ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES vital experience in acoustics | civil | electrical | ESD | fire | hydraulic | lifts mechanical | property asset management | structural | underground power Albany, Brisbane, Busselton, Darwin, Gold Coast, Melbourne, Perth, Shenzhen, Sydney E: [email protected] W: www.wge.com.au Prepared by: Angus Grant Date: May 2013
46

ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Mar 31, 2018

Download

Documents

DuongAnh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

ELECTRICAL FUNDAMENTALS

FOR

MECHANICAL SERVICES

vital experience in acoustics | civil | electrical | ESD | fire | hydraulic | lifts

mechanical | property asset management | structural | underground power

Albany, Brisbane, Busselton, Darwin, Gold Coast,

Melbourne, Perth, Shenzhen, Sydney

E: [email protected] W: www.wge.com.au

Prepared by: Angus GrantDate: May 2013

Page 2: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

• MOST POWER CONSUMED IN MECHANICAL SERVICES SYSTEMS IS CONSUMED BY ELECTRIC MOTORS:

- FANS

- PUMPS

- COMPRESSORS

- DAMPER MOTORS

- CONTROL VALVES

• PASSIVE DEVICES CONSUME THE BALANCE OF THE POWER:

- ELECTRIC HEATER BANKS

- CONTROL SYSTEMS:

- RELAYS

- CONTACTORS

- CONTROLLERS

- MONITORING DEVICES

- COMPUTER DISPLAYS AND PRINTERS

Introduction

Page 3: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Typical Consumption

Page 4: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Electrical Terms

Voltage (Volts, V)

Current (Amps, A)

Direct Current (DC) / Alternating Current (AC)

AC Power (kW, kVA) and Power Factor (PF)

Single Phase (1ph) / Three Phase (3ph)

Page 5: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Voltage (Volts, V)• Volts is the SI measurement unit of “electrical potential difference” or

“electromotive force”. Ability to do work!

• It’s a “potential difference” and therefore always measured between two points. Voltage is most commonly referenced to the “neutral” or “earth” potential which is termed 0 volts.

• Water pipe analogy – voltage is like the pressure drop across thecircuit. City Power is like a variable speed pump which maintains aconstant pressure differential (voltage drop) across a varying load(grid).

Page 6: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Current (Amps, A)• Amps is the SI measurement unit of current or “electric charge flow”

at a specific point in a circuit.

• Water pipe analogy – current is likethe water flow through a pipe. City Power’s variable speed pump (power station) increases the water flow rate (current) to maintain a constant pressure differential (voltage drop) across the varying load (grid).

• Cables are sized based on current carrying capacity and voltage drop, the same way ducts and pipes are sized on flow rate and pressure drop.

Page 7: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Direct Current (DC) vs

Alternating Current (AC)• Direct current (DC) occurs as the result of direct voltage.

• Alternating current (AC) occurs as the result of alternating voltage.

• An AC incandescent light globe actually flickers 50 times per second in Australia!

DC AC

Page 8: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

AC Power (kW, kVA) and

Power Factor (φ)• Apparent Power (S) in kVA is the voltage (V) multiplied by the

current (I) or mathematically S = VI. Easy to remember from the units kVA!

• Real Power (P) in kW is the voltage (V) multiplied by the current (I) and Power Factor (PF) P = VI*PF.

• Reactive Power (Q) in VAr is the difference between the S and P and is the power temporarily stored by the load. Usually <20%.

• Electrical Engineers use kVA because their cables need to supply total power needed by the load.

• Mechanical Engineers are concerned with kW because they need to cool the real power (rejected heat) from the load.

Page 9: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Power Factor = 1• Purely “resistive loads” like:

• Heater bank

• Electronic “switch-mode” power supplies (e.g. computer, electronic ballast in a fluoro)

• Variable Speed Drives (electronics)

• Can be usually be switched with less expensive “AC-1” rated contactors as making & breaking currents are less and shorter duration.

ALMOST ANYTHING WHICH THE PREDOMINANT LOAD IS

ELECTRONICS

Page 10: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Power Factor = 0.8• “Inductive loads” like:

• Induction motors (without VSDs)

• Power transformers

• Usually need to be switched with more expensive “AC-3” rated contactors as making & breaking currents are higher due to the inductive characteristic of the load. I.e. causes arcing of the contacts.

ALMOST ANYTHING WHICH HAS WINDINGS

Page 11: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Single Phase (1ph) / Three

Phase (3ph)• Single Phase AC Power (e.g. 230VAC 50Hz in Australia)

• Single Phase = Fluctuating Power Input/Output!

Page 12: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Single Phase (1ph) / Three

Phase (3ph)• Three Phase AC Power (e.g. 415VAC L-L 50Hz in Australia)

• Three Phase = Constant Power Input/Output!

Page 13: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

• WE MAINLY DEAL WITH 50 HZ AC MOTORS.

• EITHER 240V SINGLE PHASE OR 415VTHREE PHASE.

• THE MOTOR INDUSTRY CONSIDERS THESE TO BE “LOW VOLTAGE” MOTORS.

• HIGH VOLTAGE MOTORS: 1,000V – 22,000V.

• WE HAVE “MEPS” TO HELP US ENSURE WEARE USING THE MOST EFFICIENT ELECTRICMOTORS.

Minimum Energy

Performance

Standards (MEPS)

Regulations in

Australia

Page 14: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

MEPS• APPLIES TO 3 PHASE MOTORS, 0.73 kW – 185 kW.

• 2006 – HIGH EFFICIENCY REQUIREMENTS WERE UPGRADED.

• “E3” – Equipment Energy Efficiency

• From 1 October 2012 – Enforced through GEMS

• “Greenhouse Energy Minimum Standards”

• http://www.energyrating.gov.au/programs/e3-program/meps/about/

• http://www.climatechange.gov.au/media/whats-new/gems-legislation-introduced.aspx

Minimum Energy

Performance

Standards (MEPS)

Regulations in

Australia

Page 15: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

MEPS

Page 16: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

TYPE ADVANTAGES DISADVANTAGES TYPICAL APPLICATION

AC INDUCTION(SHADED POLE)

LEAST EXPENSIVE

LONG LIFE

LOW POWER

ROTATION SLIPS

FROM FREQUENCY

LOW STARTING

TORQUE

SMALL FANS

AC INDUCTION(SPLIT-PHASE CAPACITOR)

HIGH POWER

HIGH STARTING

TORQUE

ROTATION SLIPS

FROM FREQUENCYAC ROTATION IN-SYNC WITH FREQ

APPLIANCES

AC SYNCHRONOUS

LONG-LIFE MORE EXPENSIVE INDUSTRIAL MOTORS

CLOCKS

AUDIO TURNTABLES

TAPE DRIVES

TYPES OF AC MOTORS

Page 17: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

EFFICIENCY IS A DESIGN FUNCTION!

Page 18: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

• CHEAP TO BUY AND INSTALL

• CHEAP TO SPEED CONTROL

• 60W – 4 KW

• SPEED IS CALCULATED BY FORMULA:N = 120 X FREQUENCY / NO. OF POLES

• 2 POLE 2900 RPM4 POLE 1400 RPM6 POLE 920 PRM

• P (WATTS) = V (VOLTS) x I (AMPS) x POWER FACTORP (WATTS) = 230 x I (AMPS) x 0.8

SINGLE PHASE – 230V 50Hz

Page 19: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

• 370W – 160 KW

• 2 POLE 2900 RPM4 POLE 1400 RPM6 POLE 920 PRM8 POLE 720 RPM10 POLE 600 RPM

• MORE EFFICIENT

• SMALLER FOR THE SAME POWER

• EASY TO CHANGE DIRECTION

• NO CAPACITOR START

• EASY TO SPEED CONTROL (VSD/VFD)

• P (WATTS) = √3 x V (VOLTS) x I (AMPS) x POWER FACTOR

• P (WATTS) = √3 x 415 x I (AMPS) x 0.8

THREE PHASE MOTORS – 415V 50Hz

Page 20: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Motor Starting and Sizes• Different methods of starting motors:

- Direct On-Line (DOL)

- Star-delta Starters

- Autotransformer Starters

- Soft-starters / Variable Speed Drives / Inverter

Page 21: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Direct On-Line (DOL) Starting• OK for motors < 3kW (9kWr @ COP = 3).

• High thermal & mechanical stress, few starts per hour.

• Simplest, least cost (Contactor + Overload)

• High starting current (5-10x Rated Current)

• High starting torque (~2.5x Rated Torque)

Page 22: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Star-Delta Starting (Old)• OK for motors < 8kW.

• Lower starting current (2-3x Rated Current)

• Low starting torque (0.2-0.5x Rated Torque)

• Lower thermal stress, 2-3x more starts per hour.

• Doesn’t work for all motors - requires winding terminals.

• Not good when starting on load (e.g. pumps)

Autotransformer Starting (Old)• OK for motors > 8kW.

• Lower starting current (1.7-4x Rated Current)

• Lower starting torque (0.5x Rated Torque)

• Low thermal stress, 3-4x more starts per hour.

• Ramps up voltage in discrete steps – replaced by solid-state Soft Starters and VSDs with almost infinite steps!

Page 23: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Soft-starters / VSDs / Inverters• Varying the frequency (from 50Hz) varies the speed!

• OK for most motors except shaded pole induction.

• OK for all types of load.

• High starting torque (configurable).

• Low (or no) starting current (configurable).

• Low stress, many starts per hours.

• Inbuilt control and protection (VSDs)

• Can be higher harmonics and PF(=1) backto the electrical infrastructureV

Page 24: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Tips for using VSDs• Keep the VSD close to the motor.

• Use a shielded/screened cable between the VSD and the motor to avoid RF interference.

• Can be single-phase input and three-phase output to run small 3-phase motors on 1-phase power supplies!

• Check the settingsV. we’ve seen motors stalling at startup because of incorrect settings. Can seriously damage the motor and VSD.

• In-built protection helps to save motors and VSDs.

• In-built protection should be disabled for “fire mode” operations.

Page 25: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

SOLID STATE RELAYS –

“CLUNK FREE”

Page 26: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

SOLID STATE RELAYS –

“CLUNK FREE”• Advantages

• No noise• No moving parts or mechanical wear• No arcing (OK for hazardous environments!)• Reliable – high operation count.• Low turn-on voltage and current (no interposing relays!)• High speed switching!

• Disadvantages• Higher cost (especially for larger relays)• Higher heat output (may require a heatsink)• Come in many typesV be sure to select the right one!

• Ideal Applications – Single phase loads <40A, heater banks, small fans and motors, things that start and stop often.

Page 27: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Electrical Codes and

Wiring Rules• Federal Legislation – Building Code of Australia

• State Legislation – VSIR 2005

• Australian Standards - Wiring Rules (AS3000:2007)

• EnergySafe - VIC Electrical Requirements

• Mechanical Electrical Contractors are required to comply with these Regulations, and all mandatory referred Standards and Regulations.

• The onus is on Contractor who holds the license. HoweverV Safety in Design!

• How does this effect Mechanical Engineers?

- Switchboard Clearances and Design

- Provision and Location of Isolators

- Power (LV) and Communications (ELV) Segregation

Page 28: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Switchboard Clearance and

Accessibility• Switchboards over 3m require 2 paths of escape.

• Minimum clearance of 600mm around doors and panels.

• Must be safely accessible – not in ceiling spaces etc.!

• Must be enclosed in a smoke sealed, non-combustible cupboard if located in the path of travel to an exit.

Page 29: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

• Advise power supply requirements:

- Location

- Volts (Single Phase 240V or Three Phase 415V)

- Amps (Full Load Amps & Starting Amps or kVA and Starting Method)

- Termination Requirements (Cables for MSSB, Isolator or Socket)

- Safety/Essential Requirements (Fire-essential or Generator or both!)

- Understanding of the system operation and power supply diversity!

• Advise communications requirements:

- Location

- Type of communications (e.g. phone line for dialer or ADSL?)

• Advise fire shutdown signal requirements:

- Location (MSSB preferred)

- Type of signal (Zone or General Alarm)

- Fire/AS1668.1 control requirements

• Request BMS Points including meters and interface type.

Mechanical Consultant to Coordinate:

Page 30: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Electrical Consultant to Coordinate• Confirm power supply requirements are documented. Including confirmation

of the power supply:

- Capacity (e.g. Three Phase 400A)

- Termination details (cable size and entry)

- Fault Level at the MSSB!!

• Advise BMS system & Metering requirements (Points Schedule):

- Location (e.g. Electrical DB location)

- Type of Point (Volt-free contact, Meter Pulse, Meter HLI)

- Meters HLI – Communication Protocol (e.g. MODBUS/LON/N2)

• Pulse-type meters are the past! It’s often best for the Mech-Elec Contractor to supply HLI meters which suit the BMS protocol (Johnson N2/LON/BacNet) for installation by the Electrical Contractor with final programming/ commissioning by the Mech-Elec Contractor!

Page 31: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Fault Levels• Fault level is expressed in kA – kiloamps (thousands of amps)

• The current that occurs when you short out the phases!

• Bigger (or more) power transformers, higher the fault level.

• Closer to the supply transformer, higher the fault level.

• Make sure the Electrical Contractor or Consultant has advised the fault level.

• Mechanical switchboards need to be constructed suitable for the fault level.• 4-10kA domestic/commercial <250A

• 25kA for 1000kVA TX

• 50kA for 2x1000kVA TX

• 150kA up for mines!

BOOM!

Page 32: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Form Rating• Compartmentalising

switchboards

• You may need to work on some services while keeping others running – go for a higher form rating!

• Form rating is all about concurrent maintainability!

Page 33: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

DO YOU NEED AN MSSB?• OPTION 1:

BUILDER’S ELECTRICIAN GIVES YOU A POWER SUPPLY AND ISOLATOR TO ALL MECHANICAL PLANT.

• WORKS OK WHEN PLANT HAS INTEGRATED CONTROLS E.G. WALL SPLITS, CASSETTES.

• OPTION 2:

BUILDER’S ELECTRICIANPROVIDES SUB-MAIN TO MSSB.

• WORKS OK WHEN:- LARGE AND VARIED MECHANICAL PLANT- 240V AND 415V EQUIPMENT.- DDC CONTROL SYSTEM

Page 34: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

RULES OF THUMB FOR SINGLE PHASE AIR CONDITIONING ELECTRICAL LOADS:• MEPS REQUIRES EER (ENERGY EFFICIENCY RATING) OF 2.75

• EER (COOLING) = RATED COOLING CAPACITY OUTPUT (KW)COOLING INPUT POWER (KW)

• COP (HEATING) = RATED HEATING CAPACITY OUTPUT (KW)HEATING INPUT POWER (KW)

• ELECTRICAL INPUT (kW) = COOLING (kW)/EER

APROXIMATELY: kW = 1/3 OF THE COOLING CAPACITY

CURRENT: FLA = 1.5 TIMES THE COOLING CAPACITY

• E.G.: 14.5 kW 1 PH R/C INV. FUJITSU DUCTED SPLITEER = 2.8kW = 5.18 (Rule of Thumb = 4.8)FLA = 21.6 (Rule of Thumb = 21.75)

• BEWARE OF MANUFACTURER CIRCUIT AMPS!

Page 35: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

RULES OF THUMB FOR THREE PHASE AIR CONDITIONING ELECTRICAL LOADS:• MEPS REQUIRES EER (ENERGY EFFICIENCY RATING) OF 3.10

EER (COOLING) = RATED COOLING CAPACITY OUTPUT (KW)COOLING INPUT POWER (KW)

• COP (HEATING) = RATED HEATING CAPACITY OUTPUT (KW)HEATING INPUT POWER (KW)

• ELECTRICAL INPUT (kW) = COOLING (kW)/EERAPPROX: kW = 1/3 OF THE COOLING CAPACITYCURRENT: FLA = 2/3 OF THE COOLING CAPACITY

• E.G.: 26.8 kW 3 PH R/C TEMPERZONE DUCTED SPLITEER = 3.12kW = 8.59 (Rule of Thumb = 8.9)FLA = 12 (Rule of Thumb = 18)

• BEWARE OF MANUFACTURER CIRCUIT AMPS!

Page 36: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

• 1 HP = 746W (MOTOR kW)

• EER = 3.0

• Therefore:

A unit with a 1 HP electrical motor will provide:0.746 x 3.0 = 2.2 kW(R) of cooling.

How do you convert “Harvey

Norman HP” to kW

(Cooling)??

Page 37: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

• CASCADE IS THE KEYTO DDC CONTROLV..

Page 38: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Cascading of current is the key to DDCControlV.

Computer output

via transistor:

Page 39: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Transistor switches relayV.

Page 40: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

Which switches a contactorV

Vwhich starts the motor!

Page 41: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

DDC equipment is locatedon the Extra Low Voltage(ELV) side of the MSSB.

Digital and Analogue Inputstrigger Digital and AnalogueOutputs.

Page 42: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

The power side of theDDC system is locatedon the Low Voltage (LV)Side of the MSSB.

A single digital outputCloses the contactor andstarts the heater.

Page 43: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However
Page 44: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However

HIGH LEVEL INTERFACE:

• KWH METERS• CHILLERS• VSD’s

Page 45: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However
Page 46: ELECTRICAL FUNDAMENTALS FOR MECHANICAL SERVICES … · ELECTRICAL FUNDAMENTALS FOR ... • Mechanical Electrical Contractors are required to comply with these Regulations, ... However