Halcrow Pakistan (Pvt) Limited 3rd Floor, Nawa-e-Waqt House, Mauve Area Sector G-7/1, Zero Point, Islamabad, Pakistan tel + 92 51 220 3451 fax + 92 51 220 3462 www.halcrowpk.com Environmental Impact Assessment for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21), Sindh Document: 500024.BZ.EIA.F01 October 2019
374

EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

Mar 25, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

Halcrow Pakistan (Pvt) Limited 3rd Floor, Nawa-e-Waqt House, Mauve Area

Sector G-7/1, Zero Point, Islamabad, Pakistan tel + 92 51 220 3451 fax + 92 51 220 3462

www.halcrowpk.com

Environmental Impact Assessment for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21), Sindh

Document: 500024.BZ.EIA.F01 October 2019

Page 2: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 HPK

Document History

 

‘Environmental Impact Assessment for Exploration and Associated Development Activities in Kotri 

North Block (E.L. 2568‐21), Sindh’ 

This document has been issued and amended as follows: 

Version  Date  Description Created by Verified by Approved by

01  17/10/19  1st Draft  AAA  AQA  AQA 

02  23/10/19  Final  AAA  AQA  AQA 

           

 

AAA: Arslan A. Asghar 

AQA: Abdul Qayyum Aslam 

Page 3: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-1 HPK

Executive Summary

ES.1 Introduction

This report presents the findings of an Environmental Impact Assessment (EIA) 

carried out by Halcrow Pakistan (Pvt) Limited for the proposed exploration and 

associated development activities in Kotri North Block (E.L. 2568‐21) by United 

Energy Pakistan Limited (UEPL) which lies within geographical jurisdiction of Sindh 

province. A key map showing the location of Kotri North Block is presented as Figure 

ES‐1. This EIA has been prepared in conformance to the requirements of the Sindh 

Environmental Protection Act 2014, the Sindh Initial Environmental Examination and 

Environmental Impact Assessment Review Regulations, 2014 and the Pakistan 

Environmental Assessment Procedures, 1997. 

The EIA report explicitly covers exploration and associated development activities in 

the entire spread of Kotri North Block. These activities range from 2D/3D seismic 

surveys, drilling of exploration/development wells, laying of flow line/s from 

producing wells to the hydrocarbons gathering system/processing facility, 

establishment of processing facilities e.g. EWT or CPP, up‐gradation/modification of 

existing facilities with associated civil and engineering works e.g. construction of 

access track/s, residential camp/s, construction of well site/s etc. and finally 

decommissioning and site restorations. Proposed project activities will be commenced 

with 2D/3D seismic survey and based upon the aforementioned seismic data 

acquisition and its interpretations, UEPL will plan to drill wells at the most certain 

perspective locations as part of exploration/development plan. After the successfully 

drilling at any proposed well location and in case of discovery, flow line/pipeline will 

be laid from each well to the new/existing hydrocarbons gathering and production 

system.  

The proposed 2D/3D seismic surveys will be carried out in the entire spread of Kotri 

North Block (hereafter also referred as the ‘project area’ in the later sections of the 

report) however, location of the seismic survey/s is not finalized yet. Similarly, the 

exact location of exploratory/development wells and alignment of flow line/s is not 

available at this stage either. The exact location of wells will only be made available 

after proposed seismic data acquisition and its interpretations by United Energy 

Pakistan Limited. Furthermore, depending on the drilling results, alignment of flow 

line/s will be finalized. Likewise depending on the need basis, location of 

hydrocarbons processing facility will be finalized and executed accordingly. Therefore, 

this EIA report is based on the fact that United Energy Pakistan Limited will submit 

the Project Initiation Report (PIR) or Activity Initiation Report (AIR) for each planned 

activity to Sindh Environmental Protection Agency (for information) prior to the start 

of each aforementioned activity in the project area.  

Page 4: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-2 HPK

The objective of exploration and associated development activities is to explore for 

potential hydrocarbons reserves in the prospective formations identified during 

previous Oil & Gas exploration activities in the region particularly in the leased area. 

ES.2 Objectives of the EIA

The objectives of the Environmental Impact Assessment (EIA) are to: 

Assess the existing environmental conditions in the project area, including the 

identification of environmental sensitive areas and develop a baseline of its 

existing environmental and socioeconomic conditions; 

Identify and investigate all impacts of the proposed exploration and associated 

development activities on the physical, biological and socioeconomic environment 

of the project area; 

To propose mitigation measures that would help UEPL in conducting the 

exploration and development activities in an environmentally sustainable manner;  

To uncover the construction and operational phase impacts up to 

microenvironment levels in which project is proposed to be sited; and 

To develop an Environmental Management Plan (EMP) that would assist UEPL in 

the effective implementation of the recommendations of the EIA. 

ES.3 The Project Proponent

United Energy Pakistan Limited, UEP Alpha Limited and UEP Beta GmbH collectively 

known as UEP (UEP Alpha and UEP Beta were previously known as OMV Maurice 

Energy Limited and OMV (Pakistan) Exploration GmbH) are subsidiaries of United 

Energy Group (UEG), an energy company listed on the Hong Kong Stock Exchange. 

UEP is the largest foreign oil & gas exploration and production (E&P) company in 

Pakistan, and have been contributing significantly in reducing Pakistan’s dependency 

on oil & gas imports through indigenous hydrocarbon production. 

UEG’s asset has a rich heritage, starting nearly four decades ago when an American 

E&P company, Union Texas Pakistan, initiated operations in Khaskeli, Badin. Since 

then, this asset has undergone several changes and a shift in ownership a number of 

times. Acquisition of British Petroleum’s assets by UEG was the first venture in 

Pakistan and since then UEG has made significant investments in the business, 

resulting in rapid growth. UEG’s onshore concessions span across 20,000 square 

kilometers and are spread across Sindh and Balochistan provinces. 

UEP is conscious of environmental footprint and work diligently to ensure that no 

harm is caused to anyone involved in or impacted by their activities. UEP not only 

comply with all applicable laws related to Health, Safety and the Environment (HSE) 

but also have a set of internal policies in place to minimize the environmental impact 

of their operations. 

In coordination with the government, communities and non‐governmental 

organizations, UEP has invested in sustainable social investment projects in the areas 

Page 5: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-3 HPK

where operating. CSR interventions have brought a positive impact in the lives of local 

communities by enhancing access to technical training, creating opportunities for 

sustainable income generation and providing quality education and healthcare 

services. UEP has invested in the alternative energy sector. UEG (parent company) has 

also invested in a wind energy project located in the Jhimpir wind corridor in the 

Sindh province. This project was one of the 14 top priority projects of the China 

Pakistan Economic Corridor (CPEC). 

ES.4 Kotri North Block (E.L. 2568-21) & Project Area

Kotri North Block (E.L. 2568‐21) is located in geographical jurisdiction of Jamshoro, 

Matiari and Hyderabad districts of Sindh province with a total area coverage of 

approximately 1,397 square kilometers (km2). Out of total covered area of the block 

district Jamshoro contributes the major part i.e. 1,133.5 km2 whereas, district Matiari 

shares approx. 257 km2 and district Hyderabad contributes about 6.6 km2 (see Figure 

ES‐2). Taluka wise distribution of abovementioned districts is provided in table below: 

No.  District   Taluka  Area Coverage (km2) 

1.   Jamshoro Kotri  442 

Manjhand  691.5 

2.   Hyderabad  Hyderabad  6.5 

3.   Matiari 

Hala  210 

Matiari  4 

Saeedabad  43 

United Energy Pakistan is operator of the block and holds 50% working interest. Other 

joint venture (JV) partners include Pakistan Petroleum Limited (PPL) and Asia 

Resources Oil Limited (AROL). PPL and AROL holds 40% and 10% working interest 

in the block respectively.  

Kotri North Block (E.L. 2568‐21) encompass several forest protected areas. There are 

about 28 reserve forests (all of them are small sized) are falling in the geographical 

jurisdiction of the Block (E.L. 2568‐21). These reserve forests includes; Kunar Rishal, 

Keti Dallu, Nur Keti, Drabo, Manjhand, Keti Khasai, Unarpur, Rudhapur, Rishal, 

Nural Abad, Racho Khanot, Pako Bhanot, Butho, Ranno, Rajri, Salaro Ghotana, Lakha, 

Khasai, Ghotana, Murid Rais, Sekhat, Matiari, Miana, Hatri, Muhammad Khan, Bada, 

Shah Bukhari and Railo Bada. These reserve forests which were once pristine riverine 

forests, now mostly are under cultivation. Location of forest protected areas is also 

shown in Figure ES‐2. 

ES.5 The Proposed Project

The entire leased area spreads over approximately 1,397 km2 and lies in Jamshoro, 

Matiari and Hyderabad districts of Sindh province. The EIA report explicitly covers 

exploration and associated development activities in the entire spread of Kotri North 

Block. These activities range from 2D/3D seismic surveys, drilling of exploration/ 

development wells, laying of flow line/s from producing wells to the existing 

hydrocarbons gathering system/processing facility, establishment of processing 

Page 6: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-4 HPK

facilities e.g. EWT or CPP, up‐gradation/modification of existing facilities with 

associated civil and engineering works e.g. construction of access track/s, residential 

camp/s, construction of well site/s etc. and finally decommissioning and site 

restorations.  

Proposed project activities will be commenced with 2D/3D seismic survey and based 

upon the aforementioned seismic data acquisition and its interpretations, UEPL will 

plan to drill wells as part of exploration/development plan. After the successfully 

drilling at proposed well location and in case of discovery, flow line/pipeline will be 

laid from each well to the new/existing hydrocarbons gathering and production 

system over the period of three years. Detailed proposed project activities will include 

but not limited to be are listed below: 

Seismic activities (2D and 3D); 

Well sites preparation & construction activities; 

Drilling of exploration, development and water injection wells (no new water 

injection well will be drilled only plugged & abandoned (P&A) well will be used 

for the purpose); 

Surface facilities development at drilled well sites including EWT; 

Laying of flow lines from producing wells to CPP/Gathering hub; 

Laying of flow lines from CPP/Gathering hub to Point of Delivery (POD); 

 Development of early production, production and testing facilities which will 

include plant construction and operations; 

Development of remote facilities; 

Up‐gradation/Modification of existing facilities; 

Relocation of existing facilities e.g. decommissioning of plant equipment and 

relocation to other location within project area; 

Construction of access roads & residential camps; 

Decommissioning of surface facilities (well sites/plant sites); and  

Sites restoration. 

The proposed 2D & 3D seismic data acquisition will be carried out using a 

combination of vibroseis and dynamite technologies. The objective of the seismic 

survey is to explore the subsurface in the area to identify hydrocarbon laden 

formations. For seismic survey a base camp with fly camp (if required) will be 

established to house the seismic crew followed by seismic activity and finally 

restoration of seismic lines and base camp/fly camp upon completion of survey area to 

original conditions. 

Drilling of each well will start with the construction of the access road, rig camp and 

well site for each proposed location. This will be followed by drilling of exploratory or 

Page 7: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-5 HPK

development well. Each proposed well will be drilled using a conventional land 

drilling rig. A specialized waste management system using Hi‐G dryers and 

centrifuges will be installed on the land drilling rig for better management and 

disposal of drilling wastes. This will also help in reducing the water requirements 

during drilling and managing the size of wastes pits at each proposed well location. 

Depending on the drilling results (success or failure), abandonment, completion or 

suspension of the well and site restoration. Furthermore, in case of discovery of 

hydrocarbons at any of the proposed well locations, laying of flow line/pipeline from 

wells to the hydrocarbons gathering/processing facilities and tie‐in/wellhead works 

will be carried out. 

The proposed 2D/3D seismic surveys will be carried out in the entire spread of Kotri 

North Block however, location of the seismic survey/s is not finalized yet. Similarly, 

the exact location of exploratory/development wells and alignment of flow line/s is not 

available at this stage either. The exact location of wells will only be made available 

after proposed seismic data acquisition and its interpretations by United Energy 

Pakistan Limited. Furthermore, depending on the drilling results, alignment of flow 

line/s will be finalized. Likewise depending on the need basis, location of 

hydrocarbons processing facility will be finalized and executed accordingly. Therefore, 

this EIA report is based on the fact that United Energy Pakistan Limited will submit 

the Project Initiation Report (PIR) or Activity Initiation Report (AIR) for each planned 

activity to Sindh Environmental Protection Agency (for information) prior to the start 

of each aforementioned activity in the leased area of Kotri North Block. 

ES.6 The EIA Methodology

Various steps undertaken in the EIA preparation included sharing of ToRs with key 

stakeholders; understanding of the proposed operation/s; review of legislations and 

guidelines; EIA scope and methodology; collection of secondary data including 

physical, biological & socioeconomic environment and heritage aspects; field data 

collection; stakeholder consultations; review of alternatives; impact identification; 

recommendations for mitigation and monitoring measures; development of 

environmental management plan (EMP) and reporting. 

Field survey for EIA study was carried out by a team of environmentalist, wildlife 

expert, botanist and sociologist/gender specialist in last week of August, 2019. Field 

data collection also included ground trusting of available secondary information. 

Secondary information was collected from UEPL, in‐house sources like previous 

environmental studies in the region in addition to respective District Census Reports 

(DCRs). Applicable environmental assessment procedures prepared by the Pakistan 

EPA were followed in the preparation of this EIA. 

ES.7 Biological Resources

Kotri North Block (E.L. 2568‐21) is predominantly located in hilly, stony and sandy 

plains followed by cultivable land & agricultural fields. Apart from them, there are 

Page 8: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-6 HPK

two other important biological habitats which includes Indus River, irrigation network 

& associated marshes and wasteland/fallow lands. During the field visit for EIA a total 

of 128 floral species belonging to 37 families, 101 birds, 20 mammals and 20 reptiles 

were recorded from entire stretch of Kotri North Block. 

Out of total 101 recorded birds, 18 species have protected status under the provision of 

Sindh Wildlife Protection Ordinance, 1972 which include some ducks, raptors, egrets 

and herons. Out of total recorded species 3 are on IUCN Red List, 12 migratory species 

are on CMS and 20 included on CITES appendices having international demand for 

trade. Out of total recorded mammals, three species are of global significance 

including Fishing cat, Hog deer and Indian pangolin. 

ES.8 Impacts and Mitigations

The EIA covers potential effects of the proposed project activities in the Kotri North 

Block. Potential impacts on the physical, biological, socioeconomic, archaeological and 

cultural environment that may arise from exploration and associated development 

operation and the mitigation measures that will be adopted to reduce or minimize the 

impact have been assessed and are summarized in Table ES‐1. Overall, the proposed 

exploration activities will have positive impacts on the local communities of the area.  

ES.9 Environmental Management Plan

For the effective implementation and management of mitigation measures, an 

Environmental Management Plan (EMP) has been prepared which meets the 

requirement of the Sindh Initial Environmental Examination and Environmental 

Impact Assessment Review Regulations, 2014 and the Pakistan Initial Environmental 

Examination and Environmental Impact Assessment Review Procedures, 2000.  

The EMP provides a delivery mechanism to address potential impacts of proposed 

project activities, to enhance project benefits and to introduce standards of good 

practices in all project related activities. The EMP has been prepared with the objective 

of: 

Defining legislative requirements, guidelines and best industry practices that 

apply to the proposed project activities; 

Defining mitigation measures required for avoiding or minimizing potential 

impacts assessed by the EIA; 

Defining roles and responsibilities of the project proponent and the execution 

contractors; and 

Defining requirements for environmental monitoring and reporting. 

ES.10 Conclusion

The EIA has fully examined the proposed project activities, the background 

environmental conditions of the project area and the environmental impacts likely to 

arise from the proposed exploration and associated development activities. Overall, 

the EIA report for exploration and associated development activities in Kotri North 

Page 9: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-7 HPK

Block (E.L. 2568‐21) has predicted that the project will comply with all applicable 

environmental standards and legislations before and during the proposed exploration 

and associated activities. This EIA has also demonstrated the acceptability of the 

residual impacts from the project and the protection of the identified environmentally 

sensitive resources. Environmental monitoring mechanism have been recommended 

before and during the proposed operation, where necessary, to verify the accuracy of 

the EIA predictions and the effectiveness of recommended mitigation measures.  

Based on the above, this report concludes that there are no potential adverse 

environmental impacts from proposed exploration and associated development 

activities in Kotri North Block. Impacts of less significance can be mitigated to an 

acceptable level by adequate implementation of the mitigation measures identified 

and suggested, hence, no significant or unacceptable change in the baseline 

environmental conditions will occur. Similarly, the operation will have a visible 

positive impact on the socioeconomic conditions of the local residents and 

significantly boost the economy of the area. Mitigation measures to help alleviating 

potential identified impacts have been recommended and a project specific EMP has 

been provided for implementation of these mitigation measures. 

Page 10: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-8 HPK

Table ES‐1: Summary of Potential Impacts and Mitigation 

Potential Impact  Sources  Recommended Mitigation Measures 

Changes in 

landscape, 

topography and 

soil erosion 

Land uptake & 

clearing 

Off‐road travel 

Over‐speeding 

Use of existing dirt 

tracks 

Poor compaction of 

working sites 

Total land uptake by the project facilities e.g. 

operational camps, well sites, processing facility 

and access roads will be kept to the minimum 

required 

All project facilities will be located in existing 

clearings and on levelled land 

Clearing of vegetation and disturbance to the 

natural soils will be minimized 

Cuttings of trees/bushes will be avoided 

Access tracks to project locations will be gravel 

topped and properly compacted 

Land area requirements for new construction 

camp/s (if required) and RoW of flow lines will be 

kept to the minimum required 

Topsoil of the RoW will be separately stored and 

will be backfilled after proper compaction 

Existing access roads shall be used as much as 

possible and off‐road travel will be avoided 

Vehicles speed will be maintained and monitored 

Periodic trainings will be provided to drivers on 

environmental sensitivity 

Movement of equipment will be restricted to 

work areas only 

Seismic lines and access tracks in the undulating 

plains and higher elevations will follow natural 

contours as much as possible 

Uncontrolled and unnecessary clearing, dozing, 

excavations or quarrying, storage of construction 

material etc. will be avoided 

Photographs will be taken at the begning and on 

regular intervals throughout the project activities 

to monitor any changes in the landscape and 

topography 

Topography will not be altered by taking all 

appropriate measures 

Soil and water 

contamination 

Domestic wastes 

Oily wastes 

Clinical waste 

Construction wastes 

Produced water 

Drilling mud and 

cuttings  

Cleaning and hydro‐

testing of flow lines 

Sewage Treatment Plant (STP) shall be the most 

preferred option for handling of black/grey water 

under BATNEEC/BAT, but in case of 

unavailability of STP, septic tank and soak pits 

shall be provided 

Project related facilities will be setup at an 

appropriate distance from the nearby settlements 

Septic tanks and soak pits at 300 m from water 

resources e.g. local water wells or hand pumps 

Page 11: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-9 HPK

Potential Impact  Sources  Recommended Mitigation Measures 

Disposal of wastes according to waste disposal 

procedure on regular and strict basis 

Soak pits to be properly covered to avoid surface 

runoff water 

Sprinkling of untreated wastewater will not be 

allowed 

No solid waste will be disposed of in the field 

Burning of waste will not be allowed 

Municipal combustible, non‐combustible and 

hazardous wastes will be handed over to 

approved contractor 

Restoration of sites including septic and soak 

system according to restoration protocols  

Temporarily store clinical wastes at site and hand 

it over to approved waste contractor for safe 

disposal 

Washing of vehicles in designated areas within 

the campsites 

Checking of vehicles and fuel tanks for fuel or oil 

leaks 

Concrete pad, bunded area and proper marking 

for all fuel tanks 

Disposal of all spills including contaminated soil 

according to waste management protocol 

At the time of seismic restoration all pin flags, 

signs and refuse from seismic lines will be 

removed 

The drill cuttings and water based mud will be 

disposed into a pit lined with an impermeable 

HDPE liner 

Produced formation fluids during testing will be 

flared along with the gas or collected inside the 

lined waste pit at the well sites or processing 

facility 

Waste pits at the well sites will be lined with an 

HDPE liner 

Drill cuttings and mud pits at the well sites will 

be at a minimum distance of 300 m from local 

water resource 

All other waste pits or enclosures at least 300 m 

from local settlements and local water resources 

Proper fuel and oil transfer operations 

Evaporation pit will be built at a distance of 300 m 

(HDPE lined) from local water sources 

Page 12: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-10 HPK

Potential Impact  Sources  Recommended Mitigation Measures 

Spill prevention and contingency plan will be 

developed and implemented 

Storage of chemicals on brick masonry pads with 

periphery drains 

Hydro‐testing of flow line will be performed 

following approved procedures, a purpose built 

pit will be used for collection of wastewater from 

the activity 

Climate and 

ambient air 

quality 

Equipment 

Machinery 

Vehicles 

Maintenance of generators, equipment and 

vehicles to keep them in good working condition 

Adopt best management practices to minimize 

the course of any segment of the proposed project 

Regulation and monitoring of vehicles speed 

Locate rig site and campsites 300 m away from 

the community 

Minimize dust emissions due to road travel by 

regulating vehicles speed and watering of the 

access track (where required) 

While selecting routes of access track maintain a 

reasonable distance from communities. Preferably 

access tracks passing through communities will 

be avoided 

If unavoidable a speed limit of less than 30 km/hr 

will be observed on the section of the road 

passing through the community 

Emissions should comply national and provincial 

standards wherever applicable 

Construction of burn pits will not be allowed 

Flare pit will be kept downwind at the well site 

and processing facility and at least 300 m from the 

nearest community 

The duration of flaring during well testing and 

production phase will be kept to the minimum 

required 

Sand blasting will be carried out under contorlled 

condition to avoid any dust emission 

Noise pollution  Equipment, 

machinery and 

vehicles 

 

It shall be ensured that generators, vehicles and 

other potentially noisy equipment used are in 

good working condition 

Well sites, campsites and production facility will 

be located 300 m away from nearest communities 

The use of horns by project vehicles shall be 

minimized. The use of pressure horns shall not be 

allowed 

Page 13: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-11 HPK

Potential Impact  Sources  Recommended Mitigation Measures 

Movement of all project vehicles and personnel 

shall be restricted to within work areas only 

Preferably, generators will be kept within 

enclosures to minimize dispersion of noise 

Water 

abstraction 

All activities 

requiring water 

Water from wetlands/dhands or other surface 

water bodies e.g. canals etc. will not be used for 

the proposed project 

Water to be used only from local wells or UEPL 

may install its own water wells after ensuring the 

available capacity at the local tube well/water 

well (safe yield minus local demand) is at least 

50% greater than the project demand 

Record water consumption for each project 

component 

Adaptation of water conservation policy and 

avoid water losses 

The use of brackish water will be maximized 

wherever possible 

Install new water well at 300 m from existing local 

wells and designed to abstract water from deep 

aquifer 

Utilization of water resources that are in 

possession of local owners shall be compensated 

as per mutual agreed terms 

Abstract water from sources recommended in the 

EIA report 

Blockage of 

natural drainage 

Construction 

activities 

Area around the well sites and all campsites shall 

be landscaped to avoid blocking of natural 

drainage 

Causeway crossings and pipe culverts will be 

provided at all stream crossings to avoid blocking 

of natural drainage 

Uncontrolled clearing, dozing, excavations or 

quarrying, storage of construction material etc. 

will be avoided 

Clearing of 

vegetation and 

loss of habitat 

Land uptake and 

clearing 

Off‐road travel 

Minimize land uptake for proposed project 

activities 

Access tracks will be properly compacted at the 

time of construction and afterwards 

Periodic training to drivers on sensitivity of 

environment 

Avoid unnecessary damage to vegetation  

All operation based camp/s will be setup in 

existing clearings and levelled land outside the 

boundary of forest protected area 

Page 14: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-12 HPK

Potential Impact  Sources  Recommended Mitigation Measures 

Apply good management practices 

Movement of project personnel will be restricted 

to working areas only 

Avoid clearing of trees or even tall shrubs 

Prohibit use of local wood for cooking or heating 

purposes 

Minimize off‐road travel 

Vehicles speed will be regulated and monitored 

During proposed seismic operation clearing of 

vegetation will be minimized by minimizing the 

width of the vibroseis tracks, minimizing the 

preparation of new access tracks and keeping the 

width of new access tracks to the minimum 

required 

Blasting, construction or drilling activities will not 

be performed in Indus River 

Crew personnel while working along seismic 

lines will concentrate within a corridor of 4.5 m 

Topsoil of the RoW for flow lines will be 

separately stored 

This topsoil of the RoW will be backfilled after 

proper compaction ensuring regeneration of 

vegetation 

Disturbance to 

wildlife 

Noise generated from 

project activities 

Movement of 

personnel and 

vehicles 

Lights used at the 

project facilities 

Clearing of vegetation 

Prohibit hunting, killing, fishing, trapping, 

feeding or harassment to wildlife 

Activities in the core habitats of protected species 

shall be avoided as much as possible 

Proposed activities in the protected areas shall be 

completed in the shortest possible time  

Awareness trainings for contractors and crew 

personnel prior to engagement in the operation 

Minimize vegetation clearing and land uptake 

Movement of project personal will be restricted 

Do not dispose of food waste in open 

Maintain vehicles speed on access road to avoid 

incidental mortalities of reptiles 

Lights used at the campsites will be kept to the 

minimum required 

Adhere with minimum distances specified in the 

EIA and EMP for entire course of the operation 

All mitigation measures listed in the EIA/EMP to 

minimize noise levels, dust emissions, exhaust 

emissions and waste generation will be adhered 

to 

Page 15: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ES-13 HPK

Potential Impact  Sources  Recommended Mitigation Measures 

Construction activities during night hours will be 

prohibited. However, in case of urgency, night 

activities will be allowed after reassessing the 

impact of activity on the environment through a 

risk assessment or change mangement statement 

and specifying additional mitigation measures if 

required 

Blasting, construction or drilling activities will not 

be performed in Indus River 

Night traveling will only be allowed when 

absolutely necessary or in case of emergency only 

Impacts of the individual projects on wildlife will 

be monitored by independent monitoring teams 

Socioeconomic, 

archaeological 

and cultural 

environment 

Acquisition of lands 

for project facilities 

Exploitation of local 

water sources 

Improper disposal of 

wastes 

Dust and exhaust 

emissions 

Noise from project 

facilities 

Movement of vehicles 

on access tracks close 

to the communities 

Protect local sources of drinking water 

Sprinkling of water to avoid dust emission 

wherever required 

Re‐routing or bypass to all major settlement 

Training will be given to drivers on safe driving 

Strict compliance on UEPL’s HSE guidelines 

Priority in employment to local residents living 

close to the project location as per the local 

regulations and company’s competency criteria 

Regulation and monitoring of vehicles speed 

The rig sites and campsites will be located at a 

minimum distance of 300 m from communities 

Land acquisition and distribution of 

compensation must be transparent and on fast 

pace 

Apply best management practice in the entire 

course of operation 

During project, links with local community will 

be maintained 

Use of local wood as fuel will be prohibited 

Maintain community complaints register 

Cultural norms will be respected 

Pay proper and justified compensation for land 

and water being utilized in the entire operation 

Dispose of all wastes following the requirements 

of the EIA 

Use local water sources only after complying with 

the relevant EIA/EMP requirements 

Maintain appropriate offsets from sites of 

religious, cultural or archaeological significance if 

encountered 

 

Page 16: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

Lat :25° 27' 32.436" NLong:68° 36' 29.484" E

Lat :25° 41' 38.688" NLong:68° 33' 20.196" EKotri

Hala

Thatta

Matiari

Hyderabad

Latifabad

Qasimabad

Tando Adam

Jamshoro

Matiari

Thatta

Hyderabad

Sanghar

68°32'0"E

68°32'0"E

68°24'0"E

68°24'0"E

68°16'0"E

68°16'0"E

68°8'0"E

68°8'0"E

68°0'0"E

68°0'0"E26

°0'0

"N

26°0

'0"N

25°5

2'0

"N

25°5

2'0

"N

25°4

4'0

"N

25°4

4'0

"N

25°3

6'0

"N

25°3

6'0

"N

25°2

8'0

"N

25°2

8'0

"N

25°2

0'0

"N

25°2

0'0

"N

LegendBlock Boundary Reserve Forest (SOP) Tehsil Boundaries

District Boundaries

·0 2.5 5 7.5 10 12.5 15 17.5 Km

Halcrow Pakistan (Pvt) LimitedUnited Energy

Pakistan

Fig ES-1: Key Map of Kotri North Block

Project:EIA for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21)

Page 17: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

h

h

h

h

h

Goth Rais Ghulam Ali Mari

Goth Tando Syed Khan Mitho

Graveyard / Shrine

Sindh Agriculture University

Graveyard

Graveyard

Goth Akro

Graveyard

Graveyard

Graveyard

Goth Tajpur

Goth Salaro

Goth Jaitharo

Goth Aliabad

Goth Haji Ishaq

Goth Karim Deno

Goth Tadri Mori

Goth Haji Shabu

Goth Khuda baksh

Goth Sufan Bacho

Goth Hayat Bhatti

Goth Bachal Dehta

Goth Bakhshia Marri

Goth Suleman Barejo

Graveyard on Highway

Goth Bego Khan Mirjat

Goth Sayen Dino Malah

Goth Mehram Khazkheli

Goth Gulshan e Shahbaz

Goth Darya Baig Mughal

Dargah Dado Khamiso Fakir

Shrine Baba Allah Bakhsh Jilani

Dargah Syed Muhammad Shah Bukhari

Goth Wadero Misri

Kotri

Hala

Matiari

Hyderabad

Thatta Latifabad

Tando Adam

Qasimabad

Tando Allahyar

Jamshoro

Matiari

HyderabadThatta

Sanghar

68°30'0"E

68°30'0"E

68°20'0"E

68°20'0"E

68°10'0"E

68°10'0"E26

°0'0

"N

26°0

'0"N

25°5

0'0

"N

25°5

0'0

"N

25°4

0'0

"N

25°4

0'0

"N

25°3

0'0

"N

25°3

0'0

"N

25°2

0'0

"N

25°2

0'0

"N

·0 2.5 5 7.5 10 12.5 15 17.5 Km

Halcrow Pakistan (Pvt) Limited

Fig ES-2: Project Area MapProject:EIA for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21)

LegendBlockBoundary/ProjectArea

!C Existing Well Site

×[

Gas CompressionFacility

"" Community

×k Graveyard

!a Power Plant

Shrine

¥B¢ University

hWater SamplingLocation

Nationla HighwayReserve Forest(SOP)

Tehsil BoundariesDistrictBoundaries United Energy

Pakistan

Page 18: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 i HPK

Contents

Executive Summary .......................................................................................................... ES-1

1 Introduction ................................................................................................................1

Environmental Impact Assessment ................................................................................... 1

The Project Proponent ........................................................................................................ 2

Kotri North Block (E.L. 2568-21) & Project Area ............................................................... 2

The Proposed Project .......................................................................................................... 3

Proposed Environmental Approval and Management System ....................................... 5

EIA Consultants ................................................................................................................... 6

Reporting .............................................................................................................................. 6

Contact Details ..................................................................................................................... 7

2 EIA Scope and Methodology ................................................................................. 10

2.1.1 Scope of the EIA .................................................................................................................. 10

The EIA Team ..................................................................................................................... 10

The EIA Methodology ........................................................................................................ 10

2.3.1 Understanding of the Proposed Project and Review of Alternatives ................................... 10

2.3.2 Review of Policies, Legislation and Guidelines ................................................................... 10

2.3.3 Secondary Data Collection .................................................................................................. 10

2.3.4 Field Data Collection ............................................................................................................ 11

2.3.5 Community/Public Consultation ........................................................................................... 11

2.3.6 Impact Identification and Assessment ................................................................................. 11

2.3.7 Recommendations for Mitigation & Monitoring Measures ................................................... 12

2.3.8 Development of Environmental Management Plan (EMP) .................................................. 12

3 Legal Framework .................................................................................................... 15

Introduction ........................................................................................................................ 15

United Energy Pakistan Limited’s Corporate HSE Policy .............................................. 15

National Environmental Policy, Legislation and Guidelines ......................................... 15

3.3.1 National Environmental Policy, 2005 ................................................................................... 15

3.3.2 National Conservation Strategy, 1992 ................................................................................. 16

3.3.3 The Biodiversity Action Plan, 2000 ...................................................................................... 17

3.3.4 Provincial & National Environmental Legislations ................................................................ 17

3.3.5 National Environmental Guidelines ...................................................................................... 23

International Treaties and Guidelines .............................................................................. 24

3.4.1 International Treaties ........................................................................................................... 24

3.4.2 Relevant International Guidelines ........................................................................................ 27

International and National Environment & Conservation Organizations ..................... 29

3.5.1 International and National NGOs ......................................................................................... 29

3.5.2 Pakistan Petroleum Exploration and Production Companies Association (PPEPCA) ......... 30

4 Project Description ................................................................................................. 42

The Proposed Project ........................................................................................................ 42

Seismic Operation ............................................................................................................. 43

4.2.1 Line Permitting ..................................................................................................................... 43

Page 19: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ii HPK

4.2.2 Line Survey and Preparation ............................................................................................... 44

4.2.3 Data Acquisition ................................................................................................................... 44

4.2.4 Camps, Staffing and Supplies ............................................................................................. 46

4.2.5 Access and Transport .......................................................................................................... 46

4.2.6 Restoration and Waste Management .................................................................................. 47

Drilling Operation .............................................................................................................. 47

4.3.1 Proposed Project Activities .................................................................................................. 47

4.3.2 Project Schedule .................................................................................................................. 48

4.3.3 Construction ......................................................................................................................... 48

4.3.4 Rig Mobilization ................................................................................................................... 49

4.3.5 Drilling .................................................................................................................................. 50

4.3.6 Demobilization & Site Restoration ....................................................................................... 53

4.3.7 Produced Water Injection Well ............................................................................................ 53

Flow Line Laying & Tie-in/Wellhead Works ..................................................................... 53

4.4.1 Flow Line Laying Activities ................................................................................................... 53

4.4.2 Development of Surface Facilities ....................................................................................... 59

Hydrocarbon Processing Facility (GPF/CPP) ................................................................. 59

4.5.1 Construction/Establishment of Gas Processing Facility ...................................................... 60

Associated Development Activities ................................................................................. 64

Noise, Wastes and Emissions .......................................................................................... 65

4.7.1 Noise .................................................................................................................................... 65

4.7.2 Wastes and Effluents ........................................................................................................... 65

4.7.3 Emissions ............................................................................................................................ 66

5 Analysis of Alternatives ......................................................................................... 77

Introduction ........................................................................................................................ 77

Management Alternatives ................................................................................................. 77

5.2.1 No Project Option ................................................................................................................ 77

5.2.2 Alternative Site Option ......................................................................................................... 79

5.2.3 Timing of the Operation ....................................................................................................... 79

Technological Alternatives ............................................................................................... 79

5.3.1 Seismic Data Acquisition Technologies ............................................................................... 79

5.3.2 Drilling Technique ................................................................................................................ 80

5.3.3 Drilling Mud .......................................................................................................................... 81

5.3.4 Disposal of Drilling Wastes .................................................................................................. 81

5.3.5 Alternative to Flow Lines ...................................................................................................... 82

5.3.6 Gas Processing Facility ....................................................................................................... 82

5.3.7 Water Abstraction ................................................................................................................ 83

6 Background Environment ...................................................................................... 88

Physical Environment ....................................................................................................... 88

6.1.1 Physiography ....................................................................................................................... 88

6.1.2 Geology & Geomorphology ................................................................................................. 89

6.1.3 Stratigraphy ......................................................................................................................... 89

6.1.4 Soils ..................................................................................................................................... 90

6.1.5 Land Capability .................................................................................................................... 90

Page 20: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 iii HPK

6.1.6 Petroleum Play .................................................................................................................... 91

6.1.7 Seismicity ............................................................................................................................. 91

6.1.8 Climate and Meteorology ..................................................................................................... 91

6.1.9 Ambient Noise & Air Quality ................................................................................................ 93

6.1.10 Water Resources ................................................................................................................. 94

Biological Environment ................................................................................................... 114

6.2.1 Data Sources ..................................................................................................................... 114

6.2.2 Protected/Sensitive Areas ................................................................................................. 114

6.2.3 Biological Habitats ............................................................................................................. 115

6.2.4 Baseline Conditions ........................................................................................................... 117

Socioeconomic Environment ......................................................................................... 147

6.3.1 Study Objectives ................................................................................................................ 147

6.3.2 Study Methodology ............................................................................................................ 147

6.3.3 Administrative Boundaries ................................................................................................. 148

6.3.4 Demographic Profile .......................................................................................................... 148

6.3.5 Economy of the Project Area ............................................................................................. 150

6.3.6 Gender Profile .................................................................................................................... 152

6.3.7 Development Needs .......................................................................................................... 153

6.3.8 Archaeological and Religious Sites ................................................................................... 153

7 Potential Environmental Impacts and Mitigations ............................................ 163

Physical Environment ..................................................................................................... 163

7.1.1 Changes in Landscape & Soil Erosion .............................................................................. 163

7.1.2 Soil and Water Contamination ........................................................................................... 167

7.1.3 Climate and Ambient Air Quality ........................................................................................ 174

7.1.4 Noise Pollution ................................................................................................................... 177

7.1.5 Use of Water ...................................................................................................................... 178

7.1.6 Blockage of Natural Drainage ............................................................................................ 181

7.1.7 Site Restoration ................................................................................................................. 181

Biological Environment ................................................................................................... 183

7.2.1 Clearing of Vegetation & Loss of Habitat ........................................................................... 183

7.2.2 Disturbance to Wildlife ....................................................................................................... 185

Socioeconomic, Cultural and Archaeological Environment ....................................... 189

8 Stakeholders Consultation .................................................................................. 194

Objectives of Stakeholders Consultation ...................................................................... 194

Community Consultations .............................................................................................. 195

Community’s Concerns & Reservations ....................................................................... 195

Other Stakeholders .......................................................................................................... 196

8.4.1 Deputy Director, Sindh Environmental Protection Agency, Karachi .................................. 196

8.4.2 Range Forest Officer, Sindh Forest Department, Hyderabad ............................................ 197

8.4.3 Deputy Director, Sindh Environmental Protection Agency, Hyderabad ............................. 198

8.4.4 Technical Officer, Directorate of Animal Husbandry, Hyderabad ...................................... 198

8.4.5 Chief Engineer, Irrigation Department, Hyderabad ............................................................ 199

8.4.6 Institute of Environmental Studies, Karachi University ...................................................... 200

8.4.7 Regional Chair, Commission on Ecosystem Management, IUCN ..................................... 201

Page 21: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 iv HPK

8.4.8 Coordinator Marine Program, Worldwide Fund for Nature, Karachi .................................. 201

8.4.9 Other meetings .................................................................................................................. 202

Key Findings and Issues ................................................................................................. 202

9 Conclusion ............................................................................................................ 207

Appendices

Appendix A Environmental Management Plan A-1 Appendix B Environmental Monitoring Checklists B-1 Appendix C Environmental Aspects Register C-1      

Page 22: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 v HPK

List of Tables

Table 2-1: Impact Characteristics Criteria ................................................................................... 13

Table 3-1: SEQS for Municipal and Industrial Effluentsa ............................................................ 31

Table 3-2: SEQS for Industrial Gaseous Emissiona ................................................................... 33

Table 3-3: SEQS for Motor Vehicle Exhaust and Noisea............................................................ 35

Table 3-4: Sindh Environmental Quality Standards for Noise ..................................................... 35

Table 3-5: Sindh Standards for Drinking Water Quality .............................................................. 36

Table 3-6: SEQS for Ambient Air ................................................................................................ 38

Table 3-7: API Standard for On-site Burial of E&P Wastes in Unlined Pitsa, b, c ....................... 39

Table 3-8: LSO 29B Criteria for On-site Burial in Unlined Pits .................................................... 40

Table 4-1: Summary of Water Usage during Various O&G Project Activities ............................. 68

Table 4-2: Summary of Approximate Domestic Wastewater and Solid Waste ........................... 69

Table 6-1: Meteorological Data of Hyderabad District, 2009 – 2018 .......................................... 96

Table 6-2: Water Quality within Project Area ............................................................................ 102

Table 6-3: Ambient Noise Levels Monitoring ............................................................................ 103

Table 6-4: List of Vegetation Species found in the Project Area ............................................... 124

Table 6-5: List of Vegetation Species of Riparian Habitat (20 x 20m Quadrate) ...................... 131

Table 6-6: List of Vegetation Species of Riparian Habitat (2 x 2m Quadrate) .......................... 131

Table 6-7: List of Vegetation Species of Marshy/Wetland Habitat (20 x 20m Quadrate) .......... 132

Table 6-8: List of Vegetation Species of Marshy/Wetland Habitat (2 x 2m Quadrate) .............. 132

Table 6-9: List of Vegetation Species of Rocky Calcareous Plain Habitat (20 x 20m Quadrate)133

Table 6-10: List of Vegetation Species of Calcareous Plain Habitat (2 x 2m Quadrate) ........... 134

Table 6-11: Vegetation Species with Medicinal and Economical Use found in the Project Area135

Table 6-12: List of Birds Observed/Reported in the Project Area ............................................. 136

Table 6-13: List of Mammals Observed/Reported in the Project Area ...................................... 141

Table 6-14: List of Reptiles Observed/Reported in the Project Area ........................................ 142

Table 6-15: Households and Population Data of Goths/Villages/Towns ................................... 155

Table 6-16: Tribal Distribution ................................................................................................... 156

Table 6-17: Development Priorities of the Communities of Suveyed Villagees ........................ 157

Table 8-1: List of Stakeholders Consulted during EIA .............................................................. 203

Page 23: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 vi HPK

List of Figures

Figure 1-1: Key Map of Kotri North Block ...................................................................................... 8

Figure 1-2: Project Area Map ........................................................................................................ 9

Figure 3-1: United Energy Pakistan Limited’s HSE Policy .......................................................... 41

Figure 4-1: Anatomy of a Rotary Land Drilling Rig ...................................................................... 70

Figure 5-1: Primary Energy Supplies by Source with ACGR ...................................................... 84

Figure 5-2: Primary Energy Supplies by Source ......................................................................... 84

Figure 5-3: Final Energy Consumption by Source ...................................................................... 85

Figure 5-4: Final Energy Consumption by Sector ....................................................................... 85

Figure 5-5: Natural Gas Production by Type/Province ................................................................ 86

Figure 5-6: Natural Gas Consumption by Sector ........................................................................ 87

Figure 6-1: Graphical Representation of Average Temperatures in Hyderabad, 2009 – 2018 . 106

Figure 6-2: Graphical Representation of Hyderabad Climatic Data, 2009 – 2018 .................... 107

Figure 6-3: Seismic Zoning Map of Pakistan ............................................................................ 108

Figure 6-4: Water Resources Map of the Project Area ............................................................. 109

Figure 6-5: Ambient Noise Sampling Locations Map of the Project Area ................................. 110

Figure 6-6: Communities, Infrastructure and Archaeological Resources Map .......................... 158

Page 24: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 vii HPK

List of Photographs

Photograph 4-1: A view of typical seismic base camp ................................................................ 71

Photograph 4-2: A veiw of seismic support camp ....................................................................... 71

Photograph 4-3: Uphole drilling by vehicle mounted rig.............................................................. 71

Photograph 4-4: Vibroseis moving on a seismic line .................................................................. 71

Photograph 4-5: Drilling of deep hole through buggy in progress ............................................... 71

Photograph 4-6: Jackrob drilling ................................................................................................. 71

Photograph 4-7: Loading of explosives in a shot hole ................................................................ 72

Photograph 4-8: A loaded shot hole ........................................................................................... 72

Photograph 4-9: Seismic base camp parking area ..................................................................... 72

Photograph 4-10: A veiw of explosive magazine ........................................................................ 72

Photograph 4-11: Seismic cable crossing on a road................................................................... 72

Photograph 4-12: Recording truck .............................................................................................. 72

Photograph 4-13: A view of land drilling rig in operation ............................................................. 73

Photograph 4-14: A view of typical drilling rig camp ................................................................... 73

Photograph 4-15: Dozer at work on access track ....................................................................... 73

Photograph 4-16: Gravel leveling with grader on well site .......................................................... 73

Photograph 4-17: Generators at well site.................................................................................... 73

Photograph 4-18: Water storage pit on well site ......................................................................... 73

Photograph 4-19: A view of lined drill cutting pit at well site ....................................................... 74

Photograph 4-20: Properly bunded diesel storage area with loading and unloading pad ........... 74

Photograph 4-21: Properly barricaded food burial pit ................................................................. 74

Photograph 4-22: Construction of septic tank at well site ........................................................... 74

Photograph 4-23: Installation of conductor pipe at well site ........................................................ 74

Photograph 4-24: Installation of BOP in progress ....................................................................... 74

Photograph 4-25: Dozer working on RoW .................................................................................. 75

Photograph 4-26: Offloading of pipes on RoW ........................................................................... 75

Photograph 4-27: Flow line placed along RoW ........................................................................... 75

Photograph 4-28: Clamping of flow line before welding .............................................................. 75

Photograph 4-29: Burial of flow line in trench ............................................................................. 75

Photograph 4-30: Working on flow line at wellhead .................................................................... 75

Photograph 4-31: Typical view of CPP ....................................................................................... 76

Photograph 4-32: Typical styled condensate storage at GPF..................................................... 76

Photograph 4-33: Typical lined evaporation pond....................................................................... 76

Photograph 4-34: Typical pipe yard at GPF ................................................................................ 76

Photograph 6-1: A view of Indus River ..................................................................................... 111

Photograph 6-2: A view of Kotri Barrage .................................................................................. 111

Photograph 6-3: Agriculture field – dominant habitat of the project area .................................. 111

Photograph 6-4: Barani agriculture field ................................................................................... 111

Photograph 6-5: A patch of waste land & fallow land................................................................ 111

Photograph 6-6: Stony plain of the project area ....................................................................... 111

Photograph 6-7: A view Matiari RF ........................................................................................... 112

Photograph 6-8: A view of Salaro Ghotana RF ......................................................................... 112

Page 25: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 viii HPK

Photograph 6-9: Marshy wetland near Goth Suleman Barejo ................................................... 112

Photograph 6-10: A view of Khasino Canal (wah) .................................................................... 112

Photograph 6-11: A view of Pannu wah .................................................................................... 112

Photograph 6-12: Cemented watercourse – Tadri Mori ............................................................ 112

Photograph 6-13: Tube well found in the project area .............................................................. 113

Photograph 6-14: A view of Rajani-7 well site........................................................................... 113

Photograph 6-15: Gas Compression Facility near Rajani-12 well site ...................................... 113

Photograph 6-16: A view of M9 motorway entering into project area ....................................... 113

Photograph 6-17: Salvadora persecia ...................................................................................... 143

Photograph 6-18: Ficus religiosa .............................................................................................. 143

Photograph 6-19: Acacia nilotica .............................................................................................. 143

Photograph 6-20: Bombax ceiba .............................................................................................. 143

Photograph 6-21: Capparis Spinosa ......................................................................................... 143

Photograph 6-22: Cordia myxa ................................................................................................. 143

Photograph 6-23: Cassia holosericeai ...................................................................................... 144

Photograph 6-24: Dalbergia sissoo ........................................................................................... 144

Photograph 6-25: Crested lark .................................................................................................. 144

Photograph 6-26: Egyptian vulture ........................................................................................... 144

Photograph 6-27: Glossy ibis .................................................................................................... 144

Photograph 6-28: Indian robin .................................................................................................. 144

Photograph 6-29: Large cormorant ........................................................................................... 145

Photograph 6-30: Pied bushchat .............................................................................................. 145

Photograph 6-31: Redshank ..................................................................................................... 145

Photograph 6-32: Sindh pied woodpecker ................................................................................ 145

Photograph 6-33: White browed fantail ..................................................................................... 145

Photograph 6-34: Indian desert monitor lizard .......................................................................... 145

Photograph 6-35: Indian garden lizard ...................................................................................... 146

Photograph 6-36: Asiatic jackal ................................................................................................ 146

Photograph 6-37: Botanist during the EIA field survey ............................................................. 146

Photograph 6-38: Wildlife specialist during the EIA field survey ............................................... 146

Photograph 6-39: A view of Goth Sufan Bacho ........................................................................ 159

Photograph 6-40: Primary school of Goth Salaro ..................................................................... 159

Photograph 6-41: Graveyard of Goth Salaro ............................................................................ 159

Photograph 6-42: Graveyard of Goth Sufan Bacho .................................................................. 159

Photograph 6-43: Primary school in Goth Bachal Dehta .......................................................... 159

Photograph 6-44: A view of Shahpur ........................................................................................ 159

Photograph 6-45: Boys’ primary school in Goth Tajpur ............................................................ 160

Photograph 6-46: Girls’ primary school in Goth Tajpur ............................................................. 160

Photograph 6-47: Dargah Wali Muhammad in Goth Tajpur ...................................................... 160

Photograph 6-48: Sindh Agriculture University ......................................................................... 160

Photograph 6-49: Primary school in Goth Tando Syed Khan Mitho ......................................... 160

Photograph 6-50: DHQ Matiari ................................................................................................. 160

Photograph 6-51: Dargah Syed Muhammad Shah Bukhari ...................................................... 161

Photograph 6-52: A view of Goth Bakhshia Mari ...................................................................... 161

Page 26: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 ix HPK

Photograph 6-53: A view of Goth Karim Deno .......................................................................... 161

Photograph 6-54: A view of Goth Jaitharo ................................................................................ 161

Photograph 6-55: Dargah Baba Allah Baksh Jilani ................................................................... 161

Photograph 6-56: A view of Goth Haji Ishaq ............................................................................. 161

Photograph 6-57: A view of Goth Gulshan-e-Shahbaz ............................................................. 162

Photograph 6-58: A view of Goth Wadero Misri ........................................................................ 162

Photograph 6-59: BHU Hyderabad ........................................................................................... 162

Photograph 6-60: High tension electric poles crossing through the project area ...................... 162

Photograph 8-1: Consultation at Goth Sufan Bacho ................................................................. 204

Photograph 8-2: Consultation with Mr. Imran Sabir, Sindh EPA ............................................... 204

Photograph 8-3: Consultation with Representatives of Sindh EPA, Hyderabad ....................... 204

Photograph 8-4: Community consultation at Goth Haji Shabu.................................................. 204

Photograph 8-5: Consultation with locals at Goth Khuda Baksh ............................................... 204

Photograph 8-6: Consultation session with RFO, Hyderabad ................................................... 204

Photograph 8-7: Consultation with Chief Engineer, Irrigation Department, Hyderabad ............ 205

Photograph 8-8: Community consultation at Goth Bachal Dehta.............................................. 205

Photograph 8-9: Consultation at Goth Bakhshia Mari ............................................................... 205

Photograph 8-10: Consultation with Dr. Abdul Manan .............................................................. 205

Photograph 8-11: Consultation session with Prof. Dr. Moazzam Ali Khan ............................... 205

Photograph 8-12: Community consultation at Goth Aliabad ..................................................... 205

Photograph 8-13: Locals are being consulted at Goth Karim Deno .......................................... 206

Photograph 8-14: Consultation session with Prof. Dr. Muhammad Zaheer Khan ..................... 206

Photograph 8-15: Consultation session Mr. Jawad Umer Khan (WWF Pakistan) .................... 206

Photograph 8-16: Community consultation at Goth Jaitharo .................................................... 206

Photograph 8-17: Community consultation at Goth Haji Ishaq ................................................. 206

Photograph 8-18: Consultation with locals at Goth Gulshan-e-Shahbaz .................................. 206

Page 27: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 x HPK

List of Acronyms

2D Two Dimensional

3D Three Dimensional

ACGR Annual Compound Growth Rate

BAP Biodiversity Action Plan

BAT Best Available Technology

BATNEEC Best Available Technology Not Entailing Excessive Cost

BOD Biological Oxygen Demand

CC Civil Contractor

CFC Chlorofluorocarbon

CITES Convention on International Trade in Endangered Species of Wild Fauna and Flora

CMS Convention on the Conservation of Migratory Species of Wild Animals

COD Chemical Oxygen Demand

CPP Central Processing Plant

DCR District Census Report

DGPC Director General Petroleum Concessions

E.L. Exploration Lease

E&P Exploration and Production

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EPA Environmental Protection Agency

EWT Extending Well Testing

GCA Gross Command Area

GoP Government of Pakistan

GoS Government of Sindh

GPF Gas Processing Facility

H2S Hydrogen Sulfide

HDPE High Density Polyethylene

HPK Halcrow Pakistan (Pvt) Ltd

HSE Health, Safety and Environment

HSEO Health, Safety and Environment Officer

IAGC International Association of Geophysical Contractors

IEE Initial Environmental Examination

IMC Independent Monitoring Consultant

IUCN International Union for Conservation of Nature and Natural Resources

LNG Liquefied Natural Gas

LPG Liquefied Petroleum Gas

LSO Louisiana State Order

MMCFD Million Cubic Feet per Day

MTOE Million Tonnes of Oil Equivalent

NCS National Conservation Strategy

NEQS National Environment Quality Standards

Page 28: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 xi HPK

NGO Non-Government Organization

NOC No Objection Certificate

O&G Oil and Gas

PEPA 97 Pakistan Environmental Protection Act, 1997

PIR Project Initiation Report

PVC Poly Vinyl Chloride

RoW Right of Way

SEQS Sindh Environmental Quality Standards

SFD Sindh Forest Department

STP Sewage Treatment Plant

SWD Sindh Wildlife Department

SWPO Sindh Wildlife Protection Ordinance

TSS Total Suspended Solids

TDS Total Dissolved Solids

UEPL United Energy Pakistan Limited

UTC Universal Time Coordinated

WBM Water Based Mud

WWF Worldwide Fund for Nature

Page 29: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 xii HPK

List of Units

cusecs cubic feet per second

dB decibels

gph gallons per hour

ha hectares

hr hour

km kilometres

m meter

mg/l milligram per litre

mg/Nm3 milligram per Normal Cubic meter

m3 cubic meter

m2 square meter

mm millimetre

m/s meter/second

°C Degree Celsius

% Percent

ppb parts per billion

ppm parts per million

sq. square

tcf Trillion cubic feet

Page 30: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 1 HPK

1 Introduction

Environmental Impact Assessment

This report presents the findings of an Environmental Impact Assessment (EIA) 

carried out by Halcrow Pakistan (Pvt) Limited for the proposed exploration and 

associated development activities in Kotri North Block (E.L. 2568‐21) by United 

Energy Pakistan Limited (UEPL) which lies within geographical jurisdiction of Sindh 

province. A key map showing the location of Kotri North Block is presented as Figure 

1‐1. This EIA has been prepared in conformance to the requirements of the Sindh 

Environmental Protection Act 2014, the Sindh Initial Environmental Examination and 

Environmental Impact Assessment Review Regulations, 2014 and the Pakistan 

Environmental Assessment Procedures, 1997. 

The EIA report explicitly covers exploration and associated development activities in 

the entire spread of Kotri North Block. These activities range from 2D/3D seismic 

surveys, drilling of exploration/development wells, laying of flow line/s from 

producing wells to the hydrocarbons gathering system/processing facility, 

establishment of processing facilities e.g. EWT or CPP, up‐gradation/modification of 

existing facilities with associated civil and engineering works e.g. construction of 

access track/s, residential camp/s, construction of well site/s etc. and finally 

decommissioning and site restorations. Proposed project activities will be commenced 

with 2D/3D seismic survey and based upon the aforementioned seismic data 

acquisition and its interpretations, UEPL will plan to drill wells at the most certain 

perspective locations as part of exploration/development plan. After the successfully 

drilling at any proposed well location and in case of discovery, flow line/pipeline will 

be laid from each well to the new/existing hydrocarbons gathering and production 

system.  

The proposed 2D/3D seismic surveys will be carried out in the entire spread of Kotri 

North Block (hereafter also referred as the ‘project area’ in the later sections of the 

report) however, location of the seismic survey/s is not finalized yet. Similarly, the 

exact location of exploratory/development wells and alignment of flow line/s is not 

available at this stage either. The exact location of wells will only be made available 

after proposed seismic data acquisition and its interpretations by United Energy 

Pakistan Limited. Furthermore, depending on the drilling results, alignment of flow 

line/s will be finalized. Likewise depending on the need basis, location of 

hydrocarbons processing facility will be finalized and executed accordingly. Therefore, 

this EIA report is based on the fact that United Energy Pakistan Limited will submit 

the Project Initiation Report (PIR) or Activity Initiation Report (AIR) for each planned 

activity to Sindh Environmental Protection Agency (for information) prior to the start 

of each aforementioned activity in the project area.  

Page 31: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 2 HPK

The objective of exploration and associated development activities is to explore for 

potential hydrocarbons reserves in the prospective formations identified during 

previous Oil & Gas exploration activities in the region particularly in the leased area. 

The Project Proponent

United Energy Pakistan Limited, UEP Alpha Limited and UEP Beta GmbH collectively 

known as UEP (UEP Alpha and UEP Beta were previously known as OMV Maurice 

Energy Limited and OMV (Pakistan) Exploration GmbH) are subsidiaries of United 

Energy Group (UEG), an energy company listed on the Hong Kong Stock Exchange. 

UEP is the largest foreign oil & gas exploration and production (E&P) company in 

Pakistan, and have been contributing significantly in reducing Pakistan’s dependency 

on oil & gas imports through indigenous hydrocarbon production. 

UEG’s asset has a rich heritage, starting nearly four decades ago when an American 

E&P company, Union Texas Pakistan, initiated operations in Khaskeli, Badin. Since 

then, this asset has undergone several changes and a shift in ownership a number of 

times. Acquisition of British Petroleum’s assets by UEG was the first venture in 

Pakistan and since then UEG has made significant investments in the business, 

resulting in rapid growth. UEG’s onshore concessions span across 20,000 square 

kilometers and are spread across Sindh and Balochistan provinces. 

UEP is conscious of environmental footprint and work diligently to ensure that no 

harm is caused to anyone involved in or impacted by their activities. UEP not only 

comply with all applicable laws related to Health, Safety and the Environment (HSE) 

but also have a set of internal policies in place to minimize the environmental impact 

of their operations. 

In coordination with the government, communities and non‐governmental 

organizations, UEP has invested in sustainable social investment projects in the areas 

where operating. CSR interventions have brought a positive impact in the lives of local 

communities by enhancing access to technical training, creating opportunities for 

sustainable income generation and providing quality education and healthcare 

services. UEP has invested in the alternative energy sector. UEG (parent company) has 

also invested in a wind energy project located in the Jhimpir wind corridor in the 

Sindh province. This project was one of the 14 top priority projects of the China 

Pakistan Economic Corridor (CPEC). 

Kotri North Block (E.L. 2568-21) & Project Area

Kotri North Block (E.L. 2568‐21) is located in geographical jurisdiction of Jamshoro, 

Matiari and Hyderabad districts of Sindh province with a total area coverage of 

approximately 1,397 square kilometers (km2). Out of total covered area of the block 

district Jamshoro contributes the major part i.e. 1,133.5 km2 whereas, district Matiari 

shares approx. 257 km2 and district Hyderabad contributes about 6.6 km2. Taluka wise 

distribution of abovementioned districts is provided in table below: 

 

Page 32: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 3 HPK

No.  District   Taluka  Area Coverage (km2) 

4.   Jamshoro Kotri  442 

Manjhand  691.5 

5.   Hyderabad  Hyderabad  6.5 

6.   Matiari 

Hala  210 

Matiari  4 

Saeedabad  43 

United Energy Pakistan is operator of the block and holds 50% working interest. Other 

joint venture (JV) partners include Pakistan Petroleum Limited (PPL) and Asia 

Resources Oil Limited (AROL). PPL and AROL holds 40% and 10% working interest 

in the block respectively.  

Kotri North Block (E.L. 2568‐21) encompass several forest protected areas. There are 

about 28 reserve forests (all of them are small sized) are falling in the geographical 

jurisdiction of the Block (E.L. 2568‐21). These reserve forests includes; Kunar Rishal, 

Keti Dallu, Nur Keti, Drabo, Manjhand, Keti Khasai, Unarpur, Rudhapur, Rishal, 

Nural Abad, Racho Khanot, Pako Bhanot, Butho, Ranno, Rajri, Salaro Ghotana, Lakha, 

Khasai, Ghotana, Murid Rais, Sekhat, Matiari, Miana, Hatri, Muhammad Khan, Bada, 

Shah Bukhari and Railo Bada. These reserve forests which were once pristine riverine 

forests, now mostly are under cultivation. Location of forest protected areas is also 

shown in Figure 1‐2. 

The Proposed Project

The entire leased area spreads over approximately 1,397 km2 and lies in Jamshoro, 

Matiari and Hyderabad districts of Sindh province. The EIA report explicitly covers 

exploration and associated development activities in the entire spread of Kotri North 

Block. These activities range from 2D/3D seismic surveys, drilling of exploration/ 

development wells, laying of flow line/s from producing wells to the existing 

hydrocarbons gathering system/processing facility, establishment of processing 

facilities e.g. EWT or CPP, up‐gradation/modification of existing facilities with 

associated civil and engineering works e.g. construction of access track/s, residential 

camp/s, construction of well site/s etc. and finally decommissioning and site 

restorations.  

Proposed project activities will be commenced with 2D/3D seismic survey and based 

upon the aforementioned seismic data acquisition and its interpretations, UEPL will 

plan to drill wells as part of exploration/development plan. After the successfully 

drilling at proposed well location and in case of discovery, flow line/pipeline will be 

laid from each well to the new/existing hydrocarbons gathering and production 

system over the period of three years. Detailed proposed project activities will include 

but not limited to be are listed below: 

Seismic activities (2D and 3D); 

Well sites preparation & construction activities; 

Page 33: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 4 HPK

Drilling of exploration, development and water injection wells (no new water 

injection well will be drilled only plugged & abandoned (P&A) well will be used 

for the purpose); 

Surface facilities development at drilled well sites including EWT; 

Laying of flow lines from producing wells to CPP/Gathering hub; 

Laying of flow lines from CPP/Gathering hub to Point of Delivery (POD); 

 Development of early production, production and testing facilities which will 

include plant construction and operations; 

Development of remote facilities; 

Up‐gradation/Modification of existing facilities; 

Relocation of existing facilities e.g. decommissioning of plant equipment and 

relocation to other location within project area; 

Construction of access roads & residential camps; 

Decommissioning of surface facilities (well sites/plant sites); and  

Sites restoration. 

The proposed 2D & 3D seismic data acquisition will be carried out using a 

combination of vibroseis and dynamite technologies. The objective of the seismic 

survey is to explore the subsurface in the area to identify hydrocarbon laden 

formations. For seismic survey a base camp with fly camp (if required) will be 

established to house the seismic crew followed by seismic activity and finally 

restoration of seismic lines and base camp/fly camp upon completion of survey area to 

original conditions. 

Drilling of each well will start with the construction of the access road, rig camp and 

well site for each proposed location. This will be followed by drilling of exploratory or 

development well. Each proposed well will be drilled using a conventional land 

drilling rig. A specialized waste management system using Hi‐G dryers and 

centrifuges will be installed on the land drilling rig for better management and 

disposal of drilling wastes. This will also help in reducing the water requirements 

during drilling and managing the size of wastes pits at each proposed well location. 

Depending on the drilling results (success or failure), abandonment, completion or 

suspension of the well and site restoration. Furthermore, in case of discovery of 

hydrocarbons at any of the proposed well locations, laying of flow line/pipeline from 

wells to the hydrocarbons gathering/processing facilities and tie‐in/wellhead works 

will be carried out. 

The proposed 2D/3D seismic surveys will be carried out in the entire spread of Kotri 

North Block however, location of the seismic survey/s is not finalized yet. Similarly, 

the exact location of exploratory/development wells and alignment of flow line/s is not 

available at this stage either. The exact location of wells will only be made available 

Page 34: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 5 HPK

after proposed seismic data acquisition and its interpretations by United Energy 

Pakistan Limited. Furthermore, depending on the drilling results, alignment of flow 

line/s will be finalized. Likewise depending on the need basis, location of 

hydrocarbons processing facility will be finalized and executed accordingly. Therefore, 

this EIA report is based on the fact that United Energy Pakistan Limited will submit 

the Project Initiation Report (PIR) or Activity Initiation Report (AIR) for each planned 

activity to Sindh Environmental Protection Agency (for information) prior to the start 

of each aforementioned activity in the leased area of Kotri North Block. 

Proposed Environmental Approval and Management System

Preparation and approval of environmental assessments that covers more than one 

exploration or production activity is not a new precedence, however, the following 

needs to be ensured in such assessments:  

Sufficient data collection and assessment of impacts to cover all environmental 

sensitivities; 

A mechanism that would require a site specific short study prior to start of each 

activity to incorporate any additional impacts and mitigation measures that were 

not addressed in the EIA; and 

A mechanism by which Sindh Environmental Protection Agency (Sindh EPA) can 

continue to exercise its control over the proponent’s activities and follow up on the 

environmental performance of the operations. 

United Energy Pakistan Limited and Halcrow Pakistan have been fully cognizant of 

the above listed issues and have addressed them in the EIA by undertaking or 

proposing the following: 

The EIA is based on primary as well as secondary data. Primary data is collected 

on all physical, biological and socioeconomic aspects; 

Assessment of all generic potentially significant impacts on the physical, biological 

and socioeconomic receptors due to proposed project activities has been addressed 

in the EIA. Relevant mitigation measures have also been discussed in detail. 

However, following methodology shall be adopted to consider the project specific 

impacts, since at this conceptual design stage exact locations for project facilities 

are not available; and 

In order to ensure that Sindh EPA continues to regulate and oversee the 

environmental performance of activities within the leased areas, the EIA has 

recommended the following environmental approval, monitoring and 

management protocol: 

o Prior to commence of any proposed project activity as defined in Section 1.4, 

United Energy Pakistan Limited will prepare and submit a Project Initiation 

Report (PIR) or Activity Initiation Report to the Sindh EPA. The report will be 

submitted at least fifteen days prior to initiation of any physical work related to 

Page 35: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 6 HPK

that particular activity. The PIR or AIR will provide details on the proposed 

activity, site specific information on the physical, biological and socioeconomic 

environment, waste management procedures and any environmental issues 

and mitigation measures additional to the EIA; 

o If required, Sindh EPA can forward any comments that it might have on the 

PIR/AIR within fifteen days of the submissions of the PIR/AIR after which the 

activity will automatically stand as approved; 

o Once any activity is initiated, United Energy Pakistan Limited will undertake 

environmental monitoring according to the requirements of the project specific 

EMP and any additional requirements specified by the Sindh EPA; and  

o United Energy Pakistan Limited will accommodate any visits by Sindh EPA, 

Sindh Wildlife Department and Forest Department officials for the purpose of 

external audits or on‐site inspections. 

EIA Consultants

This EIA study was carried out by Halcrow Pakistan (HPK) comprising of 

Environmental Specialists, Social Experts, Wildlife Specialists, Botanist and Water 

Resources Expert having sound technical expertise to perform assignments particular 

to the oil & gas sector. The details of the project team members appointed on this 

study are provided below: 

No.  Name  Expertise

1.   Abdul Qayyum Aslam  Team Lead – HSE 

2.   Arslan A. Asghar   Environmental Specialist  

3.   Abdur Razzaq Khan  Wildlife Expert 

4.   Ahmed Salman Qureshi  Environmentalist 

5.   Ghulam Sakina Memon  Social/Gender Expert 

6.   Shakeel Ahmed  Botanist 

7.   Syed Jawad  GIS Expert 

8.   Ahsan Ullah  CAD Operator 

Reporting

The EIA study has been compiled in a report form. The format of the EIA report 

conforms to the guidelines provided in the Pakistan Environmental Assessment 

Procedures, 1997.  

The EIA report is presented as one volume and describes the proposed project, 

environment of the project area, relevant legislations and guidelines, assessment of the 

project impacts, recommendations for mitigation measures and environmental 

management plan (Appendix A). The photographic records have been provided in the 

relevant sections of the EIA report.

Page 36: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 7 HPK

Contact Details

In case of further details or clarifications regarding this EIA please do not hesitate to 

contact the Proponent or the Consultant at the addresses provided below:

Proponent  Consultant

Amjad Shaikh 

Senior HSE Manager 

United Energy Pakistan Limited 

1st Floor, Bahria Complex‐1, 

24 M.T. Khan Road 

Karachi 

Pakistan 

Tel : +92 21 3561 1194 

Fax: +92 21 3561 0634 

Abdul Qayyum Aslam 

Team Lead – HSE 

Halcrow Pakistan (Pvt) Limited 

3rd Floor, Nawa‐e‐Waqt House,  

Mauve Area 

Sector G‐7/1 

Islamabad 

Tel: +92 51 220 3451‐55 

Fax: +92 51 220 3462 

Page 37: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

Lat :25° 27' 32.436" NLong:68° 36' 29.484" E

Lat :25° 41' 38.688" NLong:68° 33' 20.196" EKotri

Hala

Thatta

Matiari

Hyderabad

Latifabad

Qasimabad

Tando Adam

Jamshoro

Matiari

Thatta

Hyderabad

Sanghar

68°32'0"E

68°32'0"E

68°24'0"E

68°24'0"E

68°16'0"E

68°16'0"E

68°8'0"E

68°8'0"E

68°0'0"E

68°0'0"E26

°0'0

"N

26°0

'0"N

25°5

2'0

"N

25°5

2'0

"N

25°4

4'0

"N

25°4

4'0

"N

25°3

6'0

"N

25°3

6'0

"N

25°2

8'0

"N

25°2

8'0

"N

25°2

0'0

"N

25°2

0'0

"N

LegendBlock Boundary Reserve Forest (SOP) Tehsil Boundaries

District Boundaries

·0 2.5 5 7.5 10 12.5 15 17.5 Km

Halcrow Pakistan (Pvt) LimitedUnited Energy

Pakistan

Fig 1-1: Key Map of Kotri North Block

Project:EIA for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21)

Page 38: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

h

h

h

h

h

Goth Rais Ghulam Ali Mari

Goth Tando Syed Khan Mitho

Graveyard / Shrine

Sindh Agriculture University

Graveyard

Graveyard

Goth Akro

Graveyard

Graveyard

Graveyard

Goth Tajpur

Goth Salaro

Goth Jaitharo

Goth Aliabad

Goth Haji Ishaq

Goth Karim Deno

Goth Tadri Mori

Goth Haji Shabu

Goth Khuda baksh

Goth Sufan Bacho

Goth Hayat Bhatti

Goth Bachal Dehta

Goth Bakhshia Marri

Goth Suleman Barejo

Graveyard on Highway

Goth Bego Khan Mirjat

Goth Sayen Dino Malah

Goth Mehram Khazkheli

Goth Gulshan e Shahbaz

Goth Darya Baig Mughal

Dargah Dado Khamiso Fakir

Shrine Baba Allah Bakhsh Jilani

Dargah Syed Muhammad Shah Bukhari

Goth Wadero Misri

Kotri

Hala

Matiari

Hyderabad

Thatta Latifabad

Tando Adam

Qasimabad

Tando Allahyar

Jamshoro

Matiari

HyderabadThatta

Sanghar

68°30'0"E

68°30'0"E

68°20'0"E

68°20'0"E

68°10'0"E

68°10'0"E26

°0'0

"N

26°0

'0"N

25°5

0'0

"N

25°5

0'0

"N

25°4

0'0

"N

25°4

0'0

"N

25°3

0'0

"N

25°3

0'0

"N

25°2

0'0

"N

25°2

0'0

"N

·0 2.5 5 7.5 10 12.5 15 17.5 Km

Halcrow Pakistan (Pvt) Limited

Fig 1-2: Project Area MapProject:EIA for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21)

LegendBlockBoundary/ProjectArea

!C Existing Well Site

×[

Gas CompressionFacility

"" Community

×k Graveyard

!a Power Plant

Shrine

¥B¢ University

hWater SamplingLocation

Nationla HighwayReserve Forest(SOP)

Tehsil BoundariesDistrictBoundaries United Energy

Pakistan

Page 39: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 10 HPK

2 EIA Scope and Methodology

2.1.1 Scope of the EIA

This EIA investigates the impacts likely to arise from the proposed exploration and 

associated development activities by United Energy Pakistan Limited (UEPL) which 

predominantly covers 2D/3D seismic surveys, drilling of exploration/development 

wells, laying of flow line/s from producing wells to the existing hydrocarbons 

gathering system/processing facility, establishment of surface facilities e.g. EWT or 

CPP, up‐gradation/modification of existing facilities with associated civil and 

engineering works e.g. construction of access track/s, residential camp/s, construction 

of well site/s etc. and finally decommissioning and site restorations. 

These activities have been further discussed in detail in Chapter 4 of this report. Any 

exploration or production activity carried out by UEPL, other than those specified in 

this report will be the subject of a separate Environmental Assessment (EIA/IEE) study 

of the area. 

The EIA Team

The EIA has been prepared by a team of environmental specialists, wildlife specialists, 

botanist and sociologist/gender specialist. Relevant departments/stakeholders were 

also consulted during the EIA process. Project specific details and particulars were 

provided to HPK by United Energy Pakistan Limited. 

The EIA Methodology

The various steps undertaken in the EIA preparation are summarized below: 

2.3.1 Understanding of the Proposed Project and Review of Alternatives

Details of the proposed project activities were collected from United Energy Pakistan 

Limited and understood by the EIA Consultant. All alternatives to the proposed 

operations were reviewed including; no project option, alternative site selection, 

timing and alternative technologies to establish the context that proposed operations 

will not depreciate the environmental quality/soundness of the project area. Details of 

the proposed project and a review of alternatives have been provided in Chapter 4 

and Chapter 5 respectively of this EIA. 

2.3.2 Review of Policies, Legislation and Guidelines

National & provincial legislations, international agreements, environmental 

guidelines, best industry practices and UEPL’s environmental policy were reviewed to 

set environmental standards that UEPL would be required to adhere to during the 

project. A synopsis of these is provided in Chapter 3 of the EIA. 

2.3.3 Secondary Data Collection

Previous environmental assessments for exploration and development projects in the 

area and other published and un‐published information was collected in order to 

Page 40: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 11 HPK

gain a complete understanding of existing environmental conditions in the area 

including the following:  

Physical environment – topography, geology, geomorphology, soils, surface & 

groundwater resources and climate; 

Biological environment – habitat types, flora and fauna (particularly rare or 

endangered species), critical habitats and vegetation communities particularly 

within the forest protected areas; 

Socioeconomic environment – settlements, socioeconomic conditions, 

infrastructure and land use; and 

Heritage aspects – sites of cultural, archaeological or historical significance. 

2.3.4 Field Data Collection

The EIA field team including environmentalist, wildlife specialist, botanist and 

sociologist/gender expert visited the Block (E.L. 2568‐21) in August, 2019. During the 

site visit primary information on the physical, biological and socioeconomic 

environment of the project area was gathered. Discussions were also held with the 

members of community in the project area as well as in closer vicinities to collect 

primary information about the project area and their view and concerns regarding the 

proposed project activities. 

A description of baseline physical, biological and socioeconomic conditions of the 

project area, impacts due to proposed project activities and their mitigation 

measures are provided in Chapters 6 and Chapter 7 of the EIA report 

respectively.   

The project area for EIA contains four major habitats i.e. Agriculture Fields, Farmlands 

& Human Settlements; Indus River/Irrigation Network and Associated Marshes; 

Wastelands & Fallow Lands; and Hilly, Stony and Sandy Plains. All sampling 

locations were randomly selected, ensuring that sufficient locations are sampled for 

each identified habitat.  

2.3.5 Community/Public Consultation

Local residents of Kotri North Block were also consulted to promote better 

understanding of the proposed exploration and development activities through 

explaining its objectives and its potential positive and negative impacts during the 

fieldwork of EIA. Locals seemed positive and optimistic about the proposed project 

activities. The biggest aspiration of locals is getting only one thing i.e. employment. 

Land related issues were also highlighted during the consultation process. The 

outcomes of the consultation are detailed in Chapter 8 of the EIA report. 

2.3.6 Impact Identification and Assessment

Potential impacts arising from each phase of the proposed project activity were 

identified. These include effects of the proposed project activities on the physical, 

biological, socioeconomic, archaeological and cultural environments of the area. These 

Page 41: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 12 HPK

are detailed in Chapter 7 of the EIA. Impacts were identified and assessed on the basis 

of field data, secondary data, experts’ opinion and monitoring results of previous oil 

and gas exploration projects in Pakistan, particularly in Sindh region. 

2.3.7 Recommendations for Mitigation & Monitoring Measures

Mitigation measures to prevent or minimize all potential adverse environmental 

impacts of the project were identified based on a range of options including 

management and monitoring practices, alternative technologies and physical controls. 

The proposed mitigation measures are based on an appreciation of the sensitivity and 

behavior of environmental receptors within the project area, past experience, case 

studies, legislative controls, environmental guidelines and experts’ advices.  

Monitoring measures have been recommended for residual impacts (impacts 

remaining after applying the recommended mitigation measures) or for impacts that 

cannot be accurately predicted at the EIA stage. In such cases advice on requisite 

monitoring measures was sought from experts involved in the EIA and case studies of 

similar monitoring exercises carried out in wildlife or forest protected areas elsewhere. 

The impacts identified were characterised following the criteria provided in Table 2‐1. 

2.3.8 Development of Environmental Management Plan (EMP)

An Environmental Management Plan (EMP) for the proposed project activities has 

been prepared and provided in Appendix A of this EIA report. The EMP provides a 

framework for implementing and managing the mitigation and monitoring measures 

recommended in the EIA. The EMP includes the following:  

A mitigation and monitoring plan; 

Definition of roles and responsibilities of the proponent, project contractors and 

monitoring teams; 

Requirements for communication, documentation and trainings during the 

proposed exploration and associated development project; 

Restrictions on design, timing and conduct of the project; and 

Change Management Plan to cover unforeseen events/environmental conditions 

during the entire course of the project. 

Page 42: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 13 HPK

Table 2‐1: Impact Characteristics Criteria 

Impact Characteristics Categories

Duration of the impact  Short term – lasting only till the duration of the project such as 

noise from the drilling or seismic operations. 

Medium term – lasting for a period of few months to a year after 

the project before naturally reverting to the original condition such 

as loss of vegetation due to clearing of well site, contamination of 

soil or water by fuels or oil. 

Long term – lasting for a period much greater than medium term 

impacts before naturally reverting to the original condition such as 

loss of soil due to soil erosion. 

Geographical location of 

the impact 

Local – within the area of project i.e. well site, campsite and access 

road etc. 

Regional – within the boundaries of the project area. 

National – within the boundaries of the country. 

Likelihood of the impact  Qualitatively measured on a scale of: 

Almost certain 

Likely 

Possible 

Unlikely 

Rare 

Reversibility of the impact  Defined as: 

Reversible – when a receptor resumes its pre‐project condition. 

Irreversible – when a receptor does not or cannot resume its pre‐

project condition. 

Consequence severity of 

impact  

Rated as: 

Major – when an activity causes irreversible damage to a unique 

environmental feature; effects entire population or species of flora 

or fauna in sufficient magnitude so as to cause a decline in species 

abundance or change in distribution over more than one 

generation; has long term effects (period of years) on socio‐cultural 

or economic activities of regional significance. 

Moderate – when an activity causes long term (period of years) 

reversible damage to a unique environmental feature; effects a 

portion of a population of flora or fauna causing reversible damage 

or change in abundance or distribution over one generation; has 

short term effects (period of months) on socio‐cultural or economic 

activities of regional significance. 

Minor – when an activity causes short term (period of few months) 

reversible damage to an environmental feature; slight reversible 

damage to a few species of flora or fauna within a population over 

a short period of time; has short term (period of months) effects on 

socio‐cultural or economic activities of local significance. 

Negligible – when no measurable damage to physical, 

socioeconomic or biological environment above the existing level of 

impacts occurs. 

Page 43: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 14 HPK

Impact Characteristics Categories

Significance of the impact  Categorized as: 

High 

Medium 

Low 

Based on the consequence, likelihood, reversibility, geographical 

extent, duration, level of public concern and conformance with 

legislative or statutory requirements. 

Page 44: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 15 HPK

3 Legal Framework

Introduction

This chapter provides a synopsis of local land environmental laws, policies, 

legislations and guidelines that may have relevance to the proposed exploration and 

associated development project within Kotri North Block (E.L. 2568‐21). These include: 

United Energy Pakistan Limited’s corporate policy on Health, Safety and 

Environment (HSE); 

National and provincial environmental policies, acts, legislations and guidelines; 

and 

International conventions and guidelines. 

UEPL will be required to adhere to the relevant requirements of the acts, policies, 

legislations and recommendations of the guidelines during the proposed exploration 

and associated development activities, which have also been incorporated in the 

mitigation measures and the EMP provided in the EIA. 

United Energy Pakistan Limited’s Corporate HSE Policy

United Energy Pakistan Limited has a corporate HSE Policy in place. Under this policy 

UEPL is committed to make all workplaces and processes safe and secure for UEPL 

and its stakeholders, environment with continuous improvement, actively strive to 

minimize impacts on environment, participate in climate protection measures and 

support alternative energy resources. Moreover, UEPL constantly strives to drive 

down the environmental impacts through responsible use of natural resources and 

reduction of waste, emissions and discharges.  

The Health, Safety, and Environmental (HSE) Policy has been attached at the end of 

this chapter as Figure 3‐1. 

National Environmental Policy, Legislation and Guidelines

The enactment of comprehensive legislation on the environment, covering multiple 

areas of concern is a relatively new and ongoing phenomenon in Pakistan. Whereas, a 

basic policy and legislative framework for the protection of the environment and 

overall biodiversity in the country is now in place, detailed rules, regulations and 

guidelines required for the implementation of the policies and enforcement of 

legislations are still in various stages of formulation and discussion. The following 

section presents a brief overview of the existing national policies, legislations and 

guidelines. 

3.3.1 National Environmental Policy, 2005

The National Environmental Policy (NEP) is the primary policy of Government of 

Pakistan that addresses the environmental issues of the country. The broad goal of 

Page 45: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 16 HPK

NEP is, “to protect, conserve and restore Pakistan’s environment in order to improve 

the quality of life of the citizens through sustainable development”. The NEP identifies 

the following set of sectoral and cross‐sectoral guidelines to achieve its goal of 

sustainable development.  

a. Sectoral Guidelines 

Water and sanitation, air quality and noise, waste management, forestry, biodiversity 

and protected areas, climate change and ozone depletion, energy efficiency and 

renewable, agriculture and livestock, and multilateral environmental agreements. 

b. Cross‐sectoral Guidelines 

Poverty, population, gender, health, trade and environment, environment and local 

governance, and natural disaster management. 

The NEP suggests the following policy instruments to overcome the environmental 

problems throughout the country: 

Integration of environment into development planning; 

Legislation and regulatory framework; 

Capacity development; 

Economic and market based instrument; 

Public awareness and education; and  

Public private civil society partnership. 

NEP is a policy document and does not apply to proposed exploration or associated 

development project. However, UEPL shall ensure that the project activities should 

not add to the aggravation of the environmental issues identified in NEP and 

mitigation measures shall be adopted to minimize or avoid any contribution of the 

project impacts in these areas. 

3.3.2 National Conservation Strategy, 1992

Before the approval of National Environmental Policy (NEP), the National 

Conservation Strategy (NCS) was considered as the Government’s primary policy 

document on national environmental issues. At the moment this strategy just exists as 

a national conservation program. The NCS identifies 14 core areas including 

conservation of biodiversity, pollution prevention and abatement, soil and water 

conservation, preservation of cultural heritage and recommends immediate attention 

to these core areas in order to preserve the country’s environment. 

NCS does not directly apply to oil and gas E&P projects. However, UEPL shall ensure 

that proposed project should not add to the aggravation of the 14 core environmental 

issues identified in the NCS and mitigation measures shall be adopted to minimize or 

avoid any contribution of the project impacts in these areas. 

Page 46: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 17 HPK

3.3.3 The Biodiversity Action Plan, 2000

The Biodiversity Action Plan (BAP), which was designed to complement the NCS and 

the provincial conservation strategies, identifies the causes of biodiversity loss in 

Pakistan and suggests a series of proposals for action to conserve biodiversity in the 

country. 

The BAP recognizes that an environmental assessment is used as a tool at a project 

level to identify environmental effects of a proposed project activities and to plan for 

reducing adverse effects. The BAP further stipulates that an environmental assessment 

needs to be initiated at an early stage of project development and that public 

participation in the review of potential effects is important. 

3.3.4 Provincial & National Environmental Legislations

a. Sindh Environmental Protection Act, 2014 

After passage of 18th amendment by the parliament in April 2010, Government of 

Sindh has enacted its own environmental law. The Sindh Environmental Protection 

Bill, 2014 having been passed by the Provincial Assembly of Sindh on 24th February, 

2014 and assented to by the Governor of Sindh on 19th March, 2014 as an Act of 

Legislature of Sindh. 

According to Part‐VI, Environmental Examinations and Assessments; no proponent of a 

project shall commence construction or operation unless he has filed with the Agency 

an Initial Environmental Examination (IEE) or Environmental Impact Assessment 

(EIA) and has obtained from the Agency approval in respect thereof. This EIA is being 

submitted by United Energy Pakistan Limited to Sindh Environmental Protection 

Agency to fulfil the requirements of the Act.  

b. Sindh Environmental Protection Agency Review of IEE and EIA Regulations, 2014 

In exercise of the powers conferred by Section 37 of the Sindh Environmental 

Protection Act, 2014, the Sindh Environmental Protection Agency, with the approval 

of Government, issued the following regulations, namely ‘Review of Initial 

Environmental Examination and Environmental Impact Assessment Regulations, 2014’ 

which came into force at once. 

Under these regulations a new provision for submittal of ‘Environmental Checklist’ 

was also introduced in addition to IEEs and EIAs. A proponent of a project falling in 

any category listed in Schedule‐III of these Regulations shall file ‘Environmental 

Checklist’ with the Agency and the provisions of Section 17 shall apply to such 

projects. 

Other important features of the Sindh EPA IEE‐EIA Regulations, 2014 relevant to the 

proposed project activities are listed below:  

A fee is payable to the Sindh EPA for review of the EIA; 

The EIA submittal is to be accompanied by an application in the format prescribed 

in Schedule V of the Sindh EPA IEE‐EIA Regulations, 2014; 

Page 47: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 18 HPK

The Sindh EPA is bound to conduct a preliminary scrutiny and reply within 15 

days of the submittal of the report; a) confirming completeness, or b) asking for 

additional information, if needed, or c) returning the report requiring additional 

studies, if necessary;  

The Sindh EPA is required to make every effort to complete the EIA review 

process within 4 months (120 days) of the issue of confirmation of completeness 

under Regulation 9; and  

If Sindh EPA accords approval, it will be valid for three years from the date of 

accord.  

This EIA falls under Regulation‐4 of these Regulation i.e. Projects requiring an EIA, 

Schedule‐II, Category‐J ‘Environmentally Sensitive Areas’. 

c. Sindh Environmental Quality Standards, 2016 

In exercise of the powers conferred under Clause (g) of Sub‐section (1) of Section 6,  

Sindh  Environmental Protection Act 2014, the Sindh EPA, with the approval of the 

Sindh Environmental Protection Council, has established the environmental 

standards for Industrial wastewater, Effluents, Domestic sewage, Industrial air 

emissions and ambient airs, Noise for vehicles and Drinking water quality standards, 

2015. These standards came into force on 28th January, 2016 and are provided in Table 

3‐1 to Table 3‐6.  

UEPL will be required to comply with all applicable standards as prescribed in the law 

and report to Sindh Environmental Protection Agency as per their requirements or 

bindings. 

d. Self‐Monitoring and Reporting Rules, 2014 

In exercise of the powers conferred by Section 36 of the Sindh Environmental 

Protection Act, 2014, Sindh Environmental Protection Agency with the approval of 

Government of Sindh has established the rules which are called ‘Sindh Environmental 

Quality Standards (Self‐Monitoring and Reporting by Industry) Rules, 2014’ which came 

into force at once.  

As per rules set by this system, provincial industries have to monitor effluents and 

emissions in compliance with the SEQS and report it to Provincial EPA. This system 

classifies industry into three categories A, B and C each corresponding to a specified 

reporting frequency. Proposed exploration and associated development activities in 

Kotri North Block lies under ‘Category A & B’ for both liquid effluent and gaseous 

emissions (priority parameters provided in Table A & B of Schedule‐IV of these Rules, 

2014) and thus shall submit Environmental Monitoring Reports to Sindh EPA on 

monthly and quarterly basis as per categories defined in the Rules e.g. for oil & gas 

production, priority parameters need to be submitted to the Sindh EPA on monthly 

basis. 

 

Page 48: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 19 HPK

e. The Sindh Occupational Safety and Health Act, 2017 

The Sindh Occupational Safety and Health Bill, 2017 having been passed by the 

Provincial Assembly of Sindh on 17th November, 2017 and assented to by the Governor 

of Sindh on 26th December, 2017 as an Act of the Legislature of Sindh which came into 

force at once.   

The Sindh Occupational Safety and Health Act 2017, Sindh Act No. I of 2018 is an act 

to make provision for occupational safety and health conditions at all workplaces for 

the protection of persons at work against risk of injury arising out of the activities at 

work places and for the promotion of safe, healthy and decent working environment 

adapted to the physical, physiological and psychological needs of all persons at work. 

After enforcement of this Act, United Energy Pakistan Limited and all proposed 

project execution contractors will be bound to abide all provisions defined in the act. 

f. Hazardous Substances Rules, 2014 

In exercise of the powers conferred by Section 36 of the Sindh Environmental 

Protection Act, 2014, the Sindh EPA, with the approval of the Sindh Government 

announced comprehensive rules in 2014, namely ‘Hazardous Substances Rules, 2014’ 

which came into force at once. 

As per Hazardous Substances Rules, 2014, United Energy Pakistan Limited is bound to 

obtain a license from Sindh EPA for transportation, usage, handling, storage and 

disposal of hazardous substances as prescribed in Sub‐clause (b) of Clause (xxv) of 

Section 2, Schedule‐I of Hazardous Substances Rules, 2014 in exploration & production 

operations being carried out by the Company. 

g. Sindh Wildlife Protection Ordinance, 1972 and Amendments, 2001 

This ordinance provides for the preservation, protection and conservation of wildlife 

by the formation and management of protected areas and prohibition of hunting of 

wildlife species declared protected, under this Ordinance.  

The ordinance also specifies three broad classifications of the protected areas i.e. 

national parks, wildlife sanctuaries and game reserves. Activities such as hunting and 

breaking of land for mining are prohibited in national parks, as are removing 

vegetation or polluting water flowing through the park. Wildlife sanctuaries are areas 

that have been set aside as undisturbed breeding grounds and cultivation and grazing 

is prohibited in the demarcated areas. Nobody is allowed to reside in a wildlife 

sanctuary and entrance for the general public is by special dispensation. However, 

these restrictions may be relaxed for scientific purpose or betterment of the respective 

area on the discretion of the governing authority in exceptional circumstances. Game 

reserves are designated as areas where hunting or shooting is not allowed except 

under special permits. 

Two amendments to the Ordinance were issued in January and June, 2001 respectively 

pertaining to oil and gas activities within national parks and wildlife sanctuaries. The 

first amendment allowed the Government to authorise the laying of an underground 

Page 49: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 20 HPK

pipeline through protected areas. The second amendment allowed exploration and 

production activities within national parks and wildlife sanctuaries. 

As the planned project activities will be carried out far away from wildlife protected 

areas therefore, the project will not contravene with any provisions of the Act. 

However, UEPL shall ensure that the mitigation measures suggested in the EIA are 

being adhered with to preserve, protect and conserve the existing wildlife of the area. 

h. Sindh Irrigation Act, 1987 with Amendments in 2011 

The Sindh Irrigation Act (1987) is the main enactment relating to irrigation in the 

province of Sindh, under this Act the entire task of irrigation has been entrusted to the 

Provincial Government, Canal Officers, the Revenue Department and Judicial Officers. 

The main features of the Act are as under:  

Important policy aspects of Irrigation, like the appointment of the Canal Officers, 

acquisition of water for public use, payment of compensation, water rates, 

drainage schemes, canal crossing and framing the rules, have been entrusted to the 

Provincial Government; 

Operational functions are entrusted to the Canal Officers but the Act does not 

specify which Canal Officers are empowered to act under any of its provisions. 

Therefore, a Canal Officer must by duly authorized by the Provincial Government 

to act under any provision of the Act; 

The Revenue Administration helps the Irrigation Department to acquire land, 

determine compensation and collect water dues. Moreover, the Commissioner and 

Collector have substantial power to settle disputes among irrigators and can 

decide appeals against the decisions of the Canal Officers. Thus, the Canal Officers 

are substantially subservient to the Revenue Department; and 

The offences under the Act can be tried before the Magistrate. 

The canals and associated irrigation network exists in the project area and provisions 

of this acts applies to certain activities like water abstraction by project contractors etc. 

There is no project activity planned near the canal and associated network which 

could directly cause physical damage to the canal or alteration in water quality. Any 

abstraction of water from the canal shall be only done after getting formal approval 

from the concerned Irrigation Department. 

i. The Forest Act, 1927 

This act is applicable to all regions of Pakistan. It includes procedures for constituting 

and managing various types of forests, such as reserved forests and protected forests. 

The act empowers the provincial forest departments to declare any forest area as 

reserved or protected and also prohibit the breaking up or clearing of forest for 

cultivation, grazing, hunting, removing forest produce, quarrying and felling, lopping 

and topping of trees’ branches in reserved and protected forests.  

Page 50: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 21 HPK

It also defines the duties and roles of forest related public servants and penalties for 

any infringement of the rules. As per information collected from secondary sources, 

SOP maps and from consultation with Sindh Forest Department, the project area is 

also located within the forest plantation or on forest land therefore provisions of this 

act applies to all project activities. Thus, United Energy Pakistan Limited shall ensure 

that all mitigation measures suggested in this EIA are being adhered with to protect 

the natural vegetation cover of the area and to avoid habitat loss and degradation of 

biodiversity. 

j. Antiquities Act, 1975 

The protection of cultural resources in Pakistan is ensured by the Antiquities Act of 

1975. Antiquities have been defined in the Act as ancient products of human activity, 

historical sites, or sites of anthropological or cultural interest, national monuments etc. 

The act is designed to protect antiquities from destruction, theft, negligence, unlawful 

excavation, trade and export. The law prohibits new construction in the proximity of a 

protected antiquity and empowers the Government of Pakistan to prohibit excavation 

in any area which may contain articles of archaeological significance. Under the Act, 

the project proponent is obligated to: 

Ensure that no activity is undertaken in the proximity of a protected antiquity, and 

If during the course of the project an archaeological discovery is made, it shall be 

reported to the Department of Archaeology, Government of Pakistan. 

No surface archaeological sites (protected) were identified in the project area during 

the fieldwork for EIA however, there is a possibility of existence of sites with historical 

significance within the leased area due to its location therefore, UEPL shall ensure that 

all proposed mitigation measures suggested in EIA shall be adhered with during the 

execution of the proposed exploration and development project to protect the 

archaeological, heritage and cultural environment of the area. As per authentication 

measure, SOP maps and secondary data were also consulted for verification purposes 

and no protected archaeological site falls within jurisdiction of Kotri North Block. 

k. Legislation on Oil & Gas Exploration and Production 

The various regulations related to oil & gas exploration and production include: 

The Mines Act, 1923 

The Regulation of Mines and Oilfields and Mineral Development (Government 

Control) Act, 1948 

The Pakistan Petroleum (Production) Rules, 1949 

The Oil and Gas (Safety in Drilling and Production) Regulations, 1974 

The Pakistan Petroleum (Exploration and Production) Rules, 1986 

The Model Petroleum Concessions Agreement, 1994 

Page 51: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 22 HPK

The Regulation of Mines and Oilfields and Mineral Development (Government 

Control) Act, 1948 and the Pakistan Petroleum (Production) Rules, 1949 and Pakistan 

Petroleum (Exploration and Production) Rules, 1986 empowers the Ministry of 

Petroleum to oversee the petroleum exploration, development and production 

operations. The 1986 Exploration and Production Rules address environmental 

concerns and require operators to “prevent pollution, avoid accumulation of trash and 

prevent damage to the environment and surroundings”.  

As for safety, the Model Petroleum Concession Agreement (July, 1994) implementing 

the 1986 Exploration and Production Rules, specifically requires observance of the 

1974 Safety Regulations. The penalties imposed in the 1986 Exploration and 

Production Rules allow the Director General Petroleum Concessions (DGPC) to revoke 

a license if the Rules are not satisfied by the operator. The Mines and Oil Fields Act 

also specifies penalties including imposition of fines and/or imprisonment. 

The 1923 Mines Act through the Oil and Gas (Safety in Drilling and Production) 

Regulations, 1974 controls the full range of safety issues in exploration and production 

from seismic operations to construction, drilling and production. 

The 1974 Safety Regulations requires operators to send to the Chief Inspector of Mines, 

Ministry of Labour and Manpower information on safety issues including provisions 

of protective equipment and identification of safety personnel and emergency 

measures, designation of safety personnel including a Welfare and Safety Officer and 

accident reporting. 

l. The Explosive Act, 1884 and Explosive Rules, 2010 

This Act and Rules provide regulations for the handling, transportation and use of 

explosives during quarrying, blasting and other purposes. The proposed seismic 

surveys will be performed using combination of dynamite and vibroseis therefore, 

strict compliance to the provisions/guidelines should be ensured while using the 

explosives. However, subsequent drilling of wells and other associated development 

activities e.g. construction of well site or campsite sometimes needs blasting at 

rocky/mountainous areas. Same rule applies on the construction/establishment of 

processing facilities or necessary surface support facilities e.g. EWT etc. It is pertinent 

to mention that for the purpose, no such blasting is envisaged. If unavoidable the 

activity should be performed in such a manner that no contravention with any 

provisions of the Act or Rules is occurred. 

m. Pakistan Penal Code, 1860 

The Pakistan Penal Code, 1860 authorizes fines, imprisonment or both for voluntary 

corruption or fouling of public springs or reservoirs so as to make them less fit for 

ordinary use. 

 

 

Page 52: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 23 HPK

3.3.5 National Environmental Guidelines

a. The Pakistan Environmental Assessment Procedures, 1997 

The Pakistan Environmental Protection Agency (Pak EPA) prepared the Pakistan 

Environmental Assessment Procedures in 1997. The guidelines pertaining to the 

review process of EIAs and IEEs was given regulatory status in the Review of IEE and 

EIA Regulations, 2000. They are based on much of the existing work done by 

international donor agencies and Non‐Governmental Organizations (NGOs). The 

package of regulations prepared by Pak EPA includes: 

Policy and procedures for filing, review and approval of environmental 

assessments; 

Guidelines for the preparation and review of environmental reports; 

Guidelines for public consultation; 

Guidelines for sensitive and critical areas; and 

Sectoral guidelines – O&G exploration and production. 

The guidelines on policy and procedures define the policy context and the 

administrative procedures that will govern the environmental assessment process, 

from the project pre‐feasibility stage, to the approval of the environmental report. 

According to the procedures laid out in the policy guidelines, IEEs or EIAs are to be 

filed with the Provincial EPA where the project is to be implemented. The Federal EPA 

has, however, been given the right to review any environmental report at any time and 

the power to revoke the decision of the Provincial EPA, if it deems this to be necessary. 

Projects have been classified in the policy guidelines by expected degree of adverse 

environmental impacts. All projects proposed in environmentally sensitive areas 

(including Game Reserves and Wildlife Sanctuaries) require an EIA. 

The procedures require proponents to prepare terms of reference for the 

environmental assessment reports. They require that all environmental assessment 

studies shall contain baseline data on the area and must contain a detailed assessment 

of the potential environmental impacts and the recommended mitigation measures. 

Consultations with the communities that are most likely to be affected as well as 

relevant NGOs are to be an integral part of the environmental impact assessment 

process. 

The guidelines on public consultation deals with possible approaches to public 

consultation and techniques for designing an effective program of consultation that 

reaches out to all major stakeholders and ensures the incorporation of their concerns in 

any impact assessment study. The guidelines on sensitive areas are more specific in 

that they identify the officially notified protected areas in Pakistan, including critical 

ecosystems and archaeological sites. 

Lastly, there are guidelines for oil & gas exploration and production operations. The 

guidelines state that onshore exploration activities can be carried out without having 

Page 53: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 24 HPK

to submit either an IEE or an EIA. This is subject to the project proponent’s adherence 

to the provisions of the guidelines and provided that such exploration is not taking 

place within or adjacent to a sensitive or critical area/s. Possible adverse impacts that 

may arise in due to proposed project activities include damage to flora and fauna and 

to crops and livestock as well as the production of waste. Project proponents are 

required to take measures to mitigate such effects. 

b. Guidelines for Operational Safety, Health and Environmental Management, 

December, 1996 

These guidelines are the outcome of a study commissioned by the Directorate General 

Petroleum Concessions (DGPC), Ministry of Petroleum and Natural Resources, 

Government of Pakistan. The guidelines list down the relevant laws related to the 

operational/occupational health, safety and environment and also recommends 

environmental controls and management practices to be adopted in O&G exploration 

and production projects. 

International Treaties and Guidelines

3.4.1 International Treaties

Pakistan is a signatory to various international treaties and conventions on the 

conservation of the environment and wildlife protection. The country is thus obliged 

to adhere to the commitments specified in these treaties. A brief of these prime treaties 

is provided hereunder.  

a. The Convention on Biological Diversity, 1992 

The Convention on Biological Diversity was adopted during the Earth Summit of 1992 

at Rio de Janeiro, Brazil. The Convention requires parties to develop national plans for 

the conservation and sustainable use of biodiversity, and to integrate these plans into 

national development programs and policies. Parties are also required to identify 

components of biodiversity that are important for conservation, and to develop 

systems to monitor the use of such components with a view to promoting their 

sustainable use. Moreover, in accordance with the Article 26 of the convention, parties 

are also required to prepare national reports on the status of implementation of the 

convention. 

b. The Convention on Conservation of Migratory Species of Wild Animals, 1979 

(Bonn Convention) 

The Convention requires countries to take action to avoid endangering migratory 

species. The term ʺmigratory speciesʺ refers to the species of wild animals, a significant 

proportion of whose members cyclically and predictably cross one or more national 

jurisdictional boundaries. The parties are also required to promote or cooperate with 

other countries in matters of research on migratory species.  

Page 54: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 25 HPK

The Convention contains two appendices. Appendix I contain the list of migratory 

species that are endangered according to the best scientific evidence available. For 

these species, the member states to the Convention are required endeavour to: 

Conserve and restore their habitats; 

Prohibit their hunting, fishing, capturing, harassing and deliberate killing; 

Remove obstacles and minimize activities that seriously hinder their migration; 

and 

Control other factors that might endanger them, including control of introduced 

exotic species. 

Appendix II lists the migratory species, or groups of species, that have an 

unfavourable conservation status as well as those that would benefit significantly from 

the international cooperation that could be achieved through intergovernmental 

agreements. See Table 6‐12, Table 6‐13, and Table 6‐14 for list of recorded wildlife 

species covered under this convention. 

c. The Convention on Wetlands of International Importance, Ramsar, 1971 

Pakistan is a signatory to the said Convention. The principal obligations of contracting 

parties to the Convention are: 

To designate wetlands for the List of Wetlands of International Importance; 

To formulate and implement planning so as to promote wise use of wetlands, to 

make EIA before transformations of wetlands, and to make national wetland 

inventories; 

To establish nature reserves on wetlands and provide adequately for their 

wardening and through management to increase waterfowl populations on 

appropriate wetlands; 

To train personnel competent in wetland research, management and wardening; 

To promote conservation of wetlands by combining far‐sighted national policies 

with coordinated international action, to consult with other contracting parties 

about implementing obligations arising from the Convention, especially about 

shared wetlands and water system; 

To promote wetland conservation concerns with development aid agencies; and 

To encourage research and exchange of data. 

So far 19 sites in Pakistan have been declared as wetlands of International Importance 

or Ramsar Sites but none of these lies within or in the close proximity of the Kotri 

North Block. The nearest Ramsar site is Keenjhar which is also known Kalri Lake at an 

approx. distance of 33 km in southern direction. Kalri is one the largest freshwater 

lakes in Pakistan. It has length of about 24 km, width 6 km and capacity of 0.53 million 

acre feet. It is located at a distance of about 122 km east from Karachi and 19 km north‐

east of Thatta town. Indus provides Keenjhar, the required water through Kalri Baghar 

Page 55: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 26 HPK

(KB) Feeder. KB Feeder starts from Kotri Barrage. Since, the area is arid and receives 

less than 200 mm annual rainfall, hence Indus is the only source of water for this lake. 

d. Convention on International Trade in Endangered Species of Wild Fauna and Flora 

(CITES) 

This Convention came into effect on 3rd March, 1973 in Washington. In all, 130 

countries are signatory to this convention with Pakistan signed the convention in 1976. 

The convention requires the signatories to impose strict regulation (including 

penalization, confiscation of the specimen etc.) regarding trade of all species 

threatened with extinction or that may become so, in order not to endanger further 

their survival.  

The Convention contains three appendices. Appendix I includes all species threatened 

with extinction which are or may be affected by trade. The Convention requires that 

trade in these species should be subject to strict regulation. Appendix II includes 

species that are not necessarily threatened presently but may become so unless trade 

in specimens of these species is subject to strict regulation. Appendix III includes 

species which any contracting party identifies as subject to regulations in trade and 

requires other parties to cooperate in this matter. See Table 6‐12, Table 6‐13 and Table 

6‐14 for list of recorded wildlife species covered under CITES appendices.  

e. International Union for Conservation of Nature and Natural Resources (IUCN) 

Red List  

The Red List is published by IUCN and includes those species that are under potential 

threat of extinction. These species have been categorized as: 

Endangered – Species that are seen to be facing a very high risk of extinction in the 

wild in the near future, reduction of 50% or more either in the last 10 years or over 

the last three generations, survive only in small numbers, or have very small 

populations. 

Vulnerable in decline – Species that are seen to be facing a risk of extinction in the 

wild, having apparent reductions of 20% or more in the last 10 years or three 

generations. 

Vulnerable – Species that are seen to be facing a high risk of extinction in the wild, 

but not necessarily experiencing recent reductions in population size. 

Lower risk – Species that are seen to be facing a risk of extinction that is lesser in 

extent that for any of the above categories. 

Data deficient – Species that may be at risk of extinction in the wild but at the 

present time there is insufficient information available to make a firm decision 

about its status. 

Page 56: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 27 HPK

3.4.2 Relevant International Guidelines

a. World Bank Guidelines on Environment 

The principal World Bank publications that contain environmental guidelines are 

listed below: 

Environmental Assessment – Operational Policy 4.01. Washington, USA. World 

Bank 1999; 

Environmental Assessment Sourcebook, Volume I: Policies, Procedures and Cross‐

Sectoral Issues. World Bank Technical Paper Number 139, Environment 

Department, World Bank, 1991; 

Environmental Assessment Sourcebook, Volume III: Guidelines for Environmental 

Assessment of Energy and Industry Projects. World Bank Technical Paper No. 154, 

Environment Department, World Bank, 1991; 

Pollution Prevention and Abatement Handbook: Towards Cleaner Production, 

Environment Department, the World Bank, United Nations Industrial 

Development Organization and the United Nations Environment Program, 1998; 

and 

Environmental, Health and Safety (EHS) Guidelines, International Finance 

Corporation (IFC) World Bank Group, 2007. 

The first two publications listed here provide general guidelines for the conduct of an 

EIA and address the EIA practitioners themselves as well as project designers. While 

the Sourcebook in particular has been designed with Bank’s projects in mind and is 

especially relevant for the impact assessment of large‐scale infrastructure projects. It 

contains a wealth of information which is useful to environmentalists and project 

proponents. 

The Sourcebook identifies a number of areas of concern, which should be addressed 

during impact assessment. It sets out guidelines for the determination of impacts, 

provides a checklist of tools to identify possible biodiversity issues and suggests 

possible mitigation measures. Possible development project impacts on wild lands, 

wetlands and forests etc. are also identified and mitigation measures suggested. The 

Sourcebook also highlights concerns in social impact assessment and emphasizes the 

need to incorporate socioeconomic issues in EIA exercises. 

The Sourcebook dealing with the assessment of industry and energy projects is more 

specific. It contains a section on onshore development of O&G and identifies the 

potential environmental impacts of E&P activities. These include surface disturbance 

from the building of access roads in undisturbed areas, disturbance from explosive 

charges and possible damage to cultural resources. Possible socio‐cultural issues that 

may arise as a result of an influx of non‐locals are also identified in the Sourcebook. 

The Pollution Handbook provides general waste management policies with specific 

techniques for the prevention of air and water pollution. Project guidelines are 

Page 57: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 28 HPK

presented for major pollutants as well as typical emissions from industry sector 

including oil and gas. 

As of 30th April, 2007, the documents published in Volume III of the Pollution 

Prevention and Abatement Handbook have been replaced by the new versions of EHS 

Guidelines published by IFC. The EHS Guidelines are technical reference documents 

that address IFCʹs expectations regarding the industrial pollution management 

performance of its projects. They are designed to assist managers and decision makers 

with relevant industry background and technical information. This information 

supports actions aimed at avoiding, minimizing, and controlling EHS impacts during 

the construction, operation and decommissioning phase of a project or facility. The 

EHS Guidelines have become globally applied references for private sector 

development with their use extending well beyond World Bank Group operations to a 

diverse external community, such as other international financial institutions, 

regulators, industry, academics and commercial banks, including the international 

banks that have adopted the Equator Principles. Separate sets of guidelines have been 

prepared addressing general EHS issues as well as guidelines specific to various 

industrial sectors including onshore O&G development projects. 

The EHS Guidelines for onshore O&G development include information relevant to 

seismic exploration, exploration and production drilling, development and production 

activities, transportation activities including pipelines, other facilities including 

pumping, metering, pigging & compressor stations and storage facilities, ancillary and 

support operations and decommissioning. A full description of industry activities for 

this sector is also provided in the guidelines. 

b. Environmental Management in Oil & Gas Exploration and Production, IOGP 

This document provides an overview of environmental issues in the oil & gas 

exploration and production processes and discusses potential environmental impacts 

on the physical, biological and socioeconomic environment. 

The document also recommends environmental management practices and 

environmental protection measures such as waste treatment and disposal techniques, 

pollution prevention and cleaner production, oil spill contingency planning, 

decommissioning etc. for oil & gas exploration and production operations.

c. International Regulations and Guidelines for the Disposal of E&P Wastes 

These include the following: 

The Resource Conservation and Recovery Act of the United States, 1976 (hereafter 

referred to as RCRA) 

Environmental Guidance Document – Waste Management in Exploration and 

Production Operations, American Petroleum Institute, API E5, 1997 (hereafter 

referred to as API Guidelines) 

Statewide Order 29‐B, State of Louisiana, Department of Natural Resources, 1990 

(hereafter referred to as LSO 29‐B Regulations) 

Page 58: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 29 HPK

Colorado Oil and Gas Conservation Commission, Rules and Regulations (hereafter 

referred to as COGCC Regulations) 

The Interstate Oil and Gas Compact Commission guidelines on disposal of E&P 

wastes (hereafter referred to as IOGCC Guidelines) 

The United States Environmental Protection Agency (USEPA) under the RCRA 

classifies all drilling fluids, produce water and drill cuttings as non‐hazardous. The 

API and IOGCC Guidelines and LSO 29‐B and COGCC Regulations present various 

options for the disposal of drilling fluids, produced water and drill cuttings including 

land treatment, road spreading, on site burial and solidification, and recommend 

maximum concentration levels for pH, metals, oil and grease and other inorganic 

parameters to be met by each option. The most stringent limits of concentrations for 

burial have been provided in API Environmental Guidance Document E5 ʺWaste 

Management in Exploration and Production Operationsʺ provided in Table 3‐7, if the 

waste exceeds these limits then the disposal should be in lined pits. Table 3‐8 provides 

the less stringent criteria in terms of concentrations set by LSO 29‐B. 

d. Environmental Guidelines for Worldwide Geophysical Operations, International 

Association of Geophysical Contractors (IAGC); April, 1995  

The IAGC guidelines provide guidance for the management of impacts from 

geophysical operations related to: 

Physical environment including water, air and soil; 

Biological environment including vegetation and wildlife; and 

Socioeconomic environment including archaeological sites, cultural practices and 

commercial and recreational activities. 

The guidelines require project operators to: 

Plan and conduct operations in a manner that conserves the environment; 

Train personnel in environmental matters; 

Consult appropriate stakeholders at all stages of the operation; and 

Evaluate environmental performance of operations and adopt restoration 

measures. 

International and National Environment & Conservation Organizations

3.5.1 International and National NGOs

International environmental and conservation organizations such as International 

Union for Conservation of Nature (IUCN) and the Worldwide Fund for Nature 

(WWF) have been active in Pakistan for some time now. Both these organizations have 

worked closely with government and act in an advisory role with regard to the 

formulation of environmental and conservation policies. Since, the convening of the 

Rio Summit, a number of national environmental NGOs have also been formed and 

Page 59: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 30 HPK

have been engaged in advocacy and in some cases, research. Most prominent national 

environmental NGOs, such as the Sustainable Development Policy Institute (SDPI), 

Strengthening Participatory Organization (SPO), Shehri, Lead and Shirkatgah are 

members of the Pakistan National Committee (PNC) of IUCN. 

As mentioned earlier, environmental NGOs have been particularly active in advocacy, 

as proponents of sustainable development approaches. Much of the governmentʹs 

environmental and conservation policy has been formulated in consultation with 

leading NGOs, who have also been involved in drafting new legislation on 

conservation. 

3.5.2 Pakistan Petroleum Exploration and Production Companies Association

(PPEPCA)

PPEPCA is an association of private sector companies and semi‐autonomous 

departments concerned with exploration and production of O&G. It provides a forum 

for such companies to discuss issues, formulate common strategies and convey 

concerns and demands to the government and to other stakeholders in the O&G 

business. PPEPCA has also been particularly effective in collecting and disseminating 

information on current trends in exploration and production to its members and has 

been instrumental in informing members of changes in government policy and in 

formulating a response to such policy changes.

Page 60: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 31 HPK

Table 3‐1: SEQS for Municipal and Industrial Effluentsa 

Parameters Into Inland 

Water 

Into Sewage 

Treatment5 Into Sea6 

Temperature 40°C or temperature increase*  ≤3°C  ≤3°C  ≤3°C 

pH  6‐9  6‐9  6‐9 

Biochemical Oxygen Demand (BOD5) at 20°C 1  80  250  80** 

Chemical Oxygen Demand (COD)1  150  400  400 

Total Suspended Solids (TSS)  200  400  200 

Total Dissolved Solids (TDS)  3,500  3,500  3,500 

Grease and oil  10  10  10 

Phenolic compounds (as phenol)  0.1  0.3  0.3 

Chloride (as Cl‐)  1,000  1,000  SC*** 

Fluoride (as F)  10  10  10 

Total cyanide (as CN‐)  1.0  1.0  1.0 

An‐ionic detergents (as MBAS)2  20  20  20 

Sulphate (SO4)  600  1000  SC*** 

Sulphide (S‐)  1.0  1.0  1.0 

Ammonia (NH3)  40  40  40 

Pesticides3  0.15  0.15  0.15 

Cadmium4  0.1  0.1  0.1 

Chromium (trivalent & hexavalent)4  1.0  1.0  1.0 

Copper4  1.0  1.0  1.0 

Lead4  0.5  0.5  0.5 

Mercury4  0.01  0.01  0.01 

Selenium4  0.5  0.5  0.5 

Nickel4  1.0  1.0  1.0 

Silver4  1.0  1.0  1.0 

Total Toxic metals  2.0  2.0  2.0 

Zinc  5.0  5.0  5.0 

Arsenic4  1.0  1.0  1.0 

Barium4  1.5  1.5  1.5 

Iron  8.0  8.0  8.0 

Manganese  1.5  1.5  1.5 

Boron4  6.0  6.0  6.0 

Chlorine  1.0  1.0  1.0 

Source: The Sindh Government Gazette, January 28, 2016 

Notes: a All values are in mg/l, unless otherwise defined. 1 Assuming minimum dilution 1:10 on discharge, lower ratio would attract progressively stringent standards to be 

determined by the Sindh Environmental Protection Agency. By 1:10 dilution means, for example that for each one 

cubic meter of water for dilution of this effluent. 2 Methylene Blue Active Substance; assuming surfactant as biodegradable.  3 Pesticides include herbicides, fungicides and insecticides. 4 Subject to total toxic metals discharge should not exceed level given at S.N. 25. 

Page 61: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 32 HPK

5 Applicable only when and where sewage treatment is operational and BOD5=80mg/l is achieved by the sewage 

treatment system. 

6 Provided discharge is not at shore and not within 10 miles of mangrove or other important estuaries. 

* The effluent should not result in temperature increase of more than 3°C at the edge of the zone where initial mixing 

and dilution take place in the receiving body. In case zone is not defined, use 100 meters from the point of discharge. 

** The value for industry is 200mg/l. 

*** Discharge concentration at or below sea concentration (SC).

Page 62: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 33 HPK

Table 3‐2: SEQS for Industrial Gaseous Emissiona 

Parameter  Source of Emission  Standard 

Smoke  Any 

40% or 2 on Ringlemann 

scale or equivalent smoke 

number 

Particulate matterb 

Boilers and Furnaces:   

Oil fired  300 

Coal fired  500 

Cement kilns  300 

Grinding, crushing, clinker 

coolers and related processes, 

metallurgical processes, 

converter blast furnaces and 

cupolas 

500 

Hydrogen chloride   Any  400 

Chlorine  Any  150 

Hydrogen fluoride  Any  150 

Hydrogen sulfide  Any  10 

Sulfur oxidesc 

Sulfuric acid/Sulfonic acid 

plants 5,000 

Other plants except power 

plants operating on oil and 

coal 

1,700 

Carbon monoxide  Any  800 

Lead  Any  50 

Mercury  Any  10 

Cadmium  Any  20 

Arsenic  Any  20 

Copper  Any  50 

Antimony  Any  20 

Zinc  Any  200 

Oxides of nitrogend 

Nitric acid manufacturing unit 

3,000 Other plants except power 

plants operating on oil or coal 

  Oil Fired  400 

  Coal fired  600 

  Cement kilns  1,200 

Source: The Sindh Government Gazette, January 28, 2016 

Notes: a All values are in mg/Nm3, unless otherwise defined. b Based on the assumption that the size of the particulates is 10 micron or more. c Based on 1% sulphur content in fuel oil. Higher content of sulphur will cause standards to be pro‐rated. 

Page 63: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 34 HPK

d In respect of the emissions of the sulfur dioxide and nitrogen oxides, the power plants operating on oil or coal as 

fuel shall, in addition to standard specified above, comply with the following standards.

Page 64: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 35 HPK

Table 3‐3: SEQS for Motor Vehicle Exhaust and Noisea 

Parameter  Standard  Measuring Method 

Smoke 

40% or 2 on the Ringlemann 

scale during engine 

acceleration mode 

To be compared with Ringlemann 

Chart at a distance of 6 meters or 

more 

Carbon Monoxide New vehicles: 4.5% 

Used vehicles: 6% 

Under idling conditions, non‐

dispersive infrared detection 

through gas analyzer 

Noise  85 dB (A) Sound‐meter at 7.5 meters from the 

source 

Source: The Sindh Government Gazette, January 28, 2016 

Notes: a For in‐use vehicles 

Table 3‐4: Sindh Environmental Quality Standards for Noise 

No.  Category of Area/ Zone 

Effective from

1st January, 2015 

Effective from 

1st January, 2015 

Limit in dB(A) Leq

Day Time Night Time Day Time  Night time

1.  Residential area (A)  65  50  55  45 

2.  Commercial area (B)  70  60  65  55 

3.  Industrial area (C)  80  75  75  65 

4.  Silence zone (D)  55  45  50  45 

Source: The Sindh Government Gazette, January 28, 2016 

Notes: 

1. Day time hours: 6.00 am to 10.00 pm 

2. Night time hours: 10.00 pm to 6.00 am 

3. Silence zone: Zones which are declared as such by the competent authority. An area comprising not less than 100 

meters around hospitals, educational institutions and courts.  

4. Mixed categories of areas may be declared as one of the four above mentioned categories by the competent 

authority. 

5. dB(A) Leq: Time weighted average of the level of sound in decibels on scale A which is relatable to human 

hearing.

Page 65: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 36 HPK

Table 3‐5: Sindh Standards for Drinking Water Quality 

No.  Properties/Parameters  Proposed Standard Values for Pakistan

Bacterial 

1. 

All water intended for drinking 

(E.Coli or thermotolerant coliform 

bacteria) 

Must not be detectable in any 100 ml 

sample 

2. 

Treated water entering the 

distribution system (E.Coli or 

thermotolerant coliform and total 

coliform bacteria) 

Must not be detectable in any 100 ml 

sample 

3. 

Treated water in the distribution 

system (E.Coli or thermotolerant 

coliform and total coliform bacteria) 

Must not be detectable in any 100 ml 

sample. In case of large supplies, where 

sufficient samples are examined, must not 

be present in 95% of the sample taken 

throughout any 12‐month period. 

Physical 

4.  Colour  < 15 TCU 

5.  Taste  Non objectionable/Acceptable 

6.  Odour  Non objectionable/Acceptable 

7.  Turbidity  < 5 NTU 

8.  Total hardness as CaCO3  < 500 mg/L 

9.  TDS  < 1000 

10.  pH  6.5‐8.5 

Radioactive 

11.  Alpha Emitters bq/L or pCi  0.1 

12.  Beta emitters  1 

Chemical 

Essential Inorganics  mg/L 

13.  Aluminium (Al)  < 0.2 

14.  Antimony (Sb)  < 0.005 

15.  Arsenic (As)  < 0.05 

16.  Barium (Ba)  0.7 

17.  Boron (B)  0.3 

18.  Cadmium (Cd)  0.01 

19.  Chloride (Cl‐1)  < 250 

20.  Chromium (Cr)  < 0.05 

21.  Copper (Cu)  2 

Toxic Inorganics  mg/L 

22.  Cyanide (CN)  < 0.05 

23.  Fluoride (F)*  < 1.5 

24.  Lead (Pb)  < 0.05 

25.  Manganese (Mn)  < 0.5 

26.  Mercury (Hg)  < 0.001 

27.  Nickel (Ni)  < 0.02 

Page 66: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 37 HPK

No.  Properties/Parameters  Proposed Standard Values for Pakistan

28.  Nitrate (NO3)*  < 50 

29.  Nitrite (NO2)*  < 3 

30.  Selenium (Se)  0.01 

31.  Residual chlorine  0.2‐0.5 at consumer end 0.5‐1.5 at source 

32.  Zinc (Zn)  5.0 

Source: The Sindh Government Gazette, January 28, 2016  

* Indicates priority health related inorganic constituents which need regular monitoring.

Page 67: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 38 HPK

Table 3‐6: SEQS for Ambient Air 

No.  Pollutants 

Time‐

weighted 

Average 

Concentration in Ambient 

Air Method of 

Measurement Effective 

from 1st Jan, 

2009 

Effective from 

1st Jan, 2012 

1. Sulfur Dioxide 

(SO2) 

Annual 

Average* 80 μg/m3  80 μg/m3  Ultraviolet 

Fluorescence method 24 hours**  120 μg/m3  120 μg/m3 

2. Oxide of Nitrogen 

as (NO) 

Annual 

Average* 40 μg/m3  40 μg/m3  Gas Phase 

Chemiluminescence 24 hours**  40 μg/m3  40 μg/m3 

3. Oxides of 

Nitrogen as (NO2) 

Annual 

Average* 40 μg/m3  40 μg/m3  Gas Phase 

Chemiluminescence 24 hours**  80 μg/m3  80 μg/m3 

4.  O3  1 hour  180 μg/m3  130 μg/m3 Non dispersive UV 

absorption method 

5. 

Suspended 

Particulate Matter 

(SPM) 

Annual 

Average* 400 μg/m3  360 μg/m3 

High Volume 

Sampling, (Average 

flow rate not less 

than 1.1 m3/minute) 24 hours**  550 μg/m3  500 μg/m3 

6. 

Respirable 

Particulate Matter. 

PM10 

Annual 

Average* 200 μg/m3  120 μg/m3  ß Ray absorption 

method 24 hours**  250 μg/m3  150 μg/m3 

7. 

Respirable 

Particulate Matter. 

PM2.5 

Annual 

Average* 25 μg/m3  15 μg/m3 

ß Ray absorption 

method 

24 hours**  40 μg/m3  35 μg/m3  

1 hour  25 μg/m3  15 μg/m3 

8.  Lead (Pb) 

Annual 

Average* 1.5 μg/m3  1 μg/m3 

ASS method after 

sampling using EPM 

2000 or equivalent 

filter paper 24 hours**  2 μg/m3  1.5 μg/m3 

9. Carbon Monoxide 

(CO) 

8 hours**  5 μg/m3  5 μg/m3  Non Dispersive Infra 

Red (NDIR) method 1 hour  10 μg/m3  10 μg/m3 

Source: The Sindh Government Gazette, January 28, 2016  

* Annual arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniform interval.  

** 24 hourly/ 8 hourly values should be met 98% of the year. 2% of the time, it may exceed but not on two consecutive 

days.  

 

Page 68: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 39 HPK

Table 3‐7: API Standard for On‐site Burial of E&P Wastes in Unlined Pitsa, b, c 

No.  Parameter  Standard 

1.  pH  6‐9 

2.  Total Petroleum Hydrocarbons  < 1% (dry weight)d 

3.  Arsenic  41 

4.  Barium  180,000  

5.  Cadmium  26  

6.  Chromium  1,500  

7.  Copper  750  

8.  Lead  300  

9.  Mercury  17  

10.  Molybdenum  37  

11.  Nickel  210  

12.  Selenium  100  

13.  Zinc  1,400  

14.  Boron  2 mg/Le 

15.  Sodium adsorption ratio (solution phase)  < 12 

16.  Exchangeable sodium percentage (solid phase)  < 15% 

17.  Electrical conductivity   < 4 mmho/cm 

Source: API E5 Second Edition of Environmental Guidance Document, Waste Management in Exploration and 

Production Operations (February 1997), Section 5.5.4 

Notes: 

a All values in mg/kg unless otherwise stated 

b Waste exceeding the following limits should be buried or land‐filled in lined pits (provided the limits of pH, TPH 

and EC are complied with) 

c The standards also require that the top of the burial cell must be at least five feet below ground level and the 

bottom of the burial cells must be five feet above seasonal high water table 

d Dry weight 

e Based on the soluble concentration with units of mg/L rather than total concentration 

Page 69: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 40 HPK

Table 3‐8: LSO 29B Criteria for On‐site Burial in Unlined Pits  

No.  Parameter  Standard

1.  pH  6‐9 

2.  Oil and Grease  < 3% (dry weight) 

3.  Arsenic   10 ppm 

4.  Barium (Upland area)  40,000 ppm 

5.  Cadmium  10 ppm 

6.  Chromium   500 ppm 

7.  Lead   500 ppm 

8.  Mercury  10 ppm 

9.  Selenium  10 ppm 

10.  Silver  200 ppm 

11.  Zinc  500 ppm 

12.  Electrical Conductivity  < 12 mmho/cm 

13.  Moisture Content  < 50 % by weight 

Source: State wide order No. 29‐B (June, 2010) 

Notes: 

1‐ The top of the burial cell must be at least five feet below ground level. 

2‐  The bottom of the burial cells must be five feet above seasonal high water table. 

Page 70: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land
Page 71: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 42 HPK

4 Project Description

The Proposed Project

United Energy Pakistan Limited (UEPL) intends to carry out exploration and 

associated development activities in Kotri North Block (E.L. 2568‐21). These 

activities range from 2D/3D seismic surveys, drilling of exploration/ 

development wells, laying of flow line/s from producing wells to the 

hydrocarbons gathering system/processing facility, establishment of processing 

facilities e.g. EWT or CPP, up‐gradation/modification of existing facilities with 

associated civil and engineering works e.g. construction of access track/s, 

residential camp/s, construction of well site/s etc. and finally decommissioning 

and site restorations. Proposed project activities will be commenced with 2D/3D 

seismic survey and based upon the aforementioned seismic data acquisition and 

its interpretations, UEPL will plan to drill wells as part of exploration/ 

development plan. After the successfully drilling at any proposed well location 

and in case of discovery, flow line/pipeline will be laid from each well to the 

new/existing hydrocarbons gathering and production system over the period of 

three years. Detailed proposed project activities will include but not limited to 

be are listed below: 

Seismic activities (2D and 3D); 

Well sites preparation & construction activities; 

Drilling of exploration, development and water injection wells (no new water 

injection well will be drilled only plugged & abandoned (P&A) well will be used 

for the purpose); 

Surface facilities development at drilled well sites including EWT; 

Laying of flow lines from producing wells to CPP/Gathering hub; 

Laying of flow lines from CPP/Gathering hub to Point of Delivery (POD); 

Development of early production, production and testing facilities which will 

include plant construction and operations; 

Development of remote facilities; 

Up‐gradation/Modification of existing facilities; 

Relocation of existing facilities e.g. decommissioning of plant equipment and 

relocation to other location within project area; 

Construction of access roads & residential camps; 

Decommissioning of surface facilities (well sites/plant sites); and 

Sites restoration. 

Page 72: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 43 HPK

The details of core activities i.e. seismic, drilling, laying of flow line and establishment 

of processing facility are provided in following sections of this chapter. 

Seismic Operation

The objective of the seismic survey is to delineate the subsurface geological structure 

beneath the area in order to investigate the potential for oil & gas reserves and to 

identify a suitable surface location for the drilling of wells. The principle of seismic 

survey is to cause shock waves in the ground which reflect from geological strata. By 

measuring the time taken to receive the shock waves at detectors at the ground surface 

(called “geophones”), a picture of the subsurface geology can be developed. 

There are two basic types of seismic data acquisition techniques are being used in 

Pakistan i.e. two dimensional (2D) and three dimensional (3D). The seismic operation 

proposed by UEPL comprise of both 2D and 3D seismic data acquisition within the 

project area. Two dimensional seismic data collection occurs along a line of receivers 

therefore, the resultant image represents only a section below the line. A three 

dimensional seismic survey utilizes multiple points of observation. This is 

accomplished by deploying a grid of geophones and seismic source impact points 

along the surface of the area being studied. The result is a volume or cube of seismic 

data sampled from a range of different angles and distances. In a typical 2D survey, 

seismic lines can be many kilometres apart, whereas in a 3D survey, they are generally 

a few hundred meters apart. 

Two types of techniques will be used for data acquisition; vibroseis in the terrain with 

gentle slopes and flat areas; dynamite within agricultural lands and all other areas 

where access or working of the vibroseis will be difficult. Upholes may be drilled at 

selected locations within the area of the seismic survey.  

Each seismic operation will involve housing about 800 – 1,000 people in a seismic 

campsite (depending upon the technique being used). In terms of resource utilization, 

water will be used for domestic and operational purposes. Earth fill material may be 

required for the construction and operational purposes. Local labour will also be 

employed during the operation. A description of activities involved in proposed 

seismic program is provided in sections below. 

4.2.1 Line Permitting

Before commencement of work, a permitting team headed by a Chief Permit Man will 

arrive in the area. The teamʹs early arrival will facilitate activities such as liaising with 

local landowners and authorities to inform them of the operation and make necessary 

arrangements. The permitting team will identify the ownership of the land areas over 

which the seismic operation will be undertaken. In consultation with the respective 

district administration and following agreed rates, compensation will be given to the 

landowners. During the seismic survey the Chief Permit Man will be the focal point 

for communication between local inhabitants and seismic survey personnel. 

Page 73: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 44 HPK

4.2.2 Line Survey and Preparation

In this activity the seismic lines will be marked on the ground by survey teams, each 

team comprising of 4 to 5 people. The survey teams will use a Global Positioning 

System (GPS) to mark shot points on the seismic lines at every 20 – 50 m intervals with 

whitewashed stones or wooden pegs.  

In plain areas, for laying of seismic lines, area may be cleared (if required) to a width 

of 3 m and at a depth of a few inches with a bulldozer. This will allow the movement 

of vibroseis over the cleared strip of land along the line. Clearing of trees and dense 

patches of vegetation will be avoided. Seismic lines passing through agricultural fields 

will not be cleared, as dynamite will be used as the energy source in these areas. 

4.2.3 Data Acquisition

a. Dynamite 

In this technique, 1 – 20 meters deep and 10 cm diameter holes, called shot holes, will 

be drilled every 20 – 50 m along sections of the seismic lines passing through 

agricultural lands or areas where access or working of vibroseis will be difficult. These 

holes will be drilled using portable hand driven drills. Each drill will be operated by a 

team of 6 to 8 drillers headed by a foreman. A total of 5 to 10 drilling teams will be 

employed on each line. It is expected that each team will be able to drill 6 to 8 holes 

per day depending on the geological and environmental conditions of the area. If 

required each drilled hole will be cased with a Polyvinyl Chloride (PVC) pipe to 

prevent the hole from collapsing. If a shot point cannot be drilled at a specified 

location because of any environmental restriction, a replacement point will be located 

as close to the original shot point as possible. Seismic drilling activity will not be 

carried out at stream beds. However, cables and geophones will be laid across the 

surface water bodies for data acquisition purposes. 

Due to loose soil material wherever expected in the area the holes during drilling will 

be flushed with bentonite mud. The bentonite mud will be prepared near the shot 

point in a 2 m square and 0.5 m deep earthen pit. Water tankers will transport water 

required for the preparation of the mud. These water tankers will travel only on 

existing and approved tracks. In case an existing track does not reach to a shot point, 

the tanker will stop on the track at a position nearest to the shot point, from thereon 

water will be transported by means of hose pipes connected to the tanker. The spent 

drilling mud and cuttings will be stored inside a similar earthen pit. The spent mud 

and cuttings will be allowed to dry after which the pit will be backfilled with at least 

15 cm of top soil cover. The pits will be clearly marked until restored. Since, bentonite 

is a type of clay and a non‐hazardous material, burial of the mud and cuttings on site 

will not contaminate soil or groundwater. 

After completion of drilling, each shot hole will be loaded with approximately 0.5 – 3 

kg of dynamite and 1 or 2 detonators. Explosives will be handled by a loading crew 

who will be specially trained in the handling, storage, transportation, charging, firing 

Page 74: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 45 HPK

and safety of dynamite. The charges will be carefully inserted into each hole before the 

cylindrical PVC casing is removed. Each hole will then be backfilled with sand/mud. 

Approximately 70 labourers divided into six teams including front crew, back crew, 

shooting crew, recording crew and green crew will carry out shooting, recording and 

restoration along the seismic lines. These teams will operate several days behind the 

drilling team.  

The front cable crew will layout the cables and plant geophones along the seismic line. 

The cables and geophones will be symmetrically laid out 3 – 4 km along the seismic 

line on either side of a shot point. The geophones connected together in groups of 24 

or more will be planted along the line at intervals of 1 to 5 meter. Each string of 

geophones will be connected to a cable, which will be connected to a station unit. The 

station units will be connected to a recording unit through the same cable. The points 

along which cables and geophones will be laid are termed receiver array. 

The shooting crew will be responsible for the detonation of charges. Once the cables 

and geophones have been symmetrically laid out along the line, the charge is 

detonated by a crew comprising of 4 men. At the surface the sound of the detonation 

will be no more than a muffled thud. The process is repeated along the line, cables and 

geophones being removed from the back of the line and placed at the front of the line 

as the shooting crew progresses. 

The recording crew will monitor the ground electronics equipment and recording of 

the seismic data. The back cable crew will be responsible for picking up the cables, 

geophones and station units. The green crew will follow the back cable crew and 

remove any wastes from the seismic lines and restore the shot holes as close to their 

original condition as possible. 

b. Upholes 

Upholes will be drilled with the help of truck mounted drilling rig. These holes will be 

drilled to a depth of up to 150 m and will be 150 mm in diameter. To ensure stability of 

the borehole, a water based bentonite mud will be circulated through the hole. It is 

estimated that for each hole approximately 5,000 to 8,000 litres of water will be 

required for the preparation of the bentonite mud. The mud will be prepared in an 

earthen pit near the hole. A similar pit will be used to store the used mud. After 

drying the pits along with their contents (bentonite mud and cuttings) will be 

backfilled. Data from upholes will be collected either by a hammer source at the 

surface and a string of geophones suspended inside the hole or by using detonators 

inside the hole to receiver at the surface. 

c. Vibroseis 

This technique will make use of vibrators as an energy source. The vibrator consists of 

a heavy mass (up to 50 tons) attached to a steel plate mounted on a truck. The truck 

will lower the steel plate to rest on the ground while lifting the body of the truck in air 

by means of hydraulic jacks. The steel plate will be made to vibrate, creating energy 

Page 75: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 46 HPK

waves that will travel downwards into the earth’s surface. The reflected waves will be 

received on the ground by cables and geophones laid along the seismic line.  

The arrangement of cables, geophones and station units will be similar to the 

arrangement adopted for dynamite. A series of four vibrators will follow each other 

along the line. All 4 vibrators will stop at a point called vibroseis point and produce 

energy waves in the manner described above. With this technique approximately 5 – 8 

km of line can be recorded each day again depending on the topography of the area. 

4.2.4 Camps, Staffing and Supplies

One base camp and a fly camp (if required) will be prepared to house around 800 – 

1,000 crewmembers depending on the technique being used for the seismic data 

acquisition during each seismic survey. The camps will be located and constructed 

such that minimum clearing of vegetation or land is involved land maintaining a safe 

distance from the communities and sensitive environmental habitats. The approximate 

area for the seismic base camp will be 40,000 square meters (m2) and will include 

accommodation area including tents and porta‐cabins, senior and junior kitchens and 

mess, laundry area, toilets, workshops, vehicles parking area, equipment storage 

areas, fuel and oil storage areas, generators area, septic tanks, soak pits and a garbage 

pit. The camps will be fenced for security reasons. An advance party will prepare the 

base camp. Survey work will start only after satisfactory set up of the base camp.  

Approximately 40,000 litres of water would be required per day for the seismic 

operation, which will be primarily used for domestic purposes. Flush and uphole 

drilling consumes approx. 4~5,000 litres and 8,000 litres of water per hole respectively. 

Except flush and uphole drilling, use of jackrobs drilling (if required) and vibroseis 

operation will not require water. 

A bulk stock of dynamite will be transported to the project area. This will be stored in 

a purpose built explosive storage area ‘magazine’ located at a safe distance from 

communities and the seismic camps (base & fly). The explosives will be stored in an 

excavated pit lined with concrete blocks and covered with tarpaulins. The area will be 

fenced and guarded for security reasons. 

4.2.5 Access and Transport

Access to seismic lines will mostly be through existing tracks. As 4WD vehicles will be 

used by the project, these tracks can be used without any improvement. Short reaches 

of new tracks may have to be prepared in areas where there is no existing access 

however, the preparation of new tracks will be minimized. Vehicles and equipment 

likely to be used during seismic operation will include Dozers, Trucks, Unimog 

Recorder Truck, Cranes, Uphole Rigs, Jackrobs, Air Compressors, Water Tankers, 4x4 

Pick‐ups/Jeeps, Explosive Vehicles, Fuel Tankers, Vibrators, Tents, Porta‐cabins, 

Ambulances and Generators. 

Page 76: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 47 HPK

4.2.6 Restoration and Waste Management

After completion of the every seismic operation, the campsites (base & fly) will be 

restored to as close to its original condition as possible. For reference purposes a 

photographic record of the campsites prior to setup will be taken. The following 

activities will be carried out for site restoration: 

Demobilization of all equipment and machinery; 

Disposal of any waste material remaining at the time of completion of the 

operation; 

Backfilling of all soak pits and septic tanks; 

Dismantling and removal of fence or barriers surrounding the camp area; and 

General restoration of the site area including landscaping and restoration of 

drainage where required. 

Restoration of seismic lines will include removal of all cables, geophones, station units, 

flags, stakes and wastes from the lines and backfilling of all mud pits. For reference 

purposes a photographic record of selected sections of seismic lines will be taken 

before and after the operation.  

Drilling Operation

4.3.1 Proposed Project Activities

This operation will comprise of drilling of exploratory/development wells within 

prospective areas based on the 2D & 3D seismic data interpretations. The proposed 

drilling project will entail the following activities: 

Phase I – Construction  

o Civil contractor’s mobilization 

o Development of access road 

o Rig camp construction 

o Security camp construction 

o Well site construction 

o Civil contractor’s demobilization 

Phase II – Well Drilling 

o Rig mobilization and rig camp establishment 

o Well drilling and testing 

o Vertical Seismic Profiling (VSP) 

o Rig demobilization 

Phase III − Site Restoration (depending on the failure or success of the well) 

Page 77: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 48 HPK

4.3.2 Project Schedule

The drilling operation of each well, from civil works to plugging and abandonment is 

expected to take about 4~5 months. The drilling of wells is planned after the 

acquisition of 2D & 3D seismic data and its interpretation by United Energy Pakistan 

Limited. The tentative duration of key activities is provided below: 

Mobilization 15 days 

Civil works 60 days 

Drilling 60 days 

Testing 15 days 

4.3.3 Construction

In this phase of the operation, a well site, rig camp, security camp and access track will 

be developed for each proposed well. The construction contractor will develop its own 

camp for construction purposes. The camp will house a maximum of 200 people. The 

contractor will also hire local people for unskilled jobs. The construction works will 

take approximately 60 days to complete.  

The well site and rig camp will cover an area of approximately 32,400 and 8,000 m2 

respectively. Well site construction will involve the following: 

Clearing, leveling and compaction; 

Construction of the concrete drilling rig pad and cellar; 

Construction of cutting pit, water pit and wastewater pits; 

Construction of septic tanks and soak pits; 

Construction of flare pit; 

Construction of platform for fuel storage tank with sump and loading/un‐loading 

pad; and 

Installation of a chain link fence around the well site along with snake protection 

and ditch. 

The rig campsite will consist of porta‐cabins, kitchens, mess rooms, bathrooms, 

laundry area etc. for which limited construction works including levelling, grading, 

filling and compaction will be required. Development of campsite includes, but not 

limited to the following: 

Leveling and compaction of area for the campsite; 

Provision of drainage works in and around the campsite; 

Laying and compaction of the gravel or rock topping in the campsite; 

Construction of fuel storage tank with sump and loading/un‐loading pad; 

Provision of fence, access and emergency gates; 

Page 78: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 49 HPK

Construction of septic tank and soak pits; 

Installation of security guard wooden cabins; and 

Installation of sewerage flow line with manholes for the septic system. 

Construction works to develop the access road will include, but not limited to the 

following: 

Cutting and filling; 

Leveling, grading and compaction of subgrade; 

Laying of gravel and compaction; 

Construction of culverts and causeway crossings (if required);  

Provision of earthen catch drains; 

Provision of pass points at every 1,000 m; and 

Provision of milestones, road and safety signs. 

Existing tracks will be used as much as possible to access the selected drilling 

locations. Due to the network of existing tracks in the area, development of new tracks 

may be limited to short reaches of a few kilometers only. The existing tracks will be 

upgraded (if required) to a standard that is suitable for movement of 40 ft. trailers. The 

road will be 6 m wide, consisting of 5 m gravel top and 0.5 m of earthen shoulder on 

either side. 

Water required during construction will be obtained from either local tube wells, or 

new water wells installed by UEPL in the area of operation. Approximately 80,000 

liters of water would be required per day during construction phase. After completion 

of construction activities, all except for a few machinery, equipment and personnel 

required for maintenance of the access road will be demobilized from the area.  

4.3.4 Rig Mobilization

Following the construction of the each well site, campsite and access road mobilization 

of the rig and related machinery and equipment will commence. Mobilization will 

involve the transportation of the following to the designated drilling location: 

The drilling rig; 

Ancillary equipment such as power generators, mud pumps, mud tanks, shale 

shakers, cementing unit, drill pipe and collars; 

Porta‐cabin style camp, complete with all catering, power generation, laundry and 

other facilities; 

Drilling and other necessary support personnel; and 

Drilling materials such as casing and associated accessories, wellheads, drill bits, 

drilling fluid chemicals and liner hanger equipment etc. 

Page 79: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 50 HPK

The drilling rig will be transported to the site using 40 ft. long trailers. Depending on 

the type of rig, approximately 80 to 150 truckloads of equipment will be transported 

during mobilization. The rig will be assembled and erected over the well location. 

4.3.5 Drilling

Drilling will be carried out using conventional equipment, techniques and practices 

for drilling operation. A rotary drilling rig will be used in this operation. The derrick 

will be mounted on a steel platform known as the rig floor. The rig floor will provide 

working area for the drilling operations and personnel. A hoisting drum called draw 

works will be mounted on the rig floor at the base of the derrick. A wire rope called 

the drilling line will pass from the draw works to the top of the derrick through a 

system of pulleys called the crown block and will be attached to a further system of 

pulleys known as the hook and block. The whole system of wire rope and pulleys will 

operate like a crane. A drill string made up of uniform lengths of hollow steel pipes 

will be suspended from the hooks. Suspended from the drill string will be the drill bit. 

The drill bit will drill through the formations by the combined effect of the weight of 

the drill collar and the rotary action provided to the bit by a rotary table mounted on 

the rig floor. Rotation of the drilling bit and string is achieved by means of powerful 

electric motors on the surface. 

Based on the sections of the well, drill bits with diameter 26, 171/2, 121/4, 81/2 and 6 inches 

are expected to be used. As drilling progresses in a given section of the well the length 

of the drill string will be increased by the addition of new lengths of pipes. Steel pipes 

known as casing will be lowered into the hole to line the sides of the well and prevent 

the hole from collapsing. At the end of drilling each section, these steel casings will be 

cemented into place by pumping cement into the space between the casing and the 

surrounding strata. The sections of the well will be drilled in this manner until the 

desired target depth is achieved. Anatomy of a generic rotary drilling rig is shown in 

Figure 4‐1. The drilling operation will be undertaken on a round‐the‐clock basis with 

two 12 hours shifts. 

a. Drilling Mud 

A water based drilling mud will be used during the operation to serve the following 

functions. 

Flushing out drilled solids from the bottom of the hole and their transport to the 

surface; 

Lubrication and cooling of the drill bit and string; 

Deposition of an impermeable layer on the wall of the wellbore so as to seal the 

drilled formations; and 

Countering the natural formation pressures and preventing uncontrolled flow of 

fluid from the formations. 

Page 80: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 51 HPK

The drilling mud will consist of slurry of formation cuttings suspended in a liquid 

phase. Fresh water spud mud will comprise of Bentonite, Sodium hydroxide (NaOH), 

Sodium carbonate (Na2CO4) and lime (CaO) in water. The additives such as bentonite, 

barite and salts will be used for initial mud formulation and subsequent changes as 

required during the operation. The exact constituents and concentrations will be 

finalized before the drilling operation. The quantity & composition of drilling mud 

used and the cuttings generated will depend upon the well geology, depth of the well 

and other operating factors. 

b. Management of Drilling Wastes 

Conventional drilling waste management involves discharging the mud and cuttings 

into a lined waste pit. However, UEPL may use a cuttings segregation and fluid 

recovery unit in which the cuttings segregated by the shakers are processed through 

centrifuges and Hi‐G dryer. This will further allow: 

Additional drying of the cuttings making their disposal into the lined waste pit 

easier; 

Recovery of the excess mud associated with the cuttings. The mud can be re‐used 

thereby reducing the overall water consumption and chemical usage for mud 

formulation; and 

Reduction in the size of the waste pit due to the reduction in the mud content 

associated with the cuttings and due to less water consumption and mud 

formulation. 

This waste management system is considered to be technologically and 

environmentally the most preferred option. After completion of drilling, the cuttings 

remaining in the waste pit will be allowed to dry out. The cuttings will then be 

encapsulated within the HDPE liner and the waste pit will be backfilled leaving a top 

soil cover over the pit at the time of site restoration. 

c. Coring & Well Logging 

In the potential reservoir section, cores of rock may be taken from the borehole and a 

number of well logs performed. Cores and well logs will be used to confirm the 

geology of the structures being bored through and assess the accuracy of the seismic 

survey data interpretation carried out before drilling operation. Coring and well 

logging will also help identify possible hydrocarbons. 

d. Well Evaluation 

After having drilled to the specified depth, a number of logs for hydrocarbon bearing 

strata will be taken to accurately measure the pressure and fluid content of the zone. 

The main objectives of the logs will be to determine the fluid composition (gas, oil or 

water), whether or not it will flow and its pressure regime. 

Page 81: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 52 HPK

If test results show that gas has been encountered, it becomes necessary to conduct 

further tests to determine whether it is feasible to develop the well. Tests are 

conducted to determine the gas composition and the reservoirʹs permeability. 

Once the temporary or permanent valves are in place, it is ensured that the mud 

column is more than adequate to counteract any formation pressures that could be 

released. After that, a mechanical plug is used to plug off the area of the formation 

being tested, and tubing is run through the plug. A Blowout Preventer (BOP) is kept in 

place throughout the test. 

Once these steps have been taken, gas is allowed to flow to the surface and is passed 

through a 3‐phase separator that segregates the fluid into water, gas and oil or 

condensate. Metering devices and valves are used to estimate the gas production rate, 

after which the gas and associated condensate are flared and water discharged into the 

mud pit. 

e. Well Completion 

If data collected from coring, logging and well testing shows that the well can be used 

as a producing well then a completion string together with a few items of subsurface 

equipment (such as a down hole plug) to enable production from the well will be 

installed just above the producing formation. The mud in the well will be displaced by 

completion fluid, which is expected to consist of potassium chloride brine, containing 

small volumes of chemicals designed to protect the well. These chemicals will include 

a corrosion inhibitor, an oxygen scavenger, biocide and a chemical for pH control. The 

final design of the completion equipment will depend on the subsurface geology. 

f. Well Control & Blowout Prevention 

In addition to careful monitoring and control of the mud system and the installation of 

casing in each section of the well, a surface wellhead consisting of a series of BOPs will 

be installed at the top of the casing. The function of the BOP is to prevent uncontrolled 

flow from the well by positively closing in the wellbore as and when required. The 

BOP is made up of a series of hydraulically operated rams and is designed to 

withstand pressures well in excess of those expected to be encountered. 

g. Staffing and Supplies for Drilling 

It is expected that around 160 – 180 people will be required for each drilling operation. 

Local people will be hired for unskilled jobs. During the drilling program the supplies, 

with the exception of casing will be transported to the rig in smaller trucks. Casing 

will be carried to the rig in 40 ft. flatbed trucks. General supplies transported will 

include camp supplies (food etc.), fuels, oils and chemicals and equipment 

maintenance parts. Project personnel will travel to and from the rig in smaller vehicles, 

mostly four‐wheel drive pickups. 

Water for rig and rig camp operation will be transported to the project facilities from 

local water wells or to be installed by UEPL in the project area in consultation with 

local communities and by following the requirements of the EIA. A maximum of 

Page 82: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 53 HPK

80,000 litres of water will be required per day during the drilling operation, which 

may exceed to 150,000 litres during peak drilling activity. The surface water resources 

will not be used during drilling phase. Average water consumption during the camp 

operation for different O&G operations is shown in Table 4‐1. 

4.3.6 Demobilization & Site Restoration

After completion of the drilling and testing operations, the rig will be dismantled and 

demobilized off the site. The wellhead will remain in situ, but all other equipment and 

materials including empty drums used and unused chemicals, fuels and lubricants 

will be removed from the well site by their respective suppliers. 

After well evaluation, a decision on whether to abandon or further develop the well 

will be taken. If it is decided that the well is to be abandoned, the site will be restored, 

as far as possible, to its original condition. All the concrete structures will be broken 

up and removed, the fencing will be removed and the area levelled. All the broken 

concrete may be taken outside of the project area for disposal, reused for backfilling of 

pits or provided to locals for re‐use. All waste products, solid and liquid will be 

disposed of in accordance with the requirements of the EIA. All pits will be backfilled. 

Drill cuttings will be disposed of within the lined cuttings pit at the well site. Drilling 

mud and other liquids will be allowed to evaporate inside the lined pit after which the 

pits will be backfilled. The access tracks may be left intact if local people desire to use 

them. If not, they too will be restored and the land returned to its original use. 

4.3.7 Produced Water Injection Well

Produced water injection wells are also part of the proposed exploration and 

development project. Produced water from the producing wells will be re‐injected into 

deep subsurface formations wherever feasible. Drilling will not be carried out and 

only plugged and abandoned well/s will be used for the safe disposal of produced 

water from the nearby producing wells which will be connected through a nominal 

diameter of pipeline.  

Flow Line Laying & Tie-in/Wellhead Works

In case of discovery at any proposed drilling location, a flow line will be laid to 

connect it to gathering hub and ultimately to the gas processing facility. Pipelines used 

for this purpose will be dependent on specifications of fluid properties. Shortest 

possible route will be selected for laying of flow line. 

4.4.1 Flow Line Laying Activities

Flow lines will be laid to connect the well site to the existing/new processing plant by 

carbon steel NACE flow line which will be dependent on flow rate/production. Laying 

of proposed flow lines will primarily be done along the existing and proposed access 

tracks to the well sites. Flow line laying activities will include the following: 

Land survey; 

Right of way (RoW) preparation; 

Page 83: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 54 HPK

Transportation of pipes, construction materials, construction machinery and 

personnel; 

Installation (trenching, laying and backfilling); 

Cleaning, testing and commissioning; 

Operation and maintenance; 

Site Restoration; and 

Flow line decommissioning. 

A brief description of these activities is as follows: 

a. Land Survey 

Land survey for demarcating the pipeline route will be undertaken by a team of about 

5 to 6 persons equipped with computers, survey stations, GPS handsets, levelling 

instruments, steel measuring tapes and worktables. The following activities are carried 

out as part of the survey: 

Route reconnaissance; 

Traverse line survey and installation of wooden pegs; 

Topographic survey of pipelines, RoW and terminals; 

Excavation and re‐filling of pits for classification and record of soil encountered; 

Determination of subsoil water table in the area and land type classification e.g. 

fallow land or cultivated areas; 

Survey of pipeline crossings at roads or water channel etc.; 

Installation of RoW markers; and 

Installation of permanent benchmarks. 

b. Right of Way (RoW) Preparation 

A 50 ft. RoW along the proposed alignment will be leased from the local landowners. 

RoW for the proposed gas flow line will be cleared of vegetation and levelled before 

the trenching operation is started.  

The RoW route will be selected with the following considerations: 

Selection of the shortest possible route; 

Maximum usage of existing RoW of access route and flow line laid thereby, 

minimizing access requirements during the construction period and avoiding 

acquisition of private land; 

Minimum disruption to the local population, in particular avoidance of any 

population resettlement; 

Maintaining a safe distance from cultural resources (typically a distance of 50 m 

from shrines, graveyards and mosques); and 

Page 84: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 55 HPK

Minimum disruption to the natural environment. 

c. Transportation and Construction Activities 

The laying of pipeline will be done by a construction contractor. The construction 

contractor will employ a crew of around 150 – 200 people for pipeline laying. Local 

people will be hired for unskilled jobs as and when required during the project subject 

to company’s competency criteria and in accordance to all local applicable laws. The 

construction equipment required during the pipeline laying typically includes: 

Bulldozer 

Excavator 

Forklift 

Pipe layer 

Grader 

Compressor 

Welding machine 

Radiography 

Sand blasting machine 

Pumps; and 

Pipe‐bending machines. 

The crew may work in separate teams and may reside in one or two fly camps 

established at different locations. The camp will consist of tented accommodation, 

kitchens, mess rooms, bathrooms, laundries, septic tanks and soak pits etc. for which 

limited construction work will be required. At campsite the contractor may also utilize 

levelled areas for storage of pipes and other materials and machinery. The pipes will 

be transported to the site in up to 40 ft. sections over flatbed trucks. The construction 

material and construction machinery will be transported to the site on trucks. Trucks 

or pick‐ups will transport all other supplies to the camps. This will include 

construction material and consumables, fuel, oil, water and food. At campsite fuel, oil 

and chemicals will be unloaded in designated areas with impermeable floors and 

dykes to prevent soil and water contamination from spills. Water consumed during 

pipeline laying (cleaning and hydro‐testing) will be transported to the site from the 

nearest local wells or from UEPL’s existing or new wells (if required) to be installed by 

the company according to the requirements of EIA.  

d. Flow Line Installation  

A trench approximately 3 ft. wide by 5 ft. deep for laying of pipeline (to connect 

producing well to the storage or processing facility) will be excavated. The pipeline 

will be laid along the side of the trench and welded together. Welded sections of the 

line will then be placed at the bottom of the trench by pipe layers or/and cranes 

Page 85: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 56 HPK

moving along the line. The pipeline will be below the ground along its entire route 

and will be installed in a trench with a minimum depth of one meter, which will be 

backfilled to be flushed with the surrounding ground level, with the top soil replaced.  

e. Flow Line Cleaning, Testing and Commissioning 

Once a section of a pipeline has been installed, it will be cleaned by sending a traceable 

brushing pig down the section. This will remove some of the debris and water that has 

accumulated in the pipeline during construction. The line will then be flushed with 

clean water for further cleaning. The cleansing water may contain some oil, grease and 

suspended solids. The water will be collected in earthen pits where it will evaporate 

with time or drained into the nearest drainage channel. Disposal of the residual sludge 

or solids and the liner will be done following best industrial practices.  

The pipeline will then be non‐destructive tested by radiography, ultrasonic and 

magnetic particle inspection and hydro‐testing to check its integrity. Hydro‐testing 

involves filling the line with clean water (no chemicals added) and pressurizing the 

line to 1.25 times the operating pressure. Makeup water will also be required during 

testing. After final use, wastewater produced during hydro‐testing will be collected in 

lined pits at the main production facilities and evaporated or disposed of into nearby 

drainage channels with the prior approval of the concerned municipality. After the 

testing phase is over, the pipeline will be commissioned. 

As steel pipes are being used, these will be buried at a depth of 3 ft. from the natural 

surface level and a 1 ft. sand cushion underneath the pipes for added support. At 

water crossings the pipeline will be normally laid 4 ft. below its bed level. However, in 

certain cases where this is not practical due to HSE or other reasons the pipeline may 

be laid above grade. Inter‐visible white washed concrete posts or markers will be 

provided to indicate the pipeline alignment.  

Existing dirt tracks or roads will be used to access work areas along the pipeline 

alignment. The development of new tracks may be limited to short reaches only. The 

dirt tracks used may also need to be upgraded to a standard that is suitable for 

movement of flatbed trucks carrying pipelines. 

f. Well Sites Control System 

Each well will be provided with a local wellhead control panel (WHP) for equipment 

status and for local manual control of the wing valve. The Surface Safety Valve (SSV) 

and Upper Master Safety Valve (UMSV) will have self‐contained manual hydraulic 

systems for opening and closing of the valve. 

Each well will be provided with a Remote Terminal Unit (RTU) to provide status, 

control and shutdown facilities at the Gas Processing Facility (GPF) via fiber optic 

cable. 

Page 86: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 57 HPK

g. Methanol Injection 

Requirement for Methanol Injection will be reconfirmed upon completion of flow 

assurance studies to be carried out during conceptual engineering design. If it is 

required, methanol injection skid will be made available at the wellhead. Methanol 

will be injected into the wellhead via the service wing valve and it will be used to 

prevent hydrate formation in the wellhead piping, downstream of choke valve and in 

the flow line. 

h. Corrosion Inhibitor 

Corrosion Inhibitor skid and injection facility will also be installed at each wellhead 

area. Corrosion inhibitor will be injected into the flow lines (unless CRA material is 

used) to protect these and associated downstream piping systems from internal 

corrosion. 

i. Flow Line Operation and Maintenance 

Following commissioning, pipeline during operation will be continuously monitored 

for corrosion, leakages and faulty instrumentation.  

Cathodic Protection System  

For proposed steel pipelines Cathodic Protection (CP) will be done. Impressed current 

system will be provided for underground pipeline protection. With a CP system a 

direct electric current will be induced into the pipe at intervals to maintain a pipe to 

soil potential in the range of ‐0.85 to ‐1.5 volts. The normal corrosion of steel is a 

process where the electron flows from the steel surfaces towards the surrounding 

medium (ground). With a CP system this process will be reversed and will result in 

corrosion prevention. Base plates protection of tanks and sacrificial anodes to be 

provided for pipeline during construction and internal cathodic protection of tanks.  

Pipeline Coating 

Pipeline will be protected against external corrosion by a 3 layer fusion bonded epoxy 

polyethylene factory‐applied coating system. The field joint and bends will be coated 

with heat‐shrink sleeves at the site.  The above‐ground section of pipeline and block 

valves will be painted.  

Isolation Valve Stations  

Keeping in view applicable codes & standards’ requirements, four isolation valve 

stations on the pipeline shall be developed. 

j. Site Restoration 

On completion of the construction phase, the temporary infrastructure will be 

decommissioned and sites restored. This will involve: 

Removing the temporary construction camp; 

Reinstating the flow line route back to the original condition as close as possible; 

Page 87: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 58 HPK

Closing all the temporary waste pits;  

Leveling and restoration of borrow areas; and 

Site restoration also involves reinstatement of vegetation and topography.  

k. Flow Line Decommissioning 

Decommissioning of flow lines will be carried out when required according to best 

industrial practices and standards. There may be three potential options for pipeline 

decommissioning:  

Suspension – pipelines are not depressurised but are physically isolated from the 

pipeline system;  

Abandonment in place – pipelines are physically disconnected from the pipe 

system, purged and cleaned with water or inert material and sealed (capped) at the 

ends; or  

Removal – pipelines are entirely removed from the pipeline easement. 

Abandonment in place is usually environmentally most favourable option. One of the 

objectives of decommissioning will be to return the leased land to the landowners in a 

condition that poses no adverse risk to human health or to the environment. 

l. Staffing and Supplies during Flow Line/s Construction 

It is expected that around 150 – 200 people will be required for the construction of flow 

line and tie‐in works/wellhead works. These included technical, skilled and un‐skilled 

staff.  

General supplies transported will include camp supplies (food items etc.), fuels, oils, 

chemicals and equipment maintenance parts. All supplies, both for construction 

activity and for the camp, will be transported by trucks and pick‐ups. This will include 

construction material and consumables, water and food. Diesel will only be purchased 

locally from the nearest diesel filling station and will not be stored at campsite in the 

form of storage tanks. The average daily consumption of diesel would be less than 

1,000 litres. The requirement of water during construction would include water for 

construction camps, sprinkling of roads and general construction activities. Water 

required for construction purposes will be procured from local tube well or newly 

installed tube wells by UEPL and in case of a shortfall, from other groundwater 

sources as per the requirements prescribed in EIA. 

During the construction activity, material such as steel, cement, sand and aggregates 

for road and pavement construction may also be required. Earth fill will be obtained 

from selected sites where material meeting the required specifications is available. 

These sites will be selected with consideration to environmental mitigations. Pavement 

material will be obtained from regional quarries. 

Page 88: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 59 HPK

4.4.2 Development of Surface Facilities

After the successful drilling of at any proposed well location, development of surface 

facilities will also be carried out as part of exploration and development plan. This will 

include development of EWT (Extending Well Testing) in case if laying of flow line to 

the processing facility is not a feasible option at initial development phase. If any 

new/existing hydrocarbon processing facility exists in nearby areas, flow line will be 

laid from producing wells to the processing facility/gathering hub. Furthermore, flow 

line will also be laid from processing facility to the POD (Point of Delivery) i.e. SSGC 

Hub which are usually installed near Gas Processing Plant/s. 

Extended Well Testing (EWT) 

The Extended Well Test (EWT) operations are required in order to gain an 

understanding of the dynamic characteristics of the reservoir to support any future 

development of the well and are essential to determine reservoir connectivity on a 

large scale and to demonstrate sufficient reserves in place to justify any future 

development. 

Fluids produced during the EWT operations will be processed through a well test 

based process system. The intended test shall help in acquiring the dynamic data for 

further evaluation and firming up the: 

Original hydrocarbon reserves;  

Stabilized reservoir pressure; 

Depletion trend; 

Well deliverability; 

Drainage radius; and 

Strategy for field development. 

During the EWT operations, all the gas produced would be sent for flaring after 

passing through filtration unit. Thus the use of flaring will be very limited and 

intermittent. 

The proposed operation will consist of the following main activities: 

Installation and operation of EWT facilities including, but not limited to wellhead 

production and control system, de‐emulsifier injection system, line heaters, 3‐

phase separation and crude stabilization system etc.; 

Boiler/Hot oil system (optional); and 

Storage tanks and decanting facility. 

Hydrocarbon Processing Facility (GPF/CPP)

The Hydrocarbons Processing Facility i.e. Gas Processing Facility or Central 

Processing Plant (GPF/CPP) will be designed and constructed to treat the raw gas and 

meet the gas sales specifications. The GPF/CPP will also be capable of handling waxy 

Page 89: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 60 HPK

well fluids. The wax content is expected to be present in condensate which may cause 

wax formation especially during winter. The wax mitigation strategies will be further 

explored during the Front End Engineering Design Phase. The construction/ 

establishment activities of the GPF/CPP are provided in the following sections of the 

report. 

4.5.1 Construction/Establishment of Gas Processing Facility

The construction of the facility will be undertaken in two phases, selection and 

preparation of the site and installation of the equipment. These are described below: 

a. Site Selection and Preparation 

The land will be acquired/leased by United Energy Pakistan Limited. The land for the 

GPF/CPP will be cleared and temporary campsite will be constructed. A blacktop road 

will be constructed by converting the already existing track into a metalled track. 

However, some small new stretches of metalled track might also have to be developed 

to approach the CPP/GPF. 

Earthworks will be carried out to provide a raised platform for the processing plant 

area and to avoid inundation during floods. Appropriately sized and lined drainage 

ditches will be provided to direct rainwater away from the GPF/CPP. 

Once the site sub‐base has been prepared, the underground infrastructure will be 

installed and foundations laid for the process equipment and supporting 

infrastructure. The sealed site roads and paved areas will also be constructed.   

Typical activities that are conducted during the civil construction are: 

Excavation for foundations; 

Laying of foundations; 

Masonry work; 

Concrete work;  

Asphalt work (pavement and roads etc.); and 

Finishing (plastering and painting etc.). 

b. GPF/CPP Installation 

The gas processing and ancillary equipment, brought to site by road in sections, will 

be erected on site and hooked‐up. After completion of erection, the facility will be 

hydro‐tested to 1.5 times design pressure. 

Typical activities that are conducted during plant erection are: 

Site fabrication (equipment/pipe supports, equipment assemblies etc.); 

Placement of the vessels and equipment on the foundations; 

Laying of pipes; 

Welding and joining etc.; 

Page 90: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 61 HPK

Electrical installation (cabling, switchgears and transformers etc.); 

Instrument installation (field instruments, control room instruments and 

instrument cabling etc.); 

Painting; and 

Testing and commissioning. 

c. Main Facilities at GPF/CPP 

Main facilities at GPF/CPP include:  

Three Phase Separator (Production Separator); 

CO2 Removal Unit (CRU); 

Gas Dehydration Unit (DHU); 

Nitrogen Removal Unit (NRU); 

Sales Gas Compressors; 

Evaporative Cooler; 

Sales Gas Metering; 

Closed Drain System; 

Flare System; 

Fuel Gas System; 

Instrument Air System; 

Nitrogen Generation System; 

Fire Water & Pumps; 

Hot Oil System; 

Demineralized Water System; and 

CPI Separator and Pump. 

Condensate and produced water from processing trains are directed to condensate 

and produced water handling system. The produced water is disposed to Evaporation 

Ponds from Produced Water Tank or CPI Separator via Pump. 

GPF inlet header is provided with a connection to direct well fluid to processing train. 

Production Separator receives gas from the inlet header. The gas, condensates and 

produced water are separated in the Production Separator. The separated condensate 

and produced water will be routed to the Condensate System and Produced Water 

System for further treatment and disposal. 

The separated/produced gas from the Production Separator is routed to the CO2 

Removal Unit (CRU). Here the CO2 is reduced/removed to meet the CO2 specification. 

This gas is then processed to the Gas Dehydration Unit (DHU) to remove or minimize 

Page 91: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 62 HPK

the water content in the gas. After the water content removal, the gas is then routed to 

the Nitrogen Rejection Unit (NRU). NRU removes/reduces the Nitrogen content in the 

gas to meet the Sales Gas specification for Nitrogen. 

The gas from the NRU outlet is then routed to the Sales Gas Compressors. The Sales 

Gas Compressors boost the sales gas pressure to transport the sales gas to the Buyer 

network. After cooling the compressed gas up to the desired temperature, it is then 

routed to the Sales Gas Pipeline via Sales Gas Metering Skid. 

d. Construction Camps 

The construction camp will be set up for the construction of the GPF/CPP. The 

construction camp for plant construction is expected to be set up at an appropriate 

location and will be fully fenced, sign‐posted and secured to restrict access.   

The campsite will include the following facilities: 

Camp fencing and security setup; 

Offices; 

Communications base; 

Mechanical workshop; 

Maintenance workshop; 

Warehouse and stores; 

Fuel storage; 

Water treatment plant; 

Power generation plant; 

Water storage; 

First‐aid unit; 

Firefighting equipment; 

Supervisory staff and workers accommodation; 

Diners; 

Recreation unit; 

Laundry unit; 

Prayer hall; 

Walkways; 

Fully contained sewage management system and surface water drain system; 

Solid waste collection and disposal system; and 

Parking areas. 

Page 92: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 63 HPK

A separate liquid sewage disposal will be established for the construction campsite. 

Power will be supplied to the site via diesel generators. All contractor’s solid waste 

materials will be treated/disposed in on site waste disposal facilities or at an 

appropriate off‐site facility which must be approved from Sindh EPA. 

After the completion of construction the construction campsite will be rehabilitated to 

the original conditions as far as possible.  

e. Equipment 

The equipment typically used during construction of GPF/CPP will be: 

Survey sets; 

Dozers, loaders, dump trucks, cranes and trailers; 

Concrete mixers and asphalt plants; 

Pipe‐bending machines, cutting outfits, beveling machines, grinders, welding 

units, radiography equipment, sand‐blasting units, coating units and painting 

equipment; 

Excavators, thrust‐bore equipment and ditch pumps; 

Pipe‐layers, tractors, fuel trucks, service trucks, water tankers with sprinklers and 

crew vehicles; 

A water‐treatment plant, strainers, fill‐up pumps, hydrostatic testing equipment, 

temperature and pressure recorders, and air compressors;  

Generators; 

Communication equipment; 

Mobile maintenance units; and 

Warehouse storage units. 

f. Staffing 

The construction crew during the plant construction will comprise about 500 – 600 

personnel, out of which between 60 – 70 may be sourced from local communities 

depending upon their experience and skill levels particularly meeting Company’s 

competency criteria.  

g. Supplies 

The estimate includes water required for construction camps, sprinkling of roads and 

general construction activities. Water will be procured from existing groundwater 

wells and, in case of a shortfall, from other groundwater sources or UEPL’s newly 

installed water wells. 

Diesel will be the primary fuel during the construction phase, required for power 

generation, vehicles and equipment. The estimated average daily consumption of 

Page 93: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 64 HPK

diesel is 3,000 litres. Diesel will be procured locally and a tanker will be used to deliver 

it to the site. 

h. Construction Material Sourcing 

During the construction of GPF/CPP, material such as the steel, cement, sand and 

aggregates for road and pavement construction will be required. Pavement material 

will be obtained from regional quarries. 

i. Waste Streams 

The primary source of emissions to air during construction activities will be diesel 

engine‐driven generators’ exhaust. Other emission sources include construction 

machinery and vehicles exhaust emissions. Dust from the construction activities and 

movement of vehicles will be the other main source of air emissions.  

Black and grey water will be first sent to septic tank (made of concrete/impermeable 

material) and then to soaking pit. Whereas, recycling or reuse of waste material is the 

preferred option. However, where that is not possible, waste will be treated and 

appropriately disposed of as per UEPL’s policy and other legal and contractual 

obligations. 

j. Site Restoration 

On completion of the construction phase, the temporary infrastructure will be 

decommissioned and sites restored. This will involve: 

Removing the temporary construction camp; 

Reinstating the pipeline route back to the original condition; 

Closing all the temporary waste pits; and 

Leveling and restoration of borrow areas. 

The average water requirement during construction is estimated to be 150 m3. 

Associated Development Activities

Other associated development activities proposed may include but not limited to: 

Development of remote facilities; 

Up‐gradation/Modification of existing facilities; 

Relocation of existing facilities e.g. decommissioning of plant equipment and 

relocation to other location within project area; 

Construction of additional residential camps; and 

Decommissioning and site restoration of surface facilities. 

Where the category of the proposed activity is same, mitigation measures suggested 

for the broader category will be applicable.  

Page 94: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 65 HPK

Noise, Wastes and Emissions

4.7.1 Noise

Sources of noise during core activities i.e. seismic, drilling, construction and operation 

of flow line and establishment of processing facility i.e. GPF/CPP are listed below: 

a. Seismic 

Operation of generator at seismic base camp; 

Movement of light and heavy vehicles; 

Noise and vibration due to operation of vibroseis; and 

Drilling activity especially with Jackrobs (only if used). 

b. Construction (all activities including GPF/CPP) 

Operation of generator at construction camps; 

Movement of light and heavy vehicles; and 

Construction works at the well site and rig camp, along access road and RoW of 

flow line/s. 

c. Drilling 

Operations of generators at the rig camp; 

Drilling and operation of generators at the well site; 

Movement of vehicles; and 

Operation of generator at the maintenance/construction base camp. 

d. Laying of Flow Line/s 

Operations of generators at the base camp; 

Sand blasting; and 

Movement of light and heavy vehicles for the operation. 

Noise from generators will be minimized by regular maintenance and keeping them 

within enclosures. Noise from vehicles, dozers and vibroseis will be minimized by 

regular maintenance and reducing effects of project activities on environmental 

receptors by maintaining minimum safe distances. Regular monitoring will also be 

carried out in accordance to all applicable laws. 

4.7.2 Wastes and Effluents

Categories of wastes generated during proposed exploration and associated 

development activities in Kotri North Block and their proposed methods of disposal 

are discussed below: 

Clinical wastes – These will be stored separately from other wastes and sent to an 

offsite commercial or provided to a Sindh EPA’s approved waste contractor. 

Page 95: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 66 HPK

Combustible wastes – Combustible wastes will include kitchen wastes, paper, 

packaging material etc. It will be stored separately in waste segregation containers. 

Thereafter all combustible wastes will be provided to the approved waste 

contractor for appropriate disposal. All kind of food waste will be buried properly. 

Composting can also be exercised for leftover food. 

Recyclable or re‐usable wastes – These will include used oil, glass, tin, metals, 

workshop wastes etc. It will also be stored separately in waste segregation 

containers. All recyclable wastes will be collected by an approved waste contractor 

for recycling or re‐use. 

Drill cuttings and mud – A Water Based Mud (WBM) will be used during drilling. 

The drill cuttings and WBM will be stored at the well site in lined pits. The drilling 

mud will be allowed to evaporate inside the mud pit. The drill cuttings will also be 

allowed to dry out. After that, the mud pit and the cuttings pit will be backfilled. 

Sprinkling of untreated excess wastewater used for drilling purposes will not be 

allowed. Sprinkling of treated wastewater will only be done if meeting 

NEQS/SEQS. 

Sewage Treatment Plant (STP) shall be preferred for handling of black/grey water 

under BATNEEC/BAT, but in case of unavailability of STP, septic tank and soak 

will be provided. Septic tank and soak pit will be covered properly to avoid any 

obnoxious smell or environmental nuisance in surrounding areas.  

In case if septic tank gets filled with sludge, septic tank shall be emptied through 

vacuum truck and material shall be transferred to treatment facility or approved 

municipal drain. 

The wastewater and the amount of solid waste expected to be generated as a result of 

the proposed project activities is provided in Table 4‐2. 

4.7.3 Emissions

Emissions during seismic, construction including GPF/CPP, drilling and flow line 

laying/tie‐in/wellhead works will include: 

Dust emissions during seismic operation – Clearing of seismic lines with the use of 

dozer may result in dust emissions within the area of operation. Dust will not be 

generated due to use of vibroseis and flush or uphole drilling. However, use of 

Jackrobs (if used) will generate dust, but its extent will be limited to its immediate 

surrounding and fairly occupational in nature. Use of proper PPEs by the workers 

(dust masks and safety goggles etc.) will be ensured. 

Dust emissions during construction (all activities including GPF/CPP) – These will 

be controlled by proper water sprinkling and good construction management.  

Dust emissions during road travel (all activities) – These will be controlled by 

avoiding off‐road travel, observing speed limits and tracks maintenance on regular 

basis. 

Page 96: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 67 HPK

Exhaust emissions from light and heavy vehicles, construction equipment and 

machinery and generators – These will be controlled by proper maintenance 

(exhaust emissions from these sources generally meet the NEQS/SEQS). 

Emissions during flaring and H2S release during drilling and testing – The effects 

of these emissions will be controlled by maintaining a safe distance of 300 m from 

communities and adhering to emergency response plans in case of H2S release. 

Fugitive emissions – The effects of these volatile organic content (VOC) emissions 

will be controlled by maintaining safe distances. High concentration levels will be 

regularly checked/monitored as part of safety program. During operation, areas 

with higher concentration levels will be identified and appropriately mitigated. 

Page 97: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 68 HPK

Table 4‐1: Summary of Water Usage during Various O&G Project Activities 

Parameter  Ratea

Seismic Operation 

Domestic water usage    Approximatley 200 liters per capita 

per day 

Upholes  8,000 liters per hole 

Flush drilling  4,000 – 5,000 liters per hole 

Flush drilling (shallow waters)  None 

Construction of well site  80,000 b liters per day 

Drilling Operation   

Domestic and Drilling  150,000c liters per day 

Laying of Flow Line/Tie‐ins  

Domestic water usage   Approximatley 150 liters per capita 

per day 

Hydrocarbons Processing Facility  

Construction and domestic  150 m3 

Notes: 

a: The values have been taken from various seismic, construction and drilling operations 

b: The values are for total consumption of water for domestic and construction purposes. Usually construction and 

domestic activities takes up to 80%, and 10% respectively of the total water consumption with the remaining 

amount of water being used for sprinkling purposes. 

c: The values are for total consumption of water for domestic and drilling purposes. Usually drilling and domestic 

activities takes up to 60%, and 40% respectively of the total water consumption. 

Page 98: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 69 HPK

Table 4‐2: Summary of Approximate Domestic Wastewater and Solid Waste 

Parameter  Generation 

Domestic Wastewatera   

Seismic operation (litres per capita per day)  160 

Construction of well site (litres per day)  6,400 

Drilling operation (litres per day)  32,000 

Laying of flow line (litres per day)  5,400 

Construction of GPF/CPP (m3)  20 

Other Wastes (per month)a

Seismic Operation   

Recyclable solid waste generation (kg)  308 

Oil waste produced (litres)  104 

Food waste generation (kg)  150 

Others/Hazardous waste (kg)  18.2 

Construction Phase (Well Site)   

Recyclable solid waste generation (kg)  98 

Oil waste produced (litres)  9 

Food waste generation (kg)  210 

Others/Hazardous waste (kg)  3 

Drilling Phase   

Recyclable solid waste generation (kg)  2,585 

Oil waste produced (litres)  560 

Food waste generation (kg)  620 

Others/Hazardous waste (kg)  14 

Wellhead Surface Facility/Flow Line Construction  

Recyclable solid waste generation (kg)  279 

Oil waste produced (litres)  12 

Food waste generation (kg)  160 

Others/Hazardous waste (kg)  3 

Construction of Processing Facility   

Recyclable solid waste generation (kg)  5,690 

Oil waste produced (litres)  1,700 

Food waste generation (kg)  1,350 

Others/Hazardous waste (kg)  42 

Notes:  

a: Values have been calculated based on HPK environmental monitoring record for various O&G project activities.

Page 99: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 70 HPK

Figure 4‐1: Anatomy of a Rotary Land Drilling Rig 

 

Page 100: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 71 HPK

Photographs: Proposed 2D & 3D Seismic Operation (HPK Library) 

Photograph 4‐1: A view of typical seismic base 

camp  Photograph 4‐2: A veiw of seismic support 

camp 

Photograph 4‐3: Uphole drilling by vehicle 

mounted rig  Photograph 4‐4: Vibroseis moving on a seismic 

line 

Photograph 4‐5: Drilling of deep hole through 

buggy in progress  Photograph 4‐6: Jackrob drilling 

Page 101: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 72 HPK

Photograph 4‐7: Loading of explosives in a shot 

hole  Photograph 4‐8: A loaded shot hole 

Photograph 4‐9: Seismic base camp parking 

area  Photograph 4‐10: A veiw of explosive magazine

Photograph 4‐11: Seismic cable crossing on a 

road  Photograph 4‐12: Recording truck 

 

Page 102: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 73 HPK

Photographs: Proposed Drilling & Associated Construction Activities  

(HPK Library)  

 

Photograph 4‐13: A view of land drilling rig in 

operation  

Photograph 4‐14: A view of typical drilling rig 

camp 

 

Photograph 4‐15: Dozer at work on access track  Photograph 4‐16: Gravel leveling with grader

on well site 

 

Photograph 4‐17: Generators at well site    Photograph 4‐18: Water storage pit on well site 

Page 103: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 74 HPK

 

Photograph 4‐19: A view of lined drill cutting 

pit at well site  

Photograph 4‐20: Properly bunded diesel 

storage area with loading and unloading pad 

 

Photograph 4‐21: Properly barricaded food 

burial pit  

Photograph 4‐22: Construction of septic tank at 

well site 

 

Photograph 4‐23: Installation of conductor pipe 

at well site  

Photograph 4‐24: Installation of BOP in 

progress 

Page 104: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 75 HPK

Photographs: Lying of Flow Line/Tie‐in Works and GPF (HPK Library) 

 

Photograph 4‐25: Dozer working on RoW    Photograph 4‐26: Offloading of pipes on RoW 

 

Photograph 4‐27: Flow line placed along RoW Photograph 4‐28: Clamping of flow line before 

welding 

 

Photograph 4‐29: Burial of flow line in trench   Photograph 4‐30: Working on flow line at 

wellhead 

Page 105: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 76 HPK

Photograph 4‐31: Typical view of CPP Photograph 4‐32: Typical styled condensate 

storage at GPF 

Photograph 4‐33: Typical lined evaporation 

pond 

Photograph 4‐34: Typical pipe yard at GPF

Page 106: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 77 HPK

5 Analysis of Alternatives

Introduction

An analysis of available alternatives to the proposed exploration and associated 

development activities as described in Chapter 4 of this EIA have been carried out in 

this section to ensure that the best possible management and technological options are 

going to be employed during proposed project implementation. The analysis of 

alternatives has been discussed under two separate headings, management 

alternatives and technological alternatives. 

Management Alternatives

5.2.1 No Project Option

Energy is the prime mover of current day economies and is vital to the sustenance of 

economic growth, which depends crucially on the long‐term availability of energy 

from sources that are accessible, sustainable, affordable, and environment friendly. 

The energy sector plays a key role in the development and growth of Pakistanʹs 

economy. Through its history, Pakistan’s economy has paced an unsteady path with 

extended phases of low growth following moderate stints of high growth. If one looks 

at the pattern of energy supplies, Pakistan has remained an energy deficit country, 

dependent upon imports, mostly oil & oil products. 

During the Fiscal Year (FY) 2017‐18, the primary commercial energy supplies have 

increased from 80 to 86 million tonnes of oil equivalent (MTOE). The increase was in 

coal (68.5%), LNG (68.2%), renewable electricity (44.6%), nuclear electricity (41.2%), 

imported electricity (11.9%) and LPG (4.5%) as compared to last year. Consequently, 

the overall primary commercial energy supply mix during 2017‐18 was increased by 

8.4% than the previous year (2016‐17). The share of each energy commodity in primary 

energy supplies for 2017‐18 was: Oil – 31.2%, Gas – 34.6%, LNG import – 8.7%, LPG – 

1.2%, Coal – 12.7%, hydro‐electricity – 7.7%, nuclear electricity – 2.7%, renewable 

electricity sources – 1.1% and imported electricity – 0.1%. Primary energy supplies by 

source are provided in Figure 5‐1 & 5‐2. 

The annual growth rate of final energy consumption was enhanced considerably by 

9.7% and reached to 55 million tonnes of oil equivalent during 2017‐18 due to major 

increase in consumption of industry, agriculture and transport sectors. Final energy 

consumption by source & sector are shown in Figure 5‐3 & 5‐4 respectively. 

Local crude oil production moved up slightly by 0.9% from 88,409 barrels per day in 

2016‐17 to 89,197 barrels per day in 2017‐18, while the natural gas production 

decreased slightly by 0.9% from 4,032 MMCFD in 2016‐17 to 3,997 MMCFD in 2017‐18. 

Extensive activity was seen in the upstream sector where 45 exploratory and 36 

development/appraisal wells were drilled. The drilling efforts resulted in 14 

discoveries mostly of gas/condensate which needs to be continued.  

Page 107: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 78 HPK

The overall import of petroleum products was decreased by 11.9% as compared to the 

last year. Import of crude oil by the refineries was, however, increased significantly by 

19.3%. The import to aviation fuel (98.3%), motor spirit (8.1%) and HSD (1.3%) was 

increased. The import of petroleum products is decreased while the oil import bill 

increased from US $ 9.1 billion in 2016‐17 to US $ 11.9 billion in 2017‐18 due to increase 

in prices and increase in import of crude oil.  

The overall oil consumption during 2017‐18 decreased by 3.5% from 25.56 million 

tonnes to 24.68 million tonnes. Consumption of furnace oil decreased to 23.0% and 

kerosene 5.4%. However, consumption of HSD increased from 8.48 million tonnes to 

9.04 million tonnes (6.5%) and gasoline from 6.74 million tonnes to 7.51 million tonnes 

(11.5%). Whereas, natural gas consumption increased from 1,377,307 MMCft to 

1,454,697 MMCft (5.6%). Similarly, RLNG import also increased from 186,672,977 

MMBtu to 313,902,345 MMBtu (68.2%). Gas consumption in power sector increased 

from 446,941 MMCft to 544,654 MMCft (21.9%). As per available information, Kotri 

North Block is conducive to natural gas production hence, sharing the accumulative 

gas production of the Sindh province. Natural gas production by type/province is 

provided as Figure 5‐5 and consumption of natural gas is by sector is shown as Figure 

5‐6.  

Pakistan’s economy has been growing at an average growth rate of almost 5.5% and 

demand of energy is increasing rapidly. A number of contemporary studies indicate 

that Pakistan’s primary energy demand is expected to grow at an ACGR of between 

4.37 to 6.09 percent over the next 15 years, depending upon the projected GDP growth, 

and is likely to be in the range of 116 to 148 MTOE by FY 2022. 

As indicated above, Pakistan spends billions of dollars on the import of crude oil and 

other petroleum products and as a result total import bill is rising for every 

consecutive fiscal year. To reduce this loss of foreign exchange the government is 

committed to maximum replacement of imported furnace oil and diesel oil with 

indigenous natural gas. 

In view of Pakistanʹs current balance of payment difficulties, it has become imperative 

for the country to explore indigenous resources in the energy sector, as a reliable 

supply of energy is crucial to the achievement of national development targets in the 

commodity producing sectors. Natural gas is a particularly attractive option as the 

environmental effects associated with its usage are also minimal in comparison to 

other fossil fuels. 

An oil or gas discovery in the area of operation will augment the present oil & gas 

supplies of the country and reduce Pakistanʹs reliance on imported fuel. In view of the 

above and high energy demand of the country ‘No Project Option’ seems to be a 

highly unfavorable option. 

Page 108: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 79 HPK

5.2.2 Alternative Site Option

Several concession areas and exploration sites exist on Pakistanʹs map and a number of 

national and international companies are actively engaged in oil & gas exploration and 

production in the country in addition to the public sector agencies. 

As exploration activities involve large investments, the area of the operation is 

carefully selected after assessing that the geological characteristics conducive to the 

presence of hydrocarbon reserves are present in the area. Kotri North Block seems to 

be an attractive area for hydrocarbon exploration in Pakistan due to the fact that 

various successes of discovering hydrocarbon reserves during past drilling operations 

e.g. Unarpur‐1 ST‐1 in 2018. Adjacent concession e.g. Kotri Block (2468‐12) also have 

potential for hydrocarbon reserves. A recent discovery at exploratory well Yasar X‐1 is 

made in 2018. In addition to above, there are also operational hydrocarbon processing 

facilities in the nearby areas i.e. Shahdadpur (PPL), Tando Adam (PPL) and Badin 

(UEPL). In the above context, an operation in any other area may not be fruitful. 

Furthermore, strict adherence to the mitigation measures proposed by the EIA will 

ensure that any residual impacts on the forest protected areas are reversible, short 

term and insignificant. 

Proposed seismic survey in the region will verify and authenticate the potential for oil 

and gas reserves and to rightly identify suitable surface locations for drilling of wells 

in the subsequent phase of exploration and development phase. Moreover, in case of 

discovery/success, flow line will be laid to existing or newly established processing 

facility further to distribution network.   

5.2.3 Timing of the Operation

The proposed exploration and associated development project have to follow strict 

project schedule in order to meet production targets and to reduce national gas 

shortage for supporting the countryʹs economy. Restrictions on the timing of the 

proposed operation may be deemed necessary if the operations are significantly 

affecting the breeding of key wildlife species in the area. On the basis of assessment of 

the impacts done in the EIA any restrictions on timing should necessarily be 

considered as significant core habitats for the breeding of key species were also 

identified in the project area. Wetlands of the project area are visited by migratory 

birds and in addition to core habitats of some famous mammals i.e. Hog deer, Fishing 

cat, Smooth coated otter, Desert cat, Indian/Bengal fox and Indian pangolin. Famous 

game birds i.e. Grey partridge and Black partridge are also key species of the area. 

Therefore, the EIA has recommended measures to minimize the duration of activities 

within key wildlife areas/habitats and maintain minimum safe distance from sensitive 

& fragile environmental receptors.  

Technological Alternatives

5.3.1 Seismic Data Acquisition Technologies

Proposed seismic data can be acquired using the following methods:  

Page 109: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 80 HPK

Upholes; 

Deep shot hole survey; 

Shallow shot hole survey; 

Surface shots; and 

Vibrating energy sources. 

The selection of any of these sources is dependent on the quality of data, time, cost, 

land type and environmental sensitivity of the area. Care has to be exercised in 

selecting the method to ensure that geophysical data of the highest possible quality is 

collected with least possible impacts on the environment. It is important to mention 

that major part of Kotri North Block is already covered under 2D/3D seismic coverage 

however, to be more certain for selection of a well drilling, seismic activities including 

2D/3D are also proposed for the project.  

Only cables and geophones will be laid across the surface water bodies for data 

acquisition. For the rocky and sandy plains the technological options are vibroseis and 

shallow holes. In agricultural lands there is a choice between the use of dynamite and 

vibroseis as an energy source. The use of vibroseis in agricultural lands was not 

considered as a preferred option as it would involve land clearing along the seismic 

lines.    

Whereas, upholes provide highest data quality, they may pose greater environmental 

impacts if used as the only technology due to operation of heavy drilling rigs, use of 

water and the need to develop access track. Deep holes and shallow holes required for 

dynamite acquisition have comparable environmental acceptability, though deep 

holes outrank shallow holes in terms of quality of data obtained, staffing requirements 

and the total time required to complete the operation. In order to obtain high quality 

data keeping due regard for the environment, a combination of vibroseis and 

dynamite has been selected for the operation. The location of upholes will be carefully 

selected to minimize the preparation of new tracks and the location of deep holes has 

been set at every 50 m to minimize the amount of drilling in the area. Combination of 

vibroseis and dynamite sources will enable UEPL to obtain the desired quality of data 

with the least possible impacts on the existing environment. 

5.3.2 Drilling Technique

Conventional rotary drilling proposed by United Energy Pakistan Limited has been 

historically used for the drilling of oil and gas wells. Other drilling techniques include: 

Coiled tubing; and 

Slim holes. 

Despite some environmental gains in the use of coiled tubing and slim holes (reduced 

well site area and reduced waste volumes etc.) both techniques seem to share a 

number of technical disadvantages and operational limitations. Moreover, the rigs are 

not available in Pakistan and in case of a breakdown required backup and service 

Page 110: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 81 HPK

facilities may not be available as readily as for conventional rigs. Advantages of the 

two techniques therefore, do not outweigh their disadvantages. Conventional drilling 

technique proposed by UEPL is therefore evaluated to be the best alternative. 

5.3.3 Drilling Mud

Generally, two broad categories of mud are used for drilling of oil or gas wells i.e. oil 

based and water based. Oil based mud is formulated by mixing chemicals with diesel. 

This mud is not considered to be environment friendly due to the risk of 

contamination of subsurface formations during drilling and the generation of oily 

drilled cuttings which require specialized handling and treatment. A water based mud 

system will be used which due to the abovementioned reasons has environmental 

preference over oil based mud and is therefore considered to be the preferred 

alternative. 

For proposed seismic activity, as highlighted in Section 4.1.3 of Chapter 4, due to 

loose soil material wherever, expected in the area the holes during drilling will be 

flushed with bentonite mud. The bentonite mud will be prepared near the shot point 

in a 2 m square and 0.5 m deep earthen pit. Water tankers will transport water 

required for the preparation of the mud. These water tankers will travel only on 

existing tracks. In case an existing track does not reach to a shot point, the tanker will 

stop on the track at a position nearest to the shot point, from thereon water will be 

transported by means of hose pipes connected to the tanker.  

The spent drilling mud and cuttings will be stored inside a similar earthen pit. The 

spent mud and cuttings will be allowed to dry after which the pit will be backfilled 

with at least 15 cm of top soil cover. The pits will be clearly marked until restored. 

Since, bentonite is a type of clay and a non‐hazardous material, burial of the mud and 

cuttings on site will not contaminate soil or groundwater. No other type of mud is 

planned to be used by UEPL during the proposed seismic operation in project area. 

5.3.4 Disposal of Drilling Wastes

Conventional drilling waste management involves discharging the mud and cuttings 

into a lined waste pit (HDPE lined). UEPL after a review of various waste 

management alternatives has started using a cuttings segregation and fluid recovery 

unit in which the cuttings segregated by the shale shakers and processed through 

centrifuges and Hi‐G dryers. This allows: 

Additional drying of the cuttings making their disposal into the lined waste pit 

easier; 

Recovery of the excess mud associated with the cuttings. The mud can be re‐used 

thereby reducing the overall water consumption and chemical usage for mud 

formulation; and 

Reduction in the size of the waste pit due to the reduction in the mud content 

associated with the cuttings and due to less water consumption and mud 

formulation. 

Page 111: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 82 HPK

The waste management system is considered to be technologically and 

environmentally the most preferred option. The drill cuttings and mud will be 

disposed of at the well site within lined waste pits. Other options such as 

bioremediation, incineration, re‐injection or landfill are either not applicable to the 

type of waste or their cost or technical and management disadvantages outweigh the 

little benefits that they may have. 

5.3.5 Alternative to Flow Lines

After the successful drilling of well and discovery of hydrocarbons, hydrocarbons 

need to be processed before it enters into distribution network for ultimate 

consumption. Pipelines are the best available option however, transmission pipeline 

safety regulators and operators have expressed mutual interest in demonstrating the 

effectiveness of In‐Line Inspection methods for better risk evaluation and management 

of pipeline safety as an alternative to hydrostatic testing in the cases where safety can 

be verifiably maintained. Hydrostatic testing can result in substantial costs, occasional 

disruptions in service, and substantial emissions due to the routine evacuation of 

natural gas from pipelines prior to tests. Allowing alternatives to hydrostatic testing 

(including In‐Line Inspection technologies), combined with research and 

development, could help to drive innovation in pipeline integrity testing technologies 

and eventually lead to improved safety and system reliability. 

5.3.6 Gas Processing Facility

Natural gas (also called fossil gas) is naturally occurring hydrocarbon gas mixture 

consisting primarily of methane, but commonly including varying amounts of other 

higher alkanes and sometimes a small percentage of carbon dioxide, nitrogen, 

hydrogen sulphide or helium. It is formed when layers decomposing plant and animal 

matter are exposed to intense heat and pressure under the surface of earth over 

millions of years. The energy that the plants originally obtained from the sun is stored 

in the form of chemical bonds in the gas.  

In petroleum production gas is sometimes burned as flare gas. Before natural gas can 

be used as a fuel, most, but not all, must be processed to remove impurities, including 

water, to meet the specifications of marketable natural gas. The by‐products of this 

processing include ethane, propane, butanes, pentanes and higher molecular weight 

hydrocarbons, hydrogen sulfide (which may be converted into pure sulfur), carbon 

dioxide, water vapours and sometimes helium & nitrogen. Because of these properties, 

natural gas is receiving attention as low‐carbon, eco‐friendly alternative fuels.  

It is the major energy source of our country for both domestic and industrial 

operations. Natural gas processing plant converts gas reservoirʹs raw natural gases to 

produce sales gas, which is highly demanded commodity in the market. Sales gas 

specification typically required processed gas with small amount of water to avoid 

pipelines corrosion, avoid hydrates formation in the gas and for their immediate 

industry consumption. The plant is equipped with gas dehydration system facilities to 

absorb water from raw gas and most of the gas dehydration processes are using tri‐

Page 112: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 83 HPK

ethylene glycol (TEG) process unit. Therefore, gas processing plant with appropriate 

capacity is the best solution for the purpose. 

5.3.7 Water Abstraction

Water is without any doubt one of the most undervalued resources on earth. Globally, 

there is increasing pressures on water resources. In particular, population growth and 

economic development are putting pressure on available freshwater resources. Water 

quality is inextricably linked to human health in many ways and poor water quality 

can lead to diseases, reduced food availability and malnutrition. Improved access 

to fresh water has a direct positive impact on people and communities leading to 

significant social, economic and environmental benefits.  

The two primary options for obtaining water for project needs are: 

Surface water 

Groundwater 

Existing local wells – Existing local wells may be used during proposed exploration 

and associated development project activities, if these show sufficient capacity to meet 

the project water requirements. Only those local wells will be used which show an 

excess capacity of water above the local requirements (domestic and irrigation) and 

flow rate from these wells will be monitored during the operation to monitor any 

effect. The local wells located close to the existing irrigation network have sufficient 

quantity of water and does not show any significant drawdown. 

New water wells – There is also a possibility that depending on the requirement for 

proposed exploration and associated development activities, United Energy Pakistan 

Limited may install new water wells in an area where availability of groundwater is 

confirmed. However, this option will be considered if taking water from the existing 

water wells in project area is not feasible due to long haul distance or constraints. Use 

of brackish water for proposed project activities should be maximized wherever 

possible and feasible. 

During proposed exploration and associated development, under unavoidable 

conditions like long haul distances, unavailability of tube wells in the proximity of 

project area etc. limited water abstraction from seasonal watercourses will be allowed 

after getting a formal approval from the concerned department and conditional 

approval in the form of third order Change Management Statement (CMS) from IMC. 

Page 113: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 84 HPK

Source: HDIP Year Energy Book, 2017‐18 

 

Figure 5‐1: Primary Energy Supplies by Source with ACGR  

Source: HDIP Year Energy Book, 2017‐18  

Figure 5‐2: Primary Energy Supplies by Source

Page 114: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 85 HPK

 

 

 

 

 

 

 

 

Source: HDIP Year Energy Book, 2017‐18 

 

Figure 5‐3: Final Energy Consumption by Source  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Source: HDIP Year Energy Book, 2017‐18  

Figure 5‐4: Final Energy Consumption by Sector

Page 115: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 86 HPK

Source: HDIP Year Energy Book, 2017‐18 

 

Figure 5‐5: Natural Gas Production by Type/Province  

 

 

 

 

 

 

 

Page 116: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 87 HPK

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Source: HDIP Year Energy Book, 2017‐18  

Figure 5‐6: Natural Gas Consumption by Sector 

 

Page 117: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 88 HPK

6 Background Environment

In order to assess the potential environmental impacts of proposed exploration and 

associated development activities (details are provided in Chapter 4) may have on the 

environment of the area and to propose mitigation measures a detailed understanding 

of the background environment of Kotri North Block (E.L. 2568‐21) including physical, 

biological and socioeconomic environment has been established and provided in this 

chapter. 

Physical Environment

In this sub‐section, physical environment including the physiography, geology & soils, 

seismicity, climate, water resources (surface & groundwater), noise and air quality of 

the project area and its surroundings is discussed in detail. 

6.1.1 Physiography

The Kotri North Block lies in the southern part of the Sindh province and is mostly 

covered in the Indus Delta covering parts of Jamshoro, Hyderabad and Matiari 

districts. District Jamshoro contributes the major part followed by district Matiari and 

Hyderabad. 

As a whole, Jamshoro district may be divided into three parts which are entirely 

dissimilar in character namely: 

The Kohistan or hilly area; 

The barrage zone; and 

The low lands riverine area. 

For instance, taluka Kotri of Jamshoro district has a major part within Kotri North 

Block. Overall, taluka Kotri has sandy plains and a barren rocky terrain to traverse. 

Small hills, nais and dhoros (perennial rivers) add beauty to the landscape. Collectively, 

the Kohistan region consists of a range of limestone hills, known as Kirthar Range. It 

extends along the whole western boundary of the district. In Sehwan taluka it spread 

out and approach Lakhi hills, which start near Sehwan and run south along the 

western boundary of the district therefore most of the Sehwan taluka area is hilly in 

general.  

Hyderabad district is the part of the lower Indus plain conformed of vast alluvial 

along the course of the Indus River. The Indus bifurcates the district of Jamshoro from 

Hyderabad and stretches the western flanks of the district and is surrounded by 

riverine forests. There are no mountains or hills anywhere in the districts except some 

small hillocks and off shoot of Kirthar limestone (of middle Eocene) range known as 

Ganjo Takkar located in Hyderabad district. They run parallel to the river Indus for 

about 22 km south of Hyderabad city. The highest point in these hillocks is known as 

“Gaho” which is about 75 m above mean sea level (msl). There are also two small 

Page 118: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 89 HPK

hillocks on the north of Tando M. Khan town. They are named Budhaka Takkar. The 

rest of the district is a fertile plain with an average elevation of about 50 m above msl. 

Overall, the north western area of the Kotri North Block is a hilly tract known as 

Kohistan tract. These hills are the extension of the Kirthar Range. It has been described 

as succession of broad valleys laying between ranges of hills running generally north 

and south. The valleys are more or less level and fairly covered with grass or 

brushwood. The hills are bare and mostly composed of limestone. Southwards the 

area degenerates into sandy formations, uncultivated and almost devoid of vegetation, 

but much broken up by short ranges of low, stony hills and intersected by nais (locally 

called meaning torrent beds) which carry the drainage of the Kohistan to the Indus. 

6.1.2 Geology & Geomorphology

The Indus Delta is formed as a result of sediment trapping of the river Indus into the 

Arabian Sea for millions of years. The geological history of the river Indus is 

associated with the rapid tectonic uplift in the region which has led to the formation of 

Himalayan Mountains. The geology of Hyderabad district comprises of sedimentary 

and volcanic rocks which is quaternary in nature. The district has loamy and clayey 

part saline floodplain soils of the arid zone. 

Kotri North Block is majorly covered under the Eocene sedimentary and 

unconsolidated surfical deposits of silt, sand and gravel geologic formations belonging 

to the Tertiary and Quaternary ages respectively. The area is also rich in coal deposits 

with the coal field being explored currently for coal reservoirs. Coal is associated with 

basal part of laterite where a sequence of lateritic clay and shale with beds of 

arenaceous sandstone of Laki Formation, named as Sonhari member of early Eocene 

age is found. Laki formation attains a thickness of 55 m near Thatta however, the later 

sequence of Laki Formation is mainly composed of nodular limestone with shale and 

sandstone. The Sonhari coal is of poor quality lignite with high Sulphur. Sonhari 

member varies in thickness from 10 – 30 m. The meting limestone and Shale member 

consists mainly of creamy white nodular limestone with subordinate sandstone in the 

upper part. The shale is grey, greenish yellow, weathering dark rusty brown 

ferruginous and gypsiferous. The limestone is thin bedded and arenaceous whereas 

the sandstone is commonly ferruginous. Meting member is about 70 m thick at the 

type locality (Siddiqui, 2007).  

6.1.3 Stratigraphy

The Kotri North Block is located in southern Indus basin and over lower Indus trough 

and Nabisar slope. The project area under consideration for EIA is predominantly 

located over the lower Indus trough. The general stratigraphy of the lower Indus basin 

is comprised of Pliocene Swaliks up to Jurassic carbonates. The stratigraphic sequence 

change drastically from the west to the east. The Pub, Mughal Kot and Parh formation 

of the Cretaceous age pinch out in the eastern lower Indus basin. 

Page 119: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 90 HPK

6.1.4 Soils

Clay and sand are principal ingredients of the soil of Kotri North Block and one of the 

two factors by which the composition of the various soils is differentiated is the extent 

to which the clay or the sand predominates. 

The soil of Kotri North Block is mostly loamy and clayey soil with patches of gravely 

land and salt as well as seasonally affected soil. In some places of the block, the soil of 

is mostly loamy with seasonally flooded soil. According to Soil Map of Sindh, Survey 

of Pakistan, soil types in Kotri North Block is provided below: 

Rough mountain land; 

Gravelly land and rock land;  

Loamy soil; 

Clayey soil;  

Seasonally flooded soil; and 

Salt affected soil. 

The texture of soils in the project area ranges from loamy saline, silty to gravely, 

mainly loamy and clayey soils in the inland areas. The soil in the project area, 

especially those areas covered under the lower Indus basin consists mainly of loamy 

and clayey soils. 

These soils have little or no salinity (0 to 4dSm‐1) and are moderately alkaline (pH of 

7.9 to 8.4). The soils are generally non‐saline, non‐sodic except local saline patches in 

inter‐dunal valleys and some parts of the alluvial plain. 

6.1.5 Land Capability

Different land use potentials were identified on the basis of their characteristics or on 

the basis of other external limiting factors such as aridity and erosion etc. The potential 

land use for the soil regimes within the Kotri North Block has been identified in this 

study using the map of Land Capability for Sindh, Survey of Pakistan. This 

classification is expected to help in the management of soils in the area and for further 

planning on land use within the project area. Classes of land capability in Kotri North 

Block falls in Class I, II, III, VII and VIII. Description of these classification of land 

capability is presented below: 

Class I – Very good (loamy) irrigated crop land; 

Class II – Good (predominantly clayey) irrigated crop land; 

Class III & VII – Complex of mainly moderate flood‐watered crop land and some 

poor (sandy) grazing land; 

Class VIII – Agricultural unproductive open water and marsh. Agricultural 

unproductive (mountainous) land; and 

Page 120: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 91 HPK

Class VIII & VII – Complex of agricultural unproductive (rock) land and some 

poor grazing (gravely) land. 

6.1.6 Petroleum Play

The early Cretaceous shale of the Sembar Formation are the source rocks which 

charged the hydrocarbon pools on the Thar slope and the Karachi trough. The close 

vicinity of the block to the petroleum producing province and the lateral continuity of 

the early Cretaceous Lower Goru clastics ensure the presence of good quality reservoir 

horizons in this basin. The prospective play types comprise the tilted fault blocks and 

associated rollovers. 

6.1.7 Seismicity

Based on the seismic zoning map of Pakistan issued by the Geophysical Centre Quetta, 

the entire Kotri North Block falls under Zone 2A with minor to moderate damage 

category of earthquakes and a ground acceleration level of 0.08 to 0.16 g. Seismic map 

of the Kotri North Block with respect to other seismic zones of Pakistan is shown in 

Figure 6‐3. 

6.1.8 Climate and Meteorology

a. Climatic Classification 

The climate of the entire Kotri North Block is intensively hot in summer and cold 

enough in winter. The salient feature of climate is the high variability in temperature 

in different areas within the project area. Shamshad (1956) has classified the climate of 

Pakistan on the basis of characteristic seasons found in the country. Taking into 

account topography, proximity to the sea, rainfall, temperature and winds, Shamshad 

has defined eleven climatic zones for Pakistan. Under his scheme, the climate of the 

project area is classified as ‘Subtropical Double Season”, which may further be 

subdivided into hot land and coast land. The characteristic features of hot land 

climatic zone is low rainfall, (less than 250 millimeters per annum) absence of a well‐

defined rainy season, and high temperatures that increase from east to west. Whereas, 

features of the coast land climatic zone include occurrence of afternoon sea breeze, low 

rainfall (less than 250 mm per annum) with moderate and high temperatures in coastal 

and inland areas respectively. 

Rasul and Chaudhry (2004) classified the climate of Pakistan on the basis of moisture 

index. They reported that two third of the country has arid to semiarid climate type. 

According to them most of the southern half lies under arid climate thus Kotri North 

Block as well which falls into Jamshoro, Hyderabad and Matiari districts of Sindh 

province. Average secondary meteorological data of Hyderabad district for last decade 

(2009 – 2018), which is broadly applicable to the entire stretch of Kotri North Block 

(E.L. 2568‐21) is presented in Table 6‐1 whereas, graphically shown in Figure 6‐1 and 

Figure 6‐2. Figure 6‐1 represents the average temperature in °C including minimum, 

maximum and average whereas Figure 6‐2 shows the average rainfall in mm, average 

humidity in % and average windspeed in kmph. 

Page 121: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 92 HPK

b. Temperature  

Interpretation of the available meteorological data shows that the Kotri North Block 

experiences extreme hot temperatures where mean daily maximum temperatures can 

go up to 48°C and even beyond due to the direction of sea breeze from west to east. 

According to available meteorological information, hottest months of the year are 

May, June and July. Coldest months of the year are December, January and February. 

The climate of the project area is extreme and is characterized by hot summers and 

moderately cold winters. The average temperature for the year stands at 29°C 

whereas, mean annual maximum and minimum temperatures remain above 42°C in 

June and above 13°C in January respectively. Table 6‐1 shows average monthly 

maximum and minimum temperature recorded during past decade i.e. 2009 – 2018 at 

PBO Hyderabad.  

c. Rainfall 

Available meteorological information shows that the average annual rainfall in the 

project area is only about 6 millimetres. Complete record of average monthly 

precipitation for last ten years (2009 – 2018) is also presented in the Table 6‐1. Project 

area is situated in arid and semiarid zone of Pakistan and hence, prone to drought. 

Careful analysis of met data shows that the wind in the project area during the past 

era was blowing from all four directions, but it now blows from one side only, which 

shows climatic change. Now the rains occur from the sea. These rains contain salt 

concentration that impairs the soil fertility/quality and cause water‐logging in 

agricultural zones of the project area. Due to lot of precipitation from oceanic origin, 

the land gets degraded which ultimately affects the crop yield in the area of influence.  

d. Relative Humidity  

Interpretation of available meteorological data shows that the area experiences 

relatively medium humidity. The average minimum humidity for last decade (2009 – 

2018) at Hyderabad was recorded during month of December which is 25.3% at 0000 

UTC and maximum humidity was recorded in month of May was 58.7% at 1200 UTC. 

e. Wind Speed  

Average wind speed in entire project area is very erratic. According to available 

information, wind speed of the project area could reach up to averagely 25 kmph in 

the hotter months of the years which ultimately generate high speed gusts however, in 

winter months the average wind speed remain in‐between 8 – 13 kmph. 

f. Sun Hours  

Available meteorological data (2009 – 2018) of Hyderabad district shows that average 

sun hours in January are around 258 hours whereas, during the peak summer time are 

around 387.2 hours (in May). Average sun hours of Hyderabad district is also 

presented in Table 6‐1. 

 

Page 122: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 93 HPK

g. Climatic Change 

Careful analysis of climatic conditions of the area reveals that annual rainfall may 

continue to increase during the coming years with a rate of 5% per decade subjecting 

this region to flooding risks. Various studies show that the winter rainfall is 

continuously decreasing with a significant rate by every passing year. However, the 

spring rainfall is continuously increasing while the summer (monsoon) rainfall rates 

show increasing trend while, the fall season indicates a continuous decreasing trend. 

As a whole, rainfall in winter and fall is on a decreasing trend, whereas spring and 

summer rains are increasing.  

From the temperature perspective it was revealed that annual average temperature is 

increasing globally by about 0.8° Celsius due to global warming and other 

contributing environmental factors. The duration of winters is decreasing slightly 

shaping a longer span for summers. 

6.1.9 Ambient Noise & Air Quality

a. Ambient Noise 

Sources of noise during proposed exploration and associated development activities 

will be generators, vehicles, drilling rig, flaring during well testing and construction 

equipment and machinery. These sources of noise can be categorized as short term 

and intermittent arising from proposed project activities. Increased noise levels during 

the operations although will not accumulate but can individually be a source of 

nuisance for locals and a source of disturbance to the existing wildlife. 

There are no continuous major sources of noise in the project area. Existing sources of 

noise in the project area are farm tractors & related equipment and vehicles. 

Considering the intermittent nature of these noise sources, it can be presumed that the 

noise pollution in the area is low.  

Ambient noise levels were monitored through Sound Meter 840029 and Garmin GPS 

etrex 10 and their results are shown in the Table 6‐3. Figure 6‐5 shows the sampling 

locations to record ambient noise levels in the project area. Noise monitoring locations 

were randomly selected during the field visit of the area in different habitats. On the 

basis of the investigation/results, it is concluded that ambient noise level in the project 

area is of low level. 

b. Ambient Air Quality 

Due to the absence of typical sources like industrial and heavy vehicular emissions of 

air pollution within Kotri North Block, the ambient air quality of the area may be 

regarded as pristine with respect to the presence of air borne pollutants. Dust storms 

or strong winds during summer generate limited dust emissions, vehicles travelling 

on existing road network in and adjacent areas also generate limited amounts of dust. 

These dust emissions, however, apart from being a nuisance, do not pose any threat to 

human health. Proposed exploration and associated development activities may be a 

source of dust emission but activities will be well planned/designed and every effort 

Page 123: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 94 HPK

will be made as recommended in this EIA to alleviate the adverse impact on 

environment, thus not significantly deteriorating ambient air quality.

6.1.10 Water Resources

a. Surface Water Resources 

The Kotri North Block lies in the Lower Indus Basin of Sindh province where surface 

hydrology is predominantly influenced by the Indus River. The lower Indus basin is 

drained mainly by the Indus River and its tributaries including various hill torrents 

from the west which flow only in the period of heavy rain from north to south‐west 

direction. 

Indus River & Associated Irrigation Network 

The Indus provides the key water resources for the economy of the area– especially 

the Breadbasket of Punjab province, which accounts for most of the nationʹs 

agricultural production and Sindh. The river also supports many heavy industries and 

provides the main supply of potable water in Sindh. The Indus is one of the few rivers 

in the world that exhibit a tidal bore. The Indus system is largely fed by the snows and 

glaciers of the Himalayas, Karakoram and the Hindu Kush ranges of Tibet, the state of 

Jammu and Kashmir and the Northern Areas of Pakistan respectively. The flow of the 

river is also determined by the seasons – It diminishes greatly in the winter, while 

flooding its banks in the monsoon months from July to September. There is also 

evidence of a steady shift in the course of the river since prehistoric times – It deviated 

westwards from flowing into the Runn of Kutch and adjoining Banni grasslands after 

the 1816 earthquake (wikipedia). 

The irrigation system of Sindh is entirely dependent on the Indus River for supplies of 

water downstream of the area. Riverine tract of the Indus River occupies a special 

significance in the ecology of Sindh. Expansion of agriculture and subsequent 

industrial development led to the need for conserving water for agriculture purpose 

and power generation through construction of reservoirs on the river Indus and its 

tributaries with associated irrigation canal networks. A number of dams, head works, 

barrages and diversion canals have been constructed on Indus River and its tributaries 

from 1886 to 1993. 

The first barrage on the river Indus was commissioned in 1932 (Sukkur Barrage) 

followed by Kotri (Ghulam Muhammad Barrage) and Guddu in 1955 and 1962 

respectively (Osmani, 2003). Irrigation canals from mainly Kotri Barrage (Ghulam 

Muhammad Barrage, 1955) and partly from Sukkur Barrage (1932) irrigate the project 

area. 

There are four feeders which originate from Kotri Barrage including Akram Wah, New 

Fuleli, Old Fuleli and Kalri Baghar (KB) feeder. KB feeder with command area 637,041 

square miles serves irrigation network in and near the project area. The water channels 

exist within the project area and close vicinities are Pannu canal, Khasino wah, 

Budhapur minor, Buhara distributary, Jam wah, Qubi minor and Sonda distributary. 

Page 124: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 95 HPK

b. Groundwater 

Generally, groundwater becomes saline downstream of Hyderabad. This is because of 

the recent shift (in terms of geological times) of the Arabian Sea which used to be 

further southwards until Hyderabad some 12,000 years ago. The areas with saline 

groundwater show higher concentration of chlorine compared to carbonates and 

bicarbonates suggesting that some millennia ago the area was submerged into 

seawater. 

Though meandering of the river Indus had diluted the brackish water, but 800 years of 

deserting by the Indus River had allowed saline water down below to displace fresh 

water of Indus River by various processes including seawater encroachment, surface 

water evaporation and dilution. Hydro‐geological investigations carried out by the 

Water and Power Development Authority (WAPDA) on the eastern side of the Indus 

River reveals that freshwater is available at shallow depths in Hyderabad district up to 

60 m. It becomes saline to highly saline as one moves south to the coastal areas. 

Groundwater occurs under water table condition at depths varying from 3 m to 10 m. 

Water resources map of Kotri North Block is provided in Figure 6‐4. 

c. Water quality 

Water quality analysis was carried out in the project area as part of the EIA study. For 

this purpose five water samples were taken from various sources being used by locals 

for drinking purposes. These sources include three hand pumps and two surface water 

samples. Out of these two surface water samples, one was taken from Indus River 

crossing the project area and water of the river is being consumed for drinking 

purposes by the local communities residing on the banks of the river. Sixteen (16) 

parameters were analysed in each sample and thereafter compared with Sindh 

Standards for Drinking Water Quality (SSDWQ). All these parameters of water play 

an important role, especially in determining its quality and suitability for intended 

use. The lab results are provided in Table 6‐2 and sampling location of water samples 

are also marked in Figure 6‐4. Based upon chemical analysis test results it may be 

concluded that water quality is not satisfactory for drinking purposes. 

At present, sources of water contamination are open defecation, uncontrolled disposal 

of domestic and livestock wastes, uncontrolled use of pesticides and chemicals in 

agricultural fields by local communities however, no quantitative analysis of the 

extent of this contamination is available.

Page 125: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 96 HPK

Table 6‐1: Meteorological Data of Hyderabad District, 2009 – 2018 

Month/Year  

Parameters

Average Temperature (°C) Avg. Rainfall in 

mm 

Humidity in 

Avg. Wind in 

kmph 

Avg. Sun 

hours   Maximum  Minimum Average

2009 

Jan  25  14  19  1.32  38  11.3  252.5 

Feb  32  17  24  0  32  9.4  280 

Mar  37  21  29  0.51  29  10.1  308.5 

Apr  41  24  32  0.02  22  12.4  327.5 

May  46  28  36  0  36  15.1  387.5 

Jun  44  29  35  5.43  44  15.5  364.5 

Jul  42  30  35  5.51  51  15.9  371 

Aug  40  28  33  0.45  54  15.7  318.5 

Sep  41  27  33  0  47  14.5  300 

Oct  40  22  30  0  27  8.2  265 

Nov  33  18  24  0  23  8.9  225 

Dec  28  14  19  0  27  10.2  229.5 

2010 

Jan  27  12  19  0.34  32  9.3  265 

Feb  30  15  22  2.13  30  9.9  276 

Mar  40  22  30  0  31  11.3  310 

Apr  43  25  34  0  30  14.8  319.5 

May  45  28  36  0  35  16.5  387.5 

Jun  43  29  35  7.04  44  17  369 

Jul  40  29  34  36.36  56  12.7  347 

Aug  38  28  32  48.26  64  11.6  300 

Sep  39  26  32  13.71  51  10.1  288 

Oct  40  23  30  0.05  37  8.8  265 

Page 126: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 97 HPK

Month/Year  

Parameters

Average Temperature (°C) Avg. Rainfall in 

mm 

Humidity in 

Avg. Wind in 

kmph 

Avg. Sun 

hours   Maximum  Minimum Average

Nov  32  18  24  0.04  27  9.9  225 

Dec  27  11  17  0  24  10.1  232.5 

2011 

Jan  26  11  17  0.07  26  10.3  262.5 

Feb  29  15  21  0.22  39  10.3  276 

Mar  37  20  28  0.05  28  10.9  302.5 

Apr  41  23  31  0.14  27  11.1  323.5 

May  43  27  34  0.07  47  21.6  387.5 

Jun  42  29  35  1.69  48  24.7  373.5 

Jul  39  29  34  21.38  53  22.2  377 

Aug  36  28  31  139.07  65  17.2  282 

Sep  34  27  30  108.85  68  16.1  250.5 

Oct  36  24  29  0  40  12.1  267.5 

Nov  33  23  27  0.16  38  10.2  219.5 

Dec  27  15  20  0  24  12.3  232.5 

2012 

Jan  24  12  17  0.01  34  12.1  256.5 

Feb  26  13  19  0  22  13  290 

Mar  35  20  27  0  26  13.3  308.5 

Apr  40  26  33  1.88  29  14.7  326 

May  43  28  35  2.77  39  19.7  386 

Jun  42  28  34  0.67  52  27.2  373.5 

Jul  40  28  33  0.92  56  28.1  386 

Aug  38  28  32  7.77  57  22.9  339 

Sep  37  28  32  17.45  55  16  270 

Page 127: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 98 HPK

Month/Year  

Parameters

Average Temperature (°C) Avg. Rainfall in 

mm 

Humidity in 

Avg. Wind in 

kmph 

Avg. Sun 

hours   Maximum  Minimum Average

Oct  37  24  30  0.28  32  10.6  265 

Nov  32  20  26  0  27  9  225 

Dec  27  15  20  0.47  27  12.5  232.5 

2013 

Jan  26  13  18  0  25  11.7  260 

Feb  28  16  21  4.93  33  14.8  275.5 

Mar  35  22  28  0.05  24  13  306 

Apr  39  26  32  1.72  32  15.8  326 

May  43  28  35  0  35  23.7  387.5 

Jun  41  30  35  2.38  47  22.7  369 

Jul  40  30  34  0.45  54  24.9  372 

Aug  37  28  32  34.57  60  21.6  312 

Sep  39  27  33  0.43  48  17.8  300 

Oct  38  20  32  0.28  39  11.5  265 

Nov  32  15  25  0  27  9.9  225 

Dec  27  11  20  0  31  11.1  232.5 

2014 

Jan  24  11  17  0  28  12.9  257.5 

Feb  28  15  21  0  29  13.2  280 

Mar  34  21  27  2.18  26  12.8  306 

Apr  40  26  33  2.11  30  16.2  325 

May  42  29  35  0.71  37  22.1  387.5 

Jun  43  30  36  0.13  47  29.1  370.5 

Jul  40  29  34  3.89  55  27  381.5 

Aug  38  28  32  1.52  55  22.8  336 

Page 128: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 99 HPK

Month/Year  

Parameters

Average Temperature (°C) Avg. Rainfall in 

mm 

Humidity in 

Avg. Wind in 

kmph 

Avg. Sun 

hours   Maximum  Minimum Average

Sep  38  27  32  1.21  55  20.8  297 

Oct  38  25  31  0.55  31  11.6  265 

Nov  33  21  26  0  30  10.7  225 

Dec  27  15  20  0  23  11.4  231 

2015 

Jan  26  14  19  0.19  35  10.8  262.5 

Feb  30  19  24  1.45  34  13.4  269.5 

Mar  35  23  28  0.27  28  13.4  308.5 

Apr  41  28  34  0.68  29  18  320.5 

May  44  30  36  1.12  37  24.8  387.5 

Jun  42  32  36  21.53  43  21.1  364.5 

Jul  37  29  33  54.3  61  30  347.5 

Aug  37  28  31  1.85  60  28  331 

Sep  38  27  32  2.28  50  19.2  291 

Oct  38  27  32  0.32  35  14.7  276.5 

Nov  32  22  26  0  22  12.2  225 

Dec  27  16  21  0.55  22  10.2  229.5 

2016 

Jan  27  16  21  0  34  10  262.5 

Feb  30  18  23  0  18  10.8  290 

Mar  36  25  30  2.27  30  15.2  307 

Apr  40  27  33  0.38  29  17.7  314 

May  42  29  35  1.24  42  27.4  387.5 

Jun  43  30  36  0  45  24.8  372 

Jul  39  30  34  9.77  57  25.2  341 

Page 129: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 100 HPK

Month/Year  

Parameters

Average Temperature (°C) Avg. Rainfall in 

mm 

Humidity in 

Avg. Wind in 

kmph 

Avg. Sun 

hours   Maximum  Minimum Average

Aug  38  29  33  9.42  57  20.8  319.5 

Sep  39  27  32  0  54  24.1  300 

Oct  38  26  31  0  44  14.4  262.5 

Nov  34  21  26  0  25  8.7  225 

Dec  31  19  24  0  28  8.8  232.5 

2017 

Jan  25  15  19  1.31  32  11.7  263.5 

Feb  30  18  23  1.23  19  11.3  275.5 

Mar  36  23  29  0.2  25  12.7  308.5 

Apr  42  27  34  1.16  28  19.6  327.5 

May  44  30  36  0  38  23.4  387.5 

Jun  41  30  35  0.41  51  26.5  351 

Jul  37  30  33  12.48  58  25.4  362 

Aug  37  29  33  17.04  55  24.5  321 

Sep  38  28  32  9.25  50  18.4  295.5 

Oct  38  27  32  0  32  12.2  265 

Nov  32  21  26  0  23  9  225 

Dec  27  17  21  0.01  21  12.4  231 

2018 

Jan  28  17  21  0  28  8.7  265 

Feb  31  20  25  0  26  10.1  278.5 

Mar  36  24  30  0  27  13.8  306 

Apr  41  28  34  0.13  25  16.9  320.5 

May  44  31  37  0  27  19.6  386 

Jun  41  30  35  0.05  49  28  368 

Page 130: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 101 HPK

Month/Year  

Parameters

Average Temperature (°C) Avg. Rainfall in 

mm 

Humidity in 

Avg. Wind in 

kmph 

Avg. Sun 

hours   Maximum  Minimum Average

Jul  38  29  33  0.27  57  28.6  375.5 

Aug  36  28  31  3.84  60  27.8  326 

Sep  37  26  31  0.06  54  22.9  298.5 

Oct  40  31  37  0.1  25  12.4  262 

Nov  35  27  32  0  22  8.9  217.5 

Dec  29  20  26  0  26  9.7  232.5 

Source: https://www.worldweatheronline.com/hyderabad‐weather‐averages/sindh/pk.aspx

Page 131: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 102 HPK

Table 6‐2: Water Quality within Project Area 

No.  Water Parameters  Units  LOD Concentration

Sample 1 (HP) Sample 2 (HP)  Sample 3 (HP) Sample 4 (SW)* Sample 5 (SW)

1. pH  …  …  7.52  7.22  6.81  7.31  7.28 

1. TDS  mg/l  1.0  5  17  9  46  54 

2. TSS  mg/l  0.5  802  538  7675  226  171 

3. Chloride (Cl‐1)  mg/l  2.0  30.25  49.54  1162.75  20.36  9.69 

4. T. Hardness  μg/ml  …  266.23  459.13  2269.51  156.18  124.02 

5. Calcium  μg/ml  …  45.53  129.78  421.15  45.30  35.53 

6. Magnesium  μg/ml  …  35.35  32.86  296.74  10.47  8.58 

7. Fluoride (F)*  mg/l  0.05  0.41  0.33  2.86  0.57  0.55 

8. Sulphate  μg/ml  …   188.76  107.22  1660.20  45.48  30.05 

9. Lead (Pb)  μg/ml  0.04  ND  ND  ND  ND  ND 

10. Arsenic (As)  ppb  0.75  ND  14.20  ND  ND  1.73 

11. Cadmium (Cd)  μg/ml  0.01  ND  ND  ND  ND  ND 

12. Nickel (Ni)  μg/ml  0.01  ND  ND  ND  ND  ND 

13. Phenolic compounds  mg/l  0.1   ND  0.33  ND  ND  0.55 

14. Nitrate (NO3)*  mg/l  3.0  ND  ND  ND  ND  ND 

15. Iron  μg/ml  0.02  0.09  0.16  ND  0.08  0.52 

Notes:  

*: Surface water from Indus River 

HP: Hand pump 

SW: Surface water 

ND: Not detected 

LOD: Limit of determination

Page 132: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 103 HPK

Table 6‐3: Ambient Noise Levels Monitoring 

No. Location

Noise Level (dB) Latitude  Longitude

1.   22° 24ʹ 21.1ʹʹ  68° 29ʹ 20.8ʹʹ  53.7 

2.   25° 45ʹ 11.1ʹʹ  68° 28ʹ 40.3ʹʹ  54.1 

3.   25° 45ʹ 10.9ʹʹ  68° 28ʹ 21.0ʹʹ  75.4 

4.   25° 45ʹ 08.4ʹʹ  68° 27ʹ 45.1ʹʹ  54.8 

5.   25° 45ʹ 07.7ʹʹ  68° 27ʹ 19.3ʹʹ  52.5 

6.   25° 44ʹ 48.9ʹʹ  68° 26ʹ 31.8ʹʹ  56.8 

7.   25° 45ʹ 29.0ʹʹ  68° 23ʹ 48.4ʹʹ  59.8 

8.   25° 46ʹ 02.2ʹʹ  68° 23ʹ 28.1ʹʹ  53.2 

9.   25° 37ʹ 51.2ʹʹ  68° 32ʹ 36.4ʹʹ  54.1 

10.   25° 34ʹ 54.6ʹʹ  68° 29ʹ 22.6ʹʹ  63.8 

11.   25° 33ʹ 58.9ʹʹ  68° 30ʹ 58.4ʹʹ  55.6 

12.   25° 32ʹ 50.6ʹʹ  68° 32ʹ 50.4ʹʹ  56.2 

13.   25° 31ʹ 05.9ʹʹ  68° 33ʹ 12.3ʹʹ  60.7 

14.   25° 30ʹ 03.9ʹʹ  68° 35ʹ 15.9ʹʹ  55.7 

15.   25° 28ʹ 16.2ʹʹ  68° 35ʹ 21.8ʹʹ  60.1 

16.   25° 26ʹ 51.2ʹʹ  68° 35ʹ 38.2ʹʹ  56.2 

17.   25° 25ʹ 41.0ʹʹ  68° 32ʹ 21.8ʹʹ  66.5 

18.   25° 28ʹ 15.3ʹʹ  68° 27ʹ 43.7ʹʹ  55.7 

19.   25° 28ʹ 29.6ʹʹ  68° 26ʹ 32.9ʹʹ  53.5 

20.   25° 28ʹ 16.4ʹʹ  68° 26ʹ 37.5ʹʹ  53.7 

21.   25° 28ʹ 59.4ʹʹ  68° 25ʹ 58.7ʹʹ  53.1 

22.   25° 29ʹ 01.9ʹʹ  68° 25ʹ 56.0ʹʹ  58.8 

23.   25° 29ʹ 20.4ʹʹ  68° 25ʹ 20.6ʹʹ  63.2 

24.   25° 36ʹ 23.8ʹʹ  68° 26ʹ 01.2ʹʹ  62.7 

25.   25° 36ʹ 25.0ʹʹ  68° 25ʹ 47.3ʹʹ  54.8 

26.   25° 36ʹ 15.0ʹʹ  68° 26ʹ 11.0ʹʹ  56.8 

27.   25° 28ʹ 47.1ʹʹ  68° 26ʹ 19.8ʹʹ  55.3 

28.   25° 27ʹ 41.5ʹʹ   68° 28ʹ 14.1ʹʹ  54.7 

29.   25° 26ʹ 13.9ʹʹ  68° 18ʹ 10.5ʹʹ  53.9 

30.   25° 28ʹ 16.6ʹʹ  68° 22ʹ 45.1ʹʹ  52.5 

31.   25° 25ʹ 52.3ʹʹ  68° 18ʹ 04.6ʹʹ  51.6 

32.   25° 26ʹ 42.2ʹʹ  68° 18ʹ 42.1ʹʹ  50.9 

33.   25° 33ʹ 29.2ʹʹ  68° 15ʹ 38.9ʹʹ  55.3 

34.   25° 33ʹ 42.9ʹʹ   68° 14ʹ 51.3ʹʹ  51.8 

35.   25° 34ʹ 45.3ʹʹ  68° 18ʹ 46.8ʹʹ  68.6 

36.   25° 37ʹ 51.1ʹʹ  68° 18ʹ 06.4ʹʹ  64.7 

37.   25° 38ʹ 57.2ʹʹ  68° 18ʹ 07.3ʹʹ  61.3 

38.   25° 38ʹ 30.1ʹʹ  68° 17ʹ 50.5ʹʹ  53.7 

39.   25° 37ʹ 34.4ʹʹ  68° 18ʹ 15.2ʹʹ  58.4 

40.   25° 35ʹ 04.9ʹʹ  68° 20ʹ 19.4ʹʹ  60.9 

41.   25° 35ʹ 34.4ʹʹ  68° 16ʹ 37.3ʹʹ  56.6 

Page 133: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 104 HPK

No. Location

Noise Level (dB) Latitude  Longitude

42.   25° 35ʹ 11.5ʹʹ  68° 16ʹ 55.2ʹʹ  53.5 

43.   25° 28ʹ 45.5ʹʹ  68° 16ʹ 19.6ʹʹ  62.5 

44.   25° 28ʹ 48.6ʹʹ  68° 16ʹ 54.0ʹʹ  58.8 

45.   25° 29ʹ 16.8ʹʹ  68° 17ʹ 07.0ʹʹ  53.6 

46.   25° 30ʹ 59.4ʹʹ  68° 17ʹ 30.9ʹʹ  52.5 

47.   25° 30ʹ 58.6ʹʹ  68° 17ʹ 41.5ʹʹ  59.4 

48.   25° 30ʹ 10.5ʹʹ  68° 18ʹ 37.6ʹʹ  53.7 

49.   25° 30ʹ 08.2ʹʹ  68° 18ʹ 55.0ʹʹ  53.2 

50.   25° 28ʹ 32.1ʹʹ  68° 16ʹ 16.8ʹʹ  64.1 

51.   25° 24ʹ 04.0ʹʹ  68° 16ʹ 52.3ʹʹ  66.2 

52.   25° 21ʹ 32.4ʹʹ  68° 12ʹ 09.5ʹʹ  62.4. 

53.   25° 21ʹ 35.0ʹʹ  68° 12ʹ 14.2ʹʹ  59.3 

54.   25° 23ʹ 12.2ʹʹ  68° 14ʹ 47.4ʹʹ  61.6 

55.   25° 24ʹ 13.4ʹʹ  68° 18ʹ 24.4ʹʹ  52.6 

56.   25° 24ʹ 44.1ʹʹ  68° 19ʹ 04.6ʹʹ  62.5 

57.   25° 24ʹ 26.4ʹʹ  68° 16ʹ 00.9ʹʹ  65.6 

58.   25° 24ʹ 46.5ʹʹ  68° 16ʹ 15.2ʹʹ  66.1 

59.   25° 23ʹ 03.8ʹʹ  68° 21ʹ 18.3ʹʹ  63.6 

60.   25° 23ʹ 05.8ʹʹ  68° 20ʹ 36.4ʹʹ  66.2 

61.   25° 23ʹ 20.6ʹʹ  68° 20ʹ 26.1ʹʹ  67.7 

62.   25° 24ʹ 13.8ʹʹ  68° 19ʹ 37.6ʹʹ  68.5 

63.   25° 24ʹ 09.5ʹʹ  68° 18ʹ 39.1ʹʹ  69.3 

64.   25° 42ʹ 33.9ʹʹ  68° 30ʹ 06.6ʹʹ  51.4 

65.   25° 43ʹ 02.2ʹʹ  68° 29ʹ 39.3ʹʹ  53.1 

66.   25° 46ʹ 03.7ʹʹ  68° 23ʹ 20.6ʹʹ  50.8 

67.   25° 45ʹ 09.9ʹʹ  68° 26ʹ 20.2ʹʹ  51.7 

68.   25° 37ʹ 47.9ʹʹ  68° 32ʹ 33.8ʹʹ  53.4 

69.   25° 36ʹ 28.6ʹʹ  68° 31ʹ 25.7ʹʹ  52.2 

70.   25° 34ʹ 54.0ʹʹ  68° 29ʹ 38.8ʹʹ  56.8 

71.   25° 34ʹ 48.6ʹʹ  68° 29ʹ 51.7ʹʹ  60.8 

72.   25° 34ʹ 14.1ʹʹ  68° 30ʹ 51.9ʹʹ  63.3 

73.   25° 32ʹ 02.7ʹʹ  68° 33ʹ 14.3ʹʹ  55.2 

74.   25° 31ʹ 05.9ʹʹ  68° 33ʹ 12.3ʹʹ  58.9 

75.   25° 30ʹ 39.4ʹʹ  68° 32ʹ 58.3ʹʹ  51.5 

76.   25° 25ʹ 48.6ʹʹ  68° 32ʹ 40.9ʹʹ  64.7 

77.   25° 25ʹ 44.1ʹʹ  68° 27ʹ 35.9ʹʹ  52.3 

78.   25° 28ʹ 45.4ʹʹ  68° 26ʹ 20.0ʹʹ  53.2 

79.   25° 29ʹ 20.4ʹʹ  68° 25ʹ 20.6ʹʹ  54.4 

80.   25° 32ʹ 27.7ʹʹ  68° 26ʹ 08.1ʹʹ  68.9 

81.   25° 34ʹ 41.2ʹʹ  68° 28ʹ 37.6ʹʹ  55.7 

82.   25° 36ʹ 16.3ʹʹ  68° 27ʹ 12.4ʹʹ  73.6 

83.   25° 31ʹ 46.9ʹʹ  68° 16ʹ 52.5ʹʹ  71.8 

Page 134: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 105 HPK

No. Location

Noise Level (dB) Latitude  Longitude

84.   25° 33ʹ 06.6ʹʹ  68° 16ʹ 53.5ʹʹ  52.9 

85.   25° 38ʹ 07.3ʹʹ  68° 18ʹ 06.9ʹʹ  64.8 

86.   25° 33ʹ 05.7ʹʹ  68° 17ʹ 58.9ʹʹ  59.7 

87.   25° 29ʹ 11.5ʹʹ  68° 16ʹ 19.3ʹʹ  64.9 

88.   25° 27ʹ 15.0ʹʹ  68° 16ʹ 20.7ʹʹ  63.7 

89.   25° 21ʹ 48.2ʹʹ  68° 12ʹ 19.2ʹʹ  75.3 

90.   25° 22ʹ 15.4ʹʹ  68° 13ʹ 11.6ʹʹ  59.6 

91.   25° 24ʹ 20.0ʹʹ  68° 17ʹ 52.2ʹʹ  72.2 

92.   25° 24ʹ 46.1ʹʹ   68° 16ʹ 14.7ʹʹ  73.8 

93.   25° 50ʹ 15.6ʹʹ  68° 04ʹ 24.0ʹʹ  53.1 

94.   25° 47ʹ 17.5ʹʹ  68° 11ʹ 02.0ʹʹ  49.4 

95.   25° 43ʹ 41.7ʹʹ  68° 10ʹ 27.6ʹʹ  58.6 

96.   25° 47ʹ 55.8ʹʹ  68° 15ʹ 46.0ʹʹ  54.8 

97.   25° 52ʹ 05.9ʹʹ  68° 14ʹ 31.5ʹʹ  60.2 

Note: All locations were randomly selected in day time within the project area.

Page 135: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 106 HPK

Figure 6‐1: Graphical Representation of Average Temperatures in Hyderabad, 2009 – 2018

0

5

10

15

20

25

30

35

40

45

50

Jan, 09

Apr, 09

Jul, 09

Oct, 09

Jan, 10

Apr, 10

Jul, 10

Oct, 10

Jan, 11

Apr, 11

Jul, 11

Oct, 11

Jan, 12

Apr, 12

Jul, 12

Oct, 12

Jan, 13

Apr, 13

Jul, 13

Oct, 13

Jan, 14

Apr, 14

Jul, 14

Oct, 14

Jan, 15

Apr, 15

Jul, 15

Oct, 15

Jan, 16

Apr, 16

Jul, 16

Oct, 16

Jan, 17

Apr, 17

Jul, 17

Oct, 17

Jan, 18

Apr, 18

Jul, 18

Oct, 18

Average Temperature (°C) Maximum Average Temperature (°C) Minimum Average Temperature (°C) Average

Page 136: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 107 HPK

Figure 6‐2: Graphical Representation of Hyderabad Climatic Data, 2009 – 2018

0

20

40

60

80

100

120

140Mar, 09

Jun, 09

Sep

, 09

Dec, 09

Mar, 10

Jun, 10

Sep

, 10

Dec, 10

Mar, 11

Jun, 11

Sep

, 11

Dec, 11

Mar, 12

Jun, 12

Sep

, 12

Dec, 12

Mar, 13

Jun, 13

Sep

, 13

Dec, 13

Mar, 14

Jun, 14

Sep

, 14

Dec, 14

Mar, 15

Jun, 15

Sep

, 15

Dec, 15

Mar, 16

Jun, 16

Sep

, 16

Dec, 16

Mar, 17

Jun, 17

Sep

, 17

Dec, 17

Mar, 18

Jun, 18

Sep

, 18

Dec, 18

Avg. Rainfall in mm Humidity in % Avg. Wind in kmph

Page 137: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

0 90 180 270 360 450 540 63045Km

Project:EIA for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21)

Fig 6-3: Seismic Zone Map of Paksitan

Halcrow Pakistan (Pvt) Limitedwww.halcrowpk.com

Zone 2B Zone 2A

Zone 3

Zone 3

Zone 2A

Zone 2B

Zone 2B

Zone 1

Zone 4

Zone 2B

Zone 2B

Zone 4

Zone 4

Zone 3

Zone 3

Zone 4

Zone 4

Zone 4Zone 4

82°0'0"E

82°0'0"E

80°0'0"E

80°0'0"E

78°0'0"E

78°0'0"E

76°0'0"E

76°0'0"E

74°0'0"E

74°0'0"E

72°0'0"E

72°0'0"E

70°0'0"E

70°0'0"E

68°0'0"E

68°0'0"E

66°0'0"E

66°0'0"E

64°0'0"E

64°0'0"E

62°0'0"E

62°0'0"E3

6°0

'0"N

36

°0'0

"N

34

°0'0

"N

34

°0'0

"N

32

°0'0

"N

32

°0'0

"N

30

°0'0

"N

30

°0'0

"N

28

°0'0

"N

28

°0'0

"N

26

°0'0

"N

26

°0'0

"N

24

°0'0

"N

24

°0'0

"N

KotriNorthBlock

;?N

LegendZone 1  (0.05 to 0.08g)Zone 2A (0.08 to 0.16g)Zone 2B (0.16 to 0.24g)Zone 3 (0.24 to 0.32g)Zone 4 (> 0.32g)

LegendKotri North Block Seismic Zones

Zone 1

Zone 2A

Zone 2B

Zone 3

Zone 4

United Energy Pakistan

Page 138: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

h

h

h

h

h

Kotri

Hala

Matiari

Hyderabad

Thatta Latifabad

Tando Adam

Qasimabad

Tando Allahyar

Jamshoro

Matiari

Hyderabad

Thatta

Sanghar

68°30'0"E

68°30'0"E

68°20'0"E

68°20'0"E

68°10'0"E

68°10'0"E26

°0'0

"N

26°0

'0"N

25°5

0'0

"N

25°5

0'0

"N

25°4

0'0

"N

25°4

0'0

"N

25°3

0'0

"N

25°3

0'0

"N

25°2

0'0

"N

25°2

0'0

"N

·0 2.5 5 7.5 10 12.5 15 17.5 Km

Halcrow Pakistan (Pvt) Limited

Fig 6-4: Water Resources Map

Project:EIA for Exploration and AssociatedDevelopment Activities in Kotri North Block (E.L. 2568-21)

Legend

h Water_Sample h Water Sampling Location Nationla Highway

mminor and katcha tracks

Name

Canal

Indus River

Nullah

Project Boundary

District Boundaries

Block Boundary/Project Area

Tehsil Boundaries

Reserve Forest (SOP)

Legendh

Water SamplingLocationNationla HighwayCanal

Indus RiverNullah

BlockBoundary/ProjectAreaReserve Forest(SOP)

Tehsil BoundariesDistrict Boundaries

United EnergyPakistan

Page 139: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

!

!!!!!

!!

!

!

!

!

!

!

!

!

!

!!!

!!!

!!!

!

!

!

!

!

!

!!

!

!

!!

!

!!!

! !!

!!

!!

!

!

!!

!

!!

!!

!!!

!!

!!

!

!

!

!

!!!

!

!!

!!

!!

!

!

!

!

!

!

!

!

!

!!

!!

!

!

!

!

!

Kotri

Hala

Matiari

Hyderabad

Thatta Latifabad

Tando Adam

Qasimabad

Tando Allahyar

Jamshoro

Matiari

Hyderabad

Sanghar

Thatta68°30'0"E

68°30'0"E

68°20'0"E

68°20'0"E

68°10'0"E

68°10'0"E26

°0'0

"N

26°0

'0"N

25°5

0'0

"N

25°5

0'0

"N

25°4

0'0

"N

25°4

0'0

"N

25°3

0'0

"N

25°3

0'0

"N

·0 2.5 5 7.5 10 12.5 15 17.5 Km

Halcrow Pakistan (Pvt) Limited

Fig 6-5: Ambient Noise Sampling Location Map of Project AreaProject:EIA for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21)

Legend! new noise locations

!C Well Site

×[ Gas Plant

"" Goth

×k Graveyard

!a Power Plant

Shrine

¥B¢ University

h Water Sample

! Noise Sampling Location

Nationla Highway

mminor and katcha tracks

Project Area Boundary

District Boundaries

Block Boundary/Project Area

Tehsil Boundaries

Reserve Forest (SOP)

LegendBlockBoundary/ProjectArea

District BoundariesTehsil Boundaries

Reserve Forest (SOP)Nationla Highway

!Noise SamplingLocation United Energy

Pakistan

Page 140: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 111 HPK

Photographs: Physical Environment and Resource of the Project Area 

 

Photograph 6‐1: A view of Indus River    Photograph 6‐2: A view of Kotri Barrage 

 

Photograph 6‐3: Agriculture field – dominant 

habitat of the project area Photograph 6‐4: Barani agriculture field  

 

Photograph 6‐5: A patch of waste land & fallow 

land 

 Photograph 6‐6: Stony plain of the project area 

Page 141: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 112 HPK

 

Photograph 6‐7: A view Matiari RF  Photograph 6‐8: A view of Salaro Ghotana RF

Photograph 6‐9: Marshy wetland near Goth 

Suleman Barejo 

  Photograph 6‐10: A view of Khasino Canal 

(wah) 

Photograph 6‐11: A view of Pannu wah  Photograph 6‐12: Cemented watercourse –

Tadri Mori 

Page 142: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 113 HPK

 

Photograph 6‐13: Tube well found in the 

project area  Photograph 6‐14: A view of Rajani‐7 well site 

 

Photograph 6‐15: Gas Compression Facility 

near Rajani‐12 well site 

  Photograph 6‐16: A view of M9 motorway 

entering into project area 

Page 143: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 114 HPK

Biological Environment

This section of the report describes the biological environment of the project area 

proposed for exploration and associated development activities falls in Sindh 

province. Ecologically, Kotri North Block and its immediate vicinities, is rich in 

biodiversity having wide variations in physical features and climate which has 

produced diverse landscape, ecosystem and habitats.  

6.2.1 Data Sources

The present study of EIA contain data from both secondary and primary sources. 

Primary field data of biological environment for the EIA was collected by a team of 

wildlife specialist and botanist. Field survey data for the EIA was collected during 

August, 2019. The faunal field data collection included traditional wildlife survey 

techniques like line transects, incidental sightings and plot searches for birds, reptiles 

and mammals. The vegetation survey was carried out by laying 2 x 2 m and 20 x 20 m 

quadrates within the study area. The field survey methodologies followed 

scientifically established and accepted wildlife and vegetation survey techniques.  

Primary data for flora and fauna was collected at various sampling locations of the 

project area. The sampling locations were randomly selected ensuring that sufficient 

locations were sampled from each habitat and the maximum number of species 

belonging to each habitat was identified. 

The secondary data was also collected which provides a detailed insight in the 

biological environment of the Kotri North Block. For faunal attributes, this mainly 

includes work of WWF Pakistan, Sindh Wildlife Department (SWD), Zoological 

Survey Department (ZSD) and IUCN Pakistan. Previously conducted IEEs and EIAs in 

the region were also consulted for the purpose. For floral attributes, works of Roberts 

(1967, 1991 and 1997) and Schaller (1977) were primarily consulted. Information on 

other secondary data sources consulted during the current EIA study is provided in 

the references section of this EIA report. 

6.2.2 Protected/Sensitive Areas

Kotri North Block (E.L. 2568‐21) encompass several forest protected areas. There are 

about 28 reserve forests (all of them are small sized) are falling in the geographical 

jurisdiction of the Block (E.L. 2568‐21). These reserve forests includes; Kunar Rishal, 

Keti Dallu, Nur Keti, Drabo, Manjhand, Keti Khasai, Unarpur, Rudhapur, Rishal, 

Nural Abad, Racho Khanot, Pako Bhanot, Butho, Ranno, Rajri, Salaro Ghotana, Lakha, 

Khasai, Ghotana, Murid Rais, Sekhat, Matiari, Miana, Hatri, Muhammad Khan, Bada, 

Shah Bukhari and Railo Bada. These reserve forests which were once pristine riverine 

forests, now mostly are under cultivation. These reserved forests mostly lie along the 

bank of Indus River falling in north‐eastern side of the block. During project execution 

Sindh EPA, under Regulations, 2014 and Sindh Forest Department will have the 

authority to oversee the conduct of proposed project activities approved by them. 

Page 144: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 115 HPK

6.2.3 Biological Habitats

Kotri North Block (E.L. 2568‐21) is predominantly located in hilly, stony and sandy 

plains followed by cultivable land & agricultural fields however, mosaics of micro‐

habitats are also present within and around the study area. On the basis of these main 

micro‐habitats present within the project area, it can be divided into four major habitat 

types, each of which have its own ecological significance and possess unique floral and 

faunal attributes. These are: 

Hilly, Stony and Sandy Plains;  

Agriculture Fields, Farmlands & Human Settlements;  

Indus River/Irrigation Network and Associated Marshes; and 

Wastelands & Fallow Lands. 

These habitat types will be discussed in detail in later paragraphs while describing 

fauna and flora of the entire project area as a whole. During the field visit for EIA a 

total of 128 floral species belonging to 37 families, 101 birds, 20 mammals and 20 

reptiles were recorded. Complete list of biological attributes is provided in Table 6‐4 

(flora) to Table 6‐12 to 6‐14 (fauna). 

As mentioned above a total of four major habitats were identified during the field 

survey for the study. Classifications of these habitats is discussed separately in the 

following sections of this chapter. Information on the key species of flora and fauna 

associated with each habitat type has also been discussed as part of the habitat 

description.  

a. Hilly, Stony and Sandy Plains  

This common and most dominant type of habitat is found in the western side of the 

project area which mostly falls in geographical jurisdiction of Jamshoro district. The 

bottom of hills constitutes stony/sandy plains which get eroded soil and nutrients 

from watershed areas. Sometimes they get flooded during heavy rains mainly during 

monsoon. However, during most of the dry months, the conditions of these plains are 

mainly acute dry. Suitable portions of these stony plains are cultivated and are rain fed 

(wherever feasible). 

The main floral species, which are stunted and sparse due to overgrazing, include, 

Cassia italic, Zizyphus nummularia, Haloxylon salicornicum, Salsola imbricate, Withania 

coagulan and Convolvulus spinosus. The wildlife in this arid climate is of special 

significance which can survive such harsh climatic conditions.  

The typical avian species of this habitat type include See see partridge, Desert 

wheatear, Desert lark, Collared dove, Blue rock pigeon, Great grey shrike, Hoopoe and 

Common babble. Among them game birds are liked by sport hunters. Among the 

mammals, Asiatic jackal, Black napped hare, Desert cat, Indian pangolin and Long 

eared desert hedgehog may be mentioned, where enough cover is available for their 

Page 145: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 116 HPK

food and protection. Raptors like Common kestrel and Black kite were noticed 

hovering in search of small mammals and rodents. 

b. Agriculture Fields, Farmlands & Human Settlements 

Second commonly found habitat type comprises of agricultural fields, orchards and 

villages located in entire project area except for the main Indus River. The ecology this 

built environment has been altered with passage of time through different human 

interventions. Most of the riverine forests have been cleared for seasonal agriculture 

during the low flow season. These riverine forests were once flourishing now have 

almost disappeared due to negligence of relevant authorities and most of the land is 

converted into agriculture fields.  

Like other such areas, a number of species of mammals, birds and reptiles have 

adapted human presence in their neighbourhood and started living in agriculture 

fields, planted trees and even in structures. The presence of these species was noticed 

by direct sightings or through their discrete calls like doves, sparrows, mynas, bulbuls, 

larks and many passeriforms living around human presence. Mammals, which are 

nocturnal in nature were noticed through signs of their movement for search of food. 

Asiatic jackal, Indian/Bengal fox and Desert cat were noticed through their footprints, 

scats and predation on domestic birds and small animals. The small mammals/rodents 

were observed through their burrow systems usually in form of colonies. Reptiles 

were noticed living in their burrow system, on planted trees and even in 

cracks/cavities of buildings/structures.  

Besides the weed species, anthropogenic trees species like Acacia nilotica, Azardica 

indica, Albizia lebbeck, Eucalyptus camaldulensis, Cordia myxa, Dalbergia sissoo and 

Zizyphus mauritiana are scattered around the edges of the agricultural fields. These 

planted and some natural trees and orchards are the roosting places for raptors 

including Common kestrel, Brahminy kite, Black kite, Black‐winged kite, buzzards 

and sometimes eagles. These raptors feed upon rodents and small mammals and play 

positive role for farmers to reduce their loss. 

c. Indus River/Irrigation Network and Associated Marshes 

Indus River, the most critical/important ecosystem is located in the north‐eastern and 

eastern part of the project area running north south. Indus River, the irrigation system 

supported majorly through Kotri Barrage and associated dhands/marshes on banks 

which are usually inundated during monsoon. These seasonal floods are very 

important for resident wildlife. River Indus is also important for migratory birds, 

mainly water‐birds as it is used for navigation and resting ground for winter migrants. 

In addition, the important nearby wetlands like Kalri, Haleji and Hadero are also very 

important for resident and migratory water‐birds, mainly waterfowls which use these 

water bodies for staging during migration and if settled, for entire winter season. The 

abundance of different invertebrates, including insects and soil biodiversity coupled 

with different palatable floral species, the main source of food for resident and 

migratory birds make this habitat rich and important. 

Page 146: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 117 HPK

The floral species were observed from this habitat, at the river banks, and riverine 

areas which are usually under water during the monsoon floods. Species that grow 

around the river and associated marshes include Tamarix indica, Saccharum spontaneum, 

Populus euphratica, Saccharum bengalensis, Acacia nilotica and Capparis deciduas etc. 

including some submerge species e.g. Phragmites karka, Typha elphentiana and Typha 

domingensis.  

During the EIA field visit of project area, a good number of resident and migratory 

species of birds were recorded along Indus River, supporting irrigation network and 

associated dhands/marshes on its both sides. 

d. Wastelands & Fallow Lands 

Ecologically, this is the least important habitat and was noticed in some parts of the 

project area, either in highlands or in shallow lands, in form of small patches. Most of 

such areas were being cultivated in the past. However, water‐logging and salinity 

have reduced the productivity of these areas and now left without any potential use 

by the farmers. Some higher patches were not able to command by irrigation system, 

hence not productive for agriculture. The main flora includes the salt tolerant species, 

grasses and mesquite, Saccharum spontaneum, Tamarix indica, Salvadora oleoides and 

Saccharum bengalense. 

Such areas which are in shape of islands between human habitations and agricultural 

fields are also less important for wildlife. Very few species were noticed in this habitat 

type including Crested lark, Desert lark, House crow, Indian roller, Little green bee‐

eater, Indian myna and some passerines. However, the tall grasses, thickets and bushes 

provide habitat for Black and Grey partridges. Overall, such areas are of least 

ecological importance. 

6.2.4 Baseline Conditions

a. Flora 

The variation in climate between upper and lower Sindh is not reflected in any 

difference in the flora of the two zones. The vegetation is characteristic of edaphic 

conditions of the region viz. arid climate and sandy and calcareous soil, largely 

impregnated with salts. A notable feature is the predominance of plants and trees with 

small leaves, or none at all, and the large proportion of thorny species. The apparent 

contrast between the verdure of the riverine and irrigated tracts on the one hand, and 

the hilly and desert tracts on the other, is largely a matter of its intensity and 

distribution. 

Overall, Sindh Forest Department controls an area of 241,198 hectares in the Riverine 

tract of the province which are categorized as ʺRiverine Forestsʺ locally known as 

Kacho forests. These forests are located along both the banks of River Indus in Thatta, 

Hyderabad, Dadu, Larkana, Naushero Feroze, Nawabshah, Khairpur, Sukkur, 

Shikarpur, Ghotki and Jacobabad districts and have been declared as “Reserved 

Forests” under Forests Act, 1927. The rich alluvial soils support crops of Acacia nilotica 

Page 147: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 118 HPK

(Babul), Populus euphratica (Bahan), Tamarix aphylla, Tamarix dioca (Lai) and Prosopis 

cineraria (Kandi). Riverine forests are the most productive forests of Sindh, producing 

wood material for domestic and commercial purposes.  

Existence of Riverine forests of Sindh is dependent on flooding by the river. They are 

flooded by the spate of River Indus, on lands and soils over its banks. Floods occur 

due to the flow of large quantities of water in the river that cannot be accommodated. 

Both the land configuration and the soils in riverine tract are made by flood waters. 

The spate was a common summer phenomenon in the past, until such a time that the 

river water was not diverted and extracted through dams, barrages, head‐works and 

link‐canals. Riverine forests are the mainstay of forestry in Sindh. They provide 

products and services such as timber, firewood, pit props for mines, forage and 

browse for livestock, supports biodiversity and game animals. Other non‐timber forest 

products include tannin from bark, gum, honey and even fish from dhands (ponds) and 

dhoros (depression of old river beds). They act as carbon sinks, moderate climate, stop 

soil erosion and also protect soils and settlements from the ferocity of flood waters.  

The annual inundation of the riverine areas during the monsoon season act as a lifeline 

for the existence and flourishing of the Riverine forests. There has been large‐scale 

degradation of riverine forests due to severe decrease in flow of freshwater down the 

Guddu Barrage. The situation has been worsened by the recent drought and lowest 

ever flow in Indus (0.75 MAF) downstream of Kotri Barrage. Major reason for great 

depletion of Riverine forests are continuous decrease in quantum of floods due to 

upper stream storage, diversion and increasing amount of take‐off for irrigation/ 

human consumption. Areas frequently flooded before are now flooded only every 

seven or eight year interval, which is not enough to support lush floodplain forests. 

High‐lying portions of these forests are the worst affected. Reduced frequency of high 

floods has left these areas in an increasingly dry state. Xerophytic trees and shrubs have 

replaced thick and profuse growth of Acacia nilotica, which is the main and most 

important riverine specie. The common riverine forests species such as, Bahan (Populus 

euphratica) and Lai (Tamarix aphylla) are gradually disappearing from the tract. Apart 

from over all degradation of these forests, there occurred sizeable blanks within them 

due to which the required forest density has diminished.  

The Riverine forests in the past were only developed through the annual regeneration 

at the time of monsoon floods. Recently, under annual development program, some 

areas were developed and planted on the pattern of irrigated plantations by lift 

irrigation through installation of electric/diesel operated tube wells and diesel 

operated lift pumps on the river banks and depressions. The underground water in 

the riverine tract is sweet, available in abundance in the aquifer and is suitable for 

raising trees and agriculture crops. Following are the main factors responsible for 

degradation of Riverine forests: 

Severe reduction in flow of fresh water in Indus through floods; 

Population pressure for meeting the local needs of the people; and 

Page 148: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 119 HPK

Increase in the high‐lying areas due to low floods. 

Productive potential of these areas can be restored by developing artificial source of 

irrigation such as installing tube wells and lift pumps and planting suitable tree 

species for increasing wood production and protection of the environment. These 

areas are to be developed through intensive management, land levelling and 

arranging the assured supply of irrigation on high‐lying areas. In order to develop 

these forests, two strategies have been proposed in various projects i.e. departmental 

forestry or traditional forestry (forestry by the department) and participatory forestry 

(forestry by the department and local people) with main emphasis on participation of 

local people, poverty alleviation and combating desertification. 

Floral Diversity 

Ecologically, entire stretch of Kotri North Block is a part of the tropical thorn forest 

ecozone. The area is characterized by low rainfall, high summer temperatures, high 

velocity winds, poor soil and low diversity of plant species. Most of this region has 

been cleared for cultivation and last remnants of the forest are heavily degraded due 

to over grazing and felling of trees. Plant communities in the project area are also 

faced with the threats of livestock grazing. 

During field work for the EIA, 128 plant species belonging to 37 families were 

identified in main habitats within the project area. Table 6‐4 provides a complete list 

of the floral species along with their family name, life form and life span observed 

during recent EIA site survey in the major habitats of the project area.  

Out of 128 species 65 are perennial, 2 are semi‐perennial, 1 is biennial and 60 are 

annual. Life forms of the identified species are as follows: 

Life Form  Number Life Form Number 

Grass  31  Climber shrub  1 

Herb  40  Subshrub  7 

Tree  17  Prostrate subshrub  1 

Sedge  8  Prostrate herb  1 

Shrub  22  Total 128 

Life form of the project area is dominated by herb (31.25%) followed by grass (24.22%), 

shrub (17.19%), tree (13.28%), sedge (6.25%), subshrub (5.47%), climber shrub, 

prostrate subshrub and prostrate herb (0.78%) each. 

Floral Species of Medicinal or Economical Use 

The species found in the project area which are of importance in terms of  medicinal 

and economical use include Aerva javanica, Capparis deciduas, Desmostachya bipinnata, 

Salvadora oleoides and Typha elephantina. Table 6‐11 represents the plant species along 

with their medicinal and economical use. 

 

 

Page 149: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 120 HPK

Rare or Endemic Floral Species 

No endemic or rare species exist within the project area. All species have a wide range 

of distribution. Some representative photographs of the flora in the project area are 

presented at the end of this chapter. 

Quantitative Accounts of Flora 

The quantitative accounts of vegetation (i.e. Relative Cover, Relative Frequency, 

Relative Density and Importance of Index Value (I.V.I) of all the species) were also 

checked. The usual means of sampling of vegetation for floristic composition is the 

quadrate. Traditionally, quadrates are square, although rectangular and even circular 

quadrates have been used. Since, the vegetation of the project area is of different sized 

components, comprised of trees/tall shrubs and tall herbs/sub‐shrubby/herbs and 

grasses so Nested Quadrates method was adopted. Hence, two different sized 

quadrates were laid down at every sampling site in major habitats as follows: 

Measuring 20 x 20 m (Climax community for Trees/Tall shrubs)  

Measuring 2 x 2 m (Underneath flora for Tall herbs/Sub‐ shrubs/Herbs and Grass)  

Thereafter, the data in major habitats was analysed separately for each quadrate and 

habitat as well. The quantitative analysis of floral composition (vegetation) was carried 

out in calculating Relative Cover, Relative Frequency, Relative Density and 

Importance of Index Value (I.V.I) of all the species.  

The Relative Density of the species has been calculated with the following formula: 

Relative Density = 

Total number of individual of a species in all 

quadrates   100

Total number of individual of all species in all 

quadrates  

The Relative Cover of species has been calculated with the following formula: 

Relative Cover of 

Species = 

Total cover (sq. cm)  of all plants of a species   100

Total cover (sq. cm) of plants of all species 

 

The Relative Frequency % of the species has been determined with the help of the following formula: 

Relative Frequency = Frequency of a species 

  100 Total frequency of all species 

Importance Value Index (I.V.I) – Since the floral composition is not homogenous in 

project area, so data like density, cover and frequency cannot depict clearly the 

dominant species.  Therefore, for each habitat measuring two separate sized quadrates 

(i.e. 20 x 20m & 2 x 2m) Importance Value Index (I.V.I) of all the recorded species 

Page 150: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 121 HPK

calculated by adding the value of Relative Cover, Relative Frequency and Relative 

Density then divided by three as follows: 

I.V.I =  Relative Cover + Relative Frequency + Relative Density 

List of species found in the project area for EIA along with the I.V.I values for the three 

major critical habitats identified by botanist namely Riparian habitat, Marshy/wetland 

habitat and Calcareous rocky plain habitat for quadrates measuring 20 x 20m (Climax 

community for Trees/Tall shrubs etc.) and 2 x 2m (Underneath flora for Tall herbs/Sub‐ 

shrubs/Herbs and Grass) is provided in Table 6‐5 to Table 6‐10. 

Dominant Floral Species of Reserved Forests 

According to the Sindh Forest Department the reserve forests comprise of five main 

species of interest. These include Tamarix indica, Acacia nilotica, Prosopis juliflora, 

Prosopis cineraria and Saccharum spontaneum. 

b. Fauna 

The faunal field data collection included line transects, incidental sightings and plot 

searches for birds, ungulates, carnivores, small mammals and reptiles. On significant 

wetlands, surveys were also conducted for identification of water‐birds. This involved 

walking along the edges of the wetlands to select a suitable site for making 

observations using binoculars and spotting scope. The survey team ensured that the 

birds were observed without causing any disturbance. The sampling locations were 

randomly selected, ensuring that sufficient locations are sampled for each habitat and 

the maximum number of species belonging to each habitat is identified.  

Birds 

The project area of Kotri North Block, being blend of different habitats, supports a 

variety of avifauna, both resident and migratory including migratory ducks, waders, 

gulls, herons and egrets. Famous game birds including Grey and Black partridges are 

also recorded almost throughout the project area. However, Black partridges are 

confined to riverine areas and thick vegetative covers. The wetlands, dhands and 

marshy areas will be filled with the arrival of migratory birds during the peak winter 

season. The agricultural fields at the river banks and even in riverine areas provide 

food and shelter to a number of species, which have adapted with the human 

settlements. Houbara bustard sometimes is recorded from sandy plains but there had 

been no recent sighting from the project area.  

During the current EIA field visit, 101 birds’ species which includes 28 migratory and 

73 resident species were recorded from the project area of Kotri North Block and its 

immediate vicinity proposed for exploration and associated development activities. 

Out of total 101 recorded species, 64 are common, 5 are abundant 29 are less common 

and 3 are rare species. Out of total 101 recorded birds, 18 species have protected status 

under the provision of Sindh Wildlife Protection Ordinance, 1972 which include some 

ducks, raptors, egrets and herons. Out of total recorded species 3 are on IUCN Red 

Page 151: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 122 HPK

List, 12 migratory species are on CMS and 20 included on CITES appendices having 

international demand for trade. 

The common birds of the project area include Crested lark, Cattle egret, Chestnut 

shouldered petronia, Desert lark, Ring dove, Desert wheatear, Hoopoe, Indian river 

tern, Indian roller, Common moorhen, Indian pond heron, Pied kingfisher, Purple 

sunbird, Red‐wattled lapwing, Sindh nightjar, Spotted owlet and White breasted 

kingfisher. A complete list of the bird species observed in the project area can be seen 

in Table 6‐12. 

Mammals 

A total of 20 mammalian species were recorded during field visit of EIA conducted 

during August, 2019 through direct sightings and various signs of their presence. Out 

of total 20 recorded species, 12 are common, 1 is abundant, 3 are less common and 4 

are rare. Out of these 20 mammals, three species are of global significance including 

Fishing cat, Hog deer and Indian pangolin.  

Small mammals and rodents are quite abundant as noticed through their burrow 

system. Small mammals play an important and perhaps indispensable role in the 

functioning of ecosystem. They should not be viewed separately from other 

components in the ecosystem. Rather, they must be viewed in terms of their 

interrelationships with other components. Small mammals influence the structure and 

function of ecosystems as consumers of plants and small animals, as movers of soil 

and soil nutrients, and as the primary prey of raptors, snakes, hawks, eagles, owls and 

carnivorous mammals. Because of their intermediate trophic position and high 

dispersal abilities, small mammals may track changes in biotic and abiotic 

environment that result from shifts in land‐use practices and other human activities. A 

complete list of the mammalian species observed in the project area can be seen in 

Table 6‐13. 

Reptiles 

During the present EIA field visit of project area in Kotri North Block and its 

immediate vicinity, presence of 20 reptilian species was recorded through direct 

sightings and signs of their presence. Out of total 20 recorded species, 10 are common, 

9 are less common and one is rare.  

Common reptilian species of the project area include, Brilliant agama, Indian fringe‐

toed sand lizard, Garden lizard, Indian monitor lizard, Indian sand swimmer and 

Indian spiny‐tailed lizard found in the semi‐desert and loamy soil habitat for such 

reptiles. Poisonous snake species of the area include, Saw scaled viper and Indian 

cobra whereas, non‐poisonous are Brahminy blind snake, Checkered keelback, 

Dhaman, Glossy billed racer, Indian sand boa, Royal diadem snake and Pakistan 

ribbon snake. A list of reptiles observed during both field visit is provided in Table 6‐

14. 

 

Page 152: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 123 HPK

Key Faunal Species 

Based on current site visit, relative abundance and sensitivity towards human 

interventions and their listing in different Conventions and SWPO, there are several 

species which may be categorized as key species of the project area including Hog 

deer, Indian pangolin, Fishing cat and birds of prey. During the project 

implementation, special care/mitigation measure is adopted while working in habitat 

of these key species.

Page 153: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 124 HPK

Table 6‐4: List of Vegetation Species found in the Project Area 

Family Name/Plant Species Local Name Life‐Form/Habitat Life‐Span

Cyperaceae    

Cyperus rotundus Linn  Kabah  Sedge  Annual 

Cyperus longus L.  Kal  Sedge  Perennial 

Bolboschoenus affinis (Roth.) Drobov.  Cheho  Sedge  Perennial 

Bolboschoenus glaucus (Lam.) S. G. Simth  Cheho  Sedge  Perennial 

Schoenoplectus littoralis (Schrad.) Palla  Cheho  Sedge  Perennial 

Fimbristylis acuminata Vahl.  Kabah  Sedge  Perennial 

Poaceae    

Aeluropus lagopoides (Linn.) Trin. ex. Thw  Kalar gaah  Grass  Perennial 

Aristida adscensionis Linn.  Lumb gaah  Grass  Annual 

Aristida funiculata Trin. & Rupr.  Lumb gaah  Grass  Annual  

Brachiaria eruciformis (J. E. Simth) Griseb.  Sawri  Grass  Annual 

Brachiaria ramosa (L.) Stapf  Sawri  Grass  Annual 

Brachiaria reptans (L.) Gardner & Hubbard  Sawri  Grass  Annual 

Cenchrus bifloris Roxb.  Bhorut  Grass  Annual 

Cenchrus ciliaris L.  Bhourt  Grass  Annual 

Cymbopogon jawarancusa (Jones) Schult.  Katan  Grass  Perennial 

Cynodon dactylon (Linn.) Pers.  Chhabar  Grass  Perennial 

Chloris barbata Sw.  Sawari  Grass  Annual 

Dactyloctenium aegyptium (Linn.) P. Beauv.  Gandheer gaah  Grass  Annual 

Dactyloctenium aristatum Link.  Gandheer gaah  Grass  Annual 

Desmostachya bippinata (Linn.) Stapf.  Drabh  Grass  Perennial 

Dichanthium annulatum (Forssk.) Stapf  Palwan  Grass  Perennial 

Digitaria ciliaris (Retz.) Koel.  Pachar gaah  Grass  Annual 

Diplachne fusca (L.) P. Baeuv. ex Roem. & Schult.  Jhang sari  Grass  Perennial 

Page 154: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 125 HPK

Family Name/Plant Species Local Name Life‐Form/Habitat Life‐Span

Eragrostis ciliaris (L.) R. Br.  Sawri ghahh  Grass  Annual 

Eragrostis minor Host.  Sawri ghahh  Grass  Annual 

Eragrostis tenella (L.)  Bhurbhuri  Grass  Annual 

Imperata cylindrica (L.) Reuschel  Dabori  Grass  Annual 

Ochthochloa compressa (Forssk.) Hilu.  Ghander  Grass  Perennial 

Paspalum paspaloides (Michx.) Scribner  Koda  Grass  Perennial 

Pennisetum orientale L. C. Rich.  Bhurut  Grass  Perennial 

Phragmites karka (Retz.) Trin. ex Steud.  Nar/Naro  Grass  Perennial 

Saccharum bengalense Retz.  Booro   Grass  Perennial 

Saccharum griffithii Munro ex Boiss.  Kanh  Grass  Perennial 

Saccharum spontaneum Linn.  Booro/Munian   Grass  Perennial 

Stipagrostis plumosa (Linn.) Munro ex T. Anders.  Lumb gaah  Grass  Annual 

Tragus berteronianus Schult.  …..  Grass  Annual 

Tragus roxburghii Panigrahi  …..  Grass  Annual 

Aizoaceae    

Limeum indicum Stocks. ex T. Anders.  Khir wal  Herb  Annual 

Sesuvium sesuvioides (Fenzl.) Verdc.  Kori lonak  Herb  Annual 

Trianthema portulacastrum L.  Waho  Herb  Annual 

Zaleya pentandra (L.) Jeffrey.  Waho  Herb  Annual 

Amaranthaceae    

Aerva javanica var. javanica (Burm.f.) Juss. ex.   Booh  Subshrub  Perennial 

Digera muricata (L.) Mart.  Lulur  Herb  Annual 

Anacardiaceae          

Mangifera indica L.  Aumb  Tree  Annual 

Aristolochiaceae          

Aristolochia bracteolata Lamk.  Kinari wal  Herb  Annual 

Asclepiadaceae          

Page 155: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 126 HPK

Family Name/Plant Species Local Name Life‐Form/Habitat Life‐Span

Calotropis procera (Willd.) R. Br.  Ak  Shrub   Perennial 

Leptadenia pyrotechnica (Forsk.) Decne.  Khip  Shrub   Perennial 

Oxystelma esculentum (L. f.) R. Br.  Phuli  Climbing shrub  Perennial 

Asteraceae          

Launaea procumbens (Roxb) Ramayya & Rajagopal.  Bhattar  Herb  Perennial 

Eclipta alba (L.) Hassk.  Daryai buti  Herb  Annual 

Echinops echinatus Roxb.  Loot  Herb  Annual 

Iphiona grantioides (Boiss.) Anderb  Gandraf  Herb  Annual 

Pluchea lanceolata (DC.) Oliv. & Hiern.  Phaar buti  Shrub   Perennial 

Xanthium indicum Koenig ex Roxb.  Bhurt  Shrub   Annual 

Bombacaceae          

Bombax ceiba L.  Simbal  Tree  Perennial 

Boraginaceae          

Cordia myxa Linn.  Lesuro  Tree  Perennial 

Heliotropium crispum Desf.  Kharsan  Herb  Annual 

Heliotropium europaeum L.  Kharsan  Herb  Annual 

Caesalpiniaceae          

Cassia italica (Mill.) F. W. Andr.  Ghora wal  Herb  Annual 

Cassia holosericeae Fresen.  Ghora wal  Herb  Annual 

Capparidaceae          

Capparis decidua (Forssk.) Edgew.  Kirar  Shrub  Perennial 

Capparis cartilaginea Decne.  Golaro  Shrub  Perennial 

Capparis spinosa L.  …..  Herb  Annual 

Cleome scaposa DC.  Kano gah  Herb  Annual 

Dipterygium glaucum Decne.  Phair  Subshrub  Perennial 

Chenopodiaceae          

Arthrocnemum indicum (Willd.) Moq.  Lano  Shrub  Perennial 

Page 156: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 127 HPK

Family Name/Plant Species Local Name Life‐Form/Habitat Life‐Span

Haloxylon salicornicum (Moq.)  Lano  Shrub  Perennial 

Haloxylon stocksii (Boiss.)  Lani  Shrub  Perennial 

Saueda fruticosa (Linn.) Forsk.  Lani  Subshrub  Semi‐perennial 

Salsola imbricata Forssk.  Lano  Shrub  Perennial 

Combretaceae          

Conocarpus lancifoluis Engl.  Cono  Tree  Perennial 

Convolvulaceae          

Cressa cretica Linn.  Oin  Herb  Annual 

Convolvulus arvensis L.  Narro  Herb  Annual 

Ipomoea carnea Jacquin.  Narro  Herb  Annual 

Cucurbitaceae          

Citrullus colocynthis (Linn.) Schrad.  Trooh  Prostrate subshrub  Perennial 

Mukia maderaspatana (Linn.) M. J. Roem.  …..  Prostrate herb  Annual 

Cuscutaceae          

Cuscuta europaeae L.  Be paari  Herb  Annual 

Cuscuta reflexa Roxb.  Be paari  Herb  Annual 

Euphorbiaceae          

Euphorbia hirta Linn.  Kheer wal  Herb  Annual 

Euphorbia granulata Forssk.  Kheer wal  Herb  Annual 

Euphorbia prostrata Aiton  Kheer wal  Herb  Annual 

Chrozophora tinctoria (L.) Raf.  …..  Herb  Annual 

Phyllanthus reticulatus Poir.  Kamohi  Herb  Perennial 

Ricinus communis L.  Heran  Shrub  Biennial 

Fabaceae          

Alhaji maurorum Medic.  Kandero  Subshrub  Perennial 

Crotolaria burhia Ham. ex Benth.  Chag  Subshrub  Semi‐perennial 

Dalbergia sissoo Roxb.  Taari  Tree  Perennial 

Page 157: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 128 HPK

Family Name/Plant Species Local Name Life‐Form/Habitat Life‐Span

Indigofera cordifolia Heyne ex Roth.  Mahori  Herb  Annual 

Indigofera oblongifolia Forsk.  Jhil  Shrub  Perennial 

Rhynchosia minima (L.) DC.  Wanverhi  Herb  Perennial 

Sesbania sesban (L.) Kuntze  Manjhanderi  Shrub  Perennial 

Malvaceae          

Abutilon indicum (L.) Sweet  Pat‐teer  Shrub  Perennial 

Meliaceae          

Azadirachta indica A. Juss.  Nim (Neem)  Tree  Perennial 

Mimosaceae          

Acacia jacquemontii Benth.  Banwar  Shrub  Perennial 

Acacia nilotica (Linn.) Delile  Sindhi babur  Tree  Perennial 

Albizia lebbeck Linn.  Sarenh  Tree  Perennial 

Prosopis cineraria (Linn.) Druce  Kandi  Tree  Perennial 

Prosopis juliflora (Swartz) DC.  Devi  Shrub  Perennial 

Prosopis glandulosa Torr.  Devi  Shrub  Perennial 

Moraceae          

Ficus benghalensis L.  Bar  Tree  Perennial 

Ficus religiosa L.  Pepur  Tree  Perennial 

Myrtaceae          

Eucalyptus L Her.  Sufedo  Tree  Perennial 

Syzygum cumini (L.) Skeels.  Jaman/Jamu  Tree  Perennial 

Neuradaceae          

Neurada procumbens Linn.  Chhapri/Chhipri  Herb  Annual 

Nyctaginaceae          

Boerhavia procumbens Banks ex Rxb.  Dakhri  Herb  Annual 

Oxalidaceae           

Oxalis corniculata L.  Sawari  Herb  Annual 

Page 158: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 129 HPK

Family Name/Plant Species Local Name Life‐Form/Habitat Life‐Span

Palmeae          

Phoenix dactylifera Linn.  Khaji  Tree  Perennial 

Rhamnaceae          

Zizyphus mauritiana Lam.   Ber  Tree  Perennial 

Zizyphus nummularia (Burm. f.) Wt. & Arn.  Jhangoori ber  Tree  Perennial 

Salvadoraceae          

Salvadora oleoides Decne.  Jar/Peroon  Shrub  Perennial 

Salvadora persica L.  Khabar  Shrub  Perennial 

Scrophulariaceae          

Bacopa monnieri (L.) Penn.  Bhattar  Herb  Annual 

Solanaceae          

Datura metel Linn.  Charyo dhatooro  Herb  Annual 

Solanum surattense Burm. f.  Kanderi wal  Subshrub  Annual 

Solanum nigrum var. nigrum Linn.  Kanwal buti  Herb  Annual 

Withania somnifera (Linn.) Dunal  Akri  Shrub  Perennial 

Tamaricaceae          

Tamarix aphylla (Linn.) Karst.  Lawo  Tree  Perennial 

Tamarix indica willd.  Lawi  Shrub  Perennial 

Tamarix dioica Roxb. ex Roth.  Lawi  Shrub  Perennial 

Tiliaceae          

Corchorus depressus (Linn.) Stocks.  Mundheri  Herb  Annual 

Corchorus tridens Linn.  Datehri  Herb  Annual 

Typhaceae          

Typha domingenasis Pres.  Pan  Sedge  Perennial 

Typha elephantina Roxb.  Pan  Sedge  Perennial 

Verbenaceae          

Phyla nodiflora (L.) Greene  Bukan  Herb  Perennial 

Page 159: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 130 HPK

Family Name/Plant Species Local Name Life‐Form/Habitat Life‐Span

Zygophyllaceae          

Fagonia indica var. schweinfurthii Hadidi  Dramaaho  Subshrub  Annual 

Tribulus terrestris L.  Bakhro/Bhurt  Herb  Annual 

Tribulus longipetalus Viv.  Bakhro/Bhurt  Herb  Annual 

Zygophyllum simplex L.  Pat lani  Herb  Annual 

Page 160: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 131 HPK

Table 6‐5: List of Vegetation Species of Riparian Habitat (20 x 20m Quadrate) 

No.  Plant Species  Density  Relative D* Frequency Relative F**  Total Cover Relative Cover I.V.I

1.   Acacia nilotica   4.75  24.05  75  16.67  1934707.68 36.80  25.84 

2.   Capparis decidua   1.25  6.33  50  11.11  190139.4 3.62  7.02 

3.   Calotropis procera   1  5.06  50  11.11  80455.68 1.53  5.90 

4.   Phyllanthus reticulatus   0.25  1.27  25  5.56  25456.68 0.48  2.44 

5.   Prosopis cineraria  1  5.06  25  5.56  282852 5.38  5.33 

6.   Prosopis juliflora   3.5  17.72  75  16.67  532390.32 10.13  14.84 

7.   Prosopis glandulosa   2.25  11.39  50  11.11  400546.7172 7.62  10.04 

8.   Salvadora oleoides  0.75  3.80  25  5.56  637359.84 12.12  7.16 

9.   Salvadora persica  1.5  7.59  25  5.56  912669.12 17.36  10.17 

10.   Tamarix indica   3.5  17.72  50  11.11  260871.2568 4.96  11.26 

D* ‐ Density, F** ‐ Frequency  

Table 6‐6: List of Vegetation Species of Riparian Habitat (2 x 2m Quadrate) 

No.  Plant Species  Density  Relative D* Frequency Relative F** Total Cover Relative Cover I.V.I

1.   Abutilon indicum   1  5.80  50  16.67  11314.08 15.53  12.66

2.   Alhaji maurorum   7.75  44.93  100  33.33  21921.03 120.76  66.34

3.   Cynodon dactylon   3.25  18.84  75  25.00  13237.4736 72.92  38.92

4.   Desmostachya bippinata   5.25  30.43  75  25.00  26399.52 145.43  66.95

D* ‐ Density, F** ‐ Frequency 

Page 161: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 132 HPK

Table 6‐7: List of Vegetation Species of Marshy/Wetland Habitat (20 x 20m Quadrate) 

No.  Plant Species  Density  Relative D* Frequency Relative F**  Total Cover Relative Cover I.V.I

1.   Acacia nilotica   0.20  0.57  10.0  3.57  277194.96 2.43  2.19 

2.   Capparis decidua   0.10  0.29  10.0  3.57  38722.4388 0.34  1.40 

3.   Prosopis cineraria  0.10  0.29  10.0  3.57  149358.4272 1.31  1.72 

4.   Prosopis juliflora   0.30  0.86  10.0  3.57  60341.76 0.53  1.65 

5.   Prosopis glandulosa   3.20  9.20  60.0  21.43  814613.76 7.14  12.59

6.   Saccharum bengalense   0.30  0.86  10.0  3.57  122531.4864 1.07  1.84 

7.   Salvadora persica  1.40  4.02  40.0  14.29  3449537.28 30.22  16.18

8.   Saueda fruticosa   17.10  49.14  50.0  17.86  4067722.897 35.64  34.21

9.   Tamarix indica   12.10  34.77  80.0  28.57  2433784.32 21.32  28.22

D* ‐ Density, F** ‐ Frequency 

Table 6‐8: List of Vegetation Species of Marshy/Wetland Habitat (2 x 2m Quadrate) 

No.  Plant Species  Density  Relative D* Frequency Relative F** Total Cover Relative Cover I.V.I

1.   Aeluropus lagopoides   0.40  2.30  10.0  4.17  804.557 0.65  2.37 

2.   Alhaji maurorum   0.70  4.02  10.0  4.17  3717.932 3.00  3.73 

3.   Bacopa monnieri  1.00  5.75  20.0  8.33  2545.668 2.06  5.38 

4.   Cressa cretica   2.20  12.64  30.0  12.50  11684.930 9.44  11.53

5.   Cynodon dactylon   1.20  6.90  20.0  8.33  13614.610 11.00  8.74 

6.   Cyperus longus   1.00  5.75  10.0  4.17  1131.408 0.91  3.61 

7.   Desmostachya bippinata   1.60  9.20  30.0  12.50  22175.597 17.92  13.20

8.   Diplachne fusca   0.30  1.72  10.0  4.17  2121.390 1.71  2.53 

9.   Fimbristylis acuminata   0.70  4.02  10.0  4.17  1781.968 1.44  3.21 

10.   Paspalum paspaloides   2.60  14.94  20.0  8.33  2941.661 2.38  8.55 

11.   Phragmites karka   1.60  9.20  30.0  12.50  16292.275 13.16  11.62

12.   Schoenoplectus littoralis   0.30  1.72  10.0  4.17  1847.966 1.49  2.46 

13.   Typha domingenasis   3.80  21.84  30.0  12.50  43112.930 34.83  23.06

D* ‐ Density, F** ‐ Frequency 

Page 162: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 133 HPK

Table 6‐9: List of Vegetation Species of Rocky Calcareous Plain Habitat (20 x 20m Quadrate) 

No.  Plant Species  Density  Relative D* Frequency Relative F**  Total Cover Relative Cover  I.V.I

1.   Capparis decidua   0.71  6.17  28.57  9.09  127283.4 4.00  6.42 

2.   Calotropis procera   0.57  4.94  85.71  27.27  97351.3728 3.06  11.76 

3.   Indigofera oblongifolia  0.29  2.47  14.29  4.55  30799.44 0.97  2.66 

4.   Prosopis cineraria  0.14  1.23  14.29  4.55  23787.8532 0.75  2.18 

5.   Prosopis juliflora   1.57  13.58  28.57  9.09  86427 2.71  8.46 

6.   Prosopis glandulosa   3.14  27.16  57.14  18.18  301180.8096 9.45  18.27 

7.   Rhazia stricta  1.43  12.35  14.29  4.55  95069.7 2.98  6.63 

8.   Salvadora oleoides  2.14  18.52  42.86  13.64  2098808.982 65.88  32.68 

9.   Zizyphus nummularia   1.57  13.58  28.57  9.09  325276.6572 10.21  10.96 

D* ‐ Density, F** ‐ Frequency 

Page 163: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 134 HPK

Table 6‐10: List of Vegetation Species of Calcareous Plain Habitat (2 x 2m Quadrate) 

No.  Plant Species  Density  Relative D* Frequency Relative F** Total Cover Relative Cover I.V.I

1.   Aristida adscensionis   15.29  18.61  71.43  8.33  33627.96 11.21  12.72 

2.   Aristida funiculata   6.29  7.65  28.57  3.33  8850.12 2.95  4.64 

3.   Cassia holosericeae   0.71  0.87  28.57  3.33  4541.35 1.51  1.91 

4.   Cassia italica   5.14  6.26  85.71  10.00  25456.68 8.48  8.25 

5.   Cenchrus bifloris   8.57  10.43  85.71  10.00  12068.35 4.02  8.15 

6.   Cenchrus ciliaris   4.00  4.87  42.86  5.00  7127.87 2.38  4.08 

7.   Corchorus depressus   11.14  13.57  71.43  8.33  29661.75 9.89  10.59 

8.   Cymbopog jawaracusa  1.14  1.39  28.57  3.33  8146.14 2.71  2.48 

9.   Eragrostis ciliaris   4.43  5.39  71.43  8.33  4773.91 1.59  5.11 

10.   Eragrostis minor   3.14  3.83  42.86  5.00  5600.47 1.87  3.56 

11.   Euphorbia granulata   6.71  8.17  57.14  6.67  24963.26 8.32  7.72 

12.   Fagonia indica  2.43  2.96  57.14  6.67  19287.36 6.43  5.35 

13.   Indigofera cordifolia  0.57  0.70  14.29  1.67  3633.08 1.21  1.19 

14.   Iphiona grantioides  0.71  0.87  28.57  3.33  3079.94 1.03  1.74 

15.   Ochthochloa compressa  6.29  7.65  71.43  8.33  49920.24 16.64  10.87 

16.   Zygophyllum simplex   5.57  6.78  71.43  8.33  59323.49 19.77  11.63 

D* ‐ Density, F** ‐ Frequency 

Page 164: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 135 HPK

Table 6‐11: Vegetation Species with Medicinal and Economical Use found in the Project Area 

No.  Scientific Name  Common Name Family Medicinal or Economical Use

1.   Acacia nilotica   Sindhi Babur  Mimosaceae Trunk used as pillars in making huts and agricultural implements, leaves and 

flowers/fruits used as a fodder. The tree is also used as a fuel 

2.   Aerva javanica   Booh  Amaranthaceae  Fodder and medicinal value 

3.   Alhagi maurorum  Kandero  Fabaceae  Fencing around huts, medicinal value 

4.   Calotropis procera  Ak  Asclepiadaceae Medicinal value, silky floss of the seeds is used for stuffing pillows, the smoke of 

the plant is used to keep away mosquitoes 

5.   Capparis decidua   Kirar  Capparidaceae Trunk is used for fuel, unripe fruit is used as vegetable, ripened food is edible, 

young twigs used as fodder 

6.   Cressa cretica  Oin  Convolvulaceae  Fodder and also considered as a neutralizer for acidic soils 

7.   Crotolaria burhia  Chag  Fabaceae  Fodder, medicinal value, thatching of roof 

8.   Cynodon dactylon   Chhabar  Poaceae  Fodder, medicine 

9.   Desmostachya bipinnata   Drabh  Poaceae  Fodder, stalk used for brooms, leaves woven to make ropes 

10.   Euphorbia hirta  Kher wal  Euphorbiaceae  Fodder 

11.   Leptadenia pyrotechnica  Khip  Asclepiadaceae  Branches used for thatching of roof, fodder, medicinal value 

12.   Saccharum bengalense  Booro  Poaceae Stem used for making roof and chairs, leaves used for making mats, used in a 

medicine for cattle 

13.   Saccharum spontaneum  Booro/Munian  Poaceae Stem used for making roof and chairs, leaves used for making mats, used in a 

medicines for cattle 

14.   Suaeda fruticosa  Lani  Chenopodiaceae  Ash of the plant is used for washing of clothes, the plant is also a fodder for 

camels 

15.   Typha domingenasis  Pan  Typhaceae  Leaves used for thatching of roof and making mats 

16.   Typha elephantina  Pan  Typhaceae  Used for making jute bags, leaves used for thatching of roof and making mats 

Page 165: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 136 HPK

Table 6‐12: List of Birds Observed/Reported in the Project Area 

No.  Common Name  Scientific Name 

Status  Occurrence  Listing 

Migratory 

Resident 

Common 

Abundant 

Less Common 

Rare 

WPO/Act 

IUCN Red List 

CMS Appendix 

CITES Appendix 

1.   Ashy headed finch lark  Eremopterix grisea    x  x               

2.   Bank myna  Acridotheres ginginianus    x  x               

3.   Bay backed shrike  Lanius vittatus    x  x               

4.   Black drongo/King crow  Dicrurus macrocercus    x  x               

5.   Black kite  Milvus migrans    x  x        x      II 

6.   Black partridge  Francolinus francolinus    x      x           

7.   Black redstart  Phoenicurus ochruros  x        x           

8.   Black crowned finch lark  Eremopterix nigreceps    x  x               

9.   Black shouldered kite  Elanus caeruleus/E.leucurus    x  x        x      II 

10.   Black‐winged stilt  Himantopus himantopus  x    x            II   

11.   Blue cheeked bee‐eater  Merops superciliosus  x        x           

12.   Blue rock pigeon  Columba livia    x    x            III 

13.   Blue throat  Luscinia svecica  x        x           

14.   Blyth’s reed warbler  Acrocephalus dumetorum  x        x           

15.   Brahminy kite  Haliastur indus    x  x        x      II 

16.   Brown tree pipit  Anthus trivialis  x        x           

17.   Cattle egret  Bubulcus ibis    x  x        x      III 

18.   Chestnut shouldered petronia  Petronia xanthocollis    x  x               

19.   Chiffchaff  Phylloscopos collybita  x    x               

20.   Collared dove  Streptopelia decaocto    x  x               

Page 166: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 137 HPK

No.  Common Name  Scientific Name 

Status  Occurrence  Listing 

Migratory 

Resident 

Common 

Abundant 

Less Common 

Rare 

WPO/Act 

IUCN Red List 

CMS Appendix 

CITES Appendix 

21.   Common/Blue kingfisher  Alcedo atthis    x  x               

22.   Common babbler  Turdoides caudatus    x    x             

23.   Common buzzard  Buteo buteo  x        x    x      II 

24.   Common kestrel  Falco tinnunculus  x    x        x    II  II 

25.   Common redstart  Phoenicurus phoenicurus  x          x         

26.   Common sandpiper  Actitis hypoleucos  x    x               

27.   Common snipe  Gallinago gallinago  x        x        II   

28.   Crested honey buzzard  Pernis ptilorhynchus    x      x    x      II 

29.   Crested lark  Galerida cristata    x    x             

30.   Crow pheasant  Centropus sinensis    x  x               

31.   Desert lark  Ammomanes deserti    x  x               

32.   Desert wheatear  Oenanthe deserti  x        x           

33.   Egyptian/Scavenger vulture  Neophron percnopterus  x        x    x      II 

34.   Eurasian sparrow hawk  Accipiter nisus    x      x    x    II  II 

35.   Eurasian scops owl  Otus scops    x  x              II 

36.   Golden backed woodpecker  Dinopium benghalense    x  x               

37.   Great grey shrike  Lanius excubitor    x  x               

38.   Grey partridge  Francolinus pondicerianus    x  x               

39.   Hoopoe  Upupa epops    x  x               

40.   House crow  Corvus splendens    x  x               

41.   House sparrow  Passer domesticus    x    x             

Page 167: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 138 HPK

No.  Common Name  Scientific Name 

Status  Occurrence  Listing 

Migratory 

Resident 

Common 

Abundant 

Less Common 

Rare 

WPO/Act 

IUCN Red List 

CMS Appendix 

CITES Appendix 

42.   House swift  Apus affinis    x  x               

43.   Indian river tern  Sterna aurantia    x  x               

44.   Indian robin  Saxicoloides fulicata    x  x               

45.   Indian roller  Coracias benghalensis    x  x               

46.   Indian sand martin  Riparia paludicola    x  x               

47.   Indian tailor bird  Orthotomus sutorius    x  x               

48.   Indian tree‐pie  Dendrocitta vagabunda    x  x               

49.   Indian/Common moorhen  Gallinula chloropus  x    x               

50.   Indian/Common myna  Acridotheres tristis    x  x               

51.   Jungle babbler  Turdoides striatus    x      x           

52.   Kentish/Snowy plover  Charadrius alexandrinus  x        x        II   

53.   Little brown dove  Streptopelia senegalensis    x  x              III 

54.   Little cormorant  Phalacrocorax niger    x  x        x       

55.   Little egret  Egretta garzetta    x  x        x       

56.   Little grebe  Tachybaptus ruficollis    x  x               

57.   Little green Bee‐eater  Merops orientalis    x    x             

58.   Little owl  Athene noctua    x      x          II 

59.   Little ringed plover  Charadrius dubius  x    x            II   

60.   Little stint  Calidris minuta  x        x        II   

61.   Little tern  Sterna albifrons  x        x        II   

62.   Long‐eared owl  Asio otus  x          x        II 

Page 168: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 139 HPK

No.  Common Name  Scientific Name 

Status  Occurrence  Listing 

Migratory 

Resident 

Common 

Abundant 

Less Common 

Rare 

WPO/Act 

IUCN Red List 

CMS Appendix 

CITES Appendix 

63.   Long‐tailed grass warbler  Prinia burnesii    x      x      NT     

64.   Marsh harrier  Circus aeruginosus  x    x        x      II 

65.   Merlin  Falco columbarius  x          x  x    II  II 

66.   Night heron  Nycticorax nycticorax    x  x        x       

67.   Paddy bird/Indian pond heron  Ardeola grayii    x  x        x       

68.   Pied bushchat  Saxicola caprata    x  x               

69.   Pied kingfisher  Ceryle rudis    x  x               

70.   Pied/Variable wheatear  Oenanthe picata  x    x               

71.   Purple moorhen  Porphyrio porphyrio    x  x        x       

72.   Purple sunbird  Nectarinia asiatica    x  x               

73.   Red turtle dove  Streptopelia transquebarica    x      x           

74.   Redshank  Tringa totanus  x    x            II   

75.   Red‐vented bulbul  Pycnonotus cafer    x  x               

76.   Red‐wattled lapwing  Hoplopterus indicus    x  x               

77.   Richardʹs pipit  Anthus novaeseelandiae    x      x           

78.   Rose‐ringed parakeet  Psittacula krameri    x      x        III   

79.   Ruff  Philomachus pugnax  x        x        II   

80.   Rufous backed shrike  Lanius schach    x  x               

81.   Rufous tailed/Isabelline shrike  Lanius isabellinus  x        x           

82.   Short toed eagle  Circaetus gallicus    x  x        x      II 

83.   Sindh jungle sparrow  Passer pyrrhonotus    x      x           

Page 169: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 140 HPK

No.  Common Name  Scientific Name 

Status  Occurrence  Listing 

Migratory 

Resident 

Common 

Abundant 

Less Common 

Rare 

WPO/Act 

IUCN Red List 

CMS Appendix 

CITES Appendix 

84.   Shikra  Accipiter badius    x      x      LC     

85.   Sindh nightjar  Caprimulgus mahrattensis    x  x               

86.   Sindh pied woodpecker  Dendrocopos assimilis    x      x           

87.   Small Indian pratincole  Glareola lactea    x  x               

88.   Small/Wandering minivet  Pericrocotus cinnamomeus    x  x               

89.   Spotted little owl  Athene brama    x  x              II 

90.   Streaked weaver bird  Ploceus manyar    x  x               

91.   White/Pied wagtail  Motacilla alba  x    x          LC     

92.   White breasted waterhen  Amaurornis phoenicurus    x  x               

93.   White browed wagtail  Motacilla maderaspatensis    x  x               

94.   White eyed buzzard  Butastur teesa    x      x    x      II 

95.   White tailed plover  Chettusia leucura  x    x               

96.   White throated munia  Eodice malabarica/Lonchura malabarica    x      x          III 

97.   White‐breasted kingfisher  Halcyon smyrnensis    x  x               

98.   White‐browed fantail flycatcher  Rhipidura aureola    x  x               

99.   White‐cheeked bulbul  Pycnonotus leucogenys    x  x               

100.   Wire tailed swallow  Hirundo smithii    x  x               

101.   Yellow bellied prinia  Prinia flaviventris    x  x               

Abbreviations: WPO – Wildlife Protection Ordinance; LC – Least concerned; NT – Near threatened 

Page 170: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 141 HPK

Table 6‐13: List of Mammals Observed/Reported in the Project Area 

No.  Common Name  Scientific Name 

Occurrence  Listing 

Common 

Abundant 

Less Common 

Rare 

WPO/Act 

IUCN Red List 

CITES Appendix 

1.   Asiatic jackal  Canis aureus  x            III

2.   Black‐naped hare  Lepus nigricollis      x         

3.   Balochistan gerbil  Gerbillus nanus  x             

4.   Desert cat  Felis silverstris      x        III

5.   Fishing cat  Prionailurus viverrinus        x  x  VU II 

6.   Five stripped palm squirrel  Funambulus pennantii  x             

7.   Hog deer  Axis porcinus        x  x     

8.   House mouse  Mus musculus  x             

9.   Indian/Bengal fox  Vulpes bengalensis      x         

10.   Indian bush rat  Golunda ellioti  x             

11.   Indian desert jird  Meriones hurrianae  x             

12.   Indian pangolin  Manis crassicaudata        x  x  LC  

13.   Indian gerbil  Tatera indica    x           

14.   Indian grey mongoose  Herpestes edwardsi  x            III

15.   Indian porcupine  Hystrix indica  x             

16.   Indian wild boar  Sus scrofa  x             

17.  Little Indian field mouse  Mus booduga  x             

18.  Long eared desert hedgehog  Hemiechinus collaris  x             

19.   Small Indian mongoose  Herpestes javanicus  x        x    III

20.   Smooth coated otter  Lutrogale perspicillata        x  x  VU II 

Abbreviations: WPO – Wildlife Protection Ordinance; VU – Vulnerable; LC – Least Concerned 

Page 171: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 142 HPK

Table 6‐14: List of Reptiles Observed/Reported in the Project Area 

No.  Common Name  Scientific Name 

Occurrence  Listing 

Common 

Less Common 

Rare 

WPO/Act 

IUCN Red List 

CITES Appendix 

1.   Black pond/Spotted turtle  Geoclemys hamiltonii      x  x     

2.   Brahminy blind snake  Typhlops braminus    x    x     

3.   Brilliant agama  Trapelus agilus isolepis  x           

4.   Brown river turtle  Kachuga smithii    x    x    II 

5.   Checkered keelback  Xenochrophis piscator piscator    x    x    III 

6.   Cobra  Naja naja    x      DD II 

7.   Common ground agama  Trapelus ruderata baluchiana    x         

8.   Desert monitor  Varanus griseus koniecznyi    x    x    I 

9.   Dhaman/Rat snake  Ptyas mucosus  x      x    II 

10.   Garden lizard  Calotes versicolor  x           

11.   Glossy bellied racer  Coluber vetromaculatus   x           

12.   Indian fringe‐toed lizard  Acanthodactylus cantoris cantoris  x           

13.   Indian monitor  Varanus bengalensis  x      x    I 

14.   Indian sand boa  Eryx johnii johnii    x         

15.   Indian sand swimmer  Ophiomorus raithmai  x           

16.   Indian spiny‐tailed lizard  Uromastyx hardwickii  x          II` 

17.   Pakistan ribbon snake  Psammophis leithii    x    x     

18.   Royal diadem snake  Spalerosophis diadema diadema    x    x     

19.   Saw scaled viper  Echis carinatus pyramidum  x           

20.   Yellow bellied house gecko  Hemidactylus flaviviridis  x           

Abbreviations: WPO – Wildlife Protection Ordinance; DD – Data Deficient 

Page 172: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 143 HPK

Photographs: Biological Environment of the Project Area 

 

Photograph 6‐17: Salvadora persecia    Photograph 6‐18: Ficus religiosa 

 

Photograph 6‐19: Acacia nilotica    Photograph 6‐20: Bombax ceiba 

 

Photograph 6‐21: Capparis Spinosa  Photograph 6‐22: Cordia myxa 

Page 173: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 144 HPK

 

Photograph 6‐23: Cassia holosericeai  Photograph 6‐24: Dalbergia sissoo 

 

Photograph 6‐25: Crested lark  Photograph 6‐26: Egyptian vulture 

 

Photograph 6‐27: Glossy ibis    Photograph 6‐28: Indian robin 

Page 174: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 145 HPK

 

Photograph 6‐29: Large cormorant  Photograph 6‐30: Pied bushchat 

 

Photograph 6‐31: Redshank    Photograph 6‐32: Sindh pied woodpecker 

 

Photograph 6‐33: White browed fantail    Photograph 6‐34: Indian desert monitor lizard 

Page 175: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 146 HPK

 

Photograph 6‐35: Indian garden lizard    Photograph 6‐36: Asiatic jackal 

 

Photograph 6‐37: Botanist during the EIA field 

survey  

Photograph 6‐38: Wildlife specialist during the 

EIA field survey 

Page 176: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 147 HPK

Socioeconomic Environment

A random sampling survey was carried out within Block (E.L. 2568‐21) and in its close 

surroundings to collect first hand reliable and authentic socioeconomic data of the 

area. For this purpose a semi‐structured interview schedule was used. The information 

was collected with the objective to obtain a clear and complete understanding of the 

social and economic conditions of the locals, assess the vulnerability of the local 

communities and identify the concerns of locals regarding the proposed project 

activities. During the socioeconomic field visit substantial information was collected 

that was required to understand the socioeconomic conditions of the area and the 

impacts of the proposed project on local communities. Since, the socioeconomic 

assessment and recommendations for mitigation measures primarily addresses the 

issue despite of individual/community. Issues related to individual/community will be 

mitigated through an on‐site mechanism suggested in the EIA. The local residents will 

be able to register their complaints and grievances during the project and the 

individual or community not covered in this study will receive due compensation or 

mitigation for its complaint. Socioeconomic environment and infrastructure of the 

project area is shown in Figure 6‐6. 

6.3.1 Study Objectives

The socioeconomic study undertaken for the EIA was designed and conducted to meet 

the following objectives: 

To assess the human environment of the area i.e. to determine the life’s quality of 

communities within the region of influence; 

To have an insight into the day to day activities of people especially focusing on 

their income generating activities viz. agriculture, livestock and labor;  

To access the vulnerabilities of the local communities and the effects of project 

activities on their quality of life and; 

Consultation with communities regarding the proposed project activities and to 

find out their concerns and aspirations. 

6.3.2 Study Methodology

Random Sampling Survey techniques were used to collect data in the project area. The 

sampling locations were carefully selected for true representation of the project area. 

Specific tools were used to conduct the study included informal group interviews, 

focus group discussions, need assessment, participant observation, secondary data 

review, village meetings and social mapping. At some places, key informants and 

community activists were used as the main instruments for data collection. Focused 

group discussions were conducted to assess the socioeconomic conditions, concerns 

and problems of the communities.  

Page 177: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 148 HPK

6.3.3 Administrative Boundaries

Kotri North Block (E.L. 2568‐21) is located in geographical jurisdiction of Jamshoro, 

Matiari and Hyderabad districts of Sindh province with a total area coverage of 

approximately 1,397 square kilometers (km2). Out of total covered area of the block 

district Jamshoro contributes the major part i.e. 1,133.5 km2 whereas, district Matiari 

shares approx. 257 km2 and district Hyderabad contributes about 6.5 km2. Taluka wise 

distribution of abovementioned districts is provided in table below:  

District   Taluka  Area Coverage (km2) 

Jamshoro Kotri  442 

Manjhand  691.5 

Hyderabad  Hyderabad  6.5 

Matiari 

Hala  210 

Matiari  4 

Saeedabad  43 

6.3.4 Demographic Profile

During the field visit of EIA population data on 23 villages/goths was collected and this 

data is presented in Table 6‐15. All villages/goths/towns were carefully selected where 

exploration activities have been planned or which might be influenced by the 

propsoed exploration and associated development activities.  

According to the recent census of 2017, the population of the area has been 

significantly increased having annual growth rate of 2 – 3% to the 1998. For instance, 

the population of Hyderabad districts have annual growth rate of 2.02%. If the 

population grows at the present rate, it will be doubled in next 31 years. Population of 

districts where Kotri North Block falls are detailed in table below: 

Kotri North Block (E.L. 2568‐21)

District  Population (Census)

Year 2017 Year 1998 

Jamshoro  993,142  582,094 

Matiari  769,349  494,244 

Hyderabad  2,199,463  1,494,866 

Source: www.pbs.gov.pk 

a. Major Castes 

In surveyed villages it is observed that the main castes/tribes (biraderies) inhabiting the 

project area are Khaskheli, Mari Bloch, Khoso, Bhambro, Mallah, Talpur, Solangi, 

Bhatti, Mughal, Syed, Shaikh, and Lashari. Some other minor biraderies of the area 

include Bhenchai, Nizamani, Umrani, Daito, Bheel, Kohli, Qambrani, Jamali, Hajana, 

Khokar, Shar, Palari and Chandio. Other populations depending on their professions 

like mistri, naaee, kumhar and lohars etc. are also inhabitants of the project area. Sunni 

sect is more prevalent in the area as compared to Shias. Other minorities that exist in 

Page 178: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 149 HPK

the area are Christians, Hindus, Ahmadis and other schedule castes. The tribal 

distribution of the surveyed villages is provided in Table 6‐16. 

b. Basic Amenities 

The cities and towns of the districts in the project area are inter‐connected through a 

network of blacktop roads and jeepable tracks in fair weather. The access to most of 

the villages of the project area is provided through katcha roads. The system of 

communication in the project area is satisfactory. The project area can be accessed 

through National Highway which enters the Kotri North Block from Karachi. The area 

is connected to main cities of nearby districts through National Highway. Karachi – 

Hyderabad motorway (M9) also enters the project area from southern side. A number 

of farm to market roads also exist in the area. Brick roads are also in place connecting 

villages with the main metaled road.  

The main line of Pakistan railways runs through the districts. The major railway 

stations exist in Hyderabad, Jungshahi and Latifabad. Besides these railway stations 

there are many small railway stations located within the project area. The nearest 

airports to the project area are Karachi, Nawabshah and Moenjo Daro. 

Electricity and mobile facilities are present in almost every part of the project area. Out 

of total 23 visited villages, electricity is available in 16 villages/towns however, the 

residents complained about the load shedding. Project area has also a network of post 

offices and postal facilities as well. 

c. Languages 

Sindhi is the mother tongue language being spoken in the project area followed by 

Urdu and Punjabi etc. The locals in rural areas follow their norms and values very 

rigidly/strictly than that of urban areas. But with the passage of time and development 

trends, these societal values has been changed and are not followed as rigidly as it 

used to be in the past. 

d. Water Usage 

There is a proper source of irrigation in many parts of the project area and in some 

areas the land is irrigated with rainy water (mostly western and northwestern). 

Drinking water supply schemes developed by Government departments also serves 

the rural population. The remaining population fulfil their domestic water need from 

groundwater borings, open dug wells and hand pumps. Sufficient amount of water for 

drinking and domestic purposes is available in the area. 

e. Pattern of Settlements 

Settlements are mainly in the form of large and complex clusters/villages. At places, 

these clusters are big blocks of 100 plus household while at other places small blocks 

of 5 to 10 households also exist. Generally, aggregation of settlements is based on 

kinship relations, with each settlement being inhabited by descendants from the same 

family lineage. All the villages in the project area have usually two parts, the core and 

Page 179: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 150 HPK

the suburbs. Usually the core contains the bulk of population while the suburbs have 

cluster of houses along the roadsides where usually one family resides. There are two 

considerations for moving outside the core village. Firstly, to have easy access to the 

family’s farmlands and secondly, as the population of a household grows denser, it 

requires more space for living. 

f. Marriages 

The ideal marriage age is 18 and 25 for females and males respectively in the project 

area. These early marriages result in big households, which is clear from their high 

populations. Presently, the trend of early marriages is on its decline due to increase in 

literacy level. The concept of dowry has taken firm roots in the population. Marriages 

are occasions of festivity for everyone in the village. A three dish menu is served for 

common guests while special guests get special dishes. 

g. Education 

People in the project area are very conscious of the educational needs of the society. In 

most of the cases every child of school‐going age in the project area is getting 

education in one way or another. Almost every village of the study area has primary 

school either in public or private sector. Middle and high schools are also present in 

some of the villages of the project area. The network of Boys and Girls Degree Colleges 

both in public and private sectors at Hyderabad and Jamshoro is providing higher 

educational facilities. Main medium of education in most of the local schools is Urdu. 

Private schools also exist in the project area where medium of education is mostly 

English.  

h. Health 

There are District Head Quarter (DHQ) Hospitals at Hyderabad and Matiari. There are 

Basic Health Units (BHUs) and a number of Rural Health Centre (RHCs) also exist in 

the project area and providing health care facilities to countless number of locals. In 

addition to that, private health care facilties also exist in the project area. 

During the survey, locals termed five most common diseases in the project area which 

include acute respiratory infection, diarrhea, fever (clinical malaria), dysentery and 

cough. Malaria tops the list of diseases, as every one out of ten patients is affected. 

Serious medical cases are taken to Hyderabad and Karachi where better medical 

facilities are available.  

6.3.5 Economy of the Project Area

Economy of the project area is dependent on four occupations i.e. agriculture, services, 

small business and livestock grazing. People are also involved in occupations such like 

shopkeeping, transport, masonry and other daily wage earning occupations. However, 

the bulk of workforce is working outside the village in armed forces and in large cities 

such as Hyderabad and Karachi or abroad in the middle‐east. 

 

Page 180: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 151 HPK

a. Major Occupations 

Agriculture 

There is a proper source of irrigation in the major parts of the project area. The existing 

standards and management levels of agriculture in the project area are satisfactory. As 

a result, the present subsistent agriculture produces enough to meet the food and 

financial requirements of the farm population. Uncertainty in precipitation in some of 

the rain‐fed areas is the primary constraint on agricultural development. 

Diversified cropping pattern were practiced under existing conditions due to the 

irrigation supplies. Whole of the area available for cultivation is very much fertile and 

possesses great potentials for agricultural production provided optimum water and 

non‐water inputs are applied. However, the other non‐water inputs will remain 

underutilized unless adequate irrigation water is provided which is the basic and 

more important input. 

Tractors and harvesters are usually used by the locals for agricultural purposes. Main 

Kharif crops are Jawar, Bajra, Rice, Cotton and Sugarcane while Rabi Crops are Wheat, 

Barley, Gram, Mung, Peas and fruits like Mango, Banana, Chikoo, Guava, Grapes, 

Jamun, Papaya, Phalsa and others are grown. Hyderabad district is also famous for the 

production of flowers particularly roses (Rosa damascena). 

Livestock 

The practice of livestock rearing is majorly for household dairy needs. The concept of 

livestock rearing for commercial purposes is very rare. As such this particular aspect 

of an agrarian economy is largely overlooked. Majority of the households keep 

livestock e.g. cows, goats and sheep. Buffaloes are common in irrigated areas only, 

though few were observed in the parts of project area where pasture is less available. 

All the animals are of native breed and thus they can survive the local harsh 

environment and drought like conditions better.  

Feeding practices include free grazing and stall‐feeding. Under free grazing system, 

rangelands and government lands are used. Agricultural fields after harvests are also 

used for grazing. Family members usually carry out the activity of grazing their 

livestock but sometimes the services of local herder are taken. Some of the tribes have 

large flocks of animals. 

It is estimated that 80% of the work related to livestock is carried out by women and 

children. This includes watering, feeding, milking and bathing the livestock. People 

also keep poultry for domestic consumption of eggs and meat. Goats outnumber any 

other farm animals as it can survive on meagre water and fodder. Data reveals that on 

the average, each household has 7.5 heads of farm animals with at least 10 goats. 

b. Other Occupations 

Apart from agriculture and livestock, the male population has to resort to some other 

alternatives as well. The other major occupations in the area are government services, 

Page 181: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 152 HPK

shop keeping, fish farms and daily‐wagers. Some of the locals have also gone abroad 

for work in the Gulf States. Poultry farming is also carried out on reasonable scale in 

the area by the locals. 

6.3.6 Gender Profile

Literature in gender studies suggests that poverty exacerbates gender disparities. 

“Pakistan is only one of 12 countries which spends less than 2% of its GDP on 

education” (HRCP, 2004). Out of this whole budget, only a tiny amount goes into the 

primary education which is not enough for providing separate infrastructure for both 

genders. Co‐education is not common especially after the primary education is over. 

This explains a huge dropout rate amongst girls than prevalent for boys. Furthermore, 

the literature also shows that inequalities between girls and boys in access to schooling 

or adequate health care are more acute among the poor than among those with higher 

incomes. These disparities disadvantage women and girls and limit their capacity to 

participate in and benefit from development. 

Siddiqui et al (2003) produces evidence that women empowerment leads to better 

household consumption. “Empirical evidence showed if woman has empowerment 

and control over household resources, they spend more money on basic needs such as 

foods, clothing, education and health.” (Sathar and Kazi, 1997 and Siddiqui et al, 2003). 

Focused group discussions separately with men and women in the area lead to the 

following two generalizations: 

Scarcity of resources aggravates the gender inequalities, depriving women of basic 

needs, particularly education; and 

Fatalistic cultural traditions/institutions work the same way as scarcity of 

resources and results in women’s illiteracy. 

The scarcity of resources is evident. When voice about cultural traditions and 

institutions is raised, it necessarily includes religion as a guiding force. In the Sindhi 

context, culture and religion are embedded deeply in social norms and behaviors. 

Similarly, religion (as a variable noted in Dollar and Gatti’s analysis) may be attributed 

to ‘extreme patriarchy’ a phenomenon cementing women alienation in rural 

uneducated societies. 

Women are not equal to men in the project area. There are various manifestations of 

this phenomenon. For example, at bus stops there is neither sitting arrangements for 

women nor toilet facilities. Women generally observe purdah (seclusion) from 

outsiders. The purdah restrictions are more stringent for young girls. Adult women 

may appear before male members of the same tribe. Restrictions on mobility vary with 

the marital status, age of women, tribe affiliation and local customs. Mostly women in 

Sindhi families of all ages shake hand with the male relatives. Married and relatively 

older women are freer to attend marriage, death and birth ceremonies in other villages 

and even go to markets with male members of the family. 

Page 182: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 153 HPK

A married woman has to seek permission for a social visit from her husband or 

mother in law and is usually accompanied by her husband or sister in law. Married 

woman also do not observe purdah from male members of the same tribe or village. In 

agriculture activity women help their male members in the fields. 

Females from landowning families do not work in the fields. The gender specialist 

analyzed that the poverty and women mobility are directly proportional. As much as 

they get rich, the females secluded to their homes and observe strict purdah or even 

wear black or mostly white veils. All women take dupata on their heads even inside 

their homes and during household chores. Girls before attaining the puberty are 

confined to their homes. For outdoor activities of fire wood collection, agriculture or 

water fetching they use the same dupatas but for visiting the relatives for marriage and 

death ceremonies and doctors for health issues, women wear Ajrak or big embroidered 

dupata. 

Shopping or recreational visit are very uncommon for women. Shopping for 

unmarried girls is carried out by brothers or father while husbands do for the married 

women. Mostly communities in the project area are peaceful. Karokari or honor killing 

is uncommon in the area and no cases have been heard or reported for a long time 

however, there are still killings of women on different pretexts ‘accidentally’. The 

brutal killing is thought to discourage women’s mobility. 

Decision making inside the household resides on the male head of the household. 

Women are generally not consulted in issues related to households’ major decisions on 

lands, cropping, marketing and livestock etc. Eldest women in the household usually 

have issues related to marriages. 

6.3.7 Development Needs

The analysis of field survey data suggests that education, health, electricity, potable 

water and gas rank highest amongst all priorities but their relevant weightage varies 

with locality i.e. demand for drinking water is higher in the project area that falls away 

from Indus River and potable sources of drinking water are not available in the area. 

The top three development priorities expressed by each sampled survey is shown in 

Table 6‐17. Provision of waste management facilities and others e.g. employment, 

micro financing & provision of sewerage system were identified as their priorities of 

lesser weightage as compared to education, health, electricity, potable water and gas. 

6.3.8 Archaeological and Religious Sites

There are no reported or documented sites of archaeological significance within the 

project area that are protected by either the federal government under the Antiquities 

Act, 1975 or the Government of Sindh under the Sindh Cultural Heritage 

(Preservation) Act, 1994.  

Antiquities are protected under clause 19(1) of the Antiquities Act 1975 and this law 

defines an antiquity as: “any ancient (an antiquity in existence for a period of not less 

than 75 years) product of human activity, movable or immovable”. Any antiquities 

Page 183: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 154 HPK

found in the area that falls under the proponent’s area of operation, must be protected, 

and not removed from their location. During the survey of the project area no surface 

archaeological site (protected) was observed however, there are several sites of 

religious and cultural interest in the entire spread of Kotri North Block.  

A total 12 notified archaeological sites exist in Hyderabad district whereas, 4 in Matiari 

and 8 in Jamshoro district. However, none of these falls under the geographical 

jurisdication of Kotri North Block. It is important to highlight that, there are several 

sites of cultural and religious significance spreading in entire stretch of Kotri North 

Block in the form of shrines and graveyards. Therefore, mitigation measures suggested 

for the protection of archaeological, cultural, heritage and religious environment will 

be ensured.

Page 184: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 155 HPK

Table 6‐15: Households and Population Data of Goths/Villages/Towns 

No.  Village/Town Name  District  No. of Household*  Population* 

1.   Goth Sufan Bacho   Matiari  75  800 

2.   Goth Salaro   Matiari  100  900 

3.   Goth Haji Shabu   Matiari  120  1,200 

4.   Goth Suleman Barejo  Matiari  15  80 

5.   Goth Mehram Khaskheli  Matiari  300  2,000 

6.   Goth Bachal Dehta  Matiari  250  1,500 

7.   Shahpur  Matiari  600  4,000 

8.   Goth Tajpur  Matiari  1,200  5,500 

9.   Goth Tadri Mori  Hyderabad  10  90 

10.   Goth Tando Syed Khan Mitho  Hyderabad  1,500  6,500 

11.   Goth Raees Ghulam Ali Mari  Hyderabad  60  650 

12.   Goth Hayat Bhatti  Hyderabad  250  900 

13.   Goth Sayen Dino Mallah  Jamshoro  400  1,500 

14.   Goth Darya Baig Mughal  Hyderabad  1,200  9,000 

15.   Goth Khuda Baksh  Jamshoro  8  40 

16.   Goth Bakhshia Mari  Jamshoro  300  1,200 

17.   Goth Aliabad  Jamshoro  2,000  15,000 

18.   Goth Karim Deno  Jamshoro  50  500 

19.   Goth Jaitharo  Jamshoro  20  80 

20.   Goth Bego Khan Mirjat  Jamshoro  800  4,500 

21.   Goth Haji Ishaq  Hyderabad  45  400 

22.   Goth Gulshan‐e‐Shahbaz  Hyderabad  1,100  5,500 

23.   Goth Wadero Misri  Hyderabad  90  700 

  Total  2,319 14,750

Notes: * Approximate numbers (information provided by the locals and best judgement during the field survey) 

Page 185: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 156 HPK

Table 6‐16: Tribal Distribution 

No.  Village/Town Name  Vital Tribes 

1.   Goth Sufan Bacho   Bhenchai 

2.   Goth Salaro   Nizamani/Khaskheli 

3.   Goth Haji Shabu   Mari Baloch 

4.   Goth Suleman Barejo  Khoso 

5.   Goth Mehram Khaskheli  Khaskheli, Bhambro, Khoso 

6.   Goth Bachal Dehta  Mallah, Umrani, Daito 

7.   Shahpur  Khoso, Mari, Kohli, Bheel 

8.   Goth Tajpur  Talpur, Solangi, Khoso, Qambrani, Jamali 

9.   Goth Tadri Mori  Khoso, Hajana, Khaloro  

10.   Goth Tando Syed Khan Mitho  Mari, Mirbahar, Khaloro, Hajana 

11.   Goth Raees Ghulam Ali Mari  Mari Bugti  

12.   Goth Hayat Bhatti   Bhatti 

13.   Goth Sayen Dino Mallah  Mirbahar, Khaloro 

14.   Goth Darya Baig Mughal  Mughal  

15.   Goth Khuda Baksh  Mari Bugti 

16.   Goth Bakhshia Mari  Sheikh, Mari, Mallah, Kohli 

17.   Goth Aliabad  Lashari, Shar, Hajana, Baloch, Khokar 

18.   Goth Karim Deno   Mirbahar 

19.   Goth Jaitharo  Burfat 

20.   Goth Bego Khan Mirjat  Burfat, Khoso, Mirjat, Shora, Kanrio 

21.   Goth Haji Ishaq  Laghari, Mari 

22.   Goth Gulshan‐e‐Shahbaz  Baloch, Chandio, Palari, Kholro 

23.   Goth Wadero Misri  Sheikh, Palari 

 

 

 

 

 

 

 

 

 

 

Page 186: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 157 HPK

Table 6‐17: Development Priorities of the Communities of Suveyed Villagees 

Village/Goth Name Development Priorities 

1  2  3 

Goth Sufan Bacho   Electricity  Health  ‐ 

Goth Salaro   Health  Employment  ‐ 

Goth Haji Shabu   Electricity  Health  Education 

Goth Suleman Barejo  Health  Education  ‐ 

Goth Mehram Khaskheli  Health  Waste Management  ‐ 

Goth Bachal Dehta  Education  Health  ‐ 

Shahpur  Waste Management  Employment  Micro financing 

Goth Tajpur  Education  Waste management  Micro financing 

Goth Tadri Mori  Electricity  Health  Employment 

Goth Tando Syed Khan Mitho  Potable water  Employment  ‐ 

Goth Raees Ghulam Ali Mari  Health  Employment  ‐ 

Goth Hayat Bhatti  Gas  Employment  ‐ 

Goth Sayen Dino Mallah  Electricity  Waste management  Employment 

Goth Darya Baig Mughal  Gas  Employment  ‐ 

Goth Khuda Baksh  Electricity  Potable water  ‐ 

Goth Bakhshia Mari  Electricity  Potable water  Education 

Goth Aliabad  Gas  Potable water  Health 

Goth Karim Deno  Health  Education  Potable water 

Goth Jaitharo  Electricity  Gas  Potable water 

Goth Bego Khan Mirjat  Education  Health  ‐ 

Goth Haji Ishaq  Education  Potable water  Education 

Goth Gulshan‐e‐Shahbaz  Potable water  Health  Sewerage system 

Goth Wadero Misri  Health  Waste management  ‐ 

 

Page 187: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

h

h

h

h

h

Goth Rais Ghulam Ali Mari

Goth Tando Syed Khan Mitho

Sindh UniversityJamshoro

DHQ Matiari

Jamshoro Power Plant/ Water Sample 5

Sindh Agriculture University

Goth Akro

Goth Tajpur

Goth Salaro

Goth Jaitharo

Goth Aliabad

Goth Haji Ishaq

Goth Karim Deno

Goth Tadri Mori

Goth Haji Shabu

Goth Khuda baksh

Goth Sufan Bacho

Goth Hayat Bhatti

Goth Bachal DehtaGoth Bakhshia Marri

Goth Suleman Barejo

Goth Bego Khan Mirjat

Goth Sayen Dino Malah

Goth Mehram Khazkheli

Goth Gulshan e Shahbaz

Goth Darya Baig MughalShrine of Wali Muhammad

Dargah Dado Khamiso Fakir

Shrine Baba Allah akhsh Jilani

Dargah Syed Muhammad Shah BukhariGoth Wadero Misri Water Sample 6

Kotri

Hala

Matiari

Thatta

Hyderabad

Latifabad

Tando Adam

Qasimabad

Tando Allahyar

Jamshoro

Matiari

Hyderabad

Thatta

Sanghar

68°30'0"E

68°30'0"E

68°20'0"E

68°20'0"E

68°10'0"E

68°10'0"E25

°50

'0"N

25°5

0'0

"N

25°4

0'0

"N

25°4

0'0

"N

25°3

0'0

"N

25°3

0'0

"N

25°2

0'0

"N

25°2

0'0

"N

·0 1.5 3 4.5 6 7.5 9 10.5 Km

Halcrow Pakistan (Pvt) Limited

Fig 6-6 Communities , Infrastructure & Archeaological Resource Map

Project:EIA for Exploration and Associated Development Activities in Kotri North Block (E.L. 2568-21)

LegendBlock Boundary/Project Area

"" Communties

×[ Gas Compression Facility

×k Graveyard

"' Hospital

!a Power Plant

Shrine

¥B¢ University

h Water Sampling Location

!C Existing Well Site

Nationla HighwayReserve Forest (SOP)

Tehsil BoundariesDistrict Boundaries

United EnergyPakistan

Page 188: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 159 HPK

Photographs: Socioeconomic, Cultural & Archeaological Environment of the Project Area 

 

Photograph 6‐39: A view of Goth Sufan Bacho    Photograph 6‐40: Primary school of Goth 

Salaro 

 

Photograph 6‐41: Graveyard of Goth Salaro    Photograph 6‐42: Graveyard of Goth Sufan 

Bacho 

 

Photograph 6‐43: Primary school in Goth 

Bachal Dehta 

  Photograph 6‐44: A view of Shahpur  

Page 189: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 160 HPK

 

Photograph 6‐45: Boys’ primary school in Goth 

Tajpur  

Photograph 6‐46: Girls’ primary school in Goth 

Tajpur  

 

Photograph 6‐47: Dargah Wali Muhammad in 

Goth Tajpur  

Photograph 6‐48: Sindh Agriculture University 

 

Photograph 6‐49: Primary school in Goth 

Tando Syed Khan Mitho 

  Photograph 6‐50: DHQ Matiari 

Page 190: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 161 HPK

 

Photograph 6‐51: Dargah Syed Muhammad 

Shah Bukhari 

Photograph 6‐52: A view of Goth Bakhshia 

Mari 

 

Photograph 6‐53: A view of Goth Karim Deno    Photograph 6‐54: A view of Goth Jaitharo  

Photograph 6‐55: Dargah Baba Allah Baksh 

Jilani 

Photograph 6‐56: A view of Goth Haji Ishaq

Page 191: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 162 HPK

 

 

Photograph 6‐57: A view of Goth Gulshan‐e‐

Shahbaz 

  Photograph 6‐58: A view of Goth Wadero 

Misri 

Photograph 6‐59: BHU Hyderabad  Photograph 6‐60: High tension electric poles 

crossing through the project area  

Page 192: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 163 HPK

7 Potential Environmental Impacts and Mitigations

This section discusses the potential positive and negative impacts that may arise from 

the proposed exploration & development activities and the mitigation measures that 

will be adopted to reduce or minimize these impacts. The impacts and mitigation 

related to physical, biological and socioeconomic environment have been discussed 

under three separate headings. 

Physical Environment

7.1.1 Changes in Landscape & Soil Erosion

The potential sources for changes in landscape and soil erosion due to the proposed 

project activities include operation of vibroseis, preparation and establishment of 

campsites for seismic/drilling/flow line/GPF operations, preparation of new tracks for 

seismic operations, construction of access roads for well sites, construction of well 

sites, quarrying of gravel or sand, use of project access roads, off‐road travel, 

development of new access tracks and earthworks at RoW/GPF for flow lines. 

a. Source Specific Assessment 

Seismic Operation 

For seismic lines in agricultural lands, shot or deep holes will be drilled for which no 

line clearing will be required. At selected locations upholes will be done which will 

not require significant land clearing. Vibroseis technique will be mostly used in areas 

having flat topography (not in agriculture fields). 

Preparation of Campsites for Seismic Operation – For seismic operation campsites will be 

developed to accommodate the seismic crew. The campsites will preferably be located 

in levelled land and existing clearings to avoid any disturbance to soil or vegetation. 

Preparation of Access Tracks for Seismic Operation – Due to the presence of numerous 

existing access tracks, the need for preparation of new tracks will be minimal. Only 

limited number of tracks might have to be prepared to access remote locations. The 

mitigation measures listed at the end of the section will ensure that any impacts due to 

this activity are kept to the minimum. 

Drilling Operation  

Construction of Access Road – The existing tracks will be upgraded and used as much as 

possible, except for small stretches of new tracks that will be built to access proposed 

well sites. Construction of the access tracks in the levelled sections will not involve any 

major cut and fill. Since, the entire road section will be covered with compacted gravel 

topping (the topping maybe of in‐situ or imported gravel) soil erosion from the road 

will not occur. Because of compacted gravel topping no erosion from the road will 

occur. 

Page 193: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 164 HPK

Mitigation measures to minimize chances of soil erosion or land slippage from the 

entire length of the road have been recommended at the end of this section. This will 

primarily be due to wind erosion, from earth‐fill stock piles and loose road surface 

during construction. 

Construction of Well Sites and Campsites – For each well site, land will have to be cleared 

for the preparation of well site, rig camp, security camp and access track. Considering 

the limited land area requirement for the development of a well and rig campsite 

(approximately 32,400 sq. m for well site, 8,000 sq. m for rig camp and 3,900 sq. m for 

security camp), no significant impacts due to this activity will occur provided the 

mitigation measures listed at the end of this section are adhered with. The well site 

and rig camp are proposed in levelled areas so no large earthworks would be required 

for their construction. The top surface at these areas will be compacted minimizing 

any chances of soil erosion. 

Quarrying of Earth‐fill – During construction of well sites, rig camps and access roads 

fill material may be required. Quarrying if done un‐appropriately can lead to erosion. 

To minimize erosion due to quarrying, the quarry sites will be carefully selected such 

that they are located in levelled areas with existing clearing and the quarry sites are 

restored after use. 

Laying of Flow Lines/Tie‐in/Wellhead Works 

Laying of Flow Lines – Flow lines will be laid to connect producing wells to the main 

processing plant/facility. For the flow lines potential sources of soil erosion may 

include clearing of land along the Right of Way (RoW) which will be 40 to 50 ft. for 

flow lines, use of existing tracks, development of short reaches of new tracks and 

preparation of construction campsites. 

The flow lines generally run along the access roads to the well sites and further to the 

processing plant/facility. In the project area, the flow lines should preferably follow 

the roads developed to access the individual well locations. Lying of flow lines should 

avoid major cut and fill during construction/establishment. 

During the laying of flow lines use of the existing local access tracks and roads should 

be used. Development of new roads should be minimized. The construction camps 

developed during laying of the flow lines should be located in flat terrain and existing 

clearings.  

A certain level of soil loss can be expected from poorly compacted backfills over 

buried flow lines and the use of dirt tracks during laying of flow lines. In order to 

minimize this soil loss, it is recommended that laying of flow line activities should be 

planned keeping into consideration two key principles 1); to minimize disturbance to 

soil by minimizing land clearing and 2); to minimize loss of soil from disturbed areas 

by ensuring soil binding. Detailed mitigation measures based on these principles are 

listed at the end of this section below. 

Page 194: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 165 HPK

Quarrying of Earth‐fill – The impacts will remain the same as discussed in the section 

on drilling operation. 

Construction/Establishment of GPF/CPP 

Establishment/Construction of GPF/CPP – Construction/establishment of GPF/CPP will 

be carried out in an already existing cleared and levelled land. Considering the limited 

land area requirement for the plant and a single access road will be developed, no 

significant impacts due to this activity will occur provided the mitigation measures 

listed at the end of this section are adhered with. Construction will follow good 

industry practices to avoid unnecessary clearing outside the work corridors and 

likelihood of soil erosion along or across natural drainage paths. The access road will 

be properly compacting to minimize soil erosion. Construction camps will be located 

in flat area with existing clearings. 

Quarrying of Earth‐fill – During construction activities fill material may be required. 

Quarrying if done un‐appropriately can lead to erosion. To minimize erosion due to 

quarrying, the quarry sites will be carefully selected such that they are located in 

levelled areas with existing clearing and the quarry sites are properly restored after 

use. 

Road Travel during Project – The use of the road during the project may result in erosion 

of soil from the road surface. On gravel‐topped roads, erosion is less significant due to 

the compacted gravel topping. During the project, erosion from road surface will be 

minimized by sprinkling of water over the project access road and compacting loose 

surfaces wherever required. However, as water is a precious resource in the area there 

will have to be some rationing of its use. 

b. Residual Impacts 

Even after application of mitigation measures the characteristics of the residual 

impacts for each component of proposed project activity are tabulated below: 

Characteristic Activity

Seismic Drilling GPF/CPP Flow Lines 

Duration  Medium Medium  Medium  Medium 

Extent  Local Local  Local  Local 

Likelihood  Certain Possible  Possible  Possible 

Consequence  Minor Minor  Minor  Minor 

Reversibility  Reversible Reversible  Reversible  Reversible 

Significance  Medium Low  Low  Low 

c. Mitigation Measures 

General 

During construction movement of construction equipment will be restricted to 

work areas only to avoid unnecessary disturbance to soils in the project area; 

Page 195: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 166 HPK

To minimize erosion due to quarrying, the quarry sites will be carefully selected 

such that they are located in levelled areas with existing clearing and the quarry 

sites will be restored after use; 

Clearing of vegetation and the cutting of trees will be minimized as much as 

possible; 

Off‐road travel will be strictly prohibited and observance of this will be monitored 

during the operation; 

Vehicles speed will be regulated and monitored to avoid excessive dust emissions; 

Total land uptake by the camps and access road will be kept to the minimum 

required; 

Periodic trainings will be provided to drivers on mitigation measures related to 

off‐road travel and speed limits; 

UEPL Rep and IMC will monitor the access tracks (other than the main access 

track for the project) to be used by water tankers, dumper trucks and other 

vehicles; 

Stream crossings when built shall be such that the slopes of the stream bank are 

properly adjusted and compacted resulting in a stabilized and sealed surface; and 

The width of the new/improved track should be kept to the minimum 5 m 

required, except at bends where safety considerations will dictate additional 

width. 

Seismic Operation 

Seismic lines in the undulating plains will follow natural contours wherever 

possible. However, in areas where seismic line cutting is a requirement, the 

activity will be carried out in a way that would minimize disturbance to natural 

topography and soils;  

The width of seismic lines cleared for vibroseis will be limited to 4.5 m to minimize 

clearing of vegetation and disturbance to soil; 

Construction and seismic camps will be located in existing clearings and on 

levelled land; 

During seismic operation the number of routes used will be kept to a minimum 

and road travel will be minimized; and 

During seismic operation the preparation of new access tracks will be minimized. 

Where improvement of existing tracks or development of short lengths of new 

tracks is unavoidable the width of the access track will not exceed 5.5 m. 

Drilling Operation 

Total land uptake by each well site, rig camp and access road will be kept to the 

minimum required; 

Page 196: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 167 HPK

The access track to each well site will be selected to utilize existing tracks as much 

as possible; 

The well site, rig camp and construction camp will preferably be located in existing 

clearing and levelled land and will avoid major earthworks; and 

The access track to each well site will be properly compacted at the time of 

construction and thereafter properly maintained throughout the entire 

construction and drilling operation. 

Laying of Flow Lines/Tie‐in/Wellhead Works 

Land area requirements for construction camps and RoW of flow line laying will 

be kept to the minimum required; 

Topsoil of the RoW will be separately stored. This topsoil will be backfilled after 

proper compaction ensuring minimum loss of topsoil; 

Clearing of vegetation (especially dense vegetation) will be minimized by careful 

selection of construction camps and flow line alignment; and 

During the laying of flow line, use of the existing local access tracks and gravel top 

roads prepared should be used. Development of new tracks should be minimized. 

The construction camp developed during laying of flow line should be located in 

flat terrain and existing clearings. 

Construction/Establishment of GPF/CPP 

Land uptake for establishment of GPF/CPP and access road will be kept to the 

minimum required; 

Existing access tracks to the GPF/CPP will be used as much as possible; 

Already cleared and levelled land will be acquired for GPF/CPP avoiding major 

earthworks; and  

Access track to the GPF/CPP will be properly compacted at the time of 

construction and thereafter properly maintained throughout the entire operational 

life. 

7.1.2 Soil and Water Contamination

During seismic operations, potential sources of impact will include domestic wastes, 

fuel or oil leakages or spills, bentonite mud used during drilling of shot holes and 

upholes. During drilling operations potential sources may include domestic wastes, 

drilling mud (WBM or may be OBM) and cuttings, produced formation fluids, and 

spillage or leakage of fuel, oil or chemicals. During flow line laying, tie‐in & wellhead 

works wastewater will be generated during hydro‐testing in addition to domestic 

wastes generated at the campsites. Similarly, during construction/establishment of 

GPF/CPP potential sources of impact will include domestic wastes (solid & liquid), 

fuel or oil leakages or spills and other construction wastes.   

Page 197: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 168 HPK

a. Waste Generation and Disposal 

Waste will be generated during the proposed exploration and development activities. 

If the waste generated during the project activities is managed and disposed of in an 

environmentally friendly manner then adverse impacts related to soil and water 

contamination could be avoided or minimized. Moreover, if all mitigation measures 

recommended in this EIA are followed, contamination of soil or water resources is not 

expected to occur and hence impacts will not be cumulative. For the purpose of risk 

assessment the likelihood of oil spillages during transportation has been assessed as 

possible. Because any contamination that may occur will be remediated following 

standard protocols, the effect of such spills will therefore not be cumulative. 

A water based mud system is normally used by United Energy Pakistan Limited due 

to its environmental preference over oil based mud. Generally two broad categories of 

muds are used for drilling of oil or gas wells i.e. oil based and water based. Oil based 

mud is formulated by mixing chemicals with diesel. This mud is not considered to be 

environment friendly due to the risk of contamination of subsurface formations during 

drilling and the generation of oily drilled cuttings which require specialized handling 

and treatment. If cuttings not handled, stored and treated properly then it may result 

in soil and water contamination. UEPL may use Mineral Oil Based Mud System 

(OBM) during drilling activity where wellbore issues will be encountered. However, 

the use of OBM will be limited to short reaches of section/s. In order to cool the 

drilling bit and flush out rock fragments, diesel‐based drilling mud will be 

continuously circulated down the drill pipe and back up the well hole. By circulating 

the mud through the drill string and up out of the hole, the mud will carry oil 

contaminated drilled solids (cuttings) to the surface. The separated solids (cuttings) 

will be temporarily stored in a lined cuttings pit or in steel containers and will be 

transported to land farming site or thermal desorption contractor site in dump trucks 

with water tight containers for treatment. The final disposal of drill cuttings with OBM 

will be carried out after treatment at land farming site or by thermal desorption. OBM 

cuttings will be treated and disposed of in guidance with American Petroleum 

Institute (API) or State of Louisiana, Department of Natural Resources, State Wide 

Order 29B (LSO – 29B). The final disposal of drill cuttings may be disposal into HDPE 

lined pits, concrete lined pits, land spread after dilution with native soil, use as fill 

material for road construction or cement solidification. The drill cuttings and mud 

produced during use of WBM will be disposed of at the well site within lined waste 

pits. Domestic and excavation debris, plastic equipment wrapping is the major waste 

that will be produced during construction of CPF/GPF. 

 

 

 

Page 198: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 169 HPK

A summary of waste generated due to proposed exploration and associated 

development activities, including type and description of waste and recommended 

waste disposal methods are provided in the following table: 

Activity 

Description  Proposed Disposal Method Seismic 

Dri lling 

GPF/CPP 

Flow Lines 

       Food waste: Kitchen waste e.g. fruit, 

meat, vegetable residues etc. 

Burial in bury 

pit/composting 

       

Recycleable waste: Paper, plastic, 

textiles, cardboard, rubber, wood, 

glass, tin cans, metal scrap, 

aluminium cans, ferrous/non‐

ferrous materials and batteries etc. 

Oily waste: Oily rags and used oil 

etc. 

Recycling 

 

 

 

 

 

Recycling & incineration 

       Recycleable waste: Plastic or 

aluminum pipe protection etc. 

Recycling 

       Clinical waste: Syringes, glass 

bottles, used bandages and expired 

drugs etc. 

Incinerate at appropriate 

facility 

       

Grey water: Wastewater from 

kitchen, laundry and showers etc.  

To be first sent to septic 

tanks and finally 

disposed of in soak pits 

In case the soak pits get 

filled during the 

operation, grey water 

will be transferred to 

nearest municipal drains 

with prior approval of 

concerned authorities 

       

Sewage/Black water: Wastewater 

from toilets 

STP should be the 

preferred option 

If no STP is available 

then to be disposed of in 

septic tanks and soak 

pits 

   

 

 

Drilling waste: Drill cuttings, excess 

or spent drilling mud and rig wash 

water 

A water based mud will 

primarily be used 

during drilling. The drill 

cuttings and WBM will 

be stored at the well site 

in lined pit. The drilling 

mud will be allowed to 

Page 199: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 170 HPK

Activity 

Description  Proposed Disposal Method 

Seismic 

Dri lling 

GPF/CPP 

Flow Lines 

evaporate inside the 

mud pit and also dry 

out. After that, the mud 

pit and the cuttings pit 

will be backfilled  

OBM and cuttings will 

be passed through a 

separation system 

consisting of shale 

shakers and a Hi‐G 

dryer. The separated 

solids (cuttings) will be 

temporarily stored in a 

lined cuttings pit or in 

steel containers and will 

be transported to land 

farming site or thermal 

desorption contractor 

site  

   

 

 

Bentonite mud & cuttings: For 

drilling of upholes and deep holes 

to avoid the holes from collapsing 

To be disposed of into 

earthen pits, backfilled 

after the mud and 

cuttings are dried. 

Bentonite is a natural 

clay material and non‐

hazardous in nature. 

The mud and cuttings 

after drying will return 

to dust 

       

Minor  Oil spills/soil 

contaminated by oil 

leakages or stains: Leaks 

from vehicles, 

equipment, or storage 

containers at campsites 

or work areas outside 

the campsite or oil or 

fuel stains produced 

during handling and 

transfer operations 

Specialized treatment 

such as incineration or 

remediation such as 

thermal, chemical or 

biological 

Best industrial 

guidelines will be 

followed 

In case of chemical spill 

the contaminated soil to 

be land filled 

Page 200: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 171 HPK

Activity 

Description  Proposed Disposal Method 

Seismic 

Dri lling 

GPF/CPP 

Flow Lines 

Quantity: Area and 

depth of soil 

contaminated; < 1 m2 

and 0.3 m respectively 

Moderate  Fuel, oil or chemical 

spills during transfer 

or handling operations.

Quantity: Spill less than 

200 litres 

Major  Spill during 

transportation of fuel, 

oil or chemicals or 

failure of the 

containment areas  

Quantity: Spill more 

than 200 litres 

   

   

Wastewater generating from process: 

Cleaning and hydro‐testing of 

pipelines 

To be disposed of in 

earthen pits 

To be drained to the 

nearest drainage 

channel with prior 

approval of concerened 

   

 

  Produced Water  To be disposed of in 

impermeable (HDPE) 

lined evaporation ponds 

To be re‐injected into 

deep subsurface 

formations where 

possible 

   

   Condensate  To be transported and 

sold to the nearest 

refinery 

 

   

  Solid Waste: Concrete, building 

materials, off cut pipe, plastic pipe 

protectors, plastic sheeting and 

cable drums etc. 

Landfilling and 

recycling as appropriate 

b. Residual Impacts 

It is believed that after applying the recommended mitigation measures, no 

contamination of soil or water will occur.  

 

Page 201: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 172 HPK

Characteristic 

Waste Type

Domestic and 

Clinical Wastes 

Fuel, Oil or 

Chemical 

Spills 

Operational 

Wastes 

Duration  Short  Medium  Medium 

Extent  Local  Local  Local 

Likelihood  Unlikely  Possible  Unlikely 

Consequence  Minor  Minor  Minor 

Reversibility  Reversible  Reversible  Reversible 

Significance  Low  Medium  Low 

c. Mitigation Measures 

Mitigation measures for each category of waste are listed below. Where a category of 

waste is common, the mitigation measures will apply equally to all segments of the 

proposed project. 

Domestic and Medical Wastes  

Sewage Treatment Plant (STP) shall be preferred for handling of black/grey water 

under BATNEEC/BAT, but in case of unavailability of STP, septic tank and soak 

pits shall be provided. Septic tank and soak pit shall be covered properly to avoid 

any bad smell in surrounding areas; 

Wastewater from laundry, kitchen washings and showers will be disposed of into 

separate soak pits; 

Soak pits will be built in absorbent soil and located 300 m away from a perennial 

surface water source or water well; 

Soak pits will be constructed such that surface runoff cannot enter the pits; 

Soak pits will be designed to accommodate wastewater generated during the total 

duration of the operation; 

In case the septic tank gets filled with sludge, septic tank shall be emptied through 

vacuum truck and material shall be transferred to treatment facility or approved 

municipal drain; 

No solid waste will be disposed of in the field. All solid wastes will be disposed of 

in waste bins provided within the campsite’s area; 

All types of combustible, non‐combustible and hazardous wastes including plastic 

or glass bottles and cans will be temporarily stored on site and sold/handed over to 

a waste/recycling contractor who will utilize these wastes for recycling purposes; 

Burning of wastes (any type) will not be allowed; 

At the time of restoration septic tanks will be dismantled in place and backfilled 

with at least 1 m of soil cover; 

Page 202: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 173 HPK

At the time of restoration soak pits will be backfilled with at least 1 m of soil cover; 

and 

Medical wastes will be temporarily stored onsite separately and incinerated at 

appropriate facility. 

Oily & Hazardous Wastes 

Used oil and wastes will be transported to local contractors for recycling; 

Shovels, plastic bags and absorbent material should be present near fuel and oil 

storage or handling areas to attend spills and leaks; 

A spill prevention and contingency plan will be prepared to deal with moderate 

and major spills; 

The soil contaminated from major spills may require specialized treatment such as 

incineration or bioremediation. In case of chemical spill the contaminated soil may 

have to be landfilled; 

The soil contaminated from minor and moderate spills will be removed and 

properly buried in such a manner that it does not contaminate the surrounding 

soils or groundwater. In the case of spill >200 liters the contaminated soil will be 

disposed of in line with the best industrial practices; 

Fuels tanks will be daily checked for leaks and all such leaks will be plugged 

immediately; 

Fuel and oil storage areas will have secondary containment in the form of concrete 

or brick masonry bunds. The volume of the containment area should be equal to 

125% of the total volume of fuel stored; 

All fuel tanks will be properly marked to highlight their contents; 

All fuel and oil storage areas will have a concrete pad underneath to prevent soil 

contamination in case of leaks or spills; and 

Vehicles will be daily checked for fuel or oil leaks. Vehicles with leaks will not be 

operated until repaired. 

Operational Wastes 

At the time of restoration all pin flags, signs and refuse from seismic lines will be 

removed; 

Bentonite mud used for the purpose of uphole and deep hole drilling will be 

prepared in rig tanks. The used mud will be disposed of in the pit and left to dry. 

After the mud has dried the pit will be backfilled; 

During fuel and oil transfer operations such as re‐fuelling vibroseis/bulldozers 

through a dedicated fuel vehicle, drips and spills will be avoided and drip pans 

will be used; 

A water based mud system will primarily be used for drilling of wells; 

Page 203: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 174 HPK

Waste pit at the well site will be lined with an HDPE liner; 

The drill cuttings and WBM will be disposed into a pit lined with an impermeable 

geo‐membrane. The pit will be larger than the required capacity to accommodate 

overflows. At the time of restoration the pit will be backfilled with the cuttings 

encapsulated within the liner and with a top soil cover; 

The final disposal of OBM (if used) and contaminated drill cuttings will be carried 

out after treatment at land farming site or thermal desorption;  

UEPL will carry out feasibility study and prepare detailed treatment and disposal 

plan of OBM cuttings; 

OBM (if used) cuttings will be treated and disposed of (based on the chemical test 

results) in guidance with American Petroleum Institute (API) or State of Louisiana, 

Department of Natural Resources, State Wide Order 29B (LSO – 29B); 

Produced formation fluids during testing will be flared along with the gas or 

collected inside the lined waste pit at the well site. In case the fluids discharge into 

the flare pit the soil at the sides of the flare pit will be excavated and disposed of 

into the lined waste pit at the well site; and 

Water used for cleaning and hydro‐testing of pipelines will be collected in earthen 

pits where it will evaporate with time or drained into the nearest drainage channel 

with the prior approval of concerned. The residual sludge or solids and the liner 

will be disposed of following best industrial practices. 

Minimum Distances for Waste Pits 

Septic tanks and soak pits at 300 m from local water wells or hand pumps; 

Drill cuttings and mud pits at the well site 300 m from local water resource; and 

All other waste pits or enclosures at least 300 m from local settlements and local 

water resources. 

7.1.3 Climate and Ambient Air Quality

a. Source Specific Assessment  

This section of the report considers the sources of emissions generated during the 

proposed exploration and development activities on ambient air quality. The sources 

of emissions can be categorized into intermittent and short term sources of emissions 

during the operations which will last for a few months including seismic, drilling and 

laying of flow lines. 

Monitoring of air emissions from generators used in exploration activities shows that 

the emissions remain within the NEQS (HPK’s various Independent Environmental 

Monitoring projects of exploration and development activities in Sindh region). The 

emissions will also disperse quickly with the prevalent wind currents. 

 

Page 204: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 175 HPK

Exhaust Emissions from Generators, Vehicles & Equipment 

As discussed earlier stack emissions from generators that will be used at the campsites 

and well site will generally remain within NEQS/SEQS. Any slight increase from the 

NEQS/SEQS will not have any impact on the environment, as the emissions will 

quickly disperse with the prevailing wind currents. Control over black smoke from 

vehicles and construction machinery shall be kept by maintaining visual monitoring 

and tuning or maintenance of the vehicles. 

Dust Emissions due to Construction & Road Travel 

Dust emissions due to construction and road travel shall be minimized by practising 

good construction practices (such as keeping stock piles down wind and away from 

communities and camp) and sprinkling water over the access road (wherever 

required). 

Emissions from Flaring 

Emissions in the form of oxides of carbon, nitrogen and sulphur will be produced 

during flaring. Emissions from flaring will have no effects on communities or rig site 

workers and local air quality because the flare pit will be kept downwind of the well 

site and more than 300 m from communities and the emissions will disperse and 

dilute with prevalent wind currents. Safe distance will also be maintained for 

construction/establishment of GPF/CPP. 

Possible H2S Emissions in Case of Emergency 

In the event of any release of hydrogen sulphide gas above safe acceptable limits 

emergency response procedures will be adopted. 

b. Residual Impacts 

It is believed that after applying the recommended mitigation measures, no 

deterioration of air quality will occur.  

Characteristic Activity

Seismic Drilling GPF/CPP Flow Lines 

Duration  Short Short  Long  Short 

Extent  Local Local  Local  Local 

Likelihood  Unlikely Unlikely  Possible  Unlikely 

Consequence  Minor Minor  Minor  Minor 

Reversibility  Reversible Reversible  Reversible  Reversible 

Significance  Low Low  Medium  Low 

c. Mitigation Measures 

General 

Campsites will be located at least 300 m away from communities; 

During construction dust emissions due to road travel will be minimized by 

regulating vehicles speed and watering of the access track (wherever required); 

Page 205: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 176 HPK

Burning of waste (any kind) will not be allowed; 

Generators, compressors and vehicles used will be maintained in a good condition 

to ensure that emissions are kept to a minimum level; 

During operation, emissions from all point sources should be monitored to check 

compliance with SEQS;  

Dust emissions during construction activities should be minimized by good 

management practices such as locating stock piles out of the wind direction, 

keeping the height of the stock piles to a minimum, keeping earthwork areas damp 

etc.; 

During construction leveling or widening along the access roads will be done in 

sections, immediately followed by sprinkling of water and also preferably 

compaction (where required); and 

Appropriate measures will be taken to avoid ozone depletion & global warming 

e.g. prohibit use of CFC gases etc. 

Seismic Operation 

Generators, compressors and vehicles used during seismic operations will be 

maintained in a good condition to ensure that emissions are kept to a minimum 

level. 

Drilling Operation 

Generators and vehicles used during construction of each well site and subsequent 

drilling operations will be maintained in a good condition to ensure that emissions 

are kept to a minimum level; 

During drilling and construction dust emissions due to road travel will be 

minimized by regulating and monitoring vehicles speed and watering of the access 

track; 

The access track selected to access the well location will maintain a reasonable 

distance from communities; and 

Flare pit will be kept downwind of the well site and at least 300 m from the nearest 

community. The duration of flaring during well testing will be kept to the 

minimum required. 

Establishment/Construction of GPF/CPP 

During detailed design for the GPF/CPP, emissions from point sources such as 

flare and incinerator (for acid gases) should be modelled so that if there are any ill‐

effects on local communities and workers appropriate mitigation measures such 

adjusting the stack heights can be taken; and 

During operation of the GPF/CPP emissions from all point sources should be 

monitored to check compliance with SEQS. 

Page 206: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 177 HPK

Lying of Flow Lines/Tie‐in/Wellhead Works 

Access tracks used during laying of gas pipeline passing through communities will 

be avoided. If unavoidable a speed limit of less than 30 km/hr will be observed on 

the section of the road passing through the community. 

Minimum Distances 

The following minimum distances will be maintained from communities: 

o Well Site, rig camp and construction camps for all activities – 300 m 

o Quarry locations – 1,000 m 

o Flare pit at well sites – 300 m 

Access tracks to well sites and any other permanent facility – 300 m unless driven 

by community demand. If a distance less than 300 m is maintained appropriate 

water sprinkling over the access track. 

Access tracks used during drilling – Preferably access tracks passing through 

communities will be avoided. If unavoidable a speed limit of less than 30 km/hr 

will be observed on the section of the road passing through the community. 

7.1.4 Noise Pollution

a. Source Specific Assessment 

Sources of noise during seismic, construction including GPF/CPP and drilling will be 

generators, vehicles, drilling rig, flaring during well testing, plant operation and 

construction equipment & machinery. These sources of noise like air emissions can be 

categorized as short term and intermittent arising from seismic and drilling activities 

and other associated developmental activities.  

Increased noise levels during the operations although will not accumulate but can 

individually be a source of nuisance for locals and a source of disturbance to wildlife. 

Monitoring of actual noise levels from drilling rigs and campsites has also shown that 

noise during construction and drilling attenuates to ambient levels (background levels 

within the project area) after approximately 300 m from the campsites and well site. 

Noise levels monitored from different vehicles under different conditions by HPK in 

other drilling operations show that the noise levels from all vehicles comply with the 

NEQS/SEQS level of 85 dB @ 7.5 m from the source and reach the ambient noise level 

in the area at distances ranging from 40 to 70 m from the source. Table presented 

below explains the permissible noise exposure limits which shall be met at working 

sites during the entire course of operation. 

  For Lex & LAeq For Peak Pr (Lpk)

OSHA Action Level 85 dB‐A for TWA of 8 hours exposure 

135 dB‐C 82 dB‐A for TWA of 12 hours exposure  

OSHA Upper 

Exposure Limit 

90 dB‐A for TWA of 8 hours exposure 140 dB‐C 

87 dB‐A for TWA of 12 hours exposure 

Page 207: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 178 HPK

As the project facilities will maintain appropriate distances from communities, effects 

of noise on communities will not occur. Similarly, effects of vehicles noise on 

communities will also not occur if the access tracks maintain a reasonable safe distance 

from communities. Any effects of noise during the operation shall be further mitigated 

by the measures listed below. 

b. Residual Impacts 

It is believed that after applying the recommended mitigation measures, the effects of 

noise will be of low significance.  

Characteristic Activity

Seismic Drilling GPF/CPP Flow Lines 

Duration  Short Short  Long  Long 

Extent  Local Local  Local  Local 

Likelihood  Unlikely Unlikely  Unlikely  Unlikely 

Consequence  Minor Minor  Minor  Minor 

Reversibility  Reversible Reversible  Reversible  Reversible 

Significance  Low Low  Low  Low 

c. Mitigation Measures 

It shall be ensured that generators, vehicles and other potentially noisy equipment 

used are in good working condition; 

Well sites, campsites and all other project related surface facilities e.g. GPF/CPP 

will be located 300 m away from nearest communities; 

The use of horns by project vehicles shall be minimized. The use of pressure horns 

shall not be allowed; 

Movement of all project vehicles and personnel shall be restricted to within work 

areas; 

Noise levels at communities nearest to the GPF/CPP shall be monitored by Health, 

Safety and Environment Officer (HSEO) of UEPL. In case these are found to exceed 

safe acceptable limits appropriate mitigation shall be taken; 

Generators will be kept within enclosures to minimize dispersion of noise; and 

In areas with higher noise levels or longer shifts ear plugs and earmuffs will be 

provided to workers. 

7.1.5 Use of Water

a. Source Specific Assessment 

Use of water from local surface or groundwater resources for the project resulting in 

decreased availability of water for local users. 

The project area have well‐established surface water resource. The most important 

surface water feature in the area is Indus River which usually peaks in mid‐August or 

Page 208: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 179 HPK

early September. Apart from that, the project area also houses few dhands which are 

located in low laying depressions where groundwater surfaces to the ground level. A 

number of tube wells also exist in the project area with sufficient yield. The use of local 

water wells during exploration and associated development activities is a common 

practice by all operators and in almost all areas of Pakistan.  

Due to the high surface water demand for irrigation and the biological significance of 

surface water bodies, abstraction of surface water will not be done. The Indus River, 

canals and associated irrigation network is the source of surface water in the area and 

its use will not be feasible as the water is not potable. Hauling the water only for 

operational use would mean increased logistics management, as potable water would 

still have to be supplied from water wells for domestic use. Under special 

circumstances like long haul distances, improper access for water bowsers in protected 

areas etc. surface water resources may be exploited for limited water abstraction 

during seismic operation only after getting approval from the concerned department. 

Other than that, surface water resources will not be used during drilling activities.  

Except flush and uphole drilling, water will not be required for jackrob drilling and 

vibroseis operation. Limited upholes will only be drilled at selected locations. Since, 

the water requirement during seismic surveys is not high it is assessed that the effect 

on local wells will not be significant enough to cause any localized depletion of 

aquifers or effects on local water requirement. In order to ensure that this remains to 

be the case, the local water wells will only be used after ensuring that they have the 

excess capacity to supply the water requirement and water levels/discharges will be 

monitored to ensure that any effects remain negligible. Water for project will either be 

obtained from water wells in the project area or UEPL may install its own water well 

at a suitable location in the project area in consultation with the local community. The 

aquifer yield will be calculated for ensuring that the available capacity at the local tube 

well (safe yield minus local demand) is at least 50% greater than the project demand. 

Discharge from the tube well will be regularly monitored to monitor any changes in 

the yield of the well. In order to conserve sweet groundwater, it is also recommended 

that UEPL should maximize wherever possible the use of brackish groundwater in its 

operations such as seismic, drilling and establishment of associated surface facilities 

etc.  

With regards to water usage of it should be recognized that groundwater is a 

communal resource. In order to share the groundwater in the project area with the 

local communities, UEPL must ensure that its operations must not exploit the resource 

in an unsustainable manner and that local communities are appropriately 

compensated for the use of the communal resource. Therefore, for water abstraction 

during proposed exploration and development activities, compensation means the 

payment to local well owner at appropriate rates for the quantity of water obtained.  

Page 209: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 180 HPK

b. Residual Impacts 

Even after application of mitigation measures water will continue to be used during 

the entire development phase of the project but in a sustainable manner.  

Characteristic Activity 

Seismic Drilling GPF/CPP Flow Lines 

Duration  Short  Long  Long  Short 

Extent  Local  Regional  Regional  Local 

Likelihood  Unlikely  Possible  Possible  Unlikely 

Consequence  Minor  Minor  Minor  Minor 

Reversibility  Reversible  Reversible  Reversible  Reversible 

Significance  Low  Medium  Medium  Low 

c. Mitigation Measures 

Water from surface water bodies i.e. wetlands or canals etc. will not be used for the 

proposed exploration and associated development activities. Under special 

circumstances like long haul distances, improper access for water bowsers in 

protected areas etc. surface water resources may be exploited for limited water 

abstraction during seismic operational needs only after getting approval from the 

concerned department. The surface water resources will not be used other 

exploration and development activities; 

The quantity of water used during different project activities will be kept to the 

minimum required by taking prudent water conservation measures on site. A 

complete record of water consumption will be maintained by the UEPL’s Rep; 

Groundwater will be used for project activities from existing tube wells or by 

UEPL’s installed water wells. Water from the tube wells will only be used after 

ensuring that the available capacity at the groundwater is roughly 50% greater 

than the project demand. Discharge from the existing tube wells or UEPL’s 

installed tube wells will be regularly monitored to monitor any changes in the 

yield of the wells; 

If a new water well is to be installed, the well will be located 300 m from existing 

local wells and will be designed to abstract water preferably from deep aquifer not 

being used by local communities; 

Contamination of surface and groundwater resources will be avoided; 

Preferably, the potable water requirement will be met by installing water treatment 

system (such as reverse osmosis);  

UEPL and project contractors will pay appropriate and justified compensation for 

water utilized to the owners of water well; and 

Marginally sweet water wells will be used for project activities. Where possible, 

use of brackish water should be maximized for the project activities. 

Page 210: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 181 HPK

7.1.6 Blockage of Natural Drainage

a. Source Specific Assessment 

It is recommended that well sites, campsites and associated development facilities e.g. 

manifolds, EWT, GPF/CPP will be located in cleared and levelled terrain. The entire 

project area experience rapid flow during rainfalls particularly along the surface water 

bodies. As the well sites, campsites wand associated facilities will have limited areas 

therefore no blockage to this rapid flow will occur. However, as a precautionary 

measure area around the facilities shall also be landscaped to avoid blocking of natural 

drainage. 

The access roads and pipeline’s RoW may cross streambeds. Causeway crossings and 

pipe culvert bridges will be provided at all stream crossings. To avoid obstruction to 

sheet runoff in plain areas, any soil windrows formed along the access road during 

construction activities shall be levelled. The gas transmission pipeline will be laid at a 

depth of 3ft. Since, the water table in the project area is generally more than 10 ft. 

below the ground surface, no direct impact on groundwater quality is anticipated 

during pipeline laying. 

b. Mitigation Measures 

Area around the well sites, campsites and associated surface facilities shall be 

landscaped to avoid blocking natural drainage; 

Causeways and pipe culverts will be provided at all watercourse and minors 

crossings to avoid blocking of natural drainage; and 

Uncontrolled and unnecessary clearing, dozing, excavations or quarrying, storage 

of construction material etc. will be avoided.  

7.1.7 Site Restoration

a. Potential Sources of Impact 

After completion of each activity, the project facilities will be restored as close to its 

original condition as possible. One of the important tools is the photographic record of 

project facilities e.g. campsite/s prior to setup will be taken and will be compared after 

site restoration. The restoration of well sites and associated facilities (including access 

tracks and campsites) is of utmost importance. As these facilities occupies areas of the 

wildlife habitats, retention of these sites or improper disposal of wastes left at the end 

of the drilling or construction activities would be in conflict with the principle of least 

environment disturbance over the least possible time period in these areas. 

b. Mitigation Measures 

General 

Demobilization of all equipment and machinery; 

Disposal of any waste material remaining at the time of completion of the 

operation; 

Page 211: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 182 HPK

Backfilling of all soak pits and septic tanks; 

Dismantling and removal of fence or barriers surrounding the campsite areas; and 

General restoration of the site area including landscaping and restoration of 

drainage where required. 

Seismic Operation 

Restoration of seismic lines will include removal of all cables, geophones, station 

units, flags, stakes and wastes from the lines and backfilling of all mud pits. For 

reference purposes a photographic record of selected sections of seismic lines will 

be taken before and after the operation. 

Drilling Operation 

Complete Restoration – Dry Well 

All wastes at the well sites will be disposed of according to the requirements of the 

EIA/EMP; 

Liner from the water and waste pits at the well sites may be taken out and re‐used 

or disposed of in the existing pits with proper restoration; 

All concrete structures at the well sites will be broken and either transported out of 

the project area or site restoration contractors will sent it for sale or reuse or 

disposed of into the pits; 

All pits at the well sites will be backfilled; and 

The areas covered by the portion of the access track that will be of no use for other 

wells will be restored, in that all gravel topping will be removed. This scenario will 

be applicable only if the locals require the potions of the track to be restored or 

otherwise it will be left on the site on the consent of the locals. 

Partial Restoration – Producing Well 

The well sites and access roads will be retained to support well access work for 

further testing or during the production phase; 

The outer chain link fence will be retained as a safety measure to keep wildlife 

away from the pit areas; 

The wellhead will be enclosed by a locked steel cage. This will serve as both a 

safety and security measure as the site will be down‐manned pending further 

production operations work; and 

The constructed pit areas will be retained but all liquid and solid waste material 

will be removed from the site and disposed of in line with the requirements of this 

EIA/EMP.

Page 212: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 183 HPK

Biological Environment

7.2.1 Clearing of Vegetation & Loss of Habitat

a. Source Specific Assessment 

Loss of vegetation can occur during the proposed exploration and associated 

development project activities due to clearing of land along seismic lines, well sites, 

campsites and RoW prepared for pipelines laying and the tracks prepared to access 

the well sites, campsites, flow lines and surface production facilities.  

Impacts on vegetation due to the sources mentioned above will be of less significant if 

existing tracks are used as much as possible. No endemic species were identified in the 

project area during the EIA site visit. The distribution of vegetation communities are 

found in wide range in the project area during site visit. Therefore, limited vegetation 

clearing will not result in extinction of any vegetation communities. Clearing will 

preferably be carried out in areas where the vegetation is in a degraded state due to 

livestock grazing or harvesting by local communities, and cutting of trees will be 

avoided. The vegetation clearing on steep slopes will also be avoided to minimize soil 

erosion. 

b. Residual Impacts 

If all mitigation measures given below are adhered with residual impacts will be the 

loss of vegetation cleared from permanent facilities such as producing well sites, 

access roads and GPF/CPP. At all other areas such as at temporary tracks vegetation 

will regenerate with time. Even at the permanent facilities regeneration will also occur 

after decommissioning and restoration of the sites. 

Characteristic Activity

Seismic Drilling  GPF/CPP Flow Lines 

Duration  Medium  Medium  Medium  Medium 

Extent  Local  Local  Local  Local 

Likelihood  Certain  Certain  Certain  Certain 

Consequence  Minor  Minor  Minor  Minor 

Reversibility  Reversible  Reversible  Reversible  Reversible 

Significance  Low  Low  Low  Low 

c. Mitigation Measures 

General 

Project related camps/facilities should be established outside the environmental 

sensitive areas; 

The campsite areas will be kept to the minimum required; 

Camps will be located in existing clearings; 

Use of local vegetation/wood as fuel by crew personnel will be prohibited; 

Page 213: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 184 HPK

Clearing of trees will be avoided as much as possible. Under unavoidable 

circumstances any clearing required in forests shall be done with prior approval 

and be compensated as per rules and regulations of Forest Department; 

Outside forest protected area, any tree cutting if unavoidable for clearing of site 

will be replaced/compensated by plantation of trees (10 trees for each tree cut). The 

tree species should be indigenous to the region; 

Periodic trainings will be provided to drivers on mitigation measures related to 

off‐road travel and speed limits; 

Dust emissions on access tracks will be reduced by keeping speed limits below 40 

km/hr; 

Vehicles speed will be regulated and monitored to avoid excessive dust emissions; 

Campsites will avoid areas of dense vegetation as much as possible; 

Access tracks will be avoided from passing through patches of dense vegetation; 

Off‐road travel, required at sections of the road where construction work is in 

progress, will be minimized and if required will be allowed only after approval 

from UEPL’s Rep; 

Clearing of vegetation will be minimized by keeping the road width to 5 m (except 

at bends where greater width will be required for safety reasons), and by keeping 

the length of new sections of the road to a minimum; and 

Blasting, construction or drilling activities will not be performed in Indus River. 

Seismic Operation 

During seismic operation clearing of vegetation will be minimized by minimizing 

the width of the vibroseis tracks, minimizing the preparation of new access tracks, 

and keeping the width of new access tracks to the minimum required; 

Crew personnel while working along seismic lines will concentrate within a 

corridor of 4.5 m; and 

Total land uptake by seismic camps and access track will be kept to the minimum 

required. 

Drilling Operation 

During construction good management practices will be adopted to avoid 

disturbance to areas adjacent to work areas including the access tracks, well sites 

and campsites; 

Well sites and campsite areas will be kept to a minimum; and 

Campsite established for the purpose of construction will be located in existing 

clearing. Vegetation clearing from these sites will be kept to a minimum. 

 

Page 214: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 185 HPK

Establishment/Construction of GPF/CPP 

Existing access tracks will be utilized as much as possible; 

The access track to the GPF/CPP will be properly compacted and maintained 

throughout the entire operational life; 

During construction movement of construction equipment will be restricted to 

work areas only to avoid unnecessary disturbance to soils in the project area; 

To minimize erosion due to quarrying, the quarry sites will be carefully selected 

such that they are located in levelled areas with existing clearing and the quarry 

sites are restored after use; 

Clearing of vegetation will be minimized; 

Off‐road travel will be strictly prohibited and observance of this will be monitored 

during the operation; and 

Vehicles speed will be regulated and monitored to avoid excessive dust emissions. 

Lying of Flow Lines/Tie‐in/Wellhead Works 

Topsoil of the RoW of gas pipeline/flow line, will be separately stored. This topsoil 

will be backfilled after proper compaction ensuring regeneration of vegetation; 

Good engineering practices will be adopted during construction activities to 

ensure that unnecessary clearing of vegetation outside work areas is avoided; and 

Land area requirements for construction camps and RoW of gas pipeline will be 

kept to the minimum required. 

7.2.2 Disturbance to Wildlife

a. Source Specific Assessment 

Potential sources of impacts on wildlife during the project activities include 

disturbance due to construction of access roads, well sites, seismic camps, rig 

campsites, construction/establishment of GPF/CPP, laying of pipelines, access road 

usage during the project, light and noise from the camps, light and noise from well 

sites (including flaring at the well sites and GPF/CPP). 

Birds 

The project area support fair populations of native and migratory birds. As the EIA 

prohibits hunting, fishing, harassment, trapping, killing or feeding of any wildlife 

species, therefore impacts of the project on these species found will be very less. 

Similarly, the resident water birds associated with the wetland of the project area may 

only be disturbed temporarily due to activities spread of this habitat. During the 

migratory season, operation in this habitat may disturb the wintering birds as they 

occupy most of the wetland being large in number. However, this impact would be 

temporary and insignificant for survival of species as they will have the choice to settle 

in neighbouring wetlands on Indus and nearby surface water bodies.  

Page 215: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 186 HPK

Mammals 

The status of mammals including ungulate i.e. Hog deer is very poor in suitable 

habitat within the project area. Their hunting will not be permissible being protected 

under the provisions of SWPO, 1972. Other mammals like Asiatic jackal, Indian 

porcupine, gerbils and jirds are quite common and very adaptive.  

The residual impact of long duration activities of mammalian fauna may be 

significant. The movement of vehicular transport, presence of personnel, exploration 

and development activities may disturb the mammals, including burrowing taxa. Such 

disturbance during mating and breeding season may seize or reduce the reproduction 

of mammals as they require privacy and convenient protected places. Any activity 

close to this area can potentially disturb the shy animals and may cause migration 

from the area. The aspects of the proposed exploration and associated development 

activities that may disturb the wildlife include presence of people in the area, noise 

and movement of vehicles and machinery, physical damage to the habitat (breeding 

sites, resting places, and grazing areas), blockage of access to escape terrain and 

existing water resources. Careful planning and management of activities can avoid all 

of the above impacts. The mitigation measures presented in the following section can 

reduce the impact to acceptable level. 

Reptiles 

It is expected that reptiles will be displaced from close vicinity of proposed exploration 

and associated development project activities but at the same time, project activities 

will create hiding places for snakes and other reptiles. However, owing to the large 

and wide spread population size of these reptilian species and the large area otherwise 

available to them, insignificant or very less effect of the proposed project on reptiles 

may occur. Mortality of reptiles during construction or due to road travel will be 

avoided by adopting mitigation measures like speed control and restricting night 

driving. In general all mitigation measures suggested at the end of this section will 

ensure that wildlife species are protected and not adversely impacted by any means 

due to proposed project activities. 

b. Residual Impacts 

Residual impact on wildlife will be the loss of habitat due to uptake by permanent 

project facilities such as the producing wells or establishment of GPF/CPP. 

Characteristic Activity

Seismic Drilling GPF/CPP Flow Lines 

Duration  Short  Short  Short  Short 

Extent  Local  Local  Local  Local 

Likelihood  Possible  Possible  Possible  Possible 

Consequence  Minor  Minor  Minor  Minor 

Reversibility  Reversible  Reversible  Reversible  Reversible 

Significance  Low  Low  Low  Low 

Page 216: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 187 HPK

c. Mitigation Measures 

General 

Prior to commencement of any activity, awareness trainings will be provided to 

contractor’s management and field crew on matters related to the requirements of 

the EMP in this regard; 

All mitigation measures to minimize noise levels, dust emissions, air emissions, 

and waste management required by the EIA will be adhered to; 

Food wastes will not be disposed of in the open. Food wastes collected in waste 

segregation units will be disposed of according to waste disposal procedure on a 

regular and strict basis as advised by the UEPL’s Rep; 

Construction work near areas which show reptile populations will commence after 

a soft start up and will be randomly monitored; 

Hunting, fishing, feeding, harassment, killing or trapping of wildlife will not be 

allowed; 

Vehicles speed on access roads will be controlled to avoid incidental mortalities of 

reptiles. Any such incident will be reported to the UEPL’s Rep. Vehicles speed will 

be randomly monitored; 

Vehicles speed will be regulated and monitored to avoid excessive dust emissions; 

Cutting of trees/bushes will be avoided; 

Project related camps/facilities should be established outside the environmental 

sensitive areas; 

Movement of all project personnel will be restricted to work areas; 

Movement of project vehicles will be restricted only to the project access road or to 

routes approved by the UEPL’s Rep; 

Night travelling will only be done in case of emergency after getting approval 

from UEPL’s Rep;  

Off‐road travel will be strictly prohibited and observance of this will be monitored 

during the operation; and 

Blasting, construction or drilling activities will not be performed in Indus River. 

Seismic, Drilling, Construction of GPF/CPP and Flow Lines  

Land uptake by seismic camps, seismic lines, well sites, campsites, GPF/CPP and 

access roads will be minimized; 

Clearing of RoW for access tracks & flow lines will be kept to the minimum; 

The total duration of seismic, construction and drilling will be minimized by good 

management practices; 

Page 217: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 188 HPK

Lights used at the well sites, campsites and project related facilities will be kept to 

the minimum required; 

Flaring during well testing will be done within enclosed ground burning flares 

rather than elevated flares, to minimize light, heat radiation and noise levels; and 

The duration and intensity of flaring at GPF/CPP will be kept to the minimum 

required.

Page 218: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 189 HPK

Socioeconomic, Cultural and Archaeological Environment

All development initiatives give rise to secondary impacts that affect socioeconomic 

receptors in the project area. Socioeconomic impacts vary from project to project and 

are not easily quantifiable. These are consequences of project activities on the human 

population that alter the ways in which people live, work, interact, relate to one 

another, organize to meet their needs and generally exist as members of society. 

These also include more long‐term impacts such as cultural impacts involving changes 

to the norms, values and beliefs that guide and rationalize their cognition of 

themselves and their society. In the past socioeconomic impacts of large development 

projects were mitigated through monetary compensation, or were altogether ignored. 

However, the importance of these impacts has been recognized and it is very strongly 

felt that impacts on communities’ cultural activities, local practices and day‐to‐day 

activities have far reaching impacts on their psychological, emotional and social 

wellbeing, whereby having an effect on their quality of life. Further to above, 

utilization of any resources that are in possession of local owners shall be 

appropriately compensated as per mutual agreement of both parties. In case of any 

damage during company’s activities, matter shall be resolved mutually. This section 

identifies, assesses and proposes mitigation for potential impacts of the project on key 

parameters which define the wellbeing of the communities. 

a. Source Specific Assessment 

Sustenance income 

o Leasing of private lands 

o Sharing of water sources 

o Uptake of livestock grazing areas/effect on mobility of local herdsmen and 

potential for loss of livestock due to road accidents 

o Effects on local businesses 

Drinking water 

o Sharing of local domestic water resources 

Employment 

o Distribution of employment opportunities during construction and operation 

phase, subject to availability of local resource as per UEPL required 

competency 

Health 

o Effect on health of local communities due to project wastes and dust emissions 

Education 

o Increased or reduced emphasis on education due to the project 

Safety and Security 

Page 219: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 190 HPK

o Potential for road accidents, conflicts with locals and safety of local employees 

Mobility and transportation 

o Ease in mobility and transportation 

Culture and religion 

o Damage to cultural, archaeological or religious sites 

Potential issues related to sustenance incomes have been assessed below: 

Leasing of Private Lands 

Land might have to be leased or acquired for seismic camp/s, seismic lines, well sites, 

rig campsites, access tracks, construction campsites, GPF/CPP and RoW of pipelines. 

Land for the project activities shall be leased as per local regulations and according to 

mutual consent and deliberations of both parties.  

Sharing of Water Resources 

The project water usage will not affect the accessibility of locals to the water source in 

the long or short term. Water should not be extracted from the shallow local reservoir 

and the local water should only be used after ensuring that the abstraction process will 

not result in any water shortage for the locals. New UEPL wells may be installed to 

abstract water from the deep aquifer.  

Uptake of Livestock Grazing Area/Effect on Mobility of Livestock Herds/Potential for 

Loss of Livestock due to Road Accidents 

The project will cover livestock grazing areas. Compared to the total available grazing 

area, the uptake by the project will be insignificant and will not have any measurable 

significant impacts. Project vehicles will follow safe speed limits, especially on seeing a 

livestock herd near the road, to avoid any road accidents. 

Effects on Local Businesses 

Local business (such as shops and tea stalls) will experience a rise in sales as junior 

level project staff and local employees will purchase items of general use from shops 

and will patronize local tea stalls and eateries on a regular basis. However, it must be 

noted that the impact so created will be of short‐term nature owing to the larger 

workforce required during the construction phase than the operation phase of the 

project. 

Employment 

Opportunities for wage labour in the project area are very few. As a consequence the 

expectations of local residents in relation to employment during the project 

(construction phase) will be high. Core activities of seismic, well sites, GPF/CPP and 

pipeline construction require skilled and trained labour force, which is marginally 

available in the area. However, the project will also, to a great extent, require the 

services of unskilled workforce. All unskilled and some semi‐skilled workforce should 

Page 220: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 191 HPK

be hired equitably from within the local communities and the different tribes in the 

area keeping in view of local regulations and company’s policy. 

Health 

Communities that are located close to the seismic camps, well sites, access roads, 

GPF/CPP and pipeline routes will be exposed to dust emissions, gaseous emissions 

from the well sites and any incidental spillage of fuel or oils. If the mitigation 

measures relating to the control of dust emissions, oil or fuel spills and project wastes 

are followed no impacts will occur. Local complaints of dust emissions and gaseous 

emissions from rig sites and GPF/CPP will be noted and addressed immediately. 

Safety & Security 

The operations may affect the safety and security of the inhabitants of the areas in the 

following ways: issues of road safety, conflicts between residents and the project 

contractors and issues pertaining to the carriage of fire arms on the site. Community 

sensitive project planning and implementation as prescribed through the 

recommended mitigation measures will minimize the occurrence of any such impacts. 

Disturbance from Noise 

Seismic camps, construction camps, well sites and surface production facilities e.g. 

GPF/CPP, manifolds or EWT must be located more than 300 m from communities. As 

per assessment done in the section for physical environment no effect of the project 

noise will occur on the local communities if the mitigation measures recommended 

controlling the effect of noise are adhered with. 

Mobility & Transportation 

The project activities may affect mobility of local women, especially during the 

construction phase of the project. Project personnel will be given gender sensitization 

briefings and will be instructed to respect local norms and culture, particularly in 

relation to the womenfolk. In connection to the usage of the access track by the women 

of the area, they will not be restricted in any way and will be given due right to 

crossing the road in pursuit of the daily chores, such as fetching water and fuel wood.  

Community Grievances 

It is very much possible that in spite of adhering to all mitigation measures, some 

community grievances may arise during the construction and operation phase of the 

project. Those grievances should be duly considered and addressed by the concerned 

authorities in United Energy Pakistan Limited.  

Archaeological, Cultural and Religious Opportunities 

Cultural sites in the form of shrines, mosques and graveyards exist in the project area. 

Location of construction campsites, rig sites and route alignment of gas pipeline 

should be planned at appropriate distances from cultural sites to avoid damage to 

access of local communities (especially woman) to these sites. There are no notified 

Page 221: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 192 HPK

archaeological sites in the project area. However, there are several graveyards and 

other areas of cultural interest in the Kotri North Block. 

b. Residual Impacts 

Residual impact on socioeconomic, culture and archaeological environment will alter 

the ways in which people live, work, interact, relate to one another, organize to meet 

their needs and generally exist as members of society due development initiatives. 

Characteristic Activity

Seismic Drilling GPF/CPP Flow Lines 

Duration  Short  Short  Long  Short 

Extent  Local  Local  Local  Local 

Likelihood  Unlikely  Unlikely  Unlikely  Unlikely 

Consequence  Minor  Minor  Minor  Minor 

Reversibility  Reversible Reversible  Reversible  Reversible 

Significance  Low  Low  Low  Low 

c. Mitigation Measures 

Project contractors and field staff shall be taken through a Community and 

External Affairs Induction program before execution of project activities; 

Local sources of drinking water will not be over‐exploited; 

The access roads will be watered regularly to minimize dust emissions; 

Construction of bypass to all major settlements and where necessary re‐routing the 

access roads so that a safe distances is maintained from a settlements; 

Drivers will be trained in responsible and safe driving practices; safe speed limits 

for vehicles will be followed; 

Strict compliance will be observed with UEPL’s HSE guidelines;  

Use of local firewood for cooking by project and contractor staff to be prohibited; 

Project surface facilities e.g. campsites or well sites will be located at minimum 

distance of 300 m from communities thereby, mitigating the effect of noise and 

emissions; 

Any land acquired and distribution of compensation will be carried out 

transparently on fast pace in accordance with the UEPL’s compensation 

procedures; 

All mitigation measures related to waste management, minimizing air emissions 

and noise recommended in the EIA/EMP should be adhered with; 

Project staff will respect cultural norms; 

All community grievances will be addressed and rectified as appropriate; 

All project facilities will be restored according to the standard protocols and 

recommendations of the EIA/EMP; 

Page 222: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 193 HPK

Flow lines and access tracks will maintain a distance of 100 m from cultural, 

religious and archaeological sites unless community demands greater distance e.g. 

graveyards or mosques; 

RoW for flow line should by pass major settlements to maintain safe distances; 

The access roads will be watered regularly to minimize dust emissions (if 

required); and 

Construction of bypass to all major settlements, and where necessary rerouting the 

access road so that a safe distances is maintained from a settlement.

Page 223: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 194 HPK

8 Stakeholders Consultation

Stakeholders Consultation is a tool used for the purpose of communication, taken to 

include; information dissemination, exchanging views, soliciting feedback and 

suggestions on issues pertaining to the proposed project, plan future actions, initiate a 

needs assessment and identify areas of concern.  

During the field survey for this study, meetings were held with the communities 

residing within the project area and its surroundings. Goths (village) headmen were 

particularly sought after for consultations. The objective of these meetings was to 

explore and record their views and concerns for inclusion in project design at the 

planning phase. 

In the same vein, meetings were also held with community and members of local and 

provincial government. All the stakeholders were briefed regarding the proposed 

exploration and associated development project activities planned by United Energy 

Pakistan Limited in Kotri North Block (E.L. 2568‐21). Their concerns and suggestions 

were recorded which are reproduced in this chapter. 

Objectives of Stakeholders Consultation

Consultation with stakeholders leads to an overall understanding of the project on the 

part of the communities and also gives the proponent a clearer understanding of the 

stakeholder’s perspective. Effective public consultation can add substantial value to 

the EIA process. The information gained through consultation exercise on the 

stakeholders’ concerns, interests and their ability to influence decision‐making helps to 

identify key cause of environmental problems. 

This can be used to evaluate direct and indirect environmental impacts and assess 

short term and long‐term resource use implications. The input from local communities 

and affected stakeholders can help evaluating alternatives and strengthen the 

management planning by incorporating local inputs and know‐how. These factors 

contribute towards improved project implementation sensitized to the human 

environment of the area. The objectives of stakeholders’ consultation were to: 

Promote better understanding of the proposed exploration and associated 

development activities through explaining its objectives and potential positive and 

negative impacts; 

Identify and address the concerns of all interested and affected stakeholders; 

Provide a mechanism to resolve issues identified by communities, before project 

plans are finalized and development begins, thereby, avoiding public outcry and 

resentment; and 

Instill trust between various stakeholders and the proponent to promote 

cooperation. 

Page 224: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 195 HPK

Community Consultations

Community consultations were carried out in the project area through formal and 

informal meetings, focus group discussions and in depth interviews especially 

covering issues related to ‘gender’. The consultation exercise was conducted in Sindhi. 

A local Sindhi speaker (Sociologist), assisted by environmentalist initiated the sessions 

by giving a brief, simple and non‐technical description of the proposed project 

activities providing an overview of likely positive and negative impacts. This was 

followed by an open discussion in which all participants were encouraged to voice 

their concerns and opinions. Feedback obtained from the members of the community 

were documented and all issues and suggestions raised were recorded in detail. 

Through this process the consultant reached out to a wide segment of the population 

of the area, whereby actively involving all stakeholders in the decision‐making 

process. 

All information was imparted to the communities and other stakeholders in such a 

manner that their expectations were not unnecessarily or unrealistically raised in order 

to avoid any future conflict involving local public, leaders or administrators. Formal 

and informal community consultations and focused group discussions were carried 

out in almost all visited villages/goths during the field survey for current EIA.  

Community’s Concerns & Reservations

All people with whom meetings were held were open to the idea of development in 

the project area. No adverse concerns were raised, neither were there any objections to 

the project concept. Most people welcomed the idea of project activities sensing a 

relative boom in the localized economy particularly employments and provision of 

better civic amenities in the area. They envisaged the project activities a short‐term as 

well as long term benefit for the communities residing in the area. However, the 

communities raised some legitimate concerns. The main concerns common to most 

communities are listed below: 

Local villagers shall be given priority during employment process especially local 

unemployed educated people shall be given preference for technical jobs; 

Compensations for land acquired/leased and standing crops should be disbursed 

in a transparent manner on fast pace; 

Standardized and accessible health facilities to the local communities of the area 

should be provided; 

Provision of better educational facilities should also be ensured to the children of 

the residing communities; 

Local cultural norms should be respected; and  

Safety and security of the local communities should also be given due 

consideration during the proposed project activities. 

Page 225: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 196 HPK

Other Stakeholders

In addition to holding consultation meetings with communities, meetings with 

members of local and provincial government were also deemed essential. All the 

stakeholders were given maximum project information verbally, by sharing TORs and 

project area maps. Their concerns and suggestions were noted which have been 

reproduced below. Proceedings of the meetings with Deputy Director Technical 

(Sindh Environmental Protection Agency, Karachi), Range Forest Officer (Sindh Forest 

Department, Hyderabad), Deputy Director (Sindh Environmental Protection Agency, 

Hyderabad), Chief Engineer (Irrigation Development Sindh, Hyderabad), Technical 

Officer (Directorate of Animal Husbandry Hyderabad, Livestock & Fisheries 

Department, GoS ), Representative of Institute of Environmental Studies, Karachi 

University, Regional Chair (West Asia, Commission on Ecosystem Management, The 

World Conservation Union – IUCN, Zoology Department, Karachi University) and 

Coordinator Marine Program (Worldwide Fund for Nature, Karachi). The remaining 

meetings which were conducted consisted primarily of information collection and 

dissemination. A complete list of these stakeholders consulted is provided in Table 8‐

1. 

8.4.1 Deputy Director, Sindh Environmental Protection Agency, Karachi

HPK’s EIA team also paid a customary visit to meet Mr. Imran Sabir, Deputy Director 

(Technical) at his Karachi office. Mr. Sabir was informed about the proposed 

exploration and associated development activities with the help of prospective area 

map. It was briefed to Mr. Sabir that United Energy Pakistan Limited is operator of the 

lease with JV partners i.e. PPL and AROL and have also conducted environmental 

assessments in the past for previously conducted exploration and development 

activities. Mr. Sabir expressed much interest in briefing and provided his following 

valuable suggestions: 

As the project area lies in forest protected areas hence, Sindh Forest Department 

(SFD) must be taken on‐board before and during the proposed project activities in 

the leased area; 

No Objection Certificate (NOC) from the relevant stakeholders (other than Sindh 

EPA) must be obtained before commencement of project activities; 

All applicable laws and regulations shall be complied during the proposed project 

execution in addition to best industrial guidelines ensuring no or least harm on the 

physical, biological and socioeconomic environment of the area; 

In addition the SFD, local administration should also be taken on‐board during the 

execution of the project activities to avoid social conflicts; 

Appropriate offsets should be provided from sensitive environmental features e.g. 

core wildlife areas, archeological sites, settlements etc. during the proposed project 

activities; 

Page 226: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 197 HPK

Project specific Waste Management Plan should be developed for both domestic 

and operational wastes and implemented with true spirit; 

Local environmental protection department should also be consulted to improve 

the environmental performance of the proposed project; and 

Contamination of local water resources shall be strictly avoided during the project 

activities and water conservation measures shall be taken during the entire course 

of the operation. 

Mr. Sabir further informed that when the EIA report would be officially submitted to 

Sindh Environmental Protection Agency, it would be reviewed in detail and 

comments will be addressed at that stage. EPA guidelines for carrying out impact 

assessment are also crucial. 

8.4.2 Range Forest Officer, Sindh Forest Department, Hyderabad

A formal consultation meeting was conducted with Mr. Bakht Hussain Jatoi to discuss 

the environmental issues related to the proposed exploration and associated 

development activities and their potential environmental impacts. Details of proposed 

project activities and the prospective areas were briefed to Mr. Jatoi with the help of 

maps. Mr. Jatoi briefed that agriculture has been stopped in the forest’s land as per 

directions issued by the respected Supreme Court of Pakistan. He also explained the 

jurisdiction of Forest Department and authoritative role for conduction of 

development activities in jurisdiction of Forest Department. Mr. Jatoi also explained 

the mechanism for obtaining NOC from the department and other legal obligations 

which should be followed/fulfilled before and during the proposed project activities. 

Furthermore, he expressed few certain concerns regarding the proposed project which 

are discussed as follows: 

NOC must be obtained from the department before commencement of project 

activities in the area; 

Natural habitat loss is a major concern which is anticipated due to proposed 

project activities. The operation will certainly disturb the existing biodiversity and 

ecosystem of the area therefore, proper mitigation measures should be suggested 

to lessen the impacts on the natural existing environment and suggested 

mitigation measures should be made part of operational and management 

systems; 

Deforestation must be avoided by taking appropriate measures; 

Trees cutting should be avoided to the extent possible; 

Key floral and faunal species of the area should be protected and conserved; 

Systems and procedure should be developed for revival and protection of 

ecosystem; and 

Monitoring of the project related activities and reporting of the non‐conformance 

to all concerned with reference to mitigation measures as suggested in the EIA. 

Page 227: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 198 HPK

8.4.3 Deputy Director, Sindh Environmental Protection Agency, Hyderabad

HPK paid a customary visit to meet with Mr. Abdul Rauf Qureshi, Deputy Director at 

his Hyderabad office. He was informed with the help of the project area map about the 

proposed project activities and their anticipated environmental impacts which may 

arise during the execution of the activities. Later the meeting was also joined by other 

officials from Sindh EPA, Hyderabad i.e. Mr. Ali Nawaz and Mr. Zulfiqar Baloch. All 

representatives of Sindh EPA appreciated the consultation process and expressed 

much interest in the briefing and provided valuable suggestions which are reproduced 

below: 

All applicable laws and regulations should be complied with during the proposed 

project execution in addition to best industrial guidelines ensuring no or least 

harm on the biological, physical and socioeconomic environment of the area; 

As the project activities also fall in reserved forests’ boundary therefore, Sindh 

Forest Department must be taken on‐board before and during the proposed project 

activities;  

Restoration of exploration and production sites is becoming nuisance and causing 

environmental degradation hence, restoration of project sites must be ensured by 

the proponent and Sindh EPA can be taken on‐board for the purpose; 

As the project activities are planned in forest protected area with good diversity of 

wildlife therefore, every effort should be made to protect the natural existing 

environment; 

Construction or blasting should not be performed in main body of Indus River; 

Community development work in area focusing lower class suffering from the 

enduring education, poverty, unemployment and social underdevelopment should 

be carried out; 

Vegetation clearing must be avoided and minimized to avert the biodiversity loss; 

and 

Contamination of soil and groundwater must be avoided by taking appropriate 

mitigation measures.  

Mr. Qureshi further informed that public participation should be ensured during the 

EIA process. Sindh EPA once receive the EIA, comments will also be shared with the 

proponent at that stage. 

8.4.4 Technical Officer, Directorate of Animal Husbandry, Hyderabad

Member of EIA team also visited to meet Dr. Abdul Manan (Technical Officer, 

Directorate of Animal Husbandry, Livestock and Fisheries Department, GoS) and 

briefed about the proposed project scope and prospective area with the help of maps. 

The purpose to carry out this meeting was to obtain the detailed information on the 

livestock of the area, proposed exploration and development activities and their 

potential impacts on the livestock which is a major source of income and social 

Page 228: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 199 HPK

security for communities residing in leased area. Dr. Manan briefed about the common 

diseases for domestic animals which mainly includes goats, sheep, cows, buffalos, 

donkeys and horses. During discussion Dr. Manan highlighted the importance of 

global warming and its effects on domestic & wild animals. Impacts of pesticides and 

chemicals used by the locals in agriculture fields were also discussed due to their 

effects on growth and mortality rate of domestic animals. Dr. Manan also informed 

that, in case of any disease outbreak (domestic or wild) in their jurisdiction, 

Directorate takes the initiative to protect the domestic livestock and even wildlife. He 

appreciated the stakeholder’s consultation process and his major concerns and 

suggestions were as follows:  

Zoning mechanism should be adopted for protection of livestock of the area. 

Livestock saturated zones should be avoided to the extent possible; 

Available water reservoirs should not be damaged or over exploited by the 

proposed project activities; 

Flaring should be minimized particularly during well testing and production 

operations;  

Controlled use of chemicals should be ensured to avoid the impact on locals 

animals; 

Veterinary Hospital with provision of complete facilities including Vet Officer (for 

timely identification and rectification of project’s adverse impacts on the livestock 

of the area), Mobile Unit and sufficient budget etc. was strongly recommended; 

Every effort shall be made for protection of natural habitats of the area; and 

Vegetation clearing shall be kept to the minimum required particularly range 

lands. 

8.4.5 Chief Engineer, Irrigation Department, Hyderabad

A formal consultation meeting was also carried out with Mr. Amjad Pervaiz Dawach 

to discuss the environmental sensitivities related to the proposed exploration and 

associated development project activities focusing the existing irrigation network in 

the area. Details of the proposed activities and prospective areas was briefed to Mr. 

Dawach with the help of maps. Furthermore, he expressed certain concerns regarding 

the project activities, which are indicated below: 

As the proposed project activities will also fall in the area where irrigation network 

exits therefor, appropriate mitigation measures should be suggested to avert any 

damage to existing irrigation network; 

All applicable laws and regulations with respect to irrigation and drainage should 

be complied with;  

Vegetation clearing must be avoided and minimized particularly along the banks 

of the existing irrigation network; and  

Page 229: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 200 HPK

Water abstraction for irrigation network should be done with the prior approval of 

the department. 

8.4.6 Institute of Environmental Studies, Karachi University 

A formal consultation meeting was also carried out with Prof. Dr. Moazzam Ali Khan 

to share project scope and to discuss the potential environmental issues related to the 

proposed project activities planned by United Energy Pakistan Limited in Kotri North 

Block (E.L. 2568‐21). As the institute has active participation in advisory role to various 

agencies and departments on environmental matters, therefore considering a basic 

stakeholder it deemed necessary to take Institute on‐board during the assessment 

process. Details of proposed exploration and associated development activities with 

respect to prospective area was briefed to Dr. Khan with the help of maps. He is an 

erudite, outspoken and well‐informed personality about the environmental scenarios 

in Sindh. Furthermore, he expressed some certain concerns regarding the proposed 

project activities, which are indicated below: 

Restoration of project working sites should be ensured after successful completion 

of any segment of the proposed project; 

There is need to cover all physical, biological and socioeconomic aspects of the 

project area in detail; 

Initiatives taken under CSR should be audited through independent auditing 

mechanism; 

Noise and dust emission which will be generated due to proposed project activities 

should be controlled and mitigated as appropriate. Regular noise and ambient air 

monitoring shall also be carried out as per all applicable laws; 

Sustainable use of water should be ensured by taken prudent water conservation 

measures during the entire phase of the proposed project; 

A comprehensive Waste Management Plan should be developed for the project 

which must cover all sorts of waste (liquid & solids) and followed on strict basis;   

Safe and environmentally friendly provisions should be recommended in the EIA 

report;  

Environmental enhancement should also be focused which is usually ignored; 

There should be arrangements for Independent Environmental Monitoring (IMC) 

of the project related activities and reporting of all non‐conformances with 

reference to EMP to Sindh EPA on strict and regular basis. 

Dr. Khan further emphasized on abidance of all applicable laws and regulations 

during the proposed project execution. In addition, best industrial guidelines shall also 

be practiced ensuring no or least harm to the existing environmental conditions of the 

area. 

Page 230: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 201 HPK

8.4.7 Regional Chair, Commission on Ecosystem Management, IUCN

A formal consultation meeting was also held with Prof. Dr. Muhammad Zaheer Khan 

to discuss the proposed exploration and associated development project activities and 

their potential impacts on the diverse wildlife of the Kotri North Block and its 

immediate vicinities. Dr. Khan is Regional Chair, West Asia, Commission on 

Ecosystem Management, The World Conservation Union – IUCN. Dr. Khan briefed 

about ongoing research projects in wildlife protected areas of Sindh region. Details of 

proposed project with sequence of events was briefed to Dr. Khan with the help of 

maps. The outcome of the meeting is reproduced below: 

As the project area lies in reserved forest areas hence, Sindh Forest Department 

must be taken on‐board during the execution phase of the project; 

All appropriate and practical mitigation measures should be suggested and taken 

to protect and improve the existing natural environment of the area; 

Vegetation clearing should be avoided as much as possible; 

Most advanced and environment friendly techniques & technologies should be 

employed/used during the execution of the project activities posing least 

environmental disturbance;  

Ambient air quality should not be deteriorated by the proposed project activities; 

Local fuel wood shall not be used by the parties working in the project area; and 

Range lands should also be protected during the execution of the proposed 

exploration project activities. 

8.4.8 Coordinator Marine Program, Worldwide Fund for Nature, Karachi

Members of EIA team also visited World Wildlife Fund for Nature’s (WWF) office in 

Karachi to meet with Mr. Muhammad Moazzam Khan (Technical Director) but due to 

his unavailability Mr. Jawad Umer Khan represented WWF in the consultation 

meeting. Details of proposed exploration and associated development activities and 

the prospective area was briefed to Mr. Khan with the help of maps. Mr. Khan openly 

discussed his suggestion and reservations regarding the proposed activities in Kotri 

North Block, which are discussed as follows: 

All applicable laws and regulations should be complied with true spirit; 

As the project area lies within the forest protected area hence, Forest Department 

should be taken on‐board before and during the proposed project activities; 

All adjacent areas to Indus River should be treated as environmentally sensitive 

and fragile;  

Activities should be planned in such a way that breeding seasons of key wildlife 

species of the area are not disturbed; 

Potential migration of wildlife due to operational reasons e.g. noise should be 

closely monitored and take appropriate actions thereon; 

Page 231: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 202 HPK

Restoration of project sites/facilities should be ensured after successful completion 

of project activities;  

General public participation should be ensured during the assessment process and 

their reservations and concerns should be addressed appropriately; and  

Independent monitoring needs to be ensured during the execution of the proposed 

exploration and associated development project activities. 

8.4.9 Other meetings

Meetings were also held particularly with villages’ heads to disseminate information 

regarding the proposed exploration and associated development activities. None of 

the stakeholders consulted during the EIA consultation process showed any 

uneasiness or apprehensions about the proposed project. Important recommendation 

from villages’ heads and local elders are as under: 

Locals should be preferred for employment; 

The local cultural norms should be respected; and 

The proponent should initiate comprehensive community development work in 

the project area. 

Key Findings and Issues

Biodiversity of area particularly should be protected by taking all concerned on‐

board; 

Most of the communities and to some extent the local influential people are not 

concerned over the environmental issues. They are mostly interested in getting 

maximum benefits in terms of employment, local market boom and community 

development programs; 

People have hopes that the company would employ locals during its operations. 

The biggest aspiration of the locals is getting one thing i.e. ‘employment’; 

People have hopes that the company would develop roads and improve the 

infrastructure of area; and 

Compensations for land acquired/leased and standing crops should be disbursed 

in a transparent manner on fast pace. 

Page 232: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 203 HPK

Table 8‐1: List of Stakeholders Consulted during EIA 

No.  Representative  Organization/Department Designation

1.   Mr. Mohammad Imran Sabir Sindh Environmental Protection 

Agency, Karachi  

Deputy Director 

(Technical) 

2.   Mr. Bakht Hussain Jatoi  Sindh Forest Department  RFO, Hyderabad 

3.   Mr. Abdul Rauf Qureshi Sindh Environmental Protection 

Agency, Hyderabad 

Deputy Director, 

Hyderabad Region 

4.   Mr. Ali Nawaz Sindh Environmental Protection 

Agency, Hyderabad 

Field Inspector, 

Hyderabad 

5.   Mr. Zulfiqar Baloch Sindh Environmental Protection 

Agency, Hyderabad 

Field Inspector, 

Hyderabad 

6.   Dr. Abdul Manan 

Directorate of Animal 

Husbandry, Hyderabad, 

Livestock and Fisheries 

Department, GoS 

Technical Officer 

7.   Mr. Amjad Pervaiz Dawach  Sindh Irrigation Department  Chief Engineer 

8.   Prof. Dr. Moazzam Ali Khan Institute of Environmental 

Studies, University of Karachi Professor  

9.   Prof. Dr. Muhammad Zaheer Khan 

University of Karachi/ West 

Asia, Commission on Ecosystem 

Management, The World 

Conservation Union – IUCN 

Professor/Regional 

Chair  

10.   Mr. Jawad Umer Khan Worldwide Fund for Nature 

(WWF) Pakistan 

Coordinator Marine 

Program 

 

Page 233: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 204 HPK

Photographs: Consultation Record 

 

Photograph 8‐1: Consultation at Goth Sufan 

Bacho 

  Photograph 8‐2: Consultation with Mr. Imran 

Sabir, Sindh EPA 

 

Photograph 8‐3: Consultation with 

Representatives of Sindh EPA, Hyderabad 

  Photograph 8‐4: Community consultation at 

Goth Haji Shabu 

 

Photograph 8‐5: Consultation with locals at 

Goth Khuda Baksh 

  Photograph 8‐6: Consultation session with 

RFO, Hyderabad 

Page 234: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 205 HPK

 

Photograph 8‐7: Consultation with Chief 

Engineer, Irrigation Department, Hyderabad 

Photograph 8‐8: Community consultation at 

Goth Bachal Dehta 

 

Photograph 8‐9: Consultation at Goth Bakhshia 

Mari 

  Photograph 8‐10: Consultation with Dr. Abdul 

Manan 

 

Photograph 8‐11: Consultation session with 

Prof. Dr. Moazzam Ali Khan 

  Photograph 8‐12: Community consultation at 

Goth Aliabad 

Page 235: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 206 HPK

 

Photograph 8‐13: Locals are being consulted at 

Goth Karim Deno 

Photograph 8‐14: Consultation session with 

Prof. Dr. Muhammad Zaheer Khan 

 

Photograph 8‐15: Consultation session Mr. 

Jawad Umer Khan (WWF Pakistan) 

  Photograph 8‐16: Community consultation at 

Goth Jaitharo 

 

Photograph 8‐17: Community consultation at 

Goth Haji Ishaq 

  Photograph 8‐18: Consultation with locals at 

Goth Gulshan‐e‐Shahbaz 

Page 236: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 207 HPK

9 Conclusion

Pakistan is an energy deficient country, a large part of the country’s energy demands 

are met through imports which is a severe burden on country’s foreign reserves and 

economy. There is, therefore, a vital need to explore for additional energy reserves. On 

the other hand, Pakistan is struggling to overcome a severe energy crisis that is 

directly and indirectly affecting all sectors of economy. The oil import bill of the year 

2017‐18 reached US $ 12 billion, creating a huge burden on the foreign exchange 

reserves.  

Oil & gas exploration and production have the potential to transform and can help to 

revolutionize the energy mix existing within the country and can significantly 

improve Pakistan’s economy. However, if country makes concreted and dedicated 

efforts, the same obstacles may be transformed into opportunities. It is essential to act 

now, and to develop our oil and natural gas resources, especially in the wake of acute 

shortages. Moreover, the report also discusses the generation of economic activity 

through oil and gas exploration and the possible benefits for thousands of Pakistanis 

who are in need of sources of sustainable livelihoods.  

Whereas the proposed O&G exploration and associated development activities in 

Kotri North Block (E.L. 2568‐21) will help towards achieving this objective. The 

environmental study of the project area requires that potential environmental effects 

due to the proposed project are evaluated, mitigation measures required to minimize 

or obviate these impacts are assessed, implemented and monitored. Any residual 

impacts are assessed for their significance.  

These requirements have been addressed in this Environmental Impact Assessment 

(EIA) study, which has covered in detail the following: 

The proposed project activities; 

Environmental baseline conditions of the project area;  

Legislative requirements related to the proposed project; 

Potential environmental effects of the proposed project activities on physical, 

natural or biological and socioeconomic receptors; and 

Mitigation and monitoring measures that will help in avoiding or minimizing 

these impacts.  

The operation will have a visible positive impact on the socioeconomic conditions of 

the local residents of the area, manifested as increased local businesses, local 

employment generated during the operations, increased mobility and increased 

income due to disbursed money.  

On the other hand, conservation of biodiversity in a sustainable way is also vital for 

future of any country. Pakistan has taken practical steps towards protection of 

environment in steady manner. Many efforts have been made for protection and 

Page 237: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 208 HPK

improvement of environmental biodiversity to reach the international standards 

however, there are still too many gaps and differences due to lack of proper 

management activities. Therefore, it is necessary to take serious actions for effective 

management of protected areas. Enforcement of existing laws in more effective mode, 

effective management plans, community involvement, engagement of more experts to 

achieve conservation targets, funding and recommendations of the EIA will ensure 

that protected areas and its existing environment is not adversely affected due to 

proposed project activities.  

This EIA concludes that the proposed exploration and associated development project 

will not lead to adverse environmental impacts of such nature or magnitude if the 

mitigation measures for all impacts identified here are implemented as per the 

prescriptions of the EIA. Similarly, no significant and unacceptable changes in the 

baseline environmental conditions of the project area will occur. Additionally, careful 

implementation of the project specific Environmental Management Plan (EMP) will 

ensure that environmental impacts are managed and minimized with project 

proponent meets all legal & statutory requirements.

Page 238: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

List of References

Ahmad, M. F. & Ghalib, S.A., 1975: A Checklist of Mammals of Pakistan. Ref.  Zool 

Sur. Pak. VII (1 & 2): 1‐34. 

Ali, S. I. & Qaiser M., 1995‐till to date: Flora of Pakistan Fascicles. Karachi. 

Ali, S., 1996: The Book of Indian Birds (Twelfth edition) Bombay Natural History 

Society & Oxford University Press, Mumbai. 

Alam, S.M., Naqvi, M.H. 2003. Water Scenario and Pakistan. NIA, Tandojam, Pakistan. 

Government of Sindh., Sindh Environmental Protection Act., 2014. 

Boyd, C.E. 2000. Water Quality: An introduction. Kluwer Academic Publishers Boston, 

MA, USA. Burbank, D.W. 1982. 

Busnel, R.G. and John Fletcher (eds.), 1978: Effects of Noise on Wildlife. New York: 

Academic Press. 

Convention on International Trade in Endangered Species of Wild Fauna and Flora 

(CITES)., 1973. 

Council of Environment Quality., USA 1978. 

Department of Natural Resources., 1990: Statewide Order 29 – B, State of Louisiana. 

Dharma Kumarsinhji, K. S., 1959: A field guide to big game census in India. Leaflet 

No. 2. Issued by the Indian Board for Wildlife.  

Dunbar brander, A.A., 1931: Wild Animals of central India, Edward Arnold, London. 

E&P Forum, 1994: Guidelines for the Development and Application of Health, Safety 

And Environmental Management Systems, Report No. 6.36/210, Exploration And 

Production Forum July. 

Ellerman, J.R. & T.C.S. Marrison‐Scott., 1951: Checklist of Palearctic and Indian 

Mammals, 1758 to 1946. British Museum (Natural History), London. 

EUAD/IUCN., 1992: The Pakistan National Conservation Strategy, Environment and 

Urban Affairs Division, GoP and The World Conservation Union. 

Fukushi, K., Kurisu, F., Oguma, K., Furumai, H., Fontanos, P. 2010. Southeast Asian 

water environment 4, IWA publishing, London, UK. 

Giles, H.R., 1971: Wildlife Management Techniques (Vol. 2). The Wildlife Society, 

Washington, D.C. 

Government of Pakistan., 1923. The Mines Act. 

Government of Pakistan., 1949. Pakistan Petroleum (Production) Rules, Ministry of 

Petroleum and Natural Resources, GoP. 

Government of Pakistan., 1975. The Antiquities Act.  

Page 239: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

Government of Pakistan., 1986: Pakistan Petroleum (Exploration and Production) 

Rules, Ministry of Petroleum and Natural Resources, GoP. 

Government of Pakistan., 1997 a: Guidelines for Public Consultation: Draft, Pakistan 

Environmental Protection Agency, GoP. 

Government of Pakistan., 1997 c: Guidelines for Preparation and Review of 

Environmental Reports: Draft, Pakistan Environmental Protection Agency, GoP. 

Government of Pakistan., 1997 d: Policy and Procedures for Filing, Review and 

Approval of Environmental Assessments, Pakistan Environmental Protection Agency 

(September). 

Government of Pakistan., 1997 e: Sectoral Guidelines – Oil and Gas Exploration and 

Production, Pakistan Environmental Protection Agency (December). 

Government of Pakistan., 2018. Pakistan Energy Year Book 2017‐18. Islamabad: 

Ministry of Petroleum and Natural Resources, Hydrocarbon Development Institute of 

Pakistan. 

Government of Pakistan., Pakistan Environmental Protection Act., 1997. 

Government of Pakistan., The Pakistan Penal Code., 1860. 

Grimmet, R.Inskipp, C. & Inskippe, T., 1998: Birds of the Indian Subcontinent. 

Halcrow Pakistan., 2004: Sectoral Guidelines for Upstream Petroleum Sector – 

Onshore, Pakistan Petroleum Exploration & Production Companies Association 

(PPEPCA) 

Halcrow Pakistan., 2018: Environmental Impact Assessment (EIA) for 3D Seismic and 

Drilling of Two Wells in Sukkur Block (E.L. 2768‐9), Sindh. 

Halcrow Pakistan., 2019: Environmental Impact Assessment (EIA) for 3D Seismic 

Survey and Drilling of Three Wells in Taung Block (E.L. 2567‐12), Sindh. 

Halcrow Pakistan., 2017: Environmental Impact Assessment (EIA) for Drilling and 

Associated Development Activities in Badhra Development & Production Lease, 

Sindh. 

Halcrow Pakistan., 2010: Environmental Impact Assessment (EIA) for Exploration 

Activities in Kotri, Kotri North and Jungshahi Blocks.   

Halcrow Pakistan., 2010: Initial Environmental Examination (IEE) for Exploration 

Activities in Kotri, Kotri North and Jungshahi Blocks. 

Halcrow Pakistan., 2017: Initial Environmental Examination for 3D Seismic Activities 

in Zamzama Development & Production Lease. 

Hompland, Gary et al., 1985: ʺElk Responses to Simulated Mine Disturbance in 

Southeast Idaho.ʺ Journal of Wildlife Management. 49(3)751‐757. 

IOGCC., The International Oil and Gas Compact Commission Guidelines on Disposal 

of E&P Waste. 

Page 240: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

IPIECA in cooperation with E&P Forum., 1997: London.  

IUCN., 1997: Biodiversity Action plan for Pakistan: First Draft, the World 

Conservation Union. 

IUCN., 1998: Draft Model Provincial Wildlife (Protection, Conservation and 

Management) Act, the World Conservation Union. 

IUCN., 2000: Red List of Threatened Animals. 

IUCN., Guide lines on Oil and Gas conservation Commission, Rules and Regulations. 

Jefferies, M., 1997: Biodiversity and Conservation London & New York. 

Khan, F.K. 1991. A geography of Pakistan; environment, people and economy. Oxford 

University Press. Karachi, Pakistan. 

Larry W. Canter., 1996: Environmental Impact Assessment, McGraw Hill Publications. 

Levin, D. A., 2000: The origin, expansion and demise of plant species. Oxford. 

Lydekker, R., 1924: The game animals of India, Burma, Malaya and Tibe. Rowland 

Word Ltd., London, 416 pp. 

Malik, K. A., 1984: Palmae in Nasir, E. & Ali, S. I. (eds.) Flora of Pakistan. Karachi, pp 

1‐33. 

Miller, J.N., Miller, J.C. 2000. Statistical and chemometrics for analytical analysis. 

Prentice Hall, California, USA. 

Model Petroleum Blocks Agreements., 1994. 

Munsell Color Company USA, 1954: Munsell Soil Colour Charts. 

Nasir, E. & Ali, S. I., 1972‐1995: Flora of Pakistan Fascicles, Karachi, Islamabad. 

NCS., 1972, National Conservation Strategy. 

Oil and Gas (Safety in Drilling and Production) Regulations., 1974. 

Population Census Organization., 2000: Government of Pakistan, 1998 District Census 

Report of Dadu, Population Census Organization (PCO), Statistics Division, 

Islamabad. 

Population Census Organization., 1999: Government of Pakistan, 1998 District Census 

Report of Hyderabad, Population Census Organization (PCO), Statistics Division, 

Islamabad. 

Population Census Organization., 1999: Government of Pakistan, 1998 District Census 

Report of Thatta, Population Census Organization (PCO), Statistics Division, 

Islamabad. 

Prator, S.H., 1965: The Book of Indian Animals. Bombay Natural History Society, 

India. 322 pp. 

Raunkiaer, C., 1934: The life forms of plants and statistical plant geography, Oxford. 

Page 241: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

Ref. Minton, S.A., 1996: A contribution to the Herpetology of Pakistan.  

Regulation of Mines and Oil fields and Mineral Development (Government Control) 

Act., 1948. 

Roberts, T.J., 1991: The Birds of Pakistan. Vol. 1 (Non‐Passeriformes), Oxford 

University Press, Karachi. 

Roberts, T.J., 1992: The Birds of Pakistan. Vol.2. Passeriformes. Oxford University 

Press, Karachi. 

Roberts, T.J., 1997: The Mammals of Pakistan. Oxford University Press, Karachi. 

Schemnitz, D.S, 1990: Wildlife Management Techniques Manual. Fourth Edition: 

Revised. The Wildlife Society. Washington D.C. 

Scott., D.A.(E,D), 1989: A directory of Asian Wetlands. IUCN, Gland, Switzerland and 

Cambridge, U.K. 

The Convention on Conservation of Migratory Species of Wild Animals., 1979. 

The Convention on Wetlands of International Importance, Ramsar., 1971. 

Ticehurst, Claude B., 1923: The birds of Sind, Ibis: Jan., Part 3 pp. 1‐43. 

USAID, 2013. Supplemental Report on Climate Change, Kurram Tangi Dam 

Construction, usaid.gov/pdf‐docs/PA00KB12.pdf 

UNIDO, 2000. Industrial Policy and the Environment in Pakistan: Industrial Policy 

and Environment. 

World Bank, United Nations Industrial Development Organisation and the United 

Nations Environment Program., 1998: Pollution Prevention and Abatement 

Handbook: Towards Cleaner Production. Environment Department, the World Bank, 

United Nations Industrial Development Organisation and the United Nations 

Environment Program. 

World Bank., 1999: Environmental Assessment‐Operational Policy 4.01. Washington, 

DC, USA.

Page 242: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 HPK

Appendix A Environmental Management Plan

Page 243: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-1 HPK

Appendix A – Environmental Management Plan

A.1 Introduction

United Energy Pakistan Limited (UEPL) intends to carry out exploration and 

development activities in Kotri North Block (E.L. 2568‐21). These activities range from 

2D/3D seismic surveys, drilling of exploration/development wells, laying of flow line/s 

from producing wells to the hydrocarbons gathering system/processing facility, 

establishment of processing facilities e.g. EWT or CPP, up‐gradation/modification of 

existing facilities with associated civil and engineering works e.g. construction of 

access track/s, residential camp/s, construction of well site/s etc. and finally 

decommissioning and site restorations.  

This Environmental Impact Assessment (EIA) for the proposed project activities in 

Block (E.L. 2568‐21) has identified potential impacts that are likely to arise. The EIA 

has examined in detail both negative and positive impacts of each stage of the 

operation from the initial establishment of the logistics facilities to demobilization and 

restoration. Where adverse impacts have been identified, the EIA has recommended 

practical mitigation measures. These mitigation measures include management and 

monitoring practices, alternative technologies, physical controls or compensation. The 

mitigation measures proposed are based on a good understanding of the sensitivity 

and behaviour of environmental receptors within the project area, past experience, 

case studies, legislative controls, guidelines and experts’ advices. 

For any residual impacts (impacts remaining after applying the recommended 

mitigation measures) or for impacts in which there has been a level of uncertainty in 

prediction such as the level of disturbance to wildlife, monitoring measures have been 

recommended. Advice on monitoring measures required was sought from experts 

involved in the EIA and case studies of similar monitoring carried out in other 

protected areas in Pakistan. 

For the effective implementation and management of the mitigation measures and 

monitoring requirements an Environmental Management Plan (EMP) has been 

prepared and presented in this section. The EMP satisfies the requirement of the Sindh 

Initial Environmental Examination and Environmental Impact Assessment Review 

Regulations, 2014 and Pakistan Initial Environmental Examination and Environmental 

Impact Assessment Review Procedures, 2000. 

A.1.1 Regulatory Approval and Monitoring Mechanism

After getting ‘No Objection Certificate (NOC)’ from Sindh Environmental Protection 

Agency (Sindh EPA), United Energy Pakistan Limited (UEPL) will be allowed to 

conduct its proposed exploration and associated development activities in Kotri North 

Block (E.L. 2568‐21). This EIA report is based on the fact that UEPL will obtain NOC 

for the EIA (covering proposed exploration and associated development activities as 

described in Chapter 4 of this EIA) from Sindh EPA and will submit the Project 

Page 244: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-2 HPK

Initiation Report (PIR) for each proposed exploration and development to Sindh EPA 

(for information) fifteen days prior to the start of any operation.  

Kotri North Block (E.L. 2568‐21) encompass several forest protected areas. There are 

about 28 reserve forests (all of them are small sized) are falling in the geographical 

jurisdiction of the Block (E.L. 2568‐21). These reserve forests includes; Kunar Rishal, 

Keti Dallu, Nur Keti, Drabo, Manjhand, Keti Khasai, Unarpur, Rudhapur, Rishal, 

Nural Abad, Racho Khanot, Pako Bhanot, Butho, Ranno, Rajri, Salaro Ghotana, Lakha, 

Khasai, Ghotana, Murid Rais, Sekhat, Matiari, Miana, Hatri, Muhammad Khan, Bada, 

Shah Bukhari and Railo Bada. These reserve forests which were once pristine riverine 

forests, now mostly are under cultivation.  

All activities which are being planned particularly seismic, drilling, laying of flow line 

activities and establishment of processing facility (GPF) within the project area will be 

monitored by a team of Independent Monitoring Consultant (IMC). The team will 

comprise of activity monitor, wildlife monitor and a wildlife specialists (SWD 

representative). Monthly effects monitoring and activity monitoring will also be 

carried out according to the monitoring program recommended in the EMP. 

A.1.2 Objectives of the Environmental Management Plan (EMP)

The EMP provides a delivery mechanism to address adverse environmental impacts, 

to enhance project benefits and to introduce standards of good practice to be adopted 

for all project works. The primary objectives of the EMP are: 

Outline mitigation measures recommended in the EIA and define the 

responsibility and timing for the implementation of these measures; 

Develop a monitoring mechanism and identify parameters that can confirm the 

implementation of the mitigation measures; 

Define roles and responsibilities of the project proponent for the implementation of 

EMP and identify areas where these roles and responsibilities can be shared with 

other stakeholders; and 

Define the requirements necessary for documenting compliance with the EMP and 

communicating it to all concerned regulatory agencies. 

A.1.3 Methodology

The basic approach to prepare this plan mainly comprise of: 

A review of relevant environmental laws, policies, legislations and guidelines; 

A review of past environmental studies carried out in Kotri North Block and 

immediate concessions; 

A review of relevant environmental data in Kotri North Block; 

On the basis of past experience gained during the monitoring of similar projects in 

relation to O&G exploration and production; and 

Page 245: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-3 HPK

Consultation with United Energy Pakistan Limited’s staff. 

A.2 Legislation and Guidelines

The EIA has discussed national and international legislation and guidelines and their 

relevance to the proposed project. United Energy Pakistan Limited shall ensure that 

the operation is conducted in conformance to UEPL’s corporate environmental policy, 

national legislation and relevant international conventions and that guidance is sought 

from national and international guidelines. All relevant legislation, guidelines, 

convention and corporate requirements are discussed in Chapter 3 of this EIA. UEPL 

shall also ensure that the key project management staffs are aware of these legislation 

and guidelines.  

The Sindh Environmental Quality Standards (SEQS) specify standards for industrial 

and municipal effluents, gaseous emissions, vehicular emissions and noise levels is 

provided in Table 3‐1, Table 3‐2 and Table 3‐3 of EIA report. The standards for 

ambient air requirements, noise levels and drinking water quality are provided in 

Table 3‐4 to 3‐6. International standards for land treatment and on‐site burial of E&P 

wastes in unlined pits is provided in Table 3‐7. Table 3‐8 provides the less stringent 

criteria set by LSO 29B. 

A.3 Organizational Structure with Roles & Responsibilities

A.3.1 Organizational Structure

The proposed project includes the following main organizations: 

United Energy Pakistan Limited as the project proponent and owners of the EMP; 

The seismic, construction, drilling, laying of flow line, establishment of processing 

facility and all other contractors as the executors of the EMP; 

Independent Monitoring Consultants (IMC) as the monitors for the execution of 

the EMP and effects monitoring; and 

Sindh Environmental Protection Agency, Sindh Wildlife Department and Sindh 

Forest Department as the regulators. 

These organizations will have the following roles and responsibilities during the 

project activities. 

A.3.2 Roles & Responsibilities

Abovementioned organizations will have the following role and responsibilities 

during the proposed project activities. 

a. Roles & Responsibilities of United Energy Pakistan Limited (UEPL) 

As project proponents, UEPL will be responsible for ensuring the implementation of 

the EMP. The HSE (Health, Safety and Environment) Manager will be responsible for 

the overall environmental performance during the proposed operations. He will 

delegate a representative from UEPL who will have functional responsibilities for 

Page 246: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-4 HPK

Health, Safety and Environmental (HSE) matters during the project. The UEPL 

representative will hold prime responsibility for ensuring that the environmental 

performance of the project is in accordance with governing legislations, UEPL’s 

corporate objectives and the recommendations of this EIA. UEPL will ensure that the 

provisions of the EMP are translated into the contractor’s requirements and that these 

requirements are implemented to the full extent. 

b. Roles & Responsibilities of Project Contractors 

For the proposed project, UEPL will appoint contractors for different field operations. 

The contractors will be responsible for implementation of, or adherence to all 

provisions of the EIA and the EMP and with any environmental and other codes of 

conduct required by UEPL. Overall responsibility for the contractor’s environmental 

performance will rest with the person holding the highest management position 

within the contractor’s organization in Pakistan. Reporting to their management the 

contractor’s site manager will be responsible for the effective implementation of the 

EIA and the EMP. The contractor’s HSE officer will have functional responsibilities to 

ensure implementation of or adherence to the requirements of the EMP. 

c. Roles and Responsibilities of IMC 

To fulfil the monitoring requirements within area of operation, UEPL will appoint an 

Independent Monitoring Consultant (IMC). The IMC will be responsible for carrying 

out monitoring according to the requirements of the EMP. Program Manager of IMC 

will be responsible for the management of the IMC field monitors and effects 

monitoring team comprising of an activity monitor, wildlife monitor and wildlife 

specialist (SWD) which will report to the Program Manager. IMC’s field 

representatives will have functional responsibilities to ensure monitoring of the project 

activities as per the requirements of the EMP. The IMC will report directly to UEPL 

who will then disseminate the IMC reports and findings to Sindh EPA. 

d. Roles and Responsibilities of Regulators 

In pursuance to the sub‐regulation (2) of Regulation 9 of Sindh Initial Environmental 

Examination and Environmental Impact Assessment Review Regulations, 2014 after 

receiving the subject EIA from the proponent and issuing the confirmation of 

completeness cause to be published in any English or Urdu national newspaper and in 

a local newspaper of general circulation in the area affected by the project, a public 

notice mentioning the type of project, its exact location, the name and address of the 

proponent and the places at which the EIA of the project, subject to the restrictions in 

sub‐section (3) of  Section 17, can be accessed. The notice will fix a date and time and 

place for the Public Hearing for any comments on the project or the EIA. 

Sindh EPA, SFD and SWD will monitor compliance with the requirements of EMP of 

the project and any additional mitigation measures provided in the NOC for the 

project. 

 

Page 247: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-5 HPK

A.3.3 Planning & Design of the Operation

a. Design of the Operation 

Design of the operation includes the activities detailed in the Chapter 4 of EIA report. 

Following approval of the EIA, any changes to the proposed activities will be handled 

through the Change Management Plan provided in this EMP. 

b. Approvals 

Obtaining No Objection Certificate (NOC) from the Sindh EPA will not relieve the 

proponent of other legal obligations and hence UEPL and project contractors will 

obtain all other relevant clearances and necessary approvals required by the 

Government of Pakistan or Government of Sindh prior to commencing the respective 

operations. 

c. Contractual Provisions 

Adherence to the requirements of the EIA and EMP in terms of environmental 

mitigation will be required from all project contractors and thus EMP will form part of 

their contracts with United Energy Pakistan Limited. 

A.3.4 Implementation of the Operation

a. Coordination with Stakeholders 

United Energy Pakistan Limited will ensure that coordination with project 

stakeholders i.e. Sindh EPA and SFD on environmental and social matters as required 

by the EMP are maintained throughout the course of operation. SWD can also be taken 

on‐board to improve the biodiversity of the area. 

b. HSE Management Systems 

United Energy Pakistan Limited and its contractors will ensure that the mitigation 

measures mentioned in the Mitigation Management Matrix for the core activities of 

seismic, drilling, laying of flow line activities and establishment of processing facility 

(Table A‐1, Table A‐2, Table A‐3 and Table A‐4) are adhered to and organizational 

HSE Management Systems are implemented during the proposed project. The 

contractors will abide by the relevant contractual provisions relating to the 

environment. 

c. Minimum Distances 

The EIA specifies minimum distances to be maintained from environmental features 

including communities, water resources, wildlife sensitive areas and archaeological 

sites (if encountered) etc. These minimum distances from sensitive environmental 

features for project activities are provided in Table A‐5, A‐6 and A‐7. The Contractors 

shall ensure that these minimum distances are adhered to during the operation and 

are inspected by United Energy Pakistan Limited’s Representative. 

 

Page 248: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-6 HPK

d. Monitoring 

United Energy Pakistan Limited, contractors of the project and IMC will ensure that 

monitoring of the proposed project activities are carried out according to the 

monitoring program given in the EMP. An environmental monitoring program is 

provided in Section 4 of the EMP. A tentative frequency of monitoring mitigation 

measures is provided in Table A‐8. 

e. Emergency Procedures 

United Energy Pakistan Limited and the contractors will prepare contingency plans to 

deal with any emergency situation that may arise during the operation e.g. major oil 

spills, medical evacuation and communicate these to the regulatory agencies if 

required or inquired. 

f. Approvals 

The project contractors will be responsible for obtaining all relevant approvals from 

IMC such as approvals for waste contractors, water sources, camps’ location and 

setup, and others as specified in the Mitigation Management Matrix. 

g. Trainings 

All contractors engaged in the activities will be responsible for the selection and 

training of their staff capable of completing the project activities properly and 

efficiently. The contractor with the assistance of IMC will be responsible for providing 

trainings to their staff members according to the training program. The training 

program is discussed briefly in Section 8. 

h. Communication and Documentation 

UEPL, IMC and the contractors will ensure that the communication and 

documentation requirements specified in the EMP are fulfilled during the entire phase 

of proposed project activities. 

i. Restoration  

United Energy Pakistan Limited will be responsible for the final restoration of work 

areas according to the requirements of the EIA. 

A.4 Environmental Monitoring

The objective of the environmental monitoring during proposed exploration and 

associated development phase will be as follows: 

To check compliance of the contractors and UEPL with the EMP by monitoring 

activities of the project on a daily basis; 

To monitor impacts of the operation in which there has been a level of uncertainty 

in prediction such as impacts on wildlife and to recommend mitigation measures if 

the impacts are assessed to be in excess of or different from those assessed in the 

EIA. The aim will be attained through Effects Monitoring; and  

Page 249: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-7 HPK

To ascertain residual impacts of the entire course of the operation. This will be 

achieved by Post‐Project Monitoring. 

To achieve these objectives the following monitoring program will be implemented. 

a. Compliance Monitoring 

Compliance monitoring will be carried out to ensure compliance with the 

requirements of the EIA and to document and report all non‐compliances. The 

Mitigation Management Matrix for core activities i.e. Seismic, Drilling, Laying of Flow 

Line/Tie‐in/Wellhead Works and Establishment of GPF/CPP are provided in the EMP 

will be used as a management and monitoring tool. Inspection may be carried out 

using standard checklists provided in the EMP. Activity monitoring will be the 

responsibility of all organizations involved in the operation i.e. UEPL, IMC, Seismic, 

Drilling and other project executor contractors. 

The contractors HSEO will be responsible for monitoring the compliance of their 

organization with the relevant EMP requirements. An IMC field monitor will monitor 

the contractor’s compliance and will also ensure that during proposed project 

activities, a system and plan is in place for effective compliance monitoring. Any non‐

compliance observed by IMC will be recorded in non‐compliance recording forms and 

discussed during the daily environmental meeting. UEPL’s Representative will make 

regular checks on the contractor’s works, keep records of all non‐compliances 

observed during the execution of the project activities and the details of all remedial 

actions taken to mitigate the adverse project impacts. 

b. Effects Monitoring 

IMC field monitor will be responsible to carry out the required effects monitoring 

during the seismic, overall construction and drilling activities. A wildlife monitor and 

specialists will also accompany him during monthly wildlife effects monitoring 

survey.  

c. Post‐Project Monitoring 

The objective of this monitoring will be to determine the level of residual impacts of 

the project activities on physical, biological and socioeconomic receptors of the project 

area. The monitoring may be carried out within one month after the end of all 

activities in the project area. As part of the post‐project monitoring methodology 

restoration of sites will also be checked. 

A.5 Communication & Documentation

A.5.1 Project/Activity Initiation Report

Prior to the start of any segment of the proposed exploration and associated 

development activities, United Energy Pakistan Limited will inform the Sindh 

Environmental Protection Agency (Sindh EPA) about the initiation of the respective 

activity and relevant details such as site specific baseline conditions and any changes 

from the EIA. The information will be submitted to Sindh EPA in the form of Project 

Page 250: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-8 HPK

Initiation Report or Activity Initiation Report at least 15 days prior to the start of the 

particular activity.  

A.5.2 Kick-off Meeting

For proposed exploration and associated development operation, prior to 

commencement of work and after setup of the field camp, a meeting will be held on‐

site to discuss implementation of the EMP, show commitment to adhere with the EMP 

and check readiness of the contractors to start the project. The meeting will be 

attended by relevant management staff from United Energy Pakistan Limited and the 

contractors. Sindh EPA, SFD and SWD officials may also be invited to attend the 

meeting. 

A.5.3 Daily Meetings & Reports

A daily meeting will be held during the proposed exploration and associated 

development project activities to discuss the environmental conduct of the respective 

operation, non‐compliances noted and their remedial measures. The meeting will be 

attended by the UEPL Site Representatives, Contractor’s HSEO and IMC’s Activity 

Monitor. The meetings will be recorded in the form of a Daily Environmental Report. 

The report will be communicated to the UEPL’s HSE Representatives and senior 

members of the contractors. The report will include: 

Summary of project activities on that day;  

UEPL and contractors environmental representatives present onsite; and 

Non‐compliances observed and mitigation measures taken or required. 

A.5.4 Monthly Reports

A Monthly Environmental Report (MER) will be prepared by IMC summarizing the 

project activities and results of activity and Effects Monitoring. The purpose of these 

reports will be to review the performance of the operation by reviewing the number of 

non‐conformances and the environmental incidences that occurred during the 

reporting period, progress on daily action items and to list recommendations for 

additional controls, mitigation measures or monitoring requirements. 

A.5.5 Effects Monitoring Reports

The results of effects monitoring surveys on biological, physical and socioeconomic 

environment e.g. on wildlife, use of water resources, communities etc. will be 

compiled by the Independent Monitoring Consultant in the form of a report. This 

section on effects monitoring will be included in the monthly and final environmental 

monitoring report. Effects monitoring requirements for proposed exploration and 

associated development activities is provided in Table A‐9. The report as a minimum 

will include: 

Objectives and methodology; 

Person(s) involved in the survey; 

Page 251: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-9 HPK

Areas surveyed: 

Results of the monitoring exercise along with raw data collected on field; and 

Conclusions on the effects of the project activities. 

A.5.6 Social Complaints Register

The UEPL’s Site Representative will maintain a register of complaints received from 

local communities and measures taken to mitigate these concerns. All community 

complaints received will be sent to the UEPL’s HSE Management for further action.  

A.5.7 Change Record Register

All changes to the EMP or the project will be handled through the Change 

Management Plan provided in the EMP. These changes will be registered in a Change 

Record Register. 

A.5.8 Photographic Record

United Energy Pakistan Limited will ensure that a photographic record including the 

following is maintained: 

All areas used by the project activities; before use, during use and after restoration; 

Key non‐compliances; and 

Key project activities. 

A.5.9 Final Monitoring Report

For each project a final monitoring report will be prepared by Independent Monitoring 

Consultant (IMC). The report will include the following: 

Introduction; 

Details of the project activities; 

Natural resources used during the project; 

Non‐compliances recorded; 

Effects of the project on wildlife, communities and physical resources; 

Photographic records; 

Approvals provided during the project;  

Change management statements; 

Trainings;  

Conclusions; and 

Recommendations for future projects. 

Page 252: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-10 HPK

A.6 Mitigation Management Matrix

Mitigation Management Matrix for proposed core operations i.e. seismic, drilling, 

laying of flow line and establishment/construction of GPF with associated civil and 

engineering activities is provided in Table A‐1, Table A‐2, Table A‐3 and Table A‐4. 

The Mitigation Management Matrix will be used as a management and monitoring 

tool for implementation of the mitigation measures required by the EIA. The matrix 

lists down: 

The required mitigation measures recommended in the EIA; 

The person/organization directly responsible for adhering to or executing the 

required mitigation measures and monitoring adherence to the mitigation 

measures; 

The parameters which will be monitored to ensure compliance with the mitigation 

measures; and 

The timing at which the mitigation or monitoring has to be carried out. 

United Energy Pakistan Limited will hold primary and overall responsibility for 

ensuring full implementation of the EMP. 

A.7 Change Management Plan

The EIA recognizes that changes in the operation or the EMP may be required during 

the proposed exploration and associated development project activities therefore, 

provides a Change Management Plan to manage such changes. The management of 

changes is discussed under two separate headings, Changes to the EMP and Changes 

to the Operation. 

A.7.1 Changes to the EMP

The EIA and the EMP have been developed based on the best possible information 

available at the time of the EIA study. However, it is possible that during the conduct 

of the proposed operation some aspects of the EMP may need to be changed owning 

to their non‐applicability in a certain area of operation or the need for additional 

mitigation measures based on the findings of environmental monitoring during the 

operation. In such cases following actions shall be taken. 

A meeting will be held between United Energy Pakistan Limited, the contractor and 

the Independent Monitoring Team (if required). During the meeting the proposed 

deviation from the EMP, planning and designing will be discussed and agreed upon 

by all parties. 

Based on the discussion during the meeting, a change report will be produced 

collectively, which will include the original EMP clause/plan or design, the change 

that has been agreed upon and the reasons for the change. The report will be signed by 

all the parties and will be filed at the site office. All relevant project personnel will be 

informed of the change. 

Page 253: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-11 HPK

A.7.2 Changes to the Operation

The change management system recognizes three orders of changes. 

a. First Order Change 

A first order change is the one that leads to a significant departure requires a 

reassessment of the environmental impacts. Examples of first order impacts include: 

Any other activity other than those specified in this EIA e.g. construction of PV 

plant, establishment of wind farm; and 

Seismic, drilling or establishment of hydrocarbon processing facility outside of 

Kotri North Block; 

Action Required – Environmental impacts of the proposed change will be reassessed 

and sent to the Sindh Environmental Protection Agency for approval. 

b. Second Order Change 

A second order change is one that does not result in the project description or impacts 

that are significantly different from those detailed in the EIA. Examples of second 

order changes include: 

During project activities, inability to adhere with the  minimum distances 

recommended in the EIA/EMP; 

Use of oil based mud during drilling;  

Increasing the crew size by over 100% during seismic acquisition; 

Undertaking of construction activity during night time; and 

Under unavoidable conditions (due to improper access for water bowsers, long 

haul distances or unavailability of tube wells in the project area etc.) limited water 

abstraction from surface water resources (not visited/inhabited by wildlife) to be 

allowed (for seismic acquisition only) by IMC after getting a formal approval from 

locals/influential and regulators like Irrigation Department and ensuring that 

limited water will not result in water shortage at that point and social conflicts. 

Action Required – The required action for such changes is to reassess the impact of the 

activity on the environment and specify additional mitigation measures if required 

and report the changes to the Sindh EPA. Sindh EPA will review the change 

management statement and communicate any concerns. If Sindh EPA agrees with the 

assessment of the IMC, it does not have to send a formal approval. 15 days after 

submission of the change management statement, the change will be implemented 

unless a communication to the contrary has been received from Sindh EPA. 

c. Third Order Change 

A third order change is one that does not result in impacts above those already 

assessed in the EIA, rather these may be made on site to minimize the impact of an 

activity such as: 

Page 254: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-12 HPK

Increasing the crew size by over 50% during seismic acquisition; 

Use of vibroseis in a small portion of agricultural land; 

Change in alignment of seismic lines or RoW of flow line to avoid sensitive areas; 

and 

One or all of the minimum distances specified in the EIA cannot be maintained 

only once or twice during the operation. 

Action Required – The only action required for such changes will be to record the 

change in the Change Record Register. 

A.8 Training Program

Environmental trainings will be formed, part of the environmental management 

system. The training will be directed towards all personnel for general environmental 

awareness. 

A.8.1 Objectives

The key objective of training program is to ensure that the requirements of the EMP 

are clearly understood and followed throughout the project. The trainings to the staff 

will help in communicating environmental related restrictions specified in the EIA and 

EMP. 

A.8.2 Roles and Responsibilities

The contractors will be primarily responsible for providing environmental training to 

all project personnel on potential environmental issues of the project. The contractors 

will be responsible to arrange trainings and ensure the presence of targeted staff. 

A.8.3 Training Program

The environmental awareness, EIA and EMP trainings will also be carried out during 

the entire course of the proposed operation on the basis of following criteria:  

a. Training Logs 

All training logs will be maintained by the contractors. The training log will include: 

Topic 

Date, time and location 

Trainer 

Participants 

b. Training Needs Assessment 

In addition to the training specified in the training log special/additional trainings will 

be provided during the project activity. The criteria to assess the need of training will 

be based on the following: 

When a specified percentage of staff is newly inducted in the project; 

Page 255: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-13 HPK

When any non‐compliance is repeatedly reported, refresher training will be 

provided regarding that issue; 

When any environmental incident/accident of minor or major nature occurs; 

Arrival of new contractor/sub‐contractor; and 

Start of any new process/activity. 

Suggested training program during the proposed exploration and associated 

development activities is provided in Table A‐10. 

c. Training Material 

The contractors will develop and prepare training material regarding environmental 

awareness, sensitivity of the area, EIA, EMP and restrictions to be followed during the 

project. Separate training material will be prepared for each targeted staff.  

 

Page 256: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-14 HPK

Table A‐1: Mitigation Management Matrix for Proposed Seismic Activities 

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

1  Changes in Landscape & Soil Erosion 

1.1  Seismic lines in the undulating areas will follow natural contours 

wherever possible. However, in areas where seismic line cutting is a 

requirement, the activity will be carried out in a way that would 

minimize disturbance to natural topography and soils 

UEPL, IMC, SC  Check line preparation  During line 

preparation 

1.2  The width of lines cleared for vibroseis will be limited to 3 m to 

minimize clearing of vegetation and disturbance to soil 

UEPL, IMC, SC  Randomly check width of lines  During line 

preparation 

1.3  Clearing of vegetation will be kept to a minimum, especially dense 

patches of vegetation and the areas where the wildlife presence is 

confirmed and near surface water bodies 

UEPL, IMC, SC  Monitor land clearing activities  During land clearing  

1.4  The cutting of trees or tall shrubs will be avoided as much as possible  UEPL, IMC, SC  Supervise land clearing activities  During land clearing 

1.5  Construction and seismic camps will be located in existing clearings 

and on levelled land 

UEPL, IMC, SC  Identify campsite for the SC  At the time of site 

selection for campsite 

1.6  Total land uptake by the camps and access road will be kept to the 

minimum required 

UEPL, IMC, SC  Check areas  Prior to and during 

construction of camps 

1.7  During seismic operation the number of routes used will be kept to a 

minimum and road travel will be minimized 

UEPL, IMC, SC  Approve access tracks and check 

road travel 

During the entire 

operation 

1.8  During seismic operation the preparation of new access tracks will be 

minimized. Where improvement of existing tracks or development of 

short lengths of new tracks is unavoidable the width of the access track 

will not exceed 3 m 

UEPL, IMC, SC  Supervise preparation of access 

tracks and randomly check width 

of access track 

Prior to and during 

track preparation 

1.9  Vehicles speed will be regulated and monitored to avoid excessive dust 

emissions 

UEPL, IMC, SC  Set and monitor speed limits  During the entire 

operation 

1.10  Off‐road travel should be avoided and observance of this should be 

monitored during the operation 

UEPL, IMC, SC  Approve access track and 

monitor off‐road travel 

During the entire 

operation 

Page 257: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-15 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

1.11  Periodic trainings will be provided to drivers on mitigation measures 

related to off‐road travel and speed limits 

UEPL, IMC, SC  Check training log and provide 

trainings 

During the entire 

project 

1.12  Photographs will be taken before any activity to record the conditions 

of campsite, roads and seismic lines at locations that are likely to under 

go soil erosion. Similar photographs will be taken at intervals 

throughout the survey to monitor any changes and soil conditions 

IMC, UEPL  Supervise and ensure compliance During the entire 

project 

2  Soil and Water Contamination 

2.1  Sewage Treatment Plant (STP) shall be preferred for handling of 

black/grey water under BATNEEC/BAT, but in case of unavailability of 

STP, septic tank and soak pits shall be provided 

UEPL, IMC, SC  Check provision of STP  During the design and 

construction of 

campsite 

2.2  Wastewater from laundry, kitchen washings and showers will be 

disposed of into separate soak pits 

UEPL, IMC, SC  Check provision of soak pits at 

campsite 

During the 

construction of 

campsite 

2.3  Soak pits shall be built in absorbent soil and located 300 m away from a 

surface water source or a groundwater well 

UEPL, IMC, SC  Check soil condition and distance 

between the soak pits and the 

nearest water body 

During the 

construction of 

campsite 

2.4  Soak pits will be constructed such that surface runoff cann’t enter into 

the pits 

UEPL, IMC, SC  Check design of the soak pit and 

monitor construction 

During the 

construction of 

campsite 

2.5  All kinds of wastewater pits will be designed to accommodate 

wastewater generated during the total duration of the operation 

UEPL, IMC, SC  Check design of wastewater pits  Before construction 

2.6  In case the soak pits get filled during the operation, grey water will be 

discharged in the nearest municipal drains after getting formal 

approval from local authorities. Sprinkling of grey water will be not be 

allowed 

UEPL, IMC, SC  Check provision of soak pits and 

monitor the transfer activity 

During the entire 

operation 

2.7  No solid waste will be disposed of in the field. Within the camp areas 

all solid wastes will be disposed of in waste bins provided within the 

camp area 

UEPL, IMC, SC  Check provision of waste bins  During the entire 

operation 

Page 258: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-16 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

2.8  Combustible, non‐combustible and hazardous wastes including plastic 

or glass bottles and cans will be temporarily stored on site and 

sold/handed over to a waste/recycling contractor who will utilize these 

wastes for recycling purposes 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

2.9  At the time of restoration soak pits will be backfilled with at least 1 m 

of soil cover keeping in view landscape of surrounding natural surface

UEPL, IMC, SC  Check soil cover  During the restoration 

2.10  At the time of restoration septic tanks will be dismantled in place and 

backfilled with at least 1 m of soil cover above the buried dismantled 

septic tank 

UEPL, IMC, SC  Check soil cover  During the restoration 

2.11  It will be ensured that after restoration activities the campsites are 

clean and that no refuse has been left behind 

UEPL, IMC, SC  Detail inspection  After restoration 

2.12  All concrete structures at the campsites will be removed and buried in 

garbage or soak pits and the pits backfilled with at least 1 m of soil 

cover 

UEPL, IMC, SC  Check compliance  During the restoration 

2.13  Restoration of seismic lines will include removal of all cables, 

geophones, station units, flags, stakes and wastes from the lines and 

back filling of all mud pits. For reference purposes a photographic 

record of selected sections of seismic lines will be taken before and 

after the operation 

UEPL, IMC, SC  Check line restoration  During and after the 

restoration of seismic 

lines 

2.14  Vehicles will only be washed in designated areas within campsites  UEPL, IMC, SC  Ensure provision of washing 

areas and monitor any non‐

compliances 

During the entire 

operation 

2.15  Vehicles will be daily checked for fuel or oil leaks. Vehicles with leaks 

will not be operated until repaired 

UEPL, IMC, SC  Check maintenance logs and 

ensure daily inspection of 

vehicles for leaks 

During the entire 

operation 

2.16  All fuel and oil storage areas will have a concrete pad underneath to 

prevent soil contamination in case of leaks or spills 

UEPL, IMC, SC  Ensure provision of concrete pad  During camp setup 

and construction 

activity 

Page 259: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-17 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

2.17  All fuel tanks will be properly marked to highlight their contents  UEPL, IMC, SC  Check safety signs  During the entire 

operation 

2.18  Fuel and oil storage areas will have secondary containment in the form 

of concrete or brick masonry bunds. The volume of the containment 

area should be equal to 125% of the total volume of fuel stored 

UEPL, IMC, SC  Check containment volume of the 

bunded area 

At the time of 

construction 

2.19  During fuel and oil transfer operations such as re‐fuelling 

vibroseis/bulldozers through a dedicated fuel vehicle, drips and spills 

will be avoided and drip pans will be used 

UEPL, IMC, SC  Ensure provision of drips pans, 

provide training on safe re‐

fuelling practices, monitor oil or 

fuel transfer 

During the entire 

operation 

2.20  Fuels tanks will be daily checked for leaks and all such leaks will be 

plugged immediately 

UEPL, IMC, SC  Inspect fuel tanks for leaks  During the entire 

operation 

2.21  The soil contaminated from minor and moderate spills will be removed 

disposed of appropriately 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

2.22  The soil contaminated from major spills may require specialized 

treatment such as incineration or bioremediation 

UEPL, IMC, SC  Monitor and supervise special 

treatment, if any 

During the entire 

operation 

2.23  A spill prevention and contingency plan will be prepared to deal with 

moderate and major spills 

UEPL, IMC, SC  Study and examine the plan and 

identify any flaws, if any before 

its approval 

Before the 

commencement of 

project 

2.24  Shovels, plastic bags and absorbent material should be present near 

fuel and oil storage or handling areas to attend spills and leaks 

UEPL, IMC, SC  Check provision of materials  During the entire 

operation 

2.25  Used oil and vehicle related waste will be transported to local 

contractors for recycling 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

2.26  Bentonite mud used for the purpose of uphole and deep hole drilling 

will be prepared in earthen pits. The used mud will be disposed of in 

the same pit and left to dry. After the mud has dried the pit will be 

backfilled 

UEPL, IMC, SC  Monitor preparation and disposal 

of mud 

During deep hole and 

uphole drilling 

2.27  Medical wastes will be temporarily stored onsite separately and 

incinerated at nearest facility 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

Page 260: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-18 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

2.28  Construction of burn pit and burning of waste will not be allowed  UEPL, IMC, SC  Check compliance  During the entire 

operation 

2.29  Blasting, construction or drilling activities will not be performed in 

Indus River 

UEPL, IMC, SC  Ensure compliance  During the entire 

operation 

3  Deterioration of Air Quality 

3.1  Generators, compressors, equipment and vehicles used during seismic 

operations will be maintained in a good condition to ensure that 

emissions are kept to a minimum level 

UEPL, IMC, SC  Check maintenance logs   During the entire 

operation 

3.2  During seismic operations vehicles speed will be regulated and 

monitored to minimize dust emissions 

UEPL, IMC, SC  Set and monitor speed limits  During the entire 

operation 

3.3  Campsites will be located at least 300 m away from communities  UEPL, IMC, SC  Check distances of campsite from 

communities 

Prior to construction of 

campsites 

3.4  During construction and seismic operation dust emissions will be 

minimized by sprinkling of the access tracks (wherever applicable) 

UEPL, IMC, SC  Set and monitor speed limits. 

Monitor sprinkling of access track

During the entire 

operation 

3.5  Burning of waste will not be allowed and all combustible and non‐

combustible wastes will be handed over the approved waste contractor

UEPL, IMC, SC  Check compliance  During the entire 

operation 

3.6  Comply with minimum safe distances from environmental receptors 

recommended in the EIA study 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

3.7  Access tracks used during proposed seismic operation passing through 

communities will be avoided. If unavoidable a speed limit of less than 

30 km/hr will be observed on the section of the road passing through 

the community 

UEPL, SC, IMC  Ensure compliance  During the entire 

operation 

3.8  During operation emissions from all point sources and ambient air 

quality shall also be monitored to check compliance with SEQS in 

accordance to applicable laws and regulations  

UEPL, IMC, SC  Ensure compliance with SEQS  During the entire 

operation 

3.9  Appropriate measures will be taken to avoid ozone depletion  UEPL, IMC, SC  Monitor measures  During the entire 

operation 

Page 261: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-19 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

3.10  During preparation of access tracks, levelling or widening along the 

access road/s will be done in sections, immediately followed by 

sprinkling of water and also preferably compaction (where required) 

UEPL, IMC, SC  Ensure compliance  During the 

construction phase 

4  Noise Pollution 

4.1  It will be ensured that generators, vehicles and other potentially noisy 

equipment used during seismic activities are in good working 

condition 

UEPL, IMC, SC  Monitor noise levels  Prior to use of 

machinery and 

vehicles 

4.2  Seismic camps will be located 300 m away from nearest communities  UEPL, IMC, SC  Check distances from the 

community 

Prior to construction of 

the campsites 

4.3  The use of horns by project vehicles will be minimized. The use of 

pressure horns will not be allowed 

UEPL, IMC, SC  Train drivers, check vehicles and 

record non‐compliances 

During the entire 

operation 

4.4  Movement of all project vehicles and personnel will be restricted to 

within work areas only 

UEPL, IMC, SC  Advise all drivers and monitor 

non‐compliances 

During the entire 

operation 

4.5  Appropriate control actions shall be taken to mitigate adverse noise 

impacts in working areas, if levels found in excess of NEQS or SEQS at 

the neighboring communities 

UEPL, IMC, SC  Monitor noise levels at 

neighboring communities 

During the entire 

operation 

4.6  Conduct regular noise monitoring as per applicable rules and 

regulations 

UEPL, IMC, SC  Conduct regular noise monitoringDuring the entire 

operation 

5  Water Abstraction 

5.1  Water from dhands, canals or any other suface water body will not be 

used. Under special circumstances like long haul distances, improper 

access for water bowsers in remote areas etc. surface water resources 

may be exploited for limited water abstraction during seismic 

operation (for operational needs only) after getting approval from the 

concerned department 

UEPL, IMC, SC  Check sources of water 

abstraction and ensure 

compliance 

During the entire 

operation 

5.2  The quantity of water used during seismic, drilling (flush or uphole 

etc.) and camps construction operations will be kept to the minimum 

required by taking prudent water conservation measures on site 

UEPL, IMC, SC  Check consumption of water  During the entire 

operation 

Page 262: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-20 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

5.3  A complete record of water consumption during seismic and camps 

construction will be maintained 

UEPL, IMC, SC  Check records  During the entire 

operation 

5.4  Water required for seismic and construction of camps operation may 

be obtained from existing local wells or newly installed UEPL water 

wells in the area 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

5.5  If a new water well is to be installed, the well will be located 300 m 

from existing local wells and will be designed to abstract water 

preferably from deep aquifer not being used by local communities 

UEPL, IMC, SC  Monitor distance from the 

existing wells 

Before the start of the 

operation 

5.6  Water from a local well will only be used after ensuring that the 

available capacity at the tube well (safe yield minus local demand) is at 

least 50% greater than the project demand. Discharge from the tube 

well will be regularly monitored to monitor any changes in the yield of 

the wells. If a single well fails to meet this requirement, water will be 

obtained from multiple wells such that each well meets the above‐

mentioned requirement 

UEPL, IMC, SC  Check local demand and water 

abstraction 

During the entire 

operation 

5.7  For all water obtained from local wells, the owner will paid for the 

water abstracted at the appropriate rates 

UEPL, IMC, SC  Ensure compliance  During the entire 

operation 

5.8  Preferably, the potable water requirement will be met by installing 

water treatment system (such as reverse osmosis) 

SC, IMC, UEPL  IMC to guide on preservation of 

water 

During the entire 

operation 

6  Clearing of Vegetation & Loss of Habitat

6.1  The campsite areas will be kept to the minimum required  UEPL, IMC, SC  Check areas for the camps 

establishment 

Prior to camp setup 

6.2  Camps will be located in existing clearings and levelled land  UEPL, IMC, SC  Check compliance  Before camp setup 

6.3  Clearing of vegetation will be kept to a minimum and avoided as much 

as possible, especially dense patches of vegetation where wildlife 

presence is confirmed and areas near surface water bodies 

UEPL, IMC, SC  Monitor clearing activities  During entire 

operation 

Page 263: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-21 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

6.4  The cutting of trees or tall shrubs will be avoided as much as possible. 

Under unavoidable circumstances any clearing required will be done 

with prior approval of IMC and custodian of the area. Each tree cutting 

for clearing of site will be replaced/compensated by plantation of trees 

at site (10 trees for each tree cut). The tree species shall be indigenous 

to the region 

UEPL, IMC, SC  Supervise land clearing activities  During land clearing 

activities 

6.5  Use of local vegetation/wood as fuel by crew personnel will be stirctly 

prohibited 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

6.6  Dust emissions on access tracks will be reduced by keeping speed 

limits below 40 km/hr 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

6.7  Crew personnel while working along seismic lines will concentrate 

within a corridor of 3 m 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

6.8  Earthen pits for preparation and disposal of bentonite mud and drill 

cuttings will be located in an area where minimum vegetation clearing 

is involved 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

6.9  Campsites will avoid areas of dense vegetation as much as possible  UEPL, IMC, SC  Check site allocated for campsites Before the start of 

clearing acitivities 

6.10  Access tracks will be avoided from passing through patches of dense 

vegetation 

UEPL, IMC, SC  Check the alignment of access 

tracks 

Before land clearing 

and construction 

operation 

6.11  During seismic operation clearing of vegetation will be minimized by 

minimizing the width of the vibroseis tracks, minimizing the 

preparation of new access tracks and keeping the width of new access 

tracks to the minimum required 

UEPL, IMC, SC  Check compliance  During entire 

operation 

7  Disturbance to Wildlife 

7.1  Prior to commencement of seismic operation, awareness trainings will 

be provided to contractor’s management and field crew on matters 

related to the requirements of the EMP in this regard 

UEPL, IMC, SC  Provide environmental awareness 

training  

Before commencement 

of seismic operation 

Page 264: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-22 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

7.2  Hunting, fishing, harassment, feeding, trapping or killing of wildlife 

will be strictly prohibited 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

7.3  Vegetation clearing and land uptake during seismic operations will be 

minimized 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

7.4  Campsites for seismic operation will be located 300 m from surface 

water bodies 

UEPL, IMC, SC  Check compliance  Before the construction 

7.5  The time period of operation near wetland/dhands/surface water bodies 

and dense patches of vegetation will be minimized or avoided, if 

possible; especially during rutting or breeding period of the key 

wildlife species found in the project area by good planning and 

efficient working to reduce the time period of disturbance. Within the 

core habitat of wildlife the seismic operation should be completed 

within the shortest time possible 

UEPL, IMC, SC  Check compliance  During operation in 

the area 

7.6  Development of new access tracks during seismic activity will be 

minimized, where access tracks are prepared their width will be kept 

to 3 m 

UEPL, IMC, SC  Check compliance  During entire 

operation 

7.7  For preparation of access tracks, routes involving minimum clearing of 

vegetation will be selected, clearing of dense patches of vegetation will 

be avoided 

UEPL, IMC, SC  Monitor clearing operation  During land clearing 

7.8  Seismic deep holes and upholes will avoid disturbing live bird nests 

and small mammal and reptile holes 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

7.9  Food wastes will not be disposed or left in the open  UEPL, IMC, SC  Check compliance  During the entire 

operation 

7.10  Night traveling will be strictly prohibited and will only be allowed in 

case of emergency 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

7.11  A distance of 50 m will be maintained from surface water bodies 

during data acquisition and line clearing 

UEPL, IMC, SC  Check distances and ensure 

compliance 

During the entire 

operation 

Page 265: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-23 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

7.12  Compressors and vehicles will be maintained in good condition and 

provided with muffles to reduce noise 

UEPL, IMC, SC  Check maintenance logs and 

ensure the provision of muffles 

During the entire 

operation 

7.13  Blasting, construction or drilling activities will not be performed in 

Indus River 

UEPL, IMC, SC  Ensure compliance  During the entire 

operation 

7.14  Impacts of the individual projects on wildlife will be monitored by 

independent monitoring teams 

UEPL, IMC  Check compliance  During the entire 

operation 

8  Disturbance to Communities 

8.1  Project contractors and field staff shall be taken through a Community 

and External Affairs Induction program before execution of seismic 

activities 

UEPL, IMC, SC  Ensure arrangement of induction 

program 

Before commencement 

of seismic activities 

8.2  All community grievances will be recorded and maintained in a 

Community Complaints Register. In addition to this close liaison will 

be maintained between the community and the site representatives of 

UEPL throughout the course of activities 

UEPL, IMC, SC  Check the provision of complaint 

register and its access for 

communities 

During the entire 

operation 

8.3  Compensation amounts for land leased for various project components 

will be disbursed in equitable and transparent manner on fast pace 

UEPL, SC, IMC  Check compensation records  During the entire 

operation 

8.4  Compensation amounts will be paid to land owners before land is 

acquired, if not possible, then amounts should be paid as soon as 

possible 

UEPL, SC, IMC  Check compensation records  During the entire 

operation 

8.5  Loss of standing crops, traditional land rights and community 

ownership will be given due consideration while determining 

compensation amounts 

UEPL, SC, IMC  Check compliance  During the entire 

operation 

8.6  Compensation amounts will be settled based on prevailing market 

rates and will be settled after an agreement is reached between the 

local residents, operator and local administrator 

UEPL, SC  Check compliance  During the entire 

operation 

8.7  All mitigation related to management of wastes, noise and dust 

emissions suggested in the EIA will be adhered with 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

Page 266: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-24 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

8.8  UEPL contractors will employ local residents during the project 

activities subject to company’s competency criteria. Residents living 

closest to the project location will be given priority in the employment 

process  

UEPL, IMC, SC  Check compliance  During the entire 

operation 

8.9  Skilled and unskilled labour from local communities will be recruited 

equitably from amongst the various tribes, avenues for conflict 

resolution will be open and the employment procedures will be 

transparent 

SC, UEPL  Check compliance  During the entire 

operation 

8.10  Water sources currently being used for irrigation by the resident 

communities will be exploited only after complying with relevant 

requirements of the EIA 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

8.11  Local sources of water will be used only after complying with relevant 

requirements of the EIA 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

8.12  Flow of water in canals or water crossings will not be impeded  UEPL, IMC, SC  Check compliance  During the entire 

operation 

8.13  Any damage to canals, watercourses, local roads or other infrastructure 

will be repaired or compensated as per mutually agreed terms 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

8.14  Strict compliance will be observed to UEPL’s HSE guidelines  UEPL, IMC, SC  Check compliance  During the entire 

operation 

8.15  Drivers will be trained in responsible and safe driving practices, safe 

speed limits for vehicles will be followed 

UEPL, IMC, SC  Provide training and monitor 

compliance 

During the entire 

operation 

8.16  In order to keep nearby local communities informed of the progress of 

the operation, communication channels will be maintained between 

local community and UEPL 

UEPL, SC  Check compliance  During the entire 

operation 

8.17  Project staff will respect cultural norms  UEPL, IMC, SC  Train project staff on social norms 

and sensitivities 

During the entire 

operation 

8.18  Appropriate offsets will be provided from sites of religious, cultural or 

archaeological significance 

UEPL, IMC, SC  Check compliance  During the entire 

operation 

Page 267: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-25 HPK

No  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring Method Timing 

9  Site Restoration       

9.1  Demobilization of all equipment and machinery  UEPL, SC, IMC Check compliance  During site restoration 

9.2  Disposal of any waste material remaining at the time of completion of 

the operation 

UEPL, SC, IMC Ensure compliance  During site restoration 

9.3  Backfilling of all soak pits and septic tanks UEPL, SC, IMC Check compliance  During site restoration 

9.4  Dismantling and removal of fence or barriers surrounding the seismic 

base camp area/fly camp/support camp 

UEPL, SC, IMC Check compliance  During site restoration 

9.5  General restoration of the site area including landscaping and 

restoration of drainage where required 

UEPL, SC, IMC Ensure compliance  During site restoration 

9.6  Restoration of seismic lines will include removal of all cables, 

geophones, station units, flags, stakes and wastes from the lines and 

back filling of all mud pits. For reference purposes a photographic 

record of selected sections of seismic lines will be taken before and 

after the operation 

UEPL, SC, IMC Ensure compliance  During site restoration 

  Notes: SC: Seismic Contractor; IMC: Independent Monitoring Consultant; UEPL: United Energy Pakistan Limited’s Management or Representative 

Page 268: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-26 HPK

Table A‐2: Mitigation Management Matrix for Drilling and Associated Construction Activities 

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

1  Changes in Landscape & Soil Erosion      

1.1  Access tracks in the undulating areas will follow natural 

contours to minimize disturbance to natural topography and 

soils. Cutting along the sides of the slopes will be minimized 

UEPL, IMC, CC  Monitor clearing operation  During land clearing 

activities 

1.2  Clearing of vegetation will be kept to a minimum, especially 

dense patches of vegetation, areas where the presence of wildlife 

is confirmed and near the surface water bodies 

UEPL, IMC, CC  Monitor land clearing activities  Prior and during the land 

clearing operation 

1.3  The cutting of trees or tall shrubs will be avoided as much as 

possible 

UEPL, IMC, CC  Supervise land clearing 

activities 

During land clearing for 

access track, well site and 

campsite 

1.4  Total land uptake by the well site, camps and access road to the 

well site will be kept to the minimum required 

UEPL, IMC, CC  Monitor land clearing activities 

and randomly check compliance 

with actual design 

During construction 

1.5  The access track to the well site will be selected to utilize existing 

tracks as much as possible 

UEPL, IMC, CC  Monitor land clearing activities  Prior to the construction 

activitiy 

1.6  The well site, rig camp and construction camp will preferably be 

located in existing clearing and levelled land 

UEPL, IMC  Check location of facilities  At the time of site selection 

for well site, rig camp and 

construction camp 

1.7  The access track will be properly compacted at the time of 

construction and thereafter properly maintained by watering 

and compaction throughout the entire construction and drilling 

operation 

UEPL, IMC, CC  Check compaction and 

maintenance 

During the entire operation 

1.8  During construction movement of construction equipment will 

be restricted to work areas only to avoid unnecessary 

disturbance to soils in the project area 

UEPL, IMC, CC  Monitor movement of vehicles 

and off‐road travel 

During construction of project 

facilities 

1.9  Vehicles speed will be regulated and monitored to avoid 

excessive dust emissions 

UEPL, IMC, CC, 

DC 

Set and monitor speed limits  During the entire operation 

Page 269: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-27 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

1.10  Off‐road travel should be avoided and observance of this should 

be monitored during the operation 

UEPL, IMC, CC, 

DC 

Approve access track and 

monitor off‐road travel 

During the entire project 

1.11  Periodic trainings should be provided to drivers on mitigation 

measures related to off‐road travel and speed limits 

UEPL, IMC, CC, 

DC 

Check training log and provide 

trainings 

During the entire project 

1.12  Photographs will be taken before any activity to record the 

conditions of campsite, roads and well site at paticular locations 

that are likely to undergo soil erosion. Similar photographs will 

be taken at time intervals throughout the operation to monitor 

any changes and soil conditions 

UEPL, IMC  Supervise and ensure 

compliance 

During the entire project 

2  Soil and Water Contamination       

2.1  Sewage Treatment Plant (STP) shall be preferred for handling of 

black/grey water under BATNEEC/BAT, but in case of 

unavailability of STP, septic tank and soak pits shall be provided

UEPL, IMC, CC  Check provision of STP  During the design and 

construction of campsite 

2.2  Wastewater from laundry, kitchen washings and showers will be 

disposed of into separate soak pits 

UEPL, IMC, CC  Check provision of soak pits at 

campsites 

During the construction of 

campsite 

2.3  Soak pits will be built in absorbent soil and located 300 m away 

from a surface water source or a water well 

UEPL, IMC, CC  Check soil condition and 

distance between the soak pits 

and the nearest water body 

During the construction of 

campsite 

2.4  Soak pits will be constructed such that surface runoff cann’t 

enter the pits 

UEPL, IMC, CC  Check design of the soak pit and 

monitor construction 

During the construction of 

campsite 

2.5  All soak pits will be designed to accommodate wastewater 

generated during the total duration of the operation 

UEPL, IMC, CC  Check design of soak pit  Before construction 

2.6  In case the soak pits get filled during the operation, grey water 

will be discharged in the nearest municipal drains after getting 

formal approval from local authorities. Sprinkling of grey water 

will be not be allowed 

UEPL, IMC, CC, 

DC 

Check provision of soak pits and 

monitor the transfer activity 

During the entire operation 

2.7  No solid waste will be disposed of in the field. Within the camp 

areas all solid wastes will be disposed of in waste bins provided 

UEPL, IMC, CC, 

DC 

Check provision of waste bins  During the entire operation 

Page 270: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-28 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.8  All combustible, non‐combustible and hazardous waste 

including plastic or glass bottles and cans will be temporarily 

stored on site and sold/handed over to a waste/recycling 

contractor who will utilize these wastes for recycling purposes 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

2.9  Construction of burn pit and burning of waste will not be 

allowed 

UEPL, IMC, CC  Check compliance  During the entire operation 

2.10  At the time of restoration septic tanks will be dismantled in place 

and backfilled with at least 1 m of soil cover above the buried 

dismantled septic tank 

UEPL, IMC, CC  Supervise restoration and 

randomly check thickness of soil 

cover 

During the restoration phase 

2.11  At the time of restoration soak pits will be backfilled with at least 

1 m of soil cover keeping in view landscape of surrounding 

natural surface 

UEPL, IMC, CC  Supervise restoration and 

randomly check thickness of soil 

cover 

During the restoration phase 

2.12  It will be ensured that after restoration activities the campsites 

are clean and that no refuse has been left behind 

UEPL, IMC, CC  Visually check the restored site 

and identify non‐complinace, if 

any 

After restoration 

2.13  All concrete structures at the campsites will be removed and 

buried in garbage or soak pits and the pits backfilled with at 

least 1 m of soil cover 

UEPL, IMC, CC  Supervise removal and burial of 

concereted strutures and 

randomly check thickness of soil 

cover 

During restoration 

2.14  Vehicles will only be washed in designated areas within 

campsites 

UEPL, IMC, CC, 

DC 

Ensure provision of washing 

areas and monitor any non‐

compliances 

During the entire operation 

2.15  Vehicles will be daily checked for fuel or oil leaks. Vehicles with 

leaks will not be operated until repaired 

UEPL, IMC, CC, 

DC 

Check maintenance logs and 

ensure daily inspection of 

vehicles for leaks 

During the entire operation 

2.16  All fuel tanks will be properly marked to highlight their contents UEPL, IMC, CC, 

DC 

Ensure that proper signs are 

placed with the tanks 

During the entire operation 

Page 271: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-29 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.17  Fuel and oil storage areas will have secondary containment in 

the form of concrete or brick masonry bunds. The volume of the 

containment area should be equal to 125% of the total volume of 

fuel stored 

UEPL, IMC, CC  Check containment volume of 

the fuel or oil bunded area 

At the time of construction 

2.18  Fuels tanks will be daily checked for leaks and all such leaks will 

be plugged immediately 

UEPL, IMC, CC, 

DC 

Inspect fuel tanks for leaks  During the entire operation 

2.19  The soil contaminated from minor and moderate spills will be 

removed and disposed of properly 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

2.20  The soil contaminated from major spills may require specialized 

treatment such as incineration or bioremediation 

UEPL, IMC, CC, 

DC 

Monitor and supervise special 

treatment, if any 

During the entire operation 

2.21  A spill prevention and contingency plan will be prepared to deal 

with moderate and major spills 

UEPL, IMC, CC, 

DC 

Study and examine the plan and 

identify any flaws, if any before 

its approval 

Before the commencement of 

project 

2.22  Shovels, plastic bags and absorbent material should be present 

near fuel and oil storage or handling areas to attend spills and 

leaks 

UEPL, IMC, CC, 

DC 

Check provision of material & 

equipment 

During entire operation 

2.23  Used oil and vehicle related waste will be transported to local 

contractors for recycling 

UEPL, IMC, CC, 

DC 

Approve waste contractor and 

randomly check proper 

recycling 

During the entire operation 

2.24  Medical wastes will be temporarily stored onsite separately and 

incinerated at nearest facility 

UEPL, IMC, CC, 

DC 

Check compliance  During entire operation 

2.25  A water based mud system will be used for drilling  UEPL, IMC, DC  Check compliance  During entire operation 

2.26  Waste pits at the well site will be lined with an HDPE liner  UEPL, IMC  Check provision of HDPE liner  Before comissioning of waste 

pits 

2.27  The drill cuttings and drilling mud will be disposed into pits 

lined with impermeable geo‐membrane. The pits will be larger 

than the required capacity to accommodate overflows. At the 

UEPL, IMC, CC, 

DC 

Check design of waste pit and 

ensure provision of geo‐

membrane. Monitor restoration 

Before comissioning, during 

operation and after 

restoration of waste pits 

Page 272: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-30 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

time of restoration the pits will be backfilled with the cuttings 

encapsulated within the liner and with a top soil cover 

with provision of proper soil 

cover 

2.28  Produced formation fluids will be flared along with the gas or 

collected inside the lined waste pit at the well site. In case the 

fluids discharge into the flare pit the soil at the sides of the flare 

pit will be excavated and disposed of into the lined waste pit at 

the well site 

UEPL, IMC, DC, 

CC 

Check compliance  Prior to and during disposal 

of waste fluids 

2.29  Produced formation fluids will be re‐injected into deep 

subsurface formations (wherever possible) 

UEPL, DC, IMC  Check compliance  Prior to and during disposal 

of waste fluids 

2.30  Sprinkling of untreated excess wastewater used for drilling 

purposes will not be allowed. Sprinkling of treated wastewater 

will only be done if meeting NEQS/SEQS 

UEPL, IMC  Check compliance  During the entire operation 

3  Use of Water       

3.1  The surface water resources will no be used during construction 

and drilling activities 

UEPL, IMC, CC, 

DC 

Check sources of water 

abstraction and ensure 

compliance 

During the entire operation 

3.2  The quantity of water used during construction and drilling will 

be kept to the minimum required by taking prudent water 

conservation measures on site 

UEPL, IMC, CC, 

DC 

Check consumption of water  During the entire operation 

3.3  A complete record of water consumption during construction 

and drilling will be maintained 

UEPL, IMC, CC, 

DC 

Check Compliance  During the entire operation 

3.4  Water required for drilling and construction of camps operation 

may be obtained from local wells (close to surface water bodies) 

or new water wells installed by UEPL in the project area 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

3.5  Water from a local well will only be used after ensuring that the 

available capacity at the tube well (safe yield minus local 

demand) is at least 50% greater than the project demand. 

Discharge from the tube well will be regularly monitored to 

UEPL, IMC, CC, 

DC 

Check local demand and water 

abstraction 

During the entire operation 

Page 273: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-31 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

monitor any changes in the yield of the wells. If a single well 

fails to meet this requirement, water will be obtained from 

multiple wells such that each well meets the above‐mentioned 

requirement 

3.6  For all water obtained from local wells, the owner will be paid 

for the water abstracted at the appropriate rates 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

3.7  If a new water well is to be installed, the well will be located 300 

m from existing local wells and will be designed to abstract 

water preferably from deep aquifer not being used by local 

communities 

UEPL, IMC, CC, 

DC 

Monitor distance from the 

existing wells 

Before start of the operation 

3.8  Preferably, the potable water requirement will be met by 

installing water treatment system (such as reverse osmosis) 

UEPL, CC, DC, 

IMC 

IMC to guide on preservation of 

water 

During the entire operation 

4  Deterioration of Ambient Air Quality      

4.1  Generators, vehicles and equipment used during construction 

and drilling operations will be maintained in a good working 

condition to ensure that emissions are kept to a minimum level 

UEPL, IMC, CC, 

DC 

Check maintenance logs   During the entire operation 

4.2  Well site and campsites will be located at least 300 m away from 

nearest community 

UEPL, IMC, CC  Check distances of well site and 

campsite from communities 

Prior to construction of well 

site and campsites 

4.3  During drilling and construction dust emissions due to road 

travel will be minimized by regulating and monitoring vehicles 

speed and watering of the access track wherever required 

UEPL, IMC, CC  Set and monitor speed limits. 

Monitor sprinkling of access 

track 

During the entire operation 

4.4  The access track selected to access the well location will maintain 

a reasonable safe distance from communities 

UEPL, IMC, CC  Check alignment of the access 

track 

Prior to improvement and 

construction of the access 

track 

4.5  Dust emissions during construction activities will be minimized 

by good management practices such as locating stock piles out of 

the wind direction, keeping the height of the stock piles to a 

minimum, keeping earthwork areas damp etc. 

UEPL, IMC, CC  Monitor dust emissions during 

earthworks. Train CC on good 

management practices 

During the construction 

operation 

Page 274: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-32 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

4.6  Flare pit will be kept downwind of the well site and at least 300 

m from the nearest community. The duration of flaring during 

well testing will be kept to the minimum required 

UEPL, IMC, CC, 

DC 

Check location and distance of 

the flare pit from nearest 

community and monitor flaring 

Prior to construction of the 

flare pit and during flaring 

4.7  No burning of waste will be allowed on site  UEPL, IMC, CC  Ensure compliance  During the entire operation 

4.8  Appropriate measures will be taken to avoid ozone depletion & 

global warming e.g. prohibit use of CFC gases etc. 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

4.9  During operation emissions from all point sources shall be 

monitored to check compliance with SEQS 

UEPL, IMC, CC, 

DC 

Ensure compliance  During the entire operation 

5  Noise Pollution       

5.1  It will be ensured that generators, vehicles and other potentially 

noisy equipment used during construction and drilling are in 

good working condition 

UEPL, IMC, CC, 

DC 

Monitor noise levels  Prior to and during use of 

machinery and vehicles 

5.2  Well site, construction camps and rig camp will be located 300 m 

away from nearest community 

UEPL, IMC, CC  Check distances from the 

community 

Prior to construction of the 

well site, rig camp and 

campsites 

5.3  The use of horns by project vehicles will be minimized. The use 

of pressure horns will not be allowed 

UEPL, IMC, CC, 

DC 

Train drivers, check vehicles and 

record non‐compliances 

During the entire operation 

5.4  Movement of all project vehicles and personnel will be restricted 

to within work areas only 

UEPL, IMC, CC, 

DC 

Advise all drivers and 

investigate non‐compliances 

from staff 

During the entire operation 

5.5  Regular noise monitoring will be carried out from all noise 

generating sources to ensure SEQS compliance 

UEPL, IMC, CC, 

DC 

Check monitoring records  During the entire operation 

5.6  Blasting will be prohibited during proposed construction 

activities of well sites in the project area to provide relief to the 

sensitive environmental receptors. If deemed necessary it shall 

be covered by change management plan provided in EMP of this 

EIA 

UEPL, IMC, CC  Ensure compliance  During construction activity 

6  Blocking of Natural Drainage   

Page 275: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-33 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

6.1  Area around the wells and campsites shall be landscaped to 

avoid blocking natural drainage 

UEPL, IMC, CC  Check compliance  During construction activities 

6.2  Causeways and pipe culverts will be provided at all 

watercourses (seasonal or permanent) crossings to avoid 

blocking of natural drainage 

UEPL, IMC, CC  Ensure not to block the natural 

drainage 

During construction activities 

6.3  Uncontrolled & unnecessary clearing, dozing, excavations or 

quarrying, storage of construction material etc. will be avoided 

UEPL, CC, IMC  Ensure compliance  During construction activities 

7  Clearing of Vegetation & Loss of Habitat      

7.1  The well site and rig camp areas will be kept to the minimum 

required 

UEPL, IMC, CC  Check design and ensure 

compliance 

Before and during the 

construction activity 

7.2  The well site location will avoid areas of dense vegetation as 

much as possible 

UEPL, IMC, CC  Check location of well site  Before selection of drilling 

location 

7.3  The construction camp and rig camp will be located in existing 

clearings and will avoid areas of dense vegetation 

UEPL, IMC, CC  Check compliance  Before selection of drilling 

location 

7.4  Clearing of vegetation will be kept to a minimum; especially 

dense patches of vegetation, areas where the presence of wildlife 

is confirmed and near surface water bodies 

UEPL, IMC, CC  Monitor clearing operation  During land clearing 

activities 

7.5  The access road to each well site will be aligned to minimize 

dense patches of vegetation and will use existing tracks as much 

as possible 

UEPL, IMC, CC  Check alignment of access road 

and use of existing facilities 

Before construction operation 

7.6  The cutting of trees or tall shrubs will be avoided as much as 

possible. Under unavoidable circumstances any clearing 

required will be done with prior approval of IMC and custodian 

of the area. Each tree cutting for clearing of site will be 

replaced/compensated by plantation of trees at site (10 trees for 

each tree cut). The tree species shall be indigenous to the region 

UEPL, IMC, CC  Supervise land clearing 

activities 

During land clearing 

activities 

7.7  Use of local vegetation as fuel by crew personnel will be 

prohibited 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

Page 276: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-34 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

7.8  Dust emissions on access tracks will be reduced by keeping 

speed limits below 40 km/hr 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

7.9  Access tracks will be avoided from passing through patches of 

dense vegetation 

UEPL, IMC, CC  Check the alignment of access 

tracks 

Before land clearing and 

construction operation 

7.10  Quarry sites if required will be carefully selected such that they 

are located in levelled areas with existing clearing and the quarry 

sites are restored after use 

UEPL, IMC, CC  Check quarry sites and their 

restoration 

During construction activities 

8  Disturbance to Wildlife       

8.1  Prior to commencement of drilling operation, awareness 

trainings will be provided to contractor’s management and field 

crew on matters related to the requirements of the EMP in this 

regard 

UEPL, IMC, CC, 

DC 

Provide environmental 

awareness training  

Before commencement of 

construction and drilling 

operation 

8.2  Hunting, fishing, trapping, feeding ,harassment or killing of 

wildlife will be strictly prohibited 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

8.3  Vegetation clearing and land uptake will be minimized  UEPL, IMC, CC  Check compliance  During the entire operation 

8.4  Locate well site & campsite 300 m away from any surface water 

bodies 

UEPL, IMC, CC  Randomly check distances and 

identify any non‐compliances 

Before the construction 

activity 

8.5  The drilling of wells within the areas where good population of 

wildlife is confirmed shall be avoided as much as possible 

UEPL, IMC  Check compliance  Before selection of drilling 

location 

8.6  For preparation of access tracks, routes involving minimum 

clearing of vegetation will be selected, clearing of dense patches 

of vegetation will be avoided 

UEPL, IMC, CC  Check alignment of access 

tracks/routes and monitor 

clearing operation 

During land clearing activity 

8.7  Food wastes will not be left in the open  UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

8.8  Night traveling will be strictly prohibited and will only be 

allowed in case of emergency 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

8.9  Equipment and vehicles will be maintained in good working 

condition and provided with muffles to reduce noise 

UEPL, IMC, CC, 

DC 

Check maintenance logs and 

ensure the provision of muffles 

During the entire operation 

Page 277: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-35 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

8.10  The time period of operation near wetland/dhands/surface water 

bodies and dense patches of vegetation will be minimized or 

avoided, if possible; especially during rutting or breeding period 

of the key wildlife species found in the project area by good 

planning and efficient working to reduce the time period of 

disturbance 

UEPL, IMC, CC, 

DC 

Check time period of operation  During the entire operation 

8.11  Blasting will be prohibited during construction activities to 

provide relief to the sensitive environmental receptors of the 

area. If deemed necessary it shall be covered by change 

management plan provided in EMP of this EIA 

UEPL, IMC, CC  Ensure compliance  During construction activity 

8.12  The duration and intensity of flaring will be kept to the 

minimum required 

UEPL, IMC, DC  Monitor flaring activity  During flaring activity 

8.13  Construction and drilling activities will not be performed in 

Indus River 

UEPL, IMC  Ensure compliance  During the entire course of 

project 

9  Disturbance to Communities 

9.1  Contractors staff shall be taken through a Community and 

External Affairs Induction program before commencement of 

each component of the project activities 

UEPL, IMC, CC, 

DC 

Ensure compliance  Before commencement of 

each component of project 

9.2  All community grievances will be recorded and maintained in a 

Community Complaints Register. In addition to this close liaison 

will be maintained between the community and the site 

representatives of UEPL throughout the construction and 

drilling activities 

UEPL, IMC, DC, 

CC 

Check the provision of 

complaint register and 

maintaining a close liaison of 

site representatives with locals   

During the entire operation 

9.3  Compensation amounts for land leased for various project 

components will be disbursed in equitable and transparent 

manner on fast pace 

UEPL, IMC, CC  Check compensation records  Before the commencement of 

project activities 

Page 278: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-36 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

9.4  Compensation amounts will be paid to land owners before land 

is acquired, if not possible, then amounts should be paid as soon 

as possible 

UEPL, IMC, CC  Monitor time taken for the 

payment of compensations and 

identify any sluggishness, if any

Before the commencement of 

project activities 

9.5  Loss of standing crops, traditional land rights and community 

ownership will be given due consideration while determining 

compensation amounts 

UEPL, IMC, CC  Monitor adherence with the 

requirement during the 

assessment of land value to 

provide compensations 

Before the commencement of 

project activities 

9.6  Compensation amounts will be settled based on prevailing 

market rates and will be settled at mutually agreed terms and 

conditions 

UEPL, IMC, CC  Monitor adherence with the 

requirement during the 

assessment of land value to 

provide compensations 

Before the commencement of 

project activities 

9.7  All mitigation related to management of wastes, noise and dust 

emissions suggested in the EIA will be adhered with 

UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

9.8  UEPL contractors will employ local residents during project 

activities subject to company’s competency criteria 

UEPL, IMC, CC, 

DC 

Monitor adherence with the 

requirement 

During the entire operation 

9.9  Skilled and unskilled labour from local communities will be 

recruited equitably from amongst the various tribes, avenues for 

conflict resolution will be open, and the employment procedures 

will be transparent 

UEPL, IMC, CC, 

DC 

Monitor adherence with the 

requirement 

During the entire operation 

9.10  Local residents living closest to the project location will be given 

priority in the employment process 

DC, UEPL, IMC, 

CC 

Monitor adherence with the 

requirement 

During the entire operation 

9.11  Water sources currently being used for domestic/irrigation by 

the resident communities will be exploited only after complying 

with relevant requirements of the EIA 

UEPL, IMC, CC, 

DC 

Monitor adherence with the 

requirement 

During the entire operation 

9.12  Local sources of drinking water will be used only after 

complying with relevant requirements of the EIA 

UEPL, IMC, CC, 

DC 

Monitor adherence with the 

requirement 

During the entire operation 

9.13  Flow of water in canals or water crossings will not be impeded  UEPL, IMC, CC, 

DC 

Check compliance  During the entire operation 

Page 279: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-37 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

9.14  Any damage to canals, water courses, roads or other 

infrastructure during project activities will be repaired or 

compensated as per mutual understandings 

UEPL, IMC, CC, 

DC 

Check for damages along canals, 

water courses, roads or other 

infrastructure and ensure its 

repair is conducted 

During the entire operation 

9.15  Strict compliance will be observed to UEPL’s HSE guidelines  UEPL, IMC, CC, 

DC 

Monitor adherence with the 

requirement 

During the entire operation  

9.16  Drivers will be trained in responsible and safe driving practices. 

Safe speed limits for vehicles will be followed 

UEPL, IMC, CC, 

DC 

Provide training and monitor 

compliance 

During the entire operation  

9.17  In order to keep nearby local communities informed of the 

progress of the operation, communication channels will be 

maintained between local community and UEPL 

UEPL, IMC, CC, 

DC 

Monitor adherence with the 

requirement by holding 

frequent meetings to update 

locals regarding project 

activities 

During the entire operation 

9.18  A complaints register regarding environment will be maintained 

on site for registering of local complaints 

UEPL, IMC, CC, 

DC 

Check the provision of 

complaint register and its access 

for general public 

During the entire operation 

9.19  Project staff will respect cultural norms  UEPL, IMC, CC, 

DC 

Monitor adherence with the 

requirement 

During the entire operation  

9.20  Appropriate offsets will be provided from sites of religious, 

cultural or archaeological significance 

UEPL, IMC, CC  Monitor adherence with the 

requirement 

Before construction activity 

10  Site Restoration       

  Complete Restoration – Dry Well       

10.1  All equipment and machinery at the well site will be 

demobilized 

DC, IMC, UEPL  Check compliance  During site restoration 

10.2  All wastes at the well site will be disposed of according to the 

requirements of the EIA 

DC, IMC, UEPL  Check compliance  During site restoration 

Page 280: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-38 HPK

No.  Impacts & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

10.3  Liner from the water and waste pits at the well site may be taken 

out and re‐used or disposed of in the existing pits with proper 

restoration 

CC, IMC, UEPL  Check compliance  During site restoration 

10.4  All concrete structures at the well site will be broken and either 

transported out of the project area by the demolition or site 

restoration contractors for sale or reuse or disposed of into the 

pits 

CC, IMC, UEPL  Check compliance  During site restoration 

10.5  All pits at the well site will be backfilled  CC, IMC, UEPL  Check compliance  During site restoration 

10.6  The areas covered by the portion of the access track that will be 

of no use for other wells will be restored, in that all gravel 

topping will be removed. This scenario will be applicable only if 

the locals require the potions of the track to be restored or 

otherwise it will be left intact on the consent of the locals 

CC, IMC, UEPL  Check compliance  During site restoration 

  Partial Restoration – Producing Well    

10.7  The well site and access roads will be retained to support well 

access work for further testing or during the production phase 

UEPL  Check compliance  During site restoration 

10.8  The outer chainlink fence will be retained as a safety measure to 

keep wildlife away from the pit areas 

UEPL, IMC  Check chain link fence is 

retained 

During site restoration 

10.9  The wellhead will be enclosed by a locked steel cage. This will 

serve as both a safety and security measure as the site will be 

down‐manned pending further production operations work 

UEPL, IMC  Inspect wellhead is enclosed by 

locked steel cage 

During site restoration 

10.10  The constructed pit areas will be retained but all liquid and solid 

waste material will be removed from the site and disposed of in 

line with the requirements of this EIA 

IMC, UEPL  Ensure that all liquid and solid 

waste is removed 

During site restoration 

Note: IMC: Independent Monitoring Consultant; DC: Drilling Contractor; CC: Construction Contractor; UEPL: United Energy Pakistan Limited’s Management or Representative 

 

 

 

Page 281: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-39 HPK

Table A‐3: Mitigation Management Matrix for Laying of Flow Line/Tie‐ins/Wellhead Works 

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

1  Changes in Landscape and Soil Erosion

1.1  Land area requirements for construction camp and RoW 

of flow line will be kept to the minimum required 

PC, UEPL  Check compliance  After marking of the campsite 

layout, RoW of flow line on 

ground by the PC and prior to 

clearing of land at these areas 

1.2  Good engineering practices will be adopted during 

construction activities to ensure that unnecessary clearing 

of vegetation and disturbance to soils outside work areas 

are avoided 

PC, UEPL  Monitor land clearing activities  During construction activity 

1.4  Topsoil of the RoW will be separately stored. This topsoil 

will be backfilled after proper compaction ensuring 

minimum loss of topsoil 

PC, UEPL  Check complaince  During construction activity 

1.5  Clearing of vegetation (especially dense vegetation) will 

be minimized by careful selection of construction camp 

and flow line alignment 

PC, UEPL  Monitor land clearing activities  During construction activity 

1.6  Cutting of trees or even tall shrubs will be avoided  PC, UEPL  Monitor land clearing activities  During construction activity 

1.7  Use of existing tracks with the required improvement 

works will be maximized. Unless driven by community 

demand construction of new tracks will be kept to the 

minimum 

PC, UEPL  Check complaince  During construction activity 

1.8  Off‐road travel will be avoided  PC, UEPL  Monitor off‐road travel  During construction activity 

1.9  Vehicles speed will be regulated and monitored to avoid 

excessive dust emissions 

PC, UEPL  Monitor vehicles speed  During construction activity 

1.10  Periodic trainings will be provided to drivers on 

mitigation measures related to off‐road travel and speed 

limits 

PC, UEPL  Check compliance  During construction activity 

Page 282: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-40 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2  Soil and Water Contamination 

2.1  Approval to start of construction of flow line should only 

be provided by UEPL representative after ensuring that 

all waste management facilities (waste segregation units, 

soak pits, septic tanks etc.), equipment (waste bins, drip 

pans, tarpaulins etc.) and procedures (approvals for 

waste contractors etc.), prescribed in the EIA are in a state 

acceptable to the UEPL representative 

PC, UEPL  Approval for waste contractors, 

check provision of waste 

management facilities at 

construction camp 

Before construction activity 

2.2  Sewage will be disposed of into septic system comprising 

of septic tanks and soak pits. The septic tanks should be 

built of concrete and brick masonry to avoid leaching of 

wastewater from the tanks 

PC, UEPL  Check provision of septic tank 

and soak pit 

During construction activity 

2.3  Wastewater from laundry, kitchen washings and showers 

will be disposed of into separate soak pits 

PC, UEPL  Check provision of soak pits  During construction activity 

2.4  Soak pits will be built in absorbent soil and located 300 m 

away from a perennial surface water source or water well

PC, UEPL  Check soil condition and 

distance between the soak pits 

and the nearest water body 

During construction activity 

2.5  Soak pits should be covered and constructed such that 

surface runoff cannot enter the pits. Soak pits will be 

designed to accommodate wastewater generated during 

the total duration of the operation 

PC, UEPL  Check design of the soak pit and 

monitor construction. Monitor 

provision of covers and berms 

During construction activity 

2.6  In case the soak pits get filled during the operation, grey 

water will be discharged in the nearest municipal drains 

after getting formal approval from local authorities. 

Sprinkling of grey water will be not be allowed 

PC, UEPL  Monitor wastewater levels in the 

soak pits 

During construction activity 

2.7  Sprinkling of sewage will not be allowed  PC, UEPL  Check compliance during 

routine visits 

During construction activity 

Page 283: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-41 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.8  No solid waste will be disposed of in the field. Within the 

construction camp all solid wastes will be disposed of in 

waste bins provided in the camp area 

PC, UEPL  Monitor provision of sufficient 

waste bins  

During construction activity 

2.9  All combustible material, non‐combustible and 

hazardous wastes including plastic or glass bottles and 

cans will be temporarily stored on site and sold/handed 

over to a waste/recycling contractor who will utilize these 

wastes for recycling purposes 

PC, UEPL  UEPL to approve waste 

contractors. Monitor waste 

segregation and safe 

transportation to the recycling 

contractorʹs facility 

During construction activity 

2.10  Burning of waste will not be allowed  PC, UEPL  Monitor compliance  During construction activity 

2.11  At the time of restoration septic tanks will be dismantled 

in place and backfilled with at least 1 m of soil cover 

PC, UEPL  Monitor restoration activity  At the time of restoration 

2.12  At the time of restoration soak pits will be backfilled with 

at least 1 m of soil cover 

PC, UEPL  Monitor restoration activity  At the time of restoration 

2.13  Clinical wastes will be temporarily stored onsite 

separately and incinerated at nearest hospital or a similar 

facility 

PC, UEPL  UEPL to approve disposal 

arrangement. Monitor waste 

segregation and safe storage 

onsite 

During construction activity 

2.14  Soil contaminated by minor spills/leakages (defined as 

leaks from vehicles, machinery, equipment or storage 

containers such that the area and depth of soil 

contaminated is less than 1 sq ft and 3 inches 

respectively) should be scraped and disposed of 

according to best industrial guidelines 

PC, UEPL  Monitor any oil leaks and 

appropriate disposal  

During construction activity 

Page 284: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-42 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.15  Moderate spills defined as spills of volume less than or 

equal to 200 liters should be contained and controlled 

using shovels, sands and native soil. These equipment 

and materials should be made available at construction 

campsite. The contaminated soil should be excavated and 

stored in a bunded area lined with an impermeable base. 

Depending on the volume, the contaminated soil should 

be disposed of in accordance to best industrial guidelines

PC, UEPL  Ensure provision of equipment 

and material to control and 

handle such spills on site. 

Monitor disposal as per the 

requirements of the EIA 

During construction activity 

2.16  Major spills (defined in the EIA as spills of volume much 

greater than 200 liters) will require initiation of UEPLʹs 

Emergency Response Procedures. These spills should be 

handled and controlled according to the measures listed 

in UEPL’s Oil Spill Contingency Plan and will require 

special treatment such as bioremediation etc. 

PC, UEPL  Ensure that UEPL Emergency 

Response Procedures and Oil 

Spill Contingency Plan are 

available onsite. Ensure 

appropriate response is initiated 

at the time of such incident. 

UEPL to check that the plan is 

understood by all key personnel

At the time of construction 

2.17  All fuel and oil storage areas should have a concrete pad 

underneath to prevent soil contamination in case of leaks 

or spills 

PC, UEPL  Ensure provision of concrete padDuring construction activity 

2.18  All fuel tanks should be properly marked to highlight 

their contents 

PC, UEPL  Ensure that proper signs are 

placed with the tanks 

During construction activity 

2.19  Fuel and oil storage areas should have secondary 

containment in the form of concrete or brick masonry 

bunds. The volume of the containment area should be 

equal to at least 125% of the total volume of fuel or oil 

stored 

PC, UEPL  Check containment volume of 

the bunded area 

At the time of construction 

Page 285: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-43 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.20  During fuel and oil transfer operations such as re‐fuelling 

drips and spills should be avoided by using drip 

pans/trays 

PC, UEPL  Ensure provision of drips pans, 

provide training on safe re‐

fuelling practices, monitor oil or 

fuel transfer activity 

During construction activity 

2.21  Fuels tanks should be daily checked for leaks and all such 

leaks should be plugged immediately 

PC, UEPL  Inspect fuel tanks for leaks  During construction activity 

2.22  Waste oil should be provided to waste contractors 

approved by the UEPL where it will be re‐used/recycled 

PC, UEPL  UEPL to approve waste 

contractor and monitor safe 

transportation of the waste oil 

During construction and 

operation phase 

2.23  Shovels, plastic bags and absorbent material should be 

present near fuel and oil storage or handling areas to 

attend spills and leaks 

PC, UEPL  Monitor presence of materials 

and equipment 

During construction activity 

2.24  Vehicles should only be washed within designated areas 

within campsite. Mechanical maintenance works should 

be done only in workshops 

PC, UEPL  Ensure provision of washing 

areas and maintenance 

workshops and monitor any 

non‐compliances with the EIA 

requirement during routine 

monitoring 

During construction activity 

2.25  Vehicles should be daily checked for fuel or oil leaks. 

Vehicles with leaks should not be operated until repaired

PC, UEPL  Randomly inspect vehicles and 

designated parking areas 

During construction activity 

2.26  Water used for cleaning and hydro‐testing of flow line 

will be collected in lined pits where it will evaporate with 

time or drained into the nearest drainage channel with 

the prior approval of concerned authority. The residual 

sludge or solids and the liner will be disposed of 

following best industrial practices 

UEPL, PC  Check compliance  During hydro‐testing of flow 

lines and site restoration 

Page 286: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-44 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.27  Evaporation pits will be built at a distance of 300 m from 

local water wells or any perennial surface water source 

 

PC, UEPL  Check location of pits according 

to safe distance 

Before construction activity 

3  Deterioration of Air Quality 

3.1  Generators, vehicles and other equipment and machinery 

used during the operation should be properly tuned and 

maintained to minimize air emissions 

PC, UEPL  Check maintenance logs   During construction activity 

3.2  Construction campsite will be located at least 300 m away 

from communities 

PC, UEPL  Check distances of campsite 

from communities 

Prior to construction of 

campsite 

3.3  Dust emissions due to road travel should be minimized 

by regulating vehicles speed and watering of the access 

track (where applicable) 

PC, UEPL  Set and monitor speed limits. 

Monitor sprinkling of access 

track 

During construction activity 

3.4  Dust emissions during construction activities should be 

minimized by good management practices such as 

locating stock piles out of the wind direction, keeping the 

height of the stock piles to a minimum, keeping 

earthwork areas damp etc. 

PC, UEPL  Monitor dust emissions during 

earthworks. Train PC on good 

management practices 

During construction activity 

3.5  Burning of wastes will not be allowed  PC, UEPL  Monitor compliance  During construction activity 

3.6  Access tracks used during laying of flow line passing 

through communities will be avoided 

PC, UEPL  Check alignment of the access 

track and monitor vehicles speed

Before and during construction 

activity 

3.7  Appropriate measures will be taken to avoid ozone 

depletion & global warming e.g. prohibit use of CFC 

gases etc. 

PC  Ensure compliance  During construction activity 

4  Noise Pollution 

4.1  During all operations generators, vehicles and other 

equipment and machinery will be maintained in a good 

condition to ensure that noise from them is kept to a 

minimum level 

PC, UEPL  Monitor noise levels  During construction activity 

Page 287: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-45 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

4.2  Noise levels at communities nearest to the construction 

campsite should be monitored by UEPL and PC. In case 

these are found to exceed safe acceptable limits 

appropriate mitigation should be taken 

PC, UEPL  Monitor noise levels as part of 

the Effects Monitoring 

During construction activity 

4.3  Construction campsite will be located at least 300 m away 

from nearest communities 

PC, UEPL  Check distances from the 

community 

Prior to construction of the 

campsite 

4.4  Generators will be kept within enclosures to minimize 

dispersion of noise 

PC, UEPL  Check provision of enclosure  During construction activity 

4.5  The use of horns by project vehicles should be 

minimized. The use of pressure horns should not be 

allowed 

PC, UEPL  Train drivers, check vehicles and 

record non‐compliances 

During construction activity 

4.6  Movement of all project vehicles and personnel should be 

restricted to within work areas only 

PC  Advise all drivers and 

investigate non‐compliances 

from staff 

During construction activity 

4.7  Conduct regular noise monitoring as per applicable laws 

and regulations 

PC, UEPL  Monitor compliance  During construction activity 

5  Use of Water 

5.1  Water from surface water resources will not be used for 

project activities 

PC, UEPL  Check compliance  During construction activity 

5.2  The quantity of water used during construction phase 

will be kept to the minimum required by taking prudent 

water conservation measures on site. A complete record 

of water consumption will be maintained by the UEPL’s 

Representative 

PC, UEPL  Monitor water consumption, 

advise water conservation 

measures 

During construction activity 

Page 288: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-46 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

5.3  In case local water well has to be used, it will be 

approved by the UEPL Rep. Water from these tube wells 

will only be used after ensuring that the available 

capacity at the tube well (safe yield minus local demand) 

is at least 50% greater than the project demand. Discharge 

from the tube well will be regularly monitored to monitor 

any changes in the yield of the wells. If a single well fails 

to meet this requirement, water will be obtained from 

multiple wells such that each well meets the above‐

mentioned requirement 

PC, UEPL  Approve water well, record 

abstraction of water  

During construction activity 

5.4  If a new water well is to be installed, the well will be 

located 300 m from existing local wells and will be 

designed to abstract water preferably from deep aquifer 

not being used by local communities 

PC, UEPL  Monitor distance from the 

existing wells 

Before drilling of new water 

well 

5.5  UEPL and project contractors will pay proper and 

justified compensation for water utilized to the water 

well owners 

PC, UEPL  Ensure compliance  During construction activity 

5.6  Contamination of surface and groundwater resources will 

be prohibited 

PC, UEPL  Ensure compliance  During construction and 

operation 

6  Blockage of Natural Drainage 

6.1  Area around construction campsite should be landscaped 

to avoid blocking natural drainage 

PC  Monitor landscaping and any 

obstruction caused to natural 

drainage 

During construction activity 

6.2  Causeway crossings will be provided during the laying of 

flow line at all surface water bodies to avoid blocking of 

natural drainage 

PC, UEPL  Ensure construction of causeway 

crossings where required 

During construction activity 

Page 289: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-47 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

6.3  Uncontrolled & unnecessary clearing, dozing, excavations 

or quarrying, storage of construction material etc. will be 

avoided 

PC  Ensure compliance  During construction activity 

7  Site Restoration         

7.1  Demobilization of all equipment and machinery  PC, UEPL  Ensure compliance  During restoration phase 

7.2  Disposal of any waste material remaining at the time of 

completion of construction activities 

PC, UEPL  Ensure compliance  During restoration phase 

7.3  Backfilling of all soak pits and septic tanks 

 

PC, UEPL  Ensure compliance  During restoration phase 

7.4  Dismantling and removal of fence or barriers 

surrounding the campsite area 

PC, UEPL  Ensure compliance  During restoration phase 

7.5  General restoration of the site area including landscaping 

and restoration of drainage where required 

PC, UEPL  Ensure compliance  During restoration phase 

8  Clearing of Vegetation & Loss of Habitat

8.1  Land area requirements for construction camp and RoW 

of flow line will be kept to the minimum required 

UEPL  Check area of camp and width of 

RoW 

Before construction activity 

8.2  Construction campsite established for the purpose of 

construction will be located in existing clearing and 

levelled land 

PC, UEPL  Check location of campsite   Before construction activity 

8.3  Off‐road travel will be avoided  PC, UEPL  Monitor movement of vehicles  During construction activity 

8.4  During construction movement of construction 

equipment will be restricted to work areas only to avoid 

unnecessary disturbance to the native vegetation in the 

project area 

PC  Check compliance  During construction activity 

8.5  The access track (if any) will be properly compacted at 

the time of construction and thereafter properly 

maintained throughout the entire operational life 

PC, UEPL  Monitor compaction of access 

track 

During construction activity 

Page 290: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-48 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

8.6  Vehicles speed will be regulated and monitored to avoid 

excessive dust emissions 

PC, UEPL  Regulate and monitor vehicles 

speed 

During construction activity 

8.7  Periodic trainings will be provided to drivers on 

mitigation measures related to off‐road travel and speed 

limits 

PC, UEPL  Provide training to drivers  During construction activity 

8.8  Good engineering practices will be adopted during 

construction activities to ensure that unnecessary clearing 

of vegetation outside work areas is avoided 

PC  Train construction supervisors, 

monitor construction activities 

During construction activity 

8.9  Topsoil of the RoW of flow line will be separately stored. 

This topsoil will be backfilled after proper compaction 

ensuring regeneration of vegetation 

PC  Check compliance  During excavation and 

backfilling operation 

8.10  Cuttings of trees or tall shrubs will be avoided  PC, UEPL  Check compliance  During construction activity 

8.11  Use of local vegetation/wood as fuel will not be allowed  PC, UEPL  Check compliance  During construction activity 

9  Disturbance to Wildlife 

9.1  Prior to commencement of construction activity, 

awareness trainings will be provided to contractor’s 

management and field crew on matters related to the 

requirements of the EMP in this regard 

UEPL, PC  Provide environmental 

awareness training  

Before commencement of 

construction activity 

9.2  Land uptake by project facilities will be minimized  UEPL, PC  Check compliance  After marking of the site layout 

on ground by the PC and prior 

to clearing of land at these 

areas 

9.3  The total duration of construction phase will be 

minimized by good management 

PC, UEPL  Check compliance  During construction phase 

9.4  All mitigation measures to minimize noise levels, dust 

emissions, air emissions and waste management required 

by the EIA will be adhered to 

PC, UEPL  Check compliance  During construction activity 

Page 291: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-49 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

9.5  Food wastes will not be disposed of in the open. Food 

wastes collected in waste segregation units will be 

disposed of according to waste disposal procedure on a 

regular and strict basis as advised by the UEPL Rep 

PC, UEPL  Monitor collection and disposal 

of food waste 

During construction activity 

9.6  Construction work near areas which show small mammal 

and reptile populations will commence after a soft start 

up and will be randomly monitored 

PC, UEPL  Check compliance  During construction activity 

9.7  Vehicles speed on access road will be controlled to avoid 

incidental mortalities of reptiles. Any such incident will 

be reported to the UEPL representative. Vehicles speed 

will be randomly checked 

PC, UEPL  Monitor speed limits  During construction activity 

9.8  Cutting of trees or tall shrubs will be avoided  PC, UEPL  Check compliance  During construction activity 

9.9  Movement of all project personnel and vehicles will be 

restricted to work areas and to approved routes only 

PC, UEPL  Check compliance  During construction activity 

9.10  Night work during construction will be prohibited, night 

traveling will not be allowed unless absolutely necessary 

PC, UEPL  Check compliance  During construction activity 

9.11  Lights used at construction campsite will be kept to the 

minimum required 

PC, UEPL  Check compliance  During installation of lights 

9.12  Hunting, fishing, killing, feeding, trapping or harassment 

of wildlife will not be allowed 

PC, UEPL  Check compliance  During construction activity 

9.13  Within the sensitive habitats of wildlife, operation will be 

completed within the shortest time possible PC, UEPL  Ensure compliance  During construction activity 

10  Socioeconomic, Archaeological and Cultural Environment

10.1  Local sources of drinking water will not be exploited  PC, UEPL  Monitor adherence with the 

requirements 

During construction activity 

10.2  The access road will be watered regularly to minimize 

dust emissions 

PC, UEPL  Monitor water sprinkling  During construction activity 

Page 292: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-50 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

10.3  RoW for flow line should by‐pass major settlements to 

maintain safe distances 

UEPL, PC  Check alignment of flow line  Before construction activity 

10.4  Drivers will be trained in responsible and safe driving 

practices, safe speed limits for vehicles will be followed 

PC, UEPL  Provide training and monitor 

compliance 

During construction activity 

10.5  Strict compliance will be observed with UEPL’s HSE 

guidelines 

UEPL, PC  Ensure compliance  During construction activity 

10.6  Labour from local communities will be recruited 

equitably amongst the various tribes, avenues for conflict 

resolution will be open and the employment procedures 

will be transparent 

PC, UEPL  Monitor adherence with the 

requirement and maintain 

record of labour 

During construction activity 

10.7  Use of local firewood for cooking or heating by project 

and contractor staff to be prohibited 

PC, UEPL  Monitor adherence with the 

requirement 

During construction activity 

10.8  The vehicles speed for traveling along the access road 

will be limited  

PC, UEPL  Monitor speed limits  During construction activity 

10.9  The construction campsite will be located at minimum 

distance of 300 m from communities thereby, mitigating 

the effect of noise and emissions 

UEPL, PC  Check distances  Before construction activity 

10.10  Any land acquired and distribution of compensation will 

be carried out transparently 

UEPL  Check compliance  Before construction phase 

10.11  All mitigation measures related to waste management, 

minimizing air emissions and noise recommended in the 

EIA should be adhered with 

PC, UEPL  Check compliance  During construction activity 

10.12  Project staff will respect cultural norms  PC, UEPL  Check compliance  During construction activity 

10.13  All community grievances will be addressed and rectified

as appropriate 

PC, UEPL  Check compliance  During construction activity 

10.14  All project facilities will be restored according to the 

standard protocols and recommendations of the EIA 

UEPL, PC  Check compliance  During restoration 

Page 293: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-51 HPK

No.  Impact & Mitigation Measure Responsibility & 

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

10.15  During project communication links with local 

communities will be maintained 

PC, UEPL  Check compliance  During construction and 

operation 

10.16  During construction, all cultural, religious and 

archaeological sites will be identified (if found) and 

mitigation measures specified in the EIA will be followed

PC, UEPL  Check compliance  During construction and 

operation 

10.17  RoW of flow lines will maintain a distance of 100 m from 

cultural, religious and archaeological sites, unless 

community demands a greater distance e.g. graveyards 

or mosques 

UEPL, PC  Check compliance  During construction and 

operation 

Notes: UEPL: United Energy Pakistan Limited’s Management or Representative; PC: Project Contractor/s

Page 294: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-52 HPK

Table A‐4: Mitigation Management Matrix for Establishment/Construction of GPF/CPP 

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

1  Changes in Landscape and Soil Erosion

1.1  Total land uptake by the construction contrator campsite/s 

will be kept to the minimum required 

UEPL, IMC, CC  Check compliance  After marking of the site layout 

on ground by the CC and prior 

to clearing of land at these areas 

1.2  Contractor campsite/s will preferably be located in existing 

clearing and levelled land and will avoid major earthworks 

UEPL, IMC, CC  Location of campsite in levelled

areas 

Prior to site layout on ground 

1.3  Existing access track/s to the GPF/CPP will be used as much 

as possible 

 

CC, UEPL, IMC  Monitor off road travel and 

record non‐compliances 

During the entire operation  

1.4  To minimize erosion due to quarrying, the quarry sites will be 

carefully selected such that they are located in levelled areas 

with existing clearing and the quarry sites will be properly 

restored after use 

CC, UEPL, IMC  Check compliance  Prior to execution 

1.5  Access track to the GPF/CPP will be properly compacted at 

the time of construction and associated activities and 

thereafter properly maintained throughout the entire 

operational life 

CC, UEPL, IMC  Check compliance  Compaction during execution to 

minimize dust emissions and 

loose sections of the track for the 

use of entire operation 

1.6  Off‐road travel should be strictly prohibited and observance 

of this should be monitored during the operation  

CC, UEPL, IMC  Advise all personnel, monitor 

any staff complaints and signs 

of off‐road travel 

During the entire operation 

1.7  Vehicles speed should be regulated and monitored to avoid 

excessive dust emission 

CC, UEPL, IMC  Set speed limits, train drivers 

and monitor non‐compliances 

During the entire operation 

1.8  Clearing of vegetation and the cutting of trees will be 

minimized as much as possible 

CC, UEPL, IMC  Monitor land clearing activities During design and construction 

1.9  Movement of construction equipment should be restricted to 

work areas only to avoid unnecessary disturbance to soils in 

the project area 

CC, IMC  Monitor movement of vehicles 

and off‐road travel 

During Construction activity 

Page 295: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

1.10  UEPL will monitor the access tracks (other than the main 

access track for the project) to be used by water tankers, 

dumper trucks and other vehicles 

UEPL, CC, IMC  Sprinkling of water on access 

track to water wells 

During the entire operation 

1.11  Periodic trainings should be provided to drivers on 

mitigation measures related to off‐road travel and speed 

limits 

UEPL, CC, IMC  Check training log, provide 

trainings 

During the entire project 

2  Soil and Water Contamination   

2.1  Food waste and combustible packaging wastes that have no 

re‐use should be stored temporarily onsite within designated 

waste segregation areas for ultimate safe disposal 

CC, UEPL, IMC  Provision of sufficient waste 

bins, segregation of waste 

During the entire operation 

2.2  Dedicated waste segregation units/containers should be built 

or placed at GPF and campsites 

CC, UEPL, IMC  Construction and monitoring of 

waste segregation units 

During entire project 

2.3  Recyclable wastes including glass, tins, and metal scrap 

should be provided to recycling contractors as appropriate 

CC, UEPL, IMC  IMC to approve waste 

contractors. Monitor waste 

segregation and safe 

transportation to the recycling 

contractorʹs facility 

During the entire operation 

2.4  Waste oil should be provided to contractors for recycling as 

appropriate. Recycled oil will not be brought back to site 

CC, UEPL, IMC  IMC to approve waste 

contractor and monitor safe 

transportation of the waste oil 

During the entire operation 

2.5  Medical wastes should be temporarily stored onsite 

separately and incinerated at a suitable location 

CC, UEPL, IMC  UEPL Rep to approve disposal 

arrangement. Monitor waste 

segregation and safe storage 

onsite 

During the entire operation 

2.6  Wastes should not be disposed of in the open  CC, UEPL, IMC  Monitor during routine visits  During the entire operation 

2.7  For collection of wastes at the GPF and campsite adequate 

number of waste bins should be provided 

CC, IMC  Monitor provision of sufficient 

waste bins  

During the entire operation 

Page 296: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.8  Grey wastewater should be collected directly into septic tanks 

and then to soak pits. Sprinkling of grey wastewater will not 

be allowed  

CC, IMC, UEPL  Check provision of soak pits 

and quality of wastewater 

During the entire operation 

2.9  Sewage generated from the toilets should be collected and 

treated in septic tanks. The septic tanks should be built of 

concrete and brick masonry to avoid leaching of wastewater 

from the tanks. The overflow from the tanks should discharge 

into soak pits. In case the soak pits get filled the wastewater 

shall be transferred from the site in a tanker and disposed of 

into municipal drains in the nearest area 

CC, UEPL, IMC  Check provision of septic tank 

and soak pit. Monitor 

wastewater levels in the soak 

pits 

During the entire operation 

2.10  Soak pits should be built in absorbent soil and located 300 m 

away from a surface water source or a groundwater well 

CC, UEPL, IMC  Check soil condition and 

distance between the soak pits 

and the nearest water body 

During design and construction 

2.11  Soak pits should be covered and constructed such that surface 

runoff cannot enter the pits 

CC, UEPL, IMC  Monitor provision of covers 

and berms 

Provision of berms during 

construction and proper covers 

during the entire operation 

2.12  Soil contaminated by minor spills/leakages (defined as leaks 

from vehicles, machinery, equipment or storage containers 

such that the area and depth of soil contaminated is less than 

1 sq. ft and 3 inches respectively) should be scraped and 

treated as appropriate  

CC, UEPL, IMC  Monitor any oil leaks and safe 

disposal of contaminated soil 

During the entire operation 

Page 297: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.13  Moderate spills defined as spills of volume less than or equal 

to 200 liters should be contained and controlled using 

shovels, sands and native soil. These equipment and 

materials should be made available at GPF/CPP and campsite 

during the operation. The contaminated soil should be 

excavated and stored in a bunded area lined with an 

impermeable base. Depending on the volume, the 

contaminated soil should be properly buried in such a 

manner that it does not contaminate the surrounding soils or 

groundwater 

CC, UEPL, IMC  Ensure provision of equipment 

and material to control and 

handle such spills on site. 

Monitor disposal as per the 

requirements of the EIA 

During the entire operation 

2.14  Major spills (defined in the EIA as spills of volume much 

greater than 200 liters) will require initiation of UEPLʹs 

Emergency Response Procedures. These spills should be 

handled and controlled according to the measures listed in 

UEPL’s Oil Spill Contingency Plan and will be disposed of as 

per methods defined in UEPL’s Oil Spill Contingency Plan 

UEPL, CC, IMC  Ensure that UEPL Emergency 

Response Procedures and Oil 

Spill Contingency Plan are 

available onsite. Ensure 

appropriate response is 

initiated at the time of such 

incident. IMC to check that the 

plan is understood by all key 

personnel 

During the entire operation 

2.15  All fuel and oil storage areas should have a concrete pad 

underneath to prevent soil contamination in case of leaks or 

spills 

CC, UEPL, IMC  Ensure provision of concrete 

pad 

During construction activity 

2.16  All fuel tanks should be properly marked to highlight their 

contents 

CC, UEPL, IMC  Ensure that proper signs are 

placed with the tanks 

During the entire operation 

2.17  Fuel and oil storage areas should have secondary 

containment in the form of concrete or brick masonry bunds. 

The volume of the containment area should be equal to at 

least 125% of the total volume of fuel or oil stored 

CC, UEPL, IMC  Check containment volume of 

the bunded area 

At the time of construction 

Page 298: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

2.18  During fuel and oil transfer operations such as re‐fuelling 

drips and spills should be avoided and drip pans should be 

used 

CC, UEPL, IMC  Ensure provision of drips pans, 

provide training on safe re‐

fuelling practices, monitor oil 

or fuel stains 

During the entire operation 

2.19  Fuel tanks should be regularly checked for leaks and all such 

leaks should be plugged immediately 

CC, UEPL, IMC  Inspect fuel tanks for leaks  During the entire operation 

2.20  Shovels, plastic bags and absorbent material should be 

present near fuel and oil storage or handling areas to attend 

spills and leaks 

CC, UEPL, IMC  Monitor presence of materials 

and equipment 

During the entire operation 

2.21  Vehicles should only be washed within designated areas 

within campsites. Mechanical maintenance works should be 

done only in workshops 

CC, UEPL, IMC  Ensure provision of washing 

areas and maintenance 

workshops and monitor any 

non‐compliances with the EIA 

requirements during routine 

monitoring 

During the entire operation 

2.22  Vehicles shall be daily checked for fuel or oil leaks. Vehicles 

with leaks shall not be operated until repaired 

CC, UEPL, IMC  Randomly inspect vehicles and 

designated parking areas 

During the entire operation 

2.23  Produced water separated at GPF/CPP shall be re‐injected to 

reservoir through deep well injection (first priority). 

However, it can be sent to lined E‐Pond if no technical 

feasible options are available 

CC, UEPL, IMC  Check compliance   During the entire operation 

3  Climate and Ambient Air Quality 

3.1  Campsites will be located at least 300 m away from 

communities 

UEPL, CC, IMC  Check Compliance  Before construction 

3.2  Generators, compressors and vehicles used should be 

properly tuned and maintained to minimize air emissions 

CC, UEPL, IMC  Check maintenance logs   During the entire operation 

Page 299: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

3.3  Dust emissions due to road travel should be minimized by 

regulating vehicles speed and watering of the access track 

(where applicable) 

CC, UEPL, IMC  Set and monitor speed limits. 

Monitor sprinkling of access 

track 

During the entire operation 

3.4  Dust emissions during construction activities should be 

minimized by good management practices such as locating 

stock piles out of the wind direction, keeping the height of the 

stock piles to a minimum, keeping earthwork areas damp etc.

CC, UEPL, IMC  Monitor dust emissions during 

earthworks. Train CC on good 

management practices 

During the construction 

operation 

3.5  During detailed design of the GPF/CPP, emissions from point 

sources such as flare and incinerator (for acid gases) should 

be modelled so that if there are any ill‐effects on local 

communities and workers appropriate mitigation measures 

such as adjusting the stack heights can be taken 

UEPL, CC, IMC  Check compliace   During the entire operation 

3.6  During construction leveling or widening along the access 

road will be done in sections, immediately followed by 

sprinkling of water and also preferably compaction (where 

required) 

CC, UEPL, IMC  Access road construction/ 

maintenace 

During construction activity 

3.7  Emissions from all point sources should be monitored to 

check compliance with SEQS 

UEPL, CC, IMC  Ensure monitoring being 

conducted 

During the entire operation  

4  Noise Pollution   

4.1  It shall be ensured that generators, vehicles and other 

potentially noisy equipment used are in good working 

condition 

CC, UEPL, IMC  Monitor noise levels  Prior to use of machinery and 

vehicles 

4.2  Noise levels at communities nearest to the GPF/CPP, 

campsite and access track should be monitored and in case 

these are found to exceed safe acceptable limits appropriate 

mitigation shall be taken 

UEPL, CC, IMC  Monitor noise levels as part of 

the Effects Monitoring Program

Frequency of monitoring 

specified in the Effects 

Monitoring Program 

4.3  Campsite/s will be located 300 m away from nearest 

communities 

CC, UEPL, IMC  Check distances from the 

community 

Prior to construction  

Page 300: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

4.4  The use of horns by project vehicles should be minimized. 

The use of pressure horns should not be allowed 

CC, UEPL, IMC  Train drivers, check vehicles 

and record non‐compliances 

During the entire operation 

4.5  Movement of all project vehicles and personnel should be 

restricted to within work areas only 

CC, UEPL, IMC  Advise all drivers and 

investigate non‐compliances 

from staff 

During the entire operation 

4.6  Provide noise barriers/enclosures to control noise levels from 

generators and mechanical workshops etc. Moreover, 

locate/setup noisy equipment or machinery as far as possible 

from nearby receptors 

UEPL, CC, IMC  Check provision of noise 

barriers/enclosures  

 During construction phase 

4.7  Conduct regular noise monitoring as per applicable laws and 

regulations 

UEPL, CC, IMC  Ensure compliance  During the entire project 

5.  Use of Water 

5.1  Water from surface water bodies will not be used   CC, UEPL, IMC  Check compliance  During the entire operation 

5.2  The quantity of water used during construction and operation 

will be kept to the minimum required by taking prudent 

water conservation measures on site. A complete record of 

water consumption will be maintained 

CC, UEPL, IMC  Monitor water consumption, 

advise water conservation 

measures 

During the entire operation 

5.3  Marginally sweet water wells will be used for constrution and 

other project related activities. Where possible, use of 

brackish water should be maximized for the project activities. 

Discharge from the water well will be regularly monitored to 

monitor any changes in the yield of the wells 

CC, UEPL, IMC  Approve water well, record 

extraction of water  

During the entire project 

5.4  If a new water well is to be installed, the well will be located 

300 m from existing local wells and will be designed to 

abstract water preferably from deep aquifer not being used by 

local communities 

UEPL, IMC  Ensure safe distance from 

community water wells  

During or before project activity 

Page 301: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

5.5  Utilization of water resources that are in possession of local 

owners shall be appropriately compensated as per mutual 

agreement of both parties  

CC, UEPL, IMC  Ensure that proper 

compensation is being paid 

During the entire project 

5.6  Preferably, the potable water requirement will be met by 

installing water treatment system (such as reverse osmosis) 

UEPL, CC, IMC  IMC to guide on preservation 

of water 

During the entire operation 

6.  Blockage of Natural Drainage 

6.1  Area around the GPF/CPP and campsite shall be landscaped 

to avoid blocking natural drainage 

CC, UEPL, IMC  Monitor landscaping and any 

obstruction caused to natural 

drainage 

During  the construction activity 

6.2  Causeway crossings and pipe culverts will be provided at 

stream crossings to avoid blockage of natural drainage 

CC, UEPL, IMC  Ensure construction of culverts 

where required particularly 

along the access track 

During construction activity 

6.3  Uncontrolled & unnecessary clearing, dozing, excavations or 

quarrying, storage of construction material etc. will be 

avoided 

CC, IMC  Ensure compliance  During construction activity 

7  Clearing of Vegetation & Loss of Habitat

7.1  Total land uptake will be kept to the minimum required  UEPL  Check compliance  After marking of the site layout 

on ground by the CC and prior 

to clearing of land at these areas 

7.2  Off‐road travel, required at sections of the road where 

construction work is in progress, will be minimized and if 

required will be allowed only after approval from UEPL Rep 

CC, UEPL, IMC  Train drivers and investigate 

non‐compliances  

During the entire operation 

7.3  Campsite areas will be located in existing cleared area  CC, IMC, UEPL  Supervise camp setup  During setup of the construction 

camps 

7.4  The access track to the GPF/CPP will be selected to utilize 

existing track as much as possible 

CC, UEPL, IMC  Ensure existing track to used as 

much as possible 

During selection of access track 

Page 302: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

7.5  Clearing of vegetation will be avoided as much as possible. 

Under unavoidable circumstances any clearing required will 

be done with prior approval of IMC and custodian of the 

area. Each tree cutting for clearing of site will be 

replaced/compensated by plantation of trees at site (10 trees 

for each tree cut). The tree species shall be indigenous to the 

region 

CC, UEPL, IMC  Supervise land clearing 

activities 

During land clearing for the 

campsites 

7.6  Periodic trainings will be provided to drivers on mitigation 

measures related to off‐road travel and speed limits 

CC, UEPL, IMC  Check training log, provide 

trainings 

During the entire project 

7.7  Dust emissions on access tracks will be reduced by keeping 

speed limits below 40 km/hr 

CC, UEPL, IMC  Check compliance  During the entire operation 

7.8  Vehicles speed will be regulated and monitored to avoid 

excessive dust emissions 

CC, UEPL, IMC  Check compliance  During the entire operation 

7.9  Use of local vegetation as fuel will not be allowed  CC, UEPL, IMC  Check compliance  During the entire operation 

8.  Disturbance to Wildlife 

8.1  Prior to commencement of construction, awareness trainings 

will be provided to contractor’s management and field crew 

on HSE awareness 

UEPL  Provide environmental 

awareness training  

Before commencement of 

construction  

8.2  Land uptake will be kept to minimium required  UEPL, CC, IMC  Check compliance  After marking of the site layout 

on ground by the CC and prior 

to clearing of land at these areas 

8.3  All mitigation measures to minimize noise levels, dust 

emissions, air emissions, and waste management required by 

the EIA will be adhered to 

CC, UEPL, IMC  Check compliance  During the entire operation 

8.4  Food wastes will not be disposed of in the open   CC, UEPL, IMC  Monitor collection and disposal 

of food waste 

During the entire operation  

Page 303: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

8.5  Vehicles speed on access road will be controlled to avoid 

incidental mortalities of reptiles. Any such incident will be 

reported to all concerned departments with copy to 

departmental heads. Vehicles speed will be randomly 

checked 

UEPL, CC, IMC  Monitor speed limits  During the entire operation 

8.6  Cutting of trees will be avoided as much as possible  CC, IMC  Check compliance  During Construction activity 

8.7  Movement of all project personnel will be restricted to work 

areas only 

UEPL, CC, IMC  Check compliance  During entire operation  

8.8  Movement of project vehicles will be restricted only to the 

project access road or to routes approved by UEPL’s Rep 

UEPL, CC, IMC  Check compliance  During the entire operation 

8.9  Night travelling will only be done after getting approval from

UEPL’s Rep 

CC, UEPL, IMC  Check compliance  During the entire operation 

8.10  Lights used at the GPF/CPP and campsite will be kept to the 

minimum required 

CC, UEPL, IMC  Ensure that the EIA 

requirement are met 

During the entire operation 

8.11  Hunting, fishing or trapping of wildlife will not be allowed  UEPL, CC, IMC  Check compliance  During the entire operation 

8.12  Feeding or harassment of wildlife will not be allowed  UEPL, CC, IMC  Check compliance  During the entire operation 

9  Socioeconomic, Archaeological and Cultural Environment

9.1  Project contractors and field staff shall be taken through a 

Community and External Affairs Induction program before 

execution of project activities 

UEPL  Ensure training to contractors  Before start of project activities 

9.2  Local sources of drinking water will not be exploited  UEPL, CC, IMC  Monitor adherence with the 

requirement 

During the entire operation 

9.3  The access road will be watered regularly to minimize dust 

emissions (if required) 

UEPL, CC, IMC  Monitor water sprinkling  During the entire operation 

9.4  Construction of by passes to all major settlements and where 

necessary re‐routing the access road so that a safe distances is 

maintained from a settlement 

UEPL, CC, IMC  Check alignment of access 

routes 

During construction activity 

Page 304: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

No.  Impact & Mitigation Measure Responsibility &

Execution 

Action/Monitoring 

Parameter/Monitoring MethodTiming 

9.5  Drivers will be trained in responsible and safe driving 

practices, a speed limit shall be set and maintained in 

addition vehicle log books will be maintained and inspected 

for compliance 

UEPL, CC, IMC  Provide training and monitor 

compliance 

During the entire operation 

9.6  Labour from local communities will be recruited equitably 

amongst the various tribes subject to company’s competency 

criteria  

UEPL, CC, IMC  Monitor adherence with the 

requirement and maintain 

record of labour 

During the entire operation 

9.7  Use of local firewood for cooking by contractor staff to be 

prohibited 

CC, IMC  Monitor adherence with the 

requirement 

During the entire operation  

9.8  Campsite will be located at minimum distance of 300 m from 

nearest residential communities thereby mitigating the effect 

of noise and emissions 

UEPL, CC, IMC  Check the distance   Before construction activity 

9.9  Generators and vehicles will be regularly maintained to 

minimize emissions 

UEPL, CC, IMC  Monitor air emissions  During the entire operation  

9.10  Project staff will respect cultural norms  UEPL, CC, IMC  Check compliance  During the entire operation 

9.11  Access road will be re‐aligned to maintain safe distance from 

the edge of any graveyard and shrine (if found) 

UEPL, CC, IMC  Check distance  Before and during construction 

9.12  All community grievances will be addressed and rectified 

appropriately  

UEPL, CC, IMC  Check compliance  During the entire operation 

Notes: CC: Construction Contractor; IMC: Independent Monitoring Consultant; UEPL: Management or Representative of United Energy Pakistan Limited

Page 305: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-63 HPK

Table A‐5: Recommended Distances from Environmental Features during Seismic Operation 

Item  Distance

New access track/s  50 m from all surface water sources 

100 m from archaeological significant and cultural sites (including 

graveyard, religious sites and shrines) 

100 m from villages (if and where possible) 

Campsite/s  300 m from villages/town/city 

Upholes  30 m from water wells 

50 m from houses 

50 m from surface water bodies 

50 m from reptile hole/nest/den 

50 m from archaeological significant and cultural sites (including 

graveyard, religious sites and shrines) 

Shot holes  50 m from water wells 

50 m from houses 

50 m from surface water bodies 

50 m from reptile hole/nest/den 

50 m from archaeological significant and cultural sites (including 

graveyard, religious sites and shrines) 

Table A‐6: Recommended Distance from Environmental Receptors during Drilling and Flow Line 

Laying/Wellhead Works 

Area/Facility 

Distance (m) 

Community Community 

Water Well 

Archaeological or 

Cultural Site 

Well site  300  300  300 

Rig camp  300  300  300 

Soak pits  NA  300 m from 

ground/surface 

water resources 

NA 

RoW of flow line  100  100  50 

Construction camp   300    300 

Minimum distances of various project activities from environmental receptors (not mentioned in this table) will be decided 

during project execution phase.  

 

 

 

 

 

Page 306: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-64 HPK

Table A‐7: Minimum Distance from Environmental Receptors during Establishment/ 

Construction of GPF/CPP 

Area/Facility 

Distance (m)

Community Community Water 

Well 

Archaeological or Cultural 

Site 

Construction camp  300  300  300 

Quarry location  1,000  300  300 

Soak pits  NA  300 m from 

ground/surface water 

resources 

NA 

Minimum distances of various project activities from environmental receptors (not mentioned in this table will be decided 

during project execution phase. 

Page 307: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

Table A‐8: A Tentative Frequency of Monitoring Mitigation Measures 

Item  Frequency

Line inspections  Prior to start work on any seismic line 

Access track inspection  Prior to start work on any of access track development 

Camp construction  At the time of camp construction 

Waste disposal at campsites  Once a week as a minimum

Waste disposal at rig site & GPF  Daily during routine field visits 

Waste disposal along access tracks 

and survey lines 

Daily during routine field visits 

Water use  Once every week 

Recycling contractors  At the time of approval and then once during the operation 

Access tracks and road travel  Daily during routine field visits 

Preparation of survey lines  During survey of seismic lines 

Shot holes/Upholes drilling, 

shooting and recording 

On a routine basis on selected seismic lines 

Vehicles – Field inspections  Daily during routine field visits

Vehicles – Camp inspections  Twice a week as a minimum 

Handling of fuels, oils and 

chemicals 

Once during camp construction & twice a week during 

camp operation 

Condensate storage  Daily during routine field visits 

Chemical storage  Once every week 

General controls  Daily during routine field visits 

Restoration  During restoration 

Page 308: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-66 HPK

Table A‐9: Effects Monitoring Requirements 

Parameter  Potential Issue Monitoring 

Parameter 

Method Frequency Responsibility

Physical Parameters 

Water  Water lowering of 

groundwater table or 

reduced discharge in 

water wells used by the 

project and within 300 m 

radius 

Water well 

discharge  

Volumetric 

discharge 

measurement 

Monthly during each 

project 

United Energy 

Pakistan Limited 

Limited (UEPL) 

Biological Environment 

Wildlife  Disturbance to wildlife 

including key species of 

the project area  

Presence and 

distribution 

of wildlife in 

the area of 

operation 

Wildlife surveys  For each project the 

frequency will be as 

follows: Pre‐project, at 

regular intervals during 

the projects and after 

restoration 

Independent 

Monitoring Team 

(IMC) 

Socioeconomic Environment 

Communities  Disturbance to 

communities and 

community complaints 

Community 

complaints 

Community 

consultation and 

community 

complaints register 

Consultation with 

communities through 

UEPL’s site representative 

prior to and throughout 

each project 

United Energy 

Pakistan Limited 

Limited (UEPL) 

Page 309: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 A-67 HPK

Table A‐10: Suggested Training Program 

Project Activity  Staff  Contents

Seismic, Construction (all 

activities) and Drilling 

Drivers  Road safety 

Road restrictions 

Vehicles restrictions 

Waste disposal 

Seismic and Construction 

(all activities) 

Survey Crew  Wildlife sensitivities 

Identification of sensitive areas 

Communication of environmental problems to 

appropriate personnel 

Waste disposal 

Seismic, Construction (all 

activities) and Drilling 

Bulldozer Operators  Wildlife sensitivities 

Identification and avoidance of sensitive areas 

Waste disposal 

Communication of environmental problems to 

appropriate personnel 

Seismic, Construction (all 

activities) and Drilling 

Mechanics and 

Vehicles Operators  

All Personnel 

Environmental controls of 

vehicles and equipment 

Waste disposal 

Seismic, Construction (all 

activities) and Drilling 

Camp Staff  Safe camp operation  

Waste disposal 

Seismic, Construction (all 

activities) and Drilling 

Restoration and Clean‐

up Team 

Restoration requirements 

Note: ‘Construction’ activities also include construction of flow lines and GPF/CPP 

Page 310: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 HPK

Appendix B Environmental Monitoring Checklists

Page 311: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-1 HPK

Checklist for Camp Establishment 

No.  Description  Status Additional 

Comments

1.  Has the campsite been selected in consultation with 

HSEO?  Yes  No 

 

2.  Have photographs been taken to record the pre‐

camping conditions?  Yes  No 

 

3.  Has the campsite been selected in existing clearings 

and on levelled land?  Yes  No 

 

4.  Has the campsite been selected at least 300 meters 

away from any communities?  Yes  No 

 

5.  Has the campsite been selected 300 meters from any 

surface water body?  Yes  No 

 

6.  Have compensation amounts been settled based on 

prevailing market rates?  Yes  No 

 

7.  Has any vegetation been cleared?   Yes  No   

8.  If yes, is the vegetation loss significant?   Yes  No   

9.  If yes, have the mitigation measures specified in the 

EIA been adhered with?  Yes  No 

 

10.  Has the top soil been damaged significantly or root 

stock destroyed?  Yes  No 

 

11.  Have the trees or bushes been used as fuel wood?   Yes  No   

12.  Have any trees been cut?   Yes  No   

13.  Has the natural drainage been disturbed or blocked?   Yes  No   

14.  Does the campsite have a septic system comprising of 

septic tank and soak pit?  Yes  No 

 

15.  Have the soak pits for laundry, kitchen and showers 

been built?  Yes  No 

 

16.  Have the soak pits been built in absorbent soil?   Yes  No   

17.  Have the soak pits (where required) been built down‐

slope from the camp?  Yes  No 

 

18.  Have the soak pits been designed to accommodate 

wastewater generated during the total duration of the 

operation? 

 Yes  No 

 

19.  Are the soak pits within 300 meters of any surface 

water source or a ground well?  Yes  No 

 

20.  Can surface water enter the soak pits?   Yes  No   

21.  Has plastic sheeting been placed under all concreted 

structures?  Yes  No 

 

22.  Have all other mitigations measures specified in the 

EIA been adhered to?  Yes  No 

 

23.  Are UEPL’s HSE guidelines being followed?   Yes  No   

Name:  Signature: 

    Date:     

Page 312: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-2 HPK

Additional Comments       

         

         

         

         

         

Page 313: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-3 HPK

Checklist for Camp Operation 

No.  Description  Status Additional 

Comments 

1.  Has any vegetation been cleared or damaged?   Yes   No   

2.  Are bushes or trees been used as fuel wood?   Yes   No   

3.  Is water drawn from a local water source?   Yes   No   

4.  If yes to point 3, has the yield and demand been 

determined to ensure there is enough to meet the 

requirements of the locals? 

 Yes   No 

 

5.  If yes to point 3, is water well discharge being checked 

and recorded on a regular basis?  Yes   No 

 

6.  If yes to point 3, is compensation being paid for the 

water use?  Yes   No 

 

7.  Has the natural drainage been disturbed?    Yes   No   

8.  Are the fuels and oils handled in a safe manner, 

ensuring no leakage or spillage?  Yes   No 

 

9.  Are the soak pits being constructed 300 meters away 

from a surface water source or groundwater well?  Yes   No 

 

10.  Has any surface water entered the soak pits?   Yes   No   

11.  In case the soak pits get filled during the operation, has 

the grey water been transferred to the nearest 

municipal drains? 

 Yes   No 

 

12.  Is sprinkling of wastewater being done on site?   Yes   No   

13.  Has arrangements for the transportation of black water 

to the municipal drains been in placed?  Yes   No 

 

14.  Are there enough waste bins around the camp?   Yes   No   

15.  Are the waste bins emptied on a regular basis?   Yes   No   

16.  Is food waste disposed in the open?   Yes   No   

17.  Has the burning of wastes been practiced?   Yes   No   

18.  Is the combustible and non‐combustible waste being 

sent to the approved waste contractor(s)?  Yes   No 

 

19.  Is medical waste being stored separately at the 

campsite?  Yes   No 

 

20.  Is medical waste being disposed of properly i.e. 

incinerated?  Yes   No 

 

21.  Are water consumption figures being maintained?   Yes   No   

22.  Are UEPL’s HSE guidelines being followed?   Yes   No   

23.  Have requirements of the EIA been adhered to?   Yes   No   

Name:  Signature: 

    Date: 

Additional Comments 

         

         

         

Page 314: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-4 HPK

Checklist for Vehicles 

No.  Description  Status Additional 

Comments

1.  Are the vehicles maintained and inspected regularly?   Yes   No   

2.  Are the oil, fuel and other leaks from the vehicles 

immediately attended to?  Yes   No 

 

3.  Are the vehicles with leaks being operated?   Yes   No   

4.  Has there been any spillage during vehicle re‐fueling 

or maintenance?  Yes   No 

 

5.  If yes, have recommended mitigation measures been 

adhered to?  Yes   No 

 

6.  Are the vehicles being washed or serviced in the field?   Yes   No   

7.  Are the vehicles being washed in designated areas 

having concrete pad and wastewater collection pits?  Yes   No 

 

8.  Is vehicle related waste, such as oils, filters, old tires or 

parts are left unattended?  Yes   No 

 

9.  Is vehicle related waste, such as oils, filters, old tyres or 

parts being disposed of properly?  Yes   No 

 

10.  Are the vehicles emitting excessive smoke?   Yes   No   

11.  Do the potentially noisy vehicles have properly 

functioning silencers (mufflers)?  Yes   No 

 

12.  Do all vehicles have provision for containers/trash 

bags to store trash/refuse?  Yes   No 

 

13.  Are UEPL’s HSE guidelines being followed?   Yes   No   

14.  Have all other mitigations measures specified in the 

EIA been adhered to?  Yes   No 

 

Name:  Signature: 

    Date: 

Additional Comments     

         

         

         

         

         

 

Page 315: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-5 HPK

Checklist for Road Travel 

No.  Description  Status Additional 

Comments

1.  Is the number of routes kept to a minimum?   Yes  No   

2.  Have photographs been taken to record pre‐usage 

conditions?  Yes  No 

 

3.  Are the existing routes being used to access the 

desired locations?  Yes  No 

 

4.  Have new access routes been developed?   Yes  No   

5.  If yes, have requirements of the EIA been adhered to?   Yes  No   

6.  Has vegetation clearing been minimized?   Yes  No   

7.  Has off‐road travel been observed or short cuts been 

used?  Yes  No 

 

8.  Is vehicle speed limit of 30‐40 km/hr being followed?   Yes  No   

9.  Are heavily traveled routes watered (wherever 

required) on a daily basis to minimize dispersion of 

dust? 

 Yes  No 

 

10.  Are the drivers careful and watchful about wild and 

domestic animals?  Yes  No 

 

11.  Has any natural drainage been disturbed or altered?   Yes  No   

12.  Is any soil erosion observed?   Yes  No   

13.  If yes, have the mitigation measures been adhered to?   Yes  No   

14.  Is night travel avoided?   Yes  No   

15.  Is the use of horns avoided as far as possible?   Yes  No   

16.  Are pressure horns being used?   Yes  No   

17.  Do the vehicles carry adequate containers/trash bags 

for litter/garbage and are they emptied at the 

campsite or other designated location regularly? 

 Yes   No   

18.  Are there any damages caused by project activities to 

canals, watercourses, local roads or other 

infrastructure (where applicable)? 

 Yes  No 

 

19.  If yes, are these damages being repaired/compensated 

as per mutual agreed terms?  Yes  No 

 

20.  Are UEPL’s HSE guidelines being followed?   Yes  No   

21.  Have all other mitigations measures specified in the 

EIA been adhered to?  Yes  No 

 

Name:  Signature: 

    Date: 

Additional Comments 

         

         

         

         

Page 316: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-6 HPK

Checklist for Fuels, Oils and Chemicals 

No.  Description  Status Additional 

Comments 

1.  Do the fuel storage facilities have adequate secondary 

containment up to 125% capacity in case of leakage or 

spillage? 

 Yes   No 

 

2.  Is there any other combustible or flammable material 

in the fuel storage area?  Yes   No 

 

3.  Is regular inspection carried out to check leaks and 

spills?  Yes   No 

 

4.  Have the entire oil and fuel storage areas concrete floor 

underneath to prevent soil contamination from leaks 

or spills? 

 Yes   No 

 

5.  Are the fuel tanks properly marked with their 

contents?  Yes   No 

 

6.  Are the fuel transfer arrangements protected against 

spills?  Yes   No 

 

7.  Are the drip trays/pans being used?   Yes   No   

8.  Are tarpaulin sheets placed under equipment and fuel 

containers that have the potential to spill or drip?  Yes   No 

 

9.  Is the fuel transfer operation being supervised in the 

field?  Yes   No 

 

10.  Are the spills and leaks thoroughly cleaned?   Yes   No   

11.  Are the spilled oil or fuel and used clean‐up material 

being disposed properly?  Yes   No 

 

12.  Are the spills and leaks reported and recorded?   Yes   No   

13.  Is contaminated soil being removed or covered 

following proper clean‐up procedures?  Yes   No 

 

14.  Is the environmental emergency response plane 

available on site?  Yes   No 

 

15.  Is the UEPL’s emergency response plan being followed 

for spills and leaks (moderate or major spills)?  Yes   No 

 

16.  Has all the mitigation measures suggested in the EIA 

been adhered to?  Yes   No 

 

17.  Are UEPL’s HSE guidelines being followed?   Yes   No   

Name:  Signature: 

    Date: 

Additional Comments       

         

         

         

         

Page 317: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-7 HPK

General Environmental Checklist 

No.  Description  Status Additional 

Comments 

1.  Are activities taking place in agricultural or grazing 

areas?   Yes   No 

 

2.  If yes, have compensation amounts being settled as per 

mutual agreed terms or prevailing market rates?  Yes   No 

 

3.  Are permitting staff informing village leaders of 

location and timing of all major activities?  Yes   No 

 

4.  Is a community complaints register being managed 

and maintained?  Yes   No 

 

5.  Are there any damages caused by project activities to 

canals, watercourses, local roads or other 

infrastructure (where applicable)? 

 Yes   No 

 

6.  If yes, are these damages being repaired/compensated 

as per the recommendations of the EIA?  Yes   No 

 

7.  Are the cultural norms being respected by the project 

staff?  Yes   No 

 

8.  Has off‐sets been provided from sites of religious, 

cultural or archeological significance (if found)?  Yes   No 

 

9.  Is trash, wrappers, shopping bags, paper, cans, bottles 

or any other kind of litter being left out in the open?  Yes   No 

 

10.  Have measures been taken to protect the vegetation of 

the area?  Yes   No 

 

11.  Is the HSEO immediately notified of any wildlife 

sightings and are the sightings logged?  Yes   No 

 

12.  Is the “no hunting, no killing, no feeding, no 

harassment, no fishing and no trapping” policy strictly 

enforced? 

 Yes   No 

 

13.  Are any archeological sites or places of cultural or 

religious significance disturbed?  Yes   No 

 

14.  In the event of incidental discoveries of archaeological 

sites, are the contingency measures followed?  Yes   No 

 

15.  Is the “no shortcuts” policy followed?   Yes   No   

16.  Has all the mitigation measures suggested in the EIA 

been adhered to?  Yes   No 

 

17.  Are UEPL’s HSE guidelines being followed?   Yes   No   

Name:  Signature: 

    Date: 

Additional Comments 

         

         

         

         

Page 318: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-8 HPK

Checklist for Restoration and Rehabilitation of Drilling Sites 

No.  Description  Status Additional 

Comments 

General        

1.  Have the erosion control measures been taken where 

needed?  Yes   No 

 

2.  Has the contaminated soil been removed and disposed 

of appropriately?  Yes   No 

 

3.  Have the sites been inspected to ensure the 

recommended restoration measures have been strictly 

adhered to? 

 Yes   No 

 

For Dry or Producing Well       

1.  Has the outer chainlink fence for producing well been 

retained?  Yes   No 

 

2.  Has the wellhead for producing well been enclosed by a 

locked steel cage for further production operations 

work? 

 Yes   No 

 

3.  Has all equipment and machinery at the dry well site 

been  demobilized?  Yes   No 

 

4.  Has all wastes at the well site been disposed of 

properly?  Yes   No 

 

5.  Has liner from the water and waste pits at the dry well 

site been taken out and re‐used or disposed of properly? Yes   No 

 

6.  Have all concrete structures at the dry well site been 

broken and either transported out of the project area by 

the demolition or site restoration contractors for sale or 

reuse or disposed of into the pits? 

 Yes   No 

 

For Campsites, Access Route        

1.  Have the camping sites been restored as close as 

possible to the original condition?  Yes   No 

 

2.  Have the campsites been cleaned, leaving no refuse or 

wastes behind?  Yes   No 

 

3.  Have the routes been restored as close as possible to the 

original condition?  Yes   No 

 

4.  Have all the soak pits and septic tanks been backfilled 

with an extra cap of 1 meter soil on top to cater 

compaction? 

 Yes   No 

 

5.  Are UEPL’s HSE guidelines being followed?   Yes   No   

Name:  Signature:   

    Date:     

Additional Comments 

         

         

         

 

Page 319: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-9 HPK

Checklist for Laying of Seismic Lines 

No.  Description  Status Additional 

Comments 

1. Have photographs been taken to record pre‐survey 

conditions?  Yes  No   

2. Has proper offsets been given from settlements? (if 

any)  Yes  No   

3. Has proper offsets from surface water bodies been 

given? (if any)  Yes  No   

4. Has proper offsets been provided to local water 

sources or other water sources?  Yes  No   

5. Has minimum distances from environmental receptors 

been maintained from wetlands during data 

acquisition? 

 Yes  No   

6. If yes, was it absolutely minimized?   Yes  No   

7. Were any trees felled?   Yes  No   

8. Were any trees or bushes burnt or disposed of?   Yes  No   

9. Has soil erosion been observed as a result of the survey 

related activities?  Yes  No   

10. If yes, are mitigation measures needed?   Yes  No   

11. If yes, have the mitigation measures specified in the 

EIA being adhered to?  Yes  No   

12. Are whitewashed rocks used to mark survey lines?   Yes  No   

13. Are UEPL’s HSE guidelines being followed?   Yes  No   

Name:  Signature: 

    Date: 

Additional Comments 

         

         

         

         

         

Page 320: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-10 HPK

Checklist for Shooting and Recording 

No.  Description  Status Additional 

Comments 

1. Are the holes drilled deeper than required?   Yes  No   

2. Is the hole diameter larger than required?   Yes  No   

3. Are the charges set at the specified depth?   Yes  No   

4. Have the bird nests, small mammals and reptile holes 

and carnivore Dens/caves being avoided during deep 

holes and up holes operation? 

 Yes  No   

5. Is the charge quantity kept to a minimum, according to 

the requirement?  Yes  No   

6. Are deep holes packed with sand before shooting?   Yes  No   

7. Is vegetation clearing avoided for drilling the holes?   Yes  No   

8. Are the shot hole locations restored after the 

recording?  Yes  No   

9. Are all flagging, survey stakes and debris removed 

after the recording?  Yes  No   

10. Is refuse and waste collected and sent to the campsite 

for proper disposal?  Yes  No   

11. Has night traveling been observed?   Yes  No   

12. Has all the mitigation measures suggested in the EIA 

been adhered to?  Yes  No   

13. Are UEPL’s HSE guidelines being followed?   Yes  No   

Name:  Signature: 

    Date: 

Additional Comments 

         

         

         

         

         

Page 321: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 B-11 HPK

Checklist for Restoration & Rehabilitation of Seismic Operation 

No.  Description  Status Additional 

Comments 

1. Have the campsite been restored as close as possible to 

the original condition?  Yes  No   

2. Have the campsite been cleaned, leaving no refuse or 

wastes behind?  Yes  No   

3. Have the routes been restored as close as possible to 

the original condition?  Yes  No   

4. Have the survey lines been restored as close as 

possible to the original condition?  Yes  No   

5. Have all flags, stakes, signs and refuse been removed?   Yes  No   

6. Have all holes and mud pits made for the purpose of 

up holes and deep holes been backfilled and restored?  Yes  No   

7. Have the photographs of the above mentioned 

activities been taken to compare with the pre‐project 

conditions? 

 Yes  No   

8. Have all damages caused to local infrastructure during 

the operation been repaired and restored?  Yes  No   

9. Have the erosion control measures been taken where 

needed?  Yes  No   

10. Has it been ensured that the survey lines do not 

become new routes?  Yes  No   

11. Have the concrete blocks from the explosive storage 

area been removed?  Yes  No   

12. Have all the ditches, soak pits and septic tanks been 

backfilled with an extra cap of 1 meter soil on top to 

cater compaction? 

 Yes  No   

13. Has the contaminated soil been removed and disposed 

of appropriately?  Yes  No   

14. Have the sites been inspected to ensure the 

recommended restoration measures have been strictly 

adhered to? 

 Yes  No   

15. Are UEPL’s HSE guidelines being followed?   Yes  No   

Name:  Signature: 

    Date: 

Additional Comments 

         

         

         

         

         

 

 

Page 322: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

Checklist for Flow Line Laying 

No.  Description  Status Additional 

Comments 

1.  Has the cutting along the slopes been minimized?   Yes   No   

2.  Has the width of RoW been limited to 40 ft to 

minimize clearing of vegetation and disturbance to 

soil? 

 Yes   No 

 

3.  Has the clearing of dense patches of vegetation been 

avoided?  Yes   No 

 

4.  Has clearing for RoW blocked the natural drainage?    Yes   No   

5.  Is tree cutting being minimized?    Yes   No   

6.  Were any trees felled?   Yes   No   

7.  Were any trees or bushes burnt or disposed of?   Yes   No   

8.  Are communities informed before commencing the 

activity close to the settlements?   Yes   No 

 

9  Has soil erosion been observed as a result of the 

construction activities?  Yes   No 

 

10.  Has topsoil of the RoW been stored separately?   Yes   No   

11.  Has topsoil been backfilled ensuring minimum loss of 

topsoil?  Yes   No 

 

12.  Has water used for cleaning and hydro‐testing of flow 

line collected in lined pits?  Yes   No 

 

13.  Are safety measures for locals in place?   Yes   No   

14.  Has RoW for flow line by‐passed major settlements?   Yes   No   

15.  If yes, are mitigation measures needed?   Yes   No   

16.  If yes, have the mitigation measures specified in the 

EIA being adhered to?  Yes   No 

 

17.  Are UEPL’s HSE guidelines being followed?   Yes   No   

Name:  Signature: 

    Date: 

Additional Comments 

         

         

         

         

         

 

Page 323: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 HPK

Appendix C Environmental Aspects Register

Page 324: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-1 HPK

Appendix C – Environmental Aspects Register

The appendix provides an environmental impacts and aspects of the proposed 

exploration and associated development activities mainly comprise of seismic, 

drilling, flow line laying/tie‐ins/wellhead works and establishment/construction of 

processing facilities i.e. GPF/CPP presented in Table C‐2, C‐3, C‐4 and C‐5 

respectively. The register identifies the potential impacts of construction and 

operational activities on various environmental resources. The register also categorizes 

the significance of the impacts on the basis of their severity of consequence and the 

probability of occurrence. The impact significance has been categorized on the basis of 

the following criteria provided in Table C‐1. 

Page 325: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-2 HPK

Table C‐1: Criteria for Environmental Impacts and Aspects for Exploration and Associated Development Activities 

    1  2  3  4  5 

Frequency 

E           

D           

C           

B           

A           

    1  2  3  4  5 

    Consequence 

  Low 

  Tolerable (If ALARP) 

  Intolerable 

   

Environmental Risk Scoring ‐ Consequence

Massive environmental damage in an extended  area outside the boundaries 

Extensive actions of remediation/restoration are required 

Extended breaches of regulations, complaints of international concern 

Major environmental damage  within an large area outside the boundaries 

Major actions for remediation/restoration are required 

Major breaches of regulations, complaints of national concern 

3  Medium environmental damage within a large area outside the boundaries 

Medium actions for remediation/restoration are required 

Page 326: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-3 HPK

Repeated breaches of regulations, complaints of local/regional concern 

 Low environmental damage within a limited area outside the boundaries / Medium environmental damage within the 

boundaries 

Actions for clean‐up are required 

Occasional breaches of regulations, complaints of local concern 

1  Negligible environmental damage within the boundaries 

Actions for clean‐up may be required 

   

Environmental Risk Scoring ‐ Frequency 

E  Frequent ‐ happens several times per year in a location 

D  Probable ‐ happens several times per year in our Company 

C  Seldom ‐ happens once per year in our Company 

B  Unlikely ‐ heard of in our industry 

A  Improbable ‐ never heard of in our industry 

Page 327: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-4 HPK

Table C‐2: Environmental Aspect Register for Seismic Activities 

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

1  Land 

acquisition 

Loss of 

vegetation/crops/tree

Public grievances  N  Land Acquisition 

Act, 1894 

  Equitable disbursement of 

compensation amounts after 

mutual agreement of both 

parties 

Manage and maintain a 

community complaints 

register 

Acceptable      

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

2  Diesel storage 

at site 

Fire due to ignition 

of spilled diesel 

Air Pollution 

(SOx, NOx, Acid 

rain, Global 

warming) 

E  Commitments in 

EIA/EMP of 

particular area 

  Spill control Plans 

No smoking at site 

Inspection of secondary 

containments 

SOP of diesel filling 

procedure 

Acceptable  Training of 

staff at site 

regarding 

Site 

Emergency 

Response 

Plans 

 

           

 

Evaluate Risk 

2  D 

Tolerable (if 

ALARP)

 

‐  ‐ 

 

‐ 

Diesel spill from 

diesel storage tanks 

and from power 

generation 

equipment 

Land 

contamination 

and water aquifer 

deterioration 

A  Commitments in 

EIA/EMP of 

particular area 

  Secondary containment 

around diesel tank 

Liner under the power 

engines 

Routine inspections 

Acceptable 

  

 

1  1  1  2  2  7 

           

‐  ‐ 

 

‐ 

3  Equipment and 

crew 

mobilization 

and 

demobilization 

Dust and vehicular 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standard, 

2016 

  Regulate and monitor 

vehicles speed 

Maintain vehicles in a good 

working condition  

Avoid off‐road travel  

Conduct vehicle and 

equipment emission testing 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Noise and vibration  Noise pollution  N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standard, 

2016 

  Minimize use of horns by 

project vehicles  

Use of pressure horns will 

not be allowed 

Conduct noise monitoring of 

noise emitting vehicles and 

equipment 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Driving practices  Safety hazards – 

locals  

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

  Train drivers in responsible 

and safe driving practices 

Observe and maintain 

minimum/safe distances 

from local communities  

Avoid night travelling unless 

required in case of an 

emergency 

Acceptable     

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

4  Construction/ 

Improvement 

of access tracks 

Land clearing  Soil erosion  N  Commitments in 

EIA/EMP of 

particular area 

  Minimize preparation of new 

access tracks  

Width of existing tracks 

development or 

improvements will be kept to 

a minimum 

Restrict movement of 

personnel and construction 

Acceptable     

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 328: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-5 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

equipment to work areas 

only  

Maintain photographic 

records of all activities to 

monitor any changes and soil 

conditions 

Train drivers on mitigation 

measures related to off‐road 

travel  

Avoid off‐road travel 

Maximize usage of existing 

tracks 

    Handling of fuel, oil 

and chemicals 

Soil and water 

contamination 

N  Hazardous 

Substances Rules, 

2014 

  Vehicles will be daily 

checked for fuel or oil leaks 

Fuel and oil transfer 

operations will be done using 

a dedicated fuel vehicle  

Drip pans will be used to 

avoid drips and spills  

Procedure for transfer shall 

be developed and 

implemented 

Acceptable 

  

 

2  1  1  2  2  8 

           

‐  ‐ 

 

‐ 

  Use of horns/ 

improperly 

maintained 

machinery 

Noise pollution  N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standards, 

2016 

  Minimize use of horns by 

project vehicles  

Use of pressure horns will 

not be allowed 

Properly maintain vehicles 

and construction equipment 

Restrict all project vehicles 

and personnel within work 

areas 

Conduct noise monitoring 

Acceptable 

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Dust and vehicular 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standards, 

2016 

  Regulate and monitor 

vehicles speed  

Minimize dust emissions by 

employing good 

management practices 

Avoid off‐road travel   

Train drivers on mitigation 

measures related to off‐road 

travel and speed limits 

Acceptable 

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Loss of vegetation/ 

crops 

Soil erosion/loss 

of habitat 

N  The Forest Act, 

1927 

  Minimize vegetation 

clearance  

Prohibit use of local 

vegetation as fuel  

Minimize preparation of new 

access tracks  

Width of existing tracks 

development or 

improvements will be 

minimized 

Avoid clearing of trees  

Acceptable 

  

 

2  2  3  2  2  11 

           

‐  ‐ 

 

‐ 

Page 329: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-6 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Access tracks should avoid 

passing through the areas 

with dense vegetation 

  Land acquisition for 

access tracks 

Loss of habitat  N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments 

2001, Sindh 

Environmental 

Protection Act, 

2014 

  Minimize total land uptake 

by access roads  

Width of existing tracks 

development or 

improvements will be 

minimized 

Access tracks should avoid 

passing through the areas 

with dense vegetation 

Avoid clearing of trees  

Use single approved track 

during construction 

Acceptable 

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

  Driving practices/ 

Resource utilization 

Safety hazards 

and disturbance 

to communities 

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

  Train drivers on mitigation 

measures related to off‐road 

travel and speed limits  

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

Manage and maintain a 

community complaints 

register  

Local sources of drinking 

water will be used only after 

complying with relevant 

requirements of the EIA/EMP 

Repair any damage caused 

by project activities to local 

infrastructure  

Observe strict compliance 

with UEPL’s HSE guidelines 

Project staff to respect all 

cultural norms 

Provide offsets from sites of 

religious, cultural or 

archaeological significance 

Acceptable 

  

 

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

  Vegetation clearing/ 

Vehicular movement 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

  Prohibit hunting, fishing, 

trapping or harassment, 

killing or feeding of wildlife  

Minimize preparation of new 

access tracks  

Width of existing tracks 

development or 

improvement will be 

minimized 

Select routes with minimum 

vegetation clearing 

Avoid dense patches of 

vegetation 

Maintain construction 

vehicles and equipment  

Acceptable 

  

 

2  2  2  2  3  11 

           

‐  ‐ 

 

‐ 

Page 330: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-7 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Minimize time period of 

operation near surface water 

bodies (especially which are 

breeding areas)  

Monitor impacts of the 

individual project on wildlife 

species 

Access tracks should avoid 

passing through the areas 

with dense vegetation 

5  Camp/s 

construction/ 

Establishment/ 

Operation 

Vegetation clearing  Soil erosion/ 

Physical scarring 

N  The Forest Act, 

1927 

  Minimize vegetation clearing 

Avoid cutting of trees 

Locate campsite in existing 

clearings and on levelled 

land 

Minimize cut and fill as 

much as possible 

Minimize total land uptake 

by the camps  

Maintain photographic 

records of all activities to 

monitor any changes in soil 

conditions 

Campsites will be located 

outside of the boundaries of 

areas with dense vegetation 

Acceptable 

  

 

2  1  2  2  2  9 

           

‐  ‐ 

 

‐ 

  Waste management/ 

Handling of fuels, 

oils and chemicals 

Soil/Water 

contamination 

N  Sindh 

Environmental 

Protection Act, 

2014 

Hazardous 

Substances Rules, 

2014 

  Dispose sewage generated at 

the campsite in septic system 

comprising septic tanks and 

soak pits 

Dispose wastewater from 

laundry, kitchen washings 

and showers into separate 

soak pits  

Build soak pits in absorbent 

soil  

Keep septic system at 

minimum distances of 300 m 

from surface water sources or 

groundwater wells 

Design and construct soak 

pits to prevent surface runoff 

Design soak pits to 

accommodate wastewater 

generated during the total 

duration of the operation 

In case the soak pits get filled 

during the operation, grey 

water will be transferred to 

nearest municipal drains 

Sprinkling of wastewater will 

not be allowed 

Acceptable 

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 331: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-8 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Solid wastes at the campsite 

will be stored temporarily on 

site for onward supply to a 

waste contractor  

Wash vehicles in designated 

areas within campsite 

Regularly check vehicles for 

fuel or oil leaks 

All fuel and oil storage areas 

will have a concrete pad 

underneath to prevent soil 

contamination in case of 

leaks or spills 

All fuel tanks will be 

properly marked to highlight 

their contents 

Fuel and oil storage areas 

will have secondary 

containment in the form of 

concrete or brick masonry 

bunds 

Ensure provisions for proper 

fuel and oil storage and 

handling 

  Dust/Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standards, 

2016 

  Maintain vehicles and 

equipment in good condition 

Select campsite locations at 

least 300 m away from 

communities 

Employ good management 

practice to minimize dust 

emissions 

Acceptable 

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Use of horns/ 

Improper maintained 

machinery 

Noise and 

vibration 

N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standards, 

2016 

  Ensure that generators, 

vehicles and other potentially 

noisy equipment are in good 

condition 

Select campsite location at 

least 300 m away from 

communities 

Minimize use of horns by 

project vehicles  

Use of pressure horns will 

not be allowed 

Restrict all project vehicles 

and personnel within work 

areas 

Acceptable 

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Resource utilization  Resource 

depletion and 

water pollution 

N  Sindh 

Environmental 

Protection Act, 

2014 

  Prohibit use of water from 

surface water bodies  

Employ prudent water 

conservation measures  

Keep complete records of 

water consumption during 

project 

Acceptable 

  

 

2  3  2  2  2  11 

           

‐  ‐ 

 

‐ 

Page 332: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-9 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Obtain water required for 

seismic and construction 

operation from local wells,  

existing or new UEPL water 

wells in the area 

Install (if required) new 

water wells 300 m from 

existing local wells  

Abstract water from deep 

aquifer 

Water from a local well will 

only be used after ensuring 

that the available capacity at 

the tube well (safe yield 

minus local demand) is at 

least 50% greater than the 

project demand 

Abstraction of water for 

seismic operation, from 

irrigation network will only 

be used after getting 

approval from irrigation 

department 

Noise and vibration/ 

Waste disposal 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

  Prohibit hunting, fishing, 

trapping, killing, feeding or 

harassment of wildlife  

Select campsite locations 300 

m from surface water bodies 

Avoid clearing of dense 

patches of vegetation  

Food wastes will not be left 

in the open and shall be 

buried 

Maintain compressors and 

vehicles in good condition 

Monitor impacts of the 

individual projects on 

wildlife species 

Acceptable 

  

 

2  3  3  3  3  14 

       

 

 

‐  ‐ 

 

‐ 

6  Clearing and 

levelling of 

seismic lines 

Vegetation clearing  Soil erosion/ 

Physical scarring 

N  The Forest Act, 

1927 

  Minimize vegetation 

clearance  

Avoid cutting of trees 

Maintain photographic 

records of all activities to 

monitor any changes in soil 

conditions  

Minimize disturbance to 

natural topography and soils  

Regulate and monitor 

vehicles speed  

Avoid off‐road travel 

Train drivers on mitigation 

measures related to off‐road 

travel and speed limits 

Acceptable 

  

 

2  2  1  2  2  9 

       

 

 

‐  ‐ 

 

‐ 

Page 333: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-10 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Waste disposal/ 

Handling of fuel, oils 

and chemicals 

Soil and water 

contamination 

N  Sindh 

Environmental 

Protection Act, 

2014 

Hazardous 

Substances Rules, 

2014 

  Prohibit solid waste disposal 

in the field 

Regularly check vehicles for 

fuel or oil leaks 

Use a dedicated fuel vehicle 

for fuel and oil transfer 

operation  

Use drip pans to avoid drips 

and spills  

The soil contaminated from 

minor and moderate spills 

will be removed and sent to 

waste contractor for 

appropriate disposal e.g. 

incineration or can be 

disposed of in accordance to 

best industrial guidelines 

Acceptable 

  

 

2  1  2  2  2  9 

       

 

 

‐  ‐ 

 

‐ 

Use of horns/ 

Improperly 

maintained 

machinery 

Noise pollution/ 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

 

  Minimize use of horns by 

project vehicles  

The use of pressure horns 

will not be allowed  

Restrict  movement of 

personnel and construction 

equipment within work areas  

Acceptable 

  

 

2  2  1  2  2  9 

       

 

 

‐  ‐ 

 

‐ 

  Dust/Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standards, 

2016 

 

  Maintain vehicles in good 

condition 

Dust emissions during line 

clearance activities will be 

minimized by good 

management practices 

Minimize dust emissions by 

employing good 

management practices 

Conduct vehicle and 

equipment emission testing 

Acceptable 

  

 

2  2  1  2  2  9 

       

 

 

‐  ‐ 

 

‐ 

Loss of vegetation  Loss of habitat  N  The Forest Act, 

1927 

  Minimize clearing of 

vegetation  

Prohibit use of local 

vegetation as fuel by crew 

personnel  

Avoid clearing of trees 

Acceptable 

  

 

2  2  2  2  3  11 

       

 

 

‐  ‐ 

 

‐ 

Page 334: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-11 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Waste disposal/ 

Vehicular movement 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

  Prohibit hunting, fishing, 

trapping, killing, feeding or 

harassment of wildlife  

Minimize vegetation clearing 

and land uptake  

Avoid clearing of dense 

patches of vegetation 

Food wastes will not be left 

in the open and shall be 

buried 

Maintain minimum distances 

of 50 m from the canals and 

wetlands during line clearing 

Maintain vehicles in good 

condition to reduce noise 

Minimize time period of 

operation near surface water 

bodies (especially which are 

breeding areas) by good 

management practices  

Monitor impacts of the 

individual project on wildlife 

species 

Acceptable 

  

 

2  2  2  2  3  11 

       

 

 

‐  ‐ 

 

‐ 

  Driving practices/ 

Resource utilization 

Safety hazards 

and disturbance 

to communities 

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

Train drivers on mitigation 

measures related to off‐road 

travel and speed limits  

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

Manage and maintain 

community complaints 

register  

Local sources of drinking 

water will be used only after 

complying with relevant 

requirements of the EIA/EMP 

Repair any damage caused 

by project activities to local 

infrastructure  

Observe strict compliance 

with UEPL HSE guidelines 

Project staff to respect 

cultural norms 

Provide offsets from sites of 

religious, cultural or 

archaeological significance 

Acceptable 

   1  2  1  2  2  8 

     

  ‐  ‐  ‐ 

Page 335: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-12 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

7  Seismic survey 

and data 

acquisition 

Disturbance to 

communities and 

resource utilization 

Safety hazards 

and community 

complaints 

N  Commitments in 

EIA/EMP of 

particular area 

  Train drivers on mitigation 

measures related to off‐road 

travel and speed limits  

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

Manage and maintain 

community complaints 

register  

Local sources of drinking 

water will be used only after 

complying with relevant 

requirements of the EIA/EMP 

Repair any damage caused 

by project activities to local 

infrastructure  

Observe strict compliance 

with UEPL HSE guidelines 

Project staff to respect 

cultural norms 

Provide offsets from sites of 

religious, cultural or 

archaeological significance 

Water sources currently 

being used for irrigation by 

the resident communities 

will be exploited only after 

complying with relevant 

requirements of the EIA/EMP 

Maintain effective 

communication channels 

with local communities to 

inform them about the 

progress of various project 

activities 

Acceptable 

  

 

1  1  1  2  2  7 

       

 

 

‐  ‐ 

 

‐ 

Page 336: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-13 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

  Waste disposal/ 

Equipment handling 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

 

 

 

  Prohibit hunting, fishing, 

trapping, feeding, killing or 

harassment of wildlife  

Avoid disturbance to live 

bird nests, reptiles and small 

mammal holes during 

seismic deep holes and 

upholds drilling 

Food wastes will not be left 

in the open and shall be 

buried 

A minimum distance of 100 

m to be maintained from the 

canals and wetlands  

Maintain compressors and 

vehicles in good condition  

Minimize time period of 

operation near surface water 

bodies (especially which are 

breeding areas) by good 

management practices 

Monitor impacts of 

individual project on wildlife  

All the waste from site shall 

be collected and properly 

managed at campsite 

Acceptable 

  

 

2  2  2  3  3  12 

       

 

 

‐  ‐ 

 

‐ 

  Noise and vibration  Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

 

 

 

  Minimize the use of horns by 

project vehicles   

The use of pressure horns 

will not be allowed 

Restrict movement of all 

project vehicles and 

personnel within work areas 

All vehicles and equipment 

shall be properly tuned and 

maintained 

Noise measurement shall be 

carried out of all noisy 

equipment and vehicles 

Acceptable 

  

 

2  2  2  2  2  10 

       

 

 

‐  ‐ 

 

‐ 

  Dust/ Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

Environmental 

Quality Standards, 

2016 

  Maintain vehicles in good 

condition 

Minimize dust emissions by 

good management practices 

Regulate vehicles speed  

Vehicles to be properly tuned 

Conduct emission 

monitoring as per applicable 

laws and regulations 

Acceptable 

  

 

2  2  2  2  2  10 

       

 

 

‐  ‐ 

 

‐ 

Page 337: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-14 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

  Waste management/ 

Handling of fuels, 

oils and chemicals 

Soil 

contamination 

N  Sindh 

Environmental 

Protection Act, 

2014 

Hazardous 

Substances Rules, 

2014 

  No solid waste will be 

disposed of in the field 

Regularly check vehicles for 

fuel and oil leaks 

Use dedicated vehicle for fuel 

and oil transfer 

The soil contaminated from 

minor and moderate spills 

will be removed and sent to 

waste contractor for 

appropriate disposal e.g. 

incineration or can be 

disposed in accordance to the 

best industrial guidelines 

Acceptable 

  

 

2  2  3  2  2  11 

       

 

 

‐  ‐ 

 

‐ 

  Loss of vegetation  Soil 

erosion/Public 

grievance 

N  The Forest Act, 

1927 

  Avoid cutting of trees  

Prohibit use of local 

vegetation as fuel  

Contain crew personnel 

within work areas  

Camps shall be established in 

existing cleared land 

Acceptable 

  

 

2  2  3  3  3  13 

       

 

 

‐  ‐ 

 

‐ 

  Resource utilization  Water pollution/ 

Resource 

depletion 

N  Sindh 

Environmental 

Protection Act, 

2014 

  Prohibit use of water from 

surface water bodies  

Employ prudent water 

conservation measures  

Keep complete records of 

water consumption during 

project 

Obtain water required for 

seismic and construction 

operation from local wells, 

existing or new UEPL water 

wells in the area 

Water from a local well will 

only be used after ensuring 

that the available capacity at 

the tube well (safe yield 

minus local demand) is at 

least 50% greater than the 

project demand 

Acceptable 

  

 

2  3  2  2  2  11 

       

 

 

‐  ‐ 

 

‐ 

  Vehicular/Machinery 

movement 

Soil erosion/ 

Physical scarring 

N  Commitments in 

EIA/EMP of 

particular area 

  Maintain photographic 

records of all activities to 

monitor any changes in soil 

conditions  

Regulate vehicles speed 

Avoid off‐road travel  

Train drivers on mitigation 

measures related to off‐road 

travel and speed limits 

Acceptable 

  

 

1  2  1  2  2  8 

       

 

 

‐  ‐ 

 

‐ 

8  Waste 

management 

Improper disposal of 

waste/Handling of 

fuel, oil and 

chemicals 

Soil and water 

contamination 

N  Sindh 

Environmental 

Protection Act, 

2014 Sindh 

  Dispose sewage generated at 

the campsite in septic system 

comprising of septic tanks 

and soak pits 

Acceptable 

  

 

2  2  3  2  2  11 

           

‐  ‐ 

 

‐ 

Page 338: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-15 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Environmental 

Quality Standard, 

2016 

Hazardous 

Substance Rules, 

2014 

Dispose wastewater from 

laundry, kitchen washings, 

and showers into separate 

soak pits 

Build soak pits in absorbent 

soil  

Ensure that the soak pits 

remain covered all the time 

and measures are taken to 

prevent entry of rainwater 

into them 

Design soak pits to 

accommodate wastewater 

generated during the total 

duration of the operation 

In case the soak pits get filled 

during the operation, grey 

water will be transferred and 

disposed in nearest 

municipal drains with prior 

approval of concerned 

authorities 

Sprinkling of wastewater will 

not be allowed 

No solid waste will be 

disposed of in the field 

Recycle non‐combustible 

waste 

Burry all food waste properly 

and shall not be left in open 

Send combustible (except 

food waste) to waste 

contractor 

Wash vehicles in designated 

areas within campsite 

Check vehicles for fuel or oil 

leaks 

All fuel and oil storage areas 

will have a concrete pad 

underneath to prevent soil 

contamination in case of 

leaks or spills 

All fuel tanks will be 

properly marked to highlight 

their contents 

Fuel and oil storage areas 

will have secondary 

containment in the form of 

concrete or brick masonry 

bunds 

Use dedicated vehicles for 

fuel and oil transfer 

operations 

Page 339: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-16 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Use drip pans to avoid drips 

and spills  

Check fuel tanks for leaks  

The soil contaminated from 

minor and moderate spills 

will be removed and sent to 

waste contractor for 

appropriate disposal e.g. 

incineration or can be 

disposed of in accordance to 

the best industrial guidelines 

A spill prevention and 

contingency plan will be 

prepared to deal with 

moderate and major spills 

Ensure provisions for proper 

fuel and oil, storage and 

handling  

Recycle used oil and vehicle 

related waste  

Bentonite mud used for the 

purpose of uphold and deep 

holes drilling will be 

prepared in rig tank  

Restore upholds and deep 

holes 

Incinerate all medical wastes 

Maintain generators, 

compressors and vehicles in 

good condition 

Minimize dust emissions by 

good management practices 

9  Community 

issues 

Vegetation clearing/ 

Loss of standing 

crops 

Soil 

erosion/Public 

grievance 

N  The Forest Act, 

1927 

  Manage and maintain a 

community complaints 

register 

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

UEPL contractors will 

employ local residents 

during the project activities 

Water sources currently 

being used for irrigation by 

the resident communities 

will be exploited only after 

complying with relevant 

requirements of the EIA/EMP 

Local sources of drinking 

water will be used only after 

complying with relevant 

requirements of the EIA/EMP 

Acceptable 

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 340: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-17 HPK

No 

Detailed Description of the Aspect – Impact   

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description 

of Aspect 

(source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, 

wildlife or natural 

f?

Is there the potential to 

create an 

environmental 

libili

?

Is there the potential to 

dam

age the 

Compan

y’s 

reputation? 

Does the 

Size or 

Nature of 

the 

scenario 

present an environment 

issue in its 

own right? 

If >5 the 

aspect is significant 

 

Evaluate 

Environmental 

Risk

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required 

for Significant 

Environmental 

Aspects 

Flow of water in canal or 

water crossings will not be 

impeded 

Repair any damage caused 

by project activities to canals, 

watercourses, local roads or 

other infrastructure  

Strict compliance will be 

observed to UEPL HSE 

guidelines 

Train drivers in responsible 

and safe driving practices 

Inform local communities 

about the progress of various 

project activities 

Respect cultural norms 

Provide appropriate offsets 

from sites of religious, 

cultural or archaeological 

significance 

10  Restoration  General  Public grievances/ 

Wildlife 

protection/Waste 

management/ 

Safety hazards 

N  Commitments in 

EIA/EMP of 

particular area 

  Restore soak pits after project 

completion 

Ensure that after restoration 

activities the campsite is 

clean and that no refuse has 

been left behind 

Remove all concrete 

structures  

Remove all pin flags, signs, 

and refuse from seismic lines 

Restore upholds and deep 

holes 

Acceptable 

  

 

1  2  2  2  2  9 

           

‐  ‐ 

 

‐ 

11  Explosive 

Camp 

Construction 

General  Public grievances/ 

Wildlife 

Protection/Waste 

management/ 

Safety hazards 

N  Commitments in 

EIA/EMP of 

particular area 

  Excavation as per 

requirement, material for its 

restoration Ensure distance 

from local population and 

wildlife  

Restore properly with same 

excavated material 

Acceptable 

  

 

1  2  2  2  2  9 

           

‐  ‐ 

 

‐ 

N = Normal; A = Abnormal; E = Emergency                     

Page 341: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-18 HPK

Table C‐3: Environmental Aspect Register for Drilling and Associated Construction Activities 

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

1  Land acquisition  Vegetation clearing/ 

Loss of standing crops 

Public grievances  N  Land Acquisition 

Act, 1894 

  Equitable disbursement of 

compensation amounts as per 

mutual agreement of both 

parties 

Manage and maintain a 

community complaints register 

Acceptable      

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

2  Equipment and 

crew 

mobilization and 

demobilization 

Dust and vehicular 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Regulate and monitor vehicles 

speed 

Maintain vehicles in a good 

condition  

Avoid off‐road travel 

Conduct vehicle and 

equipment emission testing 

Acceptable 

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Noise and vibration  Noise pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Minimize use of horns by 

project vehicles  

The use of pressure horns will 

not be allowed 

Conduct noise monitoring of 

noise emitting vehicle and 

equipment 

Acceptable 

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Driving Practices  Safety hazards – 

locals  

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

  Train drivers in responsible 

and safe driving practices 

Observe and maintain 

minimum/safe distances from 

local communities  

Avoid night travelling unless 

required in case of an 

emergency 

Acceptable 

  

 

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

3  Construction/ 

Improvement of 

access tracks 

Land clearing  Soil erosion  N  EIA/EMP 

Commitments 

  Minimize preparation of new 

access tracks 

Width of existing tracks 

development or improvements 

will be kept to a minimum 

Restrict movement of 

personnel and construction 

equipment to work areas only 

Maintain photographic records 

of all activities to monitor any 

changes and soil conditions 

Train drivers on mitigation 

measures related to off‐road 

travel  

Avoid off‐road travel 

Maximize usage of existing 

tracks  

Access track to the well site 

will be properly compacted 

Acceptable 

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 342: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-19 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

    Handling of fuel, oil 

and chemicals 

Soil and water 

contamination 

N  Hazardous 

Substances Rules, 

2014 

  Vehicles will be daily checked 

for fuel or oil leaks 

Fuel and oil transfer operations 

will be done using a dedicated 

fuel vehicle 

Drip pans will be used to 

avoid drips and spills 

Concrete pad will be 

constructed for refuelling of 

vehicles at drilling site 

Procedure for transfer of fuel 

or oil shall be developed and 

implemented 

Oil spill drill will be carried 

out on regular interval to cater 

with emergency situation 

Acceptable

  

 

2  1  1  2  2  8 

           

‐  ‐ 

 

‐ 

  Use of horns/ 

Improperly 

maintained machinery 

and vibration 

Noise Pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Minimize use of horns by 

project vehicles  

Use of pressure horns will not 

be allowed 

Properly maintain vehicles and 

construction equipment 

Restrict all project vehicles and 

personnel within work areas 

Conduct noise monitoring 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Dust and vehicular 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Regulate and monitor vehicles 

speed 

Minimize dust emissions by 

employing good management 

practices 

Avoid off‐road travel   

Train drivers on mitigation 

measures related to off‐road 

travel and speed limits 

Sprinkling to be carried out to 

avoid dust emission 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Loss of vegetation  Soil erosion/ 

Damage to habitat 

N  The Forest Act, 1927    Minimize vegetation clearance  

Prohibit use of local vegetation 

as fuel  

Minimize preparation of new 

access tracks  

Width of the access track to the 

well site will not exceed 5.5 m 

Width of existing tracks 

development or improvements 

will be minimized 

Avoid clearing of trees 

Access tracks should avoid 

passing through the areas with 

dense vegetation 

Acceptable

  

 

2  2  3  2  2  11 

           

‐  ‐ 

 

‐ 

Page 343: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-20 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

  Land acquisition for 

access tracks, well site 

and campsite 

Loss of habitat  N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

Sindh 

Environmental 

Protection Act, 2014 

  Avoid clearing of trees 

Use single approved track 

during construction 

Width of the access track to the 

well site will not exceed 5.5 m 

Minimize total land uptake by 

access roads, well sites and 

campsites 

Width of existing tracks 

development or improvements 

will be minimized 

Access tracks should avoid 

passing through the areas with 

dense vegetation 

Acceptable

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

  Driving practices/ 

Resource utilization 

Safety hazards and 

disturbance to 

communities 

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

  Train drivers on mitigation 

measures related to off‐road 

travel and speed limits 

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

Manage and maintain a 

community complaints register 

Local sources of drinking 

water will be used only after 

complying with relevant 

requirements of the EIA/EMP 

Repair or compensate any 

damage caused by project 

activities to local infrastructure 

Observe strict compliance with 

UEPL HSE guidelines 

Project staff to respect all 

cultural norms 

Provide offsets will from sites 

of religious, cultural or 

archaeological significance 

Acceptable

  

 

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

  Vegetation clearing/ 

Vehicular movement 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

  Prohibit hunting, fishing, 

trapping, killing, feeding or 

harassment of wildlife  

Minimize preparation of new 

access tracks  

Width of existing tracks 

development or improvement 

will be minimized 

Select routes with minimum 

vegetation clearing 

Avoid dense patches of 

vegetation 

Maintain construction vehicles 

and equipment  

Minimize time period of 

operation near surface water 

Acceptable

  

 

2  2  2  2  3  11 

           

‐  ‐ 

 

‐ 

Page 344: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-21 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

bodies (especially which are 

breeding areas)  

Monitor impacts of the 

individual project on wildlife 

species 

Access tracks should avoid 

passing through the areas with 

dense vegetation 

Avoid night travelling unless 

required in case of an 

emergency 

4  Camp & well 

site construction/ 

Establishment/ 

Operation 

 

Vegetation clearing  Soil erosion/ 

Physical scarring 

N  The Forest Act, 1927    Minimize vegetation clearing 

Avoid cutting of trees  

Locate well site and campsites 

in existing clearing and on 

levelled land 

Avoid cut and fill as much as 

possible 

Minimize total land uptake by 

the well site and camps  

Maintain photographic records 

of all activities to monitor any 

changes in soil conditions 

Stockpiles will be located 

downwind during well site 

construction 

Campsites will be located 

outside the boundaries of areas 

with dense vegetation 

Acceptable

  

 

2  1  2  2  2  9 

           

‐  ‐ 

 

‐ 

  Waste management/ 

Handling of fuels, oils 

and chemicals 

Soil/Water 

contamination 

N  Sindh 

Environmental 

Protection Act, 2014 

Hazardous 

Substances Rules, 

2014 

  Dispose sewage generated at 

the campsite in septic system 

comprising of septic tanks and 

soak pits 

Dispose wastewater from 

laundry, kitchen washings and 

showers into separate soak pits 

Build soak pits in absorbent 

soil  

Keep septic system at 

minimum distances of 300 m 

from surface water sources or 

groundwater wells 

Design and construct soak pits 

to prevent surface runoff 

Design soak pits to 

accommodate wastewater 

generated during the total 

duration of the operation 

In case the soak pits get filled 

during the operation, grey 

water will be transferred and 

disposed into the nearest 

Acceptable

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 345: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-22 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

municipal drains with the 

prior approval of concerned 

authorities  

Sprinkling of wastewater will 

not be allowed 

Solid wastes at the campsite 

will be stored temporarily on 

site for onward supply to a 

waste contractor 

Burning of waste will not be 

allowed  

Wash vehicles in designated 

areas within campsite 

Regularly check vehicles for 

fuel or oil leaks 

All fuel and oil storage areas 

will have a concrete pad 

underneath to prevent soil 

contamination in case of leaks 

or spills 

All fuel tanks will be properly 

marked to highlight their 

contents 

Fuel and oil storage areas will 

have secondary containment in 

the form of concrete or brick 

masonry bunds 

Ensure provisions for proper 

fuel and oil storage and 

handling 

Ensure preparation of a spill 

prevention and contingency 

plan 

Ensure provisions of a HDPE 

liner for the waste pits at the 

well site 

  Dust/Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Maintain vehicles and 

equipment in good condition 

Select well site and campsite 

locations at least 300 m away 

from communities 

Employ good management 

practice to minimize dust 

emissions 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Use of horns/ 

Improperly 

maintained machinery 

Noise and 

vibration 

N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Ensure that generators, 

vehicles and other potentially 

noisy equipment are in good 

condition 

Select well site and campsite 

locations at least 300 m away 

from communities 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Page 346: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-23 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Minimize use of horns by 

project vehicles  

Use of pressure horns will not 

be allowed 

Restrict all project vehicles and 

personnel within work areas 

  Resource utilization  Water pollution/ 

Resource depletion 

N  Sindh 

Environmental 

Protection Act, 2014 

  Use of water from surface 

water bodies is prohibited 

Employ prudent water 

conservation measures  

Keep complete records of 

water consumption during 

project 

Obtain water required 

construction and drilling 

operation from local wells 

(close to Irrigation canal), 

existing or new UEPL water 

wells in the area 

Install (if required) new water 

wells 300 m from existing local 

wells  

Abstract water from deep 

aquifer 

Water from a local well will 

only be used after ensuring 

that the available capacity at 

the tube well (safe yield minus 

local demand) is at least 50% 

greater than the project 

demand 

Abstraction of water for 

drilling operation, from 

irrigation network will only be 

used after getting approval 

from irrigation department 

Pay appropriate compensation 

for the amount of water 

abstracted to the well owners 

Acceptable

  

 

2  3  2  2  2  11 

           

‐  ‐ 

 

‐ 

Page 347: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-24 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Noise and vibration/ 

Waste disposal 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001  

 

 

 

  Prohibit hunting, fishing, 

trapping, killing, feeding or 

harassment of wildlife  

Select campsite locations 300 m 

from surface water body  

Avoid clearing of dense 

patches of vegetation  

Food wastes will not be left in 

the open and shall be buried 

Maintain vehicles and 

equipment in good condition 

Monitor impacts of the 

individual project on wildlife 

species 

Avoid night travel unless 

required in case of an 

emergency 

Acceptable

  

 

2  3  3  3  3  14 

       

 

 

‐  ‐ 

 

‐ 

5  Waste 

management 

Improper disposal of 

waste/Handling of 

fuel, oil & chemicals 

Soil and water 

contamination 

N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

Hazardous 

Substances Rules, 

2014 

 

  Dispose sewage generated in 

septic system comprising 

septic tanks and soak pits 

Dispose wastewater from 

laundry, kitchen washings and 

showers into separate soak pits 

Build soak pits in absorbent 

soil  

Ensure that the soak pits 

remain covered all the time 

and measures are taken to 

prevent entry of rainwater into 

them 

Design soak pits to 

accommodate wastewater 

generated during the total 

duration of the operation 

In case the soak pits get filled 

during the operation, grey 

water will be transferred and 

disposed into nearest 

municipal drains with the 

prior approval of concerned 

authorities 

Sprinkling of wastewater will 

not be allowed 

No solid waste will be 

disposed of in the field 

Recycle non‐combustible waste 

Burry all food waste properly 

Send combustible waste 

(except food waste) to waste 

contractor 

Burning of waste will be 

prohibited 

Acceptable

  

 

2  1  2  2  2  9 

           

‐  ‐ 

 

‐ 

Page 348: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-25 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Wash vehicles in designated 

areas within campsite 

Check vehicles for fuel or oil 

leaks 

All fuel and oil storage areas 

will have a concrete pad 

underneath to prevent soil 

contamination in case of leaks 

or spills 

All fuel tanks will be properly 

marked to highlight their 

contents 

Fuel and oil storage areas will 

have secondary containment in 

the form of concrete or brick 

masonry bunds 

Use dedicated vehicles for fuel 

and oil transfer operations 

Use drip pans to avoid drips 

and leaks 

Check fuel tanks for leaks or 

spills 

The soil contaminated from 

minor and moderate spills will 

be removed and sent to waste 

contractor for appropriate 

disposal e.g. incineration or 

can be disposed of in 

accordance to the best 

industrial guidelines 

A spill prevention and 

contingency plan will be 

prepared to deal with 

moderate and major spills 

Ensure provisions for proper 

fuel and oil, storage and 

handling  

Recycle used oil and vehicle 

related waste  

Incinerate all clinical wastes 

Maintain vehicles and other 

equipment  in good condition 

6  Community 

issues 

Land acquisition/ 

Vegetation clearing/ 

Loss of standing crops 

Public grievances  N  The Forest Act, 1927    Manage and maintain a 

community complaints register 

Comply with all EIA/EMP 

mitigations related to waste, 

noise and dust emissions 

UEPL contractors will employ 

local residents during the 

project activities 

Acceptable

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 349: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-26 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Local residents living closest to 

the project location will be 

given priority in the 

employment process subject to 

company selection criteria 

Groundwater sources 

currently being used for 

irrigation by the resident 

communities will be exploited 

only after complying with 

relevant requirements of the 

EIA/EMP 

7  Fire and 

explosion at 

drilling rig 

derrick 

 

Release of raw gas 

from wellhead during 

drilling activity 

Air pollution due 

to burning flames 

Land and water 

contamination 

from drilling mud 

and hydraulic 

fluids 

E  Oil & Gas Safety 

Regulations, 1974 

UEPL 

Environmental 

Management 

Standard 

  Well Control System 

Blowout Preventer are 

installed in order to control the 

back kick of raw natural gas 

Acceptable

  

 

           

 

Evaluate Risk 

4  B 

Tolerable (if ALARP)   

‐ 

Follow the site 

emergency response 

plan and emergency 

drills as  per routine 

 

‐ 

8  Produced water 

production 

during testing 

operation 

Overflow from lined 

pit due to high 

produced water 

production and high 

rains 

Soil erosion   A  Commitments in 

EIA/EMP of 

particular area 

  Testing operation comprises 

only of 2‐3 days operation  

During that period, produced 

water is sent to lined pit which 

is big enough to handle 

amounts of produced water 

Even in case of high levels or 

with chance of overflow, 

produced water will be sent to 

pit made for drill cuttings 

Produced water can be re‐

injected into the deep 

subsurface formations 

wherever possible 

Acceptable

  

 

1  2  2  2  2  9 

           

‐  ‐ 

 

‐ 

9  Chemicals 

storage at 

drilling site  

Spill of chemicals  Land 

contamination and 

soil erosion 

A  Commitments in 

EIA/EMP of 

particular area 

  Storing of chemicals in 

secondary containments 

Acceptable

  

 

           

 

Evaluate Risk 

2  D 

Tolerable (if 

ALARP)

 

‐ 

Inspection of 

secondary 

Containment 

 

‐ 

10  Diesel storage 

and use at 

drilling site 

Fire due to ignition of 

spilled diesel 

Air Pollution 

(NOx, SOx, Acid 

rain, Global 

warming) 

E  Commitments in 

EIA/EMP of 

particular area 

  Spill control Plans 

No smoking at site 

Inspection of secondary 

containments 

SOP of diesel filling procedure 

Acceptable

  

 

           

 

Evaluate Risk 

2  D 

Tolerable (if 

ALARP)

 

‐ 

Training of staff at 

site regarding Site 

Emergency 

Response Plans 

 

‐ 

Diesel spill from diesel 

storage tanks and 

Land 

contamination and 

A  Commitments in 

EIA/EMP of 

particular area 

  Secondary containment 

around diesel tank 

Liner under the power engines 

Acceptable

  

 

1  1  1  2  2  7 

           

‐  ‐ 

 

‐ 

Page 350: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-27 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Conditions (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an 

environment issue in its own 

If >5 the 

aspect is significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

from power 

generation equipment 

water aquifer 

deterioration 

Routine inspections 

11  Use of mud 

during drilling 

operation 

Loss of containment 

from mud tanks and 

circulation system 

including pumps 

Land 

contamination/ 

Water aquifer 

contamination 

E  Commitments in 

EIA/EMP of 

particular area 

  Mud control system 

PM of mud pumps 

Acceptable

  

 

           

 

Evaluate Risk 

2  D 

Low 

 

‐  ‐ 

 

‐ 

12  Restoration  General  Public grievances/ 

Wildlife 

protection/Waste 

management/ 

Safety hazards 

N  Commitments in 

EIA/EMP of 

particular area 

  All pits at the well site and 

campsite will be backfilled 

Ensure that after restoration 

activities the well site and 

campsite is clean and that no 

refuse has been left behind 

Remove all concrete structures 

In case of a dry well, access 

track sections not in use will be 

restored 

In case of a producing well , 

well site and access roads will 

be retained to support well 

access works for testing and 

other operational requirements 

Wellhead for a producing well 

will be enclosed by a lock steel 

cage 

In case of producing well, 

retain construction pit areas for 

producing wells but remove all 

liquid waste from the site 

Acceptable

  

 

1  2  2  2  2  9 

           

‐  ‐ 

 

‐ 

N = Normal; A = Abnormal; E = Emergency                     

Page 351: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-28 HPK

Table C‐4: Environmental Aspect Register for Laying of Flow Line/Tie‐in/Wellhead Works 

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

1  Land acquisition  Vegetation clearing/ 

Loss of standing crops 

Public grievances  N  Land Acquisition 

Act, 1894 

  Equitable disbursement of 

compensation amounts for 

land leased 

Pay compensation amounts as 

soon as possible 

Loss of standing crops, 

traditional land rights and 

community ownership will be 

given due consideration while 

determining compensation 

amounts 

Compensation amounts will be 

settled based on prevailing 

market rates  

Manage and maintain a 

community complaints 

register  

Avoid settlements and 

agriculture fields as far as 

possible 

Compensation amounts will be 

settled after an agreement is 

reached between the local 

residents, company and local 

administrator 

Acceptable     

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

2  Equipment and 

crew 

mobilization and 

demobilization 

Dust and vehicular 

emissions  

Air pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Regulate and monitor vehicles 

speed 

Maintain vehicles in a good 

condition  

Avoid off‐road travel as much 

as possible  

Conduct vehicle and 

equipment emission testing 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Noise and vibration  Noise pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Minimize use of horns by 

project vehicles 

The use of pressure horns will 

not be allowed 

Conduct noise monitoring of 

noise emitting vehicles and 

equipment 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Driving practices  Safety hazards – 

locals  

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

  Train drivers on responsible 

and safe driving practices 

Observe minimum distances 

from local communities 

Regulate and monitor vehicles 

speed 

Maintain vehicles in a good 

condition  

Avoid off‐road travel  

Acceptable

  

 

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

Page 352: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-29 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Conduct vehicle and 

equipment emission testing 

Vehicular/machinery 

movement 

Damage to local 

infrastructure 

N  Commitments in 

EIA/EMP 

  Minimize and control 

unnecessary logistic activities  

Regulate speed limits on local 

roads subject to road condition 

Observe height of overhead 

electric/phone transmission 

lines especially during 

transportation of heavy 

equipment 

Properly manage 

transportation of heavy 

equipment and movement of 

heavy traffic 

Acceptable

  

 

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

3  Construction/ 

Improvement of 

access tracks 

Vegetation clearing/ 

Off‐road travel 

Soil erosion/ 

Wildlife 

disturbance 

N  Sindh Wildlife 

Protection 

Ordinance 1972 and 

Amendments, 2001 

  Minimize vegetation clearing 

and cutting of trees 

Locate campsite and other 

land acquired for flow line and 

operation activities in existing 

clearings (if possible) and on 

levelled land 

Minimize preparation of new 

access tracks 

Select routes of minimum 

disturbances for development 

of new tracks 

Width of existing tracks 

development or improvements 

will be kept to a minimum 

Restrict movement of 

personnel and construction 

equipment to work areas only 

Maintain photographic records 

of all activities to monitor any 

changes and soil conditions 

Train drivers on mitigation 

measures related to off‐road 

travel  

Avoid off‐road travel as much 

as possible 

Maximize usage of existing 

tracks  

Acceptable

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

    Handling of fuel and 

oil 

Soil and water 

contamination 

N  Hazardous 

Substances Rules, 

2014 

  Vehicles will be daily checked 

for fuel or oil leaks 

Fuel and oil transfer 

operations will be done using 

a dedicated fuel vehicle  

Drip pans will be used to 

avoid drips and spills 

Procedure for transfer shall be 

developed and implemented 

Acceptable

  

 

2  1  1  2  2  8 

           

‐  ‐ 

 

‐ 

Page 353: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-30 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

  Use of horns/ 

Improperly 

maintained machinery 

Noise pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Ensure that generators, 

bulldozers, vehicles and other 

potentially noisy equipment is 

in good condition 

Select campsite locations at 

least 300 m away from 

communities 

Minimize use of horns by 

vehicles  

Use of pressure horns will not 

be allowed 

Restrict all vehicles and 

personnel within work areas 

only 

Conduct noise monitoring 

 

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Dust and vehicular 

emissions 

Air pollution   N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Regulate and monitor vehicles 

speed 

Minimize dust emissions by 

employing good management 

practices 

Avoid off‐road travel as much 

as possible 

Train drivers on mitigation 

measures related to off‐road 

travel and speed limits 

Properly maintain vehicles and 

equipment 

Restrict all project vehicles and 

personnel within work areas 

only 

Employ good management 

practice to minimize dust 

emissions 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Vegetation clearing/ 

Loss of standing crops 

Soil erosion/Public 

grievance 

 N  The Forest Act, 

1927 

  Minimize vegetation clearance

Minimize preparation of new 

access tracks  

Width of existing tracks 

development or improvements 

will be minimized 

Avoid clearing of trees 

Loss of standing crops, 

traditional land rights and 

community ownership will be 

given due consideration while 

determining compensation 

amounts 

Access tracks should avoid 

passing through the areas with 

dense vegetation 

Minimize vegetation clearance 

Prohibit use of local vegetation 

as fuel 

Acceptable

  

 

2  2  3  2  2  11 

           

‐  ‐ 

 

‐ 

Page 354: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-31 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

  Land clearing of 

access track 

Loss of habitat/ 

Disturbance to 

wildlife 

 N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

Sindh 

Environmental 

Protection Act, 2014 

  Minimize total land uptake by 

access roads  

Width of existing tracks 

development or improvements 

will be minimized 

Access tracks should avoid 

passing through the areas with 

dense vegetation 

Avoid clearing of trees 

Use single approved track 

during construction 

Acceptable

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

  Driving practices/ 

Dust emissions 

Safety hazards and 

disturbance to 

communities 

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

  Train drivers on mitigation 

measures related to off‐road 

travel and speed limits  

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

Manage and maintain a 

community complaint register 

Repair any damage caused by 

project activities to local 

infrastructure by mutual 

consensus 

Observe strict compliance with 

UEPL HSE guidelines 

Project staff to respect all 

cultural norms 

Provide offsets from sites of 

religious, cultural or 

archaeological significance 

Acceptable

  

 

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

  Vehicular/Machinery 

movement 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

  Prohibit hunting, fishing, 

killing, trapping, feeding or 

harassment of wildlife 

Minimize preparation of new 

access tracks  

Width of existing tracks 

development or improvement 

will be minimized 

Select routes with minimum 

vegetation clearing 

Maintain construction vehicles 

and equipment  

If possible minimize time 

period of operation in areas 

where wildlife presence is 

confirmed, especially reported 

breeding areas 

Access tracks should avoid 

passing through the areas with 

dense vegetation 

Acceptable

  

 

2  2  2  2  3  11 

           

‐  ‐ 

 

‐ 

4  Camp 

construction/ 

Vegetation clearing/ 

Physical scarring 

Soil erosion  N  The Forest Act, 

1927 

  Minimize vegetation clearing 

Avoid cutting of trees  

Acceptable  

 2  1  2  2  2  9 

           ‐  ‐ 

 ‐ 

Page 355: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-32 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Establishment/ 

Operation 

Locate campsites in existing 

clearings and on levelled land 

Minimize total land uptake by 

the camps  

Maintain photographic records 

of all activities to monitor any 

changes in soil conditions 

Proper restoration will be done 

after camp demobilization 

  Waste management/ 

Handling of fuel, oils 

& chemicals 

Soil and water 

contamination 

N  Sindh 

Environmental 

Protection Act, 2014 

Hazardous 

Substances Rules, 

2014 

  Dispose sewage generated at 

the campsite in septic system 

comprising of septic tanks and 

soak pits 

Dispose wastewater from 

laundry, kitchen washings and 

showers into separate soak pits

Build soak pits in absorbent 

soil  

Ensure provision of grease pits 

at kitchen drain outlets 

Keep septic systems at 

minimum distances of 300 m 

from surface water sources or 

groundwater wells 

Design and construct soak pits 

to prevent surface runoff 

Design soak pits to 

accommodate wastewater 

generated during the total 

duration of the operation 

In case the soak pits get filled 

during the operation, grey 

water will be transferred to 

nearest municipal drains with 

prior approval of concerned 

authorities 

Solid wastes at the campsite 

will be disposed of in waste 

bins 

Burning of waste will not be 

allowed  

Wash vehicles in designated 

areas within campsite 

Regularly check vehicles for 

fuel or oil leaks 

All fuel and oil storage areas 

will have a concrete pad 

underneath to prevent soil 

contamination in case of leaks 

or spills 

All fuel tanks will be properly 

marked to highlight their 

Acceptable

  

 

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 356: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-33 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

contents 

Fuel and oil storage areas will 

have secondary containment in 

the form of concrete or brick 

masonry bunds 

Ensure provisions for proper 

fuel and oil storage and 

handling 

  Dust/Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Maintain vehicles and 

equipment in good condition 

Select campsite locations at 

least 300 m away from 

communities 

Employ good management 

practice to minimize dust 

emissions 

Carryout emission testing of 

vehicles and equipment 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Use of horns/ 

Improperly 

maintained machinery 

& equipment 

Noise and 

vibration 

N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Ensure that generators, 

vehicles and other potentially 

noisy equipment are in good 

condition 

Select campsite locations at 

least 300 m away from 

communities 

Minimize use of horns by 

project vehicles  

Use of pressure horns will not 

be allowed 

Restrict all project vehicles and 

personnel within work areas 

only 

Maintenance of equipment and 

machinery shall be carried out 

on regular basis 

Carryout noise monitoring of 

noisy equipment 

Acceptable

  

 

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

  Water abstraction/ 

Resource utilization 

Water pollution/ 

Resource depletion 

N  Sindh 

Environmental 

Protection Act, 2014 

  Prohibit use of water from 

surface water bodies  

Under unavoidable conditions 

(due to improper access for 

water bowsers, long haul 

distances or unavailability of 

tube wells in the project area 

etc.) water abstraction from 

surface water body will be 

allowed after getting a formal 

approval from relevant 

department 

Employ prudent water 

conservation measures  

Keep complete records of 

Acceptable

  

 

2  3  2  2  2  11 

           

‐  ‐ 

 

‐ 

Page 357: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-34 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

water consumption for camps 

and operational usages 

Install (if required) new water 

wells 300 m from existing local 

wells  

Abstract water from deep 

aquifer 

Groundwater resources will 

not be over exploited 

Water from a local well will 

only be used after ensuring 

that the available capacity at 

the tube well (safe yield minus 

local demand) is at least 50% 

greater than the project 

demand 

Utilization of water resources 

that are in possession of local 

owners shall be appropriately 

compensated as per mutual 

agreement of both parties 

Waste disposal/Use of 

machinery 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001  

 

 

 

  Prohibit hunting, fishing, 

killing, trapping, feeding or 

harassment of wildlife  

Food wastes will not be left in 

the open 

Food waste will be properly 

buried in a bury pit 

Maintain compressors and 

vehicles in good condition 

Acceptable

  

 

2  3  3  3  3  14 

       

 

 

‐  ‐ 

 

‐ 

5  Clearing, 

levelling and 

excavation for 

flow line right of 

way (RoW)  

Vegetation clearing/ 

Physical scarring 

Soil erosion/ 

Damage to habitat 

A  The Forest Act, 

1927 

  Minimize vegetation clearance 

Avoid cutting of trees 

Maintain photographic records 

of all activities to monitor any 

changes in soil conditions  

Minimize disturbance to 

natural topography and soils  

Regulate and monitor vehicles 

speed  

Avoid off‐road travel as much 

as possible  

Train drivers on mitigation 

measures related to off‐road 

travel and speed limits 

Acceptable

  

 

2  2  2  2  1  9 

       

 

 

‐  ‐ 

 

‐ 

Page 358: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-35 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Waste disposal/ 

Handling of fuel, oil 

and chemicals  

Soil and water 

contamination 

A  Sindh 

Environmental 

Protection Act, 2014 

Hazardous 

Substances Rules, 

2014 

  Prohibit solid waste disposal 

in the field 

Regularly check vehicle for 

fuel or oil leaks 

Use a dedicated fuel vehicle 

for fuel and oil transfer 

operation  

Use drip pans to avoid drips 

and spills  

Incineration or bioremediation 

to treat soils contaminated 

with oil spills 

Acceptable

  

 

2  1  2  2  2  9 

       

 

 

‐  ‐ 

 

‐ 

Use of horns/ 

Improperly 

maintained machinery 

Noise and 

vibration 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

 

  Minimize use of horns by 

project vehicles  

Maintain generators 

construction machinery in 

good condition 

The use of pressure horns will 

not be allowed  

Restrict  movement of 

personnel and construction 

equipment within work areas 

Acceptable

  

 

2  2  1  2  2  9 

       

 

 

‐  ‐ 

 

‐ 

    Dust/Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

 

  Maintain vehicles in good 

condition 

Minimize dust emissions by 

employing good management 

practices 

Carryout emission testing of 

vehicle and equipment 

Maintain safe distances from 

sensitive environmental 

receptors 

Acceptable

  

 

2  2  1  2  2  9 

       

 

 

‐  ‐ 

 

‐ 

Vegetation clearing/ 

Loss of standing crops 

Loss of habitat/ 

Public grievance 

N  The Forest Act, 

1927 

  Minimize clearing of 

vegetation 

Prohibit use of local vegetation 

as fuel by crew personnel 

Avoid cutting of trees 

Loss of standing crops, 

traditional land rights and 

community ownership will be 

given due consideration while 

determining compensation 

amounts 

Minimize width of flow line 

right of the way 

Acceptable

  

 

2  2  2  2  3  11 

       

 

 

‐  ‐ 

 

‐ 

Page 359: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-36 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

Waste disposal/ 

Vehicular movement 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

  Prohibit hunting, fishing, 

killing, trapping, feeding or 

harassment of wildlife  

Minimize vegetation clearing 

and land uptake  

Avoid clearing of dense 

patches of vegetation 

Food wastes will not be left in 

the open 

Food waste will be properly 

buried in a bury pit 

Maintain vehicles in good 

condition to reduce noise 

Initiate activities with soft start 

to allow time for wildlife 

species to move away from the 

project area 

Acceptable

  

 

2  2  2  2  3  11 

       

 

 

‐  ‐ 

 

‐ 

    Driving practices/ 

Local resource 

utilization 

Safety hazards and 

disturbance to 

communities 

N  Motor Vehicles 

Rules, 1969 or 

Provincial Motor 

Vehicles 

(Amendment) 

Ordinance, 2002 

  Train drivers on mitigation 

measures related to off‐road 

travel and speed limits  

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

Manage and maintain 

community complaints 

register  

Local sources of drinking 

water will be used only after 

complying with relevant 

requirements of the EIA/EMP 

Repair any damage (if any) 

caused by project activities to 

local infrastructure by mutual 

consensus 

Observe strict compliance with 

UEPL HSE guidelines 

Project staff to respect cultural 

norms 

Provide offsets from sites of 

religious, cultural or 

archaeological significance 

Maintain effective 

communication channels with 

local communities to inform 

them about the progress of 

various project activities 

Acceptable

  

 

1  2  1  2  2  8 

       

 

 

‐  ‐ 

 

‐ 

Page 360: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-37 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

6  Flow line laying   

(stringing, 

welding etc.)/ 

Flow line 

operation 

Disturbance to 

wildlife 

Ecological 

misbalance 

N  Sindh Wildlife 

Protection 

Ordinance, 1972 

and Amendments, 

2001 

  Prohibit hunting, fishing, 

killing, trapping, feeding or 

harassment of wildlife  

Food wastes will not be left in 

the open. Food waste will be 

properly buried in a bury pit 

Maintain compressors and 

vehicles in good condition 

Acceptable

  

 

2  3  3  3  3  14 

       

 

 

‐  ‐ 

 

‐ 

Use of horns/ 

Machinery movement 

Noise and 

vibration 

N  Sindh 

Environmental 

Protection Act, 1997 

Sindh 

Environmental 

Quality Standards, 

2016 

  Minimize the use of horns by 

project vehicles   

The use of pressure horns will 

not be allowed 

Restrict movement of all 

project vehicles and personnel 

within work areas 

Carryout noise monitoring of 

noisy equipment and 

machinery 

Acceptable

  

 

2  2  2  3  3  12 

       

 

 

‐  ‐ 

 

‐ 

  Dust/Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 2014 

Sindh 

Environmental 

Quality Standards, 

2016 

  Maintain vehicles in good 

condition 

Minimize dust emissions by 

good management practices 

Regulate vehicles speed  

Carryout emission testing of 

vehicle and machinery 

Maintain safe distances 

Acceptable

  

 

2  2  2  2  2  10 

       

 

 

‐  ‐ 

 

‐ 

  Waste disposal/ 

Handling of fuel, oil 

and chemicals 

Soil and water 

contamination 

N  Sindh 

Environmental 

Protection Act, 2014 

Hazardous 

Substances Rules, 

2014 

  No solid waste will be 

disposed of in the field 

Regularly check vehicle for 

fuel and oil leaks 

Use dedicated vehicle for fuel 

and oil transfer 

Incineration or bioremediation 

to treat soils contaminated 

with oil spills 

Waste management plan shall 

be developed 

oil/fuel transfer procedure 

shall be developed and 

implemented 

Acceptable

  

 

2  2  3  2  2  11 

       

 

 

‐  ‐ 

 

‐ 

Page 361: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-38 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

    Water abstraction/ 

Resource utilization 

Water pollution/ 

Resource depletion 

N  Sindh 

Environmental 

Protection Act, 2014 

  Prohibit use of water from 

surface water bodies  

Under unavoidable conditions 

(due to improper access for 

water bowsers, long haul 

distances or unavailability of 

tube wells in the project area 

etc.) water abstraction from 

surface water body will be 

allowed after getting a formal 

approval from concerned 

government department 

Employ prudent water 

conservation measures  

Keep complete records of 

water consumption for camps 

and operational usages 

Install (if required) new water 

wells 300 m from existing local 

wells  

Abstract water from deep 

aquifer 

Groundwater resources will 

not be over exploited  

Water from a local well will 

only be used after ensuring 

that the available capacity at 

the tube well (safe yield minus 

local demand) is at least 50% 

greater than the project 

demand 

Utilization of water resources 

that are in possession of local 

owners shall be appropriately 

compensated as per mutual 

agreement of both parties 

Acceptable

  

 

2  3  2  2  2  11 

       

 

 

‐  ‐ 

 

‐ 

7  Waste 

management 

Improper disposal of 

waste/Handling of 

fuel, oil & chemicals 

Air, soil and water 

contamination 

N  Sindh 

Environmental 

Protection Act, 2014 

Hazardous 

Substances Rules, 

2014                 

Sindh 

Environmental 

Quality Standards, 

2016 

  Dispose sewage generated at 

the campsite in septic systems 

comprising septic tanks and 

soak pits 

Dispose wastewater from 

laundry, kitchen washings and 

showers into separate soak pits

Build soak pits in absorbent 

soil  

Construct soak pits to prevent 

surface runoff entry 

Design soak pits to 

accommodate wastewater 

generated during the total 

duration of the operation 

Ensure provision of grease pits 

Acceptable

  

 

2  2  3  2  2  11 

           

‐  ‐ 

 

‐ 

Page 362: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-39 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

at kitchen drain outlets 

In case the soak pits get filled 

during the operation, grey 

water will be transferred to 

nearest municipal drains with 

prior approval of concerned 

authorities 

No solid waste will be 

disposed of in the field 

Recycle non‐combustible 

waste 

Wash vehicles in designated 

areas within campsite 

Burning of waste will be 

prohibited 

Check vehicles for fuel or oil 

leaks 

All fuel and oil storage areas 

will have a concrete pad 

underneath with secondary 

containment in the form of 

concrete or brick masonry 

bunds to prevent soil 

contamination in case of leaks 

or spills 

All fuel tanks will be properly 

marked to highlight their 

contents 

Use dedicated vehicles for fuel 

and oil transfer operations 

Use drip pans to avoid drips 

and leaks  

Incineration or bioremediation 

to treat soils contaminated 

with oil spills 

A spill prevention and 

contingency plan will be 

prepared to deal with 

moderate and major spills 

Recycle used oil and vehicle 

related waste  

Incinerate all clinical wastes 

Maintain generators, 

compressors and vehicles in 

good condition 

Minimize dust emissions by 

good management practices  

Food wastes will not be left in 

the open. Food waste will be 

properly buried in a bury pit 

8  Community 

issues 

Vegetation clearing/ 

Loss of standing crops 

Soil erosion/Public 

grievance 

N  The Forest Act, 

1927 

  Manage and maintain a 

community complaints 

Acceptable  

 2  2  2  2  2  10 

           ‐  ‐ 

 ‐ 

Page 363: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-40 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

register 

Disburse compensation 

amounts in an equitable and 

transparent manner 

Pay compensation amounts as 

soon as possible 

Loss of standing crops, 

traditional land rights and 

community ownership will be 

given due consideration while 

determining compensation 

amounts 

Pay appropriate compensation 

amounts 

Comply with all EIA/EMP 

mitigation related to waste, 

noise and dust emissions 

If there are opportunities, 

ensure equitable and 

transparent recruitment of 

local unskilled labour during 

different phases of the project 

activities subject to company’s 

selection criteria 

Local residents living closest to 

the project location will be 

given priority in the 

employment process 

Local sources of drinking 

water will be used only after 

complying with relevant 

requirements of the EIA/EMP 

Flow of water in surface water 

body will not be impeded 

Strict compliance will be 

observed to UEPL HSE 

guidelines 

Train drivers in responsible 

and safe driving practices 

A mechanism will be defined 

to address the local 

community grievances 

appropriately 

Project staff will respect 

cultural norms 

Provide appropriate offsets 

from sites of religious, cultural 

or archaeological significance 

9  Restoration  General  Public grievances/ 

Wildlife 

protection/Waste 

N       Restore soak pits after project 

completion 

Ensure that after restoration 

activities the campsite is clean 

Acceptable

  

 

1  2  2  2  2  9 

           

‐  ‐ 

 

‐ 

Page 364: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-41 HPK

No 

Detailed Description of the Aspect – Impact  

Existing Controls and their Adequacy  

Impacts Significance Evaluation Questions   Risk 

(only evaluated for accident 

scenarios) 

  Management 

Attention 

 Actions 

Description of 

Aspect 

(source‐

pathway‐

receptor) 

Condition (Threat) Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

or natural features? 

Is there the potential to 

create an environmental 

liability? 

Is there the potential to 

dam

age the Compan

y’s 

reputation? 

Does the Size or Nature of 

the scenario present an env 

issue in its own right? 

If >5 the 

aspect is 

significant 

 

Evaluate 

EnvironmentalRisk

Consequence 

Frequency 

Risk 

 

For 

Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions 

Required for 

Significant 

Environmental 

Aspects 

management/ 

Safety hazards 

and that no refuse has been left 

behind 

Remove all concrete structures 

Avoid using local fuel wood 

N = Normal; A = Abnormal; E = Emergency                     

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 365: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-42 HPK

Table C‐5: Environmental Aspect Register for Hydrocarbon Processing Facility (GPF/CPP) 

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

1  Land 

acquisition 

Loss of 

vegetation/crops/ 

trees 

Public 

grievances 

N  Land 

Acquisition 

Act, 1894 

  Compensation as per 

mutual agreement 

Acceptable      2  2  2  2  2  10 

           ‐  ‐ 

 ‐ 

2  Equipment and 

crew 

mobilization 

and 

demobilization 

Dust and 

vehicular 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 (Sindh 

Environmental 

Quality 

Standard, 2016) 

  Regulate and monitor 

vehicles speed 

Maintain vehicles in a 

good condition  

Avoid off‐road travel  

Maintain safe distances 

from communities 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

    Noise and 

vibration 

Noise 

pollution 

N  Sindh 

Environmental 

Protection Act, 

2014 (Sindh 

Environmental 

Quality 

Standard, 2016) 

  Minimize use of horns 

by project vehicles  

The use of pressure 

horns will not be 

allowed 

Reduce speed while 

passing close to 

settlements 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

    Driving practices  Safety hazards 

‐ locals 

N  Motor Vehicles 

Rules, 1969 or 

Provincial 

Motor Vehicles 

(Amendment) 

Ordinance, 

2002 

  Train drivers in 

responsible and safe 

driving practices 

Observe minimum 

distances from local 

communities  

Night travelling will 

only be done after 

getting approval from 

HSEO 

Acceptable     

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

3  Construction/ 

Improvement of 

access tracks 

Land clearing  Soil 

erosion/loss of 

habitat/loss of 

vegetation 

N  Land 

Acquisition 

Act, 1894 

Sindh Wildlife 

Protection 

Ordinance, 

1972 and 

Amendments 

2001 

Sindh 

Environmental 

Protection Act, 

2014 

  Use of existing track as 

much as possible to 

minimize preparation of 

new access track  

Width of existing track 

development or 

improvements will be 

kept to a minimum 

Restrict movement of 

personnel and 

construction equipment 

to work areas  

Maintain photographic 

records of all activities to 

monitor any changes 

and soil conditions 

Acceptable     

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 366: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-43 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

Train drivers on 

mitigation measures 

related to off‐road travel  

Avoid off‐road travel 

Access track to the 

GPF/CPP will be 

properly compacted 

    Handling of fuel, 

oils and 

chemicals 

Soil and water 

contamination 

N  Hazard 

Substances 

Rules, 2014 

  Vehicles will be daily 

checked for fuel or oil 

leaks 

Fuel and oil transfer 

operations will be done 

using a dedicated fuel 

vehicle  

Drip pans will be used 

to avoid drips and spills 

Acceptable      

2  1  1  2  2  8 

           

‐  ‐ 

 

‐ 

    Use of 

horn/improperly 

maintained 

machinery 

Noise 

pollution 

N  Sindh 

Environmental 

Protection Act, 

2014 (Sindh 

Environmental 

Quality 

Standard, 2016) 

  Minimize use of horns 

by project vehicles  

Use of pressure horns 

will not be allowed 

Properly maintain 

vehicles and 

construction equipment 

Restrict all project 

vehicles and personnel 

within work areas 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

    Dust and 

vehicular 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 (Sindh 

Environmental 

Quality 

Standard, 2016) 

  Regulate and monitor 

vehicles speed  

Minimize dust emissions 

by employing good 

management practices 

Avoid off‐road travel 

Sprinkle water where 

necessary 

Train drivers on 

mitigation measures 

related to off‐road travel 

and speed limits 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

    Driving 

practices/resource 

utilization 

Safety hazards 

and 

disturbance to 

communities 

N  Motor Vehicles 

Rules, 1969 or 

Provincial 

Motor Vehicles 

(Amendment) 

Ordinance, 

2002 

  Train drivers on 

mitigation measures 

related to off‐road travel 

and speed limits  

Comply with all 

EIA/EMP mitigation 

related to waste, noise 

and dust emissions 

Acceptable     

1  2  1  2  2  8 

           

‐  ‐ 

 

‐ 

Page 367: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-44 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

Manage and maintain a 

community complaints 

register  

Local sources of 

drinking water will be 

used only after 

complying with relevant 

requirements of the EIA 

Observe strict 

compliance with UEPL 

HSE guidelines 

Project staff to respect all 

cultural norms 

Provide offsets from 

sites of religious, 

cultural or 

archaeological 

significance 

    Vehicular 

movement 

Disturbance to 

wildlife/loss of 

vegetation 

N  Sindh Wildlife 

Protection 

Ordinance, 

1972 and 

Amendments 

2001 

  Prohibit hunting, 

fishing, trapping or 

harassment of wildlife  

Minimize preparation of 

new access tracks  

Width of existing tracks 

development or 

improvements will be 

kept to a minimized 

Select routes with 

minimum vegetation 

clearing 

Avoid dense patches of 

vegetation 

Maintain construction 

vehicles and equipment 

Minimize time period of 

operation near dhands 

(especially which are 

breeding areas) and 

canals 

Monitor impacts of the 

individual projects on 

wildlife species 

Access tracks should 

avoid passing through 

the areas with dense 

vegetation 

Acceptable     

2  2  2  2  3  11 

           

‐  ‐ 

 

‐ 

Page 368: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-45 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

4  Camp/GPF/CPP 

expansion, 

establishment 

and operation 

Vegetation 

clearing 

Soil erosion/ 

Physical 

scarring 

N  The Forest Act, 

1927   Minimize vegetation 

clearing 

Avoid cutting of trees  

Locate campsites in 

existing clearing and on 

levelled land 

Minimize total land 

uptake by campsite and 

GPF/CPP 

Maintain photographic 

records of all activities to 

monitor any changes in 

soil conditions 

Acceptable     

2  1  2  2  2  9 

           

‐  ‐ 

 

‐ 

    Waste 

management 

/handling of fuel, 

oils and 

chemicals  

Soil/Water 

contamination 

N  Sindh 

Environmental 

Protection Act, 

2014 

Hazardous 

Substance 

Rules, 2014 

  Sewage Treatment Plant 

(STP) shall be preferred 

for handling of 

black/grey water under 

BATNEEC/BAT, but in 

case of unavailability of 

STP, septic tank and 

soak pits shall be 

provided. Septic tank 

and soak pit shall be 

covered properly to 

avoid any bad smell in 

surrounding areas 

Sprinkling of grey water 

will not be allowed; in 

case the septic tank gets 

filled with sludge, septic 

tank shall be emptied 

through vacuum truck 

and material shall be 

transferred to treatment 

facility or approved 

municipal drain 

Produced water 

separated at GPF shall 

be re‐injected to 

reservoir through deep 

well injection (first 

priority). 

However it can be sent 

to lined E‐Pond if no 

technical feasible 

options are available 

Acceptable      

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 369: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-46 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

Solid wastes at the 

campsite and GPF/CPP 

will be disposed of in 

waste bins  

Wash vehicles in 

designated areas within 

campsite 

Regularly check vehicles 

for fuel or oil leaks 

All fuel and oil storage 

areas will have a 

concrete pad underneath 

to prevent soil 

contamination in case of 

leaks or spills 

All fuel tanks will be 

properly marked to 

highlight their contents 

Fuel and oil storage 

areas will have 

secondary containment 

in the form of concrete 

or brick masonry bunds 

Ensure provision for 

proper fuel and oil 

storage and handling 

Ensure preparation of a 

spill prevention and 

contingency plan 

Ensure provisions of a 

HDPE liner for the waste 

pits at the campsite and 

GPF/CPP 

    Dust/Exhaust 

emissions 

Air pollution  N  Sindh 

Environmental 

Protection Act, 

2014 (Sindh 

Environmental 

Quality 

Standard, 2016) 

  Maintain vehicles and 

equipment in good 

condition 

Select campsite locations 

at least 300 m away from 

communities 

Employ good 

management practice to 

minimize dust emissions 

Regular monitoring of 

GPF/CPP point source 

emissions to ensure 

compliance with SEQS 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

Page 370: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-47 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

    Use of 

horns/improper 

maintained 

machinery 

Noise and 

vibration 

N  Sindh 

Environmental 

Protection Act, 

2014 

  Ensure that generators, 

vehicles and other 

potentially noisy 

equipment are in good 

condition 

Select campsite locations 

at least 300 m away from 

communities 

Randomly monitor noise 

levels at nearest 

receptors. Also consult 

communities regarding 

disturbance due to noise 

and vibration 

Minimize use of horns 

by project vehicles  

Use of pressure horns 

will not be allowed 

Restrict all project 

vehicles and personnel 

within work areas 

Use noise barriers if 

required 

Acceptable     

2  2  1  2  2  9 

           

‐  ‐ 

 

‐ 

    Resource 

utilization 

Resource 

depletion/ 

water 

pollution 

N  Sindh 

Environmental 

Protection Act, 

2014 

  Prohibit use of water 

from surface water 

bodies  

Employ prudent water 

conservation measures  

Keep complete records 

of water consumption 

during project 

construction and 

operation 

Obtain water required 

for project activities 

from local wells, existing 

or new UEPL water 

wells in the area 

Install (if required) new 

water wells 300 m from 

existing local wells  

Abstract water from 

deep aquifer 

Water from a local well 

will only be used after 

ensuring that the 

Acceptable     

2  3  2  2  2  11 

           

‐  ‐ 

 

‐ 

Page 371: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-48 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

available capacity at the 

tube well (safe yield 

minus local demand) is 

at least 50% greater than 

the project demand  

Water from dhands will 

not be used 

Minimize fuel 

consumption, encourage 

conservation techniques 

    Noise and 

vibration/waste 

disposal 

Disturbance to 

wildlife 

N  Sindh Wildlife 

Protection 

Ordinance, 

1972 and 

Amendments 

2001 

  Prohibit hunting, 

fishing, trapping or 

harassment of wildlife  

Food wastes will not be 

left in the open  

Maintain vehicles and 

equipment in good 

condition 

Night travelling will 

only be done after 

getting approval from 

HSEO 

Acceptable     

2  3  3  3  3  14 

           

‐  ‐ 

 

‐ 

5  Waste 

management 

Improper 

disposal of waste/ 

handling of fuel, 

oil and chemicals 

Soil and water 

contamination 

N  Sindh 

Environmental 

Protection Act, 

2014 (Sindh 

Environmental 

Quality 

Standard, 2016) 

  Dispose sewage 

generated in septic 

systems comprising of 

septic tanks and soak 

pits 

Dispose wastewater 

from laundry, kitchen 

washings, and showers 

directly into soak pits 

Build soak pits in 

absorbent soil  

Ensure that the storage 

soak pits remain covered 

all the time and 

measures are taken to 

prevent entry of 

rainwater into them 

Design soak pits to 

accommodate 

wastewater generated 

during the total duration 

of the operation 

In case the soak pits get 

filled during the 

Acceptable     

2  2  3  2  2  11 

           

‐  ‐ 

 

‐ 

                                                                                              

   

 

 

Page 372: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-49 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

operation, grey water 

will be transferred to 

nearest municipal drains 

with prior approval of 

concerned authorities 

Produced water 

separated at GPF/CPP 

shall be re‐injected to 

reservoir through deep 

well injection (first 

priority). 

However it can be sent 

to lined E‐Pond if no 

technical feasible 

options are available 

No solid waste will be 

disposed of in the field 

Recycle non‐combustible 

waste 

Burning waste will not 

be allowed 

Wash vehicles in 

designated areas within 

campsite 

Check vehicles for fuel 

or oil leaks 

All fuel and oil storage 

areas will have a 

concrete pad underneath 

to prevent soil 

contamination in case of 

leaks or spills 

All fuel tanks will be 

properly marked to 

highlight their contents 

Fuel and oil storage 

areas will have 

secondary containment 

in the form of concrete 

or brick masonry bunds 

Use dedicated vehicles 

for fuel and oil transfer 

operations 

Use drip pans to avoid 

drips and oil stains  

Page 373: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-50 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

Check fuel tanks for 

leaks 

The soil contaminated 

from minor and 

moderate spills will be 

removed and sent to 

waste contractor for 

appropriate disposal e.g. 

incineration 

A spill prevention and 

contingency plan will be 

prepared to deal with 

moderate and major 

spills 

Ensure provision of 

proper fuel and oil, 

storage and handling  

Recycle used oil and 

vehicles related waste 

Incinerate medical waste 

in a medical waste 

incineration facility 

Maintain vehicles and 

other equipment in good 

condition 

Minimize dust emissions 

by good management 

practices  

Food wastes will not be 

left in the open  

Ensure provision of a 

HDPE liner for the waste 

pits at the campsite and 

GPF/CPP 

6  Community 

issues 

Land acquisition/ 

Vegetation clearing/ 

Loss of standing 

crops 

Public 

grievances N  As per 

commitments 

of EIA/EMP 

  UEPL Community 

Representative will deal 

with community to 

address their stances  

A mechanism will be 

defined to address the 

local community 

grievances appropriately 

Manage and maintain 

community complaints 

register 

Acceptable     

2  2  2  2  2  10 

           

‐  ‐ 

 

‐ 

Page 374: EIA Kotri North Block F01 - epasindh.gov.pk tech/EIA Kotri North Block.pdf · OCTOBER 2019 ES-5 HPK development well. Each proposed well will be drilled using a conventional land

EIA for Exploration and Associated Development Activities in Kotri North Block, Sindh

OCTOBER 2019 C-51 HPK

No 

Detailed Description of the Aspect ‐ Impact  

Existing Controls and their Adequacy   Impacts Significance Evaluation 

Questions 

  Risk (only evaluated for 

accident scenarios) 

 Management Attention 

 Actions 

Description of 

Aspect (source‐

pathway‐

receptor) 

Condition 

(Threat) 

Impact 

(Consequence)  N/A/E 

Applicable 

Legislation 

 

Control Measures 

(Engineered and 

Management) 

Control 

Measure 

Status 

Comments 

 

What is the regulatory 

status? 

Is there the potential to 

endan

ger human

s, w

ildlife 

Is there the potential to 

create an env liability? 

Is there the potential to 

dam

age the Compan

y’s 

Does the Size or Nature of 

the scenario present an 

If >5 the 

aspect is 

significant 

 

Evaluate 

Environmental Risk 

Consequence 

Frequency 

Risk 

 

For Normal 

and 

Abnormal 

Events 

For 

Accident 

Scenarios 

 

Actions Required for 

Significant Environmental 

Aspects 

Comply with all 

EIA/EMP mitigation 

related to waste, noise 

and dust emissions 

Groundwater sources 

currently being used by 

the resident 

communities will be 

exploited only after 

complying with relevant 

requirements of the EIA 

Local sources of 

drinking water will be 

used only after 

complying with relevant 

requirements of the EIA 

Strict compliance will be 

observed to UEPL HSE 

guidelines 

Respect cultural norms 

Provide appropriate 

offsets from sites of 

religious, cultural or 

archaeological 

significance 

N = Normal; A = Abnormal; E = Emergency