-
International Bank for Reconstruction and Development
E-235 VOL. 14 SecM98-525
FRO.MI: The Secretary July 2, 1998
THAILANDEGAT - INVESTMENT PROGRAM SUPPORT PROJECT
PARTIAL CREDIT GUARANTEE FOR 2X$300 MILLION BOND
ISSUESENVIRONMENTAL ASSESSMENT SUMMARY
I. Attached is the environmental assessment summary for the EGAT
- InvestmentProgram Support Project. The proposed Project would
provide IBRD's Partial CreditGuarantee for each of two bond issues,
each of approximately US$300 million, in theThai fiscal years
(October 1 to September 30) FY1998 and FY1999 respectively, to
meetIpart of the finan.ing gap for EGAT 'investments during the
period FY1998 - FY2000, forpower generation and transmission
facilities whose implementation has alreadycommenced. Specifically,
the sub-projects are:. (a) generation: (i) the 300 MW KrabiThennal
Unit 1; (ii) the 2x700 MW Ratchaburi Thermal Units I and 2; (iii)
the3x600MW Ratchaburi Combined Cycle Blocks 1-3; and (iv) the 600
MW Wang NoiCombined Cycle Block 2; and (b) transmission: (i) the
500 kV Transmission System for.evacuation of power from IPP plants
in Thailand and the Hong Sa Project in Laos; (ii)strengthening of
the Bulk Power Supply System for greater Bangkok, Stage 1; (iii)
Stagen of the EGAT-TNB (Malaysia) Transrnission Interconnection;
and (iv) the TransmissionSystem Expansion Project 9.
2. The environmental assessment summary was prepared by the
borrower, theEietctricity Generating Authority of Thailand (EGAT).
Circulation of the summary doesnot signify evaluation or
endorsement by the Bank. The environmental assessment issubject to
further review and change during the appraisal process.
3. Questions may be referred to Mr. Darayes Mehta (ext.
80472).
Distribution
Executive Directors and AlternativesPresidentBank Group Senior
MdnagementVice Presidents, Bank, IFC and MIGADirectors and
Department Heads, Bank, IFC and MIGA
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
-
EGAT - INVESTMENT PROGRAMSUPPORT PROJECT
WORLD BANK PARTIAL CREDITGUARANTEE
EXECUTIVE SUMMARY
ENVIRONMENTAL IMPACTASSESSMENT
BangkokJune 26, 1998
-
EXECUTIVE SUMMARYENVIRONMENTAL IMPACT ASSESSMENT
The proposed project includes four generation components at
three sites and fourtransmission components in various stages of
completion. Generation Components:Krabi Thermal Unit 1 (300 MW);
Ratchaburi Thermal Units 1-2 (2x700 MW) andCombined Cycle Blocks
1-3 (3x600 MW); and, Wong Noi Combined Cycle Stage 2 (600MW).
Transmission Components: 500 kV Transmission System for IPPs;
Strengtheningof Bulk Power Supply System for Greater Bangkok Area;
EGAT-TNB (Malaysia) - Stage IIInterconnection; and Transmission
System Expansion No. 9 (TS. 9). Executive Summariesof the
environmental impact assessments (EA) or environmental impact
analyses (EIA) ofeach component prepared by EGAT are attached.
Environmental Protection. Power plants and transmission lines
are subject to stringentenvironmental standards in Thailand (more
stringent than the Bank guidelines in general).The proposed
generation facilities will utilize cleaner fuels like natural gas.
Flu GasDesulfurization (FGD) will be installed for power plants at
Rachaburi and Krabi (fuel oilwith 2% sulfur). The selected FGD
systems represent commercially proven technologyand will be
designed to remove at least 80% of sulfur at Krabi and 90% at
Ratchaburi. Anenvironmental monitoring and management group will be
instituted at each facility inorder to meet regulations, along with
EGATs corporate policy goals and responsibility.
Environmental Considerations. In accordance with the Bank
Operational Directive4.01 on Environmental Assessment, the overall
project has been assigned Category 'A'.EGAT, with assistance of
local and international consultants, prepared the EAs for thefour
generation facilities (at three sites) and two transmission lines
as required by theThailand's regulation. Focused EIAs for the
remaining two transmission lines (notrequired by the Thailand's
regulations) were prepared for the Bank project. All EAsrequired by
the Thailand's regulation have been submitted and most of them
approved bythe Office of Environmental Policy and Planning (OEPP)
of National EnvironmentalBoard (NEB). The two transmission line EAs
were reviewed by the Bank earlier as a partof another project and
were found satisfactory. EGAT has provided addendum andexecutive
summaries to the EAs for this project which provide updated
information,further clarification and explanation. All eight
components of the project have beendesigned and will be implemented
in accordance with the modem concept ofenvironmental management and
Thailand's regulations. EGAT is also consideringimplementation of
ISO 14001 at their current generation facilities.
Fuel transport EAs for each generation facility (not financed
under this project) have alsobeen prepared by fuel suppliers (e.g.
Petroleum Authority of Thailand - PTT) andreviewed and approved by
the OEPP in Thailand. These EAs have been sent to the Bank.
Generation Components. For power generation, EGAT has proposed
to useenvironmentally friendly and clean natural gas at Wang Noi
and Rachaburi Combinedcycle and 2% sulfur fuel oil for Rachaburi
thermal and Krabi. FGD systems with at least
2
-
80% efficiency at Rachaburi thermal and 90% at Krabi will be
utilized to meet stringentsulfur dioxide emissions standards in
Thailand. Particulates will also be partiallycontrolled by the FGD.
The theoretical amount of particulate emissions at
Ratchaburithermal and Krabi are expected to be around 70 mg/Nm3
which is less than the 1988Bank guidelines (applicable when these
power plants were designed and initiated butthese are higher than
the 1998 guidelines of 50 mg/Nm3>. Dispersion modeling for the
sitepredicted maximum ground level contribution of the power plant
to be luss than 5 urnimnwhich is minimal. Considering the location
of these facilities, further particulate controlis not needed.
However, ambient monitoring will be conducted and if power plant
isshown to be a major contributor to the exceedance of particulate
standards, furthercontrols may be considered.
When possible, gypsum which is a by product of FGD will be
utilized for constructionindustry. Nitrogen oxides will be
controlled at each facility by low NOx burners, flue
gasrecirculation and water injection as required to meet emissions
standards. Continuousmonitoring for sulfur and nitrogen oxides and
early warning systems for air pollution willbe instituted at each
facility.
Water usage will be minimized by employing close loop (or
recirculating cycle) coolingsystems. Water intakes will be
pretreated and discharges will be controlled to meet Thaistandards
and World Bank guidelines. A holding pond, water reservoir and a
waste watertreatment system will be constructed to reduce discharge
water temperature. Whenrequired, water will be neutralized before
being discharged. Oil/water separators areprovided at oil storage
and handling areas, and sanitary sewage would be treated. Net
andother methods to prevent fish entering the inlet water pipes
will be employed.
EGAT facilities will be surrounded with visual screens like
greenbelt and other barriers toreduce noise and intrusion. Noisy
activities (mine blasting) will be conducted only duringthe day
time and in coordination with the local authority.
Transmission Components. In selection of routes for transmission
lines andsubstation sites, EGAT uses design criteria to minimize
environmental impacts on forest,wildlife, watershed areas,
populations, archeological sites. and scenery. Transmissionline
right of ways are not to be located through: (a) restricted Class
IA watershed area,according to laws and regulations; and, (b) holy
places, archeological sites andgovernment sites. Transmission line
right of ways should also avoid: (a) watershed areaclass IB, Class
C forest conservation areas, mangrove forest, national parks and
otherconservation areas; (b) community and developed areas; (c)
lines should be in parallelwith or close to telephone and telegraph
cables for a long distance to avoid interference;and, (d)
airports.
Detailed Route Surveys. Before construction of the transmission
system, detailed routesurveys will be performed by EGAT staff
together with the Royal Forest Department(RFD). The number of
forest trees to be cut will be documented. In addition, final
route
3
-
selection adjustments to avoid dwellings and circumvent other
areas of potential negativeimpact will be made, according to EGATs
environmental design criteria.
Construction. EGATs guidelines for construction activities are:
(a) avoid installation ofnew access roads for construction
purposes; try to utilize existing trails; (b) nocutting of trees
over the limitations set by RFD; and, (c) clean up construction
sitesupon completion of construction work.
Maintenance of the Right of Way. Along the valleys, only trees
considered to behazardous to the stability of the transmission
system would be cut down. Landownersare permitted to cultivate
economic crops along the right of way corridors. Uponcompletion of
transmission line construction work, ground cover around the towers
willbe planted and land contouring will be done as required to
provide a protective coveringfor the earth and to prevent soil
erosion. No herbicides are used in right of waymaintenance.
Environmental Management and Monitoring. For all components in
this project,environmental aspects have been taken into
consideration and should cause minimaldisturbance to the human and
natural environment. An environmental managementprogram consisting
of mitigation, monitoring, and action plans at the plant level
havebeen incorporated into the project to confirm environmental
performance on a sustainablebasis. Monitoring will be conducted at
each facility for air and water effluent quality,noise. ground
water hvdrologv and qualitv. aauatic ecologv. solid waste
management.socio-economic indicators, public health and safety.
Analysis of Alternatives. In planning and development analysis,
EGAT takes intoaccount the alternatives for: site locations, fuel
type and transport, and gypsum supply anddispo,sal when FGD is
utilized. Before the projects are included in the formal
powersector development (PDP) analyses of: feasibility;
alternatives; fuel availability bothlocally and in the
international markets; flexibility and reliability of fuel supply;
transportoptions; initial environmental impacts; land availability
and ownership; extent ofresettlement; socio-economic impact;
political and international treaties; and others areperformed by
EGAT along with local and international consultants. EGAT also
takes intoaccount the Government of Thailand's needs related to
energy security by diversifyingfuel -use and sites. The projects
that satisfy these criteria, are further processed through aprogram
called PRO-SCREEN for prioritization and inclusion in PDP. All
componentsunder considerations in this project were selected after
an extensive analysis as describedabove.
Public Consultation. EGATs corporate policy requires public
participation and seekstheir acceptance of the development project.
For the components in this project, EGATsobjectives in public
consultation was to obtain the opinions, needs, problems
andobstacles of the people and communities living in the
operational areas, as well asdisseminating accurate information
about the project. Local communities, leaders, andgovernment and
non-governmental organizations (NGO) were canvassed and
requested
4
-
recommendations. Several public meetings were held at each of
the project site to discussconcerns, mitigation measures and seek
resolutions. Alternatives to the projects werediscussed with the
local communities, as appropriate for each site as detailed in
theproject specific environmental executive summaries. Even though
public participation isincluded in EGAT policy, the timing,
transparency and public awareness of planningconsiderations in
project selection will be further improved.
5
-
Executive summaryKrabi Thermal Power Plant Unit 1 and 2
Environmental Impact Assessment
1. Introduction: The Krabi Thermal Power Plant Unit I and 2 will
be located atTambon Khlong Khanan, King Amphoe Nua Khlong, Changwat
Krabi. The plant will use oil(2% sulphur) as main fuel source. The
nominal capacity for each unit is 300 MW. The proposedpower plant
would be located within EGAT premises near the old lignite-fired
Krabi PowerPlant which was decommissioned in September of 1995.
Civil works had just begun on site asof June, 1998.
2. Fuel Transportation: The Krabi Power Plant will use domestic
or imported oil. Thebarge transport EIA has been submitted to the
Thailand Office of Environmental Policy andPlanning (OEPP). Oil
would be transfered from ships to 1,000 ton barges, through an
estuary(24 km) to a dock near the power station, and then via
pipeline to the power station.Preliminary analysis indicates an
alternative for cost and environmental reasons may be apipeline
from an offshore ship loading facility, to an underground pipeline
(16 km) along anexisting road right of way to the power station.
This alternative is under study; if thisalternative is preferred,
the Pipeline EIA would be subject to review by the World Bank
afterapproval by OEPP.
3 Fuel Storage: Backup fuel (diesel and heavy stock) would be
stored in abovegroundtanks with environmental safeguards including:
impermeable diked storage areas; grounding;high and low level
alarms; and fire fighting systems. Emergency spill and firefighting
planshave been develnped and an arccident prevention program would
bp institd. Fie protecion.systems within the power plant area and
vicinity will be designed according to National FireProtection
Association (NFPA) Standards. The facility Emergency Plan covers
fire andexplosion. A spill prevention, control and response plan
will be added to the site EmergencyPlan, and added to the emergency
response drill routine.
4. Hazardous Chemical Containment and Storage: All chemical
storage tanks,solution tanks, and chemical feed pumps will be
located on curbed concrete containmentareas drained through
separate chemical waste collection piping to a neutralization basin
or achemical waste collection sump. A curbed concrete area will be
provided with a chemical-resistant coating suitable for the
particular service. As a minimum, the combined volume ofthe curbed
area and the associated neutralization basin or waste sump will be
adequate tocontain the entire volume of the largest single tank
served. A spill prevention, control andresponse plan will be added
to the site Emergency Plan, and added to the emergency
responsedrill routine.
5. Chlorine: The chlorination station for the condenser cooling
water will be equippedwith a leak detection and alarm system, wind
sock, leak stemming gear and personnelprotective equipment,
including self contained breathing apparatus. A chlorine
leakageresponse scenario will be added to the plant emergency plan,
and leak response drillsundertaken as part of the emergency
response drill routine.
6. Water Demand and Raw Water Sources: During operation water
will be used forsteam production, S02 removal system, and domestic
consumption. The main sources of raw
6
-
water tor tne aDove purposes are two existing reservoirs. Kaw
water wouli be pre-treatea Dyclarification, filtration, and
chlorination. Make up water for the circulating cooling systemwould
be drawn from Khlong Pakasai, and would amount to only 4.5% of the
minimum flowrate of Khlong Pakasai. Water quality in Khlong Pakasai
has been found to meet standards.
7. Wastewater Treatment: Oil handling areas would be drained
through oil/waterseparators and then to the holding pond. Chemical
area drains and the demineralisation planteffluent would be treated
in a neutralisation basin prior to discharge to the holding
pond.Sewage will be treated to meet Ministrv of Lndust-y discharge
standuards before discharge intothe wastewater holding pond.
Wastewater treatment facilities are meet Thai and World
Bankdischarge standards at the treatment unit. The holding pond
discharge would amount to less thanone percent of the flow of
Khlong Pakasai.
8. Ambient Air Quality: Since the lignite-fired Krabi power
station wasdecommissioned, ambient air quality has been well below
limits for pollutants; there are noother significant sources of air
pollution in the vicinity. One year of meteorological data wasused
in dispersion modelling, while ambient baseline air quality was
sampled in wet and dryseasons. Modelling results indicate that
ground level concentrations of NO2, S02 and TSP arewithin Thai and
World Bank standards when the FGD is in operation.
9. Enission Control System: Sulphur Dioxide and dust will be
controlled by a wetlimestone Flue Gas Desulfurization System (FGD)
with a minimum of 80% efficiency prior toemission. An emergency
plan has been adopted in case of FGD malfunction, since
dispersionmodelling indicates unacceptable air quality would
result. The operation of the power plant willbe stopped within 10
minutes after the signal of FGD break down is shown. Stopping
theoperation of the thermal power plant with FGD system can be done
immediately since there isenough Reserved Margin in the system.
There will be 2 units of power plant; stopping operationof one 300
MW unit would not affect the total national electricity demand. In
case the FGDbreaks down but it is necessary to continue operation
of the power plant, diesel fuel would beused with the oil, and
generation would be reduced.
10. Solid Waste Management: Gypsum will be generated from
operation of the FGD's.This by-product will be transported to an
existing mine pit within EGAT's premises withcapacity of about 10
MCM, sufficient for the 25 year operating life of the power
plant.Wastewater treatment plant sludge will also be disposed in an
onsite mine pit, according toregulations of the Ministry of
Industry for sanitary landfills. Domestic waste will be removedand
disposed of properly by the Nua Khlong Sanitary District. Used
resin will be sent back tothe supplier as designated in the
contract. If necessary, it can be buried in the area in
accordancewith the regulations on waste landfill of the Ministry of
Industry. Used oil will be bumed withthe fuel.
11. Analysis of Alternatives: Two alternatives for fuel, oil
versus imported coal, werestudied. Two alternative gypsum disposal
sites were considered, and two alternatives for fueltransport.
Dispersion modelling was used to determine the need for FGD, and
the response toFGD malfunction.
12. Cultural and Aesthetic Resources: The nearest archaeological
sites, (which havebeen vandalized over the years) are 5.5 and 13
kIm from the power station, and would not beimpacted. Aesthetic and
tourist sites are at least 20 km from the power station, routes
for
7
-
transportation of construction materials are not access roads to
tourist sites, and the plant site issurrounded by a visual screen
of mangrove forest and rubber plantations.
13. Public Consultation: EGAT's objectives included: assessing
public opinion, needs,problems and obstacles relating to the
project from the peopie and communities living in theoperational
project area, as well as disseminating accurate information about
the project. Localcommunities were canvassed, local leaders,
govemment and non-governmental groups. NGO'scontacted included
local business and the Krabi Environmental Conservation Society.
Threepublic meetings and were held during February - April, 1996,
to present project andenvironmental analysis progress, and for
gathering needs, opinions, and recommendations.Environmental
concerns raised at these meetings included concern over the barge
fuel transportoption, and oil spill prevention and response
measures; need for accurate information about thepower station
boundary; worry that the use of fuel oil could have an impact on
local shrimping;and concern over the use of low grade fuel oil and
sulphur emissions. EGAT responded to theseconcerns, including
explanation of the use of only low sulphur fuel oil, as well as the
FGDemissions control system; oil spill response and control
measures, and analysis of a pipeline asan alternative fuel oil
transport method.
14. Environmental Management and Monitoring: An environmental
managementunit will be instituted at the power station, responsible
for carrying out the monitoring plan,reporting performance,
environmental training, and follow up with management.
Theenvironmental unit would report directly to the Plant Manager.
The environmental monitoringplan covers the construction period as
well as ongoing operations, and includes: effluent andsurface water
quality; noise; groundwater hydrology and quality; aquatic ecology;
solid wastem..anagem-ent; transportation; srocior%ntn mic
indicators; public health-; nennatinnal health andsafety and public
relations. The monitoring plan includes continuous air emissions
and ambientair quality monitoring during operations.
8
-
ENVIRONMENTAL IMPACT AND MITIGATION MEASURES FORKRABI THERMAL
POWEFI PLANT PROJECT
Environmental Period Impact Mitigtion MonitoringAspect
Air Quality Construction - Parliculate matter and emission from
- Spray water on the cleared surface twice daily TSP, PM toengine
and vehicles. - Limit the traveling speed within the construction
site at 30 km/hr. twice yearly
- Wash the wheel of the truck before leavingconstruction site.-
Cover the truck with canvas to reduce dust,sand blowing.
80 % efficient FCDOperation SO0 emission will be mainly from
fuel Partial shutdown of generation when FGD is off line stack
emission, continuous:
burning Stack will be at least 150 m high, greater than local
inversion level. SO2 NOx
low NOx buirners, flue gas recirculation limestone crusher,
twiceyearly: TSP, PM4,0.
NOx emissions Water spray flor dust controlambient air,
continuous: SO,
Dust from grinding and limestone NOx, TSP, PMI 10. windcrushing
process speed and direction
Noise Operation Power plant Personal Protective equipment should
be provide of staff 4 sites, 3 days every 6Noise level outside
plant is acceptable months;
Explosion, at the limestone quarry The time for Iblasting should
publicized to the communities. crusher 4 timesfyearlhe alarm shiuld
be used to declare before blasting.
9
-
Environmental Period Impact Mitigation hMonitoringApect _ _ _
_
Sutface Water Construction - withdrawal - minimal
impactHydrology Operation - withdrawal - closed cycle cooling,
withdrawal is 0.44 % of minimum
flow of khlongSurface Water Construction - The construction
might be -Construct temporary sump, capacity or 3 hr, to collect
Khlong Pakasai, Khlong Phela, 2 EGATQuality cause the high
turbidity and surface runoff from construction site reservoirs,
every 6 months: temperature,
suspended solids - Install septic system for sanitary waste
turbidity, TSS ,DO, TDS, BOD , O&G.- The wastewater treatment
plant has to be as least Total & Fecal coli50 m from the
waterway- Construct simple oil/grease trap for the wastewater
fromconstruction camp.- Regularly check the perfornance or
wastewatertreatment system.- Install septic systems adequate for
EGAT staff andfamilies.
Operation pH from demineralization neutralization pit to holding
pond before discharge a treatmenl facility or unit: pH and
lempplant oil/water separators at all oily water drains continuous;
O&G, rss, residual chlorine,oily water spill containment dikes
in all oil storage and handling daily; Khlong Pakasai, Khlong
Phela, 2 EGAT
areas reservoirs, every 6 months: temperature,thermal effluent
closed cycle condenser cooling lowers turbidity, TSS ,DO, TDS. BODs
O&G, Totalsanitary sewage package treatment plant & Fecal
coli , Pb, Cr, Hg, N, cond, phosphate
______________._ P, sulfate S. color, hardnessGroundwater
Construction - impact on groundwater level - No groundwater
extraction for the project usage at four sites every 6 mos., const.
& operation:Hydrology and level, color, cond., OsH, total
solids, totalQuality Operation - Effluent leached from sludge -
Proper disposal method for the sludge bed hardness, nitrate N,
sulltate, chloride, total
beds and solid wastes disposal -Create barrier to conserve
groundwater at the waste iron, total Mn, Total & Fecal
colilorm;area disposal area such as lining the pit bottom with
Additional groundwater wells near the
compacted clay blanket or geomembranes. Gypsum waste disposal
area
10
-
Environmental Period Impact Mitigation MonitoringAspect
Solid Waste Construction - Solid waste will generale - Prohibit
dumping solid waste into khlong Pakasai and examine suitability of
collection facilities andManagement from worker approximately
EGAT's reservoir server
724 kg/day - Prohibit open burning on project site- Properly
management of solid waste at project area- Prohibit dumping sclid
waste into Khlong Pakasai andEGAT's reservoir
Operation - Solid waste will generate - Prohibit open burning on
project site examine suitability of collection facilities andfrom
staff at rate at 125 kg/day - Properly management of solid waste of
project area. server- Gypsum will generated at the -The used resin
will be sent back to the supplier asrate of 390-67 tons/day
designaled in the contract.- The waste from water - Waste oil
should be mixed with fuel oil of the powerproduction and wastewater
plant.treatment system. - Strictly conducting according to the
regulations on- Waste resin landfill of Ministry ol Industry.-
Waste oil - Gypsum should be used.
Socio-economic Construction - Negative impact - Consultation
with thie local villagers, consist of: socio-economic condition
within construction- Inconveniences from dust, * Technical crileria
camp, social profile of target villages,noise and truck * Safety
process once/year- Accidents due to vehicle and * Accountability,
act on complaintsheavy equipment * Present the preventive measure*
Urbanization and * Present and setup training programdevelopment
model mayagainst in way of life
Operation * Social problem may arise - Maintain process and
frequency in public relation changes in income. lifestyle, PR,
'powerdue to the new comer - Stress on in depth public relation
measure structure, employment, supplementary* It effect society, it
the - Support the social activity occupations, migration: 5
seleciecl villagcs,standard in controlling Ist, 3rd, 5th, and every
5 years afierenvironment impact
II~~~~~~~~~.
-
Environmental Period impact Mitiption MonitoringAspect
M_____on_Monitoring
Public Health Construction - Disease or illnesses resulted - Use
of impregnated mosquito nets and repellents. disease surveillance
andfrom unsanitary camp - Blood examination measures to prevent
transport- Problems of work injuries - Micro filaria of filariasis
detected accidents, by medical case unitand accident Traffic
accidents - Prevention of food/water-borne disease estiblished by
contractor/Krabiloud noise, dust, and rubbish - Set up a medical
care unit powver plant, every monthThe outbreak of Malaria, VD -
Driver license inspectionand AIDS. - Improve of road condition and
traffic sings
- Speed limiting- Checking of amphetamine distribution- Loud
noise minimized- examine the worker to fiind the Malaria
injection
- Provide the chemicals spreading at the camp site every 6
month.Public Health Operation The emitted SO2 NOx and -Air quality
control through emissions controls; in 8 selected communitlies:,
1st.
particulates could impact the -continuous monitoring of
enissions; 3rd, 5th, and every 5 years after:magnitudes of
respiratory -monitoring -ptogram for local ambient air quality;
analysis of community healthdiseases, skin disease, allergic
-partial shutdown procedures for FOD malfunclions; statusdiseases.
The short termi effect - Study on it effect on community health;of
exhaust, smoke and - Mobile community health service;particles are
soiling of houses - Public relation program;and clothes that cause
- Traffic control accident.nuisance.- Accident from transportation
_
Occupational Construction - Disease - All worker and risk group
examined routiine training, safetyHealth and - Injuries and
accident -- Established for warning system equiriment
inspectionSafety - Safely education
- Regular inspection, corrected of deficiencies found- Emergency
management plan and drills- Upgrading of or medical care unit
Operation - Chronic Health cffccts on - Analysis of employee's
health record analy.Ais of health data bylung capacity, hearing,
seeing, - Periodic physical checking mediL al case unit of plant
everyheat, skin and musculoske1ctal - Safety education 3 years;
routine inspection fordisease, Illness like burns, - The
temperature (WBOT) should be routincly checked, mechanically
safety, training and exercisc ofscaled, wound and inhalation adjust
or use protective device as recommend by ECATs guideline. cmergency
plan
I of volatile chemical I_ -
12
-
Environmentl Period Impact Mitigation MonitorintgAspee t ._ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _Public Construction poor
perception of project, information program, and consultation on
needs, perceptions in 7 selected com,munities:Consultation anxieti
about impacts follow up on attitudics, opinions,
needs, distribute i nformationPublic Operation poor perception
of project, continuously inform the community about the plant's
environmental follow up on attitudes, opinions,Consultation
Operation anxiety about impacts performance needs, distribute
information
13
-
The EMuent Quality of Krabi Thermal Power Plant Compared with
World Bank Guidelines
Parameters Unit Power Plant Thai Standard' World Bank Guidelines
RemarksEMuent (Maximum Value) (Maximum Value)
(Maximum Value) . ,
pH 6-9 5.5-9 6-9 Daily - Neutralization BasinTSS mgAI 150 50-150
50 Daily - Raw water treatmentBOD mg/I 20 20 - Daily - Wastewater
Treatment
Oil & Grease mgAI 5 5 10 Daily - Oil SeparatorFree Chlorine
mg/l I I - Daily - Cooling Tower Outlet
Residue Chlorine mg/I . 0.2Temperature Increase 0 C < 3 b
< 3 Closed cycle Cooling Tower,
TDS mg/I TDS in river + 5,000 TDS in river + 5,000 - Effluent
temp. equal to AmbientAluminum mg/I 0.5 - - water temp.
Arsenic mg/l 0.25 0.25Cadmium mg/l 0.03 0.03Chromium mgAI 0.5
0.75
Copper mg/l I 2
Note: a: Industrial Effluent Standard, Notification of Ministry
of Industry No. 2 B.E. 2539 (A.D. 1996)b: Temperature Increase is
based on Surface Water Quality Standard: Notification of National
Environment Board No. 8 B.E. 2537
(A.D. 1994)
14
-
Air Pollutants Emission For Kirabi Thermal Power Plant Prolect(2
% S Fuel Oil)
Pollutants Unit Power Plant EmissionSa Thai Emission Standards
World Bank Guidelinesc Remarks(1997) ___ __
S02 ppm 286 412 700NO,, ppm 146 232 225TSP mg/Nm3 70 141 Sod
Note a,b,c: the concentration of pollutants is calculated at 3%
excess O2, 0°Ca: based on power plant specificationb: Notification
of Ministry of Industry No. I B.E. 2540 (1997)d: at the time the
project was designed, the World Bank guideline (11988) was 100
mg/Nm3
15
-
Maximum Ground Level Concentration Estimates For Krabi Thermal
Power Plant Project
Pollutants Max GLC Thai Ambient Air World Bank Guidelines
Flemarks(ugfm 3 ) Quality Standard (1994) (1997)
S02 -I hr. 90 780 80 % FGD- 24 hrs. 30 300 150 Efficiency
Annual Ave. 3 100 80N0 2-I hr. - 33 .320
- 24 hrs. 150- Annual Ave. 80
TSP -.24 hrs. TSP 4 PM l120, PM, 0 150Annual Ave. TSP I TSP 330
PM,o 50, TSP 80
PMlo 5,TSP 100
16
-
Executive SummaryRatchaburi Power Plant Project
Environmental Impact Assessment
1. AritaIUuetioU: ThLle Xatciuazuri rower Plant Project will be
iocated in subdistrictTambon Ban Rai, approximately 7 km northeast
of Ratchaburi Province about 5 km. north ofMae Khlong River. The
project will incorporate four 700 MW (nominal)
supercritical,conventional heavy oil fired units and three 600 MW
(nominal) combined cycle blocks, for atotal site development of
4,600 MW. The thermal units will burn residual fuel oil (2%
sulfur)and/or natural gas and the combined cycle will burn natural
gas as the primary fuel ordistillate oil as the back-up fuel. The
area of the site is approximately 2,000 rai, and currentland use is
rice cultivation and fishponds.
2. Fuel: Sources of natural gas for Ratchaburi Power Plant are
developing productionregions located in the Gulf of Martaban, Union
of Myanmar. Estimates of natural gas reservesand production are
5,700 billion cubic feet and 525 cubic feet per day respectively.
Naturalgas pipelines will be extended from production wells across
peninsular Myanmar and enterThailand at the border (Kanchanaburi
Province), then continue to the Ratchaburi Power Plant.
3. Delivery of the residual (No. 6) fuel oil will be via a
seaberth, fuel oil terminal and adedicated pipeline. The EIA for
this pipeline to the power station has been finished. Ifalternative
fuel delivery schemes are contemplated for the project, an
additional EIA wouldbe required, and would have to pass review by
OEPP and the World Bank.
4. Water Supply: The raw water supply (75.03 M.m3/year) will be
provided from MaeKhlong River at Ban Bang Li via pipeline to an
onsite-raw water reservoir. The water will bepretreated and will
serve for all plant needs, including cooling water makeup (69.60
M.M3/year), potable water, general service water and demineralized
water. The project will notcause any change in the hydrology of the
river basin.
5. Condenser Cooling:- Wastewater from the closed cycle
condenser cooling system ata maximum summertime temperature about
36 °C will be discharged into a holding pondbefore being relayed to
a wastewater retention pond.
6. Baseline Ambient Air Quality: An eight month sampling program
beforeconstruction found maximum background concentrations of S02
and NOx were less than 7perqent of the 1 hour and 24 hour national
standards. TSP concentrations were higher,especially in the dry
season, at about half the national standard.
7. Water Quality: Water quality in the Mae Khlong River is high
in total and fecalcoliform counts. This may be due to the
Ratchaburi Municipality and Lak Muang SanitaryDistrict wastewater
discharges. Khlong Bang Pa irrigation drainage canal water quality
ispoor (BOD5 4 - 23 mg/l) in the dry season, when the sluice is
shut and the water stagnates.Khlong Bang Pa receives effluent from
poultry and prawn farms.
8. Air Pollution Control for Thermal Units: Sulfur dioxide (SO2)
emissionsfrom the thermnal unit will be controlled by a wet
limestone FGD system, of 90% efficiency.The limestone source for
the FGD is at Khao Ta Krao, Tambon Hin Kong, Amphoe Muang
17
-
Ratchaburi Province. Limestone (1,056 tons/day) would be crushed
at the power plant site;the EIA for the limestone quarry is
currently under OEPP review.
9. Air Pollution Control for Combined Cycle: To control NOx, low
NOx burnerswould be used. Each stack would be equipped with
continuous on-line emissions monitoringsystems.
10. Wastewater: The wastewater sources to be recycled through an
irrigation pondinclude: sewage treatIment plant acivate sl-uuge and
extended aeration); and plant drainagethrough the oil/water
separator. Water from the irrigation pond will be reused for
gardeningand green area maintenance inside the plant boundary.
Storm drainage from the power plantarea will be collected in a
100,000 cubic meter retention pond and pumped back to thereservoir
for reuse.
11. Chemical wastewater and cooling tower blowdown would be
discharged to theKhlong Bang Pa irrigation drainage canal, via an
onsite holding pond. Air heater washwaterwill be routed to a lined
pond for detention and treatment (pH adjustment, metals
andsuspended solids reduction). Demineralization plant effluent
would be neutralized. Theeffluent would have higher total dissolved
solids (TDS) than the irrigation system drain'however, the effluent
would meet the Royal Irrigation Department standard. The quality
ofthe water discharged into Khlong Bang Pa would be better with
respect to all otherparameters than the water currently in Khlong
Bang Pa, furthermore, the discharge wouldincrease flow in the
Khlong Bang Pa, which is stagnant during the dry season.
12. Solid Waste Disposal: The wastewater from the treatment
system for circulatingwater makeup consists of an alkaline slurry
which will be dewatered using a thickener andthen a filter press.
The sludge will be landfilled, and an impermeable liner of clay or
syntheticmaterial will be used to contain leachate. A groundwater
monitoring program similar to theone for the plant site will be
used for the gypsum landfill. The landfill area will
beapproximately 600 rai (625 rai = I kmn2) and will also be used to
colleck discharge from theFGD system, sludge from sewage treatment
plant and solids from the air heater wastewatertreatment system.
Gypsum by product from the FOD system is approximately 2,000 tons
perday or 350,000 m3 per year will be dumped in the landfill area
of 600 rai at approximate heapheight of 10 meter. The estimated
volume about 9.6 million m 3 will serve for the 25 yearpower plant
life. Alternative uses of gypsum are being evaluated.
13. . Hazardous Chemical Containment and Storage: All chemical
storage tanks,solution tanks, and chemical feed pumps will be
located on curbed concrete containmentareas drained through
separate chemical waste collection piping to a neutralization basin
or achemical waste collection sump. A curbed concrete area will be
provided with a chemical-resistant coating suitable for the
particular service. As a minimum, the combined volume ofthe curbed
area and the associated neutralization basin or waste sump will be
adequate tocontain the entire volume of the largest single tank
served. A spill prevention, control andresponse plan will be added
to the site Emergency Plan, and added to the emergency
responsedrill routine.
14. Chlorine: The chlorination station for the condenser cooling
water will be equippedwith a leak detection and alarm system, wind
sock, leak stemming gear and personnelprotective equipment,
including self contained breathing apparatus. A chlorine
leakage
18
-
response scenario will be added to the plant Emergency Plan, and
leak response drillsundertaken as part of the emergency response
drill routine.
15. Fuel Oil Storage: Fuel oil will be stored in four tanks of
32 million liters capacityeach: a supply that would last fnr seven
days of genera:ion. The combined cycie units willhave three 17
million liter diesel oil tanks, a supply that would also last for
seven days ofgeneration. The area surrounding the fuel oil storage
tanks will be designed to contain oilspills resulting from
equipment failure or leaks occurring during norrnal operations. The
oilcontainment will be berms constructed of compacted earth with
liner or retaining walls builtof reinforced concrete. Design and
performance must conform with the concerned MinistryAnnouncement
and Act concerning oil storage B.E. 2474. (Modify no. 1-5 B.C.
2474-2530).Fuel oil piping will be routed above grade on pipe racks
in order to facilitate detection andrepair of leaks. If for any
reason the pipe must be located underground, it will be placed in
aconcrete trench which will be drained to the oil/water separator.
The facility Emergency Plancovers fire and explosion. A spill
prevention, control and response plan will be added to thesite
Emergency Plan, and added to the emergency response drill
routine.
16. Analysis of Alternatives: Analyses of alternatives with
respect to environmentalaspects included site selection, fuel
delivery systems (separate EIA for pipelines, sea berth,undersea
pipeline), FGD technology and wastewater discharge point. Two
altematives, MaeKhlong River or Khlong Bang Pa irrigation drainage
canal, were considered for dischargefrom the onsite wastewater
holding pond (cooling tower blowdown and pH
adjusteddemineralization plant effluent). The preferred alternative
is to discharge to the irrigationdrainage ditch.
17. Environmental Management and Monitoring: An environmental
managementunit will be instituted at the power station, responsible
for carrying out the monitoring plan,reporting performance, and
follow up with management. The environmental unit would
reportdirectly to the plant manager. The environmental monitoring
plan covers the construction periodas well as ongoing operations,
and includes: effluent and surface water quaity; noise;groundwater
hydrology and quality; aquatic ecology; solid waste management;
transportation;socio-economic indicators; public health; and
occupational health and safety. The monitoringplan includes
continuous air emissions and ambient air quality monitoring during
operations.
18. Public Consultation: Public consultation activities were
undertaken from December,1995, until November, 1997. Meetings
included heads of local and provincial administratives,Pikulthong
Subdistrict Women's Group, Ban Choa Rai Nua Subdistrict women's
Group, SamRtien Subdistrict Women's Group, and a Ratchaburi
teacher's meeting.
19
-
RATCHABURI POWER PLANT PROJECTSUMMARY OF ENVIRONMENTAL IMPACTS,
MITIGATION AND MONITORING PROGRAM
Environmental Impacts Mitigation Monitoring Location ofIssues
Measurements Program Monitoring
Air Quality - Fugitive dust from - Water sprays of active -
Twice a year ambient air - TSP&PM 10Construction Period
construction activities areas quality monitoring for one monitoring
sites:
-Emissions from - Vehicular speed ycar period before the plant
I. Ban Bang Kradoconstruction reduction start-up. Monitoring the
TSP 2. Ban Chao-Nauequipment and vehicular - Water sprays of &
PM1,,24-h.S0. I and 24- 3. Bang Don Mot-transportation. truck's
wheels h.NOx I-h and 03 1-h for 3 Tanoi
- Control handing of soil consecutive days in errh 4. Ban
Kh!giKa.and construction materials operation. - SO,, NOx and 0O-
Good maintenance of monitoring site:vehicles and construction Ban
Chao Nuaequipment- Proper solid wastedisposal avoid openbuming
Air Quality -SO2 and NOx Emissions SO2 -FGD system 90% Ambient
air quality Ambient monitoring- Operation period control efficiency
for SO2 monitoring: continuous sites:
provided with each sampling TSP, SO2 , NO2 I. Ban Bang
Kradothermal power unit. 0, 2. Ban Chao-Nau- Shutdown of the
thermal 3. Ban Don Mot-power unit by which the Emtissions a
continuous stack TanoiFGD stop functioning. emissions monitoring
system 4. Ban Khlong Kae- Shutdown one thermal will be installed
forpower unit by which the monitoring SO2 and NOxFOD stop
functioning. emitted from 4 thermal power- Shutdown one thermal
unit stacks and 6 HRSG stacks Emnissions - thepower unit in the
case that appropriatethe 3 combined cycle position of the 4block
have to bum diesel thermal power unitoil instead of natural gas.
stacks and the 6
HRSG stacks._________ ______ __ NOx - low NOx burners
Surface Water Siltation/sedimentation Major
constructionHydrology to the nearby canal and activities should be
in dry- Construction Period river season.
- Construction materialshould be in the projectsite.
Insignificant impact to theOperation Period hydrological
regime
(Water intake is rathersmall.)
Water Quality Increasing suspended Construct temporary weir
Every 4 month: pH. Khlong bang Nok- Construction Period solid in
the nearby to trap sediment. Conductivity. Temperature. Yung
. . canalriver. -Weir constructed should Turbidity, TDS. TSS.
DO. Khlong Latbe at least 10 m. from the BOD3 Khlong Bang Pa
and
Wastewater from canal bank. Khlong Talat Khawiworking personnel
-Provide sufficient toilets
with septic tanks.-Locate camps site at- least
100 m. from canals.
20
-
Environmental Issucs of Impact Mitigation Monitoring Location
ofAspects to Environment Mcasurements Program Monitoring
Water Quality- Wastewater; -Monitor the cfficiency -Evcry four
month. the recciving waterOperation Period temperature. of
treatmcnt system daily The parameters that will he ncar the
discharging
phosphate. oil/grease. -Chemical precipitation analyzed arc nH K
pntorganic of cooling water Conductivity. - I km. upstreammatter
blowdown will be Tcmperature.TDS, TSS. DO, from the dischargc
provided COD BODs P0.4 Fe, Hg. Cu. pointCd. Cr. Pb by the
standard - I km. downstreammethod accepted by from the
discharge
_____________________. responsibic agency
pointGroundwater-Construction Period - Salt water intrusion -
Control the discharge -Establish observation well -Wells as
observed
rate and explore other for monitoring water level in the power
plantaltematives water and quality twice a year in study.resource
instead of dry and rainy season for bothgroundwater demand in
construction period and
-Operation Period -Insignificant Impact future. operation period
by suchparameter
Soil and Land Quality -(if required) lime to 16 soil samples (8
borings) The location of soil-Operation Period -Soil
acidity/salinity reduce the acidity at 0-20 and 20-50 cms. sample
boring are
-Use high grade fuel to should be sampled to shown in the
soil-Soil acidity reduce the gaseous determine soil reaction
map
emission pH,EC.Fe,AI and sulfur once-Control SO2 emission a
year.to meet the standard ofOECP
Environmental Noise-Construction Period -Distance of 3 km. from
-Public relations system -Monitor noise level every -Ban sam
Roen
site will sometimes should be set up to 3 months -Ban Chao
Naureceive noise more than create a positive attitude -Center of
plant site80 dBA toward the project
-Loud or noisy activitiesshould be stoppedduring times when
quietis necessary-Noise controlequipment must be usedin the proper
way.
-Operation Period -Distance of 0.9 km. -Create noise barrier -
same as above -same as abovefrom site will sometimes around the
plant site -receive noise more than -Program for public80 dBA
relations
to help peopleunderstandthe project activities
21
-
Aquatic lifc-Construction -Wastewater - Construction camps
-Monitor composition of -Khlong Bang NokPeriod domestic wasIC
should be located at Icast plankton and benthic structure Yung
from worker camp 100 m. from natural canals every 4 month
-Khlong Lat-a temporary septic system -Khlong Bang Pa andshould be
constructed -Khlong talat Khawi-sanitary latrines should
behuilt
Aquatic life -Thermal pollution -a watcr rescrvoir should same
as above, every the receiving water-Operation he constructed to
r.duce 6 monch in dry and rainy ncar the dischargePeriod water
temperature before season point
discharged into the river -Ikm. upstream from-Wastewater
-wastewater should be the discharge pointpollution pretreated by
neutralization -I km. downstream
and by WWT system before from the dischargebeing discharged into
the water point.way
-Structure of -Use the iron net with meshbiological system in
size 0.5 cm. or less to preventthe Mae Khlong young or small
animals to beRiver sucked into the water pipe.
WaterManagement -Insignificant impact ,and Water Use
-Insignificant impact -Management of two -Annual water balance,
-Mae Khlong River-Construction reservoirs upstream especially
during dry season basin particularlyPeriod / downstream of
the-Operation project sitePeriod -Mae Khlong River
basin
Socio-economic -increasing land -Announcement of public -Annual
time series (over 3-5-Pre and prices outreach program
yrs)Construction -Increasing income -Provision of financial studies
should be carried outPeriod -Positive local management consultant
for covering the following
attitude towards land sellers parameters:the project -Management
of labor -incidence of crime caused by-Temporary camp including
opportunity workforcemigration of for relaxation -job opportunity
of localworkforce -preferential treatment for residents-displaces
land- jobs for land-renters and -land pricesrenters locals -life
style change of land
sellers-effects on former land-renters-effectiveness and
-Operation - -Income and -Continue and develop acceptability of
publicPeriod employment public outreach program outreach
program
-Electricity supply -Job training program to -attitude towards
the project-Distribution of enable young local to work 'Annual time
series studiessocial cost at the plant should be carried outand
benefit e.g., -Community development covering the followingnoise,
odor, panicularly Ban Phikun Thong parameters: -locallandscape
change employment. land prices;
industry locating near theplant site; effectiveness
andacceptability of publicoutreach program -attitudetoward the
social andenvironmental changescaused by the project
22
-
-communicable -Provision of adequate -Contractors' compliance
-Camp andPublic Health diseases environmental health facilities
with construction site-Construction e.g.: water supply latrine etc.
mentioned mitigationPeriod -Onsite health care unit measures
including transferable systemto hospifa :
cscoemergency-Establishment of earlywaming system for air
-Operation pollution indicators inPeriod -Respiratory diseases
effective communities -Local public health
-Providing medical centerscollaborate teams between -Health
records on air -Local public healthEGAT and local public health
pollution centersauthorities to care all related diseases
-Community closed toappropriately manage to -Monthly report of
respiratory air pollutioneffected people in cases of illness
monitoringhazardous air pollution -Establishment of health
stationsexposure monitoring program
concurrentlywith air pollution monitoringstations
Sanitation andwaste Handing -Increasing solid -Sanitary disposal
system -Supervision of EGAT staff -camp and-Construction waste of
solid waste -Contractors responsibility construcdon sitePeriod
-Unsanitary -Appropriate wastewater -Surrounding areas
conditions caused treatment systemby wastewater -Negotiation
with Ratchaburidrainage municipality or private sector
-Operation to sanitary manageeriuod -increasing solid -Provision
of laboratory -Daily check of effluent -Outlet site
waste facilities quality-Insignificant impactof waste water
-Construction sitedischarged
Occupational -Setting up effectiveHealth and occupational heath
and safetySafety -Accident and injury program -Local
medical-Construction -Occupational -Setting up fire protective
-Environmental monitoring examination centersand diseases and
control system program -Local medicalOperation -Effective control
of alcohol, -Medical monitoring program examination centersPeriod
drug abuse, gamnbling and other for construction workers
illegal actions -Medical monitoring program-Strict control of
all related for specific environmentalregulations
hazard-Occupational health safety andprogram-Industrial hygiene
program-Specific regulations forhealth and safety
Archaeology -Stop and report suspected-Construction
archaeological evidencePeriod related authorities in cases of
accidentally uncovering __.,
23
-
The EMuent Quality of Ratchaburi Power Plant Compared with World
Bank Guidelines
Parameters Unit Power Plant Effluent Thai Standard' World Bank
Guidelines Remarks(Maximum Value) (Maximum Value) (Maximum
Value)
pH 6.5-8.5 6.5-8.5 6-9 Daily - Neutralization BasinTSS mg/I 30
30 50 Daily - Raw walter treatmentBOD mg/l 20 20 Daily - Wastewater
Treatment
Oil & Grease mg/il 5 5 1O Daily - Oil SeparatorFree Chlorine
mg/I 1 I Daily - Cooling Tower Outlet
Residue Chlorine mg/i 0.2Temperature Increase C - < 3b < 3
Closed cycle Cooling Tower, Effluent
TDS mg/l 1,300 1,300 temp. equal to Ambient water temp.Aluminum
mg/I 0.5Arsenic mg/l 0.25 0.25
Cadmium mg/l 0.03 0.03Chromium mg/l 0.3 0.3
Copper mg/Il I I INote: a: Effluent Water Quality Standard for
Irrigation Canals, Royal Irrigation liepartment.
b: Temperature Increase is based on Surface Water Quality
Standard: Notification of National Environment Board No. 8B.E. 2537
(A.D. 1994)
24
-
Air Pollutants Emission For Ratchaburi Power Plant Proiect.
Pollutants Unit Power Plant Emissions' l'hai Emission
Standards& World Bank Guidelinesc Remarks
oil gas oil gas oil gas_ ___ __ . _ _ _ _ Thermal Unit 700
MWS0 2 ppm 84 - 412 26 700 700NO, ppm 183 120 232 155 225 155TSP
mg/Nm` 70 - 141 70 506 50d
CombustionTurbine 200 MW
SOl ppm 62 - 136 8 700 700NO2 ppm 75 50 77 51 80 61TSP mg/Nm' 8
- 56 28 50 d 5
Note : a,b,c : the concentration of pollutants is calculated at
3% and 15% excess 02 for Thermal units and Combustion Turbinea:
based on power plant specification ib: Notification of Ministry of
Industry No. I B.E. 2540 (1997)d: at the time the project was
designed, the World Bank guideline (1988) was 100 mg/Nm'
25
-
Maximum Ground Level Concentration Estimates For Ratchaburi
Power Plant Project.
Pollutants Max GLC Thai Ambient Air. World Bank Guidelines
Remarks(ug/m3 ) Quality Standard (1994) (1997)
S02 - I hr. 392 780 90 96 FGD- 24 hrs. 50 300 150 Effciency-
Annual Ave. . 9.5 100 80
NO2 - I hr. 170 320- 24 hrs. 150- Annual Ave. 80
TSP -24 hrs. PMlo 120, TSP 330 PM10 150- Annual Ave. PMlo 5, TSP
100 PMto 50, TSP 80
26
-
WANG NOI COMBINED CYCLE POWER STATIONEnvironmental Impact
Assessment
Executive Summary
i. Background: The 1,800 MW Wang Noi combined cycie base ioad
power station isfully constructed and operational on an area of 718
rai in Tambon Khao Ngam arid WangChula, Amphoe Wang Noi, Ayudhaya
Province. The generating system includes 3 blocks of600 MW
generators. Each block is composed of 2 sets of 200- MW gas
turbines and a 200-MW steam turbine. The EIA study report was
approved by the National Environment Boardin the meeting no. 5/2537
on June 8, 1994. The commercial operation of the power plantstarted
in May 1998.
Fuel: Natural gas will be supplied from the Gulf of Thailand and
inland sourcesthrough a Petroleum Authority of Thailand (PTT)
pipeline; there are no storage facilities onthe plant site for
natural gas. Distillate No. 2 oil (0.05 - 1.0% S, average 0.53% S)
is usedonly as backup. The oil is delivered to the site by tank
truck. the EIA for the pipeline hasbeen done by PTT and approved by
NEB.
Water Supply: Makeup water for the power station is drawn from
Khlong Raphiphatand a well. The power station demand would be only
6 % of the minimum (July 1992)recorded monthly flow of Khlong
Raphiphat. A groundwater well on site serves only asbackup and
potable water supply.
Condenser Cooling: A closed cycle condenser cooling water system
is used.
Air Pollution Control: Oxides of nitrogen are controlled in the
combustion turbinesby water injection in the first two blocks. the
third block will use the dry, low Nox burnersystem. The stacks are
equipped with on-line NOx monitors.
Ambient Air Quality: Ambient air quality measurements have been
taken every sixmonths during commissioning of the first two blocks.
Two sets of data are available: dryseason, January - February, and
wet season, May. Sulfur dioxide averaged over 24 hoursranged (0 - 6
ug/m3); that is, from undetectable to 2% of the national standard.
Themaximum NO2 measured at any receptor was 26 ug/m3 , less than a
tenth of the nationalstandard, and a fifth of the World Bank
standard. Tanking into account the planned expansionto 1,800 MW,
the actual air quality monitoring results to date indicate the
dispersionmodelling was conservative.
Dispersion Modelling Estimates, 1,800 MW: One year of
meteorological data wasused in the dispersion modelling. In case of
diesel-fired (6 x 200 MW) combustion turbines,1-hour maximum GLC of
NO2 is 84.4 ug/m3 (worst case), below the national standard of
320ug/m3.. For S02, the 24-hour maximum GLC is 10.5 ug/m3 (worst
case); well below thenational standard of 300 ug/m3, and the World
Bank (NOx) guideline of 150 ug/m3. Theannual average for SO2 is
estimated at 7.6 ug/m3, well below the national standard of
100ug/m3 , and the World Bank guideline of 80 ug/m3 .
For the case of natural gas fueled (3 x 600 MW), 1-hour maximum
GLC of NO2 isestimated to be 154.9 ug/m3 which is also below the
national standard of 320 ug/m3.
27
-
Wastewater: Sanitary wastewater and neutralized demineralization
plant eftluent arerouted through a 4.000 m3 holding pond, which
overflows to the retention pond (75,000 m3)onsite. Sanitary
wastewater treatment consists of aeration. clarification and
chlorination(calcium hvpochlorite). The closed cycle cooling tower
blowdown is discharged to thewastewater retention pond, along with
effluent from the oil/water separator. An automaticwater quality
sampling station is located at the outlet of the retention pond to
Khlong 26.
Water Quality: Plant effluent is pumped from ;i retention pond
to Khlong 26, "'hinalso receives irrigation system drainage,
domestic and agricultural wastes. Water qualitymonitoring at the
raw water source, holding pond discharge and Khlong 26 has
beenundertaken every six months during project development. In 1997
the results of effluentwater quality sampling during operation of
the plant were within the effluent quality standardfor irrigation
canals of the Royal Irrigation Department.
Solid Waste Disposal: Domestic solid waste, raw water and
wastewater treatmentsludge is taken off site and disposed by the
Lam Ta Sao sanitary district in Amphoe WangNoi.
Fuel Oil Storage: Oil storage is in two 29.45 million liter
tanks. The oil storagefacilities are is built to ASTM and API
standards. The area surrounding the fuel oil storagetanks is
designed to contain oil spills resulting from equipment failure or
leaks occurringduring normal operations. The oil containment is
berns constructed of retaining walls built ofreinforced concrete.
Fuel Oil piping is routed above grade on pipe racks in order to
facilitatedetection and repair of leaks. If for any reason the pipe
must be located underground, it isplaced in a concrete trench which
is drained to the oillwater separator. The facilityEmergency Plan
covers fire and explosion. A spill prevention, control and response
plan willbe added to the site Emergency Plan, and added to the
emergency response drill routine.
Hazardous Chemical Containment and Storage: All chemical storage
tanks,solution tanks, and chemical feed pumps are located on curbed
concrete containment areasdrained through separate chemical waste
collection piping to a neutralization basin or achemical waste
collection sump. A curbed concrete area is provided with a
chemical-resistantcoating suitable for the particular service. As a
minimum, the combined volume of the curbedarea and the associated
neutralization basin or waste sump is adequate to contain the
entirevolume of the largest single tank served. A spill prevention,
control and response plan will beadded to the site Emergency Plan,
and added to the emergency response drill routine.
Chlorine: The chlorination station for the condenser cooling
water is equipped with aleak detection and alarm system, wind sock,
leak stemming gear and personnel protectiveequipment, including
self contained breathing apparatus. A chlorine leakage
responsescenario will be added to the plant Emergency Plan, and
leak response drills undertaken aspart of the emergnecy response
drill routine.
Analysis of Alternatives: Alternatives analylzed for the project
included choice oftechnology, site selection, water sources,
wastewater treatment schemes and choice ofreceiving waters.
Environmental Management and Monitoring: An environmental
managementunit will be instituted at the power station, responsible
for carrying out the monitoring plan,
28
-
reporting performance. and follow up with management. The
environmental unit would reportdirectly to the plant manager. The
environmental monitoring plan covers the construction periodas well
as ongoing operations, and includes: effluent and surface water
quality; noise:groundwater hydrology and quality; aquatic ecology;
solid waste management; transportation;soci-ecnnorwmir indicators;
public health; and occupational health arid safety. The
monitoringplan includes continuous air emissions and ambient air
quality monitoring during operations.An abbreviated summary of
impacts, mitigation and monitoring is shown below.
29
-
WANG NOI COMBINED CYCLE POWER STATIONSUMMARY OF IMPACTS,
MITIGATION MEASURES AND MONITORING PROGRAMS
Environmental Resources/Values Environmental Impacts Mitigation
Meaures Monit,ring ProgramsPhysical Environmental ResourcesAir
Ouslity
Operation Phase- Al the first stage, at CT stack height of 35 -
Stack height of CT units should be kept at -Continuous Monitroing
Of NO2, S02 and windm, GLC Of SO, around the project site is 35m
minimum. speed and direction at 5 stations,acceptable. Continuous
Monitering fo stack gas for SO and- At thie final stage, at HRSG
Stack height - Stack height of HRSO should be kept at NO, at CT and
HRSGof 35 m. GLC of SO and NO2 is 35 m minimum.acceptable.
NoiseOperation Phase - No mitigation measure is required. - No
Monitoring program is required.- Noise livel at the distance of
60,120 and200 m away from the plant center willreduce to 49,43 and
39 dBA thus causingno effects to nearby community.
Surface Water Hvdroloav Operation Phase - Cooperation of EGAT
with RID ror - Water situation in relation to the Plant must be-
Impacts due to serious shortage of water in peoper water management
must be carried closely monitored.some periods. out.
- construction of a raw water reservour for5 - d storage i
necessary.
Surface Water Quality - Treatment of holking pond effluent to -
Monitroing of water quality in KhlongOperation Phase reduce SS,
conductivity and TDS is Raphiphat and Khlorg 26 for temperature,
pH,- Discharge of effluent of 5A 197 I/min required. conductivity,
trubidity, SS, TDS. alkalinity,(diesel oil fuel) and 4,9161/mon
Zgas fuelX -Treatcd effluent should partly be recycled hardness,
DO, BOD, H2S and grease & oil mbistinto Khlong 26 will affect
downstream or reuscd. be conducted twice a year in rainy
seasonwater quality in terms of SS, TDS, - Study on toxicelogican
effects of chemical (October) and in dry 'season (April).hardness,
sulfate, conductivity and susing in cooling system on in
digenouscoplymers using in cooling system. plant and aqutic
organisms is required. - Additional monitoring of water quality for
Pb,
Cr, Cu, Zn, Hg, Ni and Cdin dry season and- Contamination of
chemical s may be pesticides inrainy season must be
conducted.harmful to aquatic lives.
30
-
Environmental Resources/Values Environmental Impacts Mitigation
Measures Monitoring ProiramsGroundwater Operation Phase -
Withdrawal at optimal rate is necessary to - Minloring of land
subsidence is required.
- Amount of water for domestic supply is preven land
subsidence.within the yield of groundwater wells in this -
Monitoring of drawwown from test wells - Montoring of drawdown is
required.area. Theredore, no impact is expected. is
recommended.
- Groundwater quality is suitable for - Water for drinking
purpose must be - Monitroing of groundwater quality twice adomestic
use but must be treated, if used for treated. year is recommended
for pH, conductivity,drinking - Monitoring of groundwater quality
is turbidity. dissloved solids, suspendced solids.
recommended. alkalinity hardness calcium, iron, rnagnesium.- No
mitigation measure is required chloride sulfate and nitrate.
Aquatic Ecology and Fisheries Operation Phase - A fisheries
management unit, fish stocking- At the raw water intake pump
station, program and control of aquatic weeds inyoung fish ans fish
eggs wili be pumped Khloing Raphiphat and Khlong 26 should beinto
the intake. Degree of mortality depends established.on design of
intake structure. Foloatingweeds will also affect the intake.-
Large volume of water discharged fromthelower plant will increase
water inKhlong26 for natural risheries and aquaculture.- Changes in
flow regime of Khlong 26 willalter group composition of
aquaticorganisms
Water Use Operafionn Phase.Khlong Raphiphat, A. Nong Khae,
Saraburi- The Plant utilizes water of about 1.25MCM/month from
Khling Raphiphat atPhra Sri Silp Regulatior. The amount ofwater
required is about 6% of the totalrunoff in Khlong Raphiphat during
dryseason (21 MCM/monthX. In addition,grounwaler willb ewithdrawn
as a back-upfor construction activits. No impact is thenexpected.-
in case the pasak project is completed, -Cooperation between EGAT
and RID isrunoff in chao phTaya will be increaed by recommended50%
thus no impact is expected.
31
-
Environmental Resources/Values Environmental Impacts Mitigation
Measures lNloniloring ProgramcsPublic Health Operation Phase
- Maintenance worders and operators will - Regular medical
surveilancc is to vcbe the high risk group to working accidnets
providd for these personne.dur to improper management, fatique,
etc. - Stringent supervision and control and- Transport accients
are lidely to occur proper management are necessary to- Laboratory
personnel will be subject to minimize the accidents. The medical
cenierhealth gazards from chemical sin terms of must be
established.shin irritation. Long lerm exposure will lead - Safety
regulalions must be provided withinto respratory tract disease and
d.etion of the plant and personnel must be aware ofkidney and
liver. safety.
- Air quality muste be maintained within thenational amlhient
air quality standard andmust be monitored regularly.
Occupational Health and - Noise from operation of machine such
as - Minatenance of machine should he done - Monilroing of noi ~c
at generator andSafety gas turbine and intake area will not exceed
regularly. instrumlcnt air unit A,hould he done once a Vear.
85 dBA which commplies with the standard - Insulation ol turbine
casing should heof Ministry of Interior (90 dBA). Thus no replaced
periodically to reduce noise andserious effect from noise is
expected. vibration.
- Control roon should be provided in case olcontinuous exposure
to noise.- Ear protection equipment should bhprovided for
employees.- Monitoring fo nise should be conductedregularly.-
Hearing loss should be tested for worders - lTst ler hearing loss
should B'r wo rers heinewho work in noisy areas. exposed to loud
noise.
- Since the machine tha Ieauses heal is - Heat insulation is
provided. - WGB I-should he itionittiicd oncc a yearcovered in the
enclosure therefore such healwill not cause any adverse health
effect toworkers. - Proper management and close wupervision -
Sickiness and accidents of all llvels I. lust he- Accidents may
occur from ussafe acts ol should be impiemented. recorded
throughiout the tourse oif operation.workecrs esppecially during
maintenance. Ifpreventive measures are eflictivelyimplemenied and
followed up, impacts willnot be serious. - Regular check-up of pope
conditions is - Continouous gas deteclor uwilh on line s% stetli-
Leakage of gas popeline may cause serious recommeded. should be
iistalled Cm. monitoring purpose.damages. - Monitoring ol nois. at
generator and
instrumiient air unit shlould he donc once a year.
32
-
Environmental ResourcesNValues Environmental Impacts Mitigation
Measures _ Monitoring ProgrimsAesthetic Values andTourism Operntion
Phase - rovision of green hclts and arcas should- Sinokc from ihc
power plant will reduce hc deone.aesthetic quality ol thc sitc. -
Local agencies should control- The power plant will induce housing
and establishment of housing cstates andindutrial development in
the area. faclories
33
-
The EMuent Quality -of Wang Noi Combined Cycle Power Plant
Compared with World Bank Guidelines;
Parameters Unit Power Plant Effuent Thai Standard' World
BankGuidelines | Remarks_____ .____,____,___ (Maximum Value)
(Maximum Value) (Maximum Value) ______
pH 6.5-8.5 6.5-8.5 6-9 Daily- Neutraliztion BasinTSS mg/I 30- 30
50 Daily - Raw water treatmentBOD mg/i 20 20 \ Daily - Wastewater
Treament
Oil & Grease mg/I 5 5 10 Daily - Oil SeparatorFree Chlorine
mg/l I 1 \ Daily - Cooling lower Outlet
Residue Chlorine mgAI - 0.2Temperature Increase 0 C - < 3b
< 3 Closed cycle Cooling Tower, Effluent
TDS mg/I 1,300 1,300 temp. equal to Arnbient water temp.
Aluminium mg/t 0.5 \Arsenic mg/l 0.25 0.25
Cadmium mg/i 0.03 0.03Chromium mg/I 0.3 0.3
Copper mg/lI I I_ _ -Note: a: Effluent Water Quality Standard
for Irrigation Canals, Royal Irrigation Department.
b: Temperature Inerease is based on Surface Water Quality
Standard: Notification of National Environment Board No. 8B.E. 2537
(A.D. 1994)
34
-
Air Pollutants Emission For Wane Noi Combined Cycle Power Plant
Proiect.
Pollutants Unit Power Plant Emissions' Thai Emission Standards"
World Bank Guidelines' Remarks.__._._._._. oil gas oil gas oil
gas_
SO ppm 1 10 - 136 8 700 700NO, ppm 50 50 77 51 80 61TSP mg/Nm, 8
- 56 28 50 50
Note a,b,c the concentration of pollutants is calculated at 15%
excess O!, 00Ca: based on power plant specificationb: Notification
of Ministry of Industry No. I B.E. 2540 (1997)
35
-
Maximum Ground Level Concentration Estimates For Wane Nol
Combined Cycle Power Plant Prolect
Pollutants Max GLC Tlhai Ambient Air World Bank Guidelines
Remarks(uglm 3) Quaity Standard (1994) (1997)
S02 - I hr. 780-24 hrs. 41.5 300 150- Annual Ave. 5.6 100 80
NO2 - I hr. Diesel 142 Gas 190.3 320-3 hrs. Diesel 74.2 Gas
103.5 150-24 hrs 80- Annual Ave.
TSP - 24 hrs. PMto 120, TSP 330 PM,0 150- Annual Ave. PM l0 5,
TSP 100 PM lo 50, TSP 80
36
-
Executive Summary
500 KV Transmission System for Independent Power
Producersand
Grate#r B3ng Are,a"
Environmental Guidelines for Planning, Construction
andMaintenance of Transmission Lines
Introduction
1. The Electricity Generating Authority of Thailand (EGAT) is a
state enterprise underdirect supervision of the Office of the Prime
Minister. EGAT was established on May 1,1969 to nationalize and
consolidate the functions and responsibilities of three
independentstate enterprises: the Yanhee Electricity Authority
(YEA), the Lignite Authority (LA) and theNorth-East Electricity
Authority (NEEA). EGAT is now in the process of privatization.EGAT
has the responsibility to provide electricity for the entire
Kingdom of Thailand bygenerating, transmitting and selling bulk
energy to two distributing entities, namely theMetropolitan
Electricity Authority (MEA) and the Provincial Electricity
Authority (PEA).
2. The current EGAT long term Power Development Plan (PDP 95-01)
includes about13,100 MW total power purchase from IPPs up to the
year 2011, representing 30% of thetotal installed capacity at that
time. To facilitate private sector investment in IPP projects,EGAT
will construct two 500 KV transmission lines along the Gulf of
Thailand from BangSaRhan (Prachuap Khiri Khan Province) to Chom
Bung on the western coast and fromRavong to Nonz Chok and Wang Noi
on the eastem coast. These 500 KV lines will receivethe power from
IPP power plants and transmit most of the generated power to the
load centersin Greater Bangkok and the surrounding area. In
addition, a 500 KV transmission system forthe Greater Bangkok Area
will be developed, replacing the existing 230 KV system.
Proiect DescriDtion
3. Western Area, 500 KV Transmission Lines: The transmission
system for thedisbursement of power from IPPs in the Western Area
includes construction of twotransmission lines: (i) 275 km long VSt
route of 500 KV double circuit line from Bang Saphanto Chom Bung;
(ii) 280 km long 2 nd route of 500 KV double circuit line from Bang
Saphansubstation to Chom Bung.
4. Western Area, Substations: The substation projects for the
Western Area includeexpansion of the following 3 existing
substations: (i) Expansion of Bang Saphan 500 KVsubstation with
installation of 500/230 KV of 1000 MVA transformer, line shunt
reactors andaddition of a communication system; (ii) Expansion of
Chom Bung 500 KV substation withinstallation of line shunt reactors
and addition of a communication system; and (iii) expansionof Sai
Noi 500 KV substation and addition of a communication system.
37
-
5. Eastern Area. 500 KV Transmission Lines: The transmission
lines for the EastemArea include two transmission lines: (i) 155 km
long I" route of 500 KV double circuit linefrom Rayong 4 to T
Junction; and, (ii) 170 km long 2 nd route of 500 KV double circuit
linefrom Rayong 4 substation to T Junction.
6. Eastern Area, Substations: The substations for the Eastern
Area include theconstruction of one new and expansion of one
existing substation: (i) new 500/230 KVRayong 4 substation with
installation of line shunt reactors at 500 KV Rayong 4-Nong Chokend
Payong A -Wong Noi iines, anci addition ot a communication system;
and, (ii) expansionof the 230 KV Rayong 2 substation with addition
of a communication system.
7. Greater Bangkok Area: The project would replace four existing
sections of 230 KVtransmission line with 500 KV transmission lines:
Bangkok Noi - Sai Noi (29.4 km); Sai Noi- Rangsit (24.7 km);
Rangsit - Chaeng Watthana (7.4 km); and, Nong Chok - On Nuch,(17.9
km).
Lega1 and Administrative
8. Environmental Impact Assessment (EIA) is not required under
current Thailand lawand regulation for the 500 KV Transmission
System for IPPs Project. The EIA for thetransmission system will be
expected only when all or a portion of the transmission lineroutes
are located in Watershed classification class lB or forest
conservation area classC, Wildlife sanctuary area, National Park
area, or Mangrove area. The project route doesnot traverse any of
these. The report is a focused environmental analysis of
environmentalimpacts of project components and their mitigation
measures as required by the World Bank.
9. EGAT would have to submit a report to the RFD for permission
to use some part ofthe National Forest Reserves as right of way for
the transmission lines.
Analysis of Alternatives
10. Westem Area: It was determined that the transmission line
route should not parallelthe railway line and main road (highway 4)
because both sides of these corridors are denselypopulated, in
addition, the transmission line should not pass over railway lines,
according toEGAT design criteria. The selected transmnission line
route would pass through the NationalForest Reserves only in low
areas at the edges where the land use is now mostly
agricultural.The bottom lands of the National Forest Reserves have
been heavily encroached andconverted to agricultural uses. There is
no alternate route in the western area of the southernpeninsula
because it is narrow and near the border of Myanmar.
11. Eastern Area: The final route selection was based on the
following: (i) there are verydense residential areas along both
side of the main road, including a network of secondaryroads; (ii)
EGAT environmental criteria call for avoidance of residential areas
as much aspossible; only line two of the transmission system passes
through (two) National ForestReserves. These sections of the
National Forest Reserves have been encroached and arecurrently
agricultural areas and forest plantations.
12. Greater Bangkok Area: The new 500 KV transmission line would
be constructed asfar as possible along the existing 230 KV
transmission line ROW. The alternative would be
38
-
to acquire new ROW's through the populated Greater Bangkok Area,
which would entail fargreater environmental and social impact.
Route Selection Cri:eria an'd Mitgation Strategies
13. In selection of routes for transmission lines and substation
sites, EGAT uses designcriteria to minimize environmental impacts
on forest, wildlife, watershed areas, populations,archeological
sites and scenery. Transmission line right of ways are not to be
locatedthrough: (a) restricted Class IA watershed area and Class C
forest conservation areas,according to laws and regulations; and,
(b) holy places, archeological sites and governmentsites.
Transmission line right of ways should also avoid: (a) watershed
area class IB,mangrove forest, national parks and other
conservation areas; (b) community anddeveloped areas; (c) parallel
with, or close to telephone and telegraph cables for a
longdistance; and, (d) airports.
14. Detailed Route Surveys: Before construction of the
transmission system, detailedroute surveys will be performed by
EGAT staff together with the Royal Forest Department(RFD). The
number of forest trees to be cut will be documented. In addition,
final routeselection adjustments to avoid dwellings and circumvent
other areas of potential negativeimpact will be made, according to
EGAT's environmental design criteria.
15. Construction: EGAT's guidelines for construction activities
are: (a) avoidinstallation of new access roads for construction
purposes; try to utilize existing trails;(b) no cutting of trees
over the limitations set by RFD: and. (c) clean up constructinn
sitesupon completion of construction work.
16. Maintenance of the Right of Way: Along the valleys, only
trees considered to behazardous to the stability of the
transmission system would be cut down. Landowners arepermitted to
cultivate economic crops at EGAT's option along the right of
waycorridors. Upon completion of transmission line construction
work, ground cover aroundthe towers will be planted and land
contouring will be done as required to provide aprotective covering
for the earth and to preventsoil erosion.
Environmental Issues:
17. Environmental Impact on Water Resources: Potential impacts
of a transmissionsystem on water quality are related to
construction activities: surface run-off fromconstruction sites;
wastewater from the temporary office and construction camps;
and,wastewater contaminated with oil or grease from machinery. The
study of the 500 KVEastern and Westem systems revealed that the
banks of the Pranburi River at the end ofPranburi Dam where both of
the Westem transmission lines cross are steep. The soil is sandyand
liable to erosion. Any transmission tower located here should be
located at least 50meters from the riverbank. The Eastem Area
transmission system crosses over the BangPrakong River; but would
have little impact from soil erosion since the river is so large,
theriver banks are not very steep, and the water is already rather
high in turbidity. In the GreaterBangkok area, the existing ROW
would be used, and minimal soil disturbance and clearingwould be
necessary.
39
-
18. Forest resources: The field study revealed that the national
forest reserves in theproposed Western transmission line area are
degraded due to encroachment and conversion ofthe land for
agricultural purposes. However, forest areas can still be found in
the mountainousareas. These areas are not traversed by the proposed
transmission system right of way. Thetransmission line right of
ways have been laid out through topographically level areas
andwithin the forest reserve areas that have been converted to
agriculture through encroachment.Only the Western right of way area
represents the potential to impact on forest resources.The area in
question is a stunted dry dipterocarp forest. In the area of the
right of way for thetwo lines the national forest reserve is
deteriora:cd forest, wiih smali and stunted trees. TheEastern ROW
areas do not traverse forest cover. Impacts on eucalyptus and
casaurinaplantations are minor because the right of ways use a
narrow stretch of private land, and thiscan be reforested or
compensation paid to the owner(s). There are no forest
resourcesinvolved in the Greater Bangkok Area component of the
project.
19. Wildlife: The field study did not find any species in the
ROW areas that aresignificant for conservation. Significant species
are usually found in unspoiled naturalhabitats; and these are
strictly protected. The reserve forest where the 500 KV
transmissionsystem traverses has already been cleared for
agriculture and other purposes. The speciesfound in the ROW's are
mostly small in size and they can adjust well to various
humanactivities. There is little wild flora or fauna in the
existing ROW in the Greater BangkokArea.
20. Land Use: The project will cause the lost and limitation of
agricultural land use in theROW; however, the impact is on a small
total land area because most of the crops have a shortgrowing
season and they do not exceed the hieght restrictions for
vegetation in the ROW.These crops include rice, pineapple and
cassava. In addition, after the project construction isdone, the
crops can be grown as usual, with the exception of tall perennials
and trees. In theGreater Bangkok Area the 230 KV lines already
exist in the ROW's, and the area has beendeveloped into a
combination of residential, industrial and agricultural land.
21. Cultural and Esthetic Resources: There were no cultural or
esthetic resources thatwould potentially be impacted along the
Western Route (Bang Saphan-Chom Bung). TheEastern transmission line
one would traverse Tharanukroh Cemetery, as revealed by
thepreliminary route survey. In Greater Bangkok there are 17
temples and mosques locatedwithin 1 km either side of the existing
230 KV ROW. The existing 2330 KV line cannot beclearly observed
within the visual context of these cultural landmarks. There are
two templeslocated adjacent to the existing 230 KV ROW's; however,
there would only be a slightchange in the visual impact of the 500
KV line in the same ROW. There are no knownarchaeological sites
along the existing ROW in the Greater Bangkok Area.
PCB Mana2ement
22. The proposed 500 KV transmission system (Eastem and Westem
lines) will notinvolve replacement of equipment potentially
contaminated with PCB. EGAT has surveyedall potentially
contaminated electrical equipment in the Greater Bangkok Area; the
onlyremaining PCB's are in the power generation facilities.
40
-
Mitigation Measures:
23. Natural Resources: Foundation towers and construction
activities includingtransportation of construction materials,
material storage and worker housing would belocated at least 50
meters awav from surface water resources to avoid soil erosion. in
case itis necessary to use areas closer to water resources, soil
barriers would be built to blockerosion and sedimentation.
Vegetative cover would be replaced along streambanks and
thesurrounding project site if disturbed, to prevent soil erosion.
In all areas, sanitary latrines willbe constructed for workforce
and temporary offices, and good housekeeping measures willminimize
potential water contamination due to oily waste or chemicals.
24. Forest Resources: The following mitigation measures would be
followed: (i)deforestation to be done only in the right of way; ii)
reforestation is the responsibility ofEGAT, the area of
reforestation would be more than the area of national forest
reserve usedfor the ROW; iii) in case private land is used in
construction, it is the responsibility of EGATto contact the owner
and pay fair compensation.
25. Wildlife: The impacts can be controlled by: i)
'deforestation only in the rightof way area; ii) prohibition on
disturbing wildlife, including nests, eggs, holes, hollows andother
habitat; iii) prevention of noise pollution by limiting work hours
between 8.00 am and16.00 pm., all work to be forbidden at
night.
26. Land Use: EGAT would plan all the project activities
including materialtransportation, pole mounting and others in the
dry season, because most of the crops wouldalready have been
harvested. Removal of agricultural plants (particularly
perennials') onuldbe done oniy as necessary and compensation paid.
Farmers would be allowed to grow short-lived crops with heights of
less than 3 meters in the ROW.
27. Cultural and Esthetic Resources: The transmission line one
of the Eastern area(Rayong 4-Nong Chok) goes through Tharanukroh
Cemetery; therefore, it would be movedaway to minimize visual
impact.
Monitoring
28. The following monitoring plan will be adopted to track the
effectiveness ofmitigation techniques, and to address recognized
problems in an appropriateand timely manner. This regular scheduled
monitoring program will consistchiefly of visual inspections during
construction and operation for:
o erosion along access roads, substation and transmission
towerfoundations;
o encroachment of settlements within rights of ways,
encroachment ofsettlements within protected areas via transmission
line access roads,exploitation of forest resources in protected
areas via access roads;
41
-
o vegetation clearances below transmission lines, and invasion
of exoticspecies along right of ways;
o transformer fluid leakage and spills.
42
-
Executive Summary
TNB Stage IT Inter Co.nection andTransmission System Expansion
Project No. 9
Environmental Guidelines for Planning, Construction and
Maintenance of Transmission Lines
Introduction
1. The Electricity Generating Authority of Thailand (EGAT) is a
state enterprise under
direct supervision of the Office of the Prime Minister.- EGAT
was established on May 1,
1969 to nationalize and consolidate the functions and
responsibilities of three independent
state enterprises: the Yanhee Electricity Authority (YEA), the
Lignite Authority (LA) and the
North-East Electricity Authority (NEEA). EGAT is now in the
process of privatization.
EGAT has the responsibility to provide electricity for the
entire Kingdom of Thailand by
generating, transmitting and selling bulk energy to two
distributing entities, namely the
Metropolitan Electricity Authority (MEA) and ~he Provincial
Electricity Authority (PEA).
2. The current EGAT long term Power Development Plan (PDP 95-01)
includes about
13,100 MW total power purchase from IPPs up to the year 2011,
representing 30% of the
total installed capacity at that time. To facilitate private
sector investment in IPP projects,
EGAT will construct Transmission System Expansion Project No. 9
and TNB Stage U Inter
Connection .
Proiect Description
43
-
3. Transmission System Expansion Project No. 9 is also prepared
in response to the
Government's policy to continue the development of
infrastructure to sustain the economic
growth of the country. TS 9 is a package of 26 subprojects of
transmission lines and substations
expansion and reinforcement. The project involves the
construction and reinforcement of
transmission lines totalling 1,890.0 circuit-kilometers, and 10
substations. The total amount of
5,900 MVA transformer capacity and 1,202.4 MVA reactive power
compensation equipment
installed at the existing substations are also included.
4. TNB stageII Interconnection consisits of two parts: the
construction of HVDC
transmission, and intemal system reinforcement.
Legal and Administrative
5. Environmental ImRact Assessment (EIA) is not required under
current Thailand law
and regulation for the Transmission System Expansion Project No.
9 and TNB StageII Inter
Connection . The EIA for the transmission system will be
expected only when all or a
portion of the transmission line routes are located in Watershed
classification class lB (or
wildlife sanctuary area, or national park area, or mangrove
area). The project routes do not
traverse any of these. This report is a focused environmental
analysis of environmental
impacts of project components and their mitigation measures as
required by the World Bank.
Analysis of Alternatives
6. Power system studies were reviewd based on the latest EGAT
and TNB Power
Development Pl