Implementing Engineering Change Order (ECO)
Implementing Engineering Change Order (ECO)
Responsibility = Manufacturing and Distribution
Manager1.Navigate to the Engineering Change Orders window. (N)
Engineering > ECOs> ECOs2.Use F11 to start a query.3.Enter
the following data:- ECO Number = "enter the ECO number you wish to
query"4.Use Ctrl F11 to run the query.5.(M) Tools > Implement
(B) Yes6.Ensure that the request is completed. (M) View >
RequestsView the components on the primary Bill of
Material7.Navigate to the Bills of Material window. (N) Bills of
Materials > Bills > Bills8.Use F11 to start a query9.Enter
the following data:- Item = "(XX 1000-User Defined Item
Number)"10.Use Ctrl F11 to run the query.
11. Select the ECO tab to view the change order.12.Close the
window.
Oracle ECO Approval process and shortcomings
With the environment of a company becoming more and more
dynamic, the pressure on engineering processes to accommodate for
changes is ever increasing. For such changes to yield engineering
efficiencies, an arrangement can be formulized whereby they cannot
become effective until a responsible agent releases an Engineering
Change Order (ECO). Being an essential component of Engineering
Change Management, an ECO is a written document authorizing to
incorporate changes in the scope of the engineering process. An ECO
specifies changes to one or more items that are logically related
to each other, such as a new product introduction, changes to BOM
structure of an assembly item, component item revision changes and
so on. In oracle EBS system, each ECO specifies changes for one or
more revised items and each revised item change can be associated
with one or more of its corresponding revised component changes.
Depending on the ECO type, an ECO can be enabled to revise/update
only manufacturing items and bills, or be enabled to revise/update
both manufacturing and engineering items and bills. An ECO can
update prototype and/or production routings too.
Every ECO needs to be approved before it can be implemented in
real-time. Standard functionalities of the Oracle EBS support
manual maintenance of static approval lists for this purpose. The
Engineering change order processes involve workflow based and
non-workflow based approval methods. When the ECO is submitted for
approval through a standard EBS workflow, the approvers specified
in the static approval list receive workflow notifications or email
that the corresponding ECO is awaiting their approval. The static
approval list comprises of a set of active employees (recommended
to be apps users) in the system designated as Approvers,
represented by an approval list name. The lists name is the
identifier referenced on every ECO while the approvers of that list
are the identified stakeholders for approval of that document.
Depending on the ECO type and priority, one of the seeded approval
workflow processes is chosen on the ECO based on the application
module setups. Depending on the logic of the workflow process being
selected, the analysis of approval is performed based on the
responses provided by the approvers of the static list. Upon
completion of this vote analysis process, the ECO is considered
Approved or Rejected and its status changes accordingly. Only an
approved ECO can be implemented.
The advantages of this standard EBS methodology are the ease of
control and reduction in system complexity. Also, the number of
approvers in each approval list is unconfined. However, the
downside to this approach is that even a minor change of adding a
new approver to the approval list requires creation of a new
approval list because, any change to the original approval list
would affect all ECOs referencing the same-which may not always be
necessary. Also, the addition and/or removal of approvers from/to
an existing approval list is a manual task involving a lot of
intra-organizational communication and involves considerable time
and effort in this decision making. In essence, the revised items
and revised components on the ECO and their nature determine the
approvers for that Engineering change. An automated approach of
maintaining a system generated ECO specific approval list is dealt
in my whitepaper.
Approvers of an ECO are the stakeholders who are directly or
indirectly affected across the supply-chain due to the proposed
changes for the respective items being revised by that document.
These stakeholders normally include Buyers for purchased
components, Industrial Engineers, Planners, Quality Engineers,
Customer Sales representatives and other stakeholders of the
management committee. Though not all items being revised on the ECO
directly affect all of the above mentioned types (groups) of
stakeholders, the changes proposed for these items can trigger the
alteration of the nature of other related items of the supply chain
that eventually require action from their respective stakeholders.
For Example, when a raw component item undergoes revision change,
it can affect the finished assemblies (which uses the component
item) being manufactured by the organization and/or may mandate
quality compliance testing to adhere to the industry standards
and/or may require advanced planning of all other raw materials
along with the revised item in order to cater to the upcoming
customer demands and/or to manage customer expectations based on
the ultimate results/effects of the ECO.
In the EBS system, the identification of approvers for every ECO
depends on the Bills of Material (BOM) of every ECO revised item or
the revised component. Every item being revised may either be Make
or a Buy item depending on whether it is the assembly or the
component of the Bills of Material respectively. For every ECO
revised item, there is a need to identify its full product exposure
at all BOM levels to identify all other affected items relating to
the revised item. For each of these identified items, the
responsible stakeholders or approvers as described above are to be
identified manually and added to a new approval list. For instance,
even in an ECO comprising of just 2 revised purchased items P1 and
P2 which are raw components of a single level BOM, the minimum
number of affected items would be P1 and P2 and the parent
assemblies of these two. This totals to minimum of 4 affected
items, each of which may determine at least 1 stakeholder each,
directly or indirectly affected due to the revision changes on that
ECO. In such a case, each of these individual stakeholders is to be
added to the static approval list on the ECO. This is a time
consuming process and redundantly increases the cycle time of
implementation of the Engineering change. Moreover, the number of
such static lists grows by time due to the volume of ECOs being
implemented in the organization, thus eventually increasing scope
for errors and chances of delays.
According to an automotive manufacturer organization in
Michigan, USA, the Engineering change coordinators spend anywhere
from 30 minutes to 2 hours for every ECO in identifying all
required approvers who need to be included in the approval cycle
depending on the ECO complexity.
The focus of my white paper is to automate this task of
stakeholder identification within the EBS R12 environment and
reduce this effort to mere mouse clicks.
Please let me know if anyone would be interested to learn more
about my approach and access my white paper and source-code in
relation to accomplishing the same.
Oracle Engineering - Setup steps
Step 1: Set Profile Options (Must)Set the Engineering profile
options for a) ENG: Change Order Autonumbering System Administrator
Accessb) ENG: ECO Departmentc) ENG: ECO Revision Warningd) ENG:
Engineering Item Change Order Accesse) ENG: Mandatory ECO
Departmentsf) ENG: Model Item Change Order Accessg) ENG: Planning
Item Change Order Access
Step 2: Enter Employee (Must)Define employees for your
organization. ECO requestors and approvers must be defined as
employees
Step 3: Define Change Order Types (Optional)You can assign a
change order type to your ECOs, either using the ECO change order
type that Oracle Engineering provides or choosing a change order
type from any number of types you define using your own
terminology, such as Design Revision, Manufacturing Change etc
Step 4: Define ECO Departments (Optional)You can group users
that use the engineering change order (ECO) system through ECO
departments, creating multiple ECO departments within your
Inventory organization.
Step 5: Define Autonumbering (Optional)You can define customized
autonumbering (for a user, organization, or site) for new ECOs or
mass change orders
Step 6: Define Approval Lists (Optional)You can define lists of
approvers required to approve an ECO before itcan be released
Step 7: Define Material Dispositions (Optional)You can define
your own customized material dispositions, and then assign them to
revised items when defining ECOs
Step 8: Define Material Dispositions (Optional)You can define
your own customized material dispositions, and then assign them to
revised items when defining ECOs
Step 9: Define Priorities (Optional)You can define scheduling
priorities for engineering changes to describe the urgency of your
ECO
Step 10: Start AutoImplement Manager (Optional)If you
automatically implement ECOs, you must specify the frequency that
you want the AutoImplement manager to run
Click on revised items to enter revised items, BOM and routing
information.
http://oracleappscommunity.com/oracle/blog/1941/engineering-change-order/
Click ECO Revision.
Click revised items.
Manual implementation
Automatic Implementation
This program implements all scheduled ECOs. Item status should
be scheduled and specify an effective date.