Page 1: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Electrical Predictive

and Preventative

Maintenance

Page 2: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 3: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Electrical and mechanical

equipment is subject to

failure at the worst

possible time for no

apparent reason.

- Mose Ramieh III

Page 4: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 5: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 6: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 7: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 8: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 9: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

There are two types of

facilities…

Page 10: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Those that have HAD a

failure…

Page 11: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

And those that will…

Page 12: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

IEEE 493-2007

Page 13: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 14: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Agenda

• Safety and Maintenance

• Types of equipment failures

• Non-Intrusive Predictive Options

• Somewhat Intrusive Predictive

Options

• Intrusive Options

Page 15: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Electrical

Maintenance

&

Safety NFPA 70B, 70E, IEEE

Page 16: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 17: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

NFPA 70E Standard for Electrical Safety in the Workplace

– Electrical Arc, Flash, and Blast

– Safe work practices

– Energized Electrical Work Permit

– Minimum PPE Requirements

– Make systems electrically safe prior to work

– Mechanical controls (IR Windows)

Page 18: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Article 110.4

Multiemployer Relationship

States:

On multiemployer worksites (in all industry

sectors), more than one employer may be

responsible for hazardous conditions that

violate safe work practices.

Page 19: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Reasons for Electrical

Predictive and

Preventive

Maintenance

Page 20: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Safety

• To minimize unsafe conditions

• Avoid personnel injuries

• Reliability Centered Maintenance is

directed by safety first, then

economics. When determined that

safety is not a factor, then preventive

maintenance is justified on economic

grounds. IEEE 493-2007 Section 5.5

Page 21: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Economics

• To avoid future and more costly

equipment failures.

• To avoid premature equipment

failures.

• To avoid interruption of services to

production and processes.

Page 22: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Legal & Contracts

• Avoid legal consequences and/or to

meet legislated mandates (Codes &

Standards)

• To comply with insurance

company requirements.

Page 23: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Go Green

• Avoid environmental damage

• Accomplish equipment life

cycle extension.

Page 24: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Downtime=Money!

Page 25: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

NFPA 70B

Page 26: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

IEEE 493-2007

5.3.2 Causes of Electrical Failure

Page 27: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 28: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

IEEE 493-2007

5.3.2 Causes of Electrical Failure

Page 29: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Insulation Failures

Page 30: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 31: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Mechanical Failures

Page 32: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Mechanical Failures

Page 33: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Non-Invasive PdM

Page 34: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

House Keeping

Page 35: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Walk Through Inspections

Page 36: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 37: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

What You Can’t See

Page 38: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

What is Partial Discharge (PD)?

PD is a localized electrical discharge in an

insulation system that does not completely

bridge the electrodes

Phase to Phase

or

Phase to Ground

Page 39: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

What You Can’t See

Page 40: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

What is Partial Discharge?

PMDT Proprietary

Partial Discharge Emission Light Heat Odor (Ozone) Sound Electromagnetic pulse

Typical PD Types Corona discharge Floating discharge Particle discharge Void discharge Surface discharge

Page 41: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

PD Activity

0

90

180

270

360

Partial Discharge Pulses

Negative Polarity

Pulse in positive half

cycle and Positive

polarity pulse in

negative half cycle

One 60Hz Cycle

V

TEV

signal

(nano

Secs)

-ve

4.1 mS

Page 42: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Detection Bandwidth

TEV: 3MHz~100MHz

UHF: 300MHz~1500MHz

AE: 20kHz~300kHz

Ultrasonic:40kHz

HFCT: 500kHz~50MHz

Application GIS MV switchgear Power cable Transformer

PMDT Proprietary

Level I PD Detection Services

Page 43: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Level I PD Detection Services

• UHF – Radio Frequency

• TEV – Transient Earth

Voltage (capacitive)

• Ultrasonic (airborne acoustic)

Page 44: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 45: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Typical Retrofit Switchgear Application

Sensor Selection Guideline

RFCT – One for every cable-set (in or out)

Coupling Capacitors – One set for every 3 structures

RFCT

Coupling Capacitors

LEGEND

Load Cables or Bus

Switchgear Cable Compartment

L1 L2 L3

52 MV Power Circuit Breaker

Cable Shields

Breaker Cubicle 1 Breaker Cubicle 2 Breaker Cubicle 3 Breaker Cubicle 4 Breaker Cubicle 5 Breaker Cubicle 6

Page 46: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

On-Line Partial Discharge

Continuous Monitoring

Page 47: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Transformer Oil Samples

Page 48: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 49: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Slightly Invasive PdM

Page 50: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Thermographic Surveys

Page 51: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Subject

149.0

Ref.

41.1

*>55.0°F

*<35.0°F

36.0

38.0

40.0

42.0

44.0

46.0

48.0

50.0

52.0

54.0

Page 52: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 53: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Survey Hazards

Page 54: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

IR Windows

Page 55: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Short Outage PdM

Page 56: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

IEEE 493-2007

5.3.2 Causes of Electrical Failure

• Dirt on moving parts can cause sluggishness

and improper electrical equipment

operations…

• Checking the mechanical operation of

devices and manually or electrically

operating any device that seldom operates

should be standard practice.

Page 57: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Seldom Operated

Page 58: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

“Traditional” Outage PM

Page 59: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

When to Test?

NETA MTS and NFPA 70B

• Monthly

– Visual Inspections

– Make notes regarding operating status and house keeping

• Annually

– Thermographic Survey

– Out of Service Maintenance

• 1-5 Years

– Follow Manufacturer Guidelines

– NETA Guidelines (Handouts Available)

– Check with Insurance Carrier for additional Guidelines.

Page 60: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Circuit Breaker Testing

Page 61: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Circuit Breaker Testing

Page 62: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

NFPA 70E Chapter 2 Safety Related

Maintenance Requirements

• Qualified Persons to conduct maintenance.

• Over-current devices shall be maintained.

• House keeping, House keeping

• “Failure to properly maintain protective

devices can have an adversely effect on the arc

flash hazard analysis incident values.”

Page 63: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

NFPA 70E Chapter 2 Safety Related

Maintenance Requirements

“Failure to properly maintain

protective devices can have an

adversely effect on the arc flash

hazard analysis incident values.”

Page 64: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Circuit Breaker Testing

Page 65: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Transformer Testing

Page 66: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Transformer Testing

• Insulation Resistance

• Winding Resistance

• Turns Ratio Test

• Power Factor (60Hz)

• Leakage Reactance

• On Load Tap Changer

Page 67: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Power Factor vs Frequency

Page 68: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 69: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Catch it Early or Pay Big $’s Later

Effect:

High temperature and moisture

content will dramatically lower

the mechanical strength of paper

insulation

Risks:

• Lower the expected life of

transformer

• Run transformer at lower rating

Temperature / °C

50 70 90 110 130

0,1

1

10

100

1000

Life

expe

cta

nce

/ a

Dry

1%

2%

3%

4%

L. E. Lundgaard, “Aging of oil-impregnated paper in power transformers”,

IEEE Transactions on Power Delivery, Jan. 2004

Page 70: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Dielectric Frequency Response

high

low

high

high

low

low

0,001 0,01 1 100

0,001

0,01

0,1

1

1000

Frequency / Hz

Dis

sip

atio

n facto

r

0,1 10

mois

ture

an

d

agin

g o

f cellu

lose

insula

tion

geom

etr

y

oil conductivity

moisture, aging of cellulose

Sufficient data

Typical:

• Dry transformer or low

temperature

-> 0,1 mHz, 2:50 hours

• Moderate wetness /

temperature -> 1 mHz, 22 min

• Wet transformer or hot

temperature -> 0,1 Hz, 5 min

Freq/Hz0.001 0.01 0.1 1.0 10

Dis

sip

ation

fa

cto

r

0.005

0.01

0.02

0.05

0.1

0.2

0.5

1

2

New

1000

0.002

0.0001

5

Freq/Hz0.001 0.01 0.1 1.0 10

Dis

sip

ation

fa

cto

r

0.005

0.01

0.02

0.05

0.1

0.2

0.5

1

2

1000

0.002

0.0001

5Moderate

44°C

Freq/Hz0.001 0.01 0.1 1.0 10

Dis

sip

ation

fa

cto

r

0.005

0.01

0.02

0.05

0.1

0.2

0.5

1

2

1000

0.002

0.0001

5

Heavily aged

Page 71: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 72: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

The General Curve Structure

Page 73: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Cable Testing

Page 74: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

VLF Cable Testing

Page 75: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

VLF Cable Test Results

Page 76: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Protective Relays and Meters

• Monthly

– Visual Inspection

– Record and Reset Targets

• Annually

– Pick up Test and Time

Electromechanical Relays

– Verify Setting of Solid State

• 1-5 Years (Out of Service)

– Pick Up Test

– Timing Test

– Verify Operational Scheme

Page 77: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Protective Relays and Meters

• Monthly

– Visual Inspection

– Record and Reset Targets

• 1-5 Years (Out of Service)

– Pick Up Test

– Timing Test

– Verify Operational Scheme

Page 78: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 79: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer
Page 80: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

No Scheduled Maintenance

Page 81: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Critical Chiller Goes Down! Why?

• Hospitality Facility

• Heat of Summer

• Fuse Blows

• No Spares

• Patients must be

relocated.

• How many ways can

we measure the cost?

Page 82: Electrical Predictive and Preventative Maintenance PdM... · 2016-05-03 · MV Power Circuit Breaker ... NETA MTS and NFPA 70B • Monthly ... Circuit Breaker Testing . Transformer

Questions?

Answers