Top Banner
Effective Project Management: Traditional, Agile, Extreme Presented by (facilitator name) Managing Complexity in the Face of Uncertainty Ch07: How to Monitor & Control a TPM Project
36

Effective Project Management: Traditional, Agile, Extreme

Feb 01, 2016

Download

Documents

muncel

Effective Project Management: Traditional, Agile, Extreme. Managing Complexity in the Face of Uncertainty. Presented by (facilitator name). Ch07: How to Monitor & Control a TPM Project. Summary of Chapter 7. Ch07: How to Monitor & Control a TPM Project. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Effective Project Management: Traditional, Agile, Extreme

Effective Project Management: Traditional, Agile, Extreme

Presented by(facilitator name)

Managing Complexity in the Face of Uncertainty

Ch07: How to Monitor & Control a TPM Project

Page 2: Effective Project Management: Traditional, Agile, Extreme

Using tools, templates, and processes to monitor & control a project

Establishing your progress reporting system Applying graphical reporting tools Managing the Scope Bank Building and maintaining the Issues Log Managing project status meetings Defining a problem escalation Gaining approval to close the project

Summary of Chapter 7

Ch07: How to Monitor & Control a TPM Project

Page 3: Effective Project Management: Traditional, Agile, Extreme

Tools, Templates, & Processes Used to Monitor & Control

Current period reports Cumulative reports Exception reports Stoplight reports Variance reports Gantt charts Burn charts Milestone trend charts Earned value analysis Integrated milestone trend charts and earned value analysis Project status meetings Problem escalation strategies

Ch07: How to Monitor & Control a TPM Project

Page 4: Effective Project Management: Traditional, Agile, Extreme

Hold daily team meetings Complete tasks ASAP Report problems ASAP Don’t fall victim to the “creeps” Don’t guess – ask questions Good enough is good enough Meet but do not exceed requirements Be open and honest with your teammates

How to Keep a Project on Schedule

Ch07: How to Monitor & Control a TPM Project

Page 5: Effective Project Management: Traditional, Agile, Extreme

Timely, complete, accurate, and intuitive Isn’t burdensome and counterproductive Readily acceptable to senior management Readily acceptable to the project team An effective early warning system

Characteristics of Effective Progress Reporting

Ch07: How to Monitor & Control a TPM Project

Page 6: Effective Project Management: Traditional, Agile, Extreme

Determine a set period of time and day of week Report actual work accomplished during this period Record historical and re-estimate remaining Report start and finish dates Record days of duration accomplished and remaining Report resource effort spent and remaining Report percent complete

How and What Information to Update

Ch07: How to Monitor & Control a TPM Project

Page 7: Effective Project Management: Traditional, Agile, Extreme

Current period reports Cumulative reports Exception reports Stoplight reports Variance reports

Five Types of Project Status Reports

Ch07: How to Monitor & Control a TPM Project

Page 8: Effective Project Management: Traditional, Agile, Extreme

Gantt Chart Project Status Report

Figure07-01

Ch07: How to Monitor & Control a TPM Project

Page 9: Effective Project Management: Traditional, Agile, Extreme

The project is progressing according to plan.

The project has a problem. A Get Well plan is in place. The situation will correct.

The project is failing. Intervention is required.

Exception Report – Stoplight Reports

Ch07: How to Monitor & Control a TPM Project

Page 10: Effective Project Management: Traditional, Agile, Extreme

Cumulative Reports - Milestone Trend Charts

Figure07-02

Ch07: How to Monitor & Control a TPM Project

Page 11: Effective Project Management: Traditional, Agile, Extreme

Cumulative Reports - Milestone Trend Charts

Figure07-03

Ch07: How to Monitor & Control a TPM Project

Page 12: Effective Project Management: Traditional, Agile, Extreme

Cumulative Reports - Milestone Trend Charts

Figure07-04

Ch07: How to Monitor & Control a TPM Project

Page 13: Effective Project Management: Traditional, Agile, Extreme

Cumulative Reports - Milestone Trend Charts

Figure07-05

Ch07: How to Monitor & Control a TPM Project

Page 14: Effective Project Management: Traditional, Agile, Extreme

Earned Value – The Standard S-Curve

Time

Progress

2/3 Time - 3/4 Progress

1/3 Time - 1/4 Progress

Figure07-06

Ch07: How to Monitor & Control a TPM Project

Page 15: Effective Project Management: Traditional, Agile, Extreme

Earned Value – The Aggressive Curve

No ramp up - no learning time

Time

Progress

Ch07: How to Monitor & Control a TPM Project

Page 16: Effective Project Management: Traditional, Agile, Extreme

Earned Value – The Curve to Avoid

About 30% of the work done

70% to 80% of the time gone by

Time

Progress

Ch07: How to Monitor & Control a TPM Project

Page 17: Effective Project Management: Traditional, Agile, Extreme

How to Measure Percent of Value Earned

100 – 0 0 – 100 50 – 50 Proportion of tasks completed

Report date

100 - 0 0 - 100

50 - 50

10 tasks complete 4 tasks not complete

10/14

Work in process

Ch07: How to Monitor & Control a TPM Project

Page 18: Effective Project Management: Traditional, Agile, Extreme

Figure07-07

Earned Value – Cost Variance

Ch07: How to Monitor & Control a TPM Project

Page 19: Effective Project Management: Traditional, Agile, Extreme

Figure07-08

Earned Value – Schedule Variance

Ch07: How to Monitor & Control a TPM Project

Page 20: Effective Project Management: Traditional, Agile, Extreme

How to Measure Earned Value

Figure07-09

Ch07: How to Monitor & Control a TPM Project

Page 21: Effective Project Management: Traditional, Agile, Extreme

Figure07-10

Earned Value – The Full Story

ScheduleVariance

Cost Variance

PV

AC

EV

Time

Progress

Ch07: How to Monitor & Control a TPM Project

Page 22: Effective Project Management: Traditional, Agile, Extreme

Figure07-11

Earned Value – PV, EV and AC curves

Ch07: How to Monitor & Control a TPM Project

Page 23: Effective Project Management: Traditional, Agile, Extreme

Earned Value – Basic Performance Indices

Cost Performance Index (CPI)A measure of how close the project is to spending on the work performed to what was planned to have been spent.

Schedule Performance Index (SPI)A measure of how close the project is to performing work as it was actually scheduled.

CPI = EV/AC

SPI = EV/PV

INDEX VALUES< 1: over budget or behind schedule> 1: under budget or ahead of schedule

Ch07: How to Monitor & Control a TPM Project

Page 24: Effective Project Management: Traditional, Agile, Extreme

Earned Value – Performance Indices

Project Week

87654 9321

1.0

0.8

0.6

0.4

1.2

1.4

1.6

C CC

CC CS S

SS

SS

under budgetahead of schedule

over budgetbehind schedule

Project: ALPHA

Figure07-12

Ch07: How to Monitor & Control a TPM Project

Page 25: Effective Project Management: Traditional, Agile, Extreme

Earned Value – Performance Indices

Project: ALPHA

C CC

CC CS S

SS S S C

SS

Cunder budgetahead of schedule

over budgetbehind schedule

1.0

0.8

0.6

0.4

1.2

1.4

1.6

Project Week

87654 9321

Figure07-13

Ch07: How to Monitor & Control a TPM Project

Page 26: Effective Project Management: Traditional, Agile, Extreme

Earned Value – Performance Indices

Project: ALPHA

C CC

C CC

S SS

S

SS C

S

under budgetahead of schedule

over budgetbehind schedule

1.0

0.8

0.6

0.4

1.2

1.4

1.6

Project Week

87654 9321

Figure07-14

Ch07: How to Monitor & Control a TPM Project

Page 27: Effective Project Management: Traditional, Agile, Extreme

Earned Value – Performance Indices

Portfolio average

Portfolio: BETA Program

ahead of schedule

behind schedule

1.0

0.8

0.6

0.4

1.2

1.4

1.6

Project Week

87654 9321

Figure07-15

Ch07: How to Monitor & Control a TPM Project

Page 28: Effective Project Management: Traditional, Agile, Extreme

Initial deposit of 10% of total labor days All of the unfinished functions and features and the

labor time to develop them are also deposited in the Scope Bank.

The time to process and integrate a Scope Change request draws time from the Scope Bank.

To add time to the Scope Bank remove unfinished functions and features and deposit their labor time in the Scope Bank.

Client should continuously reprioritize contents of the Scope Bank

Managing the Scope Bank

Ch07: How to Monitor & Control a TPM Project

Page 29: Effective Project Management: Traditional, Agile, Extreme

ID Number Date logged Description of the problem Impact if not resolved The problem owner Action to be taken Status Outcome

Maintaining the Issues Log

Ch07: How to Monitor & Control a TPM Project

Page 30: Effective Project Management: Traditional, Agile, Extreme

Who Should Attend? When Are They Held? What Is Their Purpose? What Is Their Format?

Managing Project Status Meetings

Ch07: How to Monitor & Control a TPM Project

Page 31: Effective Project Management: Traditional, Agile, Extreme

Entire team or Task Managers for tasks open for work

Everyone stands up Rotate the meeting facilitator Status of each task is reported

On schedule Ahead of schedule (by how much) Behind schedule (by how much and get well plan)

Update Scope Bank Update Issues Log

The 15-Minute Daily Status Meeting

Ch07: How to Monitor & Control a TPM Project

Page 32: Effective Project Management: Traditional, Agile, Extreme

Affected parties only Agree on problem Agree on who owns the problem Brainstorm solutions Prioritize solutions Update Issues Log Schedule next meeting

Problem Management Meeting

Ch07: How to Monitor & Control a TPM Project

Page 33: Effective Project Management: Traditional, Agile, Extreme

Problem Escalation Strategies – Who Controls What?

Scope and Quality

Tim

e Cost

Resource Availability

Ch07: How to Monitor & Control a TPM Project

Page 34: Effective Project Management: Traditional, Agile, Extreme

Project Manager-Based Strategies No action required. Problem will self-correct Examine dependency relationships Reassign resources

Resource Manager-Based Strategies Negotiate additional resources

Client-Based Strategies Negotiate multiple release strategies Request schedule extension

Problem Escalation Strategies

Ch07: How to Monitor & Control a TPM Project

Page 35: Effective Project Management: Traditional, Agile, Extreme

No action required (schedule slack will correct the problem)

Examines FS dependencies for schedule compression opportunities

Reassign resources from non-critical path tasks to cover the slippage.

Negotiate additional resources Negotiate multiple release strategies Request schedule extension from the client

Escalation Strategy Hierarchy

Ch07: How to Monitor & Control a TPM Project

Page 36: Effective Project Management: Traditional, Agile, Extreme

When the client is satisfied that the acceptance criteria have been met the project enters the closing phase

Gaining approval to close the project

Ch07: How to Monitor & Control a TPM Project