Top Banner
Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014
22

Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Dec 14, 2015

Download

Documents

David Dingley
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Edmonton’s Anthony Henday DriveUnique Challenges

Saskatchewan P3 Summit 2014

Regina, Saskatchewan

September 9, 2014

Page 2: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Alberta’s Ring Roads

• Planned in mid-1960’s around Alberta’s two major cities

• Began purchasing land in late 1960’s and early 1970’s

• Freeway standard roadway

Page 3: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Project Delivery Mechanisms

• Traditional Design-Bid-Build

• Design-Build

• Design-Build-Finance-Operate– also known as Public Private Partnerships (P3)

Page 4: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Edmonton Ring RoadCurrent Status

• 90% open to traffic

• Design and construction started in 2000

• 80 km total length

• Fully complete in fall 2016

• $4.3 billion invested to date

Page 5: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Edmonton Ring Road

Page 6: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Edmonton Ring RoadDelivery Time Frames

• Anthony Henday Southwest – 12 years (Design-Bid-Build)

• Anthony Henday Southeast – 3 years (P3)

• Anthony Henday Northwest – 3.5 years (P3)

• Anthony Henday Northeast – 4.5 years (P3)

Page 7: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Calgary Ring RoadCurrent Status

• 70% open to traffic

• Design and construction started in 2003

• 100 km total length

• $1.9 billion invested to date

• Southwest segment remains to be completed

Page 8: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Calgary Ring Road

Page 9: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Calgary Ring RoadDelivery Time Frames

• Stoney Trail Northwest – 12 years (Design-Bid-Build)

• Stoney Trail Northeast – 3 years (P3)

• Stoney Trail Southeast – 3.5 years (P3)

Page 10: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Public Private Partnership Projects

Page 11: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Alberta P3 Philosophy

• P3 projects must demonstrate value for money

• Risk transferred to the party best able to manage it

• Agreement terms and technical requirements set before bids are submitted

• No negotiation after submission of bids

Page 12: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Risk Allocation - Construction

Page 13: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Risk Allocation - Operations

Page 14: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Challenges:Quality Management

• Implementation of contractor’s quality plan– staff with appropriate experience and qualifications

– clearly defined roles for quality control and quality assurance

– authority for quality management team to affect construction operations

– contractor’s ability to make adjustments as required

• Design and construction issues– meeting technical requirements

– addressing non-conformance

– rejection versus modification

– garnering support from consortium level

Page 15: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Challenges:Fast-Track Design-Build

• Ensure it is designed before it is built

• Everything is on fast-track schedule

• Designs are completed and submitted in sub-elements

Page 16: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Challenges:Regulatory Approvals For River Crossing

• Completed some preliminary engineering for river crossings during Functional Planning Study

• Met with Department of Fisheries and Oceans and Transport Canada well in advance of issuing RFQ

• Incorporated regulatory review and input during RFP process

• Expedited contractor’s ability to obtain regulatory approval for construction

Page 17: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Challenges:Utilities within Project Limits

• Completed Hydrovac exposure of all underground utilities (approximately 500) and made information available to proponents during RFP phase

• Existing utility agreements made available to proponents

• Contractor required to coordinate relocations with their work

• Getting utility crossing agreement with several different companies for construction phase

• Shared risk for cost of utility relocations– up to $120 million borne by contractor– from $120 to $160 million shared 50/50 with department– beyond $160 million shared 25/75 with department

Page 18: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Challenges:Agreements with Railway Companies

• Initiated discussions with CP Rail and CN Rail well in advance of issuing RFQ

• Agreement reached on cost apportionment

• Objective to have railway agreements signed and available to proponents during RFP phase

Page 19: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Challenges:Traffic Management During Construction

• Projects include reconstruction of existing freeway and interchanges

• Significant traffic disruptions occur over full duration of project

• RFP included requirements to submit construction management plan along with staging analysis

Page 20: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Challenges:Public Communications

• Multiple stakeholders

• Public expectations– open house/information sessions

– traffic advisories

– addressing complaints

Page 21: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.
Page 22: Edmonton’s Anthony Henday Drive Unique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014.

Thank you