shall be
possible without removal of the detector head from its base.C.
Measurement of detector sensitivity shall provide a discrete
electrical value.Initiating CircuitsA. For each initiating circuit,
provide a separate zoned trouble light visible when the control
unit cabinet door is open.Signal CircuitsA. Provide electronically
supervised signal circuits responding to open circuit, ground or
short circuit with a trouble signal without opening the supply
protective device. For each signal circuit, provide a separate
zoned trouble light, visible when the control unit cabinet door is
open.Vibrating SignalsA. Provide signal circuits capable of
sounding up to 20 vibrating polarized bells or up to 15 polarized
horns continuously.12.41.14Standby BatteryA. Provide sealed,
maintenance free battery pack and automatic charger inside a steel
enclosure in the control unit.B. Provide electronic supervision of
the battery pack and associated wiring such that a fault shall
energise the trouble circuitry.C. Size battery pack to provide 24
hours of supervisory operations followed by a 5 minute alarm.D.
Provide automatic change-over from AC to battery and vice
versa.PART 3 EXECUTIONElectronic SupervisionA. In wiring a
supervised component, terminate each circuit conductor under a
screw or wire terminal of the component.B. Disconnection of the
component shall not cause the trouble signal to operate.TestingA.
On completion of installation, check all detectors and circuits for
proper functioning; adjust or replace units, as necessary.B. Submit
copy of full test report to the Employer.C. Prices for Electrical
Installation are to include for all considerations arising from the
specification.