E Introduction. ELS/Angul is the only Electric from Diesel Loco Shed on 08.12 AC Electric locomotives. These equipments like SIV, MPCS, DP 1 ELECTRICAL (TRS) ELECTRIC LOCO SHED, ANGUL Loco shed of KUR division of East coast Rai 2.2005. ELS/ANGL has a present loco holding e locomotives are dedicated to freight traffic a PWCS, ESMON & VCD ilway which is a conversion of 141 numbers of WAG-7 and equipped with high end
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ELECTRIC LOCO SHED, ANGUL
Introduction.
ELS/Angul is the only Electric Loco shed of KUR division of East coast Railway which is a conversion
from Diesel Loco Shed on 08.12.2005. ELS/ANGL
AC Electric locomotives. These locomotives are dedicated to freight traffic and equipped
equipments like SIV, MPCS, DPWCS, ESMON & VCD
1
ELECTRICAL (TRS)
ELECTRIC LOCO SHED, ANGUL
ELS/Angul is the only Electric Loco shed of KUR division of East coast Railway which is a conversion
from Diesel Loco Shed on 08.12.2005. ELS/ANGL has a present loco holding of 1
AC Electric locomotives. These locomotives are dedicated to freight traffic and equipped
equipments like SIV, MPCS, DPWCS, ESMON & VCD
ELS/Angul is the only Electric Loco shed of KUR division of East coast Railway which is a conversion
has a present loco holding of 141 numbers of WAG-7
AC Electric locomotives. These locomotives are dedicated to freight traffic and equipped with high end
2
Location-
Electric Loco Shed, Angul is situated in the midst of Bhubaneswar –Sambalpur Railway route near to
Talcher ( about 158 KM from Bhubaneswar and 116 KM away from Cuttack) in Khurda Road Division of
East Coast Railway.
Importance of Shed:- Angul is the District Head Quarter of Odisha state and is a rich source of the Coal mines at Talcher of the
Mahanadi basin. Besides this, Angul has its importance on the National Geography as a hub of Thermal
Power production by NTPC and with Aluminum & Steel industries like National Aluminum
Company(NALCO), JSPL etc.Due to the above facts, ELS/ANGL has been dedicated to goods locomotive
for transportation of coal, Aluminum and steel especially to Paradeep port , Damonjodi and Visakhapatnam.
Salient features of electric loco shed
S.No DESCRIPTION DETAILS
1 AREA OF ELS YARD 20000 Sq.meter(Approx.)
2 LOCO HOMING CAPACITY 150( Estimate sanctioned for homing of
200 loco)
3 AREA OF INSPECTION BAY 1830 sq.mtr
4 AREA OF HEAVY LIFTING BAY 3477 sq.mtr
5 AREA OF MEDIUM LIFTING BAY 3660 sq.mtr
6 TOTAL No. OF PITS IN BAYS 10 Nos.
7 TOTAL COVERED AREA OF SHED 8967 sq. mtr
8 UN- COVERED AREA OF SHED 825 sq.mtr
9 CRANES PROVIDED 50/6,50/10,40/10,25/6, 10/5 ton capacity
10 ADMN. BUILDING AREA 1002 sq.mtr
11 SERVICE BUILDING AREA 1750 sq.mtr
12 STORES BUILDING 1200 sq.mtr
13 No. OF LINES FROM SHED 08 nos. lines from cover shed to exit point.
14 STORES GODOWN AREA 627 sq.mtr
15 DISTANCE BETWEEN COLUMNS 10 mtr
16 No. OF COLUMNS IN INSP.BAY 12 Nos.
17 No. OF COLUMNS IN HEAVY, MEDIUM & LIGHT
LIFTING BAY 62 Nos.
3
Time Line History of ELS/ANGL
29.07.1999:- Initially Diesel Loco Shed/Angul was sanctioned vide Pink Book item No: 327 of
1991-92 for homing of 50 BG Diesel Locomotives.
Diesel Loco Shed/Angul was commissioned on 29.07.1999.
21.08.2002:- Railway Board has decided to convert the DLS/ANGL into ELS/ANGL in 2002
for homing capacity 50 Electric Locomotive in year 1999-2000.
08.12.2005:- Electric Loco Shed, Angul was started with homing capacity of 100 Electric
locomotives with WAG5 electric locomotive in non electrified territory.
After completion of scheduled inspection at ELS/ANGL, the Locomotives were
tested at TLHR which is approximately 22.5km from ANGL.
31.03.2007:- 25 KV OHE was commissioned and line no. 1,2&3 of ELS/ANGL
are charged.
17.04.2007:- HT Testing of electric loco was started at ELS/ANGL.
16.06.2007:- Minor inspection (IC) was started at ELS/ANGL.
11.03.2008:- Major overhauling schedule AOH was started.
01.03.2009:- Homing of WAG-7 locomotive with Hitachi TM were started &
16 WAG-7 locomotive were transferred from ELS/BSL to
ELS/ANGL.
31.03.2011:-Major overhauling schedule IOH was started.
21.03.2015:- 06 numbers of WAG-7 locos fitted with Distributed Power
Wireless control System (DPWCS) has been transferred to
ELS/ANGL from ELS/VSKP. 13.01.2016:- 05 numbers of WAG-7 locos fitted with MPCS has been
transferred to ELS/ANGL from ELS/VSKP. 08.03.2016:- 02 numbers of WAG-7 locos fitted with MPCS has been
transferred to ELS/ANGL from ELS/VSKP.
16.03.2016:- 01 number of WAG-7 loco fitted with MPCS has been transferred
to ELS/ANGL from ELS/VSKP.
Shed Augmentation:
Initial Augmentation as Diesel Loco Shed:- The Diesel Loco Shed, ANGL was sanctioned vide PB No- 327 of 1991-92 at an expenditure
of `34,64,81,000/- for homing 50 BG Diesel locomotives.
Augmentation from 50 Diesel locos to 100 Electric locos:- Proposal for conversion of incomplete Diesel loco shed to Electric loco shed and
augmentation from 50 to 100 AC electric locomotives was sanctioned vide PB no.
273/04-05 with an estimated cost of `10,97,65,883/-
Augmentation from 100 AC locomotive to 150 AC locomotive:- The augmentation work for increasing the homing capacity of ELS/ANGL from 100 AC loco
to 150 loco vide PB No-377/11-12, 366/12-13, 394/13-14, 379/14-15 &498/15-16 at a
estimated cost of `22,13,98,963/- is approximately completed. 100% building work, 100%
shed work & 100% Pit work & 95% electrical work have been completed so far.
Augmentation from 150 AC locomotive to 200 AC locomotive:Augmentation of holding capacity from 150 to 200 AC
sanctioned by RB vide PB No
estimate of M&P portion
INSPEC TION BAY WITH CAT WALK OF ELS/ANGL
CAB friendly WAG
.
4
Augmentation from 150 AC locomotive to 200 AC locomotive:- Augmentation of holding capacity from 150 to 200 AC electric
sanctioned by RB vide PB No-509/2015-16, amounting to `
estimate of M&P portion sanctioned by CAO/ECoR.
INSPEC TION BAY WITH CAT WALK OF ELS/ANGL
CAB friendly WAG-7 type loco at Catwalk type inspection Bay of ELS/ANGL
electric locomotive has been
`28 crores. The detail sub-
INSPEC TION BAY WITH CAT WALK OF ELS/ANGL
7 type loco at Catwalk type inspection Bay of ELS/ANGL
5
Heavy Repair Bay of ELS/ANGL
CONFERENCE HALL OF ELS/ANGL
6
MAINTENANCE ACTIVITY OF SHED
The Shed is responsible to carry out running repair of locomotive & schedule inspection (Minor & Major)
regularly.
SCHEDULEACTIVITIES
*POH schedule is not carried out at ELS/ANGL.
PPO is working round ‘O’ clock in shift & finally giving the loco fit for use of traffic.
CLIMATIC CONDITION
Environmental conditions are extreme ie.
• Summer is very hot and temperature shoots up above 45 degree centigrade.
• Winter is very cold and foggy.
• Heavy rain with thundering and lightening.
Ground water table is very low and resulting the shortage of drinking water in summer.
VISTING PLACE
• JAGANNATH TEMPLE
• NALCO
• SATKOSIA about 60 KM away from ANGL.
Salient Features of WAG-7 locos of ELS/ANGL:-
Sl. No Equipments Holding
1 Microprocessor based Fault Diagnostic Control System (MPFDCS) 114
2 Static Inverter (SIV) 140
3 Distributed Power Wireless Control System (DPWCS) 06
4 Energy Cum Speed Monitoring System (ESMON) 141
5 Vigilance Control Device (VCD) 141
6 High Reach Pantograph 10
7 Ver-3 GPS Enabled MPFDCS 01
8 Crew Friendly Cab 114
9 Provision of Air Conditioner in Loco Cabs 13
10 Tri-plate Pneumatic Panel 110
Minor Schedule Major Schedule
Type Periodicity Tolerance Type Existing
Periodicity
Revised
Periodicity Tolerance
IA 60 DAYS
±3 days
AOH/TOH 1.5 Years 2 Years ± 10 days
IB 120 Days IOH 4.5 Years 6 Years ± 30days
IC 180 Days POH* 9 Years 10 Years ± 90 days
7
Milestones of ELS/ANGL:-
Sl. No Events Date
1 Minor inspection schedule (IA and IB) started April-2006
2 25 KV OHE Commissioned March-2007
3 Minor Inspection (IC) started June-2007
4 Commissioning of the stores depot Oct-2007
5 Commissioning of EOT cranes Nov-2007
6 Battery section was commissioned by commissioning the DM
plant and repairing an old battery charger
Jan-2008
7 Major overhauling schedule AOH started March-2008
8 Commissioning of commutator turning machine May-2008
d) Effective utilization of man power (for last 04 yrs)
2.61 staff per loco is available against
man power amongst Electric Loco Shed of IR. All core activities are carried out departmentally without
paying any OT and some non-
15
i. The loco outage during year
against a target
above
ii. The loco outage during this year
133.7
which
above the target.
Effective utilization of man power (for last 04 yrs):-
staff per loco is available against Rly.Board yard stick of 5.5 per loco in
man power amongst Electric Loco Shed of IR. All core activities are carried out departmentally without
-core activities i.e. shed & loco cleaning are outsourced.
yard stick of 5.5 per loco in May-2016. It is the least
man power amongst Electric Loco Shed of IR. All core activities are carried out departmentally without
core activities i.e. shed & loco cleaning are outsourced.
e) Current Benchmarking of manpower:ELS/ANGL is having the least manpower amongst Electric loco sheds on IR and current
benchmarking is 2.61 staff per loco as compared to current IR average of 3.63 staff per
loco.
f) INEFFECTIVENESS:
i. Statistical ineffectiveness ( 2016up to May’2016:
Statistical ineffectiveness of 3.2% has been
achieved during 2016
a target of 10% which is 68% improvement
than the target.
ii. Hourly ineffectiveness (2016up to May’2016:
Hourly ineffectiveness of 4.8 % has
been achieved during 2016
against a target of 19% which is 74.
improvement than the target.
16
e) Current Benchmarking of manpower:- ELS/ANGL is having the least manpower amongst Electric loco sheds on IR and current
staff per loco as compared to current IR average of 3.63 staff per
Statistical ineffectiveness ( 2016-17)
Statistical ineffectiveness of 3.2% has been
achieved during 2016-17(May-16) against
a target of 10% which is 68% improvement
Hourly ineffectiveness (2016-17)
Hourly ineffectiveness of 4.8 % has
been achieved during 2016-17(May-16)
against a target of 19% which is 74.74 %
improvement than the target.
ELS/ANGL is having the least manpower amongst Electric loco sheds on IR and current
staff per loco as compared to current IR average of 3.63 staff per
g) Major schedule inspection
(i) Total 06 nos. major schedule (TOH
during this year 2016-
(ii) Achievement in carrying out Major Schedule:
Year Schedule Carry
Forward
2014-15 AOH 23
IOH 23
2015-16
AOH 12
IOH 08
2016-17 TOH 00
IOH 00
h) Minor schedule inspection:- Total 116 nos. minor schedule have been carried out during this year 2016
17
g) Major schedule inspection:-
nos. major schedule (TOH-04 & IOH-00 & POH-02) have been carried out
-17(Upto May-16) against 33 locos due for major schedule.
(ii) Achievement in carrying out Major Schedule:
Carry
Forward
Due for
the Year
Total
Target Done
23 46 34
29 52 44
53 65 57 08 locos for AOH from the
target of 2015
planned for POH. All major
schedules are completed by
Feb’15. No loco remained to
carry forward to next year
22 30 30
28 28 04
03 03 00
nos. minor schedule have been carried out during this year 2016-17(Upto
have been carried out
16) against 33 locos due for major schedule.
Remarks
…
…
08 locos for AOH from the
target of 2015-16 has been
planned for POH. All major
schedules are completed by
Feb’15. No loco remained to
carry forward to next year
…
…
17(Upto May-16).
i) Overhauling of Traction Motor: 18 Nos. of Hitachi Traction Motors of WAG7 loco are overhauled during Major schedule in 2016
17(Up to May-16).
j) Unscheduled loco lifting
The unscheduled loco lifting per 100 loco during 2016
k) Loco failure on territorial basis: The loco failure per loco per year for 2016
18
Overhauling of Traction Motor: Nos. of Hitachi Traction Motors of WAG7 loco are overhauled during Major schedule in 2016
j) Unscheduled loco lifting:-
The unscheduled loco lifting per 100 loco during 2016-17(Up to May
Loco failure on territorial basis: The loco failure per loco per year for 2016-17(up to May-16) is 0.
Nos. of Hitachi Traction Motors of WAG7 loco are overhauled during Major schedule in 2016-
May-16) is 4.27.
16) is 0.17
l) Online attention of locos of other shed by the staff of ELS/ANGL:Number of Locos of other sheds attended by staff of ELS/ANGL online during this year 2016
17(Up to May-16) is NIL. Comparative Position of online attention by staff of ELS/ANGL of
other shed locos is furnished below.
m) Other Shed Loco attention at ELS/ANGL: 18(Eighteen) Locos of other shed are attended at ELS/ANGL during this year 2016
May-16). Comparative position for last 04 years is given below.
19
Online attention of locos of other shed by the staff of ELS/ANGL: Number of Locos of other sheds attended by staff of ELS/ANGL online during this year 2016
16) is NIL. Comparative Position of online attention by staff of ELS/ANGL of
shed locos is furnished below.
Other Shed Loco attention at ELS/ANGL: ) Locos of other shed are attended at ELS/ANGL during this year 2016
16). Comparative position for last 04 years is given below.
Number of Locos of other sheds attended by staff of ELS/ANGL online during this year 2016-
16) is NIL. Comparative Position of online attention by staff of ELS/ANGL of
) Locos of other shed are attended at ELS/ANGL during this year 2016-17(Up to
n) Stores position of attached depot with loco shed:
Stock position for 2016-17 for the
month of May’16:
Total Stock items: 63
Stock item available: 62
Out of stock: 05
o) Training to staff: Initial, Refresher & specialized Training has been imparted to Supervisor & staff
of ELS/ANGL regularly regarding maintenance of loco & Major equipments like GR, TFP, TM
overhauling, SIV, MPCS etc to improve the reliability of loco.
p) 3rd Best Innovation A
on IR with a prize money of
in the cooling arrangement in SIV of WAG
reduction, ease of maintenance & reusability point of view.
q) Scrap Disposal at ELS/ANGL:Scraps disposal during 2016
Year Ferrous Scrap
2011-12 6.290MT
2012-13 120.914MT
2013-14 83.695 MT
2014-15 97.77MT
2015-16 73.00MT
2016-17 42.394MT
Availability of material at ELS/ANGL (up to a) UES
Item On
locos Recommended
spare as per Rly. Bd.
% age
TM
armature
(Hitachi)
846 4
TM Stator
(Hitachi) 846 4
TFP 141 2
20
Total Stock
item
Avilable stock
Stock Item available
for 2016-17 up to
May'16
630
630
0100200300400500600700
Stock Item available for 2016-
Stores position of attached depot with loco shed:
17 for the
Total Stock items: 630
Stock item available: 625
Initial, Refresher & specialized Training has been imparted to Supervisor & staff
of ELS/ANGL regularly regarding maintenance of loco & Major equipments like GR, TFP, TM
overhauling, SIV, MPCS etc to improve the reliability of loco.
3rd Best Innovation Award:- ELS/ANGL has been awarded the 3
on IR with a prize money of `1 Lac for the year 2014-15 for the work of modification
in the cooling arrangement in SIV of WAG-7 loco which is very effective from cost
maintenance & reusability point of view.
Scrap Disposal at ELS/ANGL: Scraps disposal during 2016-17(Up to May-16) is 64.713MT.
Non-ferrous
Scrap
Total in MT
Nil 6.290MT
6.7126MT 127.6266MT
………… 83.695 MT
5.84MT 103.61MT
……… 73.00MT
22.319MT 64.713MT
Availability of material at ELS/ANGL (up to May’16):-
Recommended
spare as per Rly. Bd.
Actual
spare
Healthy
spare
Under
repair
Healthy spares as
recommended
Qty
33.84 87 83 04
33.84 63 60 03
2.82 07 04 03
Avilable stock
item
Item out of
stock
625 5
625
5
-17 up to May'16
Initial, Refresher & specialized Training has been imparted to Supervisor & staff
of ELS/ANGL regularly regarding maintenance of loco & Major equipments like GR, TFP, TM
ELS/ANGL has been awarded the 3rd
best Innovation award
15 for the work of modification
7 loco which is very effective from cost
Remarks
4.727MT Ferrous &
120.015MT Non-
ferrous has been
offered to store for
disposal so fat for
2016-17
Healthy spares as
%age of
recommended
245.27
177.30
141.84
21
(5400
KVA)
GR
141 1.5 2.11 5 1 4 47.39
RSI (Set) 141 1 1.41 15 9.5 5.5 673.759
VCB 141 3 4.23 25 11 14 260.05
Bogie
frame(Fabr
icated-G7)
282 4 11.28 14 14 00 124.11
Wheel set
(16:65) 846 ….. …… 64 51 13 ……
b) Sanctioned RSP Items:
c) Sanctioned M&P Items:
Sl.
No.
Description Qty.
Sanctioned
Qty.
Received
Balance
1 Test console for testing DC Traction
Motor
01 01 (Material
rejected)
01
2 Micro-processor based universal
dynamic testing machine for hydraulic
damper of WAG-7 locomotives
01 NIL 01
VII. Preparation of Check sheets for Inspection & OH:-
• Check sheets have been prepared for all activities like loco inspection, loco testing,
equipment overhauling, equipment testing, anti derailment, anti skidding, anti stalling,
summer precaution, monsoon precaution, winter precaution etc.
• Preparation of quality assurance check sheet of AOH/IOH:- Quality assurance
check sheet for major schedule(AOH,IOH) has been prepared for quality
improvement.
• The IOH check sheet of 5400KVA transformer has been revised w.r.t. the
latest SMIs issued by RDSO to improve quality & reliability. A new check
sheet for TFP oil filtration & air release has been introduced to eradicate QLM drop
cases of TFP due to improper air release.
Sl. No. Description Qty. Sanctioned Qty. Received Balance
1 Wheel Set (16:65) 68 set 42 26
2 Bogie Frame 07 nos. 06 01
3 Main Transformer,
5400 KVA for
WAG7 Loco
06 nos. 05 01
4 High reach Panto 35 nos. 10 25
5 Dynamic Braking
Resistors
05 nos. 00 05
6 Single bottle VCB 24 nos. 16 08
22
Modification and innovation done at ELS/ANGL
• Provision of extra protection for FDCS cable:-Re-bunching of FDCS cable,
control cable and hood modification have been carried out to avoid damage of cable.
(Before attention) (After attention)
• Provision of PVC pipe in power cable of Traction Motor :- PVC pipe has been
provided in power cable of Traction motor to avoid damage against mechanical
rubbing.
(Before attention) (After attention)
• Use of vacuum cleaner :- Cleaning of Static
Inverter and Rectifier block by vacuum
cleaner has been started during IC and AOH
schedules to improve the reliability of these
equipments.
• Use of Pneumatic torque wrench
Pneumatic torque wrenches have been
procured and used for proper tightening of
nut and bolt.
• Modification of C
Series connection of auxiliary interlock
(BBC contact) of C
to avoid TLTE in case of failure of any
auxiliary interlock resulted punctuality loss.
• MCP fan pressing
MCP fan pressing
has been designed and fabricated by the
Pneumatic section of ELS/ANGL for easy
pressing of MCP fan
• Q-30 Circuit modification
Q45
Q30
Existing Q30 circuit
23
Use of Pneumatic torque wrench :-
Pneumatic torque wrenches have been
used for proper tightening of
Modification of C-145:-
Series connection of auxiliary interlock
(BBC contact) of C-145 has been carried out
to avoid TLTE in case of failure of any
auxiliary interlock resulted punctuality loss.
fan pressing unit:-
MCP fan pressing equipment (Fan pusher)
has been designed and fabricated by the
Pneumatic section of ELS/ANGL for easy
pressing of MCP fan.
30 Circuit modification:
a1
a0
993
991
RQ30,
(3.9KΩ)
UA-2UA-1
Existing Q30 circuit
Q45
RQ30,
(3.9KΩ)
Q30
UA-1
Modified Q30 circuit
QCON
a1
a0
993
991
UA-2
Modified Q30 circuit
24
• SIV Cooling fan modification(AAL make):-
ELS/ANGL has indigenously modified 14 Nos. 3-
phase cooling fan of SIV of M/s AAL & Ms
Hirect make using 3- phase auxiliary motor
(Havells, SH, Ranjan, BT, Kirloskar) which is
more cost effective than the existing ZEIHL
ABEGG make motor.
• MPCS input card modification(Medha make) :
Shed has traced out the reason of malfunctioning of MPCS- M/s MEDHA make in
rainy season and modification (increase to sensing voltage of input card from 25
volt to 60 volts) has been suggested to RDSO for implementation. Accordingly,
RDSO has directed the firms for implementation.
• Modification of heater cum blower assembly:- Modification of the terminal of heater
cum blower assembly (from existing Coupler
type to SB type) has been carried out in
aerodynamic MPCS based WAG-7 locomotives of
ELS/ANGL w. r. t. RDSO SMI No. RDSO /
2011/ EL/ MS/ 0408, Rev. ‘0’for easy
maintenance.
• Modification of HMCS switch :- Bypassing of QDs during isolation of
Traction motor by the operation of HMCS in MPCS loco has been detected
by shed and modification (hardware as well as software)has been suggested to
RDSO for further implementation and RDSO has issued modification sheet
accordingly vide modification sheet no. RDSO/2011/EL/MS/0404 Rev’0’ vide letter
no. EL/4.2.15, dated 28.12.2011.
25
• Brake Cylinder pressure sensing modification:- ELS/ANGL has successfully
carried out Brake Cylinder pressure sensing modification in M/s AAL make ESMON
in co-ordination with firm in loco no.28136/WAG7/ANGL on trial basis. With
this modification the application of both loco & train brakes will be displayed &
recorded in the ESMON with date & time.
• Fabricated an Axle Box Overhauling stand:- ELS/ANGL has indigenously
fabricated an Axle Box Overhauling stand for
overhauling of Axle Box smoothly at shop
floor.
• TFP Oil Filtration stand :-One TFP Oil
Filtration stand has been designed arranged by
ELS/ANGL for carrying out TFP oil filtration
during Major schedule inspection.
•••• Interchangeability of MPCS :- Interchangeability of different make
MPCS (M/s Medha &M/s Stesalit) with same cable layout has been carried out by
shed on trial and same has been suggested to RDSO.
26
•••• Provision of earthing shunt :- Earthing shunts have been provided in
Microprocessor based control and fault diagnostic system (MPCS), Static Inverter to
improve the reliability of these equipments.
•••• Reduction of time period for major schedule:- The time period for major
Schedule (AOH&IOH) has been reduced by proper planning and utilization of man
power as a result major schedule of 9 to 10 locos has been carried out per month
which was previously 4 to 5 loco per month.
•••• MU formation of MPCS Loco: -
Shed has successfully made MU in Microprocessor based loco of M/s Medha, M/s
Stesalit & M/s SIL after significant modification in the control circuit of loco and so
far completed in all.
•••• Cross MU formation:- Cross Multi Unit of different make MPCS of loco-
28237(MPCS- M/s SIL Make) & loco-28167(MPCS-M/s Medha Make) has
been successfully done at ELS/ANGL.
•••• Single window system:- Single window system has been started for receipt
& dispatch of letters.
• Air dryer test bench:- An Air dryer test bench
has been modified & renovated by ELS/ANGL
& the testing of Air dryer has been started.
• MPH Test Bench: ELS/ANGL has
indigenously fabricated a MPH test bench for
testing of oil pump motor for 5400KVA loco
transformer.
• PT Overhauling Stand:- ELS/ANGL has
indigenously fabricated a panto
overhauling stand for carrying out overhauling
of Pantograph on shop floor during Major
inspection.
• Skill development programmedevelopment programme for I.T.I. students
has been organized by ELS/ANG
students from various I.T.I. of Angul have
participated.
• Test bench for testing of 3 fan ofSIV:-ELS/ANGL has indigenously
fabricated a test bench for testing of
3- phase cooling fan of SIV fitted in
WAG-7 locomotives of ELS/ANGL.
• A VCD test bench
designed by ELS/ANGL for carrying out
testing of VCDs in E4 section during
inspections to improve the reliability of
the equipment.
• Re-routing of TM Cable
TM-2 & 5 cables are
loco no.28048 to avoid
in the cleat & subsequent QOP drop.
27
Skill development programme:- A skill
development programme for I.T.I. students
has been organized by ELS/ANGL in which
students from various I.T.I. of Angul have
Test bench for testing of 3-phase cooling ELS/ANGL has indigenously
fabricated a test bench for testing of
cooling fan of SIV fitted in
locomotives of ELS/ANGL.
A VCD test bench has been indigenously
designed by ELS/ANGL for carrying out
testing of VCDs in E4 section during
inspections to improve the reliability of
routing of TM Cable: Re-routing of
2 & 5 cables are carried out in
loco no.28048 to avoid cable rubbing
in the cleat & subsequent QOP drop.
28
• UST of equalizer Beam:- Ultrasonic
testing of equalizer beam of WAG7 loco
has been introduced during IOH
inspection at ELS/ANGL to detect the
presence of flaw/internal crack for
improvement of quality.
• In-house repair of electronics cards of Microprocessor equipped in Electric
locomotives, i.e. 28 nos digital output card, 10 nos CPU card and 04 nos Display card
and saved a revenue of `6,23,318/- approximately.
• Condemnation of Loco no.28138:- Loco no.28138/WAG7/ANGL/ECoR had caught
fire on 08.06.2012 while working in goods train loaded with coal.The JA grade
committee comprising of DSE-4/RDSO, CQAM/CLW & Sr.DEE/TRS/ANGL had
submitted its final investigation report on 05.11.2014.Ministry of Railways has
approved the premature condemnation of fire accident loco vide letter no.
2013/Elect(TRS)/440/6, dated 28.12.2015.The said loco has been offered to
Dy.CMM-III/ECoR/BBS for condemnation through auction vide letter
no.ELS/ANGL/Store/S-26/16/352, dated 19.01.2016.
• Core Lifting of TFP:-
The Shed has carried out the special activity
of core lifting of TFP w.r.t. RDSO SMI-164
during 1st IOH to ensure proper tightness of
core bolts and healthiness of TFP.
Hereby, shed is able to minimize the
premature failure of TFP due to breakage of
core bolts followed by flashing in auto
winding of TFP & safe guards revenue of `
13.58 lac per TFP as a rewinding cost. The
same is completed in 18 locos so far.
• Technical Seminar on GPS based loco:- A technical seminar on GPS enabled
integrated Ver-3 Microprocessor based Fault Diagnostic & Control System has been
organized by M/s Medha at ELS/ANGL on 09.09.2015.The functions of digital input
& output cards, SCU & ISCU and remote monitoring of running & fault data paths
of Ver-3 MPFDCS using internet & GPS are discussed during the seminar.
• The in-house repair of a Jib Crane
Ton capacity has been carried out by shed &
commissioned in overhauling bay for lifting
Pantograph & auxiliary motors in the shop
floor of ELS/ANGL.
Commissioning of N
Items:-
• A new Dynamic Balancing Machine of
M/s KOSHA
ELS/ANGL on Dt: 14.12.2012 & practical
demonstration is given by firm to
concerned staff & supervisor
• Diesel hydraulic Road Mobile Crane
diesel hydraulic Road Mobile Crane
(Articulating type) of M/s Escorts make has
been received vide COFMOW contract No.
COFMOW/ IR/ S
10dtd.12.02.2015.
• Electric Driven Rotary screw type Air Compresso:- An Electric Driven Rotary screw
type Air Compressor
Godrej make has been received vide COFMOW
contract no. COFMOW/IR/S
2306 dtd. 03.02.15.
29
house repair of a Jib Crane of 1
Ton capacity has been carried out by shed &
commissioned in overhauling bay for lifting
Pantograph & auxiliary motors in the shop
floor of ELS/ANGL.
Commissioning of New M&Ps & Loco
A new Dynamic Balancing Machine of
make is commissioned at
ELS/ANGL on Dt: 14.12.2012 & practical
demonstration is given by firm to
concerned staff & supervisor.
Diesel hydraulic Road Mobile Crane:- A
diesel hydraulic Road Mobile Crane
(Articulating type) of M/s Escorts make has
been received vide COFMOW contract No.
COFMOW/ IR/ S-4710/12/P1/OP-2175/PO-
10dtd.12.02.2015.
Electric Driven Rotary screw type Air An Electric Driven Rotary screw
ressor (120 CFM capacity)M/s
Godrej make has been received vide COFMOW
contract no. COFMOW/IR/S-4820/14/P-I/OP-
• A hydraulic torque wrench machine of M/s
Tristar has been commi
ELS/ANGL on Dt: 24.03.13 for easy
Traction Motor nut & bolt.
.
• Commissioning Battery Operated Infra Red
Imaging System(Thermal Imager):
Operated Infra Red Imaging System(Thermal
Imager), Make: Testo 875
commissioned on 02.04.2014 for monitoring,
measurement & storing hot spot temperature on
various equipment(i.e. Bus ducts, bus bars,
isolators, switch board, HT/LT electrical panel
TFP bushing etc.) .
• A new Auto Boost Cum Trickle Battery Charging cum discharging by S. Electricals & Electronics, Kolkata has been
commissioned in Battery Section of ELS/ANGL in
this month.
Provision of Dust Proof DGA Room at
ELS/ANGL: The DGA room has been refurbished
and made dust proof with commissioning of second
DGA plant at ELS/ANGL
30
A hydraulic torque wrench machine of M/s
been commissioned at
: 24.03.13 for easy tightness of
Motor nut & bolt.
Commissioning Battery Operated Infra Red
Imaging System(Thermal Imager): A Battery
Operated Infra Red Imaging System(Thermal
Imager), Make: Testo 875-1, Germany has been
02.04.2014 for monitoring,
measurement & storing hot spot temperature on
various equipment(i.e. Bus ducts, bus bars,
isolators, switch board, HT/LT electrical panel
Auto Boost Cum Trickle Battery Charging cum discharging plant manufactured
by S. Electricals & Electronics, Kolkata has been
commissioned in Battery Section of ELS/ANGL in
Provision of Dust Proof DGA Room at
The DGA room has been refurbished
and made dust proof with commissioning of second
DGA plant at ELS/ANGL in November-2014.
a) Dynamic balancing:
started dynamic balancing of impeller of
auxiliary motor using portable vibration
analyzer in March-
b) Greasing adaptor for SIV Fan:
ELS/ANGL has indigenously prepared
greasing adaptor for 3
SIV for the purpose of external greasing
without removing the fan assembly from
loco.
c) Commissioning of High Reach Panto:
nos. of High reach panto (Model WBL 85
IR) of M/s Schunk Metal & Carbon India
Pvt. Ltd. has been commissioned in
WAG-7 locomotives of ELS/ANGL.
31
Dynamic balancing:- ELS/ANGL has
started dynamic balancing of impeller of
auxiliary motor using portable vibration
-2015.
Greasing adaptor for SIV Fan:-
ELS/ANGL has indigenously prepared
greasing adaptor for 3-phase cooling fan of
SIV for the purpose of external greasing
ithout removing the fan assembly from the
Commissioning of High Reach Panto:- 10
nos. of High reach panto (Model WBL 85
IR) of M/s Schunk Metal & Carbon India
Pvt. Ltd. has been commissioned in 10 nos.
7 locomotives of ELS/ANGL.
d) Provision of Safety, Innovations &
ELS/ANGL: Boards
Modifications have
e) Loco Body Painting during IOH schedule:
Loco Body Painting (Spray Painting) during IOH schedules at ELS/ANGL by outside
agency.
32
Provision of Safety, Innovations & Modifications Boards at shop floor of
Boards displaying safety measures, improvements, I
Modifications have been provided at shop floor at ELS/ANGL in November
Loco Body Painting during IOH schedule:
Painting (Spray Painting) during IOH schedules at ELS/ANGL by outside
Modifications Boards at shop floor of
measures, improvements, Innovations and
been provided at shop floor at ELS/ANGL in November-2014.
Painting (Spray Painting) during IOH schedules at ELS/ANGL by outside
33
f) Working stands for Transformer:
04 nos. of working stands for transformer have
been procured & utilized in shop floor during
overhauling & inspection of transformers in major
schedules.
g) Commissioning of Battery Charging Plant: A new Auto Boost Cum Trickle Battery Charging
cum discharging plant manufactured by S.
Electricals & Electronics, Kolkata has been
commissioned in Battery Section of ELS/ANGL in
Oct-2015.
h) Provision of 24V AC Supply:
Provision of 24V AC supply has been made in the
inspection bay of ELS/ANGL for providing
external supply to hand lamps & loco CFLs for
lighting purpose during inspection in loco.
i) Fabrication of working ladder:
Two nos. of working ladder has been
indigenously fabricated by
ELS/ANGL for easy access of loco
placed in heavy lifting bay & places
other than inspection pits.
n) Conversion of DC to AC DBR
Carried out by shed in loco no
22.09.06
o) Arrangement of Moist Air Filter
filter arrangement has been carried out
successfully in under Pit compressors for
providing dry air for greasing of loco equipments
from reliability point of view.
(p)Safety base for SLindigenously fabricated a safety b
being during removal of SL for changing &
failure attention to provide utmost safety to the
working staff.
34
Fabrication of working ladder: Two nos. of working ladder has been
indigenously fabricated by
ELS/ANGL for easy access of loco
placed in heavy lifting bay & places
other than inspection pits.
Conversion of DC to AC DBR: The conversion of DC to AC DBR has been
out by shed in loco no-27811 w.r.t. RDSO ELRS/MS/0348 Rev '0' dtd.
Arrangement of Moist Air Filter:- Moist air
filter arrangement has been carried out
successfully in under Pit compressors for
providing dry air for greasing of loco equipments
from reliability point of view.
Safety base for SL:- ELS/ANGL has
indigenously fabricated a safety base which is
being during removal of SL for changing &
failure attention to provide utmost safety to the
The conversion of DC to AC DBR has been
27811 w.r.t. RDSO ELRS/MS/0348 Rev '0' dtd.
35
SCRAP DISPOSAL OF ELS / ANGL
2015-16
Date Description Nos.
Weight in Kgs.
Value in ` Ferrous
Non Ferrous
09.04.2015 Ferrous Scrap 27MT approx released
medium phosphorous cast iron brake blocks … 27 MT … 499527
18.06.2015 [Ferrous Scrap] Medium Phosphorous cast