Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 1 | P a g e
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig
City, Metro Manila 1. BASIC PROJECT DESCRIPTION
Project Information
Project Name : 18th AVENUE DE TRIOMPHE
Location : E. Rodriguez, Jr. Avenue, Arcovia City, Barangay
Ugong, Pasig City, Metro Manila
Nature of Project : Residential
Lot Area : 1,898.16 square meters
Building Footprint Area : 1,575.34square meters
Total Built Area : 54,202.07 square meters
Total Development Area : 54,526.89 square meters
No. of Floor Level : • 4 basement parking (B1 to B4)
• 1 level of main lobby/ commercial floor
• 5 levels of podium parking (2/F to 6/F)
• 1 level of amenity deck with residential units (7/F)
• 36 levels of residential (8/F – 45/F w/o 13/F & 44/F)
• With roof deck and machine room
Total No. of Parking Slots : 269 slots
Total No. of Residential Units : 621 units
Total No. of Retail Units : 7 units
Project Duration : 3years and 8months’ development period
(tentative start of construction period is August 2018)
The Project Proponent Megaworld Corporation is engaged in the
investment, acquisition, development, construction and marketing
aspects of prime real estate properties. It was incorporated in
August 1989 and is responsible for numerous residential and office
condominium developments in the Metropolis. By June of 1994, the
company listed its shares of stocks with the Philippine Stock
Exchange, thereby opening its doors for the public to invest in one
of the country’s most dynamic and fast growing real estate
companies.
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 2 | P a g e
Megaworld’s venture into large-scale developments that combine
residential, business and commercial components began with Eastwood
City, a live-work-play centered on the Eastwood City Cyber Park.
Megaworld was the first to launch a development of this caliber and
scale in the local market. Megaworld’s aim to improve the quality
of its products and services as a means of ensuring customer
satisfaction earned it the ISO 9001:1994 certification in 1999 - a
first for any property developer in the country. It has since
upgraded its certification to the ISO 9001:2000 series. Today,
Megaworld brand reflects the proud achievements of a property
company whose various projects have enhanced the urban
landscape-providing the living, working and leisure environments
that allow families to enjoy life better and businesses to thrive
and grow. As project proponent, Megaworld will be involved in the
conceptualization, design documentation, construction,
implementation, marketing, maintenance, and operation of the
development. The proponent's expertise in handling the property
management of its built projects attest to its commitment to
continually update, upgrade and maintain the high quality of its
products for the benefit and satisfaction of its customers.
Developer : Megaworld Corporation
Office Address : 28/F Alliance Global Tower 36th Street corner
11th
Avenue, Uptown Bonifacio, Taguig City, Metro Manila
Contact Persons : Philipps C. Cando
Condesa D. de los Santos
Janine C. Villanueva
Mariano C. Cabo
Telephone No. : (02) 894-6365; (02) 894-6300 loc. 6365
Facsimile No. : (02) 894-6378
E-mail Address : [email protected]
[email protected]
[email protected]
mailto:[email protected]:[email protected]
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 3 | P a g e
2. PROJECT LOCATION AND AREA Project site is located at E.
Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila. The table below shows the boundaries of the project
which is accessible by any vehicle.
Table 1. PROJECT SITE BOUNDARIES
Direction Streets/ Roads Property/ Establishment Barangay/
Municipality
North - Vacant Lot
Barangay Ugong
East - Vacant Lot
South Kaginhawaan Bridge San Miguel Food Ave. C5
Valle Verde
West E. Rodriguez Road
(C5) Mitsubishi Diamond Motor
Corporation
Figure 1. VICINITY MAP
18th AVENUE DE
TRIOMPHE
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 4 | P a g e
Project site are bounded by the following geographic coordinates
please see Table 2 supported by Figure 2 for its lot plan.
Table 2: GEOGRAPHICAL COORDINATES
Perimeter/ boundary Points (based on OCT/ TCT/ etc)
Latitude (N) Longitude (E)
Point 1 14°34’34.742” 121°04’29.73”
Point 2 14°34’34.869” 121°04’29.577”
Point 3 14°34’34.968” 121°04’29.664”
Point 4 14°34’35.686” 121°04’30.225”
Point 5 14°34’35.864” 121°04’30.374”
Point 6 14°34’36.277” 121°04’31.041”
Point 7 14°34’36.237” 121°04’31.078”
Point 8 14°34’36.133” 121°04’31.182”
Point 9 14°34’36.121” 121°04’31.194”
Point 10 14°34’36.01” 121°04’31.314”
Point 11 14°34’35.903” 121°04’31.314”
Point 12 14°34’35.801” 121°04’31.568”
Point 13 14°34’35.782” 121°04’31.596”
Point 14 14°34’34.13” 121°04’30.468”
Figure 2: LOT PLAN
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 5 | P a g e
Impact Areas Delineation of areas are based on the degree/
nature of the potential environmental impacts brought about by the
proposed project. Environmental impacts are generally classified as
primary and secondary impacts. Primary impact areas are those that
are affected directly by the proposed action (i.e. related to
construction & operation of the facility) and areas directly
affected in terms of traffic congestion, noise, air and drainage
lines. Primary Impact Zone consists of the area within the property
itself, areas directly vulnerable to potential geological
phenomenon that may be caused by the project and areas along the
main river system that will be the receiver of water discharges.
Secondary impacts are indirect or induced changes brought by the
project. Typically, these include the associated investments and
change patterns in social and economic activities in the
neighboring areas likely to be stimulated or induced by the
proposed action. This impact zone consists of the areas
Significance and/ or extent and magnitude of the impact may not
only be confined within the primary impact zone but may also extend
to the secondary impact areas. This issue is considered in the
analysis. The location of the primary and secondary impact areas
for the proposed 18th Avenue De Triomphe project as identified in
Figure 3.
Figure 3: VICINITY MAP WITH PRIMARY AND SECONDARY IMPACT
AREAS
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 6 | P a g e
Accessibility The main access to the site development is via C5
Road and it is well-connected to Lanuza Avenue. Vehicles coming
from Lanuza Avenue must make a left turn to reach the project site,
while vehicles coming from C5/ Ortigas must take southbound of C5
and then take a u-turn slot under the Bagong Ilog flyover to reach
the project site entrance. Meanwhile, taxis or shared-service
vehicles (e.g., Uber, Grab) are now easily available and are
expected to provide more individualized services. It is also
expected that there will be UV Express services to the area. 3.
PROJECT RATIONALE Megaworld is re-shaping the Metro Manila skyline
and raising standards for commercial, residential and office
development in the Philippines to promote a high-level standard in
terms of quality, innovativeness and responsiveness to consumer's
needs. A new center of live work and play environment, the proposed
18th Avenue De Triomphe project is the perfect example. The project
will be a pioneering residential development intended to provide
residential spaces to Pasig City based executives and young
professionals. It offers convenience in terms of easy accessibility
to work and other key locations. The increase in demand for more
affordable residential spaces in terms of proximity to the work
place, shopping malls and school inspired the proponent to come up
with the project. The project will offer a variety of residential
options with a choice of flexible unit sizes and types to building
designs and facades. The project also offers attractive amenities
and security. The new development will create a unique synergy and
be a special place to live, work and play. The general objectives
of the project, among others, are to provide employment during the
construction and operational phases and to contribute to the
economic growth of the area. Megaworld aims to ensure your outmost
satisfaction through high quality products conceived in the spirit
of innovation and born-out of continuous research and development.
It gives priority to the continuous upgrading of the skill and
expertise of its key people so that they can provide service of the
highest quality. 4. PROJECT COMPONENTS The proposed project site in
a land area of about one thousand eight hundred ninety-eight and
16/100 square meters (1,898.16 sq. m.) lot. This will consist of
forty-five (45) – storey Residential Building with four (4)
basement levels as parking area. The building footprint area of the
project is one thousand five hundred seventy-five and 34/100 square
meters (1,575.34 sq. m.).
Ground floor serves as main lobby and retail area. Hence,
basement 1 to 4 and 2nd floor to 6th floor serves as parking space
with a total of two hundred sixty-nine (269) parking slots. While
7th floor serves as amenity deck with residential units, 8th floor
up to 28th floor without 13th floor which is a low zone with an
area of eighteen thousand four hundred forty-six and 60/100
(18,446.60) square meters while 29th floor up to 45th floor without
44th floor has an area about fourteen thousand seven hundred
fifty-seven and 28/100 (14,757.28) square meters. The total
development area including parking and open/ site development area
will be fifty-four thousand five twenty-six and 89/100 square
meters (54,526.89 sq. m)
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 7 | P a g e
Please see Table 3 for the area breakdown of the proposed
project and its functions and approximate space allocations as
summarized.
Table 3: AREA BREAKDOWN
Designation Level No. of Floor Total Built Area
(sq. m.)
Parking B1 to B4 4 7,315.32
Main Lobby/Commercial GF 1 1,838.65
Podium Parking 2/F 1 1,767.77
3/F to 6/F 4 7,338.68
Amenity Deck 7/F 1
1,192.97
Residential
622.80
8/F to 28/F w/o 13/F 20 18,446.60
29/F to 45/F w/o 44/F 16 14,757.28
Roof Deck / Machine Room - - 924.00
TOTAL 54,204.07
Total Lot Area : 1,898.16 square meters Building Footprint Area
: 1,575.34 square meters Main Lobby/ Commercial Area : 1,838.65
square meters Parking Area : 16,421.77 square meters Residential
Area : 33,826.68 square meters Common/ Amenity Area 1,192,97 square
meters Roof Deck/ Machine Room 924.00 square meters Open Space/
Site Development Area : 322.82 square meters
Total Development Area 54,526.89 square meters Support Services
and Facilities As a developer of the proposed development, MC shall
be responsible for the conceptualization, design, construction and
maintenance of the project. The proposed project is designed for a
more private and comfortable living condition with landscaped area
and other recreational amenities. The proposed development will
have the required fire safety utilities in modern hotel such as
automatic fire sprinkler system, smoke and heat detector system,
water supply and drainage system, electrical and lighting system,
mechanical ventilation and elevator system, telecom and cable TV
system, among others. Some of the features and highlights of the
project are as follows:
• Automatic heat/ smoke detection and fire sprinkler system for
all floors
• Private and comfortable working condition with landscaped area
and recreational amenities
• Cistern tank and underground cistern for ample water
supply
• 50% standby power generator
• Fire command center
• Building administrators/ security officer
• Closed Circuit TV (CCTV) monitoring for selected areas
• Variable Refrigerant Flow (VRF) AC system
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 8 | P a g e
• Provision of own Sewage Holding Tank
• Multi-level parking
There will be security guards on duty for 24 hours to secure
peace and order and security of the materials in the construction
site. The new development will further enhance the area with a
promise of a home and lifestyle of modern convenience for the Metro
Manila based executive and professionals. General Layout of
Facilities: Commissioned to undertake the design of the project are
as shown in Table 4.
Table 4: LIST OF CONSULTANTS
TRADE CONSULTANTS
ARCHITECTURAL Design Alliance
STRUCTURAL ESCA Inc.
MECHANICAL
Isagani M. Martinez Consulting Engineer (IMMCE) ELECTRICAL
PLUMBING AND SANITARY
FIRE PROTECTION
EGGAR Carlo D. Dayanghirang, Msc. Quaternary Geology
TIA STRIDE Consulting Inc.
Please see Figure 4 for the site development of the project
while Figure 5 shows the perspective plan of the proposed
project.
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 9 | P a g e
Figure 4: SITE DEVELOPMENT PLAN
Figure 5: PERSPECTIVE PLAN
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 10 | P a g e
5. PROCESS/ TECHNOLOGY
Power Supply Estimated power requirement of about 5.5 MVA of the
project will be taken from Cubao Meralco Substation source during
full occupancy. There will also be a back-up generator set for the
building designed to supply emergency powers during power outages.
The proposed project is a Residential building. As of now we don’t
have yet the design specifications for the generator sets.
Furthermore, in case there will be a generator sets on the actual
operation we will file the Application for “Permit to Operate” Air
Pollution Source Installations (APSI). Water Supply Water will be
supplied by Manila Water Company Inc. during the construction and
operation phases. The estimated water consumption will be 622.53 m3
per day during the full occupancy of the proposed development.
Wastewater Management Plan The proposed project will construct/
provide its own sewage pre-treatment plant to accommodate its need
as the new development progresses. Solid Waste Management Plan
Practically almost all of the component of the current solid wastes
management program being implemented by MC for the existing
building is already consistent with the applicable provisions of
the RA 9003, also known as the “Ecological Solid Waste Management
Act of 2000” It basically covers the collection, temporary storage
and hauling/ disposal of the wastes under consideration which take
into account the segregation/ sorting of wastes being handled for
purposes of material recovery, recycling and re-use and most
importantly reduction of the volume of wastes to be finally
disposed. As the implementation of the program for the current
operation of MC proved effective, it will also be adopted and
implemented for the proposed project. 6. PROJECT DURATION
Based on the proposed construction plan of the project, it is
tentatively scheduled to commence by August 2018 and expected to be
completed within three (3) years and six (8) months as its
development period. All necessary regulatory requirements with
respect to construction activities will be complied faithfully by
the proponent.
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 11 | P a g e
7. PROJECT PHASES, KEY ENVIRONMENTAL ASPECTS, WASTES, ISSUES,
BUILT-IN MEASURES
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
I. PRE-CONSTRUCTION PHASE
Engineering Geological and Geohazard Assessment Report
(EGGAR)
• Adopt EGGAR Recommendations and Conclusions
• Proponent Part of Design and Development Phase
Traffic Impact Assessment (TIA) and Traffic Management Plan
• Adopt TIA Recommendations and Conclusions
Occupational Health and Safety Program • Provision of
Occupational Health and Safety Plan
• Contractor/ Project Manager Emergency Preparedness and
Contingency Response Plan • Provision of Emergency
Preparedness and Contingency Plan
Solid Waste Management Plan • Implement RA 9003 (Ecological
Solid Waste Management Act of 2000)
• PCO/ Contractor
Hazardous Waste Management Plan • Implement RA 6969 (Toxic
Substances and Hazardous and Nuclear Wastes Control Act of
1990)
II. CONSTRUCTION PHASE
Environmental
Aspect #1
A. The Land Solid Waste
• Generation of solid construction wastes
• Strict implementation of Solid Waste Management Act which
include waste segregation, re-use and recycling and waste audit
along construction waste streams
• Contractor/ Project Manager
• Php3,000.00 per month
• Included in construction contract
• Contractors shall remove and dispose properly all debris and
excess material
• If generation of too much solid wastes is inexorable,
proper
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 12 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
housekeeping or efficient/ frequent disposal of solid wastes
should implement strictly
• Accumulation of domestic solid waste in the form of used
paper, cans, bottles, food refuse, plastics, etc.
• Provide Material Recovery Facility to utilize proper
sanitation and good housekeeping
• Contractors shall formulate guidelines on garbage disposal and
impose penalty to any workers who dispose solid waste
indiscriminately
• Provision of proper storage for raw materials
• Proper coordination with the City garbage collection system
from prompt removal of garbage from site
• Increase or provide additional garbage bins that will be
scattered throughout the entire project site to prevent
irresponsible waste disposal
Hazardous Waste
• Generation of special wastes or household hazardous wastes
such as paints, thinners, household batteries, lead-acid batteries,
spray canisters and the like
• Provide hazardous waste storage room for proper handling and
disposal of hazardous waste materials in accordance with RA
6969
• PCO • Php1,000.00 per month
• Included in construction contract
• Secure Hazardous Waste ID prior to construction
• Secure PCO Accreditation prior to
• Hazardous materials should be stored under watertight
conditions to prevent their discharge in storm water
• Hazardous wastes must be stored in sealed containers
constructed
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 13 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
• Generation of used oil and grease from the equipment and
vehicles
of suitable material with label that clearly identifies the
contents and accumulation date
Registration as Hazardous Waste Generator
• Oil and grease spills from heavy equipment and vehicles
• All project personnel should be trained to recognized
hazardous wastes on the project and to respond appropriately to
ensure safety and protect the environment
• Contractor/ Project Manager
Sub-soil Condition
• Risk of caving in during excavations
• Usage of dump trucks and pay loader to remove any excavated
soil from the site during earthwork should minimize erosion
• Contractor/ Project Manager
• Php10,000.00 per lot
• Included in construction contract
• Provision of shoring, bracing, and protection of excavations
with due importation given to proper spacing of braces, shores,
whenever necessary
• No added cost
• Monitoring and inspection of all possible movements cracks in
adjacent structures
• Necessary slope protection measures and adaptation of best
engineering practices will be implemented to prevent
excavation-related hazard
Integrity of Structures
• Stability of building foundation
• The building would be designed to conform to the National
& International Structural Code (i.e. NSCP, ASCE, ASTM and
AISC)
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 14 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
and would be capable of resisting major earthquake and stable
enough to withstand external loads
• Implementation of plans and specification will be strictly
monitored during construction thus recommendations of the soil
investigation report will be considered
Environmental
Aspect #2
B. The Water Water Quantity
• Increased water consumption in the area
• Implement water conservation • Contractor/ Project Manager
• No added cost
• Included in construction contract
Water Quality
• Possible contamination of substance spills/ leaks
• Provide/ build temporary toilet facilities with septic tank
for workers and disposed off-site to an STP with valid discharge
Permit from EMB
• Contractor/ Project Manager
• Php10,000.00 per lot
• Included in construction contract
• Provide grease trap/ oil and water separator for food
wastes
• Implement proper handling of liquid wastes
• Implement proper handling of liquid wastes
• Drivers and operators shall be instructed on proper
maintenance of vehicles and equipment. Maintenance activities
should not be done on-site to avoid spillage of oil and grease
Flooding/ Siltation/ Effluent
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 15 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
• Siltation and turbidity of receiving drainage line and water
body
• Liquid wastes or sewage discharged into a river or the sea
• Drainage system will be provided with silt trap so that
construction debris/ waste that will be generated in the
construction site will not clog up that might cause flooding in the
area. Silt trap minimizes siltation
• Contractor/ Project Manager
• Php5,000.00 per month
• Included in construction contract
• Installation of perimeter fence to avoid surface run-off along
the street
• To avoid scattering of mud there should be a designated wash
bay area for vehicle
• Stockpile aggregates properly
• Regular cleaning of drainage canals
• Earthwork activities would also be scheduled during low
precipitation periods. Proper work scheduling to hasten excavation
works
• Exposed surfaces will be cemented or landscaped to stabilize
the soil
Environmental
Aspect #3
C. The Air Dust Generation
• Generation of dust/ debris
• Regular watering on-site construction area are expected to
limit fugitive dust levels to acceptable levels
• Contractor/ Project Manager
• Php10,000.00 per lot
• Included in construction contract
• Increased in TSP level
• Constructing perimeter fences around the construction site to
serve as windbreakers or barriers
• Proper work scheduling of cut-and-fill of the ground to hasten
this activity and lessen the exposure of
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 16 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
the earth materials to wind and rainfall
• Use of canvass covers for delivery trucks
• Ensure that the transport vehicles moving around the
construction site are regulated to minimum
Air Quality
• Increase of TSP, NOX, SO2 levels at the construction site
• The equipment that will be brought to and used in the
construction site has to be in good working condition
• Contractor/ Project Manager
• Php10,000.00 per lot
• Included in construction contract
• Proper maintenance of genset and other equipment should be
implemented to help reduce the level of SO2 and NO2 emission and
reduce fuel consumption
• Limit the movement of vehicles in the area through the
assistance of traffic enforcer
• Schedule delivery of construction materials during non-peak
hours
• Assign unloading and loading area for deliveries
Noise Quality
• Possible excessive noise generation
• Construct temporary fence to acts as barriers and to confine
noise within the project area
• Contractor/ Project Manager
• Php10,000.00 per lot
• Included in construction contract
• Equipment should be properly maintained to minimize noise
emissions
• Use of mufflers on equipment mounts to lessen the noise
produce
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 17 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
• Proper scheduling of works to avoid the elevated cumulative
noise impact
• Noise generating activities shall be made during daytime hours
to ensure minimal noise disturbance to the community (7:00 AM to
6:00 PM)
Environmental
Aspect #4
D. The People Health and Safety
• Safety of workers and passersby
• Strict implementation of construction safety rules and
regulations
• Contractor/ Project Manager
• Php40,000.00 per lot
• Included in construction contract
• Appointment of safety engineers and project nurse
• Provide first aid center, medical and emergency kits within
the job site
• Provision of Personal Protective Equipment (PPE) to the
workers
• Post warning and safety reminders signs at strategic areas
• Provide fire extinguishers and safety nets at job site
• Conduct seminars on environmental management and
monitoring
• Provision of construction fence with lighted canopy and safety
net around the project sire for the falling debris
• Ensure structural openings area covered/ protected adequately
(e.g. sumps, shafts, floor openings, etc.)
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 18 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
Peace and Order
• Probable disturbance of peace
• Strict implementation of No gambling and drinking policy
• Contractor/ Project Manager
• Php2,000.00 per lot
• Included in construction contract • Assign roving guards at
night
• Imposed disciplinary measures
• Coordination with barangay and police authorities
Traffic
• Increase in traffic volume
• A traffic management plan will be implemented to have a smooth
flow of traffic
• Contractor/ Project Manager
• Php2,000.00 per lot
• Included in construction contract
• Delivery of construction materials will be schedule during
off-peak hours to minimize impact
• Hauling of cut soil and construction waste by dump trucks
would be scheduled to minimize impact on vehicular flow
• Coordination with local authorities on traffic management
• Traffic control devices such as barricades, cones, blinkers
shall be used to guide or channel traffic
• The arrangement of traffic control devices used to stop or
channel traffic (barricades, cones, blinkers) shall be periodically
inspected to ensure that the devices are in good condition
• Caution, warning and construction information warning signs
will be displayed as appropriate to warn or inform vehicle traffic
passing
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 19 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
along the roadways near the construction site
• Assign competent traffic assistance to motorists entering the
property to act as traffic signal man most especially during
hauling and deliveries of construction materials
Socio-economic
• Increase in Job and Business Opportunities
• Manpower requirement preferably to come from the community or
who are qualified skilled worker is to be given priority
• Contractor/ Project Manager
• Construction labor cost
• Included in construction contract
• Purchased construction materials, which can be supplied by
business enterprises in the city and adjacent cities
• Additional income and benefit to the local government
• Secure and pay necessary business permits and clearances local
LGU shall directly benefit from the project due to the additional
fees that would be collected from taxes and additional revenues
from licenses and permits from various commercial establishments
within the project site
• Contractor/ Project Manager
• Construction labor cost
• Include in construction contract
• Attract new investors and expected to create more new
businesses to be developed in the area resulting to increase in
property value
III. OPERATION PHASE
A. The Land Solid Waste
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 20 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
Environmental
Aspect #1
• Solid waste generation
• Waste minimization, segregation, and recycling
• PCO • Php3,000.00 per month
• Included as operational cost • Provision of a garbage chute
and
centralized garbage room for the collection of the occupants for
each building
• Establish Material Recovery Facility (MRF) to minimize
residual wastes
• Coordination with the city government for regular collection
of garbage
• There will be daily monitoring of the solid waste by the
assigned maintenance personnel to check whether the segregated
wastes are brought to their designated containers
Hazardous Waste
• Generation of special wastes or household wastes such as
paints, thinners, household batteries, lead-acid batteries, spray
canisters and the like
• These include wastes from residential and commercial sources
that
• Batteries/ generator set that are malfunctioning will be
brought back to factories for checking or replacement
• PCO • Php1,000.00 per month
• Included as operational costs
• Permit to Transport will be secured prior to hauling
• Secure hazardous waste ID
• Segregated busted fluorescent lamps and used oil from regular
waste
• Hazardous wastes will be collected in containers for
protection from spillage during storage and transport while an open
top metal drum will be used for other types of hazwastes
• Labeled containers/ drums will be brought to a qualified waste
facility
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 21 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
comprise of consumer electronics, washing machines, air
conditioners, etc.) batteries, oil and busted lamps
for proper disposal or recycling accredited by DENR
• Accumulation of used oil from generator set
• Provide hazardous waste storage room for proper handling and
disposal of hazardous waste materials until collected by DENR
accredited hazardous waste collector/ transporter
• Designation of specific space for containers/ bins/ facility
for hazardous wastes at MRF area
• Spillage on fuel storage tanks
• Proper maintenance of storage tanks
Green Area
• Wear and tear of landscape during operational period
• Continuing maintenance and development of green areas,
playgrounds and landscaped areas
• PCO • Php1,000.00 per month
• Included as operational costs
Environmental
Aspect #2
B. The Water Water Quantity
• Increase demand for water supply
• Ample water supply for the residents would be assured through
the provision of domestic water tank, fire water reserved and an
underground water tank for the whole development
• PCO • No added cost
• Included as operational costs
• The residents shall be encouraged to conserve water by
promoting water conservation practices and
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 22 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
regulated water pressure through distribution of leaflets/
pamphlets
Water Quality
• Generation of domestic wastewater/ run-off
• Provide grease trap/ oil and water separator for food
wastes
• PCO • Php4,000.00 per month
• Included as operational costs • Provision of holding tank
facility of
the project
Environmental
Aspect #3
C. The Air Air Quality
• Emission of carbon monoxide, NO2 from use of genset
• Regular monitoring and maintenance of the generator set shall
be implemented by the administration personnel
• PCO • Php20,000.00 per month
• Included as operational costs
• Secure Permit to Operate upon operation of generator sets
• A Permit to Operate will be secured upon operation of
generator set to comply with Clean Air Act
• Increase in the volume of vehicles that cause excessive
emission of carbon monoxide
• The project will have landscaped gardens and different
ornamental plants to minimize air pollution
• PCO • As needed • Included as operational costs
• Residents would be provided enough parking spaces for their
vehicles
• To minimize air pollution inside the parking levels, adequate
air ventilation will be provided
• The resident shall be advised to properly maintain their
vehicles to minimize gaseous emissions
• Traffic enforcers shall be enjoined to enforce traffic
regulations particularly rules on street parking
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 23 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
Noise Quality
• Possible excessive noise generation
• The use of generator will only be during power failure
• PCO • Php10,000.00 per lot
• Included in operation costs • The unit will be provided with
an
exhaust silencer and will be located in an enclosed area with
sound-absorbing materials
Environmental
Aspect #4
D. The People Health and Safety
• Natural hazards (fire, earthquake)
• All units and common areas are provided by fire and smoke
detector alarm system and an automatic fire sprinkler system. There
is also a fire reserve tank for continues water supply in case of
emergency
• PCO • Php40,000.00
• Included as operational costs
• Secure Fire Safety Inspection Certificate
• The building is designed in conformance to the National &
International Code (i.e. NSCP, ACI, ASCE, ASTM & AISC) and
would be capable of resisting major earthquakes and stable enough
to withstand external loads
• Probable disturbance of peace and order
• The property management shall enforce strict monitoring/
checking of all common areas
• A logbook for all visitors will be stationed at the reception
area
• Information dissemination shall be provided to all residents
in case of bomb threat
• Imposed disciplinary measures
• Coordination with barangay and police authorities
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 24 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
• Possibility of bomb threats, robbery and any other criminal
activities
• Provide competent security services/ regular security patrol
throughout the property
Traffic
• Increase in traffic volume
• Strict enforcement of traffic rules and regulations around the
project area
• PCO • No needed cost
• Operational policy
• There will be an assigned security officer who will act as
traffic control in coordination with the LGU to ensure smooth
traffic flow and proper enforcement of traffic rules and
regulations
• Possible parking problems
• Slower traffic flow due to increase in vehicle volume
• Provision for traffic signs and sufficient parking space for
the residents
• Intrinsic in site development plan • Adopt recommendations
from
Traffic Impact Assessment Study for implementation
Socio-economic
• Increase in job and business opportunities (increase in
population)
• Priority hiring of local qualified residents
• Property Administration
• As needed • Included as operational costs • Indirectly
provides social services
to the City through payment of its taxes
• Additional income and benefit to the local government
• LGU shall directly benefit from the project due to the
additional fees that would be collected from taxes and additional
revenues from licenses and permits from various commercial
establishments within the project site
-
Project Description for Public Scoping 18th AVENUE DE TRIOMPHE
E. Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 25 | P a g e
Project Phase/ Environmental
Aspect
Environmental Component Likely to be
Affected
Potential Impact Options for Prevention or
Mitigation or Enhancement Responsible
Entity Cost
Guarantee/ Financial
Arrangements
• Attract new investors and expected to create more businesses
to be developed in the area resulting to increase in property
value
IV. ABANDONMENT PHASE
Concerns the lifespan of the project or the demolition of the
building after a certain number of years. After the construction of
the building, abandonment is not foreseen for this type of project
except for the abandonment of the temporary facilities used during
construction. The General Contractor will free the site from
construction debris and temporary structures such as bunk houses,
stockrooms, toilets, etc. Instead of assigning a perpetual service
life, a 50-year life span of the buildings are being considered.
This assumes that the future association will operate and redevelop
the property after its full depreciation and deterioration of the
building utilities.
Shifting of trust in business may affect the future of the
project. However, the facility may be able to adopt new focus of
business agenda. Thus, the facility has many options to make it
usable for any type of business opportunities.
-
Public Description for Public Scoping 18th AVENUE DE TRIOMPHE E.
Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 26 | P a g e
Project Site Photos:
Latitude: 14° 34' 34.097" Longitude: 121° 04' 30.319" The
picture was taken approximately southwest of the project which is
facing to tempacil of the contractor.
Latitude: 14° 34' 35.009" Longitude: 121° 04' 31.909" The
picture delineates the build tempacil of contractor where the
proposed project located.
Latitude: 14° 34' 35.490" Longitude: 121° 04' 31.330" This
picture depicts the material’s staging area
Latitude: 14° 34' 35.249" Longitude: 121° 04' 31.690" The
picture was taken approximately southeast of the project which can
see a bulk of soil.
-
Public Description for Public Scoping 18th AVENUE DE TRIOMPHE E.
Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 27 | P a g e
Latitude: 14° 34' 35.490" Longitude: 121° 04' 31.330" This
picture depicts the material’s staging area
-
Public Description for Public Scoping 18th AVENUE DE TRIOMPHE E.
Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 28 | P a g e
Latitude: 14° 34' 35.009" Longitude: 121° 04' 31.909"
The picture delineates the build tempacil of contractor where
the proposed project located.
-
Public Description for Public Scoping 18th AVENUE DE TRIOMPHE E.
Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 29 | P a g e
Latitude: 14° 34' 35.249" Longitude: 121° 04' 31.690" The
picture was taken approximately southeast of the project which can
see a bulk of soil.
-
Public Description for Public Scoping 18th AVENUE DE TRIOMPHE E.
Rodriguez, Jr. Avenue, Arcovia City, Barangay Ugong, Pasig City,
Metro Manila
MEGAWORLD CORPORATION 30 | P a g e
Latitude: 14° 33' 32.04" Longitude: 121° 03' 18.17" The picture
was taken approximately southeast of the project which is beside at
The Palace.