Electrical, Plumbing and Gas Permit Timeline Begin Process 1 2 3 4 5 Completed Application Submitted to the Town Review Based on Quality Managment Plan Requirements (If outstanding items exist return to step 1) 1-2 weeks Issue Permit Applicant Requests Inspections (Plumbing ,Electrical ,Gas) at Strathmore.ca (quicklinks) 2 weeks - 12 months depending on type of application V4.18.04.2019 6 Re-inspection Performed (if required) Internal Circulation and Review * At this stage each stakeholder must have adequate response time for a meaningful review. VOC = Verification of compliance to confirm completion of items noted on the inspection report. 2-5 days Inspection Performed Final Inspection (if required)